Documente Academic
Documente Profesional
Documente Cultură
KADAMTALA RD BLOCK.
REPORT SHEET
The estimate amounting to Rs.
Has been framed to meet up the probable cost of the expenditure for executing the
above mentioned work and submitted to the authority for technical approval
1. SCHEME: -S.G.S.Y.
2. METHOD: -DEPARTMENTALLY BY IMPLIMENTATION
3. RATE: -AS PER R.D. ISSUE RATE
4. TIME FOR COMPLETION: -6 MONTH
5. SPECIFICATION: -AS PER R.D. SPECIFICATION
JUNIOR ENGINEER
KADAMTALA RD BLOCK
NORTH TRIPURA
ESTIMATE FOR CONSTRUCTION OF STEEL BRIDGE OVER BAMUNIACHERRA AT KADAMTALA G/P UNDER
KADAMTALA RD BLOCK.
ANEXURE II
Sl
DESCRIPTION OF ITEM
ACTIVITY OUTPUT MEASURED
MATERIALS &
No
LABOUR FOR THE
ACTIVITY
1. Drilling and boring of 40 mm dia pilot hole by any 4x4x6.0=96.0 m
H/Sk = 7 Nos
suitable method and withdrawing the same after
Sk = 19 Nos
boring of 6.00 meter
S/Sk = 41 Nos
U/Sk = 18 Nos
2. Reaming bore hole of 40 mm dia to an enlarge bore 96.0 m
H/Sk=4 Nos
hole of 80 mm dia by any suitable method.
Sk = 12 Nos
S/Sk = 26 Nos
U/Sk = 11 Nos
3. Reaming bore hole of 80 mm dia to an enlarge bore 96.0 m
H/Sk=8 Nos
hole of 150 mm dia by any suitable method.
Sk = 31 Nos
S/Sk = 80 Nos
U/Sk = 26 Nos
4. Lowering and handling of 100 mm dia (GI) nominal 96.0 m
100 mm dia GI
bore (medium) quality pipe with suitable steel cutter/
Pipe=96.0 m
threading/ jointing complete as directed.
H/Sk=4 Nos
Sk = 12 Nos
S/Sk = 26 Nos
U/Sk = 7 Nos
5. Steel work in single section including cutting/ Post [100 mm GI Pipe] -4x4x11.0=176.0 m H/Sk=14 Nos
hoisting/ fixing in position and applying a priming Bearing [100 mm GI Pipe]-4x2x2.4=19.2 m Sk = 6 Nos
coat of red lead paint.
Long Beam [100 mm GI Pipe]
U/Sk = 27 Nos
4x1x20.0 = 80.0 m
Fabrication=6775 Kg
Total=275.2 x 1.15 [wst for cutting/
Temporary Connection
6.
7.
Applying priming coat with ready mixed primer of 100 mm Dia GI Pipe-3.14x0.1x317.0
approved quality on steel work.
=99.54 sqm
65 mm Dia GI Pipe-3.14x0.065x105.0
=21.4 sqm
32 mm Dia GI Pipe-3.14x0.032x85.0
=8.54 sqm
25 mm Dia GI Pipe-3.14x0.025x468.0
=36.74 sqm
HR Sheet-2x41.0 = 82.0 sqm
Total=248.22 sqm
248.22 sqm
Paint = 22 Ltr
Sk = 20 Nos
U/Sk = 23 Nos
2x[2.4+2x1.5]x0.76x0.76=6.23 Cum
U/Sk = 4 Nos
2x[2.4+2x1.5]x0.76x0.15=1.23 Cum
2x[2.4+2x1.5]x0.76x0.15=1.23 Cum
11. Providing and laying in foundation and plinth with Post at Bed level-4x0.6x1.8x1.0=4.32 Cum
12.
2x5.4x0.5=4.32 sqm
4x[2x{1.8+0.6}]x1.0=19.2 sqm
Total=23.52 sqm
2x5.4x0.63x0.15=1.02 Cum
2x5.4x0.50x0.15=0.81 Cum
2x5.4x0.38x0.45=1.85 Cum
Total=3.68 Cum
14. 12 mm Cement plaster in cement morter 1:6 (1 Wall Above GLCement: 6 River Sand).
2x2x5.4x0.6=12.96 sqm
15. Neat cement Punning.
12.96 sqm
16. Pumping out water caused by springs tidal or river Approx. 50.0 KL
seepage broken water mains or drains
17. Extra for scaffolding work
One Job
Cement = 4 Bag
Sand = 0.83 Cum
1st Bricks =1435 Nos
H/Sk = 1 No
Sk = 2 Nos
U/Sk = 6 Nos
Cement = 0.9 Bag
Sand = 0.2 Cum
Sk=2 Nos
U/Sk=3 Nos
Cement= 0.57 Bag
Sk=1 No
U/Sk=1 No
U/Sk=135 Nos
Barak Bamboo=50 Nos
Muli Bamboo=200 Nos
Coir Rope= 10 Kg
Unit
No
No
Bag
Kg
Kg
No
Kg
Kg
Cum
Cum
Sqm
No
Job
Quantity
5987
8200
223
3543
40
100
10
10
4
23
178
100
1
Rate
Rs. 3.05
Rs.3.05
Rs.247.00
Rs.34.00
Rs.52.00
Rs.12.00
Rs.60.00
Rs.48.00
Rs.180.00
Rs.248.00
Rs.86.00
Rs.50.00
TOTAL
Unit
No
No
No
No
Quantity
58
23
186
302
Rate of Item
Rs.101.00
Rs.88.00
Rs.74.00
Rs.61.00
TOTAL
Amount
Rs.18260.00
Rs.25010.00
Rs.55081.00
Rs.120462.00
Rs.2080.00
Rs.1200.00
Rs.600.00
Rs.480.00
Rs.720.00
Rs.5704.00
Rs.15308.00
Rs.5000.00
Rs.5000.00
= Rs. 2, 54, 905.00
Amount
Rs.5858.00
Rs.2024.00
Rs.13764.00
Rs.18422.00
= Rs.40, 068.00