Sunteți pe pagina 1din 16

11.3.

2 Complete Footing Plan for the Whole


10.5.3 Reinforced Braced Systems

Structure

Bracing members of braced frames are to be

Footings

designed as struts or ties, as they will be subject to

See Drawing Sheet No 11.1 - Clause 11.16.

alternating compression and tension, and connections


between members are to have greater strength than
each connected member.
In terms of detailing, it is important to provide

11.1

GENERAL

identical system must be adopted. As distinct


from many other elements, location dimensions

11 .1.1 Foundation

adequate lateral restraint along the whole length of


the longitudinal reinforcement when it is subject to

for footings are as much the responsibility of the

The ground on which a structure rests, or is

engineer as that of the architect because the

supported by, is called the foundation .

footing layout affects the strength of the whole

compression in the form of:

Helices. The volume of steel divided by the

A footing is that part of the structure which is


in contact with the foundation . It is essential that the

Closed ties.

footing and foundation are in complete contact and, for

Asv::: 0.30 s Y1 (Ag/Ac - 1) (f'c/fsy.f)

this reason , concrete is the only satisfactory material;

(unless <jJN uo > N*)


Asv ::: 0.09 s Y1 (f'c/fsy.f)
whichever is the greater
where:
s = centre to centre spacing of the ties
= the larger core dimension

Ag = the gross cross-sectional area of column


Ac = the cross-sectional area of the core
measured over the outside of the ties
f'c

transfer the load from the structure to the foundation .

fsy.f = the yield strength of the ties


= a strength reduction factor

Nuo = the ultimate strength in compression of an

of each footing. Detailed dimensions of each


footing are normally given on its own drawing or,
where the footings are rectangular, in a footing
schedule.

Give a reference number for each footing and


for the column or wall which is supported by

11 .1.3 Preparation of the Foundation

it. Normally, the footing reference number will

In certain circumstances, it may be necessary

be the same as the reference number of the

to increase the strength of the surface layers of the


foundation by using special techniques. Some of

supported column; this is mandatory when

the common methods include compacted back-fill,

a column schedule is used, Drawing Sheet

crushed rock, lean concrete, etc, and full details must

No 11.7.

be given in the drawings or Specification.

11.3.3 Individual Footing Plan-Views

The minimum depth at which footings are to be


founded must be indicated so that an estimate of the
excavation cost can be made, together with provision

Where the shape and dimensions of a footing


are not obvious:

Draw the exact shape of the footing with all

for altering as applicable the length of the supported

necessary dimensions for excavating the hole in

column.

the foundation.

axially loaded cross-section without

eccentricity
N* = the axial compressive or tensile force on

Indicate the general shape looking down at each


footing. This view will also show the orientation

when placed and compacted properly, concrete will fill

= the characteristic compressive cylinder

strength of concrete at 28 days


<jJ

locating dimensions.

any hollows in the foundation and, after it hardens, will

or

Y1

structure. Footing centre lines are often used as

11 .1.2 Footing

volume of concrete, per unit length of member must be


greater than 0.12(f'c/fsy.f); or

Define the location of every footing. If


architectural drawings use a grid-line system, the

11.2

AS 3600 REQUIREMENTS

Specify the minimum depth to which the


excavation must be made and, in at least a

The Concrete Structures Standard does not

General Note in the drawing, an indication of the

have a section specifically allocated to footings. For

type of ground expected or allowed for together

design purposes, a footing is considered to act as if

with its predicted bearing capacity. If the

it was a beam or a slab, depending on its shape and

engineer requires soil tests, this can be stated

a cross-section.

in the drawings although it is often given in the

loading condition .

Specification in more detail.


11.3

FOOTING PLAN-VIEWS

dimensions of the column or wall supported by


the footing. Within this shape will be shown the

11.3.1 Types

location of all reinforcement cast with the footing

Two types of drawings are usually required to

but extending into the column or wall.

describe the footing arrangements:

a complete footing plan for the whole structure,


and

an individual plan-view, depending on the types


of footings used in the structure.

Give the location, orientation, shape and

Reinforcement of the footing is usually not shown


in a plan-view except in the case of simple pad
footings . As a general rule, footing details tend to
follow beam rather than slab detailing methods
in that the number of bars should be stated, not
just the spacing .

11 :1
10:4
Reinforcement Detailing Handbook

Reinforcement Detailing Handbook

11.4

FOOTING ELEVATIONS

11 .6

GENERAL COMMENTS ON FOOTING

Drawing Sheet No 11.4.

11.5

FOOTING CROSS-SECTIONS
These differ with the type of footing being

detailed.
Where the footing shape is rectangular, similar
to a strip footing, cross-sections like those of

Refer to Chapter 5 of this Handbook and

walls of concrete or masonry.

11.7.1 Strip Footings for Masonry Walls

nominal-size ties , generally at about 600 mm

in Clause 4.6. The layers are held apart by

Drawing Sheet No 11.2 shows a strip footing

centres.

by the designer; once settled, values can be tabulated

under a masonry wall. See also Drawing Sheet

In heavier construction, strip footings would be

in the General Notes section of the drawings. Note that

N011.1 .

designed individually with trench mesh or bars as

the increase in cover for footings is to accommodate

the uneven nature of excavation.

Where pad-footings or complex footings are


detailed, the shape of the main steel can be
defined by the shape of the section.

main steel. Designed ties are used to maintain

with AS 2870, Residential slabs and footings, for

the footing reinforcement relative to the ground


surface. For masonry, steps should match the

The width of a strip footing is controlled firstly

Footing reinforcement is generally required

course height. The concrete overlap must also

by the width of the wall it supports; accuracy

quickly at the start of a job, and must therefore

be dimensioned.

of excavation is generally not great and it is

be scheduled as shown on the original drawings.

important that the wall above (particularly if it

Once the excavation is completed , the footing

is of masonry) is seated in its design location

11.7.2 Strip Footings for Concrete Walls


Drawing Sheet No 11.3 illustrates a strip

steel and starter bars are fixed, and approval is

(usually central).

footing under a concrete wall. See also Drawing

given to pour a footing, this is done with utmost

The second requirement for the width is to

Sheet No 11.1 .

speed to prevent rain or ground water from

limit the bearing pressure of the footing on the

affecting the foundation .

Where the concrete wall acts structurally in a

foundation. In some cases, the footing width is

similar manner to masonry walls, the strip footing

All starter bars for columns or walls must be

greater than the depth to spread the load and

will be shown in the same way. Wall starter bars

detailed with the footings by which they are

therefore reduce the pressure; in other types

must also be detailed and scheduled with the

supported; generally starter bars are an L-shape

of soil, the width is kept as narrow as possible,

footing.

with the bottom end resting on and supported

depending on the wall width, and the depth is

Longitudinal footing reinforcement is more

by the footing reinforcement. The length of

increased to add flexural strength to the footing .

important in this case than transverse

this part should be at least twice the spacing

Dimensioning of strip footings is described in

reinforcement.

between the footing bars.

Clause 8.7.4. There it is recommended that

Because the bottom RL of a footing can change

the depth of a strip footing be given first to be

horizontal loads, as with a retaining wall,

from that shown on the original drawings,

consistent with a ground beam , regardless of

concrete and reinforcement detailing is critical

provision must be made for adjusting the length

which is the greater - depth or width. However,

because of the heavy loads involved.

of main bars in the columns rather than altering

Where the concrete wall is used to support

a dimensioned drawing is far more descriptive.

Concrete walls are described in Chapter 15,

Traditionally a layer of reinforcement is located

with particular attention being paid to detailing

An extension to the vertical part of the L-shape

in each of the top and bottom of a strip footing

of corners .

starter bars will ensure an adequate lap at the

because the force from the ground below

the column starter bars at the last minute.

Strip footings for residential work must comply


both strength and detailing purposes.

11 .6.2 Starter Bars

beams are suitable. These would show the

L12TM is the most common form of strip


footing reinforcement. Descriptions are given

AS 3600 Section 4.10. Selection of cover must be done

fitment shape and the main reinforcement layout.


See Drawing Sheet No 11.4.

"trenchmesh" such as L8TM , L11TM and

11.6.1 Selection of Cover for Footings

giving the same information as a beam elevation. They


wi ll need to be supplemented by cross-sections. See

STRIP FOOTINGS
Strip footings are traditionally used to support

DETAILS

These are usually given as longitudinal-sections;


that is, as a view taken along the length of the footing

11 .7

Cantilever retaining walls depend on the footing

top of the footing. By "cranking" or "offsetting"

and that from the wall above may not always

the column bars, and locating that portion at the

balance, as can occur at doorways in the wall or

footing reinforcement placed perpendicular to

BOTTOM of the column, additional changes can

soft-spots in the foundation.

the wall is more important for strength than that

be minimised at a higher level of the building.

Ties are used both to separate and position the

parallel to the wall.

The starter bars should not be cranked.

layers; the spacing between ties is often nominal,

Fixing of starter bars must be accurate as

and could range from 300 mm to 800 mm. Such

they affect the position of the whole structure.

ties in residential work are rarely designed as

Inspection for location is just as important as

reinforcement for strength, unless the footing is

checking that the steel layout is correct. If starter


bars are connecting with precast, tie bars may

for support against overturning forces and

very wide.

At corners, the intersecting main steel should

need to be set out using a template or checked

extend across the full width of the intersecting

by survey prior to and after concreting to ensure

strip . Laps within the strip can be specified by

they are in the correct locations .

notes or a drawing. In residential work, the actual


lap should be given rather than a reference to a
Standard; onsite copies of these are rare.

11 :2
Reinforcement Detai ling Handbook

In residential and commercial work,


11:3
Reinforcement Detailing Handbook

PAD FOOTINGS, ISOLATED FOOTINGS

11.8

COMBINED FOOTINGS AND

11 .9

CANTILEVER FOOTINGS

AND SPREAD FOOTINGS

BUILDINGS - SLAB-ON-GROUND

A raft footing is used when the soil foundation


is poor or it is often regarded as a flat slab

that, in most cases, they support more than

upside down with thickenings under the

for a raft but the magnitude of construction is

one column. In the case of a cantilever footing,

column. It enables the mass of the building to

much less . In this case, the wall loads are taken

column over a large area of the foundation .

the second column tends to counter-balance

be supported by the lowest-floor (basement)

directly to the ground by the edge footings or by

Reinforcement must be placed in the bottom

the other at the end of the footing. In Drawing

slab. Similar to the cantilever footing described

internal beams or thickened strips, all poured at

of the pad because the reaction of the ground

Sheet Nos 11.1 and 11.4, element CF3 is a

above, the foundation reaction requires that the

the same time as the slab.

acts upwards on all sides of the column . Note

cantilever footing. Column 10 is at the boundary

top reinforcement between the columns may be

particularly that the reinforcement is placed in

and is counterbalanced by column 7 inside the

heavier than the bottom. However there will be

"fINO directions because of this reaction . Not

building. Footings CF4 and CF8 are similar.

considerable reinforcement in the bottom face

Mesh is the preferred steel for the slabs and is

The upward reaction of the foundation is

under the columns, probably in two directions.

located near the top surface.

Drawing Sheet Nos 11.1 , 11.5 and 11.7.


A pad footing spreads the load from a single

only is the pad footing designed for flexure but it

complex and outside the scope of this

must be checked for punching shear. Avoid the

11 .11 RESIDENTIAL AND COMMERCIAL

These footings are similar to pad footings except

These terms mean the same thing. See

11 .10 RAFT FOOTINGS

In domestic construction, raft footings are often

This element follows the same principles as

Reinforcement in the footings resembles that in


strip footings, with trenchmesh predominating.

A vapour barrier must be specified together with

use of shear reinforcement by using a deeper

Handbook. The main design factor is that the

used for reactive clay sites and they consist of

pad footing or higher concrete strength or both.

concentrated downward loads from the columns

beams in two directions intersecting at 4 to 6

will prevent puncturing the membrane for all

The pad bars are often shown as LL-shaped ,

create the upward forces on the bottom of the

metre centres both ways with a slab joining the

habitable areas .

but in many cases, this is not necessary

footing, so that in this case, the TOP surface of

beams.

unless there is a length deficiency for stress

the footing must be the more-heavily reinforced.

development. The cover over the outermost

This is the reverse loading for a normal pad

It is not uncommon for two layers of steel to be


required in each direction top and bottom - that

design because walls will be higher than

bars in one direction is increased by hooks on

footing, and indeed for a suspended beam.

is eight layers altogether. Spacing for pouring

the bars at right angles; thus the number of bars

The elevations and sections in Drawing Sheet

and vibrating must be allowed, bundling pairs of

principles will be similar.

should be stated, not only the spacing.

No 11.4 show that the top has much more

Where the pad is less than 2500 mm wide, one

longitudinal steel than the bottom .

bars where possible.

Where a raft is used for a large multi-storey

Shear reinforcement in the form of mesh or

building , the distance between the top and

together. The cross-wires form part of the

bar stirrups is a critical design factor because

bottom layers may be one metre or more.

transverse steel as well.

the loads are much more severe than for strip

A considerable amount of extra material will

Concrete columns must be reinforced and

footings.

be needed just to support the two grids of

the bars must extend into the footing pad.

reinforcement. The Bill of Quantities if used

As previously discussed, the starter bars are

should indicate the quantities involved, and how

supplied and fixed with the footing reinforcement

to price this work if extras are to be avoided .

11.12 PIER AND BEAM FOOTINGS

above the pad.


The orientation and location of the starter bars
in relation to the column shape is extremely
important for strength and architectural
purposes; a fully dimensioned cross-section will

Where there is a poor soil overlaying a good


material, bored piers are often used to transfer
the vertical loads to the latter. The piers would
be detailed as for columns. Wall loads are
transferred to the piers by beams which are
detailed normally. The piers may be of uniform
cross-section or be belled out at the bottom.

and adequate lap lengths must be allowed

Residential work is controlled by AS 2870;


commercial buildings may need an engineering
permitted by that standard, but the detailing

or two sheets of mesh may be used, nested

reinforcement spacers on a suitable base which

In certain soils, the beam underside must be


separated from the earth below - upward
expansion can be catastrophic if the gap is
inadequate. The method to be used is a design
matter, and the solution must be detailed.

be required for odd-shaped columns .

Embedment of the starters in the pad is a


design matter, and the anchorage requirements
may need to be dimensioned in critical cases.
Generally, the starter bars will be scheduled as
L-shaped to be stood-up on the pad steel. For
fixing purposes, at least three fitments should be
detailed and supplied with the starters - two go
within the pad depth and the other is tied around
the exposed lap length. Provided the starters
do not have to be cranked (see Clause 11.6.2
earlier), the size of these fitments would normally
be the same as those for the column above.

11:4
Reinforcement Detailing Handbook

11:5
Reinforcement Detailing Handbook

11.13 PILES AND PILE CAPS

Reinforcement layout for assembly. Footing

11.14.3 Pad Footings - Standard Detail

The following notes are based on the Detailing

function as a pier when the load exceeds the

Examples shown in Drawing Sheet Nos 11.1 to 11.7

about 1800 kg (1.8 tonnes) , of which the main

Detail for an isolated pad footing under a reinforced

capacity of a single pile. The pile cap distributes

at the end of this Chapter in Clause 11.16.

top bars comprise 1 .2 tonnes. These bars must

concrete column .

system can be very complex and there can


therefore be several layers of bars in both top
and bottom faces. The bars are often not on a
rectangular grid so careful detailing is required
if the required arrangement is to be obtained .
Large scale details may be advisable.
In large buildings and civil engineering structures,

CF4 is heavily reinforced . The total steel mass is

Drawing Sheet No 11.5 illustrates a Standard

be supported upon the foundation (see also

11 .14.1 Example of Strip Footings

Clause 11.1.3) by means of the vertical legs of

Drawing Sheet Nos 11.1, 11.2 and 11.3


illustrates a footing plan for a small building and details
of strip footings. See also the notes in Clause 11.7
for both strip footings supporting a masonry wall and
supporting a concrete wall.

Drawing Sheet No 11.4 shows the details of

The number, orientation and layout of the footing


bars and associated ties are not provided with

the N16 fitments.

the Standard Detail because these vary for

Just to assemble the cage as it is drawn, and tie

each footing; neither are column cross-sections

it together with wire, will not be adequate.

given here. All of these are shown in the column

To maintain the whole cage properly will require

schedule.

additional longitudinal bars to be placed under

11.14.2 Example of a Cantilever Footing

a piling contract is often let well in advance of

Clause 12.9 and Drawing Sheet No 11.7

the fitments resting on strong concrete or

show footing and column details in schedule

purpose-made steel chairs .

format. This combines the application of a


Standard Detail for a footing and one for a

the building contract. If this is done, the actual

cantilever footings CF3, CF4 and CF8. The following

As an alternative, 2 or 3 of the 8-N28-LL-B bars

location of the piles as driven must be given in

com ments discuss factors which must be considered

can be placed first on the supports to form the

column (see also Cause 12.8 and Drawing

the drawings for the building contract. It may be

by designers and detailers to ensure the member can

initial platform free of the earth. The remainder of

Sheet No 11.6).

necessary to alter the pile cap design because

be constructed "as designed". They apply to members

the steel can then be built upon them.

the actual locations differ more than expected

other than footings as well.

Examination of cross-section CF4 shows that

upper-layer pad bars are used as supports for

there are actually three "beam" segments, each

the remainder.

from the original design.

The concrete outlines. The elevation CF4

To assist in construction, note that two of the

The designer should allow for reasonable

defines the concrete length and the cross-

of which can be assembled separately and

variation on the location of piles after driving,

section CF4 clarifies the beam depth and width.

craned into position upon the pre-set supporting

lengths for starter bars would also need to be

bars .

scheduled, such as shown in Table 11.1.

say 75mm. The tolerance permitted must be

Architectural drawings should be used to provide

shown in the drawings, with the required cut-off

the column centreline dimensions.

Splice lengths for column bars and embedment

Problem areas . The N24-1 OO-LL-B bars across

Reinforcement layout for strength. Take the

the bottom of the footing under the columns will

cantilever footing CF4 as an example. It has

need to be assembled early, so that the column

Piling - Design and installation .

been designed as an "upside-down" beam,

starter bars (not shown here) can be tied to

As with many footing designs, the top

that is there is more steel in the top than in the

them .

reinforcement will restrict access to the inside

bottom. (See Clause 11.9).

A width of 2000 mm for 20-N36 bars is

of the cage so that the method by which the

This situation requires strong tie bars to support

inadequate if concrete is to be placed properly

cage is assembled should be a design and

the top steel, each bar of which weighs about

(see Chapter 4). To allow concrete to be cast

N20

400

600

detailing matter. Access is required for placing

60 kg. These tie bars are shown on cross-

and compacted, and the column starter bars to

N24

480

720

2-R10 or 1-L9

concrete and vibrating it, as much as for fixing

section CF4 as three sets of N16-HT at each

be placed through them, the top bars should be

N28

580

840

2-R10 or 1-L10

stirrup.

reinforcement and other embedments.

Reference should be made to AS 2159: 1995

points detailed.

A group of piles is used to perform the same

the column load to the piles. The load transfer

11.14 EXAMPLES OF FOOTING DETAILS

Table 11.1 Embedment Lengths for Starter Bars and


Splice Lengths for Column Bars

Bar
Size

Straight
embedment
in footing of
20 OIA. (mm)

Splice
length
of
30 OIA. (mm)

Number of
fitments at
column bar
crank
i-RiO or 1-L7

grouped into a series of 2-bar bundles or placed

N32

640

960

1-N12 or 1-L11

The top main steel is the group labelled

in two layers with a spacer bar. This requires

N36

720

1080

2-N12 or 1-L12

20-N36-LL-T. In both cases, LL is the shape,

designer's approval, so it is simpler to detail it

T means TOP and the combination is quite

that way in the first place.

adequate to define the bars and location.

The individual stirrups of bars can perhaps be

The bottom main bars are 8-N28-LL-B, and are


drawn inside the fitments.
Because of the heavy downward column loads
and the footing width being 2000 mm, the
ends of the cantilever footing are reinforced
transversely with 6-N24-1 OO-LL -B at one end,

replaced by mesh bent to the fitment shape.


This will reduce the time to tie the bars and will
provide a rigid cage which does not require
bracing.

Drawing Sheet No 11.4 gives two examples of


cantilever footings.

and 4-N24-100-LL-B at the other.


In practice, these 10-N24's are identical because
the footing width is constant. There is no need
to show them on the cross-section because they
have been fully defined on the elevation by the
complete notation, thus eliminating at least one
extra detail.
11:6
Reinforcement Detailing Handbook

11:7
Reinforcement Detailing Handbook

11 .15 DETAILING OF FOOTING SYSTEMS

FOR SEISMIC
11.15.1 General
Adequate footing design is critical for ensuring

Footing Structures for Frames as discussed in

Design Methodology, AS 3600 provides some limited

11 .15.4 Piled Footings


Piled systems supporting structural walls may

guidance regarding footing design and detailing.

be subject to large concentrated forces due to vertical

Although the code stipulates that for footings located

load causing overturning moments and shear forces .

in soils with a maximum bearing capacity of less than

Careful design is therefore required .

that a building structure will be able to resist both the

250 kPa, restraint must be provided in the horizontal

gravity loads and seismic forces calculated.

direction to limit differential movement during an

follow the recommendations set out for columns in


Chapter 12. The end region of a pile under the footing

Detailing of reinforced concrete piles should

Where there is no possibility for inelastic

earthquake. It should be noted that reports from Kobe

deformations to develop under earthquake conditions,

indicate that although liquefaction is a problem in poor

structure should be detailed to ensure full confinement

it is considered that standard detailing of reinforcement

soils, the water in the saturated reclaimed area acted

of the longitudinal reinforcement using closed or

as for gravity loads and wind forces will be adequate.

as a dampener, restricting damage to significantly less

helical ties. The locations of peak moments in the

This will be the situation in the majority of buildings

than that experienced in the adjoining 'dry soil ' areas.

pile may necessitate the length confinement being

constructed in Australia.
However, where design indicates the

The Code considers that there is no possibility

indicate no tension loads, it is recommended that

occurrence, or possible occurrence, of reinforcement

loading, and that standard detailing of footings for

min imum longitudinal reinforcement be provided. The

yield ing during seismic action , the foundation structure,

gravity and wind induced loads only will be sufficient.

arrangement of longitudinal reinforcement should be

like the superstructure, must be detailed accordingly.

However, the author considers that certain additional

as for columns, and the reinforcement should be fully

As already mentioned, as a result of code loading

precautions can be warranted.

of the structure may be elastic.


Paulay and Priestley suggest footing systems

11 .15.2 Isolated Footings


These can prevent a problem with rocking

that may support elastic superstructures. (See as a

or tipping if a plastic hinge forms in the base of the

Reference: Paulay, T. and Priestley, M.J.N . Seismic

column. Unless precautions are taken, permanent

Design of Reinforced Concrete and Masonry Buildings,

deformation of the footing can occur due to plastic

John Wiley and Sons Inc, 1992). Two of these will be

deformation of the soil despite both the column and

relevant to Australian designers:

footing remaining elastic. The detailing of the colu mn/

Elastic Footing Systems . In regions of low


seismicity (as is generally the case in Australia)
or for low buildings with structural walls, it will be
possible to design and detail the entire structure
to respond within elastic limits.

Ductile Footing Systems . In certain cases, the


potential strength of the superstructure with
respect to the specified seismic forces may be
excessive (eg large shear wall structures). The
designer might therefore consider that it will be
preferable for the footing system rather than
the superstructure to be the principal source
of energy dissipation during inelastic response.
A potential drawback for this system is that
damage may occur during moderately strong
earthquakes. Large cracks may form if yielding
of reinforcement has occurred. Further, repairs
to footings may be difficult and costly if required
below the water table or under a floor slab.

--~-';:"",-",--

anchored within the pile cap. In non-critical regions ,


nominal transverse ties or spiral hoops should be

Fully anchor reinforcement


into pilecap

Provide at least minimum


longitudinal reinforcement
throughout entire length
Ligature spacing
$16 x diameter of
longitudinal bars

Ensure full confinement of


longitudinal reinforcement
in end region of pile

considerably extended. Further, even if calculations

for inelastic deformations to develop under earthquake

requirements or design decision, the seismic response

, - j -- - - -

Potential location of plastic hinges (possible location of


peak moment may vary). Provide closed ties as for columns.
Top hinges will always occur under large, stiff footings.
Bottom hinges are considered to be less likely to form and
ductility demands are likely to be much lower.
The designer must judge the necessity of confinement based
on site geological conditions and expected loading.

provided. Paulay and Priestley (see Reference in


Clause 11.15.1) recommend that vertical spacing not

Figure 11.1 Piled Footings

exceed 16 times the diameter of longitudinal bars. See


Figure 11.1 .

footing joint must be carefully considered .


11 .15.3 Combined Footings
It may prove more feasible to absorb large
moments transmitted by plastic hinges at column
bases by using stiff tie beams between footing s,
whereby a high degree of elastic restraint against
column rotations can be provided. In fact, thi s detail is
such that reinforcement yielding is unlikely to occur and
it is considered that no special detailing requirements
for ductility need be provided. It WOUld, however, be
necessary for' the tie beams to have sufficient reserve
strength over that of the hinging columns.
If it is required to reduce the bearing pressure
under the footing pads, they may be joined to provide
one continuous footing .
Stub columns do require special consideration
if inelastic deformations and shear fail ure are to
be avoided . Paulay and Priestley (see Reference
in Clause 11.15.1 ) consider that plastic hinges
should therefore be restricted to the column section
immediately above the beam.

11:8
Reinforcement Detailing Handbook

11 :9
Reinforcement Detai ling Handbook

11 .16 DETAILING EXAMPLES - DRAWING

11 .16.1 Drawing Sheet Number 11.1

SHEETS NUMBERED 11.1 TO 11.7

cp

The following Drawing Sheets represent


selected detailing examples for a small building
covering mainly footings and columns. They have

SEE SHEET NO .11 .7 FOR


COLUMN SCHE DULE

been referenced throughout Chapter 11 and are also

--

referenced in Chapter 12.

SF1 -3(Xl> 60J

C2 I
f-

'--

2
2
0
0

0
0

'-

(')

r-

BANK
DOWN

0
0

(')

u:

C6

(f)

(f)

SEE COLUMN SC HEDULE


(SHEET NO. 117) FOR
G SIZES

.---+--,

C~

PAD_F_O_O_TI~

C5

--E9--

f - - f--

0
0

\2.J

(')

x
0
0

(')

0
0

0
0

(')

0
0
CD

f'-.
LL

(')

(f)

BANK
DOWN

(')

C7

EEl

--

..

0
0

~
x

0
0
CD
(')

LL
()

5
4

I
I

-~

(f)

LL

~
C8
c--E3-(f)

-- -

/ _~~~-L

CD

()

ffi

\.V

_____ _

IZ
o

<Xl
LL
()

'<t

LL

5
4

I ir

0
0
CD

OJ

=:>

(l]

-Bj

C11 I

SF2 - 300 x 600

C12
1

FOOTING PLAN

WALLW2

. --.UOO
S

- - c--

BOUNDARY

WALL W1

<l ~

N
X

F3 - 600 x 300

1lf

0
0

1-

C9

f----~ f+.~

0
0
0

I
I

OJ
LL

\.V

0
0

L()

ffi

CD
LL

.'-~

0
0
CD

(')

C3

SEE SHEET NO . 11 .6 FOR


COLUMN DETA ILS

L--+-----l

C?

x 300

THE FOOTINGS ARE TO


BE FOUNDED ON SANDY
CLAY HAVING A MINIMUM
BEARING CAPACITY OF
250 kPa.

DETAILING EXAMPLE A
DRAWING SH EET NO. 11 .1

11 :10
Reinforcement Detailing Handbook

11 :11
Reinforcement Detailing Handbook

11 .16.4 Drawing Sheet Number 11.4

11 .16.3 Drawing Sheet Number 11.3

11 .16.2 Drawing Sheet Number 11.2

500

'---+-~

400
N12-300
CORNER BARS

2-N16-HT
AT EACH
SET OF
STIRRUPS

1-N16-HT
AT EACH
SET OF
STIRRUPS

N12-300, EW
IN CENTRE

2-N 16-HT
AT EACH
SET OF STIRRUPS

1200

2000

2N12 T&B

'--+---"'--

CF4

CF3, CF8

SECTION ( } )

SECTION ( ] )

SF5 , SF6, SF7

SECTION

G)
400 LAP -

4-225

--+-<11:>

..

1-1000

.I

20-N36-LL-T

~ CJ
FOOTING
600 x 300 -

___-I

N12-300
STARTER BARS -

I.

4N12 T&B

2N16-400

+-I-a.-l

R10
STIRRUPS - 450

600

6-N24 100 CRS


I
COGGED EACH END

I~BOUNDARY

CF4 - 690 X 2000

SF1 , SF9 , SF10 (SF2 SIMILAR)

SECTION

ED

2N16 T&B

COL C10
COL C12

WALLS W1 , W2 , FOOTINGS SF3 , SF4

SECTION

GROUND LEVEL

EB

12-N36-LL-T

J ~
COLUMN

( , - -01

N12-300

~R1 0

STIRRUPS - 600

1_ _

::JJ

L . -- # - ---i

300

300

1150

N12-300, EW
IN CENTRE

I~ BOUNDARY

CF3, CF8 - 600

1200
DETAILING EXAMPLE A
DRAWING SHEET NO. 11 .4

600

TYPICAL STEP DETAIL IN STRIP FOOTING


DETAILING EXAMPLE A
DRAWING SHEET NO. 11.2

PLAN WALL W1 (W2 OPPOSITE HAND)


DETAILING EXAMPLE A
DRAWING SHEET NO. 11.3

11 :13
11 :12
Reinforcement Detailing Handbook

Reinforcement Detailing Handbook

11.16.6 Drawing Sheet Number 11.6


11.16.5 Drawing Sheet Number 11.5
STAN DARD COG
CJ

ROOF
100

.f---...--+ +- _ 50 MAX. (SEE NOTES 1 & 2)


STARTER BARS SAME NUMBER
AND SIZE AS COLU MN BARS

TIE SPACING, 'S'

SCABBLE SURFAC E
2 SETS OF TIES FOR SUPPORT OF STARTER BARS
32 DIA.

f
20 D IA.

TWO SETS OF TIES AT TOP OF CRANK

1
,
1; 17

COGS MAY BE NEEDED


SEE TEXT CLAUSE 11.8

:~ 1/

TIE SPACING , 'S'

rt
$
II ,
75

I
I

50 mm BLINDING LAYER
(I F REQU IRED)

SECTION

9-=-

EXTEND AND COG CORN ER BARS ON LY

CD

~
-

1--1-

32 DI A.

100

NOTES

-. -

1 FOR LEVEL TO UNDERSIDE OF FOOTINGS, DIMENSIONS AND REINFORCEMENT SEE SHEET NUMBER 11 .7.
2 OVERBREAK BELOW FOOTINGS TO BE FILLED TO UNDERSIDE OF FOOTIN G WITH GRADE N15 CONCR ETE.

: ~ II

~I
I

::-

CJ Y

3 SETS OF TIES MINIMUM FOR


SUPPORT OF LOWER BARS

v
.......

I
1

3 OVERBREAKS AROUND FOOTINGS TO BE FILLED WITH CONCRETE OF SAME GRADE AS FOOTING .

GROUND, FIRST, SECOND FLOOR

50 TO FIRST TIE

+,

50 MAX. (SE E NOTE 1)

50 MAX. (SEE NOTE 2)

4 DETAILS ABOVE APPLY UNLESS SHOWN OTHERWISE ON DRAWINGS.

~ TIE SPACING, 'S'


LOWER
COLUMN BARS

5 REFER ALSO TO STANDARD NOTES ON SHEET NUMBER ..

DETAILING EXAMPLE A

DRAWING SHEET NO. 11 .5

d!
~ CRANKED UPPER

I
~

COLUMN DETAILS
NOTES
1 50

mm BELOW SLAB WITH 3 BEAMS OR LESS.

2 50

mm BELOW SHALLOWEST BEAM WITH 4 BEAMS.

COLUMN BARS

q,

SIMILAR FOR CO LUMN S


WITH 6 AND 8 BARS

SECTION

(1)

3 FOR SIZE AND REINFORCEMENT DETA ILS, SEE COLUMN SCHEDULE ON SHEET NUMBER 11 .7
4 REFER ALSO TO STANDARD NOTES ON SHEET NUMBER ..

DETAILING EXAMPLE A
DRAWING SHEET NO. 11 .6

11 :15
11:14
Reinforcement Detailing Handbook

Reinforcement Detailing Handbook

11.16.7 Drawing Sheet Number 11.7

~
~

~ N12-HTTIES

~[ 'F- -ie-'- - =1'r:

L...,........,.

I...

-I

380

~ 2-N12-HT

r1-N12-HT
AT EACH TIE

['---~'

300

Columns

I. .

/ J

TIE SPACING , 'S' = 300

TIE SPACING , 'S' = 300

380

-I

380

~~

rI..

1-N12-HH
AT EACH TIE

~./

12.1

size which progressively pick up the vertical loads on


each floor and, together with any lateral forces due

-I

380

to wind or earthquake resulting in shear forces if the


columns are part of a moment frame, finally transfer all
forces down to the footing.

TYPE 3

The vertical load in the column is smallest at the


roof and greatest at footing level. The load is carried by

TYPICAL COLUMN TYPES

COLUMN SCHEDULE
1, 3

COLUMN MARK

2,4,6

GENERAL AND PURPOSE


Columns are vertical members of relatively small

TIE SPACING, 'S' = 300

TYPE 2

TYPE 1

AT EACH TIE

11

7, 9

Maximum square column size (mm) for bar size


___
N um b er __________________________________
of bars N12
N16 N20 N24
N28 N32
N36

4
6
8

210

280

350

420

500

570

640

260

350

430

520

610

690

780

300

400

500

600

700

800

900

10

330

450

560

670

790

890

1010

12

360

490

610

730

both the concrete and the embedded reinforcing bars.

860

980

1110

14

390

530

660

790

To carry this increasing load downwards from roof to

930

1060

1190

16

570
600

850

1000

1130

1280

18

420
440

700

footing, four alternatives may be considered .

750

900

1060

1200

1350

20

470

630

790

950

1110

1260

1430

(1) The concrete size is increased floor by floor, but

10, 12

this makes formwork costs excessive.

ROOF
~x~~x~~ x ~~ x ~~x~~x~~ x ~

SECOND
FLOOR

COLUMN SIZE
MAIN BARS
CONCRETE GRADE
COLUMN TYPE

~x~~x~~ x ~~ x ~~ x ~~x~~ x ~

FIRST
FLOOR

COLUMN SIZE
MAIN BARS
CONCRETE GRADE
COLUMN TYPE

~x~~x~~x~~x~~ x ~~x~~x~

GROUND
FLOOR

COLUMN SIZE
MAIN BARS
CONCRETE GRADE
COLUMN TYPE

~ x ~~x~~ x ~~x~~ x ~~x~~x~

TOP OF
FOOTING

COLUMN SIZE
MAIN BARS
CONCRETE GRADE
COLUMN TYPE

4-N20
N25
1

4-N20
N25
1

8-N20
N25
3

6-N20
N25
2

4-N20
N25
1

4-N20
N25
1

(2) The concrete size is kept constant and the


number of longitudinal bars is increased, but this

4-N20
N25
1

4-N20

4-N24

8-N24

6-N20

4-N24

4-N24

4-N20

N25

N25

N25

N25

N25

N25

N25

leads to steel congestion after its area exceeds

STARTER BARS
REINFORCEMENT
FOOTING SIZE
FOOTING DEPTH

4-N24
N25
1

4-N28
N25
1

4-N24
N25
1

8-N32
N25
3

6-N28
N25
2

4-N28
N25

8-N32

6-N28

N25

N25
2

4-N28
N25
1

4-N32
N25
1

4-N28
N25

4-N32
N25

4-N24
N25
1

4-N24
N25

(3) The concrete size is kept constant and its

6-N28
SEE
SHEET
NO. 11.4

4-N28

4-N32

4-N24

SEE
SHEET
NO.11.4

SEE
SHEET
NO. 11.4

SEE
SHEET
NO.11.4

2, 4, 6

7, 9

11

10, 12

1,3

8-N24 bars -

H~

compressive strength (t'e) is increased.

(4) A combination of alternatives is used.

600 x 600

I ~'"

8-N24 bars

buildings. Solution (2) is suitable for low-rise buildings


to ensure internal dimensions remain constant floor by
floor.

300 x 1200
12.2

AS 3600 REQUIREMENTS (Section 10.7)

Figure 12.1 Maximum Column Sizes for Minimum


Steel Areas

The Concrete Structures Standard has a

4-N24
4-N28
8-N32
6-N16 EW 7-N16 EW 8-N20 EW
1400 SO. 1750 SO . 2450 SO.
400
360
540

COLUMN MARK

~"

about 4% of the cross-section.

This last solution is common with high-rise

FOOTING

Table 12.1
Maximum Square Column Size for 1% Steel Area

Section complete in itself on the design of columns


and detailing of reinforcement. The major headings are
listed here.

Example 12.1

12.2.1 Limitations on the Longitudinal Steel Area

A 600 mm square column must contain at least


4-N36 bars or 6-N28 bars or 8-N24 bars to be
above the lower limit of 1% steel.

The minimum area of steel is 1% of the crosssectional area unless the column is lightly loaded (Refer
Clause 10.7.1 of AS3600). See also Table 12.1 and

FOOTING LEVELS

See also Clause 4.3.3 for minimum column widths


based on concrete placement and Clause 4.3.1 for
fire resistance.

Figure 12.1 . The maximum steel area is 4%.

COLUMN MARK

7,10

8, 11

9, 12

UNDERSIDE OF
FOOTING LEVEL

100.040

100.000

100.540

100.100

99.900

101 .710

101.300

101.400

101 .500

DETAILING EXAMPLE A
DRAWING SHEET NO. 11.7

11 :16
Reinforcement Detailing Handbook

12:1
Reinforcement Detailing Handbook

11 .1 6.7 Drawing Sheet Number 11.7

Columns

r1-N12-HT
AT EACH TIE

N12-HTTIES

3S[

~"

3wI

-I

380

1~.

r- 1-N 12-HH
AT EACH TIE

1--

= 300

-I

380

TIE SPACING, 'S'

1--

= 300

380

GENERAL AND PURPOSE


Columns are vertical members of relatively small

size w hich progressively pick up the vertical loads on


each floor and, together with any lateral forces due

-I

TIE SPAC ING, 'S'

TYPE 2

TYPE 1

12.1

TIE SPACING, 'S'

~r ~.L

1--

.L2-N12-HT
AT EACH TIE

columns are part of a moment frame, finally transfer all


forces down to the footing.

= 300

TYPE 3

The vertical load in the column is smallest at the


roof and greatest at footing level. The load is carried by
both the concrete and the embedded reinforcing bars.

COLUMN SCHEDULE
1, 3
-

ROOF
COLUMN SIZE

MAIN BARS
FIRST

CONCRETE GRADE

FLOOR

COLUMN SIZE
MAIN BARS
GROUND

CONCRETE GRADE

FLOOR

MAIN BARS

N25

N25

4-N24

8-N24

6-N20

4-N24

4-N24

4-N20

N25

N25

N25

N25

N25

N25

N25

FOOTING SIZE

x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380

4-N24

4-N28

8-N32

6-N28

4-N28

4-N32

4-N24

N25

N25

N25

N25

N25

N25

N25

N25

N25

N25

N25

N25

N25

N25

COLUMN TYPE
STARTER BARS
RE INFORCEMENT

x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380

4-N20

380 x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380
4-N24
4-N28
6-N28
4-N28
4-N32
4-N24
8-N32

CONCRETE GRADE

FOOTING

FOOTING

N25

COLUMN TYPE
COLUMN SIZE

TOP OF

N25

380

4-N24

6-N28

4-N28

4-N32

4-N24

6-N16 EW 7-N1 6 EW 8-N20 EW

SEE

SEE

SEE

SEE

1400 SO .

1750 SO.

2450 SO.

SHEET

SHEET

SHEET

360

400

540

NO. 11 .4

NO. 11.4

SHEET
NO. 11 .4

FOOTING DEPTH

4-N28

2, 4, 6

1, 3

COLUMN MARK

8-N32

7, 9

210

280

260

350

N24

N28

350

420

500

570

640

430

520

610

690

780

N32

11

300

400

500

600

700

800

900

10

330

450

560

670

790

890

1010

12

360

490

610

730

860

14

390

530

660

790

930

980
1060

11 90

420

570

700

850

1000

11 30

1280

600

750

900

1060

1200

1350

20

470

630

790

950

111 0

1260

1430

(1) The concrete size is increased floor by floor, but


(2) The concrete size is kept constant and the
number of longitudinal bars is increased, but this
leads to steel congestion after its area exceeds

~..,

about 4% of the cross-section.


(3) The concrete size is kept constant and its

8-N24 bars -

(4) A combination of alternatives is used.


This last solution is common with high-rise

$)

compressive strength (t'e) is increased.

600 x 600

I~" ""

- 8-N24 bars

buildings. Solution (2) is suitable for low-rise buildings


to ensure internal dimensions remain constant fl oor by
floor.

300 x 1200
12.2

AS 3600 REQUIREMENTS (Section 10.7)


The Concrete Structures Standard has a

Figure 12.1 Maximum Column Sizes for Minimum


Steel Areas

Section complete in itself on the design of columns


and detailing of reinforcement. The major headings are
listed here.

Example 12.1

12.2.1 Limitations on the Longitudinal Steel Area

A 600 mm square column must contain at least


4-N36 bars or 6-N28 bars or 8-N24 bars to be
above the lower limit of 1% steel.

The minimum area of steel is 1% of the crosssectional area unless the column is lightly loaded (Refer
Clause 10.7.1 of AS3600) . See also Table 12.1 and

FOOTING LEVELS

See also Clause 4.3.3 for minimum column widths


based on concrete placement and Clause 4.3.1 for
fire resistance.

Figure 12.1 . The maximum steel area is 4%.

COLUMN MARK

7,10

8, 11

9, 12

UNDERSIDE OF
FOOTING LEVEL

100.040

100.000

100.540

100.100

99.900

101.710

101 .300

101.400

101.500

DETAILING EXAMPLE A
DRAWING SHEET NO. 11.7

11 :16
Reinforcement Detai lin g Handbook

1110

440

NO. 11.4

10, 12

N36

16

N25

COLUMN TYPE

N20

this makes formwork costs excessive.

N25

380

N16

18

10 , 12

N25

COLUMN TYPE
COLUMN SIZE

11

N12

To carry this increasing load downwards from roof to

x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380 380 x 380
4-N 20
4-N20
8-N20
6-N20
4-N20
4-N20
4-N20

CONCRETE GRADE

FLOOR

7, 9

of bars

footing, four alternatives may be considered.

380

MAIN BARS
SECOND

2,4, 6

N um b er Maximum square column size (mm) for bar size

to wind or earthquake resulting in shear forces if the

TYPICAL COLUMN TYPES

COLUMN MARK

Table 12.1
Maximum Square Column Size for 1% Steel Area

12:1

Reinforcement Detailing Handbook

Table 12.5 Fitment Bar Size Required to Restrain a Cranked


Column Bar of Length 10db.main

Table 12.4 Mesh Substitution for Ties


(After AS 3600 Clause 1O.7.4.3d)
Main bar
and tie
arrangement
Single
R6 @ 15db.m
Equivalent
Mesh:

Smallest main-bar size db.main in the column


N12
180
SL52

Single
R10 @ 15db.m 180
Equivalent
Mesh:

SL82

Bundles
R12 @ 7.5db.m 90
Equivalent
Mesh:

N16
240
SL52
240
SL72
120

N20

N24

N28

N32

N36

300
SL52
300
SL62
150

360

Floor Systems
If the concrete strength specified for the
floor system is greater than or equal to 0.75 times

N24

N28

N32

N36

420

480

540

splice must be dimensioned in relation to the floor level

28

32

37

41

46

50

transmission of forces through the joint is deemed to

Slope (mm)

120

160

200

240

280

320

360

be provided.

210

240

270

RL918 RL818 RL718 SL92 SL92 SL82 SL82

Grade D500N1 N12

N12

Grade R250N2 R10

R10

L8

L9

L10
N12

L11
N12

L12

N12

N12

N12

R10

2-R103 2-R103 2-R123 2-R123

Notes:
1 N10 is the smallest size of Grade D500N bar.
2 R10 is the most common. Use wire instead if necessary.
3 Use two fitments of common size rather than one larger-size bar.

bearing, welding or by mechanical splices; the form of


splice can be defined by notes, but the location of the
below the splice.

23

L7

The main bars are spliced by lapping, end-

reinforcement is continuous through the joint,

Offset (mm)
1.12db.m + 10

Mesh and wire L5

12.4.2 Location of Main- Bar Splices

that specified for the column and the longitudinal

If the concrete strength specified for the

Fitment bar sizes, db.fit based on a 90 bend located at a crank

SL62 SL52 SL52 SL52


180

Calculations
Bar size, db.main
based on force
in main bar
N12 N16 N20

12.2 .11 Transmission of Axial Force through

A "kicker", or a small (50 mm) plinth, can be


cast above the floor to help define the column area
and to provide a strong seating for the next set of

floor system is less than 0.75 times that specified

column formwork. Kickers should be detailed. Current

for the column and the longitudinal reinforcement

construction practice does not normally use kickers .

is continuous through the joint, then the effective


compressive strength of the concrete in the joint can be
calculated by formulae given in AS 3600 Clause 10.8.
The formulae is different depending on whether there

12.4.3 Lap Splices


Lapping is usually done at floor level so that
the lower end of the new (upper) bar is supported on

are four beams or two beams on opposing sides at the

hardened concrete. The lap length must be specified in

joint.

the drawings.
The main bars may extend more than one floor

12.3
Author's Note:
The values in the Tables 12.3 and 12.4 appear illogical
because a smaller effective area of mesh will provide
"strength equivalent to bar fitments" as the latter spacing
increases. The reverse would appear more logical.

Example 12.3
Referring to the Example 12.2, the mesh substitute
is SL92 for the bundled bars because the fitment
spacing is 150 mm. Where the smaller column size
controls the tie spacing, mesh SL52 is used as an
equivalent for spacing of R1 0 at 300 mm.

COLUMN PLAN-VIEWS
The location and orientation of all columns is

12.2.10 Restraint of Column Bars at Crank Points


The most popular and economical method
of splicing column bars is by lapping bars which are

shown on footing and floor plans-views. The scale is far


The column shape is indicated but full

must be less than 1 in 6 to attempt to prevent the

details are given separately on cross-sections or by

bars from buckling at the crank due to the horizontal

reference to the column schedule. Columns which

component of the downward force on the bars.

are rectangular or circular are easy to define but other

Additionally, extra ties should be required at the offset.

shapes will require full dimensioning.

12.4

COLUMN ELEVATIONS

This Handbook is based on the premise that


concrete elements are detailed on an element-byelement basis, and that the art of detailing is in showing
how the pieces can be joined together structurally.
Splicing of column reinforcement is critical. Suitable
methods include lap-splices, welding , mechanical
splicing, and end-bearing for columns only if always in
compression.
The length of compressive and tensile lapsplices is given in Chapter 6 for both single and
bundled bars.

The bar size of the ties depends on the

is obtained throughout, Figure 12.6. See AS 3600

Unless extra cross-Sections and other details


each storey of a column . If this approach is used, only
one bar shape need be drawn in full on the elevation

The Table assumes that corner main bars are

(see Clause 11.16 Drawing Sheet No 11.6). Where a

restrained by a 90 corner of a tie, carrying 1.5 times

column schedule is not used, the basic design notation

the horizontal component; hence both legs share

consisting of number off and bar type-size is given on a

the load. The 1.5 factor is not stated in AS 3600, but

leader to this bar and other bars can be arrowed by an

comes from AS 1480:1982 which was not a limit state

extension of this leader.


Where circular and rectangular columns are
shown on the same sheet, more than one column

links with one leg, of the same size shown in the Table,

elevation may be useful because the arrangement of

provide restraint for a force of 1.0 times the horizontal

ties will probably differ.

component.

to 1200 mm. The splices should be staggered within

are provided, it is advisable to use only one bar size in

cranked portion. These forces are derived from

For an internal bar, a separate link or pair of

These splices can best be done when located


at a convenient working height above a floor, say 600

12.4.1 Column Main-Bars

factored loads.

standard.

Welded Splices

Clause 10.7.5 and Clause 12.4.6 of this Handbook.

slope of 1 in 10. A length of 300 mm along the crank is

horizontal component of the vertical force in the

12.4.4 Location of End-Bearing and

the column storey to ensure adequate tensile strength

Table 12.5 gives some values for the type and size
of reinforcement needed to provide this restraint for a

comment made on avoiding steel congestion at


column-to-floor intersections.

too small to show reinforcement.

offset-bent (cranked). The slope of the inclined part

commonly used by schedulers.


12.2 .9 Splicing Column Steel

if there are no changes in column dimensions. Within

Chapter 13 on beam detailing, there is considerable

End-bearing
splices

600
'---1'-+--

Extra tie above


and below splices

Where column sizes change throughout the


height of the structure, adequate elevations and
sections must be used to define offsets to concrete
and bars.

Figure 12.6 Location of End-Bearing Splices

12:4
Reinforcement Detailing Handbook

12:5
Reinforcement Detailing Handbook

12.4.5 Main-Bar Arrangement at Lap-Splice Level

(3) The offset occurs through the beam or floor

Lapped longitudinal bars are achieved by using

level. Unless the beam steel can be moved

cranked bars (shape CC) .


If a column face is offset by 75 mm or more, the

scheduling and fixing problems in deciding how

main bars are not continued through the construction

to get beam steel through the cranked portion .

joint. Separate short straight bars are to be used to

Beam-column intersection problems will always

splice the lower and upper main-bars. The splice length

be severe with narrow beams. Band beams

above and below the jOint w ill depend on the stress,

provide a good solution, Figure 12.9.

Figure 12.7. See also Clause 6.12 and others.


With CC bars, the slope in the crank must not

100

-+---

.....1-114--+-

exceed 1:6 and is common ly specified as 300 mm for

Orientation of the lap at the top and through

Splice bars
(same as upper
column bars)

I IIII

II
II

32dbmn

II

I il
I

robust tying of the main bar to prevent rotation


during the column pour. Remember that the

size. This allows the overlapped portions to be tied

crank is waving around in the air one floor or

together.

more up. Only one floor lift can be made at one

the offset portion of the main bars at a lap splice.

tv II

the beam is critical and must be ensured by

all sizes. The normal offset of the centre-line is one bar

There are three common methods of arranging

I II

I ~-=--=-- ~

sideways, the cranked portion creates

'--__-+-

Tie to support
splice bars

time unless beam details are to be altered on

'---1-+-

Beam bars moved


to accommodate
cranked column bars

alternate floors to accommodate the crank.

(1) The offset is located just above the lap at the


"working floor level" . Orientation problems of the

12.4.6 Main Bars with End-Bearing and


Figure 12.7 Splice Treatment at Offset Column Faces

Mechanical Splices

crank are eliminated, the bar continues straight

An elevation is essential for defining the

through the floor above and fitment dimensions

location above floor level of the end-bearing splices.

can be made identical on each floor and


through the joint itself if shear steel is needed ,

In particular, cross-sections are required for bundled

Figure 12.8. See also Clause 12.2 above.

bars. Bundled bars in col umns require careful attention

Column bars can be continuous through two

to layout to ensure bars in each column lift can be

floors or more depending on lifting capacity and

kept concentric with the columns above and below,

a continuous mesh cage can provide full-height


rigidity. Beam details can be standardised to

Cranked column
bars

Figure 12.10. A sleeve of some form, or a mechanical


connection, must be fixed around each splice to ensure
that the sawn ends are concentric.

provide repetition of prefabrication.

Bar lengths should be multiples of the floor

This method is illustrated on the column

height for any method.

elevation in Clause 11.16 Drawing Sheet

All bars used with end-bearing splices must be

No 11.6, where one floor lift is detailed . Note


particularly how variations in the levels of the

straight and have ends sawn or machined square. The

footings can be accommodated without any

ends must be aligned concentrically by a clamp.


as crimped sleeves may not require special end

strongly recommended that this method be used

Figure 12.10 Bundled Bars Must be Kept Concentric

preparation unless specified otherwise by the

wherever possible.

manufacturer.

(2) The column bars are straight and are not

Threaded connections require special treatment

concentric throughout adjacent columns. This

with reliable protection for both female and male

method has many of the virtues of the first

threads.

method above, although the changes in location


wall construction , and with wide blade columns,

Allow for sleeve thickness when


detailing bundled bars, for
end-bearing and mechanical
splices, to maintain concentricity

Bars spliced by mechanical means such

need to replace bars previously supplied. It is

from lift to lift may be of concern. However in

Figure 12.9 Cranked Column Bars within Band


Beams

Figure 12.8 Cranked Column Bars above Working


Floor Level

it has much to commend it for the internal bars,


if not for the corner bars .

12:6
Reinforcement Detailing Handbook

12:7
Reinforcement Detailing Handbook

12.4.7 Location of Column Ties within the

Column ties may be required within the depth

Column Height

of a beam or slab under special circumstances.

Spacing is generally uniform but it is necessary

See earlier for appropriate guidance on

to indicate the location of the highest and lowest

quantities.

ties, usually 50 mm above the floor or kicker

Details of ties which act as shear reinforcement

12.6

within the beams or slab depth.

CONSTRUCTION

Allowances for adequate tolerances for fixing


main bars into corners of ties or at lap splices,

Column ties should be located above and

etc . Generally values are obtained from the

below and 50 mm below the highest soffit

below end-bearing type splices to resist forces,

AS 3600 and are not stated in the drawings

above, Figure 12.11 . See the AS 3600 because

particularly during construction.

- perhaps they should be.

The following comments are offered to assist


column construction and to reduce cycle times.

For scheduling purposes, the number of ties is

handled on site and could reduce the number of


ties making concrete placement simpler.

12.5

taken as the height from floor to soffit-above,


off to the next higher number.

The number of turns of a circular helix is given in

size bars may be an advantage in many cases,

The concrete strength f e for each lift, particularly

provided the extra ties do not increase fixing

if the column -concrete strength and the

time.

horizontal force there. This is a design matter.


See Clause 12.2.10.

~---~----1-N12-300

concrete f e.

HT + DT

near to its correct position is one of the most

The orientation, shape and dimensions of the

time-consuming tasks on site. It is advantageous

concrete outline for formwork construction. The

if all column bars have the same size and

use of a North Point or relationship to gridlines is

dimensions, and this should normally be

essential.

possible .

The shape and dimensions of the ties (usually

When method (1) of Clause 12.4.5 for designing

determined from the concrete shape) with the

main bars is used, small variations in floor-to-

basic design notation clearly stated. This should

~'"

'.

floor heights can be taken up within the splice


length above the floor.

2-SL62 LDI

consist of the number-off, the steel type and

I--

Method (3) of Clause 12.4.5 requires every

the nominal spacing, Figure 12.12. If there is


Tie spacing, S

Three sets of ties


minimum for support
of lower bars

I--L..

more than one tie at each spacing , the same

IT

is rectangular or circular. This must include


changes to the column size and the appropriate

U
I

J-'f-- - -

-I

50 to first tie

column; this leads to longer sorting times, more

L~~

chance of the wrong bars being used, reordering

NOTE:
For shape designations,
see Figures 9.1 and 9.2

Figure 12.12 Examples of Tie- Bar Notations

of replacement bars because the leftovers will


not fit, additional delays, etc.

(note 1)

column, even if the loads are eccentric. Murphy's

50 max (note

Tie spacing, S

this is not acceptable, restrict changes to one

How the bar arrangement is to be modified

face only.

progressively throughout the height of the


building from the footings . A grid system and

templates for setting out the centre lines of

below the change point must be detailed. The


beam reinforcement layout may also require

contract drawings rather than requiring repeated

re-detailing.

calculations based on nominal concrete

2. 50 mm below the
shallowest beam
with all four
intersecting beams

dimensions and concrete cover by several other

but additional splice bars are to be used,

steelfixers.

Figure 12.11 Location of Column Ties within Column


Height
12:8
Reinforcement Detailing Handbook

Where column faces are offset 75 mm or


more, the main bars are not to be cranked

people such as schedulers, formworkers and


v

If the same column size cannot be maintained,


the column bar arrangement above and

the starter bars should be detailed on the

1. 50 mm below slabs
with three or less
intersecting beams

Maintain the same column section from footing


to roof, particularly if bundled bars are used. If

alongside the lower bar.

>

Never use more than one bar size in anyone


law of material interchange will strike again .

Any special bar arrangements at lap-splices;


that is, whether the upper bar is lapped inside or

NOTES:

column bar to be detailed for a particular

bar re-arrangement.

, _lj~omal.

100

lI

The layout of all main bars within the section,


often by a "typical drawing " if the section

I
32 dia.

information must be restated .

75

Finding the correct bundle of steel for each


column, sorting the steel and then moving it

column, varies from the remainder of the floor-

where the main bar is cranked to resist any

r----t

the above comment, a greater number of smaller


1-N12-300 HT + HH

floor-concrete strength in the vicinity of the

One or more ties should be shown at the point

Manual hoisting of column bars into place is


heavy and time-consuming work. Contrary to

to a larger scale than used with a plan -view. Essential

used to make the helix.

Two sets of ties


at top of crank

information includes:

Figure 9.1 for shape SP, as is the length of wire

COLUMN CROSS-SECTIONS
To be of use, these sections must be drawn

divided by the spacing, the result being rounded

Use the fewest number of bars possible at any


section . This reduces the quantity of bars to be

the rule is quite complex.

DETAILING COLUMNS FOR

Figure 12.7.

Keep the tie layout as simple as possible . The


number of ties is controlled by the centre-tocentre spacing of the bars in each face.

12:9
Reinforcement Detailing Handbook

12.7

IDEAS FOR PREFABRICATION

12.9

EXAMPLE OF A COLUMN SCHEDULE


Clause 11.16 Drawing Sheet No 11.7

Column cages can often be fabricated away


from the forms and lifted into place by a crane or other

provides a column schedule for a pad footing and the

mechanical method. For this to happen, a reasonably

column above. The example is from the footing plan

rigid cage is required. It is not essential that all the bars

given in Clause 11.16 Drawing Sheet No 11.1 and

be tied or welded before erection.

Examples of Footing Details Clause 11.14.2.


Column cross-sections accompany the column

Often the corner bars can be fixed firmly to the

12.10 DETAILING FOR SEISMIC

(INTERMEDIATE MOMENT-RESISTING
FRAMES)
12.10.1 General
As discussed in Clause 10.5.2, MomentResisting Frame Systems , it is desirable to ensure that

outer cage of bars or mesh, and the remainder secured

schedule. Each section is defined by a "type number"

any plastic hinges that may form should do so in the

inside during the lift. Once the cage and corner bars

which is common for all columns having the same

beam elements rather than the columns by ensuring

are placed over the starter bars at each floor level , the

general shape (rectangular or square, say), the same

that the flexural capacity of the column is higher than

others are released and moved into position . Some

number of bars and same tie layout. A well -designed

that of the beam by a significant margin to allow for

flexibility should be permitted in the cage until it is

schedule can save detailing time if the number of

any 'overstrength ' due to design or materials. This is

positioned , then additional tying will be needed.

possible combinations is reduced to a practical

known as the 'weak beam/ strong column' philosophy.

minimum. Future amendments can be done merely by

Although it may not always be possible to achieve

changing the type number.

this, especially with such forms of construction as

To prevent movement during concreting , the


number and spacing of spacers should be specified in

Column orientation is important; a north-point

the drawings.
By placing the lap-splice crank at the bottom

may be necessary especially for rectangular columns.

of the column, a mesh cage for the fitments can be


used full height and even through the floor above. This
method is compatible with the concept of beam caging

The cantilever footings are detailed in


Clause 11.14.2 and Clause 11.16 Drawing Sheet
The pad footings are detailed in Clause 11.14.3

described in this Handbook. As well as simplifying


column-bar placement, this concept enables the main

and Clause 11.16 Drawing Sheet No 11.5.


Table 12.6 is an example of the type of details

beam bars to be pre-assembled outside the form,

without excessive spalling of cover concrete. Adequate

project, or on the same sheet as the column schedule.

region to maintain its axial-load-carrying capacity and

between column and beam bars. There are no

to prevent buckling of the longitudinal compression

AS 3600 requirements for the bottom bars required

reinforcement and subsequent failure. Plastic hinge

Clause 11.16 Drawing Sheet No 11.6


illustrates the lapping arrangement for one column of
the same size above a floor as below. Another column
where the face above is offset from that below is
shown in Figure 12.7.

(c) RECTANGULAR COLUMNS

regions are particularly susceptible where substantial


Table 12.6 Embedment Lengths for Starter Bars and
Splice Lengths for Column Bars

legitimate.

FOR A REINFORCED CONCRETE COLUMN

~'

transverse reinforcement must therefore be provided

column cage in such a way that there is no interference

EXAMPLES OF STANDARD DETAILS

Unconfined
concrete -----..

the structure to achieve the design level of ductility

to confine the compressed concrete within the core

12.8

..,

(b) SQUARE COLUMNS

In many cases, the ultimate compression

which can be given in the General Notes for the

through a support; "continuity" by splicing is perfectly

Unconfined
concrete

failure in the column will not occur.

and for shorter splicing bars to be passed through the

at mid span of a beam to be "continuous" into or

(a) CIRCULAR COLUMNS

band beams (see below), care should be taken that


catastrophic collapse, especially due to brittle shear

strain of unconfined concrete is inadequate to allow

No 11.4.

Unconfined
concrete -----111~

axial forces are present, eg in columns where inelastic


deformations must occur to develop a full-hinge

Bar
Size

Straight
embedment
in footing of
20 DIA. (mm)

N20

400

640

i-RiO or 1-L7

such as at the base of all columns, see Figure 10.1 ).

N24

480

770

2-R10 or 1-L9

12.10.2 Confinement

N28

560

900

2-R10 or 1-L10

N32

640

1030

1-N12 or 1-L11

N36

720

1160

2-N12 or 1-L1 2

Splice
length
of
32 DIA. (mm)

Number of
fitments at
column bar
crank

is based upon weak beam/strong column philosophy,

Unconfined
concrete

...

mechanism.
(Note: This may occur even where the design

Close-spaced transverse reinforcement acting


in conjunction with longitudinal reinforcement restrains
the lateral expansion of the concrete. This enables the
concrete to withstand higher levels of compression.
Circular or helical ties, due to their shape,
are placed in hoop ten sion by the expanding
concrete and provide confinement to the enclosed

(d) SECTION BETWEEN MAIN BARS

... +Unconfin ed
concrete

-+

++++++.... +-

I-

-+
-+
-+
-+
-+
-+
-+ ,-

..

(e) SECTION AT MAIN BARS

Figure 12.13 Confinement of Column Sections by


Transverse and Longitudinal Reinforcement

concrete Figure 12.13(a). Rectangular ties apply full


confinement only near their corners as the pressure of
the concrete bends the legs outwards. This tendency

12:10
Reinforcement Detailing Handbook

concrete between longitudinal bars are shallower, and

should be counteracted by the use of cross-ties or

consequently a greater area of concrete is confined.

interconnected closed ties. This has the additional

The presence of a number of longitudinal bars,

benefit of increasing the number of legs crossing

enclosed by closely spaced ties will also significantly

thk section. The profiles of the unconfined zones of

aid confinement. Figure 12.13(b), (e) , (d) and (e) .

12:11
Reinforceme nt Detailin g Hand book

12.10.3 Lapped Splices

The confinement of concrete is addressed in

It is inevitable that splices will occur in the

Appendix A of AS 3600 by the provision of closed ties ,

column reinforcement of multi-storey buildings. It is

where requ ired, over a distance of either:

important therefore to ensure that these are detailed

The maximum dimension of the column cross-

and located such that failure will not occur under

section; or

earthquake action. Splicing is usually achieved by the

One-sixth of the least clear distance between

longitudinal reinforcement against the core concrete.


In circular columns, the clamping force is provided by

transmission occurs due to the bond between the bars

Further, the spacing of the closed ties is to be

induced above and below the column joint and

been shown to be very efficient at resisting the radial

simultaneously occurring reversals of beam moment

cracks that can develop. Further, these ties can restrain

across the joint, cause the region to be subject to

an unlimited number of splices .

both horizontal and vertical shears of much greater

Unless the capacity has been checked by

calculated shear force in a joint resisting earthquakeinduced forces , transverse reinforcement must be

the splice under cyclical loading at up to but still below

provided through the joint to prevent the occurrence

yield stress of the reinforcement, they will not ensure

of brittle joint shear failure, rather than obtaining the

forces are to be transmitted by bond, splitting of the

a satisfactory ducti le response. This is especially true

desired flexural beam hinges. (See Reference details

concrete can occur. To prevent these occurrences,

where large-diameter bars are lapped in the p lastic

at end of this Clause). This transverse reinforcement

ties are required to provide a 'clamping force' to the

hinge zone. The splice w ill fail after a few cycles of

is provided by continuing the closed ties required for

loading large enough to induce inelastic behaviour

columns adjacent to the joint.

Under severe cyclical loading , column splices

face. (Note: do in this case is taken from the

tend to progressively 'unzip'. Further, where large steel

larger column dimension) . The overall crosssectional area of the ties must obviously be
sufficient to satisfy the shear requ irements of the
column Figure 12.14.

beams and columns themselves . However low the

be placed in potential plastic hinge reg ions. Whilst

response of concrete between adjacent bars.

the first tie located at 50 mm from the support

in the longitudinal reinforcement, with a consequent


Recommended pract ice:
Lap splices only within centrer=
half of clear column height
unless calculations show
otherwise

Recommended practice:
J - Lap splice to be confined by at least 2 closed ties

p5Sc

Column
ties

Closed ties may be spaced at 2S c (or Sc with 0.5Asv) for the depth of the shallowest
beam provided beams frame int the column from at least two directions at right angles.
For all other conditions, use ties spaced at Sc

occur at the base of first-storey columns. (Note: This is

Y1

= the larger core dimension

true for all frame types). Consideration should therefore

Ag

= the gross cross-sectional area of

Ac

= the cross-sectional area of the core

fc

= the characteristic compressive cylinder

~'D.4<\

New Zealand practice allows that columns that

t.

fsy.f = the yield strength of the ties

plastic hinges - providing the column shear strength

<I>

is similarly higher, ie matching the column flexural

Nuo = the ultimate strength in compression of

Fully scabble al I
construction joi nts

an axially loaded cross-section without

then splicing of longitudinal bars by lapping may be

eccentricity

undertaken immediately above the floor level.

couplers (eg Alpha or Lenton) is often done where bar

N* = the axial compressive or tensi le force


on a cross-section .
The area of reinforcement required may,

congestion may prove problematic. It is recommended

however, be reduced by half where equal resistance to

that under no circumstances should these be situated

joint rotation provided in at least two directions at right

in a potential plastic hinge region, in order to help

angles, but only over the depth of the shallowest of the

ensure a strong column/ weak beam failure .

framing members. (See Figure 12.14).

Site welding of bar splices requires special

Asv = cross sectional area of ties


Sc = closed tie spacing not to exceed 0.25d o' Sd b, 24d f or 300 mm
S = column tie spacing not to exceed the smaller of Dc or 15db

consideration and care during execution . It is

Dc = smaller dimension of column cross-section


D= largest column dimension, but not less than one-sixth clear height

welding is acceptable, provided it is carried out using

do = effective depth of member 2: O.S D


db = diameter o'f smallest longitudinal bar enclosed by the tie

welded splices are never used in a potential plastic

df = diameter of tie bar

= a strength reduction factor

capacity. If the formation of plastic hinges is precluded ,

Splicing by welding or the use of mechanical

Supplementary cross ties may be used if of the same diameter as the closed tie
and secured with the closed tie to the longitudinal bars

'-

strength of concrete at 28 days

of the adjoining beams are unlikely to yield and form

/ID=4d f

l-9J-Sc

measured over the outside of the ties

have greater than 1.25 to 1.4 times the flexural strength

Closed ties must be provided in all joints and in the columns for a distance, D,
above and below joints

(9

the column

be to locate the splice at mid-height of the column.

Closed tie hooks at each end

1350

where:

be given to carrying the column bars above first floor


level before splicing . A less preferred alternative would

Recommended practice where plastic hinge formation possible:


When welded splices or mechanical connection are used, not more than alternate bars
may be spliced at any section with vertical distance between splices 600 mm or more

Closed
D ties

0.09SY1 (fc/fsy.f)

= centre to centre spacing of the ties

+
Lo Clear
column
height

or

~
~

bars (see Reference: Paulay, T. and Priestley, M .J.N.

Seismic Design of Reinforced Concrete and Masonry

[unless <l>Nuo > N*]

example, a plastic hinge would normally be expected to

+ Sc

0.30SY1 (Ag /Ac - 1)(f c/fsy.f)

Recommended practice:
Provide double ties at bends

Closed
D ties

The area required Asy is to be the greater of:

gradual deterioration of bond transfer between the

Buildings, John Wiley and Sons Inc, 1992). For

135

Closed
ties

magnitude than those experienced by the adjoining

design, it is recommended that splices should not

transverse ties may ensure strength development of

and the surrounding concrete, as well as due to the

the least of 0.25d o, 8db , 24df or 300 mm with

Under seismic loading, reversing moments

helical or circular ties. This form of reinforcement has

use of overlapping parallel bars. In this method, force

consecutive flexural members framing into it.

12.10.4 Beam/Column Joints

recommended that lap welding should be avoided. Butt

a proper procedure but, again, it is recommended that

hinge region. (Figure 12.14).


\

Figure 12.14 Typical Column Details for Intermediate Moment-Resisting Frame Structures
12: 1 3
1 2:12
Reinforcement Detailing Handbook

Reinforcement Detailing Handbook

l'

Figure 12.15(a) shows the effects of shear

transfer of concrete compression forces and some


bond forces which, especially at external beam/column
connections, require special consideration with

Internal actions
and crack pattern

regard to reinforcement anchorage. A considerable

Flange
(floor slab)

Beams

13.1

Web or
stem

GENERAL

length of the top bars is ignored when calculating


13.1.1 Purpose

the development length because of expected bond

RECTANGULAR BEAM

T-BEAM

For most practical purposes, a beam is a

deterioration under cyclic load reversal. It should also


be noted that the bottom beam bars are bent upwards

horizontal member of relatively small size which carries

at the end, Figure 12.15(b). If they are not, this will

a vertical load and transfers that load to its supports.

result in poor behaviour of the joint in the direction of

These supports can be either another beam, a column

loading, In addition, proper anchorage of the bottom

or a wall.
For structural design purposes as interpreted by

beam bar is necessary in order to transfer shear

Flange
(floor slab)
Web or
stem

AS 3600, some of the methods used to design beams

through the joint via a strut mechanism. However,

Transfer of
concrete forces

tests have shown that U-bars are not as effective as

may also be used for slabs and walls . The physical

top and bottom bars anchored separately. (Reference

shape of the member, that is its cross-section, has

NZS 3101:1995) .
See the following references for more information:

considerable effect on the method to be used.

L-BEAM (AND SPANDREL)

BAND BEAM

Figure 13.1 Beam Shapes

For simplicity of description, beams are usually


called "rectangular", "T-beams" or "L-beams" because

(i) Paulay, T. and Priestley, M.J.N. Seismic

Design of Reinforced Concrete and Masonry


Buildings, John Wiley and Sons Inc, 1992

have their own particular methods of design although

illustrates the manner by which the vertical loads are

many are common.

applied to the top face of the beam - directly on to

(ii) American Concrete Institute, ACI 318-89

All of these apparently different types of beams

of the way they look and because this shape also

The span of a beam is a term often used here

(revised 1992) Building Code Requirements

the rectangular beam , or on to the attached slab for

and includes "sing le span", "continuous span", "simply

for Reinforced Concrete and ACI 318-89R

the T-beam and L-beam . In the case of the latter two

supported span", etc.

Transfer of
some bond forces

(revised 1992) commentary Chapter 21

Special Provisions for Seismic Design.


(iii) Irvine, H. Max and Hutchinson, G.I. (eds)

Australian Earthquake Engineering Manual


3rd Edition, Techbooks, 1993.

(a) Shear transfer of concrete compression forces and some bond


forces from longitudinal bars by diagonal compression
strut mechanism

types, the attached slab is called the "flange" and this


is a very important part of the total beam cross-section.

Example 13.1

Beams can also be upstand or downstand. For an

1. In Clause 11.14.2, the cantilever footing detail CF4


would have been designed as a beam - it is called
a footing because of its location - although the load
along it comes from the earth below due to the
vertical downwards column loads.

upstand beam, the slab should remain propped until


the top section of the beam is cast and cured.

Figure 13.1 illustrates various beam shapes.


The rectangular part of a T- or L-beam below
the slab is called the "web", in the bottom of which is

Not
permitted

0.5 he or 8db whichever is lesser


(this length is disregarded becausE
of loss of bonding during cyclic
loading)

the main "bottom tensile" reinforcement. The deeper


the beam, the greater will be its load-carrying capacity.
The flange at the top carries the compressive forces in

2. In Chapter 12 on columns, the fact that some


columns must be designed as beams did not
need to be known for detailing purposes, but it is
important for the designer. Columns do not always
have the main bars arranged uniformly around the
edges.

the concrete to balance the tensile forces in the bottom


reinforcement. To a lesser degree, the wider the flange
Plastic hinge

the greater the load carrying capacity as well.


Wide shallow beams (known as "band beams")

Not
permitted

are a compromise between shallow beams and deep


O.She or 8d bwhichever is lesser
(this length is disregarded becaUSE
of loss of bonding during cyclic
loading)

(b) Anchorage of beam bars when the critical section of the


plastic hinge forms at the column face

slabs, whilst narrow closely-spaced beams (called


"ribs") are another form with particular uses.
"Prestressed" and "precast" concrete beams
including beam shells are not included in this
Handbook. Refer to the Precast Concrete Handbook,
jointly published by National Precast Concrete

Figure 12.15 Shear Transfer at Beam/Column


Connections and Suggested Beam Reinforcement
Anchorage at External Columns

Association Australia and Concrete Institute of Australia,


for details of these.

13:1
12:14
RAinforcement Detailinq Handbook

Reinforcement Detailing Handbook

S-ar putea să vă placă și