Documente Academic
Documente Profesional
Documente Cultură
283 - 2
TABLE OF CONTENTS
PAGE
I.
SUMMARY
283 - 3
II.
283 - 3
III.
283 - 4
A. MARKET STUDY
283 - 4
283 - 6
283 - 7
283 - 7
B. UTILITIES
283 - 8
283 - 8
A. TECHNOLOGY
283 - 8
B. ENGINEERING
283 - 10
283 - 11
A. MANPOWER REQUIREMENT
283 - 11
B. TRAINING REQUIREMENT
283 - 12
FINANCIAL ANLYSIS
283 - 13
283 - 13
B. PRODUCTION COST
283 - 14
C. FINANCIAL EVALUATION
283 - 15
D. ECONOMIC BENEFITS
283 - 16
IV.
V.
VI.
VII.
283 - 3
I.
SUMMARY
This profile envisages the establishment of a plant for the production of tomato souce and
ketchup with a capacity of 600 tonnes per annum.
The present demand for the proposed product is estimated at 522 tonnes per annum. The
demand is expected to reach at 850 tonnes by the year 2017.
The total investment requirement is estimated at Birr 11.05 million, out of which Birr 7.04
million is required for plant and machinery.
The project is financially viable with an internal rate of return (IRR) of 24 % and a net
present value (NPV) of Birr 7.16 million, discounted at 8.5%.
II.
Tomato ketchup and souce are produced by processing fresh tomato which is clean and
wholesome. With some additives, they have high acidity taste and rich flavor. To prepare
tomato ketchup and sauce, it should be ascertained that the tomatoes used are clean
wholesome tomatoes of intense red colours. Tomato ketchup and sauce are consumed by
households, restaurants, hotels and institutions like hospitals, schools, etc.
Processing of tomato ketchup and sauce mainly depends on the availability of a large and
stable supply of fresh, quality tomato and the availability of a vast supply of water.
283 - 4
III.
A.
MARKET STUDY
1.
Tomatoes are one of the most widely grown and commercially important vegetable crops and
are valuable sources of food minerals and vitamins, particularly vitamins A and C. In
addition, studies have shown that people who eat large amounts of tomatoes or tomato
products may be at a lower risk of some kinds of cancer, especially cancer of the prostate
gland, lung, and stomach.
Tomato ketchups and sauces are produced by processing fresh tomatoes and hot fruits.
Processed and canned tomato sauces and ketchups are consumed by urban households,
restaurants, hotels, hospitals and the like. The demand for tomato sauce and ketchup is
mainly met through import (See table 3.1.)
Table 3.1
IMPORT OF TOMATO SAUSE & KETCHUP(TONNES)
Year
Import
2000
81.2
2001
57.5
2002
234.7
2003
521.3
2004
477.7
2005
841.5
2006
248.1
283 - 5
As could be seen from Table 3.1, import of tomato souse and ketchup has been generally
rising. During the period 2000-2001 the annual average level of import was about 69 tons
and increased to annual average of about 378 by the year 2002 and 2003. During the recent
three years i.e. 2004-2006 the annual average import has reached to a level of about 522 tons.
Since import has been generally showing an increasing trend the 522 tons, which is the
average of the recent three years import, has been taken as the current effective demand.
2.
Projected Demand
Demand for processed and canned tomato sauce and ketchup is mainly influenced by
urbanization, income and change in the consumption habit of the population.
Urban
population growth in Ethiopia is about 4% while GDP in the last few years has been growing
by more the 7%. As income rises and urbanizations grows there is a shift towards more
expensive but conveniently packed foods. Considering the above factors demand for tomato
souses and Ketchups is forecasted to grow by 5% per annum (See Table 3.2)
Table 3.2
FORECASTED DEMAND FOR TOMATO SOUSE & KETCHUP(TONNES)
Year
Forecast
2008
548
2009
575
2010
604
2011
634
2012
666
2013
699
2014
734
2015
771
2016
810
2017
850
283 - 6
3.
A factory gate price of Birr 15 per kilogram is proposed as a factory gate price. Experienced
wholesalers in food staffs can be appointed to distribute the product.
B.
1.
Plant Capacity
Based on the market study, the envisaged plant will have a capacity of producing 600 tonnes
of tomato ketchup and sauce per annum, out of which 150 tonnes will be tomato ketchup and
450 tonnes tomato sauce. A capacity of 2 tones per day is considered on the basis of single
shifts of 8 hours per day and 300 working days per annum. This capacity can be increased by
increasing the number of shifts per day.
2.
Production Programme
Table 3.3 shows the production programme of the envisaged project. At the initial stage of
production, the plant may require some years to penetrate into the local and export market.
Therefore, in the first and second year of production, the capacity utilization rate will be 75%
and 85%, respectively. From the third year onwards, 100% capacity production shall be
attained.
Table 3.3
PRODUCTION PROGRAMME
Production Year
Product
Unit
2008
2009
2010-2018
Tone
450
510
600
75
85
100
283 - 7
IV.
A.
The basic raw material required by the processing plant is fresh tomato. Since the quality of
the sauce and ketchup that is produced will be determined largely by the quality of the
tomato used as raw material, great importance is attached to tomato cultivation itself.
Auxiliary materials required by the plant and which are added to impart good taste consist of
salt, sugar, vinegar, spices, and other ingredients. The raw and auxiliary materials
requirements of the envisaged project at 100% capacity utilization are indicated in Table 4.1
below.
Table 4.1
ANNUAL AUXILIARY MATERIALS REQUIREMENT
AND ESTIMATED COST
Sr.
No
Cost
Description
Unit
Total
(Birr)
Tonnes
2500
3,125,000
Fresh Tomato
Salt
Kg
12.204
14.65
Sugar
Kg
37.83
208.10
Vinegar
Kg
15.504
224.80
Spices
Kg
4.374
769.80
Others
Kg
3.522
550.30
Glass bottles
Pcs
375,000
375,000
Cans
Pcs
1,125,000
1,406,250
Cartons
Pcs
62,696
50,156.80
Grand Total
4,958,174
283 - 8
Thus, the total annual cost of raw and auxiliary materials at full capacity production will be
Birr 4,958,174. The bottles and all other auxiliary materials can be procured locally, except
laminated cans which have to be imported.
B.
UTILITIES
Utilities required by the plant consist of electricity, water and fuel oil for boiler. The total
annual requirement at 100% capacity utilization rate and the estimated costs are given in
Table 4.2 below. The annual expenditure on utilities will, therefore, be Birr 252,563.
Table 4.2
ANNUAL UTILITIES REQUIREMENT AND COST
Sr.
Cost
Description
Unit
Quantity
Electricity
KWh
17,152
8,113
Water
M3
5,100
28,050
Fuel oil
Liter
40,000
216,400
No.
Total
V.
A.
TECHNOLOGY
1.
Production Process
(Birr)
252,563
To accomplish this task, a special washing technique has been developed that allows for the
preservation of the fresh, natural qualities of ripened tomato.
283 - 9
Crushing: - Washed tomato is crushed into tomato pulp (Juice) which is strained and
filtered.
Concentration: - after crushing the filtered tomato pulp becomes preheated and
Flavoring: - Salt, sugar, spices, vinegar & other ingredients are added in the seasoning
room to give it the flavor associated with tomato sauce & tomato ketchup.
Bottling/canning:-The products are then filled into bottles and cans.
Packing and dispatching: - Then the products will be packed and dispatched.
There are various recipes employed for producing tomato ketchup and sauce.
The recipe
applied for tomato ketchup shows a considerable variation from the recipe used to produce
tomato sauce. For production of tomato ketchup, spices are added to the vinegar and cooked
at about 85oC, covered in a dried kettle for about 2-3 hours. Onion, garlic and paprika are
then added directly to the ketchup.
2.
Source of Technology
Machinery & equipment as well as technology required by the envisaged plant can be
obtained from abroad.
The addresses of a firm that can be a source of technology supplier are given below.
283 - 10
1. Frelgmdires International,
Maharastera, Mumbai - 400 013, India.
Fax; + (91)-(22)-24944108/22186046/22187756.
B.
ENGINEERING
1.
The list of machineries and equipments required by the envisaged plant is indicated in Table
5.1. The total cost of machinery is estimated at Birr 7,064,312, of which Birr 5,221,446 is
required in foreign currency.
Table 5.1
LIST OF MACHINERY AND EQUIPMENT
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
Description
Tomato charging m/c
Tomato washing and sorting m/c
Continuous concentrator
Filter
Homogenizer
Seasoning mixer
Bottling m/c
Cooler
Labeler
Packing m/c
Water treatment facility
Boiler
Other auxiliary equipment
Qty.
1 set
1
1
1
1
1
2
1
1
1
1set
1
1 set
283 - 11
2.
Total land requirement is estimated at 2,000 m2. The total built-up area is estimated to be
800 m2.
This includes production hall, finished products and raw materials stores, offices
and social facilities and open spaces. The total cost of buildings and civil work at a unit cost
rate of Birr 2300 per m2, is estimated at Birr 1,840,000. The total land lease cost, at the rate
of Birr 0.7 per m2 for a period of 80 years of land holding, is estimated at Birr 112,000. The
total land lease cost is assumed to be paid in advance.
3.
Proposed location
The envisaged plant should be located in areas where fresh tomato can be abundantly
supplied and infrastructure and market is available. Taking this in to consideration, Arba
Minch zuria and Bench woredas, which are found in Gamo Gofa and Benchmaji zones
respectively can be the possible locations for the project.
From the above two woredas, Arba Minch Town, the capital of Arba Minch Zuria woreda, is
selected to be the location of the proposed project.
VI.
A.
MANPOWER REQUIREMENT
The plant requires both skilled and unskilled labour to carry out production activities.
Indirect manpower will be engaged in carrying out administrative activities.
The total
manpower requirement together with monthly and annual salaries is presented in Table 6.1.
The envisaged project requires a total of 31workforce.
283 - 12
Table 6.1
MANPOWER REQUIREMENT AND LABOUR COST
Sr.
Description
No.
Req.
Salary (Birr)
No.
Monthly
Annual
A. Administration
1
Plant Manager
2,800
33,600
Secretary
800
9,600
Accountant
900
10,800
Salesman
600
7,200
Personnel
600
7,200
Clerks
600
7,200
General Services
800
9,600
Sub-Total
11
7,100
85,200
B. Production
1
Production Supervisor
1,200
14,400
Technicians
1,200
14,400
operators
1,500
18,000
Labourers
12
2,400
28,800
Chemists
1,900
22,800
Sub-Total
20
8,200
98,400
Total
31
15,300
183,600
3,060
36,720
18,360
220,320
Workers Benefits
(20% of basic salary)
Grand Total
B.
TRAINING REQUIREMENT
One technologist should be given a one month on- the-job training in Merti Processing Plant
during erection & commissioning period.
15,000.
283 - 13
VII.
FINANCIAL ANALYSIS
The financial analysis of the tomato sauce and ketchup project is based on the data presented
in the previous chapters and the following assumptions:-
Construction period
1 year
Source of finance
30 % equity
70 % loan
Tax holidays
Bank interest
3 years
8%
8.5%
Accounts receivable
30 days
30days
90days
Work in progress
3 days
Finished products
30 days
Cash in hand
5 days
Accounts payable
30 days
A.
The total investment cost of the project including working capital is estimated at Birr 11.05
million, of which 38 per cent will be required in foreign currency.
The major breakdown of the total initial investment cost is shown in Table 7.1.
283 - 14
Table 7.1
INITIAL INVESTMENT COST
Sr.
Total Cost
No.
Cost Items
(000 Birr)
1,840.00
7,046.31
150
Vehicle
650
Pre-production Expenditure*
325.00
Working Capital
927.69
112
11,051.0
Foreign Share
N.B
38
costs of registration,
licensing and formation of the company including legal fees, commissioning expenses, etc.
B.
PRODUCTION COST
The annual production cost at full operation capacity is estimated at Birr 6.60 million (see
Table 7.2).
The material and utility cost accounts for 78.93 per cent, while repair and
283 - 15
Table 7.2
ANNUAL PRODUCTION COST AT FULL CAPACITY ('000 BIRR)
Items
Raw Material and Inputs
Utilities
Cost
4,958.17
75.10
252.56
3.83
80
1.21
102.24
1.55
42.6
0.65
68.16
1.03
5,503.73
83.37
981.63
14.87
116.35
6,601.71
1.76
100
C.
FINANCIAL EVALUATION
1.
Profitability
According to the projected income statement, the project will start generating profit in the
first year of operation.
The income statement and the other indicators of profitability show that the project is viable.
283 - 16
2.
Break-even Analysis
The break-even point of the project including cost of finance when it starts to operate at full
capacity ( year 3) is estimated by using income statement projection.
BE =
Fixed Cost
= 28 %
3.
The investment cost and income statement projection are used to project the pay-back period.
The projects initial investment will be fully recovered within 4 years.
4.
Based on the cash flow statement, the calculated IRR of the project is 24 % and the net
present value at 8.5% discount rate is Birr 7.16 million.
D.
ECONOMIC BENEFITS
needs, the project will generate Birr 5.43 million in terms of tax revenue. The establishment
of such factory will have a foreign exchange saving effect to the country by substituting the
current imports.