HAZARDS IDENTIFICATION
Condtion
No.
Main Activity
(List down in
sequence)
(The tasks
were carried
out during
which
condition?)
Sub- Activity
Hazards Desription
1. Print Checklist of
stock count from
system
1. Broken socket
2.Store room
hallways
RISK ASSESSMENT
Consequences
(Explain what type of injury may
happen if source of danger is not
being taken care of)
Initial
Risk
F
L
S
(Frequency) (Likelihood) (Severity) Rating
Sig?
(IRR)
20
II
1.0
20
II
20
1.0
20
II
20
1.0
20
II
20
1.0
20
II
30
1.0
30
III
30
1.0
30
III
30
1.0
30
III
NS
NS
NS
NS
NS
NS
20
20
1. Body Injury
20
Risk
Cat.
1.0
Final
Any
Risk
Related
Legal
(What action has been (Is the ECM Rating
Effective?) (FRR)
taken to tackle the
issues?)
II
ECM
Factor
20
Existing Control
Measures
(ECM)
1.0
STOCK
COUNT
1. Short circuit
DETERMINING CONTROLS
3. Fatal / Accident
Signage
1.
2.
3.
4.
5.
Elimination of aspects,
Isolation,
Substitution,
Engineering,
Administrative
Department :
Last Update:
dd/mm/yy
Section/Area:
Job Activity:
HAZARD IDENTIFICATION,
RISK ASSESSMENT & DETERMINING CONTROL
(HI RA DC)
Prepared by:
Reviewed by:
Approved by:
Date:
Date:
Date:
HAZARDS IDENTIFICATION
RISK ASSESSMENT
Condtion
No.
Main Activity
(List down in
sequence)
(The tasks
were carried
out during
which
condition?)
Sub- Activity
Hazards Desription
Consequences
(Explain what type of injury may
happen if source of danger is not
being taken care of)
Initial
Risk
F
L
S
(Frequency) (Likelihood) (Severity) Rating
Sig?
(IRR)
Category
Likelihood of Hazard to
Occur
> 1 year
Very unlikely
1 / 6 months
1 / 3 months
Unlikely
Likely
Most likely
Certain
Cost
Negligible
-First aid
No property damage/
< RM 5k
Minor
-<4 days MC
RM 5 ~ 10k
Existing Control
Measures
(ECM)
ECM
Factor
Final
Any
Risk
Related
Legal
(What action has been (Is the ECM Rating
Effective?) (FRR)
taken to tackle the
issues?)
Condition of assessment
N
Normal condition
Ab
Abnormal condition
Risk Rating
Risk
Cat.
Risk Level
1-9
Trivial
10 - 25
II
Acceptable
Emergency condition
Elimination of aspects,
Isolation,
Substitution,
Engineering,
Administrative
No action required
Serious
->4 day MC
Decision
Initial RR
NS
1, 2 or 3
= or <25
4 or 5
> 25
RM 10 ~ 100k
Permanent disability
RM 100 ~ 1 Million
Fatal
AP
NIL
Nil
26 - 45
III
Moderate
Significant
Extensive
> RM 1 Million
ECM Factor
46 - 85
A
(need to comply
with legal req)
> or = 85
AP
(with permit)
IV
0.1 All applicable controls are relevant, applied and systematically implemented in terms of Engineering, Administrative and PPE/SK.
0.3 All applicable control are applied, however, further control on engineering, administrative and/or PPE/SK is required
0.6 Certain engineering, administrative and/or PPE/SK control are available, however, not adequate or relevant to minimize the risk.
1.0 There's no obvious control on the activity.
Risk
Cat.
1.
2.
3.
4.
5.
DETERMINING CONTROLS
Occupational Safety
Category
Inconceivable
Yearly
Description
Is practically impossible and has
never occurred
Has not been known to occur after
many years
Category
Monthly
Remote
Weekly
Conceivable
Likely
Possible
Most likely
Most likely
Certain
Daily
Hourly
Description (criteria)
Description
Very unlikely
Condition of assessment
Environment
Unlikely
N - Normal condition
Ab - Abnormal condition
E - Emergency condition
Environment
Scale
Category
Impact on human
(H)
Category
Negligible
No or slight impact to
environment
Minor
Limited impact to
environment
Serious
Considerable impact to
environment
Impact on ecology
(E)
Impact on financial
(F)
(Economic effect)
- Contamination.
- Damage sufficiently to attack the
environmental at incident site.
- Minor damage
- Brief disruption to operations
- Localised damage
- Partial shutdown (short period)
Beneficial impact:
- Has economic effect on the
business concerned (ripple effect on
business)
Impact on organization
image (I)
(Concern of interested
parties)
Fatal
Catastrophic
Extensive impact to
environment
- Extensive damage
- Total lost of operation
Beneficial impact:
- No economic effect is expected
(ripple effect on business)
Description
0.1
All applicable controls are relevant, applied and systematically implemented in terms of Engineering,
Administrative and PPE/SK.
0.3
All applicable control are applied, however, further control on engineering, administrative and/or PPE/SK is
required
0.6
Certain engineering, administrative and/or PPE/SK control are available, however, not adequate or relevant to
minimize the risk.
WWTP
FACILITY
FACILITY
H7
H8
H6
H5
H4
GATE 3
GATE 4
C1
FPI
H2
H1a
C2
LAB
H3
SVC
GATE 2
FPI
GATE 1
L4
H1b
GATE 4
STORE
L1
MAINTENANCE
L3
L2
GATE 1
GATE 2
L5
GATE 3
GATE 5
FPI
LPT
SVC
HPC
maint
inspection
WWTP + DI water
blending
chemical cleaning
welding
dust collector
welding
FPI - SVC-HPC-LPT
manual grinding
cooling tower
molten salt
HVOF
compressor
vibratory + molydag
arc wire
blasting
waste management
peening
inspection
machining
manual grinding
blasting
coating furnace
blasting
Prepared By:
Date:
Review By:
Date:
Prepared By:
Review By:
Date:
Date:
Prepared By:
Date:
Review By:
Date:
(C )Mechanical
Hair, clothing, jewellery, rags, etc liable to become entangled in moving components
Uncontrolled or unexpected movement of machinery, components, work pieces, vehicles or loads
Inability to slow, stop or immobilise machines, vehicles
Body parts coming in contact with moving, sharp, hot, or "live" components during testing, inspection, operation, maintenance, cleaning or repair
Possibility of traffic accident
Persons or body parts trapped or sheared between moving component & fixed plant, materials or structures
Persons pushed, pulled or thrown off plant, structures
Machines, components, or materials disintegrating (eg grinding wheels)
Persons being injured by damaged, poorly maintained or unguarded equipment (including electricals)
Components, work pieces, fluids, etc being ejected
(D) Electrical
Contact with "live" components during testing, inspection, operation, maintenance, cleaning or repair.
Contact with overhead power lines
Contact with underground power cables
Explosion or ignition of electrical components, etc
Unauthorised access to electrical services, switchboards, controls, etc
Prepared By:
Date:
Review By:
Date: