Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 1 of 5
00
10th June,
2012
Ab.Maje
ed
Rev
No
DATE
Prepared
By
TITLE
Checke
d
By
Approva
ls
Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 2 of 5
Table of Contents
1. OBJECTIVE.......................................................................................................... 3
2. SCOPE................................................................................................................. 3
3. REFERECNES...................................................................................................... 3
4. ABBREVATIONS.................................................................................................. 3
5. RESPONSIBILITIES............................................................................................ 3
6. EQUIPMENT........................................................................................................ 4
7. PROCEDURE....................................................................................................... 4
8. MATERIAL........................................................................................................... 5
9. SAFETY EQUIPMENT........................................................................................ 5
10. SAFETY CHECKS............................................................................................ 5
11. MANPOWER.................................................................................................... 5
TITLE
Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 3 of 5
1. OBJECTIVE
1.1-
2. SCOPE
2.1
This method statement covers inspection and quality
monitoring of
construction activities for houses based on approved
engineering principles.
3. REFERECNES
3.1
3.2
I
3.3
3.4
Approved quarries
Approved quarries
4. ABBREVATIONS
4.1
4.2
4.3
4.4
PM
QA & QC
HSE
RFI
Project Manager
Quality Assurance & Quality Control
Health Safety & Environment.
Request for Inspection
5. RESPONSIBILITIES
5.1
Project Manager is responsible to
ensure that the
construction activities
for the building are conducted according to this method
of statement, latest
METHOD STATEMENT FOR
CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)
TITLE
Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 4 of 5
6. EQUIPMENT
6.1
6.2
6.3
6.4
material.
6.5
6.6
Mixer Machine
Block manufacturing machine
NET(Jali) for screening of material
Measuring pan (DAGA0 for measurement of exact quantity of
Hand shovel
Mortar pan if required
Hessian cloth
6.7
7. PROCEDURE
7.1
Shop drawing for sewage drainage pipes approved by
Engineer
7.2
Material must be approved by Engineer
Procedure
Following procedure will be followed
RFI(request for inspection shall be sent to engineer for approval
7.3
7.4
7.5
7.6
Laying of pipes
Maintain slope level of pipe to 1%
Hydro testing for piping, for 2 hours\
Approval for casing
TITLE
Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 5 of 5
7.7
Removing of mould after manufacturing blocks must be with
due care
7.8
Curing of concrete manufactured blocks shall be ensured in
order to
achieve required compressive strength
7.9
Minimum crushing strength of 1000 PSI average of three
units tested or 850
psi per individual unit.
7.10
Proper Cleaning of Platform where blocks are manufactured.
7.11
After hardening of concrete blocks, concrete blocks will be
picked from
platform to another place nearby platform.
7.12
Concrete blocks will be properly stacked and will be covered
with hessian
cloth to maintain the moisture for longer time.
8. Material
8.1
8.2
8.3
9.1
9.2
9.3
9.4
9.5
Safety helmet
Safety shoes
Gloves
Safety Glasses
Dust Mask
9. Safety Equipment
10.
Safety Checks
10.1
Safety Engineer will make ensure that working area is safe
and accordance
with project site regulations
11.
11.1
11.2
11.3
11.4
MANPOWER
QC Engineer
Lab Technician
Foreman
Labor