Sheet 1

Issue
11-10-2010
To
15-10-2010

Week Report Of Activities in The Program Of Works


Hotel-Ambassador- G&I 5* Hotel

Project

Ground, Technical & Mezzanine Floors


Trade

Tasks

Status

Shop Draiwings
Masonry & Problem solving (Wall Prenetration ... Etc)
POP ( Meeting Room ,Adm offices & Toilets GF)
Tiling on Floor ( GF & MF BOH)
False Ceiling Structure ( GF & MF BOH)
Tiling on To Finish
False ceiling Panel ( GF FOH )
Laundry Water proof,pads &Tile on Wall
ECG connection and electrical room ( Milestone)
Mechanical Rooms ( Milestone)
Voids Inpections

on
on
Not start
Not start
Not start
on
Stop
Stop
0n
on
on

Maine Line Finishing


FM2000 Position & Fire Fitghting System
Fuel Supply piping From pumps room to daily Tanks
Pipe insulation

on
Not Start
on
on

Plenum Installation & flexible Pipes


Ducts installation ( GF Kitchen Area & BOH to Finish )
Fixing & Connection Mufflers
Iron Ducts (Tech Fl)
Air Handling Units Drainage &Signals Installation
Fan coil Final To Fix

on
on
on
on
on
Finished

Electrical

Caling (Power, Data, Alarms , AV...Etc ( Ballroom)


Finish Electrical Cabling above Ceiling

Not Start
on

Carpentry

Wood Subframe ( Restaurant )

Not Start

Aluminium
Work

Aluminium Curtain Wall

Civil Works
GF and MF

Fire/Chilled
Water

VAC

on

% Complete

Sheet 2

Project

Issue
11-10-2010
To
15-10-2010

Week Report Of Activities in The Program Of Works


Hotel-Ambassador- G&I 5* Hotel

1st Typical Floor


Trade
Corridor

Bedrooms
Bedroom
Entrance

Toilets

Tasks

Status

Void Closure Inspection


Completion of missing items after 1st Inspection
Dar Void Closure Inspection
False Ceilling Panels in Corridors

on
on
on
on

Second Fix Electrical


Final Fix smoke detector
Finish Tile in Rooms

on
on
on

Install Wardrobe-Techman
Install frame and architrave
DAR inspection
VOID inspection
First Coat paint

on
on
on
on

VOID inspection
DAR inspection
False Ceilling Panels
Install Architrave and Door - Techman

on
on
on
on

Note

2nd typical Floor


Trade

Corridor

Bedrooms
Bedroom
Entrance

Toilets

Tasks

Status

Void Closure Inspection


Completion of missing items after 1st Inspection
Dar Void Closure Inspection

on
on
on

Second Fix Electrical


Final Fix smoke detector
Finish Tile in Rooms

on
on
on

Install Wardrobe-Techman
Install frame and architrave
DAR inspection
VOID inspection
First Coat paint

on
on
on
on
on

VOID inspection
DAR inspection
Install Architrave and Door - Techman

on
on
on

3rd Typical Floor

Note

Sheet 3

Trade

Corridor

Bedrooms
Bedroom
Entrance

Toilets

Tasks

Status

Void Closure Inspection


Completion of missing items after 1st Inspection
Dar Void Closure Inspection

on
on
on

Second Fix Electrical


2nd Fix smoke detector
Finish Tile in Rooms

on
on
on

Install Wardrobe-Techman
Install frame and architrave
DAR inspection
VOID inspection
First Coat paint
BMS
VOID inspection
DAR inspection
Install Architrave and Door - Techman

Note

Not Start
Not Start
on
on
Not Start
on
on
on
on

4th Typical Floor


Trade

Corridor

Bedrooms
Bedroom
Entrance

Toilets

Tasks
Void Closure Inspection
Completion of missing items after 1st Inspection
Dar Void Closure Inspection
Wall adjustments
First Coat Paint
Finish Tile in Rooms

Status

Note

on
on
on
on
Not Start
Stop

Wall penetrations
DAR inspection
VOID inspection
BMS

on
on
on
on

Masonry- Walls problems solving


Plaster -Finishing EMP works
Tiling & Install marble treshold
False Ceiling Structure

on
on
on
Stop

5th typical Floor


Trade

Tasks

Status

Note

Sheet 4
Corridor

Bedrooms
Bedroom
Entrance

Toilets

Void Closure Inspection


Completion of missing items after 1st Inspection
Dar Void Closure Inspection
Wall adjustments
First Coat Paint
Finish Tile in Rooms

on
on
on
Not Start
Stop

Wall penetrations
DAR inspection
VOID inspection
BMS

Stop
on
on
on

Masonry- Walls problems solving


Plaster -Finishing EMP works
Tiling & Install marble treshold
False Ceiling Structure

on
on
on
Not Stsrt

Executive Floor
Trade

Corridor

Bedrooms
Bedroom
Entrance

Tasks

Status

Finishing small shaft


Cable Trays
Fire Pipe Lines

Not start
on
Stop

Wall adjustments
Tiling
Masonry- plaster

on
Not start
on

Tiles
Air Ducts
Fire branch Lines

Not start
Not start
Not start

Toilets

Masonry- Walls problems solving

on

Executive
Lounge

Masonry- Walls problems solving

0n

Note

Presidential Floor
Trade

Corridor

Tasks
Air Ducts
Cable Trays
Fire Pipe Lines
Plaster in Corridors

Status
Stop
on
Stop

Note

Sheet 5
Bedrooms
Entrance
Bedroom

Fire branch Lines


Chiller supply & return Pipe line
Air Ducts

Not start
Not start
Stop

Masonry - walls
Masonry- plaster

on
on

Toilets

Masonry- Walls problems solving

on

Presidential
Rooms

Masonry- Walls problems solving

on

Roof Floor
Trade

Civil Works

EMP

Tasks
Louvers installations
Alucobond
Main signage
Screeding
Water proofing
Wall penetrations
Office area mechanical room building
Concrete wall of stair cases opening
Air handling units ducts connection
Instruments installation
Iron ducts installation
Air handling signals installation
Pumps power supply
Pumps power supply
Vent pipes termination
Chillers test and start up
Offices air handling unit ducts connection
Stair case pressurization ducts connection
Pipe insulation
Air handling power supply
Roof power connection

Status

Note

Not start
Not start
Stop
Stop
on
Stop
Stop
Not start
Not start
Not start
on
on
on
Not start
Not start
Not start
on
on
on

External Works
Trade

Tasks

Status

All Activities

On
Progre
ss

Note