Documente Academic
Documente Profesional
Documente Cultură
Issue
11-10-2010
To
15-10-2010
Project
Tasks
Status
Shop Draiwings
Masonry & Problem solving (Wall Prenetration ... Etc)
POP ( Meeting Room ,Adm offices & Toilets GF)
Tiling on Floor ( GF & MF BOH)
False Ceiling Structure ( GF & MF BOH)
Tiling on To Finish
False ceiling Panel ( GF FOH )
Laundry Water proof,pads &Tile on Wall
ECG connection and electrical room ( Milestone)
Mechanical Rooms ( Milestone)
Voids Inpections
on
on
Not start
Not start
Not start
on
Stop
Stop
0n
on
on
on
Not Start
on
on
on
on
on
on
on
Finished
Electrical
Not Start
on
Carpentry
Not Start
Aluminium
Work
Civil Works
GF and MF
Fire/Chilled
Water
VAC
on
% Complete
Sheet 2
Project
Issue
11-10-2010
To
15-10-2010
Bedrooms
Bedroom
Entrance
Toilets
Tasks
Status
on
on
on
on
on
on
on
Install Wardrobe-Techman
Install frame and architrave
DAR inspection
VOID inspection
First Coat paint
on
on
on
on
VOID inspection
DAR inspection
False Ceilling Panels
Install Architrave and Door - Techman
on
on
on
on
Note
Corridor
Bedrooms
Bedroom
Entrance
Toilets
Tasks
Status
on
on
on
on
on
on
Install Wardrobe-Techman
Install frame and architrave
DAR inspection
VOID inspection
First Coat paint
on
on
on
on
on
VOID inspection
DAR inspection
Install Architrave and Door - Techman
on
on
on
Note
Sheet 3
Trade
Corridor
Bedrooms
Bedroom
Entrance
Toilets
Tasks
Status
on
on
on
on
on
on
Install Wardrobe-Techman
Install frame and architrave
DAR inspection
VOID inspection
First Coat paint
BMS
VOID inspection
DAR inspection
Install Architrave and Door - Techman
Note
Not Start
Not Start
on
on
Not Start
on
on
on
on
Corridor
Bedrooms
Bedroom
Entrance
Toilets
Tasks
Void Closure Inspection
Completion of missing items after 1st Inspection
Dar Void Closure Inspection
Wall adjustments
First Coat Paint
Finish Tile in Rooms
Status
Note
on
on
on
on
Not Start
Stop
Wall penetrations
DAR inspection
VOID inspection
BMS
on
on
on
on
on
on
on
Stop
Tasks
Status
Note
Sheet 4
Corridor
Bedrooms
Bedroom
Entrance
Toilets
on
on
on
Not Start
Stop
Wall penetrations
DAR inspection
VOID inspection
BMS
Stop
on
on
on
on
on
on
Not Stsrt
Executive Floor
Trade
Corridor
Bedrooms
Bedroom
Entrance
Tasks
Status
Not start
on
Stop
Wall adjustments
Tiling
Masonry- plaster
on
Not start
on
Tiles
Air Ducts
Fire branch Lines
Not start
Not start
Not start
Toilets
on
Executive
Lounge
0n
Note
Presidential Floor
Trade
Corridor
Tasks
Air Ducts
Cable Trays
Fire Pipe Lines
Plaster in Corridors
Status
Stop
on
Stop
Note
Sheet 5
Bedrooms
Entrance
Bedroom
Not start
Not start
Stop
Masonry - walls
Masonry- plaster
on
on
Toilets
on
Presidential
Rooms
on
Roof Floor
Trade
Civil Works
EMP
Tasks
Louvers installations
Alucobond
Main signage
Screeding
Water proofing
Wall penetrations
Office area mechanical room building
Concrete wall of stair cases opening
Air handling units ducts connection
Instruments installation
Iron ducts installation
Air handling signals installation
Pumps power supply
Pumps power supply
Vent pipes termination
Chillers test and start up
Offices air handling unit ducts connection
Stair case pressurization ducts connection
Pipe insulation
Air handling power supply
Roof power connection
Status
Note
Not start
Not start
Stop
Stop
on
Stop
Stop
Not start
Not start
Not start
on
on
on
Not start
Not start
Not start
on
on
on
External Works
Trade
Tasks
Status
All Activities
On
Progre
ss
Note