1-Dec-15
Activities Description
Main Sub Station to Grid Station Completed
Cooler Sub Station to Raw Mill Substation completed
Circular Beam concrete completed
Footing Concrete completed
Mechanical
b) Potential issues
Grid Station
Civil
Issue
Excavation of Switch Yard yet not started due to shortage/limited
earth moving machines
481-Clinker Storage Shaft (Clinker Tower)
Super structure design details above +327 still awaited from Loya
associates
461-Coal Mill Building
Hold due to Mechanical Works
CCR Building
Material
Mechanical
Consequences
Completion of Civil Works in Switch Yard will be
delayed
Unit
ton
ton
ton
liter
NYA
Locals
Expats
LCL
Total
Manpower
Contractor
41
Alghazi
9
INDEC
11
Cambridge
Al Farooq
TNI
SCS
EMI
FLS
LOYA
61
Manpower
52
37
236
23
174
310
154
4
4
994
e) Civil Activates
Area
Equipment
111-Limestone Crushing
Department
133-Additive Storage
112-Clay Crushing Department
500 - Cement
Grinding Area
800 - Electrical
Departments Area
Ancillary Building
Block
Concrete (cum) masonry/Finishing(S
qm)
Formwork
(sqm)
1.92
32
16
0.72
1.8
-
24.3
44.48
-
6
15
-
5.88
-
12
1.2
0.12
49
8.1
2.5
641/642-Packing Plant
Grid Station
Main Substation
Admin Building
Supervisor Accomodation
Total Quantities
2.28
0.192
116.572
5.88
321-Raw Mill
400 - Clinker
Production Area
600 - Cement
Storage and
Dispatch Area
Excavation
(cum)
10
1
102.73
0.4
199.73
19
1.6
-
40
31.6
f) Mechanical Activities
Area
Equipment
500 - Cement
Grinding Area
531.RM100
600 - Cement
Storage and
Dispatch Area
Total Quantities
Embedment
fabrication
(ton)
0
Embedment
Padding and Structure
installation (ton) leveling (ton) erection (ton)
0
0.408
0.408
3.82382
3.82382
Equipment erection
(ton)
0
g) Mining Activates
Total Overburdened Remove Today (cum)
Target Date
11,592
137,515
3,200,000
1-Jun-16