Documente Academic
Documente Profesional
Documente Cultură
• Structural Works
1. Fabricators – Fabricator’s for Structural Plate Cutting and Plate Edge Weld
Preparation.
- Fabricator’s for General Works.
2. Welder’s – Welder’s Pre-Qualified (6G Position) M.A.W. Welding Process – Full
Penetration One (1) Side.
- Welder’s for General Works.
• Mechanical
1. Mechanical – Mechanic’s for Detailed Assembly, Gantry Drives, Mechanical
Systems.
2. Mechanical – Mechanic’s for Basic works including Assembly of Ladders, Access
Ways, Wheel Guards,etc.
• Electrical
1. Electrical – Electrician’s Pre-Qualified for Final Termination Works.
2. Electrical – Electrician’s for Cable Tray Installation and Cable Pulling / Cable Tying.
• Riggers – Experienced Riggers for the Slinging & Lifting Arrangements of the Portal
Structure and Assist with the installation of the balance of the modules for the RTG
Crane
Cable Chain
Festoon System Trolley & Hoist
Assembly
Spreader
Resistor Platform
& Resistors
Gantry Assembly
Walkway
Bridge Girder
Tie Rod
Access Way
Exhaust
System
LEG
Diesel
Generator
E-Room
Diesel Generator
Sliding and
Folding Access
Platform
Sill Beam
• Picture 1 – Lay out Bridge Girder and
Leg Structures and Level – Align.
• A qualified Structural Surveyor with a
Level Instrument and Theodolyte is
required.
• Measure the Structures and confirm
Alignments and Measure the Leg
Structure to be Cut / Trimmed for the
connection to the Bridge Girder.
Picture 1
6
• After the Structural (Fabrication / Welding / Coating of the Welded Joints) the following items can
be completed.
• Picture 4 (next Slide) –
1. Cable Tray Installation
2. Cable Installation
3. Cable Tray Covers Installation
4. Generator Exhaust Pipe Installation
5. Walkway Grating Installed
6. Crane Signs Painted (These signs are painted where the Lifting Arrangement will not damage the
Signs. In these areas the signs will be completed using a Man Lift)
7. Portal (Bridge Girder) Flood Light Installation including cabling (Photo Below)
8. Final Paint Touch –Up where damage has occurred during installation works
Flood Light
Installation
Picture 4
Walkway Gratings
Exhaust Pipe
Crane Signs
Applied
Backing Strip
Equalizer /
Wheel Fork
Assembly Level Support Stands
Counter Weight Blocks
• Picture 6 (Next Slide) – The Upper Portal Assembly - weight includind Access
Ways, Cable Trays and Cables = 31Ton ( 1 Bridge Girder & 2 Legs ) is lifted into
position using the Following Lifting Arrangement (Note also the pre-installation of
the Tie Rods) –
1. 1 x Lifting Spreader Beam – 5T.
2. 2 x Lifting Beams - 0.75T ea x 2 = 1.5T.
3. 2 x Lifting Wire Rope Sling Arrangements ( Each Sling Arrangement Capacity 35T).
4. 1 x 150 T Crawler Crane.
5. 2 x 50T Hydraulic Mobile Crane (to Tail out the Legs during the initial Lift).
• After placing the Upper Structure and Sliding the Legs over the Backing Strip on
the Sill Beam the Structure Alignment must be confirmed by the qualified
Structural Surveyor with a Theodolyte.
• The Upper Portal must be re-strained by wire ropes to counterweight blocks –
tensioning with Chain Blocks. Fixed Points are mounted under the Bridge Girder.
• The Full Penetration Weld Joint Preparation must be Q.C. Inspected and approved.
• After all the above has been completed the Welding Process can be completed
with the N.D.T. 100% U.T. Inspection.
• After the welding process is completed, the Weld Joint and surrounding area must
be Painted with the Coating Specification As per ISO 8501-1 and by mechanical
power tool cleaning.
• Picture 7 (2nd Next Slide) – After the Two (2) Upper Portal Assembles are
installed the Rail Distance (Shown by the Red Arrow) must be confirmed and then
the Tie Rods between the two (2) Assemblies may be connected.
Picture 6
Lifting Frames
Lifting – Spreader
Beam
Tie
150T Rods
Crawler
Crane Cables From Upper Portal to
Counterweight Blocks
Welding
Process
Tie Rod
Rail Distance Connection
Picture 7
• Picture 8 – Picture 8
1. Generator Installation – weight 10T
2. Generator Access Platforms Installation
3. Sill Beam Cable Tray Installation
4. Electrical Junction Box Installation
5. Electrical Cable Installation and
Termination
• Picture 9 –
1. E-Room Installation – weight 8T
2. E-Room Access Platforms Installation
3. Sill Beam Cable Tray Installation
4. Electrical Junction Box Installation
5. Electrical Cable Installation and
Termination.
Picture 9
• Picture 10 – Picture 10
1. Install Resistor Bank Platform and
Resistors
2. Install Access Ways and Lighting
Systems
• Picture 11 –
1. Install Gantry Drive Assemblies
(Electric or Chain Drive)
2. Install Wheel Turning and Locking
Assemblies
3. Install Diesel Fule Tank Systems
4. Picture 12 (next page) shows Wheel
Assemblies which will be supplied by
NCSC – to be installed.
Picture 11
• Picture 12 - Wheel Assemblies which
will be supplied by NCSC
Picture 12
Picture 12 (a)
• Picture 13 – Cabin Assembly –
Supplied by NCSC.
Picture 13
Picture 14
• Picture 15 & 16 – Cable Track & Chain
Festoon System installed and
Electrical Termination works
completed.
Picture 16
• Picture 17 – Install Head Block
Assembly (supplied by NCSC) and
Reeve Main Hoist and Anti-Sway Rope
System.
Picture 17
Picture 18 Picture 19
Picture 20