Documente Academic
Documente Profesional
Documente Cultură
INTRODUCTION
Resolute Minings Mt Wright Operation is an underground
gold mine located approximately 12 km North of Ravenswood,
in North Queensland. The first portal cut was taken in June
2006 and at the time of the trial the decline had reached the
700 m RL, a vertical distance of approximately 640 m below
surface.
The orebody is predominately a Rhyolite and Marcasite
Pyrite and contains reactive ground. Operations currently
utilise two twin boom Tamrock Super-Drill Jumbos for
development advance. Capital (Waste) headings having a
nominal size of 7 m wide 6 m high, while ore headings are
designed at 5 m wide 5 m high.
Production blasting originally utilised the open stoping
method, but recently changed to the sublevel caving method
of extraction. Electronic initiation systems have been
successfully used in the production charging cycle and this
prompted Orica to approach Resolute management to conduct
the e-Dev trial in the development cycle at Mt Wright.
Typical industry overbreak rates in underground
development headings using traditional non-electric long
period delay initiation are around 12 per cent of blasted void.
Utilising electronic initiation (such as e-Dev) has seen this
rate decrease significantly, leading to:
SYSTEM OVERVIEW
The e-Dev electronic blasting system utilises an ASIC
(integrated circuit) chip inside each detonator coded with
a unique ID number, which is replicated using a barcode
on a flag tag at the end of the lead. A scanner reads this
ID and can assign delays in 1 ms increments from 0 up to
10 000 milliseconds. The scanner can then be downloaded via
a Bluetooth connection to the blast box, which is then used for
initiation of the blast.
Scanning is passive, meaning that at no stage during
scanning is the detonator powered up. System components
can be seen in Figure 1.
Training is conducted as follows:
1. Senior Blast Technician, Orica Mining Services, Unit B Royal Oak Plaza, 263 Charters Towers Road, Mysterton, Townsville Qld 4812. Email: john.wall@orica.com
2. MAusIMM, Technical Services Manager, Orica Mining Services, Level 1, 29 Southgate Avenue, Cannon Hill Qld 4170. Email: lucas.bottomley@orica.com
1 blast box,
1 scanner (capability to scan up to 500 detonators), and
detonators as required.
Experiences have shown that most operators quickly adjust
to the new skills required and apart from some understandable
initial teething issues, face loading and tie in times are not
adversely affected.
Equipment
During the trial, a number of different computer programs and
specific hardware were utilised to both capture and interpret
the required data.
2
Shotplus T
Methodology
VRMesh
FIG 5 - Survey rods placed into perimeter holes.
portion of the drilled hole at the toe that remains after firing.
There are a number of reasons that butts may remain in the
face, but the most common are either:
Measurement of advance
The advance obtained was monitored by inspection of the face
after firing for the incidence of butts. Butts are the remaining
4
TABLE 1
Measured cast distances.
Cut number
0 (control)
3.5 m
3.5 m
15.0 m
1 (control)
3.7 m
3.7 m
14.0 m
2 (control)
3.7 m
4.0 m
16.0 m
3.5 m
4.0 m
17.0 m
4 (e-Dev)
2.0 m
5.5 m
24.0 m
5 (e-Dev)
2.2 m
6.5 m
26.0 m
6 (e-Dev)
2.2 m
6.0 m
27.0 m
7 (e-Dev)
2.0 m
5.0 m
25.0 m
two shells were then truncated, removing points from the knee
holes down (to remove possible false data from poor bogging)
and also squaring off the front and rear of the shot to create a
2.5 m slice (to remove possible false data from dishing of the
face due to poor drilling).
These shells were then enclosed to give an accurate figure
of both volume and surface area for direct comparison. The
difference between these two figures gives us the overbreak
ratio. Any underbreak was calculated by doing a Boolean
union of the two truncated shells and comparing this result
against the as blasted shell. Figure 9 shows the two truncated
shells overlaid from the 775 Sth control shot.
Table 2 shows the three control and four available e-Dev
cuts taken from 775 S comparing volume, area and overbreak
per cent. Unfortunately, cut 4 was shotcreted before a
Callidus scan was performed so any data from the blasted
void after ground support was installed would be compromised
(cast measurements were taken). Data from 775 N and 840 R8
was still being collated at the time of writing this paper.
FIG 7 - Overlay of 775 Sth control cut 0 as drilled (in green) and as blasted
(in yellow) taken from Shotplus.
Analysis of solids
After the data from both survey and Callidus scan had been
collected for each blast, a 3D shell was created in VRMesh
using the as drilled data and also the Callidus data. These
FIG 9 - As drilled shell in green with as blasted overlaid (with 30 per cent
transparency). (Note height difference on top right, indicating overbreak)
RESULTS
A reduction of overbreak between development headings
fired with long period delay detonators and electronic delay
detonators was observed.
Control cuts 0 - 2 showed an average overbreak ratio of
10.10 per cent, while the e-Dev cuts four to seven showed an
average overbreak ratio of 5.44 per cent. Data obtained from
cut 3 which was the mirrored LP firing, was not equated into
the final percentages of either data set.
The difference between the non-electric (LP) and the
electronic (e-Dev) initiated headings, shows an average
reduction of overbreak of 46 per cent which directly relates
to savings in the cost of bogging and trucking. Assuming the
SG of the rock is at 3.6 kg/m3 and that over the three faces
6
CONCLUSIONS
Results obtained from the trial indicate that the flexibility
afforded by the electronic initiation of development headings
using e-Dev has many advantages over traditional nonelectric initiation, most importantly being:
TABLE 2
Volume calculations for as drilled and as blasted.
As drilled
Cut #
As blasted
Volume m
Area m
Volume m
Area m
Volume Increase
% Overbreak
0 (control)
49.21
84.24
53.06
90.53
3.85
7.82
1 (control)
64.32
95.68
70.25
103.31
5.93
9.22
2 (control)
77.31
108.85
87.55
119.74
10.24
13.26
52.24
87.47
56.68
93.86
4.44
8.51
4 (e-Dev)
N/A
N/A
N/A
N/A
N/A
N/A
5 (e-Dev)
42.60
78.84
45.63
84.65
3.03
7.12
6 (e-Dev)
56.51
93.94
59.40
97.30
2.88
5.10
7 (e-Dev)
54.04
88.72
56.26
93.48
2.21
4.10
FIG 10 - Cut 0 - 2 traditional non-Eeectric timing total firing time 9600 ms.
FIG 12 - Revised timing with e-Dev total firing time 2360 ms.
ACKNOWLEDGEMENTS
The author would like to acknowledge the efforts of Orica
North Queensland Operations team, specifically Mick
Richards and also Orica Rapid Response team member Ryan
Jackson, without whose help the trial would not have run so
smoothly.
Also thanks go to the technical team at Orica, Kurri-Kurri, for
their support with both data analysis and technical assistance
with the Callidus Laser Scanner. Finally, the author thanks the
management team at Resolutes Mt Wright Operations for the
support shown during the trial.