Sunteți pe pagina 1din 42

SEMINAR

Introduction to Continuous Flight


Auger (CFA) piling
Thursday 21/8/2013
Facilitator: Martin Larisch

Introduction to Continuous
Flight Auger (CFA) piling

Brief History of Piling Contractors, its capabilities and market

Introduction to CFA piling

History

Piling Contractors (Qld) Pty Ltd

1995

Started as a one rig operation in Queensland in 1983

We expanded into NSW in 1999 and WA in 2006

Now work nationally


Acquired by Keller Group plc in 2006

The Keller Group

GLOBAL SCALE LOCAL FOCUS


4

The Keller Group

Safety Improvements
60.0

50.0

40.0

Incidence rate (L.T.I. Per


100 employees)
Frequency rate (L.T.I. Per 1
million Man Hours)
Severity rate (Avg. Work
days Lost Per Occurrences)

30.0

20.0

10.0

0.0
2007

2008

2009

2010

2011

2012

2013

Safety Improvements

Key Techniques

Large diameter bored piles up to 3m diameter 76m deep

Driven pre-stressed piles 550mm octagonal up to 32m single length

Continuous flight auger piles up to 1.2m diameter 32m deep

Mine Fill in joint venture with Keller Ground Engineering

Contiguous and Secant Pile Retaining Walls

Key Techniques

Diaphragm and Slurry Walls

Marine piling using leaders off falsework or barges

Driven steel tubes, sheets and steel sections and ductile piles

Large diameter shafts up to 6m diameter 76m deep

Technical Capability

Technical Activities, Representative Memberships and Industry Engagement


We take a lead role in the technical activities of the Piling and Foundation
Specialists Federation (PFSF) and the Concrete Institute of Australia (CIA).
Many of our engineering staff are Members of the major national and
international professional institutions.

We have a Graduate Training programme approved by Engineers Australia


to train new graduates and technicians in our speciality, building the future
engineers and managers of our industry.
R&D / Technical Papers
Our staff publish and present technical papers at local, regional and
international seminars and conferences and we maintain a strong
commitment to research and development.
10

National Coverage

11

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger (CFA) piles

12

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger (CFA) piles

13

Introduction to Continuous
Flight Auger (CFA) piling

Pile types and pile systems (AS2159-2009)


Displacement piles
Driven piles
Screw auger piles

Non-displacement systems
Conventional bored piles
CFA piles
Barrettes
Hard rock drilling
14

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger (CFA) piles


(process after Brueckner Grundbau)

15

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger (CFA) piles


(process after Brueckner Grundbau)

16

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger (CFA) piles


(Schematic of the CFA auger after Slatter, 2000)

17

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger (CFA) piles


(Forces acting on the auger during augering after Viggiani, 1993)

Q = Pull down force applied by piling rig


M = Torque applied by piling rig
P = Soil resistance at auger tip
N = Auger weight
z = auger length / drill depth
= Friction between surrounding soil and soil in auger
l = auger pitch
d = Outer auger diameter
d0 = Auger stem diameter
18

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Introduction)


CFA piles were developed in the 1940s in the USA, introduction in Europe during
early 1970s with the invention of the first hydraulic piling rigs
The system has been available in Australia since the 1980s
Possible diameters for CFA piles:
450mm 1200mm
Standard diameters in Australia are 450, 600, 750, 900 and 1200mm
Depth up to 35m and more possible
Common depth up to 20m with standard equipment
Common diameters 450, 600, 750 and 900mm

19

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Applications)


CFA piles are commonly used as foundation piles for:
Buildings and bridges
Pile rafts
CFA piles are used for retaining structures as:
Soldier piles
Contiguous piles
Secant piles
Pile loads are usually smaller than for conventional bored piles but generally
bigger than for auger displacement piles

20

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Applications)

Soldier pile wall

Contiguous pile wall

Secant pile wall

21

Introduction to Continuous
Flight Auger (CFA) piling

Retaining structures (e.g. secant pile wall)

22

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Applications)


CFA piles are suitable for:
Generally for all types of structures with low to medium vertical loads
Penetration and removal of underground obstructions
Piles with single length reinforcement cages up to 18m
CFA piles should be considered carefully for:
Soft soil conditions or contaminated ground
High strength rock
Piles next to existing buildings
Strata which require penetration of stiff layers
Raked piles
23

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles


(Advantages & Disadvantages)
Advantages:
Very cost effective piling system with high production rates
Installation in stiff soils / weak rock possible
Suitable for changing and non-homogenous ground conditions

Disadvantages:
Cage installation after pouring process might be difficult
Limited capacity for bending moments, lateral forces and tension forces
Might cause uncontrolled over excavation if penetration rate is not constant
24

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles


(Suitable ground conditions)
CFA piles are suitable for:
Medium to very dense sands / gravels
Stiff to hard clays
Generally all types of weak or weathered rock (exception see below)
Installation below the ground water table
CFA piles are NOT suitable for:
High strength, unfractured rock
Soft soil conditions
Changing strata
25

Introduction to Continuous
Flight Auger (CFA) piling

Load transfer through CFA piles


Loads will be transferred through skin friction and / or base resistance

26

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Risks)


Stationary augers used to transport loose granular material and water

27

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Risks)


CFA augers are soil conveyors!
Signs of severe side loading can include:
Surface coning/depressions
Difficulty extracting augers
Unexpectedly high torque demand on machine

28

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Risks)


Risk of over-excavation in loose sand layers

29

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Risks)


Piles drilled too close can result in concrete blow through

Concrete

Sand
layer

30

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Risks B63)


Second pass as per B63 Clause 6.2.3:
To ensure the base of the pile socket is clean, adopt a multi-pass technique
using a minimum of two passes. After commencement of discharge of
concrete withdraw the auger 500 mm and drill back down to the toe of the pile
to pick up any contaminated concrete before re-commencing concreting of the
pile. Verify the use of the multi-pass technique from the pile monitoring
records."

31

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Quality control)


Operator controls operations via computer data

32

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Quality control)


Computer monitoring systems are common for some systems to monitor:
Depth, penetration rate & extraction rate
Torque
Pull down forces
Rotation
Concrete Volume

33

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles


Continuous Flight Auger piles
(Quality control)
Pile record sheet

34

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Risks B63)


Breakout (Clause 6.2.2)
No breakouts are to be performed RMS needs to ask for documentation of
contractors at tender time to ensure contractors provide suitable equipment
Concrete life (Clause 6.2.3)
Concrete life should be extended to 4 hours. With current concrete technology
this can be achieved easily. 45 minutes is not realistic in some remote
locations or inner city projects
Concrete oversupply should be at least 5% (not 8%) but could be as much as
40% (function of soil conditions)

35

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Risks B63)


Concrete pressure (Clause 6.2.3)
Concrete pressure can be zero as sensor is located at the top of the mast. If
the stem is filled with concrete the pressure sensor shows zero but concrete is
still delivered to the pile via gravitational forces
Different rig monitoring systems monitor data in different ways, it is important
to understand the particular monitoring system when analysing the installation
records
Monitoring (Clause 6.3 (f))
Monitoring mm/rev is unusual, better monitor rev/m or rev/min

36

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Quality control)


Concrete quality is crucial (workability, strength, pump-ability, bleeding)

37

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Quality control)


Computer monitoring systems:
PDA & CAPWAP

Pile-top Force Comparison

Load-settlement response
38

Introduction to Continuous
Flight Auger (CFA) piling

Non displacement piles - Continuous Flight Auger piles (Quality control)


Low strain integrity tests (PIT)

39

Introduction to Continuous
Flight Auger (CFA) piling

What else:
Importance of safe working platforms (typically 400 kPa platform requirement)
Get early involvement of a piling specialist
Compare what you get for your money
Rigs and technologies are readily available, look for specialists knowledge
Keep in mind rigs are very heavy high tech machines when you specify tolerances
outside the Australian Standards or code of practice
Any further questions?

40

Introduction to Continuous
Flight Auger (CFA) piling

Feedback & Discussion:

Did the presentation meet your expectations?


What do take home?
Any further questions?

41

Thanks for your active


participation and attention
SEMINAR
Introduction to Continuous Flight
Auger (CFA) piling
Thursday 21/8/2014
Facilitators: Martin Larisch

42

S-ar putea să vă placă și