CE420 Group Project Part 2

Nov 17, 2015

Hill, Brandon
Dickman, William
Alghaith, Ahmad

Table 1 lists all activities, their durations, predecessors, early and late start and finish, as well as the total
and free float of each activity. Note that the bolded tasks are actually groups for proceeding activities.
Table 1. Project Activities.
ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27

Task Name

Duration

Planning
Beginning of Project
Design
Start of Design

Predecessors

Early Start

Early Finish

Late Start

Late Finish

0 days

Fri 1/1/16

Fri 1/1/16

Fri 1/1/16

Fri 1/1/16

0 days

Fri 1/1/16

Fri 1/1/16

Fri 1/1/16

Fri 1/1/16

43 days

Fri 1/1/16

Tue 3/1/16

Fri 1/1/16

Wed 3/2/16
Fri 1/1/16

0 days

Fri 1/1/16

Fri 1/1/16

Fri 1/1/16

4 days

Fri 1/1/16

Wed 1/6/16

Wed 1/6/16

14 days

Fri 1/1/16

Wed 1/20/16

Fri 1/1/16

2 days

Thu 1/7/16

Fri 1/8/16

Tue 1/12/16

Preliminary Site Survey

2 days

Mon 1/11/16

Tue 1/12/16

Fri 1/15/16

Test Site Soils

3 days

Mon 1/11/16

Wed 1/13/16

Thu 1/14/16

2 days

Fri 1/1/16

Mon 1/4/16

Tue 1/19/16

2 days

8,9

Thu 1/14/16

Fri 1/15/16

Tue 1/19/16

3 days

6,10,11

Thu 1/21/16

Mon 1/25/16

Thu 1/21/16

7 days

11

Mon 1/18/16

Tue 1/26/16

Tue 1/26/16

20 days

12,13SS

Tue 1/26/16

Mon 2/22/16

Tue 1/26/16

5 days

14

Tue 2/23/16

Mon 2/29/16

Tue 2/23/16

Landscape Design

5 days

12

Tue 1/26/16

Mon 2/1/16

Tue 2/23/16

Meeting for Design


Approval

1 day

15,16

Tue 3/1/16

Tue 3/1/16

Tue 3/1/16

Tue 3/1/16

End of Design

0 days

17

Tue 3/1/16

Tue 3/1/16

Wed 3/2/16

Wed 3/2/16

Pre-Construction

14 days

Tue 3/1/16

Mon 3/21/16

Wed 3/2/16

Mon
3/21/16

Develop Base Map /


Right-of-Way Plans
Traffic Study
Determine Initial
Bridge Placement

Community Input
Meeting
Environmental Impact
Assessment
Determine Final Bridge
Placement
Bridge Material
Investigation
Design Bridge Structure
and Foundation
Sign, Illumination, and
Signalization Design

Advertisement of Bid
Documents
Make Copies of Plans
and Specs.
Distribute Plans and
Specs.

Mon
1/11/16
Wed
1/20/16
Wed
1/13/16
Mon
1/18/16
Mon
1/18/16
Wed
1/20/16
Wed
1/20/16
Mon
1/25/16
Wed 2/3/16
Mon
2/22/16
Mon
2/29/16
Mon
2/29/16

0 days

18

Tue 3/1/16

Tue 3/1/16

Wed 3/2/16

Wed 3/2/16

1 day

20

Wed 3/2/16

Wed 3/2/16

Wed 3/2/16

Wed 3/2/16

1 day

21

Thu 3/3/16

Thu 3/3/16

Thu 3/3/16

Thu 3/3/16

Receive Bids

10 days

22

Fri 3/4/16

Thu 3/17/16

Fri 3/4/16

Thu 3/17/16

Receipt of Bids

0 days

23

Thu 3/17/16

Thu 3/17/16

Fri 3/18/16

Fri 3/18/16

Bid Opening

1 day

24

Fri 3/18/16

Fri 3/18/16

Fri 3/18/16

Fri 3/18/16

Pre-Construction
Meeting

1 day

25

Mon 3/21/16

Mon 3/21/16

Mon 3/21/16

Mon
3/21/16

Construction

104 days

Mon 3/21/16

Fri 8/12/16

Tue 3/22/16

Fri 8/12/16

Total
Slack
0
days
0
days
0
days
0
days
3
days
0
days
3
days
4
days
3
days
12
days
3
days
0
days
6
days
0
days
0
days
20
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days

Free
Slack
0
days
0
days
0
days
0
days
0
days
0
days
0
days
1 day
0
days
12
days
0
days
0
days
6
days
0
days
0
days
20
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days

CE420 Group Project Part 2

28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51

Start of Construction

Nov 17, 2015

Hill, Brandon
Dickman, William
Alghaith, Ahmad

0 days

26

Mon 3/21/16

Mon 3/21/16

Tue 3/22/16

Tue 3/22/16

14 days

28

Tue 3/22/16

Fri 4/8/16

Wed 4/20/16

Mon 5/9/16

2 days

28

Tue 3/22/16

Wed 3/23/16

Tue 3/22/16

Wed
3/23/16

3 days

30,29

Mon 4/11/16

Wed 4/13/16

Tue 5/10/16

Thu 5/12/16

3 days

31SS

Mon 4/11/16

Wed 4/13/16

Tue 5/17/16

Thu 5/19/16

1 day

29SS

Tue 3/22/16

Tue 3/22/16

Thu 5/19/16

Thu 5/19/16

2 days

30

Thu 3/24/16

Fri 3/25/16

Thu 3/24/16

Fri 3/25/16

5 days

31,32,33

Thu 4/14/16

Wed 4/20/16

Fri 5/20/16

Thu 5/26/16

Excavate for Abutment

10 days

35

Thu 4/21/16

Wed 5/4/16

Fri 5/27/16

Thu 6/9/16

Install Cofferdams

4 days

34

Mon 3/28/16

Thu 3/31/16

Mon 3/28/16

Thu 3/31/16

Erect Footings

30 days

37

Fri 4/1/16

Thu 5/12/16

Fri 4/1/16

Thu 5/12/16

Erect Piers

30 days

31,38

Fri 5/13/16

Thu 6/23/16

Fri 5/13/16

Thu 6/23/16

Erect Abutment

10 days

36,34

Thu 5/5/16

Wed 5/18/16

Fri 6/10/16

Thu 6/23/16

Grade to Abutment

4 days

40

Thu 5/19/16

Tue 5/24/16

Tue 6/28/16

Fri 7/1/16

Install Precast Girders

6 days

40,39

Fri 6/24/16

Fri 7/1/16

Fri 6/24/16

Fri 7/1/16

Install Decking

15 days

42,41

Mon 7/4/16

Fri 7/22/16

Mon 7/4/16

Fri 7/22/16

Pave Roadway

8 days

43

Mon 7/25/16

Wed 8/3/16

Mon 7/25/16

Wed 8/3/16

Install Precast Parapets

5 days

44

Thu 8/4/16

Wed 8/10/16

Thu 8/4/16

Signage, Signals, Paint,


Illumination

4 days

43

Mon 7/25/16

Thu 7/28/16

Fri 8/5/16

Landscape

3 days

43

Mon 7/25/16

Wed 7/27/16

Mon 8/8/16

As-Built Survey

2 days

43

Mon 7/25/16

Tue 7/26/16

Tue 8/9/16

Construction Complete

0 days

48,47,46,45

Wed 8/10/16

Wed 8/10/16

Thu 8/11/16

Thu 8/11/16

2 days

49

Thu 8/11/16

Fri 8/12/16

Thu 8/11/16

Fri 8/12/16

0 days

50

Fri 8/12/16

Fri 8/12/16

Fri 8/12/16

Fri 8/12/16

Obtain Construction
Permits
Mobilize
Survey Site for
Placements
Stake Contruction Site
Designate Workzone
With Traffic Control
Stock Materials
Demolition of
Obstructions

Inspect Bridge for


Standards
Open Bridge to Traffic

Wed
8/10/16
Wed
8/10/16
Wed
8/10/16
Wed
8/10/16

0
days
21
days
0
days
21
days
26
days
42
days
0
days
26
days
26
days
0
days
0
days
0
days
26
days
28
days
0
days
0
days
0
days
0
days
9
days
10
days
11
days
0
days
0
days
0
days

0
days
0
days
0
days
0
days
0
days
16
days
0
days
0
days
0
days
0
days
0
days
0
days
0
days
28
days
0
days
0
days
0
days
0
days
9
days
10
days
11
days
0
days
0
days
0
days

CE420 Group Project Part 2

Nov 17, 2015

Hill, Brandon
Dickman, William
Alghaith, Ahmad
Table 2, which is shown below lists all critical activities, as well as the early start and finish for each.
These are activities that do not have any float. In this table are also the milestones, which are shown in bold.
The final milestone, Open Bridge to Traffic, represents the end of the project.
Table 2. Critical Activities and Milestones.
Critical Activities / Milestones

Early Start

Early Finish

Beginning of Project

Fri 1/1/16

Fri 1/1/16

Start of Design

Fri 1/1/16

Fri 1/1/16

Traffic Study

Fri 1/1/16

Wed 1/20/16

Determine Final Bridge Placement

Thu 1/21/16

Mon 1/25/16

Design Bridge Structure and Foundation

Tue 1/26/16

Mon 2/22/16

Sign, Illumination, and Signalization Design

Tue 2/23/16

Mon 2/29/16

Meeting for Design Approval

Tue 3/1/16

Tue 3/1/16

End of Design

Tue 3/1/16

Tue 3/1/16

Advertisement of Bid Documents

Tue 3/1/16

Tue 3/1/16

Make Copies of Plans and Specs.

Wed 3/2/16

Wed 3/2/16

Distribute Plans and Specs.

Thu 3/3/16

Thu 3/3/16

Receive Bids

Fri 3/4/16

Thu 3/17/16

Receipt of Bids

Thu 3/17/16

Thu 3/17/16

Bid Opening

Fri 3/18/16

Fri 3/18/16

Pre-Construction Meeting

Mon 3/21/16

Mon 3/21/16

Start of Construction

Mon 3/21/16

Mon 3/21/16

Mobilize

Tue 3/22/16

Wed 3/23/16

Stock Materials

Thu 3/24/16

Fri 3/25/16

Install Cofferdams

Mon 3/28/16

Thu 3/31/16

Erect Footings

Fri 4/1/16

Thu 5/12/16

Erect Piers

Fri 5/13/16

Thu 6/23/16

Install Precast Girders

Fri 6/24/16

Fri 7/1/16

Install Decking

Mon 7/4/16

Fri 7/22/16

Pave Roadway

Mon 7/25/16

Wed 8/3/16

Install Precast Parapets

Thu 8/4/16

Wed 8/10/16

Construction Complete

Wed 8/10/16

Wed 8/10/16

Inspect Bridge for Standards

Thu 8/11/16

Fri 8/12/16

Open Bridge to Traffic

Fri 8/12/16

Fri 8/12/16

The network Diagram, which is shown on the next three pages shows all activities by ID number, as
well as the relationships between them. Following the network diagram is the as-planned bar chart which shows
the activities, their connections, and dates.