Documente Academic
Documente Profesional
Documente Cultură
no responsibility for the contents of this announcement, make no representation as to its accuracy
or completeness and expressly disclaim any liability whatsoever for any loss howsoever arising from
or in reliance upon the whole or any part of the contents of this announcement.
(Incorporated under the laws of the Cayman Islands with limited liability)
(Stock Code: 3668)
(1,072)
1,420
(8,808)
(1,144)
(1,436)
6,367
(15,139)
4,593
1,160
(6,093)
(121)
(7,966)
(4,564)
(6,214)
(12,530)
(0.0005)
(0.0007)
Loss per share for the period attributable to the equity holders
of the Company (expressed in US$ per share)
-1-
The Board does not recommend the payment of an interim dividend for the six-month period
ended 30 June 2014.
Assets, Liabilities and Equity
30 June
2014
US$000
(Unaudited)
31 December
2013
US$000
(Audited)
Non-current assets
Current assets
4,239,547
414,060
4,045,070
246,354
Non-current liabilities
Current liabilities
2,764,419
1,172,983
2,784,199
784,806
716,205
722,419
Total equity
RESULTS
The board of directors (the Board) of Chinalco Mining Corporation International (the Company)
is pleased to announce the unaudited interim condensed consolidated financial statements of the
Company and its subsidiaries (collectively, the Group) for the six-month period ended 30 June
2014, together with the comparative figures as follows:
-2-
Note
Revenue
11
(1,072)
1,420
(8,808)
(15,139)
Operating loss
(9,880)
(13,719)
Finance income
Finance expenses
571
(1,715)
5,827
(1,234)
(1,144)
4,593
(1,436)
Operating costs
General and administrative expenses
12
(12,460)
6,367
(9,126)
1,160
(6,093)
(7,966)
(121)
(4,564)
(121)
(4,564)
(6,214)
(12,530)
(0.0005)
(0.0007)
13
14
Dividends
Interim dividend declared
-3-
Note
ASSETS
Non-current assets
Property, plant and equipment
Intangible assets
Investment in a joint venture
Deferred tax assets
Value-added tax recoverable
Prepayments and other receivables
Restricted cash
5
7
Current assets
Inventories
Trade receivables
Prepayments and other receivables
Value-added tax recoverable
Cash and cash equivalents
6
7
5
Total assets
EQUITY AND LIABILITIES
Equity attributable to the Companys equity holders
Share capital
Share premium
Reserve
Accumulated deficits
Total equity
-4-
8
8
30 June
2014
US$000
31 December
2013
US$000
4,028,898
636
2,165
34,147
161,097
3,047
9,557
3,814,043
1,255
3,598
27,742
183,945
3,047
11,440
4,239,547
4,045,070
103,372
48,029
93,233
55,644
113,782
62,610
37,578
23,250
122,916
414,060
246,354
4,653,607
4,291,424
472,711
327,267
11,989
(95,762)
472,711
327,267
12,110
(89,669)
716,205
722,419
30 June
2014
US$000
31 December
2013
US$000
2,687,902
72,395
4,122
2,689,808
90,200
4,191
2,764,419
2,784,199
813,215
315,654
41,688
2,426
381,000
361,317
40,063
2,426
1,172,983
784,806
Total liabilities
3,937,402
3,569,005
4,653,607
4,291,424
Note
LIABILITIES
Non-current liabilities
Loans and borrowings
Provision for remediation and restoration
Deferred income
Current liabilities
Loans and borrowings
Trade payables
Accruals and other payables
Amount due to immediate holding company
9
10
(758,923)
3,480,624
-5-
(538,452)
3,506,618
Currency
translation Accumulated
differences
deficits
US$000
US$000
Share
capital
US$000
Share
premium
US$000
Capital
reserves
US$000
472,711
327,267
16,521
(4,411)
(89,669)
722,419
Total
US$000
Comprehensive loss
Loss for the period
Other comprehensive loss
Currency translation
differences
(6,093)
(6,093)
(121)
(121)
(121)
(6,093)
(6,214)
472,711
327,267
16,521
(4,532)
(95,762)
716,205
400,047
16,521
(58,605)
357,963
Comprehensive loss
Loss for the period
Other comprehensive loss
Currency translation
differences
(7,966)
(7,966)
(4,564)
(4,564)
(4,564)
(7,966)
(12,530)
72,664
329,048
401,712
472,711
329,048
16,521
(4,564)
(66,571)
747,145
-6-
(12,460)
(9,126)
262
39
1,144
1,436
375
15
(4,593)
(40,762)
(48,029)
(1,994)
2,325
(69)
(825)
(9,728)
(17,934)
2,662
(71)
(1,989)
(98,933)
(40,389)
(342,358)
(90)
(41,866)
44,686
382
1,883
(678,814)
(98)
(32,050)
(385)
101,498
372
(102,724)
2,541
(337,363)
(709,660)
508,000
(81,000)
432,000
(100,000)
402,745
(964)
427,000
733,781
162
(9,296)
122,916
(987)
(16,268)
142,656
113,782
125,401
-7-
General Information
Chinalco Mining Corporation International (the Company) was incorporated in the Cayman Islands
on 24 April 2003 as an exempted company with limited liability under the Companies Law of the
Cayman Islands. Its name was Peru Copper Syndicate, Ltd. on incorporation and changed to Chinalco
Mining Corporation International on 30 September 2011. The Companys registered office is PO Box
309 Ugland House, Grand Cayman, KY 1-1104, Cayman Islands.
The Companys shares were listed on the Main Board of The Stock Exchange of Hong Kong Limited
on 31 January 2013.
The Company is a subsidiary of Aluminum Corporation of China Overseas Holdings Limited (Chinalco
Overseas), a company incorporated in Hong Kong with limited liability. As at the date of these
financial statements were approved, the directors of the Company regard Aluminum Corporation of
China (Chinalco), a state-owned enterprise incorporated in the Peoples Republic of China (the PRC)
and administered by the State-owned Assets Supervision and Administration Commission (SASAC)
of the State Council (the State Council) of the PRC, as its ultimate holding company.
The Company and its subsidiaries (together, the Group) are principally engaged in exploration,
development and production of ore resources and other mining related activities.
In May 2003, the Companys subsidiary, Minera Chinalco Peru S.A. (MCP), was awarded by the
Peruvian government a right to develop and extract ore resource in the district of Morococha, Yauli
Province, the Republic of Peru (Peru) through a public bidding (the Toromocho Mining Project). In
June 2003, the Company signed an assignment agreement pursuant to which the Company was entitled
to exercise a purchase option of the mining concessions during a period which could be extended
to June 2008. In May 2008, the Company exercised its right and signed with Activos Mineros (an
entity incorporated by the Peruvian government), in the name of Peruvian Government, the Mining
Concessions Transference Agreement of the Toromocho Mining Project (the Assignment Agreement).
Under the Assignment Agreement, Activos Mineros transferred to the Company the title of certain
mining concessions, their surface property, buildings and water usage right pertaining to the Toromocho
Mining Project.
From August 2012 to February 2013, the Company entered into five binding off-take agreements with
four cornerstone investors and one independent third party, pursuant to which the Company agreed to
sell an aggregate of 70% of the annual production of copper concentrates from the Toromocho Mining
Project for a period of five years starting from the first official production of the Toromocho Mining
Project at a price determined by reference to certain benchmark market rates adjusted based on the
grade of the copper concentrates, two of which will automatically continue for another five years (the
Off-take Agreements).
As at the date of these financial statements were approved, the Groups operations are substantially
limited to construction and start-up activities of the Toromocho Mining Project. The Toromocho Mining
Project started commissioning in December 2013 and has not commenced commercial production.
The interim condensed consolidated financial statements are presented in US dollar (US$), unless
otherwise stated.
The interim condensed consolidated financial statements have not been audited.
-8-
2.
Basis of Preparation
The unaudited interim condensed consolidated financial statements for the six months ended 30 June
2014 have been prepared in accordance with International Accounting Standard (IAS) 34 Interim
Financial Reporting. The interim condensed consolidated financial statements do not include all
the information and disclosures required in the annual financial statements and should be read in
conjunction with the annual financial statements of the Group for the year ended 31 December 2013,
which have been prepared in accordance with International Financial Reporting Standards (IFRS)
issued by the International Accounting Standard Board.
Going concern
As at 30 June 2014, the Group had net current liabilities of approximately US$759 million (31
December 2013: US$538 million) and accumulated deficits of approximately US$96 million (31
December 2013: US$90 million). The board of directors of the Company (the Board) has considered,
among others, the internally generated funds and financial resources available to the Group as follows:
On 17 June 2013, the Company announced that the Board had approved the expansion plan in
order to optimize and increase the capacity of the Toromocho Mining Project (the Expansion
Plan) with estimated total capital expenditure of US$1.32 billion, 80% of which would be
financed by bank loans and 20% by internal funding. The Expansion Plan was approved by
National Development and Reform Commission of China (NDRC) in December 2013. In
connection with the Expansion Plan, the following financial resources are available to the Group,
including (i) in July and August 2014, the Company obtained banking facility commitments of
US$100 million, US$100 million and US$115 million from Standard Chartered Bank (Hong
Kong) Limited (SCB), Banco Bilbao Vizcaya Argentaria, S.A., Hong Kong (BBVA)
and Hong Kong and Shanghai Banking Corporation Limited (HSBC), respectively, for the
Expansion Plan and general corporate purpose, for which the formal facility agreements have
not been signed yet; (ii) in October 2013, China Development Bank (CDB) issued a letter to
NDRC indicating its principle approval to provide long-term loans with an amount of US$1,056
million for the Expansion Plan. Accordingly, the Company submitted a formal loan application
of US$1,056 million to CDB in February 2014, which is currently under CDBs final review and
approval; (iii) in January 2014, the Company submitted a formal loan application of US$1,056
million to Export-import Bank of China (Eximbank), which is currently under Eximbanks final
review and approval. Except the facilities committed by SCB, BBVA and HSBC, the remaining
bank financing resources for the Expansion Plan will be provided by CDB and Eximbank as
mentioned above.
In April 2014, Chinalco Overseas provided a loan facility of US$200 million for general
corporate purposes including but not limited to funding the working capital for the Toromocho
Mining Project. As at 30 June 2014, except for loans amounting to US$190 million drawn down
during current period, the remaining facility provided by Chinalco Overseas was US$10 million.
-9-
The Companys immediate holding company, Chinalco Overseas, has agreed not to demand
repayment of the loan due from the Group amounting to approximately US$343 million as at 30
June 2014 (31 December 2013: US$152 million) until the Group is financially capable to do so.
The Companys ultimate holding company, Chinalco also agreed that it will provide continuing
financial support to finance the future operations of the Group for a period of not less than 12
months from the date these financial statements were approved.
Based on the above, the directors of the Company believe that the Group will have adequate resources
to continue in operations for a period that is not less than 12 months from 30 June 2014. The Group
therefore continues to adopt the going concern basis in preparing these financial statements.
3.
IFRIC 21 Levies
This interpretation is applicable to all levies imposed by governments under legislation, other than
outflows that are within the scope of other standards (e.g., IAS 12 Income Taxes) and fines or other
penalties for breaches of legislation. It clarifies that an entity recognises a liability for a levy no earlier
than when the activity that triggers payment, as identified by the relevant legislation, occurs. It also
clarifies that a levy liability is accrued progressively only if the activity that triggers payment occurs
over a period of time, in accordance with the relevant legislation. For a levy that is triggered upon
reaching a minimum threshold, no liability is recognized before the specified minimum threshold is
reached. The adoption of IFRIC 21 did not have any impact on the interim condensed consolidated
financial statements of the Group as at 30 June 2014.
Improvements to IFRSs
Apart from the above, the IASB has also issued improvements to IFRSs which set out amendments to
a number of IFRSs primarily with a view to remove inconsistencies and clarify wording. The adoption
of these amendments upon their effective dates did not have any material impact on the accounting
policies, financial position or performance of the Group.
4.
3,843,943
(29,900)
2,593,709
(15,541)
3,814,043
2,578,168
3,814,043
228,062
(39)
(13,168)
2,578,168
519,517
(336)
(15)
(6,168)
4,028,898
3,091,166
At 30 June
Cost
Accumulated depreciation
4,071,902
(43,004)
3,112,875
(21,709)
4,028,898
3,091,166
- 11 -
Included in the movement of property, plant and equipment of the Group for the six months ended 30
June 2014 was a downward revision to the estimated remediation and restoration obligations in relation
to the property, plant and equipment amounting to US$19,437,000 (2013: US$12,875,000).
During the six months ended 30 June 2014, the Group capitalised financing costs amounting to
US$41,866,000 (2013: US$32,050,000) included in the additions of property, plant and equipment of
the Group.
As at 30 June 2014, bank borrowings from Eximbank amounting to US$2,400,680,000 (31 December
2013: US$2,399,204,000) (Note 9(b)) were guaranteed by Chinalco and according to the borrowing
agreements, in case that the credibility or financial status of Chinalco deteriorates or has the potential
to deteriorate, all property, plant and equipment pertaining to the Toromocho Mining Project will be
pledged as additional security for these borrowings.
5.
VAT recoverable:
to be recovered after more than 12 months
to be recovered within 12 months
- 12 -
30 June
2014
US$000
31 December
2013
US$000
161,097
55,644
183,945
23,250
216,741
207,195
6.
Trade Receivables
The Groups trading terms with its customers are mainly on credit. The credit period is generally one
month, extending up to two months for major customers.
As at 30 June 2014, all the trade receivables were aged within 6 months and non-interest bearing (31
December 2013: Nil).
7.
Other receivables:
Loan to a joint venture (Note (a))
Loan to a transportation services provider (Note (b))
Amount due from contractors for purchase of fuel
Employee advances
Amounts due from related parties
Others
Prepayments:
Prepayment to constructors
Prepaid income tax
Prepayment for construction insurance of
Toromocho Mining Project
Others
30 June
2014
US$000
31 December
2013
US$000
10,029
3,047
6,024
980
145
389
8,100
3,047
13,600
547
144
804
20,614
26,242
53,416
5,446
3,237
2,295
14,509
2,050
9,096
75,666
14,383
96,280
(3,047)
40,625
(3,047)
93,233
37,578
Notes:
(a) Loan to a joint venture amounting to US$10,029,000 (31 December 2013: US$8,100,000) is
unsecured and bears interest at LIBOR plus 5% per annum.
(b) As at 30 June 2014, the loan amounting to US$3,047,000 (31 December 2013: US$3,047,000)
represented loan to Ferrocarril Central Andino S.A., a third party Peruvian limited liability
company that provided certain transportation services to the Group. Such loan receivable is
unsecured, interest free and due in 9 years.
- 13 -
Aging analysis of other receivables at the respective balance sheet dates is as follows:
Within 3 months
3 to 6 months
6 months to 1 year
1 to 2 years
8.
30 June
2014
US$000
31 December
2013
US$000
2,890
1,636
7,387
8,701
7,168
5,887
10,140
3,047
20,614
26,242
Ordinary
shares
US$000
Share
premium
US$000
At 1 January 2014
Issuance of new shares
11,817,782,429
472,711
327,267
At 30 June 2014
11,817,782,429
472,711
327,267
At 1 January 2013
Issuance of new shares (Note)
10,001,171,429
1,816,611,000
400,047
72,664
329,048
At 30 June 2013
11,817,782,429
472,711
329,048
Note:
The Company completed the listing of its shares on the Main Board of The Stock Exchange of Hong
Kong Limited on 31 January 2013 and the over-allotment option was exercised on 22 February 2013
with 1,764,913,000 and 51,698,000 shares issued respectively at a par value of US$0.04 per share. The
issue price was HK$1.75 per share.
- 14 -
9.
Current
Borrowings from immediate holding company (a)
unsecured
Short-term bank loans (b)
guaranteed
unsecured
Long-term bank loans, due within one year (b)
guaranteed
Non-current
Borrowings from immediate holding company (a)
unsecured
Long-term bank loans (b)
guaranteed
(a)
30 June
2014
US$000
31 December
2013
US$000
190,000
400,000
100,000
281,000
100,000
123,215
813,215
381,000
153,437
151,604
2,534,465
2,538,204
2,687,902
2,689,808
3,501,117
3,070,808
151,604
190,000
1,833
250,766
2,440
(103,495)
343,437
149,711
- 15 -
(b)
Bank loans
As at 30 June 2014, bank loans are summarized as follows:
30 June 2014
Amount
Effective
US$000
interest rate
The Export-import Bank of China
(Eximbank) (i)
China Development Bank
(CDB) (ii)
Other banks (iii)
31 December 2013
Amount
Effective
US$000
interest rate
2,399,204
2.20% 3.85%
257,000
3.83%
500,000 1.16% 1.61%
220,000
300,000
3.85%
1.35% 1.80%
3,157,680
2,919,204
(i)
In December 2010, the Group obtained a banking facility amounting to US$2,000 million
from Eximbank for the purpose of financing the development of the Toromocho Mining
Project. The Group is required to pay a 1% commission fee for each drawdown and the
facility bears an interest rate at LIBOR plus 1.85% per annum. This facility is guaranteed
by Chinalco and will become secured by all property, plant and equipment pertaining to the
Toromocho Mining Project if Chinalcos credibility or financial status deteriorates (Note 4).
The Group is also required to comply with certain financial covenants relating to the use of
funds and other administrative resources.
In March 2013, the Group signed a supplemental agreement with Eximbank which provided
additional loan facility amounting to US$419 million with an interest rate at LIBOR plus
3.5% per annum. The Group is required to pay a 1% commission fee for each drawdown.
This facility is guaranteed by Chinalco and will become secured by all property, plant and
equipment pertaining to the Toromocho Mining Project if Chinalcos credibility or financial
status deteriorates (Note 4). The Group is also required to comply with certain financial
covenants relating to the use of funds and other administrative resources.
(ii) In September 2012, the Group obtained banking facilities amounting to US$83 million from
CDB for the construction, maintenance and operation of Kingsmill Tunnel Water Treatment
Plant. This facility is guaranteed by Chinalco and bears an interest rate at LIBOR plus 3.5%
per annum.
In September 2012, CDB issued a memorandum indicating its commitment to lend US$274
million to the Group for certain designated projects in relation to the development of the
Toromocho Mining Project, in which US$100 million was cancelled later due to delay of
related specific project. Pursuant to this memorandum, the Group has obtained banking
facilities which are guaranteed by Chinalco and bear an interest rate at LIBOR plus 3.5%
per annum.
- 16 -
(iii) As at 30 June 2014, the Group obtained bank loans of US$500 million from BBVA and
SCB, which are denominated in US$ and bearing interest rates at a range from 1.16% to 1.61%
per annum. Among of which, US$400 million is guaranteed by China Export and Credit
Insurance Corporation, a third party, with counter-guarantee provided by Chinalco.
During the periods ended 30 June 2014 and 2013, the movement in the borrowings from banks
are analysed as follows:
Six months ended 30 June
2014
2013
US$000
US$000
(c)
2,919,204
318,000
(81,000)
1,476
1,999,973
432,000
(4,200)
2,191
3,157,680
2,429,964
As at 30 June 2014, the long-term loans and borrowings were repayable as follows:
30 June
2014
US$000
31 December
2013
US$000
Within 1 year
Between 1 and 2 years
Between 2 and 5 years
Over 5 years
123,215
192,329
670,258
1,825,315
219,926
613,507
1,856,375
2,811,117
(123,215)
2,689,808
2,687,902
2,689,808
- 17 -
Up to 3 months
3 to 6 months
6 months to 1 year
30 June
2014
US$000
31 December
2013
US$000
240,915
63,694
11,045
352,894
1,061
7,362
315,654
361,317
11. Revenue
As the Group has not commenced commercial production, no revenue was generated during the sixmonth period ended 30 June 2014 (2013: Nil).
Management determines the operating segments based on the information reported to the Groups chief
operating decision maker. As all of the Groups activities are engaged in the mining development and
all the principal assets employed by the Group are located in Peru, the Groups chief operating decision
maker considers the performance assessment of the Group should be based on the results of the Group
as a whole.
12. General and Administrative Expenses
Six months ended 30 June
2014
2013
US$000
US$000
Employee benefit expenses
wages, salaries and allowance
directors emoluments
pension costs-defined contribution plans
others staff benefits
Less: staff cost capitalized into construction-inprogress
- 18 -
28,643
926
3,371
3,798
(31,261)
17,224
611
2,608
3,590
(18,567)
5,477
5,466
262
336
630
44
383
877
610
189
357
5,408
714
286
253
235
224
2,196
8,808
15,139
(38)
6,405
(2,003)
3,163
6,367
1,160
The Company was incorporated in Cayman Islands as an exempted company with limited liability
under the Companies Law of Cayman Islands and, accordingly, is exempted from payment of Cayman
Islands corporate income tax.
The Companys subsidiaries incorporated in Peru are subject to income tax at a rate of 32% during the
six-month period ended 30 June 2014 (2013: 30%), pursuant to the stability agreement signed with the
MEM that stablizes their income tax rates at 32%, taking effect on 1 January 2014.
The income tax on the Groups loss before tax differs from the theoretical amount that would arise
using the applicable tax rates to losses of the consolidated entities as follows:
- 19 -
(12,460)
(9,126)
3,987
2,738
3,652
(1,295)
23
(2,025)
447
6,367
1,160
14. Loss per share for the period attributable to the equity holders of
the Company
(a) Basic
Basic loss per share is calculated by dividing the net loss attributable to the equity holders of the
Company by the weighted average number of ordinary shares in issue during the period.
Six months ended 30 June
2014
2013
Loss attributable to equity holders of the Company (US$000)
Weighted average number of ordinary shares in issue (thousands)
(6,093)
11,817,782
0.0005
(7,966)
11,508,695
0.0007
(b) Diluted
Diluted loss per share for the six months ended 30 June 2014 and 2013 are the same as the basic
loss per share, as there are no dilutive potential shares.
15. Event Occurring after the Reporting Period
Saved as disclosed in Note 2 to the unaudited interim condensed consolidated financial statements, no
other reportable events or transactions take place after the balance sheet date.
- 20 -
- 21 -
- 22 -
Reserves
According to the technical report prepared by Behre Dolbear Asia Inc. dated November 2012 (the
Competent Persons Report) as disclosed in the Prospectus, the proved and probable JORCcompliant reserves of the Toromocho Project deposit are estimated to contain approximately 7.3
million tonnes of copper, 290,000 tonnes of molybdenum and 10,500 tonnes of silver.
The following tables summarise the estimated ore reserves and mineral resources in respect of the
Toromocho Project as at 30 June 2014.
Tonnes
(millions)
Copper
(%)
Grade
Molybdenum
(%)
756
784
0.51
0.434
0.02
0.018
6.39
7.31
3.9
3.4
150,000
140,000
4,800
5,700
1,540
0.471
0.019
6.86
7.3
290,000
10,500
Tonnes
(millions)
Copper
(%)
Grade
Molybdenum
(%)
Metal Content
Silver
Copper Molybdenum
(grams/tonne) (million tonnes)
(tonnes)
Silver
(tonnes)
Measured
Indicated
156
364
0.41
0.36
0.014
0.012
6.20
6.06
0.6
1.3
22,000
44,000
1,000
2,200
Total
520
0.37
0.013
6.10
1.9
66,000
3,200
Tonnes
(millions)
Copper
(%)
Grade
Molybdenum
(%)
Metal Content
Silver
Copper Molybdenum
(grams/tonne) (million tonnes)
(tonnes)
Silver
(tonnes)
174
0.460
0.015
Proved
Probable
Total
JORC Measured and Indicated
Mineral Resources Category
Inferred
Metal Content
Silver
Copper Molybdenum
(grams/tonne) (million tonnes)
(tonnes)
11.54
0.8
26,000
Silver
(tonnes)
2,000
As of 28 August 2014, the Company believes there has been no material change to its resources and
reserves since the Listing Date.
- 23 -
Central highway
Access to the Toromocho Project is by either the paved central highway or the central railway,
which both connect the Morococha mining district to Lima. The center of the Toromocho
Project deposit is approximately 2.5 kilometers (km) from the town of Morococha. Lima is
approximately 142 km away from the Toromocho project through the central highway.
Railway
A railway line from Callao port to the project is 172 km. Copper concentrates and molybdenum
oxide will be transported from the site to the port of Callao via the existing railway. The
delivery of consumables such as diesel fuel, mill balls and reagents to the Toromocho Project
site will be by way of railway. Given that the annual transportation capacity of the existing
railway is 4 million tonnes and the current railway usage is approximately 1.5 million tonnes
per annum, the remaining transportation capacity of the railway will be sufficient to deliver the
products of Toromocho Project to the Callao port.
- 24 -
Water
The total water demand of the Toromocho Project on average per year is approximately 8.65
million cubic meters. Sufficient water for the operation of the Toromocho Project has been
assured through the construction of the Kingsmill Tunnel Water Treatment Plant (KTWTP)
by Chinalco Peru for drainage of the rock acid water that was previously discharged directly
to a local river without treatment. The discharged water from the tunnel is drained through
the KTWTP where it is treated to reduce acidity and metal content. The KTWTP has been in
operation since August 2010.
The Kingsmill Tunnel is expected to provide sufficient water to support the operation of the
Toromocho Project, with an estimated flow rate of approximately 3,500 cubic meters per hour,
and the maximum designed feed rate of the KTWTP is approximately 5,000 cubic meters per
hour. The treated water will be pumped to the raw water pump station, and then to the raw
water pond. The pond will be located in the concentrator area to provide the processed water
for the concentrator and the fire-fighting system.
Power
The expected power consumption of Toromocho Project is 165 MW and power supply is
from 220 kV Pomacocha Substation which is a part of the National Grid. This substation was
recently upgraded with 220 kV double busbar and has enough capacity to supply electricity
to the Toromocho Project. Chinalco Peru has entered into a contract with Edegel S.A.A., a
power generation company, under which the electricity would be supplied by Pomacocha
Substation. Meanwhile the power transmission from Pomacocha to Toromocho is carried out
by Pomacocha Power S.A.C., a transmission company, via a 220 kV transmission line with
double circuit to assure high reliability of the power supply at Toromocho main substation.
The capacity of the transmission line is 240 MW and hence there is enough capacity for
Toromocho Project including for future expansion.
- 25 -
The Toromocho Projects main substation consists of three 220/23 kV power transformers
which are 75MVA, 100MVA (each has 75MVA to 100MVA capacity) and 110 MVA
respectively. As any two of these transformers could supply all electricity required, the
capacity of power is highly ensured. Therefore there is a redundancy which ensures the power
supply at 23 kV busbar, where gas-insulated switchgear is used for the distribution systems
for the mine and concentrator plant, including the sag semi-autogenous grinding mill and ball
mills. Harmonic Filters are also connected to this 23 kV busbar to ensure that the power is not
only suitable for the Toromocho Project and also in line with the relevant Peruvian standards.
The most important milestones that enabled the construction of the power lines were the
approval of Environmental Impact Study in March 2013, and the authorization of the Yauli
community in July 2013. Therefore on 15 October 2013 electric power supply was completed
and the main substation was energized to start the mine operations and the commissioning of
the concentrator plant.
The Development & Operation of the Toromocho Project
Main Constructions
100% of the engineering, procurement and construction of the copper concentrator of the Toromocho
Project have been completed. 100% of the construction of the molybdenum hydrometallurgy plant
has also been completed. The commissioning of the Toromocho Project commenced from 10
December 2013. The molybdenum hydrometallurgy plant will start commissioning in the fourth
quarter of this year.
Commissioning and Ramp-up
The commissioning of the Toromocho Project commenced on 10 December 2013. Commissioning in
the grinding area has progressed behind the planning schedule, and the actual efficiency of grinding
has not been maximized yet. Chinalco Peru will further facilitate commissioning of the grinding
equipments in October and the Toromocho Project is expected to reach full production capacity in
the fourth quarter of the year 2014. The Company has evaluated that the delay of ramping up to full
production capacity of Toromocho Project may result in a decrease in the estimates of production
volume for the year 2014. Based on the current operation of the Toromocho Project and information
available to the Company, the Company has further adjusted its estimate of the copper concentrates
production for the year 2014 to approximately 340,000 tonnes, with approximately 80,000 to
85,000 tonnes of copper contained, which are both 20% respectively lower than the estimates of the
Company disclosed in the announcement of the Company dated 17 June 2014 in relation to update
on the development of the Toromocho Project.
Notwithstanding the above, the Company currently estimates that the long term production of the
Toromocho Project would not be materially affected.
- 26 -
Mine
During the first quarter of 2014, Chinalco Peru has finished the commissioning of the main
equipment of the mine, including two shovels and three drillers. The training for the working
staffs in the mine area has also been conducted in the first quarter of 2014. The mining ramp-up
has been on schedule and in line with the plan. The mining has reached the full capacity since
May 2014. Currently the daily movement of the materials is approximately 240,000 tonnes.
Processing plant
The processing plant began commissioning in December 2013. As of the date of this
announcement, the plant has not reached the full capacity due to the problem in the grinding
area. Chinalco Peru is taking actions to further facilitate commissioning to improve the
efficiency of the ball mills and semi-autogenous grinding mill. The Company expects the full
production capacity will be reached in the fourth quarter of 2014.
Maintenance
With up to 400 technical and craft personnel working at the site of Toromocho Project, a
maintenance team of Chinalco Peru is supporting the operations in mine, processing plant and
utility plant.
Chinalco Peru has conducted a maintaining program with series of protocols and measures to
strengthen the management and improve the efficiency in the following areas, aiming to reduce
the material consumption, control costs, assure safety and optimize the production:
Reliability engineering
Contractor management
The maintaining program will assist the mine and processing plant ramp up to their full
capacity in the planning schedule.
- 27 -
Expansion Plan
On 17 June 2013, the Company announced that the Board had approved the Proposed Expansion in
order to optimize and increase the capacity of the Toromocho Project, subject to any amendments
and finalisation of details and any shareholders approval as may be required under applicable
law or the Listing Rules. The Proposed Expansion will be carried out at the Toromocho mine
which forms the basis of the Toromocho Project. The total capital expenditure for the Proposed
Expansion is expected to be approximately US$1.32 billion. The construction of the Proposed
Expansion is currently expected to be substantially completed by the second quarter of 2016. The
Proposed Expansion is expected to be financed (i) from the Groups internal working capital, (ii)
by re-allocating the proceeds from its initial public offering (the IPO) originally intended for the
acquisitions of suitable non-ferrous and non-aluminum mining projects to the extent required for the
Proposed Expansion, and (iii) debt financing (including but not limited to bank loans).
Ancillary projects
Kingsmill Water Treatment Plant
Kingsmill water treatment plant is in normal operation.
The commissioning of Kingsmill water supply system had been finished at the end of 2013 and
starts to pump the make-up water for the plant.
Power supply
On 15 October 2013, the construction of the 220 kV power supply system was completed
successfully. The 23 kV main substation was energized to commence the mine operations and
the commissioning of the concentrator plant. So far the power supply system has been operating
satisfactorily up to the designated requirements.
Lime Plant
Up to date, 99% of the engineering, 87% of the procurement and 34% of the construction of the
Lime Plant were completed. The major work that has been completed includes the construction
of the concrete mixing station, the construction of foundations for the transfer and crusher, piling
works and part of earthwork. All the construction of the Lime Plant is estimated to be completed in
May 2015 and the commissioning is estimated to start in the third quarter of 2015.
- 28 -
Transportadora Callao
In September 2010, Chinalco Peru invested in the newly incorporated Transportadora Callao S.A.
and acquired 7% of the equity interest in this company. Transportadora Callao is authorized to
operate a dock which is exclusively used for mineral concentrates transportation. The dock has
a process capacity of approximately 3 million tonnes per year. The specialized dock includes a
conveyor belt to load the mineral concentrates onto ships at the rate of 1,600 tonnes per hour.
The total length of this conveyor belt is 3.5 kilometers and it is fully sealed to avoid any external
exposure. The Commissioning of all the system of Callao port has been completed and this system
started to operate at the end of June 2014.
Resettlements
On 20 September 2013, the Peruvian Congress approved a law changing the capital city of the
District of Morococha from the old town to the town newly built by Chinalco Peru. Resettlement
of the affected residents in the Morococha old town started in November 2012, prior to which there
were approximately 3,200 residents in the Morococha old town. More than 92% of the residents
have moved to the new city as of 28 August 2014. The whole resettlement is expected to be
completed by the end of 2015.
Industry Review
During the first half of 2014, the Indonesian concentrate export ban, a high level of impurities in the
customs concentrates market as well as a series of maintenance closures and production disruptions
at global smelters all contributed to lower refined production. Smelting/refining capacity continues
to remain the bottleneck in the copper market. While demand continues to grow in Europe, it has
been soft throughout this year in the United States (the US). But strong Chinese imports of refined
copper in the first half have considerably tightened the market in the rest of the world.
In the second half of 2014, mine supply is expected to move into a period of sustained growth as
Grasberg resumes full output and projects start to deliver. On the refined side, the production will be
more heavily weighted towards the second half of the year, fuelled by the start-ups of new smelting
capacity in China. On the demand side, copper use is entering the slow summer season with spot
physical premiums in Shanghai, Europe and the US decreasing and actually trading below annual
contract levels in Shanghai and Europe. For the whole year, it expects to have a rather balanced
global market.
Financial Review
Revenue and cost of sales
Although the Group announced the commencement of the commissioning of Toromocho Project in
December 2013, the Group has not commenced commercial production. Therefore, no revenue has
been generated and no cost of sales has been recorded.
- 29 -
US$2 billion facility and US$419 million credit facility from the Eximbank (December 2010
and March 2013);
US$83 million, US$35 million, US$12 million, US$9 million and US$118 million credit
facilities from CDB (September and December 2012, June and November 2013 and May
2014);
- 30 -
US$81 million one year credit facilities from CDB (November 2013), which has been repaid in
May 2014;
US$100 million one year revolving loan facility and US$200 million one year term loan
facility from BBVA (October and December 2013).
US$200 million one year revolving loan facility from Standard Chartered Bank (Taiwan)
Limited and Standard Chatered Bank, Offshore Banking Unit (January 2014).
The borrowings from the banks mentioned above all carry interest at floating rate. As of 30 June
2014, the Group had cash and cash equivalents of approximately US$113.8 million. The Group
uses bank and cash balances to finance working capital and part of its capital expenditure for its
continuing growth and expansion plans. The Group determines the appropriate amount of cash to
maintain on-hand by forecasting the Groups future working capital and capital expenditure needs.
The Group also aims to maintain a certain level of extra cash to meet unexpected circumstances and
to use in relation to business expansion opportunities as they arise.
Operating activities
Net cash used in operating activities for the six months ended 30 June 2014 was approximately
US$98.9 million, which was primarily attributable to the increase in working capital. The Group has
announced commencement of the commissioning of the Toromocho Project at the end of 2013, but
it had not reached the full capacity as of 30 June 2014. Hence, the net cash flows generated from
operating activities were still negative.
Investing activities
Net cash used in investing activities in the six months ended 30 June 2014 was approximately
US$337.4 million, which was primarily attributable to the Groups purchases of property, plant
and equipment of approximately US$342.4 million, which we used for construction activities and
purchase of fixed assets.
Financing Activities
Net cash generated from financing activities in the six months ended 30 June 2014 was
approximately US$427 million, which was mainly consisted of the proceeds from the Groups loans
with its immediate holding company (US$190 million), CDB (US$118 million) and SCB (US$200
million), and the repayment of the loan with CDB of US$81 million.
- 31 -
Capital expenditure
The total capital and operating expenditure for the development of current project and the Project
Expansion estimated and incurred as of 30 June 2014 are as follows:
(a) Set forth below is the Companys estimated total capital expenditure of current project based
on the Competent Persons Report and the expenditure incurred as 30 June 2014:
Competent Costs incurred
Persons as of 30 June,
2014
Report
(US$ in millions)
Current Project
Mining
Process Plant and Infrastructure
Owners Cost and Working Capital
Additional Projects
303.50
1,871.90
704.20
622.60
314.79
1,960.54
693.65
500.77
Total
3,502.20
3,469.75
Notes:
(i)
The Capex of Mining over run the budget due to the delay of power supply in 2013.
(ii) The Capex of Process Plant and Infrastructure runs over the estimation which was due to the
delay of electricity power supply and the delay of completion of the construction of the Moly
Hydromet Plant.
(iii) Owners cost and working capital consists of costs associated with force majeure events, project
insurance, social outreach, contract services, licenses and royalties, financial costs, taxes,
exchange rate fluctuations, commissioning and pre-operational costs and acquisitions of property.
(iv) Additional projects consist of the costs incurred in relation to the lime processing plant,
Kingsmill Tunnel water treatment plant, double circuit overhead transmission line, central
highway relocation, investment in the Callao port, acquisition of certain mining concessions from
Pan American Silver with the relevant financing interest, new town construction and resettlement.
So far the lime plant is still in construction and the central highway relocation is pending the
Peruvian government approval to start.
- 32 -
(b) Set forth below is the Companys estimated total capital expenditure based on the Feasibility
Study Report and the expenditure incurred for the Proposed Expansion as of 30 June 2014:
Feasibility Costs incurred
Study as of 30 June,
2014
Report
(US$ in millions)
Project Expansion
Mining
Process Plant and Infrastructure
Owners Cost
115.19
1,061.18
142.33
395.68
1.26
Total
1,318.70
396.94
(c) Other than the capital expenditure described above, there was an amount of US$18.95 million
sustaining capital expenditure incurred during the six months ended 30 June 2014, which was
mainly the expenditure for the sustaining construction of the tailing dam and the procurement
of its relating equipments.
Capital structure
During the six months ended 30 June 2014, the Groups funding primarily came from bank loans
and borrowings from immediate holding company.
Gearing ratio
The Group monitors capital on the basis of the gearing ratio. This ratio is calculated as net debt
divided by total capital. The gearing ratio of the Group as of 30 June 2014 is as follows:
As at
30 June
2014
US$000
As at
31 December
2013
US$000
Total borrowings
Less: cash and cash equivalents
3,501,117
(113,782)
3,070,808
(122,916)
Net debt
Total equity
3,387,335
716,205
2,947,892
722,419
Total capital
4,103,540
3,670,311
Gearing ratio
83%
80%
- 33 -
The increase in the gearing ratio during the six months ended 30 June 2014 was primarily due to the
increase of the groups bank loans and other borrowings.
Employee and remuneration policy
As of 30 June 2014, the Group had 1,287 employees in total.
The Groups remuneration policy is designed to attract, retain and motivate highly talented
individuals, to ensure the capability of the Groups workforce to carry out the business strategy of
the Company and to maximize shareholder wealth creation.
Benefit schemes are maintained for employees as required by the laws in Peru and China.
Moreover, under Peruvian labour law, our Peruvian subsidiaries with more than 20 employees are
required to distribute 8% of their profits generated in any year among their employees.
In addition, the Group has proposed to adopt an equity incentive plan designed to attract, retain and
incentivize senior management and key employees with a view to encouraging the participants to
commit to enhancing value for us and our shareholders, as a whole.
Foreign Exchange Risk
The Group mainly operates in Peru with most of its transactions, which are mainly related to the
acquisition of services and loans received from related parties, denominated and settled in US
dollars.
Accordingly, the Group is exposed to foreign exchange risk that may arise from fluctuations in
the New Peruvian Soles to US dollar exchange rate. Our Directors estimate that the impact of any
changes in the New Peruvian Soles to US dollar exchange rate will not have a significant impact
on our financial condition and results. As a result, the Group does not maintain a hedging policy
against the Groups foreign exchange risk. Although the Group maintains a net liability position
expressed in New Peruvian Soles that, in its appreciation trend, may have a negative impact upon
liquidation of these monetary assets and liabilities, public estimates available do not anticipate a
severe devaluation of US dollars in the short term that may cause a major impact on the Groups
financial condition and results of operation.
During the six months ended 30 June 2014, the Group has not used any financial instrument to
hedge its foreign exchange risk.
- 34 -
Contingent liabilities
The Group has contingent liabilities in respect of legal claims and administrative procedures arising
in the ordinary course of business. However, the Group believes it has made adequate provision for
these contingent liabilities, and it is not anticipated that any material liabilities will arise from the
contingent liabilities other than those provided for. For the six months ended 30 June 2014, there
was no additional provision made by the Group in respect of legal claims.
Off-balance sheet arrangement
The Group has not entered into, nor does it expect to enter into, any off-balance sheet arrangements.
The Group also has not entered into any financial guarantees or other commitments to guarantee
the payment obligations of third parties. In addition, the Group has not entered into any derivative
contracts that are indexed to its equity interests and classified as owners equity. Furthermore, the
Group does not have any retained or contingent interest in assets transferred to an unconsolidated
entity that serves as credit, liquidity or market risk support to such entity. The Group does not have
any variable interest in any unconsolidated entity that provides financing, liquidity, market risk or
credit support to it or that engages in leasing, hedging or research and development services with it.
Event after balance sheet date
Saved as disclosed in Note 2 to the unaudited interim condensed consolidated financial statements,
there are no important events affecting the Company and its subsidiaries which have occurred since
30 June 2014.
Prospects
The Company has not carried out any additional exploration at the Toromocho Project in 2014 as it
has been focusing on the commissioning of the Toromocho Project.
The Company will continue its endeavors with optimizing the development and operation of the
Toromocho Project to ensure that it reaches full production capacity in the fourth quarter of 2014 as
well as the steady implementation of the Proposed Expansion so as to achieve satisfactory business
results and reward the shareholders of the Company.
USE OF NET PROCEEDS FROM LISTING
The net proceeds from the Listing (the Proceeds) (including those Shares issued pursuant to the
partial exercise of the over-allotment option), after deducting underwriting fees and related expenses,
amounted to approximately US$394 million, which sum was originally intended to be applied in the
manner disclosed in the Prospectus. As disclosed in the Prospectus, the Company intended to use
approximately 30% of the Proceeds to pursue selective acquisitions of suitable non-ferrous and nonaluminum mining projects and development of such acquired projects. In light of the Companys
decision to implement the Proposed Expansion (subject to any amendments and finalization of the
- 35 -
details and the availability of funds) and due to the fact that there was no suitable acquisition that
the Board had decided upon, the Board resolved on 17 June 2013 to re-allocate the above 30%
of the Proceeds from the initial intended use for the acquisitions of suitable non-ferrous and nonaluminum mining projects to the Proposed Expansion. Details of the change in use of the Proceeds
are set out in the Companys announcement dated 17 June 2013. Except for the re-allocation of 30%
of the Proceeds as described above, there were no other changes to the intended use of Proceeds as
disclosed in the Prospectus.
As at the date of this announcement, part of the Proceeds have been applied as follows:
(i)
the Company repaid US$103 million of the borrowings from Aluminum Corporation of China
Overseas Holdings Limited on 28 February 2013;
(ii) the Group had disbursed approximately US$120 million for the development of the Toromocho
Project;
(iii) the Group has disbursed approximately US$120 million for the expansion of the Toromocho
Project; and
(iv) approximately US$40 million has been used for supporting the Groups working capital
requirement.
INTERIM DIVIDEND
The Board does not recommend any interim dividend for the six-month period ended 30 June 2014.
COMPLIANCE WITH CORPORATE GOVERNANCE CODE
The Group is committed to maintaining high standards of corporate governance to safeguard the
interests of shareholders and to enhance corporate value and accountability. Except as disclosed
below, for the six-month period ended 30 June 2014, the Company has complied with the code
provisions of the Corporate Governance Code and Corporate Governance Report (the CG Code)
contained in Appendix 14 to the Listing Rules.
Under code provision A.6.7 of the CG Code, all non-executive Directors are recommended to
attend general meetings of the Company. All non-executive Directors of the Company (including
independent non-executive Directors) attended the annual general meeting of the Company held on
18 June 2014 (the AGM), other than Dr. Xiong Weiping, Dr. Liu Caiming and Mr. Ronald Ashley
Hall who were absent from the AGM due to pre-arranged business commitments.
Under provision E.1.2 of the CG Code, the chairman of the Board is recommended to attend annual
general meetings of the Company. Dr. Xiong Weiping, being the chairman of the Board, was absent
from the AGM due to a pre-arranged business commitment.
- 36 -
Under code provision A.2.1 of the CG Code, the roles of chairman and chief executive of the
Company should be performed by separate individuals, but due to Dr. Zhang Chengzhongs
background, qualifications and experience at the Company, he was considered the most suitable
person to take both roles in the current circumstances. The Board was of the view that it is
appropriate and in the best interests of the Company that Dr. Zhang Chengzhong holds both
positions at the current stage, as it helps to maintain the continuity of the policies and the stability
and efficiency of the operations of the Company. The Board also meets regularly on a quarterly
basis to review the operations of the Company led by Dr. Zhang Chengzhong. Accordingly, the
Board believes that this arrangement will not impact on the balance of power and authorisations
between the Board and the management of the Company.
COMPLIANCE WITH THE MODEL CODE FOR SECURITIES TRANSACTIONS BY
DIRECTORS OF LISTED ISSUERS
The Company has adopted the Model Code for Securities Transactions by Directors of Listed Issuers
(the Model Code) as set out in Appendix 10 to the Listing Rules as its own code of conduct
regarding Directors securities transactions. The Company has made specific enquiry to all Directors,
and all Directors have confirmed that, for the six months period ended 30 June 2014, they were in
compliance with the required standard as set out in the Model Code.
PURCHASE, SALE OR REDEMPTION OF LISTED SECURITIES
There was no purchase, sale or redemption of any listed securities of the Company by the Company
or any of its subsidiaries during the six months period ended 30 June 2014.
AUDIT COMMITTEE
The Board has established an audit committee (the Audit Committee) which comprises two nonexecutive Directors, namely, Dr. Xiong Weiping and Dr. Liu Caiming and three independent nonexecutive Directors, namely Mr. Lai Yat Kwong Fred, Mr. Scott McKee Hand and Mr. Ronald
Ashley Hall. Mr. Lai Yat Kwong Fred is the chairman of the Audit Committee.
From 28 August 2014, Dr. Li Bohan and Mr. Liu Hongjun, newly appointed non-executive Director,
have replaced Dr. Xiong Weiping and Dr. Liu Caiming, who resigned as non-executive Directors
with effect from 28 August 2014, as the Audit Committee members.
The Audit Committee has reviewed together with management the unaudited interim condensed
consolidated financial statements of the Group for the six months ended 30 June 2014. The Audit
Committee has also reviewed the effectiveness of the internal control system of the Company and
considers the internal control system to be effective and adequate.
The interim results for the six months ended 30 June 2014 are unaudited, but have been reviewed by
Ernst & Young in accordance with International Standard on Review Engagements 2410 Review of
Interim Financial Information Performed by the Independent Auditor of the Entity.
- 37 -
- 38 -