Material Approval
Submittal
(MAS Form)
Contract:
MAS Ref:
Sweden
Project Specifications Section 9 Part 2 Clause 2.1, 2.2, & 2.3; Project Specifications
Section 20 Part 2 Clause 2.7; QCS 2010 Section 9 Part 2 Clause 2.1, 2.2, & 2.3d,
Section 20 Part 2 Clause 2.7
Location of use on
NPP/0047 CCIA Project Fire Water Pump Room, Potable Water Pump Room,
project:
Workshop & Garage, Foul Water Pump Room
Technical details:
Non-Clog Type Submersible Pumps (IP68 motor protection class, 415V, 3, )
Attachments to support the materials submittal:
1
Compliance Statement with Project Specifications
Remar Please refer to pages 001 040
ks:
2
Schedule for Submersible Pumps
Remar Please refer to pages 042 043
ks:
3
Material Technical Data Sheet
Remar Please refer to pages 044 048
ks:
4
Panel Board Wiring Diagrams
Remar Please refer to pages 049 055
ks:
5
Sequence of Operation
Remar Please refer to pages 056 057
ks:
6
Material Test Certificate
Remar Please refer to pages 058 059
ks:
7
Previous Approvals
Remar Please refer to pages 060 065
ks:
8
Catalogue
Remar Please refer to pages 066 082
ks:
9
Supplier Local Registration
Remar Please refer to pages 083 086
ks:
10 Country of Origin Certificate
Remar Please refer to pages 087 088
ks:
11 Warranties/Guarantees
Remar Please refer to pages 089 090
ks:
12 Storage, Transport & Handling Requirements
Remar Please refer to pages 091 092
ks:
13 ISO Certificates
Remar Please refer to pages 093 102
ks:
14 Letter from the Manufacturer : Throughlet Size
Remar Please refer to pages 103 104
ks:
15 Letter from the Manufacturer : IP Rating
Remar Please refer to pages 105 106
ks:
16 Letter from the Manufacturer : Voltage & Ambient
Remar Please refer to pages 107 108
Temperature
ks:
17 Performance Testing Procedure
Remar Please refer to pages 109 111
ks:
18 Manufacturers Standards
Remar Please refer to pages 112 113
ks:
19 Employers Approval on the Pre-Qualification
Remar Please refer to pages 124 126
ks:
NPP00100-ACM-PRO-1201-MAS
Revision 0 24 March 2014
Page 1 of 2
Material Approval
Submittal
(MAS Form)
Disclaimer
We understand that approval of the material(s) submitted herein is only intended to determine general
conformance with the intent of the project contract documents. By submitting these materials for approval,
we confirm we have performed all necessary on-site dimensional and building utility requirement
coordination, and if approval is granted, will further coordinate the information contained within with all
other concerned contractors employed by the NPPSC.
Action:
Prepare
d by: /
Submitt
ed by:
Checke
d by:
Reviewe
d by:
Name:
Amjad
Rawashd
eh
MEP
Project
Manager
Muhame
d
Mustafa
Technical
Manager
Glisson
George
QA/QC
Manager
01-052016
01-052016
01-052016
Reviewe
d&
Approve
d by
Design
Consulta
nt:
Design
Consultant stamp
Approve
d by:
Company
stamp
Signat
ure:
Date:
Status B
(reviewed as noted)
Status C
Status D
(cancelled)
(insert CSRC reference that refers to the details of the review outcome)
Reviewed by:
Date returned
to Contractor:
NPP00100-ACM-PRO-1201-MAS