Documente Academic
Documente Profesional
Documente Cultură
1. The knowledge area of Project Time Management consists of the following processes Time Management Processes
Process
Project Phase
Key Deliverables
Planning
Define Activities
Planning
Sequence Activities
Planning
Planning
Develop Schedule
Planning
Project Schedule
Control Schedule
2. The Define Activities process has the following Inputs, Tools and Techniques and
Outputs Define Activities Process
Inputs
Outputs
Scope baseline
Decomposition
Activity list
Activity attributes
Templates
Milestone list
Expert judgment
3. The Sequence Activities process has the following Inputs, Tools and Techniques and
Outputs Sequence Activities Process
Inputs
Outputs
Activity List
Activity attributes
Milestone list
Dependency determination
Organizational process
assets
4. The Estimate Activity Resources process has the following Inputs, Tools and Techniques
and Outputs Estimate Activity Resources Process
Inputs
Outputs
Activity List
Expert judgment
Activity attributes
Alternative analysis
Resource calendars
5. The Estimate Activity Durations process has the following Inputs, Tools and Techniques
and Outputs Estimate Activity Durations Process
Inputs
Outputs
Activity list
Expert judgment
Activity attributes
Analogous estimating
Parametric estimating
Resource calendars
Three-point estimates
Reserve analysis
6. The Develop Schedule process has the following Inputs, Tools and Techniques, and
OutputsDevelop Schedule Process
Inputs
Outputs
Project Schedule
Schedule baseline
Activity List
Schedule Compression
Schedule data
Activity attributes
Resource levelling
Resource Calendars
Scheduling tool
Applying calendars
Outputs
Performance reviews
Project schedule
Variance analysis
Work performance
information
Project management
software
Change requests
10. Network diagrams are used to display activities and their dependencies. Network
diagrams can be used to perform critical path analysis. Network diagrams can also be
used to perform crashing and fast tracking of the project.
There are two type of network diagrams o Activities on Node (or Precedence)
o Activities on Arrow (or AOA)
Precedence is most commonly used. AON and AOA cannot have loops or conditional
relationships.
11. An activity in a network diagram is displayed as shown below.
Activity name
Activity Number
Estimate
5 days
13. In the above example Documentation is activity number 2 and is estimated to last 5 days.
14. Precedence (or Activity on Node) diagrams can be used to display four type of
relationship between activities. These are
o Finish-To-Start
o Start-To-Start
o Start-To-Finish
o Finish-To-Finish
Finish-to-start relationship means the dependent activity cannot start until the first
activity is finished. This is the most common way to represent relationships between
activities.
15. Activity on Array (AOA) network diagrams have the following characteristics.
o AOA only uses Finish-To-Start relationship between tasks.
o PERT and CPM can only be used with AOA.
o Dummy events are shown with dotted lines. They do not take any time. They
show dependencies between tasks.
16. Longest path through the network diagram is called the critical path. The activities on the
critical paths are called critical activities.
17. Lags are inserted waiting times in between tasks. For example Task B cannot start until
three days after task A completes.
18. Slack or Float is the amount of time a task can be delayed without delaying the project.
Tasks on the critical path have zero float.
19. Critical Path Method (CPM) has the following characteristics.
o It uses one time estimate per activity
o It can be drawn only using AOA diagrams
o It can have dummy events
20. Program Evaluation and Review Technique (PERT) has the following characteristics.
o It uses three estimates per activity - optimistic, pessimistic and most likely
o It can be drawn only using AOA diagrams
o It can have dummy events
21. PERT utilizes more information than CPM as it considers the "Pessimistic" and
"Optimistic" values in addition to the "Most Likely" value in its calculations. The
following are formulae used by PERT Mean = (P + 4M + O)/6
Standard Deviation = (P-O)/6
Variance = ((P-O)/6)2
Here P is the pessimistic estimate, O is the optimistic estimate and M is the most likely
estimate.
22. GERT is another type of network diagram. It can support looping.
23. If a project has more than one critical paths then the risk to the project increases.
24. Resource levelling refers to keeping the resources same across the duration of the project.