Document Code :
Title, Subtitle
CT
TEST REPORT
Format
A4
Rev. A
Date
15.09.2015
Lang.
En
Date
15.09.2015
Project No.
ISSUE DATE
15/09/2015
ENG. N
CT TEST REPORT
SH/OF
2/7
CLIENT N
REV.
Summary
Page
Revision
A
CHARACTERISTICS
MECHANICAL CHECKS
ELECTRICAL CHECKS
6. POLARITY CHECK
8. RATIO CHECKS
9. BURDEN TEST
Project No.
ISSUE DATE
15/09/2015
ENG. N
CT TEST REPORT
SH/OF
3/7
CLIENT N
REV.
Revision
Serial No
FLUKE / 179
MEGGER / S2-552/2
SVERKER / 760
Project No.
ISSUE DATE
15/09/2015
ENG. N
CT TEST REPORT
SH/OF
4/7
CLIENT N
REV.
2. CHARACTERISTICS
Phase
R
Phase
S
Phase
T
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
S1-S3
Manufacturer
Year
Type
Ith
CORE N 1:
Reference
Ratio
Serial Number
Power
Class
CORE N 2:
Reference
Ratio
Serial Number
Power
Class
CORE N 3:
Reference
Ratio
Serial Number
Power
Class
CORE N 4:
Reference
Ratio
Serial Number
Power
Class
Project No.
ISSUE DATE
15/09/2015
ENG. N
CT TEST REPORT
SH/OF
5/7
CLIENT N
REV.
3. MECHANICAL CHECKS
Designation
Phase
R
Phase
S
Phase
T
Phase
R
Phase
S
Phase
T
Phase
R
Phase
S
Phase
T
Visual inspection
Orientation (P1/P2)
Name plate
HV connections indentification
LV connections identification
Connections tighteness
No gas leakage
4.
ELECTRICAL CHECKS
Designation
Grounding
Primary connections
Secondary connections
5.
1S1-1S2-1S3
500 Vdc 1 mn
2S1-2S2-2S3
500 Vdc 1 mn
3S1-3S2-3S3
500 Vdc 1 mn
4S1-4S2-4S3
500Vdc 1mn
Project No.
ISSUE DATE
15/09/2015
ENG. N
CT TEST REPORT
SH/OF
6/7
CLIENT N
REV.
6. POLARITY CHECK
Phase
R
Secondary
Phase
S
Phase
T
Phase
S
Phase
T
1S1-1S3
2S1-2S3
3S1-3S3
4S1-4S3
Theorical value
1S1-1S3
2S1-2S3
3S1-3S3
4S1-4S4
Ambiant Temperature: 18 C
Phase
R
Project No.
ISSUE DATE
15/09/2015
ENG. N
CT TEST REPORT
SH/OF
7/7
CLIENT N
REV.
8. RATIO CHECK
Phase
Winding
Primary current
value
Secondary current
measured value
Theorical
Ratio
Calculated Ratio
1S1-1S3
2S1-2S3
3S1-3S3
4S1-4S3
1S1-1S3
2S1-2S3
3S1-3S3
4S1-4S3
1S1-1S3
2S1-2S3
3S1-3S3
4S1-4S3
9. BURDEN TEST
Winding
1S1 - 1S3
2S1 - 2S3
3S1 3S3
4S1 - 4S3
10.
SATURATION CURVES
Phase
R
Phase
S
Phase
T
Results