Testing & Commissioning Plan


The following inspections & tests will be performed by Allied Machinery Ltd. In the presence, of
representative from TECHNOLOGIST INC at Maimana Project.

A. Pre-Startup Inspection
Generator 01 Serial No:
Generator 02 Serial No:
S.No. Description

Acceptance criteria

1.

Drive Belts

2.

Starting motor

3.

Radiator drains

Inspect for wear, cracking & tension.


Check Loose Connection / tightness of Battery
Cable.
Check Leakage / Valve should be closed.

4.

block coolant drains

5.

Coolant fill level

6.

Coolant line connections

Check Leakage / Plug Installation.


13mm (0.5 inch) below sight glass (if equipped).
13mm (0.5 inch) below the bottom of pipe for
filling.
Check hoses & clamps.

7.

Combustion air filter

Visually inspection for any restriction.

8.

lube oil sump drain

Inspect valve / plug / Leakage.

9.

lube oil filter

10.

lube oil fill level

11.

Fuel line connections

Part No / Cat Filter / Tightness of Filter.


Maintain the oil Level between ADD mark To
Full mark
Tightness & leakage / proper installation.

12.

Fuel lines

Tightness & Leakage.

13.

Fuel filter

14.

Voltage Regulator

15.

Wiring & terminations

Part No / Cat Filter / Tightness of Filter.


Inspect connection / moisture / Loose
connection.
Inspect for wear, damage, connectors.

16.

Instrumentation

Inspect gauges, panels, sensors.

17.

Nameplates

Proper installation / complete data.

18.

Exhaust muffler
Engine & generator
mounting bolts

Proper installation / Direction.

19.

Inspect / missing / Tightness of bolts.

Remarks

Allied Machinery Limited


Old Fabreeka Pashmeena Bafee (Wool Factory), Adjacent UNO Printing Press,
Main Jalalabad Road, Kabul Afghanistan
Contact No: 0093-777 966 971, 0093 777 199 199

B) Post Startup Checks Generator Sets


S.No.
1.
2.

3.

Description
Use manual
emergency stop
switch
Use simulation to test
the over speed safety.
Use simulation to test
high water
temperature & lube
oil pressure safeties.

4.

Use simulation to test


over load safety.

5.

Meter readings

6.

Control panel
parameters

Acceptance criteria

Remarks

Engine should stop


Engine should stop on over speed simulation.

Engine should stop in both cases.


This safety has been provided in Automatic
transfer switch. On overload the ATI should open
the circuit.
Readings of panel gauges, meters, displays, and
instruments provided as permanent equipment
shall be verified during test runs, using test
instruments of greater precision and accuracy.
All the parameters have been checked & found
Ok.

C) MTS Testing
S.No. Description
1.
2.
3.

Remarks

Start one generator set and after warm up time, shift the load on running
generator set.
Start the 2nd generator set and after warm up time, shift the load on 2nd
generator set.
Repeat the cycle 2-3 times.

D) 400 kW Load Bank Testing


S.No. Description
1.

Testing the load at different steps as provided per manufacturer standard

Remarks

Allied Machinery Limited


Old Fabreeka Pashmeena Bafee (Wool Factory), Adjacent UNO Printing Press,
Main Jalalabad Road, Kabul Afghanistan
Contact No: 0093-777 966 971, 0093 777 199 199

B) Load Test
The Generator sets will be tested on suppliers provided load bank as per following
procedure.
Steps
1st Step:

Load Test
Start the genset and run without load for 15 minutes.

nd

Put 10% load and run the genset for 15 minutes

rd

3 step:

Increase the load to 25% and run for 15 minutes

4th Step:

Increase the load to 50% and run for 15 minutes

2 step:

th

Increase the load to 75% and run for 15 minutes

th

Increase the load to 100% and run for 15 minutes

5 Step:
6 Step:

Remarks

NOTE:
Due to Maimana site conditions there will be deration and must be considered while testing the
genset on load.
The genset is rated at 0.8 power factor and load bank is rated as 1.0 power factor and this must
be considered while testing the genset on load.
Block loading, more than 25% is not recommended.
Load Test Report is attached for details.

Signed for Technologists Inc

Name:
Designation

Signed for Allied Machinery Ltd

Name:
Designation