Documente Academic
Documente Profesional
Documente Cultură
Outline.
India Bangladesh Interconnector
Context/Background
Scope of work
Major Milestones
Salient Features of HVDC system
JA Y P U R H A T
M A LD A
K H E JU R IA
K A H A LG A O N
BOGRA
FARRAKA
NAOGAON
BOGRA
SOUTH
N IA M A T P U R
B A N G LA D E S H
D H U LIA N
R A JS H A H I
NATORE
S IR A JG A N J
S A G A R D IG H I
BAHARAMPUR
IS H U R D I
DURGAPUR
GOKARNA
BAHARAMPUR
(400 K V )
4 0 0 kV D /c
IN D IA
K O LA G H A T
SUBHASGRAM
JE E R A T
S H A H JA D
PUR
BAGHABARI
GHORASAL
BHERAMARA
B O T T A IL
KATW A BAKRESHW AR
PABNA
M ADHOPUR
RAGHUNATHGANJ
K H U LN A
(S O U T H )
F A R ID P U R
LE G E N D
T H E P R O JE C T
400 kV
230 kV
132 kV
E xisting
U nder C onstr. / F uture
Context/Background:
The interconnection of Electrical Grids between the India
and Bangladesh was discussed during the visit of Indian
delegation to Bangladesh from 22nd Nov. to 26th Nov.,
2009.
Various options for the interconnection were explored and
keeping in view
The Technical & Operational Aspects
Economical considerations
Indian Portion
Sub-station
Establishment of 400kV switching-station at Baharampur(India)
2 Nos of 400 kV line bays for loop-in and loop-out of Farakka-Jeerat
400kV Single circuit line
1 No. of 80 MVAR Bus Reactor
Space provision for at least 2 no. of 400kV bays
Bheramara(Bangladesh)
400kV
Double
Circuit
line
Sub-station
Establishment of 500 MW HVDC back-to-back station and 230kV
switching-station at Bheramara(Bangladesh)
Installation of 500 MW HVDC back-to-back terminal.
4 nos of 230 kV line bays for LILO of Ishurdi -Khulna South 230kV Double
Circuit line
Space provision for at least 2 no. of 230kV bays
Package Details
Date of Award/
Name of Party
Awarded Cost
Contract Agreement on
30th December 2010
400 KV Transmission
line (Indian Portion)
M/s KEC
International
Limited, Gurgaon,
India
Description
Date
1.
28th Feb'10
2.
20th May'10
3.
4.
5.
6.
Notification of Award
Contract Award
7.
8.
Description
Date
1.
28th Feb'10
2.
3.
26th April' 10
4.
5.
6.
15th Sep'10
7.
8.
29th Mar10
Notification of Award
30th Dec10
Contract Award
M.R. Chauhan/ V.S. BHAL
POWERGRID INDIA
Smoothing Reactor
Air core reactor located outside the valve hall.
Two unit of 30 mH to be installed for 500 MW block.
- Nominal inductance (1 unit) 30 mH
- Current 3200 Amps
- Maximum continuous current 3762 Amps
M.R. Chauhan/ V.S. BHAL
POWERGRID INDIA
Interconnection of
Interconnection of
India-Sri Lanka Electricity Grids
Introduction
Context/Background
Scope of work
Major Milestones
Salient Features of HVDC system
Introduction
MoU Signed between GoI & GoSL on 9th June, 2010 for carrying out
feasibility study for interconnection of India-Sri Lanka Electricity Grids
Executing Agency : POWERGRID (India) & CEB (Sri Lanka)
The HVDC link would consist of overhead line in the territories of India
and Sri Lanka and submarine cable for the sea portion between the end
point of overhead portion of Indian and Sri Lankan side.
Panaikulam
Thirukketiswaram
New Anuradhapura
M.R. Chauhan/ V.S. BHAL
POWERGRID INDIA
Scope of Work
Scope of Work
Sea Route (Scope : POWERGRID) Panaikulam(India) to Thirukketiswaram(SL) : 120km
India Sea Coast(Panaikulam) to Sri Lankan Sea coast (Thirukketiswaram) HVDC
line (Submarine Cable) (120 km)
The feasibility study report for land route in Indian Territory and complete sea route is
under the scope of POWERGRID while feasibility study report for land route in Sri
Lankan territory is under the scope of CEB.
The estimated cost of the feasibility study is US$ 3.0 Million, to be shared by Govt. of
India and Govt. of Sri Lanka in equal proportion. Out of this the share of
POWERGRID and CEB are US$2.375 Million and US$0.625 Million respectively for
the tasks assigned to them.
Project Summary
Details of HVDC Interconnection : All the following options would be studied in the
DPR
HVDC Terminal Capacity
Option-I : 4x250MW terminal in two stages
Option-II : 2x500MW terminal in two stages
Option-III : 2x500MW terminal in single stage
Project Summary
Option I (With Conventional Thyristor based System): 400kV, 4x250MW in two stages
Stage I: 400kV, 2x250MW
Stage II: 400kV, 2x250MW
Option I (With Voltage Source Converter based System): 320kV, 4x250MW in two stages
Stage I: 320kV, 2x250MW
Stage II: 320kV, 2x250MW
M.R. Chauhan/ V.S. BHAL
POWERGRID INDIA
Project Summary
Option II (With Conventional Thyristor based System): 400kV, 2x500MW in two stages
Stage I: 400kV, 1x500MW
Stage II: 400kV, 1x500MW
Option II (With Voltage Source Converter based System): 320kV, 2x500MW in two stages
Stage I: 320kV, 1x500MW
Stage II: 320kV, 1x500MW
M.R. Chauhan/ V.S. BHAL
POWERGRID INDIA
Project Summary
Option III (With Conventional Thyristor based System): 400kV, 2x500MW in single stage
Option III (With Voltage Source Converter based System): 320kV, 2x500MW in single stage
400kV Conventional Thyristor based System is using Mass Impregnated Cable and 320kV
Voltage Source Converter uses extruded cable.
Classic
VSC
Converter Valves
SCR
IGBT
Connection Valve-AC
Grid
Converter Transformer
Transformer+Reactor
Filtering
Dc Current Smoothing
Smoothing Reactor
DC Capacitor
In VSC, the roles of rectifier and inverter can be interchanged between the stations any time without
delay, without breaker switching and without polarity reversal.
VSC
Conventional Transformer
Current- Sourced
Voltage-Sourced
Line-commutated
Self-Commutated