Documente Academic
Documente Profesional
Documente Cultură
2,April 1990
1145
KEYWORDS
EHV, Transmission, Line, Design, Economics, Optimization,
Standardization, Conductor, Terrain
ABSTRACT
The design of transmission lines is often limited to a few
standard conductors and structures in order to minimize the
costs of engineering, construction, inventory, and speed of
damage restoration. Certain design factors, such as unloaded
conductor tensions, maximum allowable conductor temperatures,
and phase spacing to avoid ice galloping induced flashovers,
are also fixed. Limiting the designer's choices can be economic
in certain situations but not in others. What makes economic
sense in flat terrain or with a lightly loaded line may not be
economic in hilly terrain or with a line whose electric load
is consistently high.
This paper considers a range of line optimization
techniques which can be applied to decide whether standard
or optimized line designs are appropriate. It is found that even
simple methods of optimization can help the designer keep his
costs to a minimum.
The effects of electrical losses, structure family and
heights, conductor design limits on temperature and tension
are determined in flat and hilly terrain for a 500 kV example
case.
In the example, in flat terrain, the selection of an
optimum design in place of the standard, results in savings
of from 8% to 15% in the total present worth of revenue
required for construction and losses over the life of the line.
In a specific section of hilly terrain, the example shows that
the use of optimization methods results in savings of from 15%
to 19%. The costs of redesigning structures, using non-standard
conductors and investigating the proposed changes in design
limits must be measured against such potential savings.
1.0 BACKGROUND & INTRODUCTION
Many utilities in the United States and in Europe, utilize
standard transmission line structures in order to minimize the
costs of engineering, simplify construction, minimize inventory
and ease restoration problems in case of damage.
Since
structure loads are primarily determined by conductor loadings,
a standard single or bundled conductor corresponds to each
standard set of structures.
f o r p r i n t i n g Yarch 8 , 1989.
O55j-S950/9O/0jOO-l145$Ol
.OO 0 1990 IEEE
1146
o
o
o
o
o
o
o
o
optimum cost placement of available structures on the rightof-way either by means of an experienced tower spotting
engineer or by means of a numerical program.
3.1 Conductor ODtimization
The type and size of phase conductor are varied. Standard
structures are not varied. The minimum allowable conductor
diameter is set by the minimum required thermal capacity for
low voltage lines and by radio noise, audible noise and corona
requirements for higher voltage bundled lines. The maximum
practical conductor diameter is determined by the load limits
of the standard structures (the larger the conductor diameter,
the shorter the wind and weight spans - the stronger the
conductor, the smaller the maximum line angle of angle
structures).
Within these constraints on conductor size, the
subconductor diameter is selected such that the sum of total
present worth of revenue required (PWRR) for electrical losses
over the life of the line and the levelized costs of construction
and maintenance, are a minimum [3],[4].
3.2 Conductor and Structure Ootimization
Variations in both the conductor and the structure are
considered. The lower limit on conductor diameter is still set
by either thermal or environmental design limits but larger
conductors can be accommodated by strengthening structures.
Conductors and structures having certain novel characteristics
are considered. Since the range of choices is large, the task
of design becomes both more complex and, potentially at least,
more rewarding.
For each type of structure investigated, the structure cost
varies with crossarm height, phase spacing, conductor diameter,
tension and span length. A mathematical relationship between
structure cost and these variables must be determined before
this optimization approach can be undertaken. The resulting
optimal conductor and structures will involve the costs of
detailed structure design and perhaps some test work.
Design limits - unloaded conductor tension limits,
maximum conductor temperature, phase spacing, etc. - are
unchanged.
3.3 Conductor. Structure and Design Limit ODtimization
The evaluation of certain innovations in conductor and
structure materials and/or design may require a re-evaluation
of conductor, structures and even design limits, limited only
by the need for safety and reliability at minimum cost. For
example, a new conductor design such as SDC[S], can be
installed at higher than standard unloaded tensions and offers
reduced structure wind loading due to the use of trapezoidal
rather than round strands. The resulting savings in structure
height and/or number of tangent structures per mile must be
compared to the increased costs from more heavily loaded angle
structures and possibly higher construction loads.
The
advantages and disadvantages of such innovations require a
rather thorough rethinking of all the standard design
components and assumptions. Even with the use of standard
conductors, the consideration of non-standard design limits such
as reduced or increased tension[6] and reduced or increased
maximum temperature[7] may offer significant savings in certain
types of terrain or may provide the justification for necessary
research concerning the use of nonstandard design limits.
4.0 OPTIMIZATION OF A STANDARD 500 K V DESIGN
In order to demonstrate the preceding optimization
alternatives, the design of a 500kV transmission line using a
standard conductor and limited family of standard structure
designs will be compared to various optimized alternatives.
The example designs are kept relatively simple but are sufficient
to illustrate the concepts clearly.
1147
TYPE
TANGENT
SUSPENSION
ANGLE
STRAIN
MAX
LINE
ANGLE
PEG)
MAX
WIND
SPAN
@ M A X @ Oo
ANG.
ANG.
MAXIMUM
WEIGHT
SPAN
LOADED
BARE
(n)
1000
1000
1245
2000
60
1000
5000
2000
3000
(FT)
(m
TANGENT
SUSPENSION
ANGLE
STRAIN
XARMHT
(FT)
83
60
70
21.9
24.0
80
26.1
60
60
63.1
73
130
214
213
CDR. MAT'L
AND LABOR
61
100
ELEC. LOSSES
@ 25% LF (75%LF)
236 (421)
192
549(734)
686(871)
350
FLAT
HILLY
275
1.4
AlTACHMENT COST OF
HEIGHT
STRUCTURE
(W
1s K)
93
FLAT
HILLY
TOTALS
MAX
H/V
RATIO
Structure
Type
PRESENT
WORTH
(SK/MILE)
STRUCTURES
(IW
(FT)
DIRECT
MATERIAL &
LABOR COST
(SK/MILE)
COST
COMPONENT
'ooor-----800
600
fl
400-
'
4000
"
8000
'
'
12000
'
'
16000
'
20000
(Feet)
Figure 1
P l o t o f "Hilly" Terrain
1148
44
47
45
51
61
100
84
138
---
ACTUAL
TWR
WEIGHT
ESTIMATED
TWR
ACT-EST
WEIGHT
T
L
V
H
TRNS LONG VERT
LOAD LOAD LOAD
9901.52
19098.86
9824.24
18046.21
10172.73
19443.56
9910.56
19200.28
9560.86
18195.65
10183.58
19255.46
9750.80
18584.47
9933.53
23800.07
9415.91
19973.30
10070.33
23262.15
10513.09
20899.06
19.40
33.95
15.55
27.22
19.77
34.60
16.32
28.57
19.21
33.62
15.07
26.38
19.57
34.25
16.53
28.93
1011S.15
25%
75%
236
42 I
I70
303
2. BLUEBIRD
ENVIRONMENTAL
EFFECTS
RI @ Edge of ROW (dB)
AN @ Edge of ROW (dB(A)
25%
75%
28
80
18648.11
9865.15
24078.41
9434.85
20106.44
9965.15
23097.35
10056.06
20655.30
-0.1
-0.5
2.7
-0.8
-0.1
1.0
3.6
0.3
-0.7
1.2
0.2
0.7
-1.1
-0.7
-4.5
-1.2
12.39
9.18
11.92
10.49
12.51
10.76
13.07
11.43
30.50
6.66
38.28
19.84
35.10
9.15
8.60
7.84
33.71
59.00
30.48
53.35
35.47
62.08
32.07
56.12
32.05
56.09
28.59
50.03
33.61
58.82
31.36
54.88
t
XARM
HT
66.50
109.20
67.10
107.80
66.90
107.10
67.20
108.20
71.40
144.50
72.50
125.30
71.80
138.60
72.50
125.30
-3386
+ 12.6.T
-24.9
L + 122.6'V + 138.8. Ht
1149
weights, respectively.
Clearly, the linear regression equation
yields excellent estimates of structure weight over the range
of loading and structure heights indicated in the Table.
750 -
700
4.3.2 ODtimum Conductor & Structure in Flat TerrainIn section 4.2, a 2-conductor bundle of Bluebird ACSR was
shown to be less expensive than the standard 3- conductor
bundle of Rail ACSR yet gave roughly the same RI and Audible
noise and the same structural loads.
In this section, the
possibility of using a wider range of conductor types and sizes,
while adjusting the structure cost to reflect the conductor load
in each case, is considered. Also, the wind/weight span of
the tangent structure is varied for each candidate conductor
in searching for the minimum cost design.
Design limitsconductor unloaded tension in %RBS, maximum conductor
temperature, broken wire load assumptions, RI limits, etc.remain constant for each conductor and structure.
In flat terrain, angle towers are used wherever there is
a change in line direction. Thus the number of such towers
is constant no matter how the conductor and structure
wind/weight spans vary.
The cost of each angle structure,
however, changes with the conductor tension and the
transverse load.
Tangent towers are largely insensitive to
conductor tension, but increase in cost primarily with
transverse load.
Starting with the standard wind span of 1000 feet, the
total present worth of revenue required (PWRR) for electrical
losses and construction cost is plotted against conductor
diameter. Figures 2a and 2b are for loss factors of 25% and
75%, respectively.
3-conductor bundles of all-aluminum
conductor (AAC); 45/7 ACSR; and 54/19 ACSR were studied.
The subconductor diameter yielding minimum total present worth
of revenue required (PWRR) for construction and losses is not
sensitive to the conductor type, however, it
sensitive to loss
factor. The largest diameter subconductors of each type - 1590
kcmil Coreopsis AAC, 1590 kcmil Lapwing, and 1590 kcmil
Falcon - offer savings at either loss factor over the standard
design.
650
1
CONDUCTOR DIAMETER (IN)
CASE
FILE
TOTAL PWRR (SKIMILEI
I\
3D
i
3E
3F
RANGE OF MAX
AlTACH WIND
HEIGHTS SPAN
(FT)
(FT)
70
800
70
70
1000
60-80
60-80
60-80
60-120
60-120
I200
800
1000
I200
1200
I400
NO. OF
COST OF
STRUCTURES
STRUCTURES
TANGENTtDE-TOTAL TANGENTtDE-TOTAL
(SUMILE)
--
16 + I 1 27
I6 t 8 - 24
17 + 5 22
I l l + 224 335
121 + 162 = 282
139 + 101 240
17 + 9 = 26
20 + 5 25
18 + 4 22
17 + 3 - 20
I S + 2 = 17
I44 + 60 204
145 + 41 = I86
520
1150
70
'
WITH ANGLES
660 k
600
'
I
15
TERRAIN
__
SAG AT
MAXIMUM
TEMP FOR
1200 FT.
RULING SPAN
TOTAL
TANGENT
TOWER
COST
@./MILE1
FLAT
100
60.0
151
FLAT
50
55.0
146
HILLY'
100
60.0
124
HILLY'
so
55.0
LAPWINO
+ COREOPSIS
780.
780
21
800
MAXIMUM
ALLOWABLE
CONDUCTOR
TEMP C
'(C1
18
FALCON
WIND SPAN
120
1200 ft.
700
1151
OPTIMUM
Conductor
Max Wind Span
Tension (%RBS),T
3. Rail
1000
15%. IOOOC
.3 Lapwing
Direct Construction
Cost (SK/Mile)
191
219
734
621
505
1000
21%. SOT
549
OPTIMUM
Conductor
3. Rail
3. Coreopsis
1000
1400
Tension
(%RBS). OC
15, 100
21,
Direct Cost of
Conductor & Structures
(SK/Mile)
275
265
871
686
703
584
so
ACKNOWLEDGMENT
The authors acknowledge the contribution of Messrs. H.
Bryan White and John Bates to the sections of this study
concerning structure optimization with regard to terrain. The
algorithm used in studying tower placement in hilly terrain
was developed by them. In addition, the authors wish to thank
the Electric Power Research Institute which sponsored the
studies from which this paper was excerpted and who also
sponsored the development of the Transmission Line Optimization
Program with Terrain (TLOPWT) which was used to perform
all the optimization calculations.
6.0 REFERENCES
1.
2.
3.
4.
5.
6.
7.
5.0 CONCLUSIONS
Clearly, the indicated savings through line optimization
is not a net savings at all. The cost of implementing these
various changes in structure and conductor design and use will
clearly cost money as well as save it. The point is, that the
methods outlined in this paper point in the direction of
potential cost savings in EHV lines. The degree to which they
are actually implemented by the utility designer depends upon
the costs associated with the changes as well as upon the
savings indicated here.
Nevertheless, one may draw several conclusions from the
preceding examples of optimization:
(1)
(2)
were conductor
span, structure
and maximum
appear to be
1152
APPENDIX
Economic Data - Base Case Values
Cost of conductor steel
Cost of 1350 aluminum
Cost of tower erection
Cost of tower material
Period of analysis
Discount Rate
Line fixed charge rate
Demand charge
Demand fixed charge rate
Demand reserve
Demand charge escalation rate
Energy charge
Energy charge escalation rate
0.40 $/lb
1.00 $/lb
1.00 $/lb
1.00 $/lb
35 years
12.00%
20.00%
550.00 $/kW
20.00%
20.00%
3.50%
0.020 $/kWh
7.00%