Documente Academic
Documente Profesional
Documente Cultură
Investigation Of
Prepared by:
Prepared by:
Collins Engineers, Inc.
1180 Sam Rittenberg Blvd, Suite 105
Charleston, South Carolina 29407
1.0 INTRODUCTION
The NBIS was created in the early 1970’s as a result of the Silver Bridge collapse in
West Virginia. Before this time, there was very little public interest in the inspection and
maintenance of our nation’s bridges. After 46 people died as a result of this collapse,
the U.S. Congress required the Secretary of Transportation to establish a National
Bridge Inspection Standard and develop a program to train bridge inspectors. These
inspections are necessary for having an effective bridge maintenance program. The
SCDOT performs five main types of inspections.
Typically all of these inspection levels are coordinated through the SCDOT Bridge
Maintenance Office. The responsibility of this office is to coordinate bridge maintenance
and rehabilitation activities, as well as, overseeing the SCDOT Bridge Management
System (BMS). The bridge management system is a means for managing state wide
bridge data throughout their design life. This includes collecting bridge inventory data,
performing inspections, maintenance and rehabilitation.
The standard SCDOT Inspection Form used by the Office of Bridge Maintenance is
used as the primary means for inventorying and assigning condition and appraisal
ratings to bridges in South Carolina. This form lists several bridge characteristics and
their corresponding codes as listed in the Recording and Coding Guide. Some aspects
of the form will be presented in the following sections. For a complete view of the
information contained in this form, please refer to Appendix C.
- General Bridge Data: This section lists the Bridge Identification Number, and
general location with respect to route or waterway crossed. It also lists the year
it was built or reconditioned, the overall length, number of spans, and the type of
structure.
- Geometric Data: This section lists all pertinent bridge geometry such as:
waterway navigation clearance, under clearances, vertical clearances, structure
width, horizontal clearances, number of lanes, and sidewalk dimensions.
- Condition Ratings: This section lists the inventory and operating rating, the last
paint application date (if applicable), and the condition ratings of the deck,
superstructure, and substructure.
- Critical Inspection Data: This section lists the last inspection date, the inspection
frequency, and gives an indication if special, fracture critical, or underwater
inspections have been or need to be performed.
- Appraisal Ratings: This section lists the overall appraisal of the structure, the
deck geometry, under clearance, bridge posting, and waterway adequacy. Many
of these ratings are not assigned by the actual inspector but are calculated using
FHWA Edit/Update computer program.
Bridge Element Grout Textual Data forms are also used by the inspector during routine
bridge inspection. This form evaluates the condition of: bridge abutments, bents, piers,
bearings, girders and beams, truss members, expansion joints, decks, curbs, bridge
railings or barriers, paint systems, waterway condition, fender system, alignment of the
roadway, traffic signs, and encroachments. Under these headings in Textual Data form,
the inspector can add general or specific comments about the items listed above and
their corresponding NBIS rating. An example of this form is presented in Appendix C.
NBI ratings typically cover the deck, superstructure, and substructure in the overall
bridge rating. The PONTIS system described in the following paragraph is an element
based inspection that inventories and rates every element on the bridge. This includes
but is not limited to the deck, beams, piles, bearings, railing, joints, etc. The different
elements rated are according to the material used. For instance, a bare concrete deck
and a concrete deck with asphalt overlay are considered different elements.
The SCDOT PONTIS BMS Element Data Form is a form that lists the Commonly
Recognized (CoRe) Structural Elements for bridges. PONTIS is owned by the
American Association of State Highway and Transportation Officials. The system is
used to store bridge inventory and inspection data using the NBIS guidelines and also
assigns condition states to each bridge element. With this system, each element
corresponds to an element number in the PONTIS System. The total quantity of each
element is then calculated. This quantity is then recorded as percentage of distribution
in each corresponding condition state. Condition states are listed from Condition 1 (little
or no deterioration) to Condition 5 (advanced deterioration). Each condition state is
described for each element and any feasible actions are also presented. For example:
If a bridge has 120 reinforced concrete piles this corresponds to Element 205 according
to the CoRe Elements, and 20 of these piles have deterioration, 17 percent of these
piles would be listed under Condition State 4 and the remaining 83 percent would be
listed under Condition State 1. For the Condition State 4 rating, there are three feasible
actions that can be performed on the 20 piles showing deterioration: do nothing,
rehabilitate the piles, or replace the piles. PONTIS BMS give a more quantitative
assessment of every structural element versus the general assessment given for the
deck, superstructure, and substructure given in the NBI. The SCDOT PONTIS BMS
Element Data Form is presented in Appendix C.
The training and qualifications of an NBIS bridge inspector are presented in the Code of
Federal Regulations 650C. The following excerpt is from the FHWA Bridge Inspectors
Reference Manual:
All of the inspectors for this cursory bridge inspection meet or exceed the requirements
as presented above.
The current AASHTO LRFD code calls for bridges to be designed for a Design
Life of 75 years (Section 1.2). What the actual in-service life of a structure may be is
dependent on the owner’s desires and expectations coupled with the effects of things
like the bridge’s exposure to environmental elements, quality of materials, construction
type and practices used and the level of maintenance. The US 278 Bridges were built
in the following years; 1982 for the two structures over Skull Creek, 1983 for the
Westbound lane over MacKay Creek and 1956 for the one Eastbound lane over
MacKay Creek. This means that they were most likely designed using a Design Life of
50 years, which was common at that time. Therefore, the Eastbound lane over MacKay
Creek has already exceeded it’s intended Design Life and the others are nearing year
30 of their Design Life. This does not mean that they are no longer functional or safe as
the ability of a structure to survive and perform well beyond its Design Life has been
well documented and is mostly dependent on the environment it resides in and the
maintenance attention it has received.
Many modern structures are now being designed with a Design Life of 100 years,
such as the new Ravenel (Cooper River) Bridge in Charleston, SC. The new Oakland
Bay Bridge in San Francisco has been designed for a Design Life of 150 years. Even
though these structures are designed to last longer, whether they do or not will be
greatly dependent on the factors already mentioned.
Of the several factors that play a role in the reduction of a bridge’s service life.
Two of the harshest and one that is present at the US 278 bridges, are the coastal
environment and heavy traffic use. In this location, these structures are subjected to
high wave and wind forces as well as being constantly inundated in the corrosive salt
The result of this long term exposure to a salt laden air and water environment is
corrosion. Corrosion affects the life of both steel structures and reinforced concrete
bridges. For steel structures, there are very visual signs of coating failure and
accumulation of rust on the structural steel members. With concrete structures, the
deterioration is usually not evident until it has reached advanced stages. This is
because corrosion attacks the reinforcing steel buried within the concrete and only
becomes visible once it has caused cracks and fractures (spalls) in the concrete surface
and rust staining is then seen.
The other factor mentioned was traffic volume. As the main bridges in and out of
Hilton Head, these structures see not only large volumes of traffic, but heavy usage by
truck traffic, which puts additional strain on the structure over time. Again, the
maintenance of the structure plays the biggest role in preventing deterioration due to
increase traffic volumes and loads. According to the Average Daily Traffic (ADT)
volume obtained from the SCDOT for the 2008 period, US 278 traffic volumes within the
area of investigation range from 44,300 to 57,800. A comparison of this ADT with other
locations indicates that this volume is the highest in Beaufort County.
For your reference, some other bridges that were constructed during the 1950’s
and are located in similar coastal environments are listed below. These bridges are still
open to traffic although we are not aware of the current condition of the structures.
Little River Intracoastal Waterway Bridge (Horry County, South Carolina), Built
1935; rehabilitated 1980, Warren through truss swing bridge over Intracoastal
Waterway on S-26-20 (formerly US 17) in Little River
Intracoastal Waterway Bridge (New Hanover County, North Carolina), Built 1956,
Bascule bridge over Intracoastal Waterway on US 74/US 76 in Wrightsville
Beach
Surf City Bridge (Pender County, North Carolina), Built 1955, Swing bridge over
Intracoastal Waterway on NC50/NC210 in Surf City
Southern Boulevard Bridge (Palm Beach County, Florida), Built 1950, Bascule
bridge over Intracoastal Waterway on Southern Boulevard in West Palm Beach
Oakland Park Blvd. Bridge (Broward County, Florida), Built 1955, Bascule bridge
over Intracoastal Waterway on Oakland Park Blvd. in Fort Lauderdale
Bridge 0720027840300 carries the west bound lanes of US 278 over MacKay
Creek in Hilton Head, South Carolina. The bridge consists of 54 prestressed concrete
girder spans and one steel girder span supported by prestressed square concrete pile
bents. The deck consists of stay-in-place forms and a reinforced concrete deck.
Bridge 0720027820300 carries the east bound lanes of US 278 over MacKay
Creek in Hilton Head, South Carolina. The bridge consists of 54 reinforced concrete
girder spans and one steel girder span supported by multiple reinforced concrete pile
bents. The structure originally consisted of pile bents with five octagonal concrete piles
supporting the reinforced concrete girders. Several of the original piles had a reinforced
concrete circular jacket. When the bridge was widened, two prestressed concrete piles
were driven on each side of the bents and support two additional prestressed concrete
girders on either side of the bridge. A retrofit cap connected the widened section to the
original cap. The deck consists of reinforced concrete with an asphalt overlay.
Bridge 0720027840400 carries the west bound lanes of US 278 over Skull Creek
in Hilton Head, South Carolina. The bridge consists of 21 approach spans and five
main channel spans. The main channel piers are comprised of a reinforced concrete
hammer head piers supported by a submerged footing/seal combination founded on
multiple steel H-piles. The approach spans are supported by a reinforced concrete
hammer head pier configuration founded on a waterline pile cap footing supported by
multiple prestressed concrete piles or prestressed concrete pile bents. The
substructure units support steel plate girders with transverse steel cross bracing and a
reinforced concrete deck.
Bridge 0720027820400 carries the east bound lanes of US 278 over Skull Creek
in Hilton Head, South Carolina. The bridge is of a similar configuration to the west
bound bridge. A 22 ft research vessel was used to gain access to the superstructure
and substructure elements. Due to heavy traffic the decks were visually inspected from
the inspection vehicle.
Methods of Investigation
The following criteria govern the assessment ratings of the structural components of the
inspected bridges: These criteria are established from the Recording and Coding Guide
for the Structure Inventory and Appraisal of the Nation’s Bridges. Report No. FHWA-
PD-96-001. These codes also follow the SCDOT Bridge Inspection Form Ratings.
- Code 9 - Excellent Condition
- Code 8 - Very Good Condition – no problems noted.
- Code 7 - Good Condition – some minor problems but functioning as intended.
- Code 6 - Satisfactory Condition – structural elements show some minor deterioration
but are still functioning as intended.
- Code 5 - Fair Condition – all primary structural elements are sound but may have
minor section loss, cracking, or spalling.
- Code 4 - Poor Condition – advanced section loss, deterioration, or spalling.
- Code 3 - Serious Condition – loss of section, deterioration, or spalling has seriously
affected primary structural components. Local failures are possible.
- Code 2 - Critical Condition – advanced deterioration of primary structural elements.
Fatigue cracks in steel or shear cracks in concrete may be present or scour may have
removed substructure support. Unless closely monitored it may be necessary to close
the bridge until corrective action is taken.
The following narrative will briefly describe the existing conditions encountered
during the cursory inspections of US 278 WBL and EBL over MacKay and Skull Creek.
The inspections were conducted over the course of two days. The weather was
overcast with light rain and an air temperature of 40 ºF both days. The water under the
bridge flowed between 0 and 2 ft/s during the inspection. Underwater visibility was
approximately 2 ft.
The embankments at all four bridges were found to be in very good condition
(Code 8). The banks along the waterways in the vicinity of the bridges were observed
to be in stable condition. Embankment protection in the form of riprap was observed on
the east and west banks of MacKay Creek and aquatic vegetation and oyster shells on
the east and west banks of Skull Creek. There was no sign of active erosion. The
channel bottom consisted of silty sand and oyster shells. There were no signs of heavy
accumulation of debris or drift.
Item 58 - Deck
The concrete deck was found to be in good condition (Code 7). There were no
noticeable spalls or significant cracks in the deck or the concrete barrier. In isolated
areas, the expansion joint material had come loose along the shoulder of the roadway.
Item 59 – Superstructure
The superstructure was found to be in satisfactory condition (Code 6). Minor cracking
was noted in isolated locations on the prestressed concrete girders. Several areas of
concrete spall repair were noted in isolated locations. The steel girders supporting the
main span showed signs of light to moderate corrosion with no signs of significant
section loss.
Item 60 - Substructure
Overall, the substructure was also found to be in satisfactory condition (Code 6). Minor
isolated cracks were noted on the piles above the high-water mark. Areas of minor
isolated spall repair were noted in random locations. The most significant defects were
located on Bent 2. On the east face of the reinforced concrete pile cap a crack
measured up to 3/4 in. wide with rust stains. The crack measured approximately 10 ft
long. The southernmost pile at Bent 2 had cracks up to 1/8 in. wide with rust stains
around all faces of the pile and extended from the bottom of the pile cap down
approximately 3 ft. A spall was located on the bottom of the pile cap at Bent 2. The
spall measured approximately 1 ft by 18 in. with 1 in. of penetration.
The piles at Bents 40 through 43 were inspected below water and were found to be in
good condition. The piles exhibited a heavy layer of marine growth from the high-water
mark to the channel bottom. No significant conditions were noted on the below water
portions of these piles. Please refer to Photographs 1 to 12 for typical views of the
conditions encountered on this bridge.
Item 58 - Deck
The deck was found to be in satisfactory condition (Code 6). The asphalt overlay
showed minor signs of deterioration along the joints. Minor delamination of the asphalt
Item 59 – Superstructure
Overall, the superstructure was found to be in fair condition (Code 5). This condition
was based on what the inspectors could visually assess from the boat. The bridge
bearings were not accessible. The steel girders supporting the main span showed
signs of light to moderate corrosion.
Random minor cracks were noted on the bottom and sides of the reinforced concrete
beams. Evidence of previous spall repairs were noted in several locations throughout
the superstructure and appeared to be in good condition. One isolated spall measuring
3 ft horizontal by 1 ft vertical was located on the bottom of Beam 6 at Bent 29. The spall
exposed one reinforcing which exhibited some corrosion but any loss of section could
not be verified. Other random superficial spalls due to lack of sufficient cover over the
reinforcing bars were noted on the reinforced concrete diaphragms.
Item 60 - Substructure
Several bents of different pile arrangements were inspected below water and were
found to be in fair condition (Code 5). The piles exhibited a heavy layer of marine
growth from the high-water mark to the channel bottom. Minor cracking with rust stains
was observed within the tidal zone on several of the piles. Many of the octagonal piles
have been retrofitted with concrete pile jackets. These jackets were typically located
within the tidal zone. Several jackets exhibited minor cracking between 1/8 in. and 1/2
in. wide with rust stains; however, no significant deterioration such as: large spalls or
section loss was noted on the inspected piles. Please refer to Photographs 13 to 26 for
typical views of the conditions encountered on this bridge.
Item 58 - Deck
Overall the concrete deck was found to be in good condition (Code 7). There were no
noticeable spalls or significant cracks in the deck. In areas, the expansion joint material
had come loose in isolated locations along the shoulder of the roadway. A spall
measuring approximately 2 ft long by 10 in. wide with no exposed reinforcing steel was
found on the top of the concrete barrier rail at the east end of the bridge.
Item 59 – Superstructure
The superstructure was visually inspected from the ground and the inspection boat and
was found to be in satisfactory condition (Code 6). The steel plate girders exhibited
minor loss of protective coating and showed no appreciable corrosion. Most of the
transverse steel cross bracing had more moderate loss of protective coating with some
minor corrosion. The corrosion was more pronounced where the steel cross bracing
was connected to the steel plate girders. Due to the height of the structure any loss of
section could not be verified.
Item 60 - Substructure
The inspections of the selected substructure elements revealed the most significant
deterioration and were rated as fair condition (Code 5). The inspected substructure
units exhibited a heavy layer of marine growth from the high-water mark to the channel
bottom. The east channel pier exhibited complete footing and seal exposure with
undermining of the seal at the upstream nose of the pier. The area of undermining
measured up to 5 ft vertical. The footing of the pier located at the west side of the
navigation channel was completely exposed and had approximately 4 ft of seal
exposure. No undermining of the seal was detected at this pier. Cracks up to 1/4 in.
wide with rust stains were located on the bottom of a majority of the pile cap footings for
the approach piers. These cracks were typically located 6 to 8 in. above the bottom of
the pile cap footings and were likely caused by corrosion of the internal reinforcing steel
due to chloride interaction from the saltwater environment.
The timber fender system on the west side of the navigation channel beneath the west
bound lane was partially missing.
Item 58 - Deck
Overall the concrete deck was found to be in good condition (Code 7). There were no
noticeable spalls or significant cracks in the deck. In areas, the expansion joint material
had come loose in isolated locations along the shoulder of the roadway.
Item 59 – Superstructure
The superstructure was visually inspected from the ground and the inspection boat and
was found to be in satisfactory condition (Code 6). The steel plate girders exhibited
minor loss of protective coating and showed no appreciable corrosion. Most of the
transverse steel cross bracing had more moderate loss of protective coating with some
minor corrosion. The corrosion was more pronounced where the steel cross bracing
was connected to the steel plate girders. Due to the height of the structure any loss of
section could not be verified.
Item 60 - Substructure
The inspections of the selected substructure elements revealed the most deterioration
and were found to be in fair condition (Code 5). The inspected substructure units
exhibited a heavy layer of marine growth from the high-water mark to the channel
bottom. The east channel pier was found to have up to 5 ft of vertical seal exposure
along the upstream nose. In addition, a void was detected at the footing and seal
3.0 RECOMMENDATIONS
Item 58 - Deck
There are no repair recommendations at this time; however, the expansion joint material
should be monitored for future deterioration and may require replacement in the near
future.
Item 59 – Superstructure
It is recommended that the minor cracking of the concrete girders and the condition of
any repairs be closely monitored during future inspections. The steel girders supporting
the main span showed signs of light to moderate corrosion and should be cleaned and
coated with a protective coating suitable for marine environments.
Item 60 - Substructure
The minor cracks located within the tidal zone should be monitored for continued
deterioration during future inspections. The 3/4 in. wide crack with rust stains located
on Bent 2 should be repaired by routing the crack and filling it with a flexible mastic
sealant. In addition, the southernmost pile at Bent 2 showed more extensive cracking
and should be repaired using a similar method.
The spall at the bottom of the pile cap at Bent 2 should also be repaired. This would
include removing all unsound concrete and reforming the area to its original dimensions
using a non-shrink grout suitable for marine environments.
Item 58 – Deck
There are no repair recommendations at this time; however, the expansion joint material
should be monitored for future deterioration and may require replacement in the near
future.
Item 59 – Superstructure
It is recommended that the minor cracking of the concrete girders and the condition of
any repairs be closely monitored during future inspections. The steel girders supporting
the main span showed signs of light to moderate corrosion and should be cleaned and
coated with a protective coating suitable for marine environments.
The spall located on Beam 6 of Bent 29 should be repaired. This would include
removing all unsound concrete, cleaning and coating any reinforcing steel and
reforming the area to its original dimensions using a non-shrink grout suitable for marine
environments.
Item 60 - Substructure
There are no pile repair recommendations at this time; however, the piles and pile
jackets should be monitored for increased deterioration during subsequent inspections.
Item 58 – Deck
The expansion joint material should be monitored for future deterioration. The 2 ft long
by 10 in. wide spall at the top of the barrier parapet is primarily cosmetic. It is also
protected from impact from the median crash barrier.
Item 59 – Superstructure
The loss of protective coating is relatively minor and should be monitored for further
deterioration.
Item 60 - Substructure
The footing/seal exposure and undermining at the channel piers should be monitored
closely during future underwater inspections. In addition, it is recommended to perform
or review a scour analysis of these piers to determine the anticipated depth of scour and
design countermeasures as necessary.
The cracks located at the bottom of the pile cap footings that are larger that 1/4 in. wide
should be routed and sealed with a flexible mastic sealant.
The portion of the missing fender system on the west side of the navigation channel
should be replaced.
Item 58 - Deck
Item 59 – Superstructure
The loss of protective coating is relatively minor and should be monitored for further
deterioration.
Item 60 - Substructure
The footing/seal exposure, as well as voids in the seal, at the channel piers should be
monitored closely during future underwater inspections. In addition, it is recommended
to perform or review a scour analysis of these piers to determine the anticipated depth
of scour and design countermeasures as necessary.
The cracks located at the bottom of the pile cap footings that are larger that 1/4 in. wide
should be routed and sealed with a flexible mastic sealant.
Overall, the four bridges are in satisfactory to fair condition. The type and amount of
deterioration observed during the cursory inspection are indicative of structures of this
age. Because the EBL Bridge over MacKay creek is older, (built in 1956), we saw more
deterioration in the superstructure and substructure. This deterioration has potentially
reduced some of the structures capacity but does not pose an immediate risk of failure.
The structure should however be scheduled for significant rehabilitation and/or
replacement in the near future.
Respectfully submitted,
COLLINS ENGINEERS, INC.
Originated by:
William Barna, P.E.
References
References:
Recording and Coding Guide for the Structure Inventory and Appraisal of the
Nation’s Bridges. Publication No. FHWA-PD-96-001, 1995.
Photographs
US 278 WBL and EBL
Over MacKay and Skull Creek
Photograph 3. View of the Main Steel Girder Span, US 278 WBL over MacKay Creek.
Photograph 5. View of Crack Located on the East Face of Bent 2, US 278 WBL over
MacKay Creek.
Photograph 6. Close Up View of the Crack Located on the East Face of Bent 2, US 278
WBL over MacKay Creek.
Photograph 7. View of Spall Located on the Bottom of Bent 2, US 278 WBL over MacKay
Creek.
Photograph 8. View of Cracks with Rust Stains Located on the Southernmost Pile
of Bent 2, US 278 WBL over MacKay Creek.
Photograph 10. Typical Above Water Pile and Prestressed Concrete Girder Condition, US
278 WBL over MacKay Creek.
Photograph 11. Typical Prestressed Concrete Girder and Pile Cap Condition,
US 278 WBL over MacKay Creek.
Photograph 12. Typical Below Water Pile Condition Showing Heavy Marine Growth, US
278 WBL over Skull Creek.
Photograph 13. View of the Downstream Fascia, US 278 EBL over MacKay Creek.
Photograph 14. Typical View of Superficial Spalls due to Lack of Sufficient Concrete
Cover over the Reinforcing Steel in the Diaphragm, US 278 EBL over MacKay Creek.
Photograph 15. Typical Spall Repair Located on Bottom of Reinforced Concrete Beam, US
278 EBL over MacKay Creek.
Photograph 16. Typical Bent with Longitudinally Battered Piles and Concrete Pile
Jacket, US 278 EBL over MacKay Creek.
Photograph 17. Typical Bent with Transversely Battered Piles and Concrete Pile Jacket,
US 278 EBL over MacKay Creek.
Photograph 18. View of the Upstream Fascia, US 278 EBL over MacKay Creek.
Photograph 19. Typical Above Water Reinforced Concrete Pile Condition, US 278 EBL
over MacKay Creek.
Prestressed Reinforced
Concrete Beam Concrete
Girder Saddle Beam
Photograph 20. View of a Typical Retrofit Pile Cap, US 278 EBL over McKay Creek.
Photograph 21. Typical Concrete Encasement Condition, US 278 EBL over MacKay Creek.
Photograph 22. Typical Underdeck and Reinforced Concrete Girder Condition, US 278
EBL over MacKay Creek.
Photograph 23. Typical Main Span Steel Girder Condition, US 278 EBL over MacKay
Creek.
Photograph 24. Typical Cracks with Rust Stains on Reinforced Concrete Pile, US 278 EBL
over MacKay Creek.
Photograph 25. 3 ft by 1 ft Spall on the Bottom of the Beam 6, Span 29, US 278 EBL over
MacKay Creek.
Photograph 26. 3 ft by 1 ft Spall on the Bottom of the Beam 6, Span 29, US 278 EBL over
MacKay Creek.
Photograph 27. View of the Upstream Fascia, US 278 WBL over Skull Creek.
Photograph 28. View of Typical Exterior Girder Condition, US 278 WBL over Skull Creek.
Photograph 29. View of Typical Interior Girder and Steel Cross Bracing Condition, US 278
WBL and EBL over Skull Creek.
Photograph 30. View of Typical Main Channel Pier Configuration, US 278 WBL over Skull
Creek.
Photograph 31. View of 2 ft long by 10 in Wide Spall Located on the East End of the
Concrete Barrier, US 278 WBL over Skull Creek.
Photograph 32. Typical Deck Joint Condition, US 278 WBL over Skull Creek.
Photograph 33. Typical Condition of the Intermediate Piers with Cracks at the Bottom, US
278 WBL over Skull Creek.
Photograph 34. View of the Downstream Fascia, US 278 EBL over Skull Creek.
Photograph 35. Typical Crack With Rust Stains Located on the Bottom of the Pile Cap
Footing for the Intermediate Piers, US 278 WBL over Skull Creek.
Photograph 36. Typical Interior Girder and Steel Cross Bracing Condition, US 278 EBL
over Skull Creek.
Photograph 37. Typical Deck Condition, US 278 EBL over Skull Creek.
Photograph 38. Typical Deck Joint Condition, US 278 EBL over Skull Creek.
Photograph 39. Typical View of Intermediate Bents, US 278 EBL over Skull Creek.
Photograph 40. Typical Shoreline Condition, US 278 WBL over Skull Creek.