Documente Academic
Documente Profesional
Documente Cultură
for
Small Scale Distributed Generation
(SSDG)
Wind turbine
PV module
CEBs Customer
9 t h D e ce m b e r 2 0 1 0
Foreword
The purpose of this document is to assist the public to better understand the procedure for
application, the requirements of the Grid Code, the Feed-in-Tariffs and other related issues
regarding Small Scale Distributed Generation (SSDG).
Any prospective applicant willing to take advantage of the Small Scale Distributed Generation
(SSDG) Scheme is informed that:
I.
II.
Table of Contents
The Grid Code describes the technical criteria and requirements for interconnection of Small
Scale Distributed Generators (SSDG) with CEBs low voltage network systems.
The Grid Code addresses connection of electricity producers for the following categories:
greater than 17 kW but less than or equal to 50kW (three phase output only)
The total installed capacity of SSDGs is limited to 2MW or 200 installations whichever comes
first.
The 2MW of installed capacity is categorised as follows:
1MW: Residential customers
1MW: Other customer categories
The Grid Code caters for the production of electricity from the following renewable technologies:
1. Solar Photovoltaic
2. Wind Turbine
3. Hydro
41
2. Duly filled SSDG Application Form, requested technical specifications and processing fee (see chapter 4) to be
deposited at SSDG Unit, CEB Head Office, Curepipe.
4. CEB informs applicant to publish notice in Government Gazette and in at least two newspapers.
5. Applicant publishes notice. Any person wishing to object to the application published shall send a written and
reasoned objection to the CEB with a copy thereof to the applicant within 14 days of the date of the publication.
6. CEB considers the objection.If there is no objection to the application or if there is an objection and it is rejected,
the CEB shall initiate the procedures with the Presidents office for the granting of a permit. If the application
satisfies all conditions as set down by Law, the permit will be granted.
7.
The applicant shall be given a non-transferrable permit as per the terms and conditions that will be laid down in a
Connection Agreement to be signed by the CEB and the applicant after successful testing of the latters
installation.
8.
Following the grant of the permit, the applicant pays the connection fee (Annex 3) and shall complete the
installation within a period of twelve months from the date the permit was granted; otherwise the permit shall
lapse.
9.
Upon completion of installation, applicant/Installer shall submit a duly signed certificate of installation as per Annex
5 to the CEB.
10.CEB shall inspect and test the installation for compliance with the Grid Code requirements and standards.CEB will
then issue a certificate of commissioning to the Applicant.
12.CEB/Applicant shall then cause a proclamation to be published in the Government Gazette and two newspapers
informing the public of the start of operation of the SSDG.
13.SSDG in operation.
Range
230/400 V 6 %
(1 sec) 18 kA, (50 Hz)
50 Hz
50 Hz 1.5 %
47 Hz 52 Hz
Overload.
Short circuit within the SSDG.
Earth faults in the LV grid close vicinity of the SSDG.
Over Current.
Abnormal voltages(Table 2 below)
Abnormal frequencies (Table 2 below)
Lightning.
Loss of mains.
All protection apparatus functions shall operate down to a level of 50% of the nominal DC
supply voltage of the DC system, or the system must be able to safely disconnect and
shutdown when operation conditions are outside the nominal operating DC voltage specified
in the DC system specifications.
All protective devices supplied to satisfy the CEBs requirements shall be equipped with
operation indicators. Such indicators shall be sufficient to enable the determination of which
devices caused a particular trip.
Any failure of the applicants tripping supplies, protection apparatus and circuit breaker trip
coils shall be alarmed within the applicants installation, and the applicant shall be responsible
for prompt action to be taken to remedy such failure.
2.4 Trip settings
The trip settings must comply with the values stated inTable 2.
Parameter
Symbol
Trip setting
U>>
230 V + 10 %
Clearance
time
0,2 s
Over voltage
U>
230 V + 6 %
1,5 s
Under voltage
Over frequency (b)
U<
f>
230 V 6 %
50 Hz + 2 %
1,5 s
0,5 s
Under frequency
f<
50 Hz - 6 %
0,5 s
Loss of mains
df/dt
Vector
shift
2.5 Hz / s
10 degrees
0,5 s
2.5
Network islanding
The applicant shall not supply power to the CEBs network during any outages of the system.
The SSDG may only be operated during such outages to supply the applicants own load
(isolated generation) with a visibly open tie to the CEBs network. The SSDG shall cease to
energise the CEBs network within 0.5 seconds of the formation of an island as shown in
Table 2.
2.6
Re-connection
Following a protection initiated disconnection, the SSDG is to remain disconnected from the
network until the voltage and frequency at the supply terminals has remained within the
nominal limits for at least 3 minutes. Automatic reconnection is only allowed when
disconnection was due to operating parameters being outside the normal operating range
stated in Table 2, not if disconnection was caused by malfunctioning of any devices within the
SSDG installation.
2.7
Synchronising AC generators
The SSDG shall provide and install automatic synchronizing. Check Synchronizing shall be
provided on all generator circuit breakers and any other circuit breakers, unless interlocked,
that are capable of connecting the SSDG plant to the CEBs network. Check Synchronising
Interlocks shall include a feature such that circuit breaker closure via the Check
Synchronising Interlock is not possible if the permissive closing contact is closed prior to the
circuit breaker close signal being generated.
2.8
Earthing requirements
3.0
Power quality
The total harmonic distortion will depend on the injected harmonic current and the system
impedance seen from the PCC. However, in order to facilitate the fulfilment of the
requirements by e.g. inverter manufacturers, the voltage distortion limits have been translated
into a similar requirement on current distortion.
The SSDG system output should have low current-distortion levels to ensure that no adverse
effects are caused to other equipment connected to the utility system. The SSDG system
electrical output at the PCC should comply with Clause 10 of IEEE Std. 519-1992 and should
be used to define the acceptable distortion levels for PV systems connected to a utility. The
key requirements of this clause are summarized in the following:
a. Total harmonic current distortion (Total demand distortion, TDD) shall be less than 5%
of the fundamental frequency current at rated current output.
b. Each individual harmonic shall be limited to the percentages listed in Table 3. The
limits in Table 3 are a percentage of the fundamental frequency current at rated current
output.
c. Even harmonics in these ranges shall be <25% of the odd harmonic limits listed.
Odd Harmonics
3rd -9th
11th -15th
17th -21st
23rd -33rd
Above the 33rd
Maximum Harmonic
Current Distortion
4.0%
2.0%
1.5%
0.6%
0.3%
Table 3: Distortion limits as recommended in IEEE Std. 519-1992 for six-pulse converters
3.4 Surge withstand capability
The interconnection system shall have a surge withstand capability, both oscillatory and fast
transient, in accordance with IEC 62305-3, the test levels of 1.5 kV. The design of control
systems shall meet or exceed the surge withstand capability requirements of IEEE C37.90.
3.5 Voltage and current unbalance
The connection of unbalanced loads and generation to the distribution network can result in
unbalanced currents and voltages. Generators that use 3-phase generators or inverters
which inject balanced currents into the distribution network do not increase levels of voltage
imbalance in the network. In fact, embedded generators which use 3-phase induction
generators can actually reduce voltage imbalance.
The total voltage unbalance in the grid should be smaller than 2%, where the unbalance,
Uunbalance, is defined as the maximum deviation from the average of the three-phase voltages,
Ua, Ub and Uc, divided by average of the three-phase voltages.
U unbalance
100%
The contribution from one installation may not cause an increase of the voltage unbalance of
more than 1.3%.
When considering three phase units, the contribution to the voltage unbalance can be
described as
3 I neg, seq,load U line
U unbalance
or
I neg, seq,load
S sc
3 [U unbalancein % ] U line
S sc
Where
If nothing else is stated the Ssc shall be 2.5 MVA. The demand on voltage unbalance on a
three phase load can be translated into a demand on the maximum negative sequence
current.
I max,neg, seq,load
3 1.3% 400
3.6 A
2.5
10
Connection
Single phase
Three phase
Inrush current
19 A
30 A
Where induction generators are used, as in fixed speed wind turbines, they shall be fitted with
soft starters These devices limit inrush currents to roughly the same level as the normal
rated current. This reduces the magnitude of the step voltage changes which occur on
starting.
4.0 Power factor
The power factor of the SSDG at normal operating conditions across the statutory range of
nominal voltage shall be between 0.95 leading and 0.95 lagging.
5.0 Safety, isolation and switching
5.1 Rules for working on low voltage (LV) grid
According to the CEB safety rules based on Occupational Safety and Health Act 2005, the
following rules must be respected before working on a LV grid:
a. The system must be isolated from all possible sources of supply, all switches must be
locked in visibly open positions, the system must be tested on the site of work, and the
system must be short-circuited.
b. The SSDG shall have a local means of isolation that disconnects all live conductors
including the neutral. The producer shall not energize a de-energized CEBs Power
circuit.
c. A switch shall be installed to disable the automatic or manual closing of the
interconnecting switch or breaker. This switch shall be accessible to the CEBs personnel
to obtain the necessary safety requirements when the CEBs personnel is working on
associated equipment or lines. While the CEBs personnel is working on the grid the
operation of switches shall not be possible for others than the CEB, which can be
assured by keeping the keys to lockable switches. Alternatively the CEBs personnel will
remove and keep fuses while working on lines.
d. In all instances the switch, which must be manual, must be capable of being secured in
the off isolating position. The switch must be located in an accessible position in the
producers installation.
e. Isolation for an SSDG shall be as per Figure 1 below
11
Fusible
cut-out
`
Import/Export
Meter
Visible
switch
Local
isolator
Production
Meter
Generator
L
G
N
f.
The visible switch shall be visibly marked. Also all transformers that carry SSDG installations on
the LV side shall be visibly marked. Additionally the CEBwill maintain an updated register of all
SSDGs with precise addresses, connecting points and relevant transformers.
(b)
(c)
(d)
CEB REGISTERED
The installation operating instructions must contain the manufacturers contact details e.g.
name, telephone number and web address.
5.5 Documentation
Up-to-date information must be displayed at the SSDG as follows:
(a) A circuit diagram showing the relationship between the SSDG and the CEBs fused cutout. This diagram is also required to show by whom the generator is owned and
maintained.
(b) A summary of the protections separate settings incorporated within the equipment. The
figure 3 below is an example of the type of circuit diagram that needs to be displayed.
This diagram is for illustrative purposes and not intended to be fully descriptive.
phases;
The installer must affix a label clearly indicating the next scheduled maintenance of the
installations and inform the CEB, who will add the information to the SSDG-register.
The installer must be skilled in the field of SSDG installations and possess an approved
certificate.
6.0 Metering
In order to enable correct billing of the applicant, a bidirectional meter measuring both the
import and export energy shall be in place. Billing will not be based on the gross production
of the SSDG, but on the imported and exported energy separately. For information and data
purposes, a second meter measuring the gross production of the SSDG shall be installed as
shown in Figure 1 above.
Note:Green field installations shall not be entertained in this project.
14
EN 50438
IEC 60364-5-55
IEC 60664-1
IEC 60909-1
IEC 61000-3-2
IEC 61000-3-3
IEC 61000-6-1
IEC 61000-6-3
IEC 62305-3
IEC 60364-1
IEC 60364-5-54
15
IEEE P1547
IEEE519-1992
IEEE C37.90
The total capacity of installed distributed generators (SSDG) on the relevant 22kV/0.4 kV
or 6.6kV/0.4kV transformer exceeds 25 % of the LV transformer fuse capacity.
The total capacity of installed distributed generators (SSDG) on the relevant low voltage
feeder exceeds 90 % of the feeder fuse capacity.
The capacity of SSDG at one consumer terminal exceeds the capacity of the fuse at the
existing consumer terminal.
16
17
Islanding means a condition in which a portion of the CEBs network is energised by one or
more SSDGs through their PCC(s) while electrically separated from the rest of the system;
Isolated Generation means a condition where the electrical path at the PCC is open and the
SSDG continues to energise local loads;
kV means kilovolt;
kVA means Kilovolt Ampere
kW means Kilo Watt (1,000 W = 1,000 J/s);
kWh means Kilowatt hour (1,000 watt hours);
LV means Low Voltage (Voltage below 1,000 V);
MITD means Mauritius Institute of Training and Development
MW means megawatt (1,000,000 W = 1,000,000 J/s);
Parallel operation means a condition where the SSDG is operating while connected to
CEBs network;
PCC means point of common coupling;
Point of Common Coupling (PCC) means the point at which a SSDG is connected to the
CEBs network;
Power factor Ratio means ratio of real to total apparent power (kW/kVA) expressed as a
decimal or percentage;
Producer means a producer of electricity through a SSDG installation or the owner thereof;
PV means photovoltaic;
PWM means Pulse width modulation;
RE means renewable energy;
SSDG means Small Scale Distributed Generation up to 50 kW as categorised in Schedule 2
SWC means Surge Withstand Capability, the immunity of this equipment to fast and
repetitive electrical transients;
TT system means in a TT earthing system, the protective earth connection of the consumer
is provided by a local connection to earth;
Voltage-restrained over-current relay means a protective relay in which the pickup and
over-current tripping times are affected by the voltage.
18
Table A
Feed-in tariff for 15 Wind
years.
Rs/kWh
Hydro
Rs/kWh
PV
Rs/kWh
20
15
25
Mini(2.5+ - 10 kW)
15
15
20
Small(10+ - 50 kW)
10
10
15
Table B
Greenfield tariff for Wind
15 years.
Rs/kWh
Micro (up to 2.5 kW)
17
Hydro
Rs/kWh
12.75
PV
Rs/kWh
21.25
Mini(2.5+ - 10 kW)
12.75
12.75
17
8.50
8.50
12.75
Small(10 - 50 kW)
(a) After 15 years the feed in tariff will be the marginal electricity production cost of the CEB.
(b) The above Tariffs are applicable for up to a total of 200 installations or 2MW whichever
comes first.
(c) If the annual production/consumption (from production) ratio is greater than 3, the
tariff for the following year shall be in accordance with table B
19
20
Applicant Information
For office
use only
Name
Postal address
Contact telephone number
Fax number
Tax Account Number
VAT Registration Number (if applicable)
Business Registration Number (if applicable)
Email address
Installer details *1
Installer
Accreditation/qualification
Postal address
Contact person
Telephone number
Fax number
Email Address
Project details
For office
use only
Site/project address
Telephone number (project site)
Business Partner Number
(please refer to your electricity bill or alternatively
attach a recent electricity bill)
21
Yes/No
if submitted
Comments
*1 At the start of this project until further notice, the CEB shall accept a Certificate from the supplier of the
equipment certifying that the installer is well-versed with the installation of the equipment.
Furthermore, the topics covered and the duration of the training shall be mentioned on the
Certificate.
**2
All SSDGs to submit certificate of compliance with the Electrical Equipment Safety Regulations and the
Electromagnetic Compatibility Regulations (CE Marked). PV installations to submit certificates that the
panels are to IEC 61215 for crystalline silicon and IEC 61646 for thin film silicon. Wind installations to
submit certificates that the wind turbine is as per IEC 61400-2.
22
Parameters
Requirements
Proposed
Central Inverter OR
Micro inverter
Inverter Type
Capacity of Inverter
Protection Parameters
Settings
To specify
Trip
Setting
Clearance
Time
253 V
0,2 s
243.8 V
1,5 s
216.2 V
1,5 s
51 Hz
0,5 s
47 Hz
0,5 s
2.5 Hz / s
10 degrees
0,5 s
Trip
Setting
Clearance
Time
Trip
Indication
Provided
4
5
6
7
8
Over Voltage ( )
(230 V + 10 %)
Over Voltage
(230 V + 6 %)
Under Voltage
(230 V 6 %)
b
Over Frequency ( )
(50 Hz + 2 %)
Under Frequency
(50 Hz - 6 %)
Loss of Mains
(df/dt - Vector shift)
10
Islanding Detection
Yes
11
Isolated Generation
possible
Yes / No
12
Reconnection Time
3 mins.
13
Max. DC Current
injection to grid
Rated AC output Current
per phase
Total Harmonics
Distortion (Voltage)
Total Harmonics
Distortion (Current)
Surge Withstand
Capability
Power Factor
(leading & lagging)
Will first Switch after
meter have visible
contacts ?
Will first Switch after
meter have lock facilities
in open position ?
To specify
21
Yes / No
22
Yes
23
Will Batteries be
Installed ?
14
15
16
17
18
19
20
To specify
To specify
To specify
To specify
0.95
Yes
Yes
Yes / No
Note: For No.4 and No.7 see clause 2.4 of Grid Code
Signature of applicant:
23
Applicant/installer to submit duly signed certificate (as shown below) to the CEB.
CERTIFICATE OF INSTALLATION
I hereby certify that the installation of the SSDG, situated at address [ ] for [name of Applicant]
has been done as per the requirements of the Grid Code and as per attached detailed
schematic diagram.
Name of Certified Installer: ....
Signature of Installer:..
Date:.
Name of Applicant:
Signature of Applicant:.
Date:.
24
CERTIFICATE OF COMMISSIONING
This is to certify that the SSDG installation, situated at [address] in the name of Applicant
[name] complies with the requirements of the Grid Code and it has been commissioned
on by the Central Electricity Boards SSDG Commissioning Team.
District Section
Name: ..
Signature: .
SSDG Unit
Name: ..
Signature: .
Meter Lab section
Name: ..
Signature: .
25
_____________________.
BETWEEN
AND
1.
2. And WHEREAS the Customer owns or operates a small scale distributed generation
facility (the "Facility").
3. And WHEREAS the Customer has connected or wishes to connect its facility to CEBs
distribution system and CEB has connected or has agreed to connect the facility to the
distribution system.
4. And WHEREAS the CEB has previously reviewed and accepted the Customer's
application to connect and related materials that were submitted to the CEB in accordance
with the process set out in the Grid Code (the "Code") (altogether, the "Application")
5. And WHEREAS in accordance with the Electricity Act and the Grid Code, the CEB has
agreed to offer, and the Customer has agreed to accept, distribution service in relation to
the Facility.
NOW THEREFORE in consideration of the foregoing, and of the mutual covenants,
agreements, terms and conditions herein contained, the Parties, intending to be legally
bound, hereby agree as follows:
26
1. Definitions
1.1 Words and phrases contained in this Agreement (whether capitalized or not) that are not
defined in this Agreement have the meanings given to them in the Electricity Act, the
Central Electricity Board Act with subsequent amendments, the Utility Regulatory
Authority Act and The Interpretation and General Clauses Act or the Code.
2. Type of Facility
2.1 The Facility has a name-plate rated capacity below 50 kW and applies as a Small Scale
Distributed Generator.
4. Facility Standards
4.1 The Customer shall ensure that the Facility:
(a) meets all applicable requirements of the Electricity Act; and
(b) is installed, constructed, operated and maintained in accordance with this Agreement, the
CEBs offer to connect, and meets the technical and operating requirements described
and approved in the application form.
27
Wind
PV
Hydro
installation.
The selling price for the electricity production is set out below, and is fixed for a period of
exactly XX years; with the commencement date for this XX year period being the date this
agreement comes into effect.
For facilities exporting the net electricity production of the consumer installation to the grid,
the selling price is fixed to xx MUR/kWh.
5.2 If the annual production/consumption (from production) ratio is greater than 3, the tariff for
the following year shall be in accordance with Table B in Annex 2. An addendum to this
agreement shall be signed by both parties.
5.3 An export bill with a detachable SSDG Invoice detailing the amount of energy exported to
the grid will be given to the SSDG owner. SSDG owner has to sign on the Invoice and
forward it back to the SSDG Unit at the CEB Head Office at Curepipe.
5.4 Upon receipt of the signed SSDG Invoice,a cheque will be issued and posted to the
SSDG owner.
5.5 In case the import bill(s) is not settled after notification by CEB, the service line to the
customer will be disconnected from the grid.
28
6.2 The CEB represents and warrants to the Customer as follows, and acknowledges that the
Customer is relying on the following representations and warranties without independent
inquiry in entering into this Agreement:
(a) the CEB is duly incorporated under the laws of Mauritius;
(b) the CEB has all necessary power, authority and capacity to enter into this Agreement
and to perform its obligations under this Agreement;
(c)
this Agreement constitutes a legal and binding obligation on the CEB, enforceable
against the CEB in accordance with its terms; and
(d) any individual signing this Agreement on behalf of the CEB has been duly authorized by
the CEB to sign this Agreement and has the full power and authority to bind the CEB.
29
8.1 The Customer shall not modify (increase capacity) its connection assets or the Facility
except in accordance with this section. Where the modification will not increase the
maximum electrical output of the Facility, the Customer shall give the CEB no less than
15 working days notice prior to the date on which the modification will be made. Where
the modification will increase the maximum electrical output of the Facility, the Customer
shall submit a new application for connection to the CEB. The CEB shall process that
application for connection in accordance with the Code. The Customer shall not
commence such modification until that process has been completed.
9. Indemnity
9.1 The customer shall indemnify the CEB for damages claimed by third parties where the
cause of the loss due to acts and or omission of the customer.
12.2 The CEB will make reasonable efforts to ensure that the outages referred to in section
12.1 will be of minimal duration and cause minimal inconvenience to the Customer.
30
12.3 In connection with any planned equipment outage, either Party may disconnect or
isolate, or require the disconnection or isolation of, its Facility or system (as applicable)
from the other Partys Facility or system (as applicable) so that the employees,
contractors or agents of the Party may construct, maintain, repair, replace, remove,
investigate or inspect its own Facility or system (as applicable) in accordance with the
terms of this Agreement and good utility practice.
12.4 Where practical, the Customer shall notify the CEB prior to temporarily isolating or
disconnecting the Facility from the CEBs distribution system.
14. Amendments
14.1 The Parties may by mutual agreement amend this Agreement to reflect changes that
may from time to time be made to the Code during the term of this Agreement.
14.2 Any amendment to this Agreement shall be made in writing and duly executed by both
Parties.
15.5 Termination of this Agreement for any reason shall not affect:
31
the liabilities of either Party that were incurred or arose under this Agreement prior to
the time of termination; or
that expressly apply in relation to disconnection of the Customers facilities following
termination of this Agreement.
15.6 Subject to clause 13 above, termination of this Agreement for any reason shall be
without prejudice to the right of the terminating Party to pursue all legal and equitable
remedies that may be available to it, including injunctive relief.
15.7 The rights and remedies set out in this Agreement are not intended to be exclusive but
rather are cumulative and are in addition to any other right or remedy otherwise
available to a Party at law or in equity.
15.8 Sections 15.5 to 15.7 shall survive termination of this Agreement.
__________________________________
Customer Tax Account Number
__________________________________ __________________
Customer Signature and Date
_________________________________
Name (Print)
_________________________________
Title
__________________________________ _____________________
CEB Signature and Date
_________________________________
Name (Print)
_________________________________
Title
32