Documente Academic
Documente Profesional
Documente Cultură
Vijayawada-Gundugolanu Section
FINAL FEASIBILITY REPORT
Reports code
PAGE
REV.
TABLE OF CONTENTS
Chapter
Description
Page
0.1
INTRODUCTION ......................................................................................................................... 0-1
0.1.1 Background .................................................................................................................................... 0-1
0.1.2 Contract Objectives ....................................................................................................................... 0-1
0.1.3 Inception Report ............................................................................................................................ 0-2
0.1.4 Draft Feasibility Study Report ...................................................................................................... 0-2
0.1.5 Final Feasibility Study Report ...................................................................................................... 0-2
0.1.6 Recent NHAI Initiative ................................................................................................................... 0-2
0.2
RECENT HISTORY OF THE ROAD AND RELEVANT DOCUMENTS ................................. 0-5
0.2.1 Relevant documents ..................................................................................................................... 0-5
0.2.2 Existing Situation on NH-5 ........................................................................................................... 0-6
0.2.3 Recent history ................................................................................................................................ 0-6
0.3
TRAFFIC SURVEYS AND ANALYSIS ..................................................................................... 0-6
0.3.1 Traffic Survey ................................................................................................................................. 0-6
0.3.2 Traffic Growth rates ....................................................................................................................... 0-7
0.3.3 Traffic Projection for Capacity Analysis ...................................................................................... 0-7
0.4
TOLL STRATEGY ...................................................................................................................... 0-9
0.4.1 Existing Toll plazas........................................................................................................................ 0-9
0.4.2 Traffic Projection Tollable Revenue ...................................................................................... 0-10
0.5
0.6
PUBLIC UTILITIES ................................................................................................................... 0-11
0.6.1 Electric Lines ................................................................................................................................ 0-11
0.6.2 Fibre Optic Cable ......................................................................................................................... 0-11
0.6.3 Impact............................................................................................................................................ 0-11
0.7
0.8
0.9
PAVEMENT, SOILS AND MATERIALS INVESTIGATIONS ................................................ 0-13
0.9.1 Pavement Roughness Survey ................................................................................................... 0-13
0.9.2 Pavement Condition Survey, Viziroad and Roadrunner ........................................................ 0-14
0.9.3 Soils and Materials Investigations ............................................................................................. 0-14
0.10
AFFECTED PROPERTIES AND RIGHT OF WAY REQUIREMENTS ................................ 0-14
0.10.1 Available Right of way along the project Road ..................................................................... 0-14
0.10.2 Required right of way ................................................................................................................ 0-14
0.11
STRUCTURES .......................................................................................................................... 0-15
0.11.1 Inventory of Bridges and Culverts (Existing and Proposed) ............................................... 0-15
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE
REV.
ii
0.12
FACILITIES AND SERVICES TO THE USER ....................................................................... 0-17
0.12.1 Highway Traffic Management System ................................................................................... 0-17
0.12.2 Wayside Amenities ................................................................................................................... 0-17
0.12.3 Roadside Furniture and User Facilities .................................................................................. 0-17
0.13
0.14
MAINTENANCE ........................................................................................................................ 0-18
0.14.1 Current situation ........................................................................................................................ 0-18
0.14.2 Principles .................................................................................................................................... 0-19
0.14.3 Additional Requirements that Pertain to a Toll Road ........................................................... 0-19
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE
REV.
iii
LIST OF TABLES
Chapter
Description
Page
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
EXECUTIVE SUMMARY
0.1
INTRODUCTION
0.1.1
Background
Reports code
PAGE
REV.
0-1
The Government of India has decided to upgrade 6500 km length of existing 4-lane
divided highways into Six-Lane divided carriageway under Phase-V of National Highway
Development project (NHDP). The Phase-V of NHDP is to be executed as BOT (Toll)
Project through Public Private Partnership (PPP) on Design-Build-Finance-Operate
(DBFO) pattern. The National Highways Authority of India (NHAI) has appointed BCEOM
Societe Francaise dIngenierie, France in Association with BCEOM India Pvt. Limited,
presently known as Egis India Consulting Engineers Pvt Ltd., as consultants to carry out
Feasibility study for upgrading the existing four lane highway to Six-Lane access control
highway from Chilakaluripet-Eluru-Rajahmundry section of NH-5 under DBFO pattern, for
which the consultants have completed the study and submitted the final feasibility report.
The new Six-Lane facility would be an access controlled highway through provision of
service roads, pedestrian and cattle underpass, vehicular underpasses, grade separators,
exit/entry ramps etc. The objective is to enhance operational efficiency of highway and
safety of the traffic & the road users.
The stretch from Vijayawada to Chilakalurpet has been prioritised by NHAI for which
tenders have been called and the work has been awarded on DBFOT pattern. The
feasibility report has been reframed for the balance stretch from Vijayawada to
Rajahmundry.
Subsequently consultants were instructed to carryout feasibility study for providing
bypass for Vijayawada and Hanuman Junction city and a letter to this effect (Ref:
NHAI/CK1/PHASE-V/DPR/12/92 dated 21.05.10) has been issued to the Consultants by
NHAI to initiate the studies as an additional work. The consultant has submitted draft
feasibility report for Vijayawada bypass.
The present report has been prepared combining the earlier feasibility report and the
feasibility studies carried on the bypasses as draft combined Feasibility Report for
103.590Kms length of a section of NH-5 from Vijayawada Bypass (Km 0+000 to Km
47+880), Vijayawada (Km 1076+480) to Hanuman Junction (Km 1060+800), Hanuman
Junction Bypass (Km 0+000 to Km 6+720) and Hanuman Junction (Km 1055+650) to
Gundugolanu (Km 1022+480) in the state of Andhra Pradesh. The project highway
location map showing the existing road network from Vijayawada to Gundugolanu is
presented in following page.
0.1.2
Contract Objectives
The intention of this specific consultancy project is to study and report on the feasibility of
retrofitting the existing NH-5 from Vijayawada-Eluru-Gundugolanu from its existing
situation [a bypasses and 4-lane highway of about 103.580 Km in length] to a 4-lane and
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE
REV.
0-2
6-lane highway. The objectives of the consultancy services are to prepare a proposal to
retrofit a six-lane cross-section on to the existing 4-lane highway in a manner which
ensures:
Enhanced safety of the traffic, the road users and the people living close to the
highway.
Minimal adverse impact on the road users and the local population due to
construction. Feasible and constructible options for the project with least cost options.
0.1.3
Inception Report
The Inception Report was the first significant report to be submitted under this Study as
per Terms of Requirements (TOR), and was submitted in the month of December 2006
(Vijayawada-Gundugolanu section), July 2010 (Vijayawada Bypass) and August 2010
(Hanuman Junction Bypass). The report focused on:
0.1.4
0.1.5
0.1.6
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE
REV.
0-3
existence. Also keeping in view the present and future projected traffic, four and six laning
is proposed with minimum length of service roads.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE
REV.
0-4
Project Location Map, Vijayawada Bypass (47.88 Km), Vijayawada-Gundugolanu section (48.99Km) and Hanuman Junction Bypass (Km 6.72)
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
DTI 61 847
B03
0.2
0.2.1
Relevant documents
PAGE REV.
0-5
The Consultant has collected as-built drawings (both in electronic form and hard copy),
DPR & other secondary relevant documents (in hardcopy) from NHAI.
The chainages on the old NH-5 followed a different chainage system. Old NH-5 had
different sections, i.e., Chennai-Vijayawada, Vijayawada-Visakhapatnam etc. Each
section had different set of chainages. The NHAI has issued a circular stating that new
chainage for NH-5 will start from the Baharagora (near Kolkata) to Chennai under Golden
Quadrilateral project.
Under this circular, the chainage from Kolkata to Chennai was changed, and the new
system of chainage has been adopted. The correlation with the new chainages and old
chainages were developed and these chainage equations were incorporated in the asbuilt Drawings. Chainage equations were developed due to the construction of new
bypasses along the project highway. For easy reference the chainage equations and the
correlation between the old and as-built chainages along the project highway is given in
Table 0.1 below.
Table 0.1: Chainage Equations
To
Length (km)
From
Km 0+000
(Existing NH-5 Chainage
Km 47+880
(Existing NH-5
Km 422+800,New Ch
1112+044)
Chainage Km
1076+480)
Km 1076+480
Km 1060+800
Km 0+000
(Existing NH-5 Chainage
Km 6+720
(Existing NH-5
Km 1060+800)
Chainage Km
1055+650)
Km 1055+650
Km 1022+480
47.88
15.68
6.72
33.17
Section
Gannavaram-Hanuman
Junction (Existing NH-5)
Proposed Hanuman Junction
Bypass
Hanuman JunctionGundugolanu (Existing NH-5)
103.59
The old 2-Lane NH-5 has been upgraded to 4-Lane divided carriageway in the year of
1997-2003 under Golden quadrilateral project. The length of the project works out to be
103.590 Km as per the as-built and the DPR chainages.
An inventory was carried out by hand held GPS to understand the chainage variation in
each kilometre. The chainage is increasing from Vijayawada to Gundugolanu as per the
as-built chainage of NH-5 (from Kolkata to Chennai). The project starts at Km 0+000 to
Km 47+88 (Vijayawada Bypass), Km 1076+480 to Km 1060+800 (Gannavaram to
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
DTI 61 847
B03
PAGE REV.
0-6
0.2.3
Recent history
The existing road before taking up 4-laning works consist of 2-lane carriageway of width
varying from 6.5 to 7m except for some isolated built-up section where the carriageway
width varies from 10 to 14m. The existing pavement is of flexible type with thin bituminous
surfacing at the top developed since ages.
0.3
0.3.1
Traffic Survey
The traffic surveys conducted to study the project influence area and to meet the
objectives of the study & TOR requirements. The surveys have been conducted in the
month of December 2006 and January 2007 (for Vijayawada-Gundugolanu section). The
main traffic surveys are as below:
The project highway has been divided into following three traffic homogeneous sections:
The salient findings of the traffic volume count surveys are as below:
Average Daily Traffic (ADT) in base year 2010 minimum is 21714 (Tollable PCUs)
and 25005 total PCUs in Vijayawada Bypass to Gundugolanu section.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
0.3.2
Reports code
DTI 61 847
B03
PAGE REV.
0-7
6.6
MAV
up to
6 Axle
6.6
MAV
>6
Axles
6.6
6.6
6.6
6.6
6.6
6.1
6.1
6.1
6.1
6.1
5.0
5.0
5.0
5.0
5.0
Period
Two
Wheeler
Car
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
2011-15
8.7
7.0
5.5
5.5
6.6
6.6
2016-20
7.1
6.5
5.5
5.5
6.6
6.6
2021-25
5.3
6.0
5.0
5.0
6.1
>2025
5.3
5.0
5.0
5.0
5.0
0.3.3
HCM/
EME
6.6
Year
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV
up to 6
Axle
MAV
>6
Axles
HCM/
EME
Total
PCUs
2010
353
328
1,103
1,287
147
8,677
2015
453
418
1,408
1,643
188
11,079
2020
579
533
1,798
2,097
239
14,139
2025
739
680
2,294
2,676
306
18,046
2030
944
868
2,927
3,417
391
23,038
2035
1,205
1,108
3,735
4,361
501
29,410
2040
1,537
1,413
4,767
5,565
639
37,528
2045
1,962
1,804
6,084
7,102
816
47,898
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV
up to 6
Axle
MAV
>6
Axles
HCM/
EME
Total
PCUs
2010
620
247
1,739
811
162
9,370
2015
792
315
2,220
1,036
207
11,964
2020
1,012
402
2,834
1,322
264
15,271
2025
1,293
512
3,617
1,687
337
19,490
2030
1,651
654
4,616
2,154
432
24,886
2035
2,108
835
5,891
2,750
552
31,768
2040
2,690
1,066
7,519
3,510
705
40,549
2045
3,434
1,361
9,597
4,480
900
51,757
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE
REV.
0-8
Table 0.5: Traffic Projections for the portion from Vijayawada Bypass to Gundugolanu
LCV
2
Axle
Truck
3 Axle
Truck
MAV
up to
6
Axle
MAV
>6
Axles
HCM/
EME
Two
Wheeler
Auto
Rickshaw
1,167
568
1,667
2,521
377
2,873
1,489
725
2,128
3,217
482
3,667
91
1,899
925
2,715
4,106
615
6,270
117
2,424
1,181
3,466
5,241
785
2030
8,003
149
3,093
1,507
4,424
6,689
1,001
2035
10,213
190
3,948
1,923
5,646
8,537
2040
13,035
244
5,039
2,454
7,205
2045
16,637
311
6,432
3,132
9,195
Year
Car/
Jeep/
Van
Mini
Bus
Bus
2010
3,016
56
2015
3,849
71
2020
4,912
2025
Tempo
Agri
Tractor
Agri
Tractor
&
Trailor
Animal
Hand
drawn
Cycle
Cycle
Rickshaw
Others
Tollable
Traffic
PUCs
Total
PCUs
663
610
17
64
339
24
21,714
25,005
846
779
22
82
434
29
27,714
31,901
4,680
1,079
994
27
105
554
38
35,364
40,694
5,973
1,379
1,269
34
134
708
48
45,143
51,932
7,624
1,760
1,619
44
171
903
62
57,610
66,263
1,278
9,729
2,246
2,066
56
218
1,152
79
73,527
84,553
10,896
1,631
12,416
2,867
2,637
71
278
1,472
101
93,842
107,900
13,907
2,082
15,847
3,659
3,365
91
355
1,878
129
119,773
137,702
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE REV.
0-9
IRC: 64 - 1990 stipulates a design service volume of 40,000 PCU per day for a four lane
divided carriageway with paved shoulders at level of service B and plain terrain. This can
be further increased upto 60,000 PCUs by adopting LOS C.
The Vijayawada bypass crosses 40,000 PCUs in the year 2042 and 2040 for the sections
1 & 2 respectively. Hence it may be prudent to consider them for four laning only.
The section between Vijayawada bypass to Gundugolanu reaches 40,000 PCUs in the
year 2020 and 60,000 PCUs in the year 2028. Hence it is necessary to consider it for 6
laning now itself.
0.4
TOLL STRATEGY
0.4.1
Chainage, km
416+800
1072+230
1050+780
Tolling Section
Length, km
Km 355+000 - Km
434+150
Km 1100+680 - Km
1061+580
Km 1061+580 km
1022+480
81.6
39.1
39.1
Considering the development of the Vijayawada bypass, it is proposed to have total three
toll plaza two on the Vijayawada Bypass, one on section 1, one on section 2 and retaining
the existing toll plaza at Kalaparru.
The details are provided at Table 0.8 below :
Table 0.7: Proposed Tolling Sections
S.No.
Tolling Section
Remarks
Km 11+500
Of proposed Vijayawad
Bypass
Kaza to Gollapudi
Km 0 to Km 18+650
(15.25 km of NH-5 is
adjusted in the toll rate )
Km 35+000
Of proposed Vijayawada
Bypass
Gollapudi Chinnaavutapalli
Km 18+650 to Km 47+880
(24.2 km of NH-5 is
adjusted in the toll rate)
Km 1050+780
Of Existing Vijayawada
Gundugolanu section
Kanakadurga Varadhi
Gundugolanu
Km 1076+480 to Km
1022+480
Includes Hanuman
Junction (6.7 km) Bypass
As per the toll policy all the structures and bypasses costing more than Rs 10 crores need
to be charged separately at the toll rates specified in the policy. Since cost of the two
sections of Vijayawada bypass and the Hanuman Junction bypass are more than Rs 10
Crores each of them will be charged separately.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
PAGE REV.
Reports code
0-10
Section 2
Section 3
Daily
Yearly
Daily
Yearly
Daily
Yearly
Daily
Yearly
Rs '000s
Rs Millions
Rs '000s
Rs Millions
Rs '000s
Rs Millions
Rs '000s
Rs Millions
2015-16
175.60
64.27
271.55
99.39
2,739.59
1,002.69
3,186.74
1,166.35
2020-21
298.24
108.86
452.32
165.10
4,474.53
1,633.20
5,225.09
1,907.16
2025-26
476.98
174.10
720.25
262.89
7,308.71
2,667.68
8,505.94
3,104.67
2030-31
796.55
290.74
1,191.75
434.99
11,972.20
4,369.85
13,960.50
5,095.58
2035-36
1,311.03
479.84
1,958.54
716.83
19,767.43
7,234.88
23,037.01
8,431.54
2040-41
2,150.17
784.81
3,283.45
1,198.46
32,802.02
11,972.73
38,235.64
13,956.00
Year
0.5
There is no access control [except where some frontage roads are provided,
generally in towns] the road has far too many access points
The road mixes short distance [very local including animals herded on the road in
more rural areas] and long distance traffic so there are many movements [entering
the road, U turning in the medians, driving the wrong way down the road, grazing in
the median] which are incompatible with the high speed long distance facility this road
is supposed to provide.
The main junctions [mostly at grade] have poor advance signing, and should be
grade separated.
Little thought has been given in villages and towns crossed as to how the local
population crosses the main National Highway [other than by praying first then
running very quickly].
Guardrail [and barriers at approach to some bridges] is lacking in places, and hanging
loose in others.
In order for the proposed project and facilities to bring an improvement the following
principles should be followed:
A proper access control system should be put in place. This includes an access
system (service roads providing access to the abutting properties and possibly to the
local traffic, safe and comfortable grade separated crossings for motorised as well as
non motorised users, ramps and interchanges) and as a general principle features
preventing access (fences, curbs and barriers).
A treatment of the median in order to prevent front collision and wrong side driving as
well as limit head light glare
A proper signage in order to deliver adequate information to the user. This should
encompass the direction signs, as well as their coordination with markings. Markings
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE REV.
0-11
should be treated with sufficient care and maintained with a high level of performance
as they contribute significantly to improved traffic safety.
Removable median barriers at every 2Km will be provided along the Project highway
as specified in the Manual for allowing traffic on to the other side of the highway in
case of lane closures.
The general objectives are for the concessionaire to make the main NH-5 road [and the
service roads] as safe as possible for all users. The concessionaire shall follow [and shall
also show it has followed] all relevant Indian publications on road safety, especially The
Manual for Safety in Road Design (A guide for Highway Engineers) prepared in
September 1998 for MOST.
A formalised safety audit procedure must be followed by the concessionaire during the
detailed design [and during the Construction and post construction periods].
0.6
PUBLIC UTILITIES
All most all kinds of utility services that can be located along roads are present in the
entire project road stretch including crossings. These services were mostly re-located in
the recent 4-laning civil works contracts, however are still present in roadway itself. Some
services are just located at the edge of the shoulder and some at the toe.
0.6.1
Electric Lines
The electric poles are very close at some locations and generally located on the edge of
the right of way. The electric lines are close to project highway in the town/village areas
and it is generally within 20/25 m from the median centreline in the rural sections. The
electric transformer is also present at many locations along the highways. The electric
lines cross the project highway, and also pylons are located very close to the project
highway in the Vijayawada and Hanuman Junction city limits. The electrical poles and
pylons which are very close to the Project Highway, needs to be relocated during the
implementation of 6-lanes with service roads. The proposed Vijayawada Bypass crosses
the pylons at 14 locations nearly.
0.6.2
0.6.3
Impact
An important part of the later detailed design will be to fully determine impacts and
design, in conjunction with utility companies, the diversions or strengthening or crossing
(via pipe crossings to be provided under the roadwork contract) locations and works. It is
also very important to note that in urban road projects service relocations are an
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE REV.
0-12
important part of the preplanning, both on the actual work [definition and phasing] and
especially on the material procurement side, as in simplistic terms one cannot relocate
power lines, telephone lines and waterlines without at least a reasonable amount of
cable, pipes and fittings already in stock and immediately available.
It should be noted that there may be additional land requirements identified in the final
design as the available ROW is insufficient to accommodate the moving of utility services
and the tree planting proposals.
0.7
S.
No
Chainage Location
LHS
(New)
1040+481
1034+907
RHS
(New)
LHS
(New)
RHS
(New)
15+970
(Krishna
River)
New
43+250
New
Span
Length
(m)
Width
of
CW(m)
Deck
Width(m)
Type of
Superstructure
24.53+
36.38+
37.15+
36.85+
24.68
159.59
7.5
9.91
4 x 32.30
129.2
7.5
9.91
PSC T-Beam
12
12
Vijayawada Bypass
1 x 14
(VUP)+
101 x 30+
3144
7.5
1 x40+
2 x30
2 x 30
60
7.5
The discharge from upstream all along the project highway is duly accounted for, in
designing the cross drainage works including culverts during the 4 lane implementation.
The concessionaire shall examine in detail all the problems on existing cross-drainage
culverts and bridges and propose new ones with adequate waterway, vertical clearance
and width suiting to the 6-lane facility.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE REV.
0-13
Earthen longitudinal drains at isolated locations are present on both sides at the end of
ROW and have adequate section to cater to the requirements for efficient drainage and
suitably connected to proper outfall in the streams. These existing drains have to be
widened and have to be re-built with proper outfalls.
The lined drains provided in the built-up areas have a width varying from 1.2 to 2m and a
depth of 1m covered with concrete blocks. Generally all concrete drains in the project
road are in good condition. Further widening of road will require the shifting of these
concrete drains to the extreme edge of the new carriage way.
The risk of erosion of embankment, side slopes and surface drainage on high
embankments shall be tackled by providing kerb and channel longitudinal drains at the
end of the paved shoulder and chutes at suitable intervals along the embankment.
Embankment slopes are proposed to be pitched as necessary to prevent rain cuts and
erosion.
0.8
DESIGN STANDARDS
Design standards developed under this study are meant to supplement the separate
NHAI Manual for 4 and 6 Laning, if any contradiction exist the requirements in the Manual
take precedence. It should be noted that the geometric standards [and design speeds
following] pertain to the mainline. Service roads can [generally should] be designed for
significantly lower design speeds and also to flood more often than the mainline [i.e. in
places they can be at a lower level than the mainline, but not so low that they are very
frequently flooded, since they have to be maintained by the concessionaire].
The terrain in the project stretch is plain in general with the cross slope of the country
remaining very much less than 10%.
As per NHAI guidelines in general, existing Right of Way (ROW) of 60 m is normally
considered in bypass areas. However the project is a retrofit of a 6 laning scheme onto
the existing situation along with the proposed bypasses and as already identified
elsewhere in this report significant land acquisition will be needed. It is likely that where
land has to be acquired each section will have to be decided on a case by case basis
[and will also involve consideration of adjoining constraints]. At many isolated locations
like junctions, rest areas, toll plazas, way side amenities, entry/exit facility etc. more land
will be required.
Many median openings currently exist, and generally the intent [on safety/access control
grounds] is to close as many as possible. As per the guidelines given in the 6-laning
Manual, removable median openings will be provided at every 2 kilometer interval.
0.9
0.9.1
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE REV.
0-14
0.9.3
Visual road and pavement condition survey - including cracks, rutting, edge-break,
ravelling, patching, apparent pavement failure, drainage structures etc.;
0.10
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE REV.
0-15
(Hanuman Junction Bypass) which includes provision of shoulders and wider service road
to cater the mixed local traffic. An additional land is required at junctions, entry/exit
facilities, interchange for the provision of cross structures and for wayside amenities and
drainage channel relocation. Based on typical cross sections. and these assumptions, the
land acquisition requirement for the recommended is assessed and summarised in the
following tables.
Table 0.10: Preliminary Cost Estimates and R&R Budget
Sl No
1
Item
Quantity
Rate (Rs)
Amount (Rs )
1272.747
1200000
1527296400
5510
565013473
2960
84306957
1400
11702474
400
1020060
120000
2400000
Units
Acres
Lumpsum
Total (1+2+3+4)
175339149
2367078513
Average
Width
required
(m)
0.11 STRUCTURES
0.11.1 Inventory of Bridges and Culverts (Existing and Proposed)
There are 4 Major Bridges (Total length > 60.0 m), 46 Minor Bridges (6.0 m < Total
Length <60.0m), 5 ROBs, 6 flyovers, 33 underpasses/ cattle crossings and 238 culverts
on the project road & 109 on service road. At few locations culverts have been provided
for service roads. All the numbers of structures mentioned above are for individual 2/3
lane carriageways on the existing NH.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
60.0
80.0
Reports code
PAGE REV.
0
0-16
Major bridges*
5
33
Culverts*
347
Description
Retained without widening
Major Bridges -2 Nos.
Widened to 3 Lane
Additional 2 Lane Bridge
Retained
Minor Bridges- 17 Nos.
Replace with new 3 Lane bridge
Widened to 3 Lane
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Nos.
2
1
16
17
Description
Retained without widening
Rail Over Bridge (ROB)-2 Nos.
Replace with new 3 Lane ROB
Additional 2 Lane ROB
Retained without widening
Underpasses- 10 Nos.
Widened to 3 Lane
Replace with new 3 Lane
Widened to 3 Lane
Culverts
Replace with new 3 Lane culvert
Retained
S. No.
3
0.12
Reports code
PAGE REV.
0
0-17
Nos.
2
10
171
-
10
171
Bus Shelters
Highway lighting
Safety Barrier
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
PAGE REV.
0-18
Service Roads: Provide 5.5m service roads on both sides about 71.268 kilometers,
the service roads will be discontinued at locations of major bridges, ROBs and Toll
plazas.
Intersections:
Improvement of 5 minor intersections on existing NH.
Entry/Exit facility:
The entry/ exit facility has been proposed for safe merging/exit of through traffic and
the slow/local traffic
Lay Bays and Amenities: Provide 8 bus bays with shelter on service road wherever
applicable, 3 Comprehensive Wayside Amenities including truck lay bays.
INR 1401 Crores i.e. Rs. 13.52 Crores/km for Vijayawada Gundugolanu
section including Vijayawada and Hanuman Junction Bypasses.
0.14 MAINTENANCE
0.14.1 Current situation
Our current observations are that:
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports code
Virtually no lighting placed, except some high mast at toll plaza locations
PAGE REV.
0-19
0.14.2 Principles
Maintenance [if done fully and properly] generally [when averaged out] often represents
about 2.5% [annually, including labour, and all necessary works] of the value of the roads
and bridges. Usually the costs follow a rough cycle, annually lower when no major
pavement or reconstruction works are done on the highway (say years 1 to 4, 6 to 9 etc.
when major overlays are done every 5 years or so), then with major increases every time
a pavement overlay is carried out (say every 5 years or so). However this is not the only
cost cycle, as over time one also has to consider maintenance [and eventual
replacement] of electrical [including lighting], toll collection, and communication
equipment, and then there are other cost cycles, some completely unpredictable like
weather damage, emergencies and the like, and some more predictable like replacement
of road markings. Additionally with a road of this length [103.580km] the cycle is not
necessarily the same on every kilometer section, so figures tend to get more averaged
[and also depend to some extent on the implementation schedule of the 6 laning], rather
than being relatively low 4 years out of 5 then with sharp peaks every 5 years or so. The
concessionaire will need to set up [and thereafter implement to an acceptable standard] a
Maintenance Plan that carries out the corresponding activities.
0.14.3 Additional Requirements that Pertain to a Toll Road
Once upgraded NH-5 will comprise:
Service Roads
Roadside furniture
Special maintenance plans will be necessary for the toll plazas and associated
equipment and the Highway Traffic Management System.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Reports Code
Page
Rev.
1-1
Chapter 1: Contents
CHAPTER 1: CONTENTS .................................................................................................................... 1
1.
INTRODUCTION ...................................................................................................................... 2
1.1
GENERAL .................................................................................................................................... 2
1.1.1 Background ........................................................................................................................... 2
1.1.2 Current Situation .................................................................................................................... 2
1.2
1.3
1.4
1.5
CONTENTS OF THIS REPORT......................................................................................................... 7
1.5.1 Combined Final Feasibility Report ........................................................................................ 7
1.5.2 Contents of this Report ......................................................................................................... 7
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
1-2
1.
INTRODUCTION
1.1
GENERAL
1.1.1 Background
The National Highways Authority of India (NHAI) has been entrusted with the development,
maintenance and management of such of the National Highways as entrusted to it by the
Government. Under NHDP Phase-V Programme, the Government has decided to convert some of
the existing four lane highways into six lane highways. These projects are to be executed by private
entrepreneurs as DBFO Projects. NHAI invited consultancy services for the Preparation of Feasibility
for the selected sections of National Highways.
The design and construction is to be performed in two steps namely the preparation of feasibilitycum-preliminary design by a technical consultant followed by the detailed design and construction by
a private concessionaire as DBFO project for each highway in the programme.
This report covers the feasibility-cum preliminary design work by the Consultant for an approximately
103.58 km section of NH5. This work was carried out over the period from November 2006 to [and
including] early March 2007 (Vijayawada-Gundugolanu section), June 2010 (Vijayawada Bypass), &
July 2010 (Hanuman Junction Bypass). The project location map is presented in the following pages
through Figure 1 to Figure 2.
1.1.2
Current Situation
This section of NH-5 was widened over the period 2001 to 2006 from 2 lanes to 4 lanes. Chapter 2
and 3 of this report gives more details on the recent historical aspects, and the current situation of
this road. The majority of the widening was done on line, and also some new bypasses were
constructed. The service roads exist for some length in major City and urban settlements.
Vijayawada City falls between Km 1100+694 and Km 1090+000 on NH-5 and where the project
highway passes through Tadepalli, Benz circle of Vijayawada City. The widening to six laning along
existing alignment would involve significant land acquisition, and demolition of existing properties
along the highway. Moreover, the presence of existing two 2-lane bridges on river Krishna adds to
technical complexity in widening. Detailed project Report (DPR) has been prepared by Mott
MacDonald Consulting Engineers to provide a link between NH-5 and NH-9, and bypass for
Vijayawada on NH-5 is not included in this DPR. There were many representations in the past from
local public to provide a bypass for Vijayawada. Keeping in view all the representations, NHAI has
asked the consultants to study and prepare a Feasibility Report for providing bypass for Vijayawada
City on NH - 5.
Major settlements/ towns along the project road are: Vijayawada, Gannavaram (houses airport for
Vijayawada), Hanuman Junction and Eluru. One Bypass exists along the corridor, listed bellow
Sl. No
1
Name of Bypass
Eluru Bypass
Total length of bypasses (km)
Location
North of town
Length
17 km
Remark
New Alignment
17 km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
1-3
There are two toll plazas located along the corridor [albeit these are temporary affairs the
permanent plazas are not yet constructed]. The toll plaza locations and the associated road sections
are presented in the table below:
S. No.
Location
Section length
(km)
39.1
39.1
Total length #
Toll Section
Vijayawada Hanuman Jn.
Hanuman Jn.
Eluru/Gundugolanu
78.2 km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
1-4
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
1-5
CONTRACT OBJECTIVES
The intention of this specific consultancy project is to look and report on the feasibility of retrofitting
the existing NH-5 from Vijayawada-Eluru-Gundlagolanu in the State of Andhra Pradesh from its
existing situation [a 4 lane highway of about 49.00 km in length] to a 6-lane highway of about 103.58
km in length except Proposed Vijayawada Bypass which is a 4 lane highway with service roads at
approaches and Proposed Hanuman Junction Bypass which is a 6 lane highway with service roads
at approaches.
Specifically the objectives of the consultancy services are to prepare a proposal to retrofit a six-lane
cross-section on to the existing 4-lane highway, providing 4- lane Bypass for Vijayawada City and
providing 6 lane Bypass for Hanuman Junction on NH-5 in a manner which ensures:
Enhanced safety of the traffic, the road users and the people living close to the highway.
Minimal adverse impact on the road users and the local population due to construction.
Feasible and constructible options for the project with least cost options.
Feasible and constructible options for the project with least cost options.
Avoid heavy Traffic going through Vijayawada town thus minimising the impact on local
population.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
1.3
Reports Code
Page
Rev.
1-6
The highway is safe for the road users and the public living adjacent to the highway
Facilities created already during 4- laning are utilized to the maximum extent
Within the given constraints, the solutions are sound, economical, constructible, and
manageable.
Estimation and analysis of transport demand based on the available data with
consultants
Alternate alignment studies and finalization of bypass alignment
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
1-7
Detailed topographical survey covering all physical features within proposed ROW
(60/80m)
Preliminary design for costing purpose of highway and structures
1.5
1.5.1
This third report, in agreement with the reporting requirements, submitted by the Consultant is this
Final Feasibility Report. This report contain, inter alia, the scheme and lay out of the development of
the highway and the project facilities, preliminary design and costing for discussion with NHAI.
1.5.2
Section 1: Introduction
Section 10: Design Standards [including geometric design and regulation of access]
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
10-1
10.1
INTRODUCTION ............................................................................................................................ 2
10.2
10.3
10.4
10.5
SUPERELEVATION ........................................................................................................................ 3
10.6
10.7
10.8
10.9
10.10
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Reports Code
Page
Rev.
10-2
10.
10.1
INTRODUCTION
The design standards for the project highway has been adopted after reviewing the relevant latest
Indian Roads Congress Codes (IRC), Manual of Specifications and Standards for Six Laning of
National Highways Through Public Private Partnership published by Ministry of Shipping, Road
Transport & Highways and international standards such as AASHTO etc.
The various design elements and factors, which govern the functioning of any highway, can be
broadly grouped under the following:
Horizontal Alignment
Vertical Alignment
Subsurface drainage
The basic design philosophy is based on the consideration of providing suitable alignment, crosssectional layout, geometrics, safety and access control to cater to the fast and uninterrupted
movement of through traffic. It is also based on the consideration that the widening proposals should
be to the extent feasible within the present Right of Way (ROW) or with minimum land acquisition.
10.2
The design speed is the guiding criteria for correlating features such as sight distance, curvature and
super elevation upon which the safe operation of the vehicle depends. The design speed
recommended for different terrain classification system for the project highway is as follows:
Terrain
Design Speed(kmph)
Ruling
Minimum
0-10
100
80
Rolling
>10 - 25
80
65
Mountainous
>25 - 60
50
40
> 60
40
30
Plain
Steep
The terrain in the project stretch is virtually all plain with the general cross slope of the country
remaining very much less than 10%.
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
10.3
Reports Code
Page
Rev.
10-3
As per NHAI guidelines for Vijayawada-Gundugolanu section, the available Right of Way (ROW)
along the newly constructed bypass during four lane construction is 60m. The available ROW in the
some villages is varying from 20m to 40m. However the project is a retrofitting of a 6 laning scheme
onto the existing situation which will require significant land take. At many isolated locations more
land will be required to suitably accommodate the proposed underpasses, entry/exit ramps, rest
areas, toll plazas and way side amenities etc.
As per NHAI guidelines for Vijayawada/Hanuman Junction bypasses, proposed right of way for the
new bypass alignments is 60/80m. Consultants want to propose a right of way width of 80m, to
accommodate service roads and also to locate various utilities and also to have provision for the
future widening, if required.
10.4
The details of cross sectional elements adopted for the project road are as per 4 Laning and 6 Laning
Manual. In straight reaches, a camber of the same value as the existing 4 lane pavement is to be
provided. The adopted cross sectional elements are presented in the following sections.
10.5
SUPERELEVATION
Super elevation is provided for all the horizontal curves with radius less than 2000 m in order to
counteract the effect of centrifugal force. As per IRC: 38 -1988, super elevation to fully counteract the
centrifugal force for 75% of the design speed of 100 km/h neglecting the lateral friction developed will
be adopted in design.
The super elevation e has been calculated from the formula.
2
e = (V) / 225 R
Where V is the design speed in kmph( i.e., 100 Kmph) and
R is the radius of the curve in metres.
The maximum super elevation is limited to 7% for Vijayawad-Gundugolanu section and Hanuman
Junction bypass and 5% for Vijayawada bypass as per codal requirement. It must be noted that the
superelevation to be adopted should generally be exactly the one already constructed under the
previous 4 laning,
10.6
HORIZONTAL ALIGNMENT
The tangent sections, circular curve and transition curve elements are the major component of
Horizontal alignment. A balanced control on the above elements is required to provide safe and
continuous flow of vehicles under the general traffic conditions. The horizontal circular curve radius of
360m or more is required to meet the requirement of the design speed of 100kmph.
Transition curves in the form of spiral between the tangent sections and circular curve element are
designed to satisfy the requirements of allowable rate of change in experiencing centrifugal
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Reports Code
Page
Rev.
10-4
acceleration by the user and attaining super-elevation on carriageway for the circular curve. For the
horizontal curves with radius of curvature less than 2000 m, transition curves are generally provided
on both ends of circular curve. The minimum transition lengths suggested in the IRC guideline are
indicated in the in the following sections.
10.7
VERTICAL ALIGNMENT
There are two major elements in vertical geometry of an alignment i.e. longitudinal gradient and
vertical curve. The following gradients for Plain / Rolling terrain conditions are given below.
Gradients for Different Terrain
Classification of Gradient
Plain / Rolling
Ruling gradient
3.3% (1 in 30.0)
Limiting gradient
5% (1 in 20.0)
Exceptional gradient
6% (1 in 15.0)
Gradients up to the ruling gradient would be used as a matter of course in design. The limiting
gradients would be used where topography of a place compels this course or where the adoption of
gentler gradients would add enormously to the cost. Further, the steepest gradient or exceptional
gradient is meant to be adopted only in very difficult situations and for short lengths not exceeding
100m at a stretch.
Due to changes in grade in the vertical alignment of the highway vertical curves at the interchanges
and at locations where underpasses are to be inserted different grades will be provided in the design
so as to smoothen the vertical profile resulting in easing off of the changes in the gradients for the
fast moving vehicles. Both summit curves and valley curves will be introduced as per IRC guidelines.
The length of summit curve and valley curves (L) is guided by S, the sight distance and the deviation
angle (N).
(a) For Summit Curves :
2
i) When the length of the curve is greater than the sight distance
L = NS / 4.4
ii) When the length of the curve is less than the sight distance
L = 2 S 4.4 / N
when the length of curve is greater than the stopping sight distance
2
L = NS / (1.5 + 0.035 S)
ii) when the length of curve is less than the stopping sight distance
L = 2 S (1.5 + 0.035 S) / N
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
10.8
Reports Code
Page
Rev.
10-5
Lengths of speed change lanes for interchanges recommended are given below. Maximum vertical
gradient of 3.3 % generally would be adopted in design.
Design
Speed (Kph)
Radius
(m)
Stopping Sight
Distance (m)
Acceleration
Deceleration
Lane (m)
Lane (m)
Ramp
80
230
130
300
130
Loop
60
130
80
400
150
Description
10.9
SUBSURFACE DRAINAGE
Adequate drainage is a primary requirement for maintaining the structural condition and functional
effect of a good pavements structure including sub grade. Pavement must be protected from any
ingress of water. Otherwise over a period of time it many weaken the sub grade by saturating it and
cause distress in the pavement structure. The GSB layer shall extend through the full formation width
and shall act as the drainage layer for effective subsurface drainage.
Table 10.1 : Design Parameters for Vijayawada-Gundugolanu section and Hanuman Junction
Bypass [100 Kmph Design Speed]
S. No.
Description
Design Speed
Lane width
Details
100 Kmph
3.5 m
Raised Median
Rural
4.5m
Urban
1.2m
0.25 m
3-Lane carriageway
10.5m
Paved Shoulder
1.5m
7
8
9
Earthen Shoulder
Camber
Rural
2.0m
Urban
1.5m
2.50%
Earthen shoulder
3.00%
10
5.5 m
11
1.5m
12
1.5m
Rural
2.0m
13
Utility Corridor
14
Maximum superelevation
5.00%
15
180 m
16
360 m
17
360 m
18
2000 m
Urban
1.5m
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Reports Code
Page
Rev.
10-6
S. No.
Description
Details
19
0.30%
20
3.30%
21
0.50%
22
60 m
23
5.5 m
24
6.75 m
25
Superelevation
360
130
5.00%
400
115
5.00%
500
95
5.00%
600
80
5.00%
700
70
5.00%
800
60
5.00%
900
55
4.90%
1000
50
4.40%
1200
40
3.70%
1500
35
3.00%
1800
30
2.50%
2000
NR
Normal Camber
Description
Design Speed
Lane width
Rural
Urban
Median side paved strip (Shy distance)
2-Lane carriageway
Paved Shoulder
Rural
Earthen Shoulder
Urban
Pavement & Paved shoulder
Camber
Earthen shoulder
Width of Service Road
Separation Island Between carriageway & Service road in Urban
Minimum width of Footpath
Rural
Utility Corridor
Urban
Maximum superelevation
Minimum Stopping Sight Distance (SSD)
Minimum Intermediate Sight Distance (ISD)
Minimum radius of horizontal curve
Minimum radius of horizontal curve without transition
Min. vertical gradient
Absolute maximum vertical gradient
Maximum grade change not requiring vertical curve
Raised Median
Details
100 Kmph
3.5 m
4.5m
1.2m
0.25 m
7.0m
1.5m
2.0m
1.5m
2.50%
3.00%
7.0m
1.5m
1.5m
2.0m
1.5m
5.00%
180 m
360 m
360 m
1800 m
0.30%
3.30%
0.50%
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
S. No.
22
23
24
25
26
10.10
Reports Code
Page
Rev.
10-7
Description
Minimum length of vertical curve
Vertical clearance over NH/SH
Vertical clearance over rail
Vertical clearance over rail for DFC
Horizontal Curve Parameters
Radius of Horizontal curve (m)
Min. transition length (m)
360
120
400
110
500
95
600
95
700
95
800
95
900
95
1000
85
1200
70
1500
55
1800
0
2000
NR
Details
60 m
5.5 m
6.5
8.435 m
Superelevation
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
4.90%
4.40%
3.70%
3.00%
2.50%
Normal Camber
The cross drainage structures shall be classified as culverts, minor bridges and major bridges
depending up on the length of structure as per IRC standards. Structures up to 6m length fall into the
category of culverts, more than 6m and up to 60m in length as minor bridges and beyond this as
major bridges.
The design standards and loading to be considered for culverts, bridges, underpasses, flyovers and
ROBs shall be those laid down in the latest IRC codes and/or IS codes. Where the said codes are
found wanting or are silent other codes at national or international level shall be followed in
consultation with the client. ROBs shall be planned and designed in consultation with the concerned
Railway Authorities.
1. The Indian Road Congress (IRC) codes will be the basis of bridge designs, underpasses and
flyover/ ROBs. For items not covered by latter, provisions of Special Publications and
Specification for Roads and Bridges published by IRC shall be followed.
2. Grades of Concrete for superstructures will be as per MOST Specifications and IRC
Standards. The Minimum grade shall be M40 for PSC and M30 for RCC respectively.
3. For all new 3-lane structures, 3-lane live load will be considered as per IRC-6.
4. Locations of new Minor Bridges will generally be guided by the alignment of the highway.
But, for major bridges, the bridge location and its alignment shall override the highway
requirement in that portion.
5. On economic considerations and for ensuring good riding quality, wherever possible, for the
new bridges the layout of the existing bridges having a number of small spans will be
modified by decreasing the number of spans, maintaining the piers parallel and in line with
those of the existing structure.
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Reports Code
Page
Rev.
10-8
6. The deck will have 2.5% unidirectional camber/cross fall and the wearing course will be of
uniform thickness of 15 mm Mastic and 50 mm BC. For high traffic density, thickness of
mastic and BC shall be 25 mm and 40 mm respectively.
7. In general it has been observed during the preliminary study that the type foundations for the
existing bridges have not suffered any distress.
8. Pile foundations may be adopted for flyovers and ROB structures, depending on the
properties of the strata based on sub-soil investigation reports to be carried out by
Concessionaire.
Width of New Bridges
NHAI / 4 laning and 6 laning manual guidelines are to be followed.
Flyovers
Where flyovers are proposed, minimum vertical clearance above the cross roads will be 5.0 m.
Where viaducts [continuous] are proposed and the intent is to also use the road under for vehicular
traffic [as in a 4 lane continuous viaduct with the current road retained under] then all the structure
vertically above the roadway under should have the 5.0 m clearance [and this includes the underside
of the crossheads on the columns].
Planning for New Bridges
In general, the following aspects are taken into account while planning for the new bridges and
structures:
Aligning the piers with those of the existing structure to avoid cross currents and obstruction
to flow;
Minimum distance from the existing structure consistent with construction requirements and
hydraulic consideration;
Minimum number of spans consistent with road deck levels and minimum vertical clearance
above design HFL
Continuity (Except deck continuity) to be provided in superstructure for better riding quality.
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Reports Code
Page
Rev.
10-9
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Reports Code
Page
Rev.
11-i
11.1
11.2
11.3
11.4
11.5
11.5.1
11.5.2
11.5.3
11.5.4
11.6
11.7
11.8
11.9
11.10
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
11
Reports Code
Page
Rev.
11-1
11.1 Introduction
Pavement design basically aims at determining the total thickness of the pavement structure as
well as the thickness of the individual structural components for carrying the estimated traffic
loading under the prevailing environmental condition and adopted maintenance strategy with
satisfactory performance of the pavement will result in higher savings in terms of Vehicle
operating costs and travel time. Many design methods, from purely empirical to rigorous
analytical ones are available, and these are practiced in different parts of the world. In our
country, the generally adopted method of design of flexible pavement is the one recommended in
IRC: 37-2001, Guidelines for the Design of Flexible Pavements, is also an analytical method of
pavement design. For the effective design of pavement, rehabilitation proposals, there must
needs to assess the availability & suitability of potential construction material sources in the
project vicinity. Various engineering surveys and materials investigation has been carried out as
part of feasibility study and were discussed in the following sections.
This section presents the pavement and materials investigations followed by design process and
the resulting design recommendations.
11.2 Pavement Condition Survey
The visual pavement condition survey was carried out using Viziroad equipment along the project
road. The equipment is composed of
-
A 12 channel GPS
A Bump Integrator for the roughness measurements [refer earlier Section 11.1 for brief
description of the roughness survey]
The Viziroad software was used for data acquisition in terms of distress levels, process and
corrects the raw data for assessment of visual pavement condition functionally.
The equipment was set up for logging the following defects elements and data:
Longitudinal cracking in 3 levels
Rutting/Deformations in 3 levels
Alligator cracking in 3 levels.
Patching in 3 levels.
Potholes in 3 levels
Stripping in 3 levels
Transverse cracking in 3 levels.
Border erosion in 3 levels
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-2
Vizir Index
The Vizir index is a quality index as defined from the French Central Road Laboratory. It uses
several matrices and a decision tree to construct a final note from 1 to 7 (computed for
elementary sections of 500m) as follows.
Severity
Damage
Severe deformations,
localized
subsidence
rutting
2 f 4 cm
Deformation
rutting
Perceptible to user
but small
f < 2 cm
Cracking
Crazing
Repair
Either re-building
of part or all of
pavement
Or surface work
related to type B
defects
Deformations severely
or
affecting safety or
travel time
f 4 cm
Markedly
branched
Open and/or branching
and/or wide open
cracks
cracks;
edges
sometimes damaged
Very open crazing
Tighter crazing (<50cm)
forming blocks (<20
sometimes accompanied by
cm),
sometimes
loss of materials, stripping,
accompanied by loss
and incipient potholes
of materials
Surface work related to type A defects
Visible damage
repair itself
to
Deformation
Index
Id
Extent
Severity
0-10 %
10-50
%
> 50
%
If
Cracking
Index
If
(1)
Extent
Severity
0-10%
10-50 %
> 50 %
1-2
4-5
1-2
4-5
Id
0 to 10 %
10 to 50 %
> 50%
+1
+1
+1
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-3
Pavement condition and actions required corresponding to various values of damage Index Is:
Rating 1 or 2
o
Good surface condition requiring no (or only just requiring) immediate maintenance.
Rating 3 or 4
o
intermediate surface condition, bad enough to trigger maintenance work in the absence
of any other consideration
Rating 5-6-7
o
This rating can be cross-linked with deflection data and roughness data for further refinement of the
maintenance, overlay or reconstruction works to be selected. From the analysis of data reveals the
following description of the pavement.
Km
1076+480
1062+080
1062+080
1061+080
1056+080
1022+480
Summary condition
Relative good section, low/medium rutting due to flow. Localised severe
alligator/longitudinal cracks.
Mainly DBST section with structural rutting and extensive, sometimes
severe alligator cracking. This section is structurally not sound and not
adapted to the existing traffic.
Mainly DBST section with structural rutting and extensive, sometimes
severe alligator cracking. This section is structurally not sound and not
adapted to the existing traffic.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-4
SECTION
1
1
2
2
3
3
4
4
SUBSECTION
1
2
1
2
1
2
1
2
IRI TOPO
3.94
3.72
5.27
4.33
3.39
3.77
5.66
5.52
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-5
7
6
5
CNT50
CNT40
Linear (CNT50)
Linear (CNT40)
2
1
0
0
10
20
30
40
Reports Code
Page
Rev.
11-6
Vijayawada to Eluru:
Borrow areas for construction of embankment and subgrade were identified from the available
reports. Similarly, useable stone metal quarries, water and sand sources with their locations were
identified for the new construction. All materials complied well with respect to their engineering
and quality aspects.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-7
Sand Content /
Gradation
S.N.
Sampled at Ch.
Natural
Moisture
content (%)
Gravel
(%)
Coarse
sand (%)
Atterberg Limits
Mediu
m
Sand
size
(%)
Fine
sand
Sand
(%)
Silt &
Clay
(%)
LL
(%)
PL
(%)
PI
(%)
Soil
Classi
ficatio
n
Modified
Proctor Test
Values
MDD
(in
g/cc
)
OMC
(%)
FSI
(%)
CBR
(%)
25.6
1.20
2.80
9.40
13.4
73.2
59.4
22.9
36.5
16.5
19.0
50.0
--
Sample at Mandadam
28.2
0.00
0.80
01.8
04.4
93.0
64.6
27.6
37.0
16.9
19.8
60.0
--
27.5
0.00
01.0
02.2
04.5
92.3
63.0
25.4
37.6
16.5
18.5
55.0
--
24.7
0.00
0.00
02.8
17.2
80.0
61.6
24.0
37.6
16.5
20.5
80.0
2.3
19.3
0.80
01.4
04.2
13.4
80.2
54.3
24.3
30.0
17.1
20.0
70.0
--
Sample at Nunna at Km
1072+930
18.4
0.40
0.60
06.2
15.2
77.6
54.9
20.0
34.9
17.5
18.5
50.0
--
Nunna to Gannavaram
16.0
0.00
0.60
23.6
40.8
35.0
28.1
11.7
16.4
22.6
7.47
0.00
17.8
15.2
0.00
0.00
19.0
28.0
53.0
43.6
16.8
26.8
20.0
11.6
40.0
3.60
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Remarks
Reports Code
Page
Rev.
11-8
Finally, the investigations then carried out led to the use of earth material from the borrow areas
located along NH5 and NH9 as follows:
NH5:
1.
2.
3.
4.
5.
Km
Km
Km
Km
Km
1083+080
1081+380
1079+080
1074+080
1059+080
left
left
left
left
left
side
side
side
side
side
NH9:
1. Km 201.2 Right side, gravel quarry
2. Km 219.0 left side 1 km Munieru River Bed, sand source
3. Km.219.0 left side 2.0 km, gravel quarry
4. Km. 226.0, RS, Murieru River Bed, Sand
Sub base
The materials available in gravel/moorum quarries in the surrounding area contain high clay
contents and possess higher Liquid Limit and Plasticity Index values higher than the permissible
values. Percentage passing 75 micron sieve is also very high and these soils dont satisfy 10%
fines requirement as per clause 401 of MORTH Standard Specifications for road and bridge works.
Even blending with sand and stone dust will not satisfy most of the GSB and drainage layer
requirements. A minimum permeability of 20m/day is required for effective drainage layer. Hence
GSB as per grading III, II or grading I of table 400-2 with crushed aggregates may be provided.
All the mixes confirming to the above grading produce a minimum CBR of 30% required for sub
base. They also satisfy the permeability requirements of 20m/day and all the other MORTH and
IRC requirements.
Base and other Pavement courses
For the Vijayawada bypass, two important quarries at Perecherla and Palakaluru are available in
Guntur District. Two important quarries at Donabanda (Km 142+000 to Km 143+000 on NH-9)
and Ketanakonda (Km 1079+680 to Km 1079+580 on NH-5) are available in Krishna District.
Aggregates from these quarries are assessed for the suitability of aggregates for construction of
the base and pavement courses.
purposes of base course and other pavement courses, and were established as an acceptable
source for construction of base course and other pavement layers.
Sand Sources
The nearest source of sand (fine aggregate) in the stretch is Krishna river and quarries are
available at Seethanagaram in Guntur District and Damuluru and Moolapadu in Krishna District.
For the validation testing, the sand sample was collected from the river bed. The gradation test
performed on the sand sample indicated fineness modulus of 2.62 which lies between the F.M.
range of 2.6 to 2.9 indicating medium sand. The sample tested corresponded to Grade III. The
results of this sample show there is positive promise and potential for using this sand source for
construction works.
Moolapadu sand is suitable for filling and sand from Seethanagaram and Damuluru is suitable for
construction. Coarse sand available from Seethanagram and Damuluru quarries is suitable for use
in cement concrete works and in sand gravel mixes also.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-9
Construction Water
Water from Krishna river can be used for construction purpose. These are free from major
contamination and hence can be used as the water sources for concrete and construction of road
works. Also, tube wells at suitable places can be installed if necessary. Along with Krishna river
two more rivers were located on NH 5 and 9, which were mentioned below:
1. Tamileru River on NH5 located at Km 1039+380 on Eluru Bypass.
2. Munieru River located at Km 266+000 on NH9.
Water samples from these sources should be tested in laboratory for their suitability.
Eluru to Gundugolanu:
Borrow areas for embankment and subgrade construction inclusive of the quarry materials, water
and sand etc. meeting the technical as well as their quantity aspects were identified based on
existing reports as well as new test results.
In view of the above observations which were based on existing information as well as testing of
the limited soil, quarry and water samples, it seems reasonable to conclude that the prospects of
obtaining suitable and good quantities of various highway materials appears bright. However, it
does not in any way reduce the significance of the Concession Company collecting reasonable
numbers of samples of each type of material and subjecting them to proper engineering tests in a
recognised laboratory when construction of the new widening becomes a reality. Finally, the
investigations then carried out led to the use of earth material from the borrow areas located
along NH5 as follows:
NH-5:
1.
2.
3.
4.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-10
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-11
Reports Code
Page
Rev.
11-12
BOT/DBFO basis. Assuming 3 years time required for construction of bypass, the road will be
operated from 2014.
Summarizing, the design period for the pavement structure for the new carriageway was
considered as 20 years.
11.5.2 Traffic Volumes
As part of Feasibility study for 6 laning of Vijayawada-Eluru-Rajahmundry, section of NH-5, a
detailed traffic surveys along the project road has been conducted in the year 2007. Detailed
traffic projections over the design life and growth rates estimated for different types of vehicles
from such surveys has been used in this report. For the purpose of pavement design, commercial
vehicles of gross vehicle weight more than 3 tonnes has been considered. Such vehicles consisted
of LCVs, 2 axle trucks, 3 axle trucks and multi axle trucks, which generally use the bypass.
Growth rates estimated for the Feasibility Study for 6 laning of Chilakaluripet-Vijayawada, NH-5
and Vijayawada-Eluru-Rajahmundry are suitably modified in the light of four laning of the
Hyderabad-Vijayawada section and adopted for the present study. The growth rates estimated for
the Vijayawada bypass are presented for the realistic scenario. The estimated/proposed growth
rates for different vehicle types are as below for Vijayawada bypass and main stretch and
hanuman junction :
Adopted growth rates for Vijayawada Bypass
Period
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV up
to 6 Axle
MAV >6
Axles
HCM/
EME
2011-15
6.0
7.5
7.5
7.5
7.5
7.5
7.5
2016-20
5.5
6.5
6.5
6.5
6.5
6.5
6.5
2021-25
5.0
6.0
6.0
6.0
6.0
6.0
6.0
>2025
5.0
5.0
5.0
5.0
5.0
5.0
5.0
Adopted growth rates for existing main carriageway and hanuman junction
Period
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV up
to 6 Axle
MAV >6
Axles
HCM/
EME
2011-15
5.5
6.6
6.6
6.6
6.6
6.6
6.6
2016-20
5.5
6.6
6.6
6.6
6.6
6.6
6.6
2021-25
5.0
6.1
6.1
6.1
6.1
6.1
6.1
>2025
5.0
5.0
5.0
5.0
5.0
5.0
5.0
The above growth rates of commercial vehicles have been considered for assessment of design
traffic in terms of MSA.
Estimated traffic of the Vijayawad bypass,Hanuman junction bypass and existing stretch has been
projected with below growth rates and presented for the year 2010. Table 11.1 gives the year
2010 (now base year) traffic volumes in terms of AADT for the entire bypass section, for the
calculation of design traffic in terms of MSA for pavement design.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-13
western
alignment
section 2
(Vijayawada)
Hanuman Junction
bypass
Bus
780
1167
LCV
328
247
386
568
2 axle trucks
1102
1739
900
1667
3 axle Rigid
1287
810
891
2521
147
162
87
377
2,864
2958
3044
6033
Type of Commercial
Vehicles
Total
Vehicle Type
Pottipadu Toll
Recommended
Plaza
VDF ( Weighted
Empty
Loaded
Empty
Loaded
Average)
LCV
0.02
1.68
0.01
0.19
0.62
2 Axle
0.17
3.28
0.16
2.83
2.43
3 Axle Rigid
0.26
7.49
0.18
7.43
6.46
MAV
0.49
20.68
0.74
21.55
18.13
As the bypass is not having the bus traffic, the VDF for bus has not been considered. However, in
general the VDF for the bus in most of the cases equivalent to VDF of LCV.
From the above table it can be observed that, the 3-Axle trucks and MAV are overloaded by 20%
and 60 % respectively of the maximum permissible limits.
11.5.4 Strength of Sub grade
The strength of sub-grade in terms of California Bearing Ratio (CBR) is required for the design of
new flexible pavement if catalogue design of IRC: 37-2001 is used. The consultants had explored
and identified the potential borrow areas for the construction of sub grade and embankment
along the proposed bypass alignment. From this investigation and laboratory testing of soil
samples revealed that good strength soils with CBR values varying from 8% to 12 % are available
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-14
with reasonable lead. Also, as part of Feasibility study for Preparation of six-laning from
Vijayawada-Eluru-Rajamundry section, a number of borrow areas have been identified along the
project stretch as sources for embankment and subgrade filling material. Such investigation also,
shows that the borrow area soils of CBR 8% are available within the project vicinity with
reasonable lead (haulage distance) from site all along the project road.
Thus, a 4-day soaked CBR of 8 % has been considered as sub-grade strength for pavement
design for the entire project road except vijayawada bypass, where it has considered as 10%.
11.6 Evaluation of Design Traffic (MSA) for Pavement Design
Base year traffic (vehicle category-wise & in terms of AADT), traffic growth rates, design life (in
terms of number of years) and vehicle damage factors are required to estimate the design traffic
in terms of equivalent standard axles. The following data have been considered to arrive at the
design traffic (MSA).
For flexible pavements, the percentage of vehicles in heaviest loaded lane can be determined as
per IRC: 37-2001 guidelines given below:
Type of facility
The details of MSA calculations are provided in Table 11.4 and the summary is abstracted at
Table 11.3 below.
Table 11.3: Summary of Design MSA for the project road
Design Traffic in MSA
10 year
period
(2014 to
2023)
20 year design
life
(2014 to
2033)
34
94
31
85
20
53
46
122
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-15
VDF values
2010
Growth rate (%)
2011
2012
2013
2014
2015
Growth rate (%)
2016
2017
2018
2019
2020
Growth rate (%)
2021
2022
2023
2024
2025
Growth rate (%)
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2-Axle 3-Axle
Truck Truck
Bus
LCV
MAV
0.62
0
0.62
328
2.43
1102
6.45
1287
18.12
147
6.0
0
7.5
353
7.5
1185
7.5
1384
7.5
158
379
1273
1487
170
407
1369
1599
183
438
1472
1719
196
471
1582
1848
211
5.5
0
6.5
501
6.5
1685
6.5
1968
6.5
225
534
1794
2096
239
569
1911
2232
255
606
2035
2377
271
645
2168
2531
289
5.0
0
6.0
684
6.0
2298
6.0
2683
6.0
306
725
2435
2844
325
768
2582
3015
344
814
2736
3196
365
863
2901
3388
387
5.0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
5.0
907
952
999
1049
1102
1157
1215
1276
1339
1406
1477
1550
1628
1709
1795
5.0
3046
3198
3358
3526
3702
3887
4082
4286
4500
4725
4961
5209
5470
5743
6030
5.0
3557
3735
3922
4118
4324
4540
4767
5005
5255
5518
5794
6084
6388
6707
7043
5.0
406
427
448
470
494
519
544
572
600
630
662
695
730
766
804
1885
6332
7395
845
2864
1.90
3079
3310
3558
3825
4112
2.04
2.19
2.35
2.53
2.72
2.53
5.25
4379
4664
4967
5289
5633
2.90
3.09
3.29
3.50
3.73
8.1
11.2
14.5
18.0
21.7
5971
6330
6709
7112
7539
3.95
4.19
4.44
4.71
4.99
25.7
29.9
34.3
39.0
44.0
7916
8311
8727
9163
9621
10102
10608
11138
11695
12280
12894
13538
14215
14926
15672
16456
5.24
5.50
5.77
6.06
6.37
6.69
7.02
7.37
7.74
8.13
8.53
8.96
9.41
9.88
10.37
10.89
49.3
54.8
60.54
66.60
72.97
79.65
86.67
94.04
101.78
109.91
118.44
127.40
136.80
146.68
157.05
167.94
4-Lane
Construction
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Traffic
Opened on
New Lanes
from year
2013
Reports Code
Page
Rev.
11-16
VDF values
2010
Growth rate (%)
2011
2012
2013
2014
2015
Growth rate (%)
2016
2017
2018
2019
2020
Growth rate (%)
2021
2022
2023
2024
2025
Growth rate (%)
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2-Axle 3-Axle
Truck Truck
Bus
LCV
MAV
0.62
0
0.62
247
2.43
1739
6.45
810
18.12
162
6.0
0
7.5
266
7.5
1869
7.5
871
7.5
174
285
2010
936
187
307
2160
1006
201
330
2322
1082
216
355
2497
1163
233
5.5
0
6.5
378
6.5
2659
6.5
1238
6.5
248
402
2832
1319
264
428
3016
1405
281
456
3212
1496
299
486
3421
1593
319
5.0
0
6.0
515
6.0
3626
6.0
1689
6.0
338
546
3843
1790
358
579
4074
1898
380
613
4318
2011
402
650
4577
2132
5.0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
5.0
683
717
753
790
830
871
915
961
1009
1059
1112
1168
1226
1287
1352
1419
5.0
4806
5047
5299
5564
5842
6134
6441
6763
7101
7456
7829
8220
8631
9063
9516
9992
5.0
2239
2351
2468
2592
2721
2857
3000
3150
3308
3473
3647
3829
4020
4221
4432
4654
2958
1.72
3180
3418
3675
3950
4247
1.84
1.98
2.13
2.29
2.46
2.29
4.76
4523
4817
5130
5463
5818
2.62
2.79
2.98
3.17
3.38
7.4
10.2
13.2
16.3
19.7
426
6167
6537
6930
7345
7786
3.58
3.79
4.02
4.26
4.52
23.3
27.1
31.1
35.4
39.9
5.0
448
470
494
518
544
571
600
630
662
695
729
766
804
844
886
931
8175
8584
9013
9464
9937
10434
10956
11504
12079
12683
13317
13983
14682
15416
16187
16996
4.74
4.98
5.23
5.49
5.77
6.05
6.36
6.67
7.01
7.36
7.73
8.11
8.52
8.94
9.39
9.86
44.6
49.6
54.82
60.31
66.08
72.13
78.49
85.16
92.17
99.53
107.26
115.37
123.89
132.83
142.22
152.08
4-Lane
Construction
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Traffic
Opened on
New Lanes
from year
2013
Reports Code
Page
Rev.
11-17
Bus
LCV
0.62
780
Growth rate (%) 5.5
823
2011
868
2012
2013
916
966
2014
1019
2015
Growth rate (%) 5.5
1075
2016
1135
2017
1197
2018
1263
2019
1332
2020
Growth rate (%) 5.0
1399
2021
1469
2022
1542
2023
1619
2024
1700
2025
Growth rate (%) 5.0
1785
2026
1875
2027
1968
2028
2067
2029
2170
2030
2279
2031
2393
2032
2512
2033
2638
2034
2770
2035
2036
2908
3054
2037
3206
2038
3367
2039
3535
2040
3712
2041
0.62
386
6.6
411
439
468
498
531
2.43
900
6.6
959
1023
1090
1162
1239
6.45
891
6.6
950
1012
1079
1151
1226
18.12
87
6.6
93
99
105
112
120
6.6
566
604
644
686
731
6.6
1321
1408
1501
1600
1705
6.6
1307
1394
1486
1584
1688
6.1
776
823
874
927
983
6.1
1809
1920
2037
2161
2293
5.0
1033
1084
1138
1195
1255
1318
1384
1453
1526
1602
1682
1766
1854
1947
2044
2147
5.0
2408
2528
2654
2787
2926
3073
3226
3388
3557
3735
3922
4118
4324
4540
4767
5005
VDF values
2010
MAV
Design Cumulative
ESA in Design
Million MSA
New
Pavement
3044
1.12
3236
3441
3658
3890
4136
1.19
1.27
1.36
1.44
1.54
1.44
2.98
6.6
128
136
145
155
165
4398
4676
4972
5287
5622
1.64
1.75
1.86
1.98
2.11
4.6
6.4
8.2
10.2
12.3
6.1
1791
1901
2016
2139
2270
6.1
175
186
197
209
222
5951
6298
6666
7056
7468
2.24
2.38
2.52
2.67
2.84
14.6
16.9
19.5
22.1
25.0
5.0
2384
2503
2628
2759
2897
3042
3194
3354
3522
3698
3882
4077
4280
4494
4719
4955
5.0
233
244
257
269
283
297
312
327
344
361
379
398
418
439
461
484
7842
8234
8646
9078
9532
10008
10509
11034
11586
12165
12774
13412
14083
14787
15526
16303
2.98
3.13
3.28
3.45
3.62
3.80
3.99
4.19
4.40
4.62
4.85
5.09
5.35
5.61
5.89
6.19
28.0
31.1
34.36
37.81
41.43
45.23
49.22
53.40
57.80
62.42
67.27
72.36
77.71
83.32
89.22
95.41
Remarks
6-Lane
Construction
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Traffic
Opened on
New Lanes
from year
2013
Reports Code
Page
Rev.
11-18
2010
1,167
568
1,667
2,521
377
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
1,225
596
1,750
2,647
396
1,286
626
1,838
2,779
416
1,350
657
1,930
2,918
437
1,418
690
2,027
3,064
459
1,489
725
2,128
3,217
482
1,563
761
2,234
3,378
506
1,641
799
2,346
3,547
531
1,723
839
2,463
3,724
558
1,809
881
2,586
3,910
586
1899
925
2715
4106
615
1,994
971
2,851
4,311
646
2,094
1,020
2,994
4,527
678
2,023
2199 1071
3144
4753
712
2024
2025
2026
2027
2028
2029
2030
2031
2032
2,309
1,125
3,301
4,991
748
2,424
1,181
3,466
5,241
785
2,545
1,240
3,639
5,503
824
2,672
1,302
3,821
5,778
865
2,806
1,367
4,012
6,067
908
2,946
1,435
4,213
6,370
953
3,093
1,507
4,424
6,689
1,001
3,248
1,582
4,645
7,023
1,051
3,410
1,661
4,877
7,374
1,104
2,033
3581 1744
5121
7743
1159
6300
6614
6945
7292
7658
8041
8442
8864
9307
9772
10260
10773
11313
11879
12474.00
13097
13751
14438
15160
15917
16714
17549
18426
19348
3.87
4.06
4.26
2.28
1.94
3.95
4.15
4.35
4.57
4.80
5.04
5.29
5.56
5.83
6.13
6.43
6.75
7.09
7.45
7.82
8.21
8.62
9.05
9.50
Remarks
Awarding
&FC
4.06
8.32
10.60
12.54
16.49
20.64
24.99
29.56
34.36
39.40
44.70
50.25
56.09
62.21
68.65
75.40
82.49
89.94
97.75
105.96
114.58
123.63
133.13
Construction
period of
3yrs
1.94
5.89
10.0
14.4
19.0
23.8
28.8
34.1
39.7
45.5
51.61
58.0
64.8
71.9
79.33
87.15
95.36
103.98
113.03
122.53
6-lane facility
Reports Code
Page
Rev.
11-19
The ultimate pavement structure to account for entire design life of 20 years (2014 to 2033) is
presented in Table 11.5 below.
Table 11.5: Pavement Structure for 20 Year Design Life
Design Section
Design
CBR
Pavement composition
Design
traffic
(msa)
DBM
WMM
GSB
10
94
49
128
250
200
10
85
47
124
250
200
53
41
121
250
200
122
50
144
250
200
As mentioned earlier (Section 11.2.1), the proposed pavement design life of 20 years excluding
construction period was considered. Estimated traffic loading for 20 year concession period in
terms of cumulative standard axle load is quite low compared to the design traffic estimated for
main NH-5 from Vijayawada-Eluru-Rajahmundry section. Moreover, the assessment of traffic in
terms of number of commercial vehicles for such a distant horizon of 20 year from now has
doubtful precision. Also, vehicle fleet composition and vehicle damaging factors obtained today
may not remain same for a future period of 20 years. As per the latest codes and documents, the
strengthening/new construction shall be of 50mm BC. Thus, accordingly the BC layer of thickness
50mm has been considered and the proposed thicknesses and composition of pavement layers is
presented in the Table 11.5 below.
Table 11.5: Recommended Pavement Composition for new construction/widening
Design Section
Design
CBR
Design
traffic
(msa)
Pavement composition
(thickness of layers in mm)
BC
DBM
WMM
GSB
Sub
grade
10
94
50
125
250
200
500
10
85
50
120
250
200
500
53
50
110
250
200
500
122
50
140
250
200
500
A sub grade of 500mm thickness and 8% CBR is required as an integral part of the pavement
structure along the project road and 10% for Vijayawada bypass.
11.8
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
11.9
Reports Code
Page
Rev.
11-20
Design thickness
(mm)
40
60
250
200
500
Total thickness
(mm)
550
500
General
During the operational phase, the initial designed pavement structure will be subjected to both
load induced and environmental damages. The notion of pavement lifetime can not be easily
defined as development of fatigue damage is inherently random. Safety, riding comfort and cost
effectiveness concerns always require maintenance operations to be performed before complete
pavement failure. Thus, it becomes necessary for the Concessionaire to take up appropriate
maintenance measures to ensure that the functional quality does not fall below the prescribed
levels, and at the same time the structural integrity of the pavement is maintained so that it
serves well throughout the concession period without the need for un-scheduled rehabilitation or
reconstruction measures. During this period, performance of the pavement will be closely
monitored and appropriate maintenance actions taken to maintain its functional characteristics
and structural integrity.
11.10.2
Considering the design life of 20 years from traffic opening on to the new 4-lane bypass facility,
the following overlay treatments are proposed.
Type-I Overlay
In India, it has been observed that even if the bituminous crust is provided for 15 to 20 year
design period, first overlay is mostly required in the initial operating period of 6 to 8 years after
opening the traffic. During this period, certain damages in the form of undulation and unequal
settlements are anticipated in the pavement surface due to foundation settlement and
compaction of the body of the embankment. For correction of these, a profile correction course
(PCC) of variable thickness would be required. For this purpose, a combination of BC layer of
25mm with PCC of 25mm BC laid with total thickness of 50mm is proposed. Choice of DBM in its
place would have meant a much thicker mat, and also heterogeneous structure (DBM over BC).
Type -2 Overlay
This, comprising a thin surfacing course is essentially intended for restoring the riding quality
which might have deteriorated because of traffic action and other environmental problems. For
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
11-21
high-type roads, this is normally applied once in 6-8 years, and the same frequency is proposed.
The layer will be of BC, 40mm in thickness, using modified binder and 13mm nominal size
aggregate.
In summary, the following maintenance intervention is proposed to cover the entire
operation/concession period.
At the end of year
after COD
Type of Overlay
6th to 7th
Functional (Type 2)
40 mm BC
Functional (Type 2)
40 mm BC
12th to 13th
th
18
th
to 19
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Chapter 12:
CHAPTER 12:
Reports Code
Page
Rev.
12-1
Contents
CONTENTS ...................................................................................... 1
12.
12.1
GENERAL..................................................................................................................................................2
12.2
12.3
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
12-2
12.
12.1
GENERAL
Once the as-built drawings and site conditions were examined it became obvious that the 6 laning
[along with service roads] could not generally be fitted into within the available right-of-way.
12.2
The Right of Way details (roadway width in meters) collected from the NHAI local offices [in
December 2006] are presented in the following sections.
Discussions with local NHAI and Revenue officers reveals that the recent land-take for 4-laning of
project road was restricted [when 4 laning was undertaken in the 1990s] only to the minimum
required for the construction of additional 2 lanes on the sections other than bypasses. Further these
offices do not hold the up-dated revenue records after the acquisition for 4-laning project except for
some revenue divisions. It is also learned that the RoW boundary stones established in some
sections are destroyed locally by the public for various reasons including farming.
Subsequently the details collected were randomly verified on the field wherever possible and found
to be relatively close to the widths provided by these organisations.
Graphically, for the northern 200 km section of the project, the ROW width is shown on the following
graphs. It can be seen the ROW drops in width to under 30m in places.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
12-3
100.0
80.0
60.0
40.0
20.0
0.0
0+000
20+000
40+000
60+000
80+000
100+000
120+000
140+000
160+000
180+000
200+000
Km [Vijayawada - Divnacheru]
12.3
For the ease of analysis of land take requirements for the current objective of the project, the Right of
Way details are presented in different sections.
The right of way required for 6-laning with service roads is in the order of 54 meter in the urban
section which includes provision of shoulders and wider service road to cater the mixed local traffic
and 60 in 4 lane Vijayawada bypass, 70 in Existing NH5 widening to 6lane & 80 in Hanuman
Junction Bypass in the rural section. An additional land is required at junctions, interchange for the
provision of cross structures and for wayside amenities and drainage channel relocation. Based on
typical cross sections and these assumptions, the land acquisition requirement is assessed and
summarised in the following tables. It is apparent that the whole project road required acquisition all
along the section.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-1
STRUCTURES ............................................................................................. 2
13.1
INTRODUCTION ....................................................................................................................... 2
13.2
13.2.1
13.2.2
13.3
13.4
13.5
13.5.1
13.5.2
Major bridge no. 64/5 at km 1040+481 across Tammileru River on Eluru Bypass
Major bridge no. 70/3 at km 1034+907 across Vyaskani River on Eluru Bypass
13.7
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
STRUCTURES
13.1
INTRODUCTION
Reports Code
Page
Rev.
13-2
13.2
INVENTORY OF STRUCTURES
There are of 4 Major Bridges (Total length > 60.0 m), 34 Minor Bridges (6.0 m < Total Length
<60.0m), 4 existing ROBs, 20 underpasses/ cattle crossings and 171 culverts on the various
sections of NH5 on the project road between Vijayawada and Gundugolanu. All the numbers of
structures mentioned above are for individual 2 lane carriageway except for culverts, which are
for 4 - lane.
13.2.1 General Condition of Bridges / underpasses / ROBs
There are 2 major bridges (considering both the carriageway) on the project road. The
superstructures are of PSC / RCC T-Beam and Slab, voided slab type resting on RCC substructures
supported by Well / pile foundations.
The type of superstructures for minor bridges / underpasses / ROBs are RCC solid slab, RCC / PSC
T-beam, voided slab, box girder etc. in most bridges resting on RCC and C.C. gravity type
substructure supported on open / well / pile foundations. Few structures have RCC balanced
cantilever, superstructures also. RCC box type structures / U trough with simply supported
superstructures have been observed at some location. Some bridges have course rubble masonry
substructure and foundation.
The condition of most of the structures is generally good. Some common distresses observed are
spalled concrete; exposed and corroded reinforcement in slabs, piers and abutments; damaged
/missing RCC railing and kerb, depositions of debris and growth of vegetation on pier caps and in
ventways, damaged asphaltic / RCC wearing coat, damaged / missing precast slab, damaged
expansion joints; undismantled steining of well foundations; missing, choked drainage
spouts,leakage around holes for drainage spouts; spalled concrete and corroded reinforcement,
approach slab settlement, settlement of embankment around abutments, damaged metallic crash
barriers in structure approaches etc. In few structures, plasterwork is observed at soffit of box and
cantilever portion, which hides the actual condition of the structures. Bed protection provided, if
any, was not visible in general. Bridges in very bad condition, arch bridges and bridges having
course rubble masonry shall be replaced with new 3-lane structures.
13.2.2 General Condition of Culvert
The culverts observed along the project road are mainly of two type viz. RCC slab culverts and pipe
culverts. Some RCC box culverts are also there. The structural condition of pipe culvert is generally
good, except that some are partially choked or full buried. The condition of culverts is in general
good. Some common distresses noted are missing / damaged parapets; cracked / damaged
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-3
headwalls, abutments and wing walls; spalled concrete and corroded exposed reinforcement. Bed
protection provided, if any, was not visible.
Summary of various types of the structures on the project road is as under:
Underpasses
Major bridges *
Minor bridges *
ROBs *
/ cattle
Culverts
crossings*
4
34
4
20
171
The following common defects were observed during the visual condition survey of bridges and
other structures on the Vijayawada Rajahmundry section:
1. Damaged hand rails
RCC hand rails are found to be damaged at a number of structures. Damage to handrails is
more frequent at bridges with lesser carriageway widths. At some locations, even the
railing kerbs were found dislocated.
b)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-4
Absence of water collector channels and drainage chutes with stilling basins after
approach slab leading to scouring immediately on sides of wing walls.
d)
e)
The
packing
made
around
6. Debris on deck
Debris have collected towards the outer
edges of the carriageway thereby making
almost half a meter wide strip non usable
and causing blocking of drainage spouts. All
the strip seal expansion joints were also
found filled up by debris.
7. Drainage spouts
Drainage spouts are found to be having different distress in different structures as listed
below:
a)
b)
c)
Leakage around drainage spout from holes made in deck slab for fixing spouts and
left unplugged.
d)
e)
At some bridge locations, drainage spouts have not been provided at all.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-5
This
will
result
in
additional
at
number
of
prominent
on
old
structures.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-6
13.4
Approach slab settlement has been observed all along the project road mostly in new 2 lane
structures. The settlement may have been caused by one or a combination of following reasons:
a) Poor compaction behind abutments.
b) Leaving the embankments sides undressed after compaction
c) Absence of water collector channels and drainage chutes with stilling basins after approach
slab leading to scouring immediately on sides of wing walls.
d) Use of smaller stones of weight less than 40 kg in pitching of slopes.
This approach slab settlement requires the following general [at many structures] remedial
measures:
a) Before taking up the rehabilitation of settlement of approach slab the embankment
quadrants around the wing walls shall be stablised first.
b) Loose boulder pitching on the settled/ failed embankment shall be removed and stacked
separately.
c) The exposed embankment shall be checked for present compaction conditions. The loose
material, if any, shall be removed and replaced with suitable materials duly compacted.
d) Thereafter, the embankment shall be built up to required levels.
e) Provide loose boulder pitching with boulders weighing not less than 40 kg over 150 thick
filter media.
f)
Similarly, all areas of loose boulder pitching having smaller stones shall be replaced with
boulders weighing not less than 40 kg.
Reports Code
Page
Rev.
13-7
Provided RCC drainage chutes at 5 m intervals with one drainage chute at start and end of
water collector channel.
j)
Provided stilling basins at end of drainage chutes duly protected from scouring.
k) Now, make up the settlement in approach slab and approach embankment with suitable
bituminous course.
l)
In case settlement of approach slab has resulted in the end of approach slab resting on
bracket projecting from dirt walls projecting over the road surface, the approach slab shall
be dismantled and replaced with a new one after making up the settled parts.
13.5
Reports Code
Page
Rev.
13-8
providing a smooth transition on to the bridge and to improve the riding quality. It is proposed to
provided water collector channels after the approach slabs alongwith drainage chutes, with stilling
basins at ground level, at 5 m intervals for preventing scouring near edges of wing walls.
Rehabilitate boulder pitching on earthfill around abutments.
Widening of existing 2x2 lane structures is not feasible because it is having eccentric
superstructure (towards outer edge) along with a PSC / voided slab superstructures resting on well
/ pile foundations.
13.5.3 Major bridge no. 70/3 at km 1034+907 across Vyaskani River on Eluru Bypass
(New 4 lane)
The existing new 4 lane bridge on has 4 spans of 32.3 m each with a total length of 129.2 m. It
has PSC T Beam and slab superstructure supported on RCC circular piers resting on well
foundations and RCC solid wall type abutments resting on pile foundations. It has elastomeric
bearings and strip seal type expansion joints. Each 2-lane of existing bridge has 9.905 m deck
width comprising of 7.5 m wide carriageway and 1.865 m footpath including hand rail near outer
edge and .54 m railing kerb towards median. The end span towards Rajahmundry side also serves
as an underpass.
The bridge is in good condition and can be retained in the present condition with minor repairs.
The settlement of approach slab is proposed to be suitably repaired for providing a smooth
transition on to the bridge and to improve the riding quality. It is proposed to provided water
collector channels after the approach slabs alongwith drainage chutes, with stilling basins at
ground level, at 5 m intervals for preventing scouring near edges of wing walls. Replace the
damaged concrete near expansion joint and reset the expansion joint. Clean blocked drainage
spouts and replace the missing / damaged spout gratings.
Widening of existing 2x2 lane structures is not feasible because it is having eccentric
superstructure (towards outer edge) along with a PSC superstructure resting on well / pile
foundations.
Note: Existing 4-lane (2x2lane), Two Major bridges and Two ROBs in Eluru Bypass are having
superstructure with PSC T-Beam Girder Slab/Voided Slab/PSC Box Girder/RCC Box Girder,
supported on deep foundations. As such it is not possible to widen the existing four lane bridges
(2 x 2 lane) to six lane (2 x 3 lane) because the foundation type is deep foundation (Pile/Well)
which are designed for 2 lane loading only and widening of these foundations is not possible hence
they are not able to withstand for 3 lane loading so we have to dismantle and reconstruct the new
3 lane bridge at these locations. Dismantling of the existing structures is a difficult process and
reconstruction of new 6 lane bridges would increase the cost of the project. Therefore from the
economy considerations, the major bridges and ROBs in the Eluru Bypass are proposed for
retention without widening / reconstruction.
13.6
IMPROVEMENT PROPOSALS
There are 4 Major Bridges (Total length > 60.0 m), 34 Minor Bridges (6.0 m < Total Length
<60.0m), 4 existing ROBs, 20 underpasses/ cattle crossings and 171 culverts on the various
sections of NH5 on the project road between Vijayawada and Gundugolanu.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-9
All the numbers of structures mentioned above are for individual 2 lane carriageway except for
culverts which are for 4 - lane. All the improvement proposals, except for culverts, refer to the
improvement of structure for individual carriageway. The improvement proposals for various types
of structures are as under:
13.6.1 Major bridges / ROBs
i.
All existing major bridges in good condition shall be retained with 2 - lane configuration for
individual carriageways with necessary repairs.
ii.
Existing arch bridges and bridges in bad condition shall be replaced with new 3 lane
bridges.
iii.
The span arrangement of new 3-lane major bridges shall be matched with the span
arrangement of the retained major bridges.
iv.
The bridges with open foundations can be constructed at same location as that of existing
bridge.
v.
The total deck with for the new 3-lane major bridges shall be kept as 14.05 m consisting of
10.5 m wide carriageway, 0.5 m edge shyness near median and 0.25 m shyness near
crash barrier alongside footpath, 1.5 m wide footpath, 0.5 m wide crash barriers on either
side of carriageway and 0.3 m wide steel railing kerb on outer edge of the footpath.
vi.
For structures having width less than road cross section at that location, metallic crash
barriers shall be provided in the approaches on both sides of the structure. The length of
metallic crash barriers shall be kept in such a way that the splay is 1:10 so as to provide
a safe entry and exit from the structure having deck width lower than the respective road
cross section.
vii.
The structural arrangement of ROBs shall be finalized keeping in view the Railways
requirements.
All structures in good condition having simply supported RCC solid slab superstructure and
open foundations shall be widened to 3-lane.
ii.
Structures with well / pile foundations having 12 m total deck width shall be retained by
modifying the carriageway to 11.0 m with 0.5 m wide crash barriers on both sides of
carriageway after checking the structure for 3 lane live load.
iii.
Structures with well / pile foundations having 9.8 / 10.25m total deck width shall be
retained by replacing the superstructure with equivalent or lower weight steel concrete
composite superstructures of total deck width 12.0 m. abutments (12 m) and piers / piers
caps shall be suitably widened to accommodate the new deck after checking the structure
for 3 lane live load and additional width. The backfill behind abutments and well cap
shall be replaced with one having following properties: 35, 1.8 t / m3 and c = 0.
iv.
Structures with well / pile foundations having around 8 m total deck width shall be
replaced by new 3 lane structures.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-10
The new 3 lane structures shall be either located parallel to the existing structures with
well / pile foundations or constructed with longer spans such that the foundations of new
structures do not foul with those of existing structures. The structures with open
foundations can be constructed at same location.
vi.
Arch bridges, bridges with CRM substructure & foundations and bridges in bad condition
shall be replaced with new 3 lane bridges.
vii.
The span arrangement of new 3-lane structures shall be matched with the span
arrangement of the retained structures.
viii.
The total deck with for the new 3-lane and widened structures having simply supported
RCC solid slab superstructure and open foundations shall be kept as 14.0 m consisting of
10.5 m wide carriageway, 0.5 m edge shyness near median, 1.5 m paved shoulder and 1.0
m earthen shoulder, 0.5 m wide crash barriers on median side and outer edge of deck
(partly covering earthen shoulder).
ix.
For structures having width less than road cross section at that location, metallic crash
barriers shall be provided in the approaches on both sides of the structure. The length of
crash barrier shall be kept in such a way that the splay is 1:10 so as to provide a safe
entry and exit from the structure having lower deck width than the road cross section.
x.
While widening the existing structures, traffic shall be diverted through temporary bailey
bridges or culverts, whichever is suitable to site conditions, constructed parallel to the
existing bridge.
13.6.3 Culverts
There are 171 culverts (pipe, slab and box) on the project road. These culverts are of 4 lane
configuration. At a few locations, pipe culvert on existing 2 lane has been extended by a slab /box
culvert on new 2- lane and vice versa. The culverts are generally in good condition. Broken or
missing parapet is a general distresses observed. Headwalls of some of the pipe culverts were
found cracked. Some pipes were found partly choked. Wing walls were found damaged at some
locations.
All the existing culverts, where still functioning and usable, shall be widened to six lanes with
opening at least equal to the existing culvert. The overall width of the culvert shall match with the
highway cross section at the particular location.
13.6.4 Summary of improvement proposals of various types of the existing structures
on the project road is as under
Major bridges
Total number of major
bridges
2
Number of bridges
retained without
widening
-
Number of bridges to be
widened with new 2-lane
bridges
-
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-11
Minor bridges
Total number of
minor bridges *
Number of
bridges to be
retained without
widening *
34
1
*each carriageway considered separately
Number of
bridges to
be replace
with new
3-lane
bridges *
-
Number of
bridges to be
widened to 3lane *
Number of
bridges to be
widened with
new 2-lane
bridges *
32
ROBs
Total number of
ROBs
Number of ROBs
retained to be
without
widening
Number of ROBs to be
replace with new 3-lane
ROBs
Number of
bridges to be
widened with
new 2-lane
bridges
-
Number of Underpasses /
Cattle crossings to be
replace with new 3-lane
Underpasses / Cattle
crossings
Number of
Underpasses /
Cattle crossings
to be widened to
3-lane
10
Number of culverts to be
widened to 3-lane
Number of
culverts retained
150
Number of
culverts to be
replace with new
2/ 3-lane
culverts
21
Remove debris/ vegetation from pier and abutment caps, expansion joints and bridge
deck.
2.
3.
Provide water collector channels after end of approach slab for a length equal to 2.5 times
the height of embankment with a minimum length of 15 m.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-12
Provided RCC drainage chutes at 5 m intervals with one drainage chute at start and end of
water collector channel.
5.
Settled filing around wing walls/ cantilever returns to be filled up, duly compacted, and
pitched with boulders in wire crates as per provisions of IRC: 89 and MoRT&H
specifications.
6.
Clean drainage spouts. Provide missing / damaged gratings. Fill up the hole in deck slab
around spout. Replace drainage spouts with short or missing down take pipes. Install
missing drainage spouts at locations where they are missing / not provided at all originally.
7.
Construct concrete inspection ladders on boulder pitching around abutment s for an easy
access to the river bed for inspection.
8.
9.
10.
Replace expansion joints of old bridges with T beam and slab superstructure with strip
seal type expansion joint after rehabilitating / strengthening / thickening the deck slab
near expansion joints suitably.
11.
Provide 25 long splayed metallic crash barriers in approaches of bridges with deck width
lesser than the required configuration.
12.
13.
14.
Replace all RCC railing adjoining carriageway with RCC crash barrier.
13.7
General
The project road is proposed to be developed as an access controlled highway so that the through
traffic can flow freely with least interference from the vehicles coming from the cross roads. The
Consultants examined the various junctions and studied their traffic patterns. On the basis of this
study, certain locations have been identified for locating Bypasses and flyovers / underpasses. The
underpasses and grade separators are proposed to cater for the width of the project road. Existing
4 lane underpasses are proposed to be widened to six lane configuration (See Chapter 18).
Bypasses
Vijayawada City falls between Km 1100+694(old chainage km 433+500) and Km 1090+000 (old
chainage km 14+000) on NH-5 where the project highway passes through Tadepalli, Benz circle of
Vijayawada City. The widening to six laning along existing alignment would involve significant land
acquisition, and demolition of existing properties along the highway. Keeping in view all the
representations, NHAI has asked the consultants to study and prepare a Feasibility Report for
providing bypass for Vijayawada City on NH - 5.
The section of NH-5 forming part of the project corridor passes through Gannavaram after crossing
the Vijayawada city. The terminating point is near Pedda Avutapalli on the eastern periphery of
Gannavaram. Traffic flowing between these points necessarily has to pass through thickly
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-13
developed area of Gannavaram, using existing 4-Lane NH-5 Road. Due to the congested traffic
flow conditions, Freight movement in this section will be very difficult in the future. This
necessitates the identification of bypass to the existing NH-5 at Gannavaram and Hanuman
Junction.
Flyovers
The flyovers have been proposed at urban locations and main junctions for free flow of through
traffic by elevating the main carriageway. The lifting of main carriageway will start at location
having adequate ROW for catering to width requirement of main carriageway, the generally 7.0 m
wide service roads [and / or ramps] on either side of the main carriageway, drains, footpath etc.
Similarly, the elevated road may be brought down at locations having adequate ROW for catering
to width requirements at start of lifting of main carriageway. Overall length of the flyover will be
determined based on the above considerations in addition to cross traffic / lower ROW etc. The
project road will fly over the cross roads providing minimum 5.0 m vertical clearance. The
standards for the flyovers and for the slip roads will be as per the Manual for 6 laning / IRC
guidelines. The superstructure may consist of precast girders with cast in situ diaphragms and deck
slab or a composite superstructure having steel girders and RCC deck slab.
Underpasses
Underpasses have been proposed to cater for the cross traffic and the pedestrians. While fixing the
vertical profile, the cross road RL is proposed to be depressed to the possible extent (keeping the
cyclones and cultivation in view) so that the existing pavement is least effected. For safety,
convenience and the local requirements; following types of underpasses have been proposed viz.
(i)
Pedestrian underpass (PUP)/subways to cater for pedestrian and slow moving traffic
(ii)
vehicular underpass (VUP) of 3 types to cater for vehicular traffic at state highways
and other road crossings
(iii)
For Pedestrian underpass/subway RCC box structures with clear horizontal opening of maximum 6.
0 m and clear vertical opening of 2.5m have been proposed.
For vehicular underpasses when the project road crosses a cross road, the underpass will be a
single span 12m wide structure with vertical clearance of 5.0m has been proposed on roads
carrying heavy traffic. For other vehicular underpasses vertical clearance of 3.5m has been
proposed.
Flyovers are proposed at locations where the project road crosses a National Highway, or other
significant roads. The project road will fly over the National Highway and a divided six lane width
with individual supports has been proposed. The objective is to have the minimum structure
thickness realistically possible in the deck section as this will reduce the amount of existing road
wasted by the grade separation.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-14
Approaches
As the project road flies over the intersecting roads, adequate land width is needed for the normal
approach embankments. However, as almost all the locations of the proposed grade separators are
near the built-up areas, land acquisition may be difficult. Hence, reinforced soil structures are
proposed for the approaches, of all the flyovers, and some underpasses and some grade
separators.
The structures proposed are as under:
6 Flyovers
13 Pedestrian Underpasses
10 Vehicular Underpasses
3 Major Bridges
3 ROBs
Chainage
(km)
Span
arrangement
Effective
length (m)
Vertical
Clearance
(m)
Total width*
(m)
Remark
Vijayawada Bypass
1
0+790
2 X 30
60
5.5
2 x 12 m
18+740
2 X 30
60
5.5
2 x 12 m
47+350
2 X 30
60
5.5
2 x 12 m
Start of
Bypass
NH 9
Crossing
End of Bypass
1+060
2 X 30
60
5.5
2 x 13.4m
6+200
2 X 30
60
5.5
2 x 13.4m
Start of
Bypass
End of Bypass
2 x 13.4m
Gundugolanu
1022+930
20+30+20
70
5.5
*: The total width excludes the clear gap between two super structures, which will be dictated by
the roadway alignment.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-15
Chainage
KM
Span
(m)
VC
(m)
Width
(m)
Crossing Location
1031+452
50
3.5
Chainag
e km
Span
arrangement
Minimum
Vertical
Clearance (m)
Total
width* (m)
Remark
Vijayawada Bypass
1
3+980
1 x 7.5
3.5
2 x 12
22+800
1 x 7.5
3.5
2 x 12
24+695
1 x 7.5
3.5
2 x 12
35+950
1 x 7.5
3.5
2 x 12
40+080
1 x 7.5
3.5
2 x 12
41+120
1 x 7.5
3.5
2 x 12
1 x 7.5
3.5
2 x 13.4
Atkur
1 x 7.5
3.5
2 x 13.4
Telaprolu Access
1 x 7.5
3.5
2 x 13.4
Ambapuram
1 x 7.5
3.5
2 x 13.4
Kodurupadu Acecess
1 x 7.5
3.5
2 x 13.4
Veeravalli
1 x 7.5
3.5
2 x 13.4
Bommuluru
1 x 7.5
3.5
2 x 13.4
Dasarigudem
1073+70
5
1068+95
5
1067+92
0
1066+18
0
1065+26
0
1054+31
12
13
0
1051+94
0
*: The total width excludes the clear gap between two super structures, which will be dictated by
the roadway alignment
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-16
Chainage
km
Span
arrangement
Minimum
Vertical
Clearance (m)
Total width*
(m)
Remarks
Vijayawada Bypass
1
12+305
1x12
5.5
2 x 12
Mandadam Road
31+190
1x12
5.5
2 x 12
Nunna Road
43+380
1x12
5.5
2 x 12
Agiripalli Road
5.5
2 x 13.4
3+010
1 x 18
1075+100
1 x 12
5.5
2 x 13.4
Pedda avutapalli
1071+544
1 x 12
5.5
2 x 13.4
Pottipadu
1063+770
1 x 12
5.5
2 x 13.4
Veeravalli
1050+370
1 x 12
5.5
2 x 13.4
Eluru bypass
1033+610
1 x 12
5.5
2 x 13.4
Eluru bypass
10
1030+230
1 x 12
5.5
2 x 13.4
Denduluru
*: The total width excludes the clear gap between two super structures, which will be dictated by
the roadway alignment.
New Minor Bridges for Vijayawada Bypass
Type of Structure
SIDE
Total
Width*
3+360
Proposed Span
arrangement
Nos x length (m)
1x31
2x12
5+840
2x5x3
2x12
8+210
2x26
2x12
9+560
1x5x3
2x12
10+450
1x4x2
2x12
10+980
1x5x2
2x12
13+020
2x4x2
2x12
19+305
2x4x2
2x12
21+240
1x20
2x12
10
22+035
1x5x3
2x12
11
22+815
2x4x2
2x12
12
23+350
2x19
2x12
13
24+350
2x5x2
2x12
14
24+850
2x4x2
2x12
15
26+350
1x5x3
2x12
S.No
Chainage
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-17
Type of Structure
SIDE
Total
Width*
29+340
Proposed Span
arrangement
Nos x length (m)
1x25
2x12
17
30+565
1x10
2x12
18
33+250
1x28
2x12
19
33+715
2x4x2
2x12
20
34+250
1x12
2x12
21
35+250
1x6x2
2x12
22
36+500
1x12
2x12
23
40+900
1x10
2x12
24
42+690
1x5x2
2x12
25
43+880
1x5x2
2x12
26
44+690
1x25
2x12
27
44+950
2x4x2
2x12
S.No
Chainage
16
Chainage
2+750
Proposed Span
arrangement
Nos x length (m)
1x7.5x3.5m
5+391
2x16
Type of Structure
SIDE
Total
Width*
2x15.20
2x15.20
*: Total width excludes the clear gap between the two superstructures, which will be dictated by
roadway alignment.
New Minor Bridges on Service Roads
S. No
1
2
3
4
5
6
7
8
Structure
No
MNB No:
29/2
MNB No:
32/2
MNB No:
36/1
MNB No:
37/6
MNB No:
39/2
MNB No:
42/1
MNB No:
49/1
MNB No:
67/3
Chainage
Km
Span
Arrangement
(m)
Total Width
(m)
Remarks
1075+820
3 x 4.45
8.70
1072+737
3x6.80
8.70
1068+844
3 x 6.75
8.70
1067.326
6x6.75
8.70
1065+780
3 x 5.75
8.70
1062+540
2x3.90
8.70
1055+743
8x5.75
8.70
1037+246
1 x 9.30
8.70
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Structure
No
S. No
MNB No:
76/1
MNB No:
9
10
Reports Code
Page
Rev.
13-18
Chainage
Km
Span
Arrangement
(m)
Total Width
(m)
Remarks
1030+415
5 x 6.40
8.70
LHS
1022+851
2 x 7.20
8.70
LHS
#: The length of structures indicated is absolute minimum which is equal to the length of the
existing structure. The actual length required for the service road structure may vary.
New Minor Bridges on Service Roads in Vijayawada bypass
S.No
Chainage
22+815
Proposed Span
arrangement
Nos x length (m)
2x4x2m
24+850
40+900
Type of Structure
SIDE
Total
Width
2x8.75 m
2x4x2m
2x8.75 m
1x10m
2x8.75m
Chainage
(km)
43+250
Name
of
River /
stream
Chimala
Vagu
Proposed Span
Arrangement
nos x length(m)
Type of
structure
Side
2 x 30 m
PSC T girder
and slab
Total Width
(m)
2x8.70m
S.
No
Chainage
(km)
Name
of
River /
stream
Proposed Span
Arrangement
nos x length(m)
15+970
Krishna
River
1x14(Underpass)
+101x30+1x40+2x30
43+250
Chimala
Vagu
2x30
Type of
structure
PSC T
girder and
slab
PSC T
girder and
slab
Side
Total Width*
(m)
2x12m
2x12m
*: Total width excludes the clear gap between the two superstructures, which will be dictated by
roadway alignment.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-19
Total
Width**
2+500
Proposed Span
Arrangement
nos x length(m)
1x20+(3x24)*+1x20
2x12m
20+590
8x30+(3x24)*+8x30
2x12m
45+870
7x30+(1x24+1x30+1x24)+3x30
2x12m
S.No
Chainage
Chainage
Type of Crossing
Span Arrangement
Type of Structure
1+260
Nallah/Canal
1x4x2m
2
3
4
5
6
7
1+520
5+030
5+560
7+030
7+680
8+970
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
1x5x3m
1x4x2m
1x5x2m
1x5x3m
1x5x3m
3x1.2 m
8
9
10
11
12
13
8+990
10+710
17+570
17+730
18+070
18+340
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
3x1.2 m
1x5x2m
1x5x2m
4x1.2 m
2x1.2 m
2x1.2 m
14
15
16
17
18
19
18+975
19+960
21+835
23+020
23+730
24+900
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
3x1.2 m
1x4x2m
2x1.2 m
3x1.2 m
3x1.2 m
2x1.2 m
20
21
22
23
24
25
25+065
25+905
26+565
27+055
27+430
27+690
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
3x1.2 m
3x1.2 m
2x1.2 m
2x1.2 m
2x1.2 m
1x5x3m
26
27
28
29
30
31
28+070
28+130
28+395
28+900
29+855
31+540
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
2x1.2 m
2x1.2 m
2x1.2 m
1x4x2m
1x1.2 m
1x1.2 m
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
Box
Box
Box
Box
Box
R.C.C Box
R.C.C Hume Pipe
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-20
S.No
32
Chainage
31+610
Type of Crossing
Nallah/Canal
Span Arrangement
1x1.2 m
Type of Structure
R.C.C Hume Pipe
33
34
35
36
37
38
31+980
32+140
32+280
32+500
32+570
33+070
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
2x1.2 m
2x1.2 m
1x1.2 m
2x1.2 m
1x1.2 m
1x5x3m
39
40
41
42
43
44
33+930
34+410
34+630
35+718
35+930
36+085
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
2x1.2
2x1.2
2x1.2
2x1.2
2x1.2
4x1.2
m
m
m
m
m
m
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
Hume
Hume
Hume
Hume
Hume
Hume
Pipe
Pipe
Pipe
Pipe
Pipe
Pipe
45
46
47
48
49
50
36+540
37+005
37+735
39+258
39+920
41+770
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
1x1.2
1x1.2
2x1.2
1x1.2
4x1.2
2x1.2
m
m
m
m
m
m
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
Hume
Hume
Hume
Hume
Hume
Hume
Pipe
Pipe
Pipe
Pipe
Pipe
Pipe
51
52
53
54
41+990
42+182
42+230
42+490
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
1x1.2 m
1x1.2 m
1x4x2m
1x1.2 m
Chainage
Type of Crossing
Span Arrangement
Type of Structure
55
0+720
Nallah/Canal
2x1.2 m
Pipe Culvert
56
57
58
59
60
61
1+490
1+820
1+950
2+060
3+170
3+530
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
2x1.2 m
1x4x2m
2x1.2 m
1x5x2m
1x1.2 m
2x1.2 m
Pipe Culvert
Box Culvert
Pipe Culvert
Box Culvert
Pipe Culvert
Pipe Culvert
62
63
64
65
66
67
3+720
3+780
3+890
4+010
5+060
5+540
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
2x1.2 m
2x1.2 m
2x1.2 m
2x1.2 m
1x4x2m
1x4x2m
Pipe Culvert
Pipe Culvert
Pipe Culvert
Pipe Culvert
Box Culvert
Box Culvert
** Total width of culvert shall match with the total width of approaches / highway including
earthen shoulders.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
13-21
Chainage
Type of Crossing
Span Arrangement
Type of Structure
18+340
Nallah/Canal
2x1.2 m
Pipe Culvert
2
3
4
5
6
7
18+975
23+020
35+718
35+930
36+085
39+920
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
Nallah/Canal
3x1.2
3x1.2
2x1.2
2x1.2
4x1.2
4x1.2
Pipe
Pipe
Pipe
Pipe
Pipe
Pipe
m
m
m
m
m
m
Culvert
Culvert
Culvert
Culvert
Culvert
Culvert
Chainage
Type of Crossing
Span Arrangement
Type of Structure
3+170
Nallah/Canal
1x1.2 m
Pipe Culvert
** Total width of culvert shall match with the total width service road including earthen shoulders.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
14-1
14.1
14.2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
14-2
14.
14.1
EXISTING SITUATION
There is no existing highway traffic management system. The O&M Contract is presently undertaken,
however these do not include any HTMS.
14.2
A full system needs to be provided [and fully maintained for the life of the concession agreement],
and the requirements for this Highway Traffic Management System shall be given in the Manual for 6
laning.
The proposed system shall consist of following components:
Real time 3-way communication system between data source-control center-data sources &
display units
Highway Patrol
Lighting System
The ATMS/HTMS system shall be as per the provisions of 6-Lane manual. In addition, a Backbone
Communication System, consisting of Optical Fibre backbone cable running along the project
highway, is needed to join all the above together.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
15-1
15.1
GENERAL..................................................................................................................................................2
15.2
15.3
15.4
15.5
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
15-2
15.
USER FACILITIES
15.1
GENERAL
The requirement for User Facilities and Wayside Amenities has to be in accordance with the
provision of guidelines of IRC SP: 87-2010. The important facilities like underpasses for vehicle
crossings, flyovers etc are mentioned in chapters-13 of this report, and in chapter 16. The specific
area of Amenity Areas and Parking Areas proposed along the project highway are covered hereafter.
For the road user, wayside amenities such as drinking water, telephone booths, bus shelters and
road side rest areas are of value. The industrialisation and socio-economic development has
increased the use of telephones. Telephone booths are often available in urban areas but their
provision along highway would also be beneficial. Road side rest areas are essential for long
distance road travellers of main highway. Long distance journeys cause driver fatigue resulting in
poor driving and increase in driver reaction time. In India such services are starting to be provided
but more are needed. To promote safer driving, drivers should be encouraged to have adequate rest
when they feel tired. The provision of rest areas which are conveniently located and are economical
and easy to maintain will help achieve this.
15.2
The general guidelines which shall be considered in the planning and designing of a wayside amenity
can be broadly as follow;
i.
The facilities are to be provided along highway where these do not exist at present or lacking
ii.
Easy availability of the required land for infrastructure development should be kept in view
iii. Site should be away from urban influence and any other similar wayside complex
iv. Feasibility of locating the facility close to scenic/historic/tourist spots should be kept in view
v.
Desirably the site should be about 200m away from a road junction
vi. The road alignment should preferably have easy gradients in the vicinity of the complex
vii. Availability of infrastructure facilities like electricity, drinking water and drainage etc. near the
site should be duly considered
viii. From environmental considerations, the facility should create minimum disturbance to the
surroundings
ix. Availability of any existing petrol/repair/spare parts facilities near the proposed locations
should also be kept in view
x.
The wayside amenity should be so planned as to allow phased development, subject to the
minimum stipulated scale of facilities being provided in the first instance
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
15.3
Reports Code
Page
Rev.
15-3
Project Highway shall have Rest Area(s) planned such that they are spaced at the intervals of 90
minutes to one hour of driving time between two important cities/towns. They would not be located
between 5 km of a town or city or near interchange where entrance and exit ramps could cause
weaving conflict.
Rest areas shall be planned to cater for traffic moving in both directions such that there is no need for
the vehicles on one carriageway to cross over to the other carriageway. The entry to this Rest
Area(s) would be through deceleration lane and exit through acceleration lane. The minimum width of
these lanes shall be 5.5 m.
Rest Area(s) shall be designed for the expected peak hour long term clientage and shall provide
facilities for parking, restaurant, cafeteria, toilets, telephone and shops for selling items normally
required for traveling, fuel and garage for minor repair, telephone, first aid. The parking should
include parking for expected peak hour truck traffic and cafeteria suitable for fulfilling the need for
Indian truck drivers and shall be paved by CC blocks strong enough to withstand expected loadings.
The whole area shall be elaborately landscaped to provide a pleasing environment.
At locations along the Project Highway where some existing eateries (Dhaba) or other informal rest
areas are located, concessionaire shall make every attempt to shift the business of such
establishments to the identified planned rest area location(s) failing which a safe entry and exit to
these establishment and parking spaces for expected peak hour vehicles shall be provided with
proper signs and markings.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
15.4
Reports Code
Page
Rev.
15-4
To meet the requirements [90km spacing approximately] we required wayside amenities maximum at
two locations;
1. At KM 1023+080(Gundugolanu)
However keeping in view of the adjacent sections of NH-5 (the Project Highway) in which there could
be already these facilities exists or being proposed in NHDP projects, it is recommended to propose
these wayside amenities in integration with nearest available facility by the concessionaire after the
detailed designs.
The suggestive layout (extract from the six-laning Manual) of the comprehensive wayside amenity is
given in the Figure below.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
16-1
16.1
16.2
16.3
16.4
16.5
16.6
16.7
16.8
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
16.
Reports Code
Page
Rev.
16-2
The Project road facility along the proposed 6 lane highway is proposed to meet the requirement of
Manual of Specifications and Standards for Six Laning of National Highways through Public Private
Partnership. The major project facilities are shall include:
Bus Shelters
Street lighting
Highway lighting
Safety Barrier
The Rest areas, Toll plazas, ATMS and other user facilities are described in Chapter 14, 15 and 16
respectively.
16.1
BUS SHELTER
The project highway has the regular movement of the government and private buses. There are
about 80 numbers of existing bus ways and bus shelters on the existing 4 lane highway. The new
bus shelters have been provided for the convenience of bus commuters and safe and unimpeded
travel on main carriageway. The new bus shelters have been provided on the proposed service road
at the following locations, governing by site conditions, which will be decided during the detailed
designs by the concessionaire.
Name of
Existing
Amenity
Bus-Stop
16.2
Existing Chainage(LHS)
Existing Chainage(RHS)
Total
1075+020,1065+400,1051+950,
1051+400
1074+950,1065+500,1052+130,
1050+280
STREET LIGHTING
Street lighting exists on the following sections [generally town section, or toll plazas. Most of this
lighting will require removal/replacement or upgrading [and thereafter maintaining and power
provision at night]. Virtually no junctions, other than in some urban areas, have lighting currently
provided.
Existing Lighting Locations
From Km post
1072+530
1050+670
To Km post
1072+630
1050+770
Location
Toll Plaza
Toll Plaza
The street light and high mast light system have to provide in accordance with the manual provisions.
Tentatively the street light has been proposed along the town/ villages for safe movement of traffic on
the service road. The village/urban locations where street light is to be provided are given below.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
16-3
Chainage (Km)
Length
From
To
(Km)
Starting of Bypass
0+000
0+100
0.1
Flyover at Ch 0+795
0+745
0+845
0.1
ROB at Ch 2+500
2+450
2+550
0.1
PUP at Ch 3+980
3+930
4+030
0.1
VUP at Ch 12+305
12+255
12+355
0.1
14+540
17+400
2.86
Flyover at Ch 18+740
18+690
18+790
0.1
ROB at Ch 20+590
20+540
20+640
0.1
PUP at Ch 22+800
22+750
22+850
0.1
10
PUP at Ch 24+695
24+645
24+745
0.1
11
VUP at Ch 31+190
31+140
31+240
0.1
12
PUP at Ch 35+950
35+900
36+000
0.1
13
PUP at Ch 40+080
40+030
40+130
0.1
14
PUP at Ch 41+120
41+070
41+170
0.1
15
VUP at Ch 43+380
43+330
43+430
0.1
16
ROB at Ch 45+873
45+823
45+923
0.1
17
Flyover at Ch 47+300
47+250
47+350
0.1
18
Ending of Bypass
47+780
47+880
0.1
19
Pedda avutapalli
1075.15
1075.05
0.1
20
Atkur
1074.18
1073.08
1.1
21
Pottipadu
1071.59
1071.49
0.1
22
Telaprolu Access
1069.01
1068.91
0.1
23
Ambapuram
1067.97
1067.87
0.1
24
Kodurupadu Acecess
1066.23
1066.13
0.1
25
Veeravalli
1065.31
1065.21
0.1
26
Veeravalli
1063.82
1063.72
0.1
27
Starting of Bypass
0.1
0.1
28
Flyover at Ch 1+100
0.95
1.05
0.1
29
VUP at Ch 3+000
2.95
3.05
0.1
30
At Ch 4+000
3.95
4.05
0.1
31
Flyover at Ch 6+000
5.95
6.05
0.1
32
Ending of Bypass
6.617
6.717
0.1
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
16-4
Structure
Sl. No.
Chainage (Km)
Length
From
To
(Km)
33
Bommuluru
1054.36
1054.26
0.1
34
Dasarigudem
1051.99
1051.89
0.1
35
Eluru bypass
1050.42
1050.32
0.1
36
Eluru bypass
1033.66
1033.56
0.1
37
Denduluru
1030.28
1030.20
0.1
38
Gundugolanu
1023.08
1022.68
0.4
The proper lighting has been proposed at all Pedestrian Subway & Underpass, Vehicular
Underpasses.
The all entry exit ramps along the project highway should be properly lighted. The lighting system
has been proposed at all the bus shelters and the rest area.
16.3
The High mast lighting has been proposed at the following location along the project highway:
Flyover locations
o Gundugolanu ( KM 1022+930)
On the proposed bypasses Provide High mast lighting at locations specified below .
16.4
S. No
Chainage, Km
1
2
3
4
5
0+795
11+500
18+740
35+000
47+350
6
7
1+100
6+000
Location
Vijayawada Bypass
Start of Bypass Jn.
Toll Plaza Vijayawada Bypass Section 1
At NH 9 flyover/Grade separator
Toll Plaza Vijayawada Bypass Section 2
End of Bypass Jn.
Hanuman Junction Bypass
Start of Bypass Jn.
End of Bypass Jn.
The pedestrian guard railing between the service road and the main carriageway has to be provided
along the urban sections and the villages/towns area along the project highway for the safe
movement of the pedestrian traffic. The railing is not required along the length of villages where the
underpasses have been proposed.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
16-5
The pedestrian guard rails has to be provided between the nearest at grade junction and the bus
stop for the safe movement of the pedestrian traffic.
16.5
SAFETY BARRIER
The W beam/ concrete safety barrier has been proposed along the project highway at following
locations:
16.6
The gantry sign mounted on post indicating the village name and the important road it would lead to
at all exit locations. The position of these signs should meet the requirement of the IRC 67.
The pavement marking along the project highway should meet the requirement of the IRC 35. The
proper zebra marking has been proposed at the Underpass locations for safe crossing of the
pedestrian traffic. The safety features such as delineators, cats eyes, hazard markers and safety
barrier at hazardous locations has been proposed on the project highway.
16.7
The Truck Lay byes & Rest areas have to be provided at the locations given below.
S. No
Section Name
Service
Chainage, Km
Side
Vijayawada-Gundugolanu
1072+240
RHS
Vijayawada-Gundugolanu
1072+240
LHS
Service
Chainage, Km
Side
Rest Area
1023+080
RHS
S. No
1
16.8
Section Name
Vijayawada-Gundugolanu
The hectometre/ Kilometre and Boundary stones have been proposed as per the requirement of the
six laning manual.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-1
17.1
INTRODUCTION .....................................................................................................................................2
17.2
17.3
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-2
17.
THE SCHEME
17.1
INTRODUCTION
The scheme is the 96% widening of the existing road from 4 to 6 lanes, excluding a section of
about few km through ROB and Canal Bridges for a length of about 8km.
The scheme includes:
Service Roads: Provide 5.5m service road in rural areas for about 73.318 aggregate
kilometres and
Widening of ROB & Grade Separated Structures: Improvement and widening of 2 ROBs
and 10 Underpasses/Cattle crossings.
6 Flyovers
13 Pedestrian Underpasses
10 Vehicular Underpasses
Lay Bays and Amenities: Provide 8 bus bays with shelter on service road wherever
applicable, 2 truck lay bays, 1 rest areas and 3 toll plazas with base camps.
Others: Provide Highway Traffic Management System, User Facilities, Roadside Furniture
and safety features, localised lighting.
The current right-of-way is insufficient for all this expansion, so some very significant land
acquisition [and property acquisition/demolition] is needed in towns [and some villages| However
where 4 lane continuous viaducts are proposed landtake [along with the accompanying very large
property demolition requirements] will be either eliminated or very much minimised
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
17.2
Reports Code
Page
Rev.
17-3
THE SCHEME
Discipline
Existing road section of NH5 [all 4 lanes currently]
Length
Existing Structures
Toll Plazas
Others
Description
48.99 Km
1
Two [on Eluru Bypass]
10
See Chapter 11. Most of the retained road will
require roughness correction, using a thin
overlay with the correct formulation to avoid
flow. Only the urban area will require a structural
overlay, while the DBST section should be
studied with more attention (probably under
designed otherwise one would not adopt a
DBST).
49.0km of 6-lane with 2x1.5m paved shoulders
[excluding service roads] 47.88km
73.318
There are 34 locations of existing structures
[greater than 6m] on the road.
Most existing structures need to be widened as
applicable.
302 new structure [including the 2 six lane long
viaducts and 6 four lane long viaducts
mentioned below] locations on mainline and 123
additional structures [see Table 18.3.4] for
service road continuity.
4 lane viaducts:
2 ROBs
Krishna River Bridge 3144m
2 plazas currently, likely optimum strategy will
be 3 full plazas with base camps by shifting one
location.
Provision of full Highway Traffic Management
System
ATCC
VMS
MET System
Wayside amenities
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-4
Chainage(km)
From
To
Length
(km)
CS
Type
Chainage(km)
S.
No
From
To
Length
(km)
CS
Type
31
40+849
41+384
0.535
0+000
0+100
0.100
32
41+384
43+067
1.684
0+100
0+491
0.391
33
43+067
43+732
0.664
0+491
1+190
0.699
34
43+732
45+687
1.955
1+190
2+444
1.254
35
45+687
46+059
0.372
2+444
2+556
0.112
36
46+059
47+017
0.958
2+556
3+736
1.180
37
47+017
47+742
0.725
3+736
4+248
0.512
38
47+742
47+780
0.038
4+248
11+200
6.952
39
47+780
47+880
0.100
11+200
11+800
0.600
10
11+800
11+961
0.161
40
1076+480
1075+400
1.080
11
11+961
12+681
0.720
41
1075+400
1074+800
0.600
12
12+681
14+153
1.472
42
1074+800
1073+905
0.895
4A
13
14+153
17+770
3.617
43
1073+905
1073+505
0.400
14
17+770
18+316
0.546
44
1073+505
1072+980
0.525
15
18+316
19+169
0.853
45
1072+980
1071+844
1.136
4A
16
19+169
20+314
1.145
46
1071+844
1071+244
0.600
17
20+314
20+866
0.552
47
1071+244
1069+155
2.089
4A
18
20+866
22+574
1.708
48
1069+155
1068+755
0.400
19
22+574
23+047
0.472
49
1068+755
1068+120
0.635
20
23+047
24+463
1.416
50
1068+120
1067+720
0.400
21
24+463
24+955
0.492
51
1067+720
1066+380
1.340
4A
22
24+955
30+831
5.876
52
1066+380
1065+980
0.400
23
30+831
31+590
0.759
53
1065+980
1065+460
0.520
24
31+590
34+700
3.110
54
1065+460
1065+060
0.400
25
34+700
35+300
0.600
55
1065+060
1064+070
0.990
4A
26
35+300
35+703
0.403
56
1064+070
1063+470
0.600
27
35+703
36+199
0.496
57
1063+470
1060+800
2.670
4A
28
36+199
39+827
3.628
29
39+827
40+275
0.448
58
0+000
0+750
0.750
30
40+275
40+849
0.573
59
0+750
1+450
0.700
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-5
Chainage(km)
S.
No
From
60
Chainage(km)
To
Length
(km)
CS
Type
S.
No
From
To
Length
(km)
CS
Type
1+450
2+642
1.192
80
1046.060
1042.450
3.610
61
2+642
3+350
0.708
81
1042.450
1041.850
0.600
62
3+350
3+700
0.350
82
1041.850
1040.300
1.550
63
3+700
4+300
0.600
83
1040.300
1039.630
0.670
64
4+300
5+650
1.350
84
1039.630
1039.180
0.450
65
5+650
6+350
0.700
85
1039.180
1038.530
0.650
66
6+350
6+717
0.367
4A
86
1038.530
1037.080
1.450
87
1037.080
1036.080
1.000
1055.650
1055.105
0.545
4A
88
1036.080
1033.910
2.170
68
1055.105
1054.510
0.595
89
1033.910
1033.310
0.600
69
1054.510
1054.110
0.400
90
1033.310
1030.530
2.780
70
1054.110
1053.980
0.130
91
1030.530
1029.930
0.600
71
1053.980
1052.140
1.840
4A
92
1029.930
1027.487
2.443
72
1052.140
1051.740
0.400
93
1027.487
1027.080
0.407
73
1051.740
1051.080
0.660
4A
94
1027.080
1024.905
2.175
74
1051.080
1050.480
0.600
95
1024.905
1024.255
0.650
75
1050.480
1049.980
0.500
96
1024.255
1023.280
0.975
76
1049.980
1047.580
2.400
97
1023.280
1022.480
0.800
77
1047.580
1046.980
0.600
78
1046.980
1046.660
0.320
79
1046.660
1046.060
0.600
Total length
103.59
km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-6
4a
Description
Four-lane cross section with Raised median + fencing both side of main carriageway + embankment slope 2H:1V + Unlined
longitudinal drain and Utility corridor both side in Non Built-up Area
Four-lane Flyover/Underpass Approach cross section with 12m deck width with RE wall/RCC Retaining wall (excluding viaduct
portion) up to carriageway top level over which RCC crash barrier shall rest + 4.5m median+ 1.5m wide separator cum RCC lined cover
drain between Approach and 5.5m wide (excluding shyness) service road both side + 1.5m wide footpath cum utility duct both side after
service road
Four-lane ROB/Major Bridge Approach cross section with 12m deck width with RE wall/RCC Retaining wall (excluding viaduct
portion) up to carriageway top level over which RCC crash barrier shall rest + 4.5m median+ 1.5m wide separator cum RCC lined cover
drain between Approach .
Six-lane cross section, paved width of (2x10.5+2x1.5) with Raised median of 4.5m width, edge shyness of 0.25m each on both sides +
2.0m earthen shoulder on both sides + chain link fencing on both sides at the edge of Right of way (ROW) + embankment slope 2H:1V
+ Unlined longitudinal drain + Utility corridor of 2.0m wide on both sides in Non Built-up Areas
Six-lane cross section, with Raised median of 4.5m width, edge shyness of 0.25m each on both sides + 2.0m earthen shoulder on both
sides + chain link fencing on both sides of main carriageway (MCW), placed between MCW and service road + embankment slope
2H:1V + Unlined longitudinal drain + 5.5m wide Service Road on both sides + 1.5m earthen shoulder on either sides of the service roads
+ Utility corridor of 2.0m wide on both sides in Non Built-up Areas
Six-lane cross section with Raised Median, 1.5m wide separator cum RCC lined cover drain with Thrie beam metal barrier between
paved shoulder and 5.5m wide service road both side + 1.5m wide footpath cum Utility duct both side after service road in Built-up area.
Total Length
34.650
7.377
4.653
16.842
12.675
7.605
Rural Six-lane cross section with retaining wall(s) at Canal locations where the existing median is 2.5m; Symmetrical widening.
8.373
Rural Six-lane cross section at Canal locations where the existing median of 2.5m to replace by crash barrier in Asymmetrical widening.
0.407
Six-lane Flyover/Underpass Approach cross section with 13.4m deck width with RE wall/RCC Retaining wall (excluding viaduct
portion) up to carriageway top level over which RCC crash barrier shall rest + 1.5m wide separator cum RCC lined cover drain between
Approach and 5.5m wide (excluding shyness) service road both side + 1.5m wide footpath cum utility duct both side after service road
9.208
1.800
Total
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
103.59 km
17.3
Reports Code
Page
Rev.
17-7
The scheme for service roads is tabled in Table 17.3.1. Requirements are shown for both the left and
right of the existing road. The provisions of these service roads means new bridges [or underpasses]
are needed:
As crossing structures under the 6 lane carriageway [to link the LHS and RHS service roads
[see Table 17.3.2]
As crossing structures over the 6 lane carriageway [flyovers, footbridges], also see Table
17.3.2;
As structures on the service roads where drainage channels are crossed [i.e. matching the
drainage provisions on the 6 lane mainline] see Table 17.3.3.
Where crossing structures [and flyovers] are provided in some cases existing bridge decks need to
be raised [since the provision of each crossing structure means several hundred metres of existing
mainline roadway has to be re-profiled as approximately table in next page [exact details are subject
to detail design by the Concessionaire]. The amount of re-profiling is determined by the rise in
pavement level needed at the crossing location [this is a function of clearance provision, structural
height of roof of superstructure, and amount if any the crossing level of the structure can be
below the main road level]. Details in respect of the major bridges are described in Chapter 13
[section 13.5].
Details on the required removal of existing bridge defects, to be carried out by the Concession
Company, is given in Section 13.3. The scheme includes making most bridges on the road 6 lanes
[or equivalent of 6 lanes]. As most of the major bridges are 2 lanes in width [each way] and cannot be
widened the assumption used is most of the major bridges are retained unless there is a structural
problem already.
Table showing length of road to be realigned due to local rise of vertical profile [at underpass]
for installation of underpasses for cross access (Grades Table as per IRC)
Design Speed 100
Design Speed 80
Rise
Grade %
Length
Grade %
Length
1
0.932
215
1.314
152
1.5
1.142
263
1.610
186
2
1.318
303
1.859
215
2.5
1.474
339
2.078
241
3
1.614
372
2.276
264
3.5
1.744
401
2.459
285
4
1.864
429
2.628
304
4.5
1.977
455
2.788
323
5
2.084
480
2.939
340
5.5
2.186
503
3.082
357
6
2.283
526
3.219
373
6.5
2.376
547
3.351
388
7
2.466
568
3.477
403
7.5
2.553
588
3.599
417
8
2.636
607
3.717
430
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-8
Length (km)
Remarks
0+495
1+186
5.5
0.691
both sides
3+74
11+965
18+32
22+578
24+467
30+835
4+244
12+677
19+165
23+043
24+951
31+586
5.5
5.5
5.5
5.5
5.5
5.5
0.504
0.712
0.845
0.465
0.484
0.751
both sides
both sides
both sides
both sides
both sides
both sides
5.5
5.5
5.5
5.5
5.5
0.488
0.440
0.527
0.657
0.717
both sides
both sides
both sides
both sides
both sides
5.5
15.680
both sides
0+754
2+646
5+658
0.692
0.700
1.059
both sides
both sides
both sides
1055+793
1050+476
1047+576
1046+656
1042+446
1040+296
4.707
0.492
0.592
0.592
0.592
0.662
both sides
both sides
both sides
both sides
both sides
both sides
0.642
0.992
0.592
0.592
0.792
73.318
both sides
both sides
both sides
both sides
both sides
35+707
39+831
40+853
43+071
47+021
1076+480
36+195
40+271
41+38
43+728
47+738
End of Vijayawada Bypass
1060+800
5.5
5.5
5.5
5.5
5.5
1039+176
1038+534
1037+076
1036+084
1033+906
1033+314
1030+526
1029+934
1023+272
1022+48
Both side length of Service/Slip Road
Table 17.3.2: Location of New Grade Separation Structures on the Mainline [6 laning section]
all structures 6 Lane [except where specifically stated]
S.
No
1
Chainage
(km)
1022+930
Span
arrangement
20+30+20
Effective length
Vertical
(m)
Clearance (m)
70
5.5
Total width*
(m)
2 x 13.4
Gundugolanu
2 x 12.0
2 x 12.0
Start of Bypass
NH 9
Remark
0+790
18+740
2 X 30
2 X 30
60
60
5.5
5.5
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
S.
No
Chainage
(km)
Reports Code
Page
Rev.
17-9
Span
arrangement
Effective length
Vertical
(m)
Clearance (m)
Total width*
(m)
Remark
Crossing
47+350
2 X 30
60
5.5
2 x 12.0
End of Bypass
60
60
5.5
5.5
2 x 13.4
2 x 13.4
Start of Bypass
End of Bypass
1+060
6+200
2 X 30
2 X 30
Chainage
km
Span
arrangement
Minimum Vertical
Clearance (m)
Total width*
(m)
Remarks
Vijayawada Bypass
1
12+305
1x12
5.5
2 x 12
Mandadam Road
31+190
1x12
5.5
2 x 12
Nunna Road
43+380
1x12
5.5
2 x 12
Agiripalli Road
1 x 18
5.5
2 x 13.4
3+010
1075+100
1 x 12
5.5
2 x 13.4
Pedda avutapalli
1071+544
1 x 12
5.5
2 x 13.4
Pottipadu
1063+770
1 x 12
5.5
2 x 13.4
Veeravalli
1050+370
1 x 12
5.5
2 x 13.4
Eluru bypass
1033+610
1 x 12
5.5
2 x 13.4
Eluru bypass
10
1030+230
1 x 12
5.5
2 x 13.4
Denduluru
S. No
Chainage
km
Span
arrangement
Minimum Vertical
Clearance (m)
Total width*
(m)
Remark
Vijayawada Bypass
1
3+980
1 x 7.5
3.5
22+800
1 x 7.5
3.5
24+695
1 x 7.5
3.5
35+950
1 x 7.5
3.5
40+080
1 x 7.5
3.5
41+120
1 x 7.5
3.5
2 x 12
2 x 12
2 x 12
2 x 12
2 x 12
2 x 12
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-10
S. No
Chainage
km
Span
arrangement
Minimum Vertical
Clearance (m)
Total width*
(m)
1073+705
1 x 7.5
3.5
2 x 13.4
Atkur
1068+955
1 x 7.5
3.5
2 x 13.4
Telaprolu Access
1067+920
1 x 7.5
3.5
2 x 13.4
Ambapuram
10
1066+180
1 x 7.5
3.5
2 x 13.4
Kodurupadu Acecess
11
1065+260
1 x 7.5
3.5
2 x 13.4
Veeravalli
12
1054+310
1 x 7.5
3.5
2 x 13.4
Bommuluru
13
1051+940
1 x 7.5
3.5
2 x 13.4
Dasarigudem
Remark
1
2
3
4
5
6
7
8
9
10
Structure
No
MNB No:
29/2
MNB No:
32/2
MNB No:
36/1
MNB No:
37/6
MNB No:
39/2
MNB No:
42/1
MNB No:
49/1
MNB No:
67/3
MNB No:
76/1
MNB No:
Chainage
Km
LHS
Length
(m)
1075+820
3 x 4.45
1072+737
3x6.80
1068+844
3 x 6.75
1067.326
6x6.75
1065+780
3 x 5.75
1062+540
2x3.90
1055+743
8x5.75
1037+246
1 x 9.30
1030+415
5 x 6.40
1022+851
2 x 7.20
RHS
Type
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
Length
(m)
3 x 4.45
3x6.80
3 x 6.75
6x6.75
3 x 5.75
2x3.90
8x5.75
1 x 9.30
5 x 6.40
2 x 7.20
Type
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
RCC Solid
slab
Width of Service
Road Structure
(m)*
LHS
RHS
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
8.70
#: The length of structures indicated is absolute minimum which is equal to the length of the existing
structure. The actual length required for the service road structure may vary.
*: Deck Width indicated is absolute minimum width of Service Road including 0.25m edge shyness
on both sides, 1.8m Foot Path with railing and 0.5m Crash Barrier both sides.
**: Existing service road bridges to be widened to 8.70m width.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
17-11
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
18-1
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
18.
Reports Code
Page
Rev.
18-2
The requirements for Construction Planning, Management and Technology is given in the Manual of
Specifications and Standards for Six Laning of National Highways through Public Private Partnership published
by Department of Road Transport & Highways Ministry of Shipping, Road Transport & Highways, Government
of India. In case of any contradiction between the Manual and this Chapter, the text in the Manual
shall govern.
The existing 4 lane highway shall remain in operation and continue to be tolled during the course of
construction for expansion of its capacity to 6 lanes. This will put some constrains on construction
activities. Accordingly, the choice by the Concessionaire of construction planning methods,
construction management and technological solutions shall be subject to the following constraints.
(1)
The existing 2-lane facility, for each direction shall always be available, along main highway
or along diversion and no reduction in the capacity of the highway during construction shall
be permitted.
(2)
Construction shall not cause any deterioration in level of service more than what is expected
due to the nominal increase in traffic.
(3)
Since construction and operation shall be concurrent activities, construction shall not in any
way adversely affect safe and efficient operation of the highway.
(4)
The construction of additional features (such as underpasses, service roads) may adversely
impact the lives and business activities of the people living close to the highway boundary.
Their safety and access needs during construction shall not be compromised.
(5)
Construction traffic using the highway for approaching the construction site and parking of
construction vehicles on the highway will adversely affect the flow of normal highway traffic.
Therefore, the construction vehicles shall approach the construction site from an alternative
approach (say from service road or temporary haul roads) and park outside the existing
carriageway.
(6)
No road space shall be used for erection of temporary works or erection and launching of
any overhead structural component for permanent work. All such erection and launching
shall be from near the edge of the ROW.
(7)
Safety of the highway traffic during construction shall not be compromised and therefore, full
safety measures shall be taken during construction.
(8)
No part of the existing carriageway shall be closed for facilitating construction without
creating equivalent road space. In case it is absolutely necessary to partially close the
carriageway, it shall be for a reasonable period to be decided by the Independent Engineer.
The most essential element of construction planning shall be to ensure that equivalent capacity is
created before closing any portion of the highway for construction. This can be done either by
constructing independent diversion (which can eventually serve as service road) or by constructing
temporary diversion by carving out road space from the existing central median.
Diversion roads shall have the same width as that of the carriageway being diverted so as to ensure
that capacity of the highway or the level of service is not reduced due to construction. It shall have
fluent geometry conforming to design speed of at least 60 kmph. The pavement shall be designed for
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
18-3
10 MSA. The diversion road shall be so planned with respect to alignment and grade that it can be
eventually used as a service road. Usually, the width of one side carriageway of the existing 4 lane
highway is 8.75m while that of the diversion road shall be 7.0m. The extra paved width of 1.75m that
will become available on the service road shall be at the cost of the concessionaire and will be
utilised for meeting local needs (e.g. for parking, passing places, etc.). Once the work on main
carriageway is completed and the use of the diversion road is not required, the entry to and exit from
the diversion road shall be permanently closed such that they are not used as unauthorised entry/exit
ramps.
In case space on the existing carriageway is to be created for use as diversion, it shall be done by
knocking off the central median, removing the filling and paving the median portion with crushed
stone drainage layer over the existing GSB sub base top level followed by WMM base bituminous
layer in thickness appropriate for traffic level of 10MSA. The knocked off median shall be replaced by
pre cast concrete crash barrier segments placed at the edge of the extended pavement and tied
together to provide stability against crash. This arrangement can provide only one extra lane of
diversion in the usual case where median width is only 4.5m.
Eventually the median has to be restored to its original condition by milling the pavement and
removing the bituminous layers and WMM base and leaving the GSB layer intact for median
drainage. The restored median kerb, however, shall extend up to the top of the drainage layer of the
existing pavement such that water in the median remains confined within the kerbs and drain through
the drainage layer. The milled pavement material can be used for service road construction with the
approval of Independent Engineer.
Construction shall be managed in such a way that sequence of construction operations, coordination
of various construction activities, logistics of material and equipment movement, community needs of
access and safety, and management of the highway traffic during construction lead to least
disruption during construction. Construction activities shall generally start at the periphery and
proceed towards the main highway in the end such that diversion alternatives are available when the
main highway becomes the centre of construction activities.
Subject to actual site requirement, the general sequence of construction activities shall be in the
following order:
I. Construction of haul roads
II. Construction of drains, toe walls
III. Construction of service roads, protection of cut slopes abutting properties (wherever
required)
IV. Construction of underpasses
V. Construction of embankment for widening of the carriageway up to sub grade level
VI. Barricading of the main carriageway at the shoulder marking
VII. Excavation of the earthen shoulder of the existing carriageway
VIII. Building of pavement layers
IX. Construction of bridges, culverts, flyovers, grade separators at various points of time as per
overall planning
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
18-4
Appropriate technological solutions shall be adopted to overcome some of the site constraints and to
ensure least disruption due to construction, as conventional technology in such cases may be unsafe
or disruptive. Some of the areas where innovations shall be required are shoring the cut slopes so
that adjoining properties are not endangered, pushing a box to provide an underpass, launching
large pre-cast elements for grade separators, underpasses, etc.
Shoring the cut slopes: Appropriate solutions shall be designed for permanent solution of the cut
slopes. Soil nailing, concrete buttresses, sheet piling or any other solution adequately designed and
approved by Independent Engineer shall be adopted.
1
Adequate space for construction of casting and thrust beds shall be arranged
ii)
Construction of thrust beds will involve deep excavation. The excavated face shall invariably
be shored/protected. Where such excavation is near some properties, it shall be ensured
that these properties do not suffer any damage.
iii)
Top of the excavation shall invariably be cordoned/fenced to rule out any mishaps or
accident.
iv)
The rate of construction (pushing) shall be regulated is a manner that the existing road on
top does not get damaged.
v)
vi)
After construction is completed, the thrust bed shall be back filled and compacted in layers to
its original density.
Actually there are very few if any places where on inspection this seems a practical construction method, but
this situation may change in detail design.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-1
19.1
19.1.1
Introduction......................................................................................................................................2
19.1.2
19.1.3
19.1.4
19.2
19.2.1
19.2.2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-2
19.
19.1
19.1.1 Introduction
The preliminary Environmental Examination for the proposed project has been undertaken as a
parallel exercise with the Engineering Analysis, so as to bring out the environmental concerns in
planning and the proposed design. The basic aim of the present study is to assess the magnitude of
actual and potential environmental concerns due to conversion of the existing 4 lane National
Highways into six lanes. This is also to ensure that the environmental considerations are given due
weightage, in the design of proposed highway improvements being studied. Basic idea is to minimize
adverse environmental and social impacts with best possible engineering solutions at the optimal
cost to make development environmentally sound and sustainable.
Environmental Screening of the study area has the following major objectives:
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-3
Physical Resources
Topography
The configuration of the project area is more or less plain and lies in coastal Andhra Pradesh. The
area is crisscrossed with river Krishna river Godavari and network of various irrigation canals built on
the two rivers.
Situation
This section of project road passes through districts of Guntur, Krishna, W.Godavari and E. Godavari
in the State of Andhra Pradesh. The highway generally traverses through the agricultural zones, and
in the end passes for a short distance, close to Divencheruvu Reserve forest. The existing four lane
development itself is not witnessing designed traffic growths owing to the project highway, as per
discussions with stakeholders and the Engineering team, lying in agricultural hinterland with no major
commercial activity beyond the agricultural. This results in good environmental condition with air,
water & noise levels lying generally within limits. But, the situation may change with time
necessitating regular monitoring of the environmental parameters along the highway and especially
the towns by NHAI/Concessionaire, so that mitigation measures could be enforced in the event of air,
water, noise levels cross permissible levels
Geology, Soils
The vast stretch of the area is represented by Archaeans.The major geological formation in the area
are of Khondalites series with felspar-quartz-biotite genesis, felspar-quartz genesis. These are pre-
Source:Baseline Environmental status, vol.- IV EIA, RAP REPORT; ROAD CONSTRUCTION CONTRACT
PACKAGE AP-17
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-4
cambrian series and are coarse grained rocks and stretched from NE to SW with steep dips. The
general stratography of the area is presented in the following table:
Geology
Formation
Age
Recent to present
Upper Jurrassic
Archaeans
Archaeans
Soils
The soil in the stretch is mainly red soil with texture sandy to silty clayey. The soils are mostly alluvial
derived soils. These are the soils in general with low to medium plasticity except at few locations with
high plastic clayey soils (black cotton). The soils lack adequate drainage and lead to deterioration in
the soil structure. The soils in general are fertile.
Climate
Rainfall The climate of the study area is tropical sub humid with annual precipitation ranging from
1400 - 1600 mm and potential evapo-transpiration varying from 1300-1500 mm. The rainfall in the
area is brought by two spells i.e. South-West monsoon (June-September) and North- East monsoon
(October to November)
Temperature The temperature of the region varies between 36-18 C. It is very warm in May with
a mean maximum temperature touching to 39 C. The seasonal variation in the temperature is
presented in the following table
Season
Maximum
Minimum
Range
Winter Season
32.4
17.1
32-17
Summer Season
39.2
20.4
39-20
Rainy Season
33.1
24.6
33-24
Non-Rainy Season
30.8
17.3
32-17
Humidity - The climate in the region is generally sub-humid. The humidity is slightly less than the
adjacent coastal areas. The relative humidity ranges, generally, at 90 in the morning and 50 in the
evening.
Wind Speed and Direction - Winds are light to moderates in speed, except the gales blow during a
depression or a storm. The winds in the area in general are South-west during the monsoon season
and also in the month of November. While during October and February, winds are Northerly or
north-easterly in the mornings. And, in the afternoons mostly they are northerly or north-east and
south-east directions. In the summer season, winds blow commonly between south-east and southwest.
Endowed with a rich variety of soils the four coastal districts occupy an important place in States
agriculture, which is the most important occupation. The major agricultural produce is banana,
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-5
turmeric, carrot, paddy, black gram, green gram, wheat, groundnut, jowar, bajra and maize. The main
cash crops are sugarcane, chillies, cotton, coconut, tobacco etc.
Water Resources
The project Highway lies in the catchments of River Krishna & River Godavari which are the two
major rivers of this region. The waters of both Rivers Krishna and Godavari are believed to be sacred
and holy. The characteristic feature of the Godavari river catchment is formation of islands (Lanka).
The ground water table varies from 8m to 80m in the project area. Wells, hand pumps and water
supply through pipelines are the main sources of the drinking water whereas water from irrigation
canals is used for agricultural purpose.
Water Quality
Water quality along the road is good as reported by the local communities. There are no major
pollution sources in the area. However, the water sources, where construction activity is proposed,
should be monitored after the detail designing is done, during construction and operation, to
contain/mitigate any probable pollution.
Air Quality
Ambient air quality of the area lies within permissible limits as per the discussion with the State
Pollution Control Board personnels owing to the highway passing through agricultural hinterland and
the traffic volumes being lesser than the designed. The concessionaire should monitor the air quality
in consultation with the, Regional office of the State Pollution Control Board, so that appropriate
mitigation measures may be adopted if the air quality exceeds the permissible limits of CPCB (Table)
to minimize the adverse effects on the environment.
Table: National Ambient Air Quality Standards
Pollutant
Sulphur Dioxide
SO2
Oixde of
Nitrogen as NO2
Suspended
participate
Matter (SPM)
Respirable
Particulate
Matter (RPM)
size less than
10 m
Time
weighted
Average
Sensitive
Area
Industrial
Area
Residential,
Rural &
Other Areas
Annual *
15 g/m
80 g/m
60 g/m
24 hours**
30 g/m
120 g/m
80 g/m
Annual *
15 g/m
80 g/m
60 g/m
24 hours**
30 g/m
120 g/m
80 g/m
Annual *
70 g/m
360 g/m
140 g/m
24 hours**
100 g/m
500 g/m
200 g/m
Annual *
50 g/m
120 g/m
60 g/m
24 hours**
75 g/m
150 g/m
100 g/m
Method of
Measurement
Improved West and
Gaeke Method
Ultraviolet
Fluorescence
Jacab & Hochheiser
Modified (NaArsenite) method
Gas phase
Chemiluminescence
High Volume
Sampling
(Average flow rate
not less than 1.1
3
m / minute)
Respirable
particulate
Matter sampler
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Pollutant
Reports Code
Page
Rev.
19-6
Time
weighted
Average
Sensitive
Area
Industrial
Area
Residential,
Rural &
Other Areas
Annual *
0.50 g/m
1.0 g/m
0.75 g/m
24 hours**
0.75 g/m
1.5 g/m
1.00 g/m
8 hours**
1.0 mg/m
5.0 mg/m
2.0 mg/m
1 hour
2.0 mg/m
10.0 mg/m
4.0 mg/m
Lead (Pb)
Carbon
Monoxide (CO)
Method of
Measurement
AAS Method after
sampling using
EPM 2000 or
equivalent filter
paper
Non-dispersive
infrared
Spectroscopy
Noise Level
Since the traffic volume on the project road is not much and the highway is generally passing through
open and agricultural fields, noise is not a major problem at present. But, it may be an irritant in city
areas, in future, with the growth in traffic. Noise level monitoring should be carried out, by the
concessionaire during construction and operation, in city/built up areas so that proper mitigation
could be developed as and when the noise level exceeds the standards.
Industries
The sections of NH-5 passes, primarily, through agricultural area but there are, also, some medium
and small size industries. The area has cotton ginning/spinning mills, tobacco based industry, paper
mills, rice mills, saw mills, sugar mills etc. Vijayawada Thermal Power Plant is situated in the project
area.
The road alignment passes primarily through rich agricultural fields. In the end of the section it
passes close to Devencheruvu reserve forests. Large number of trees / plants of various species
planted along the avenue and median exist within and outside the ROW. The Photo shows the
2
typical plantation along the project road. Ecological assessment indicates that approximately 14680
trees exist (on both sides of the road) within the R.O.W.
Source: Saplings planted in the avenue after construction of existing highway ,PIU NHAI, (Vijayawada, Rajahmundri)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-7
Wildlife
The project highway does not pass through any ecologically sensitive area.
Social Forestry
The avenue and median plantations have been done under social forestry scheme along the highway
at various locations. Divisional Forest Office, Vijayawada, W. Godavari and E. Godavari have the
responsibility of maintenance of this plantation.
Peoples Perception on Project
Major perception on environmental issues raised during the discussions with local peoples and
stakeholders are summarized as follows:
Protection of water bodies, which are very close to the project road,
Protection of trees and plants which are beyond the formation width, but very close to the
project road,
The climate of the study area is tropical subhumid with annual precipitation ranging from 1400
- 1600 mm and potential evapo-transpiration varying from 1300-1500 mm. The rainfall in the
area is brought by two spells i.e. South-West monsoon (June-September) and North- East
monsoon (October to November)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-8
The major land use pattern along the project road is agricultural, interspersed with small and
medium size industries cotton ginning/spinning, sugar mills, paper mills, rice mills, stone
crushers etc.
The quality of environmental parameters i.e. Air Quality, Water Quality and Noise levels is
good.
The noise level is expected to be high at town junctions during peak traffic.
River Krishna is the major rivers of South India, which cross the project road.
Vijayawada Thermal Power Plant is situated in the vicinity of project area, which is a major
source of electricity generation.
Large number of saplings which have been planted on the avenue i.e. 14680 approx. of
various species exists, which are likely to be impacted due to proposed expansion of the
project highway. The proposed development will result in removal of some of these
saplings/plants.
Town areas along the highway e.g. Hanuman junction at Km. 46.0 from Vijayawada, popular
for the shrine, poses a practical challenge for fitting in the extra lanes.
There are a number of religious structures, falling within the corridor of impact.
Potential Impacts
The main environmental impacts have been analyzed covering Environmental Resources, Human
Use Values and Ecological Resources. A brief description of these impacts is given herewith.
Impact on Water Environment
Two rivers viz Krishna (do not cross the project highway) & Godavari, network of irrigation canals and
a few ponds exist along the project road. Construction activities may lead to degradation of water
quality in terms of increased suspended solids as well as oil / grease concentration. However, during
operation the overall impact on water resources will be positive except oil and grease content.
Adequate precautionary / mitigation measures will be exercised to control these effects during
construction and operation
Impact on Land Environment
Alteration of Agricultural land to non-agricultural land is a major impact on land, as some land needs
to be acquired for the proposed project.
Impact on Air Environment
Adverse impacts on air quality due to the movement of construction machinery as well as haulage of
construction material, site clearance, earth filling etc in construction stage.
Impact on Noise Environment
Movement of construction vehicles, operation of construction machinery and congestion due to
construction activities result in increase in increased noise level in the project area. However during
operation phase, smooth traffic flow will minimize the noise level.
Impact of Human Use Values
There are numbers of Temples, and a large number of shrines within the corridor of impact and the
widening activity will result in the negative impacts in terms of religious sentiments.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-9
Mitigation Measures
(i) By improving intersections; (ii) By removing
traffic bottlenecks; (iii) By maintaining a steady
stream flow of traffic and by segregating slow
Locations
At all towns e.g.
Gannavaram, Vijayawada,
Hanuman Junction
cross- drainage
Contamination of
water quality
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-10
Environmental
Parameters
Mitigation Measures
Locations
felled.
Road Safety
At congested locations.
Improvement
traffic is mixing
(ii) Segregation of slow traffic in congested
areas by providing service roads
(iii) Provision of proper signage & proper
lighting arrangement to avoid accidents.
(iv) Traffic management plans will be prepared
for congested locations
Recommendations
On the basis of the field study conducted and data analysis from environmental point of view,
following points should be considered while finalizing the alignment / engineering design.
There does not seem to be any major environmental issue along NH-5
The traffic volumes are not high apparently bringing environmental parameters like air and
noise within permissible limits. But, with the proposed development it may become a cause
of concern in future. Thus, it is recommended that these parameters be monitored during
construction and operation so that a suitable mitigation be designed, if they rise beyond
permissible limits especially in towns.
The traffic junctions, along the highway, itself are having free access and is cause of concern
for the current traffic. Thus it is recommended to have suitable designs to improve safety.
The existing highway is passing through cities and towns with undersigned intersections
creating a hazardous situation in present low volume of traffic. Even in town/
villages/countryside there is a tendency to move in wrong lane which necessitates controlled
access and designed intersections for smooth and unhindered traffic movement.
There are number of shrines along the highway which pose a problem for the proposed
expansion. This problem of fitting in extra lanes is more pronounced in towns like Hanuman
Jn. This makes it pertinent to take up the project in phases removing such bottlenecks, while
the work is carried out on easier sections.
Clearance Requirements
th
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-11
Schedule and at State level the State Environment Impact Assessment Authority (SEIAA) for
matters falling under Category B in the Schedule(Annexure 20.1), before any construction
work, or preparation of land by the project management except for securing the land, is
started on the project or activity.
The clearance from State Irrigation department will be required for shifting the canals along
the highway.
The existence of Vijayawada Thermal power Plant requires that use of fly ash in construction
in the radius of 100 Km (from the thermal power plant)
The proposed development along the existing highway with avenue plantation, all along,
warrants obtaining a clearance as per Andhra Pradesh (Protection of Trees and Timbers in
Public Premises) Rules 1989.
If any land is required to be acquired from the Divencheruvu reserved forest than also it can
be done by approaching the forest authorities at regional/Central level.
The NOC/ Certificate to erect & operate for siting labour camps, construction machinery will
be required from the State/Central Pollution Control Board.
19.2
Due to insufficient existing RoW in places where the currently proposed RoW is ranging between
54m in urban areas and 70m in rural areas, further acquisition is required for 6-laning of existing road
with service roads. In addition to this, new bypasses were proposed to Vijayawada city and Hanuman
Junction town where the entire project road passes through open agricultural and non-agricultural
fields owned by both private and Government (Revenue Department etc.), The estimated land
required for the widening of existing 4 lane road to 6 lane road and for laying of 4 lane new bypass
for Vijayawada city and 6 lane new bypass to Hanuman Junction town with other road safety
improvements such as creation of new underpasses, flyovers, etc is about 515.28 Ha.
The land required by the project for the construction of proposed new by-pass falls under two
classifications:
Public land owned by the State Government and administered by other departments
such as Revenue Department etc; and
Private land.
As per the preliminary assessment and base line verification survey, in about 60% of the cases the
project will require full demolishing or loss of residential or commercial structures to the extent that
either resettlement or relocation will be necessary. While in the remaining 40% of the structures
which are partially affected, in most cases only a narrow frontage strip of several meters or less will
be affected. Which thereby implies only compound wall or fences, yards, may be removed excluding
the areas where market centers are located. In market areas or where the concentrations of
residential structures are dense the requirement of resettlement and relocation options needs to be
adopted. In some cases, small portions of roadside dwellings and business will be affected. In
addition to the permanent structures a number of kiosks are also affected due to the project.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-12
Ownership
No
% to total
Private
1024
91.92
Government
53
4.76
Community
37
3.32
1114
100.00
Total
Usage
No
% to total
Residential
506
49.41
Commercial
311
30.38
Residential + Commercial
44
4.30
163
15.91
1024
100.00
Others (incl. Bath rooms, Cattle sheds, car parking sheds, Compound
4
walls etc.)
Total
Usage
No
% to total
Religious Places
32
37.64
Government Buildings
03
3.54
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-13
50
85
Total
58.82
100.00
Sl. No Type
Area Affected
No
Area (Sq.M.)
% Area
Pucca
418
37.52
102543.28
73.57
Semi pucca
411
36.89
28482.08
20.43
Kutcha
285
25.58
8358.91
6.00
139384.27
100.00
Total
1114
100.00
Area affected is excluding affected compound walls area.
Usage with type of total affected structures
Observed across the type and usage of the total affected structures, majority of the residential
(37.23%), and other structures (52.57%) including Community Property Resources are pucca in
nature. Whereas, regarding Commercial (42.48%) and Residential cum Commercial (54.55%)
structures are concerned majority of the affected structures are of Semi-Pucca in type. Details are
presented in below Table.
Table : Usage with type of total affected structures
Type of affected property (No.)
Sl. No.
Pucca
Semi pucca
Kutcha
Residential
Usage
37.23
35.79
26.98
Commercial
28.32
42.48
29.20
Res+Commercial
31.82
54.55
13.64
52.57
27.43
20.00
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-14
(i.e.), the district collector and/or NHAI staff) through notification in the official gazette by the Central
Government.
The National Highways Act, 1956
For land acquisition, the Act defines the various steps in the process as follows: (i) section 3A
power to acquire land; (ii) 3B power to enter for surveys; (iii) 3C hearing of objections; (iv) 3D
declaration of acquisition; (v) 3E power to take possession; (vi) 3F power to enter into the land
where land has vested in the central government; (vii) 3G determination of amount payable as
compensation; and (viii) 3F deposit and payment of amount. The Act requires that the processes
must be completed within a year from 3A to 3D. The acquisition process is faster due to central
government coordination and provision for arbitration or power of civil court for trying any LA-related
dispute.
Although NHAI Act significantly reduces the time frame for acquisition, the rules and principles of
compensation are derived from the LA Act of 1894 amended from time to time. The Act covers only
legal title holders and provides for: (i) market value of the land; (ii) a solatium of 30% on the market
value for compulsory acquisition; (iii) additional amount for trees, crops, houses or other immovable
properties; (iv) damage due to severing of land, residence, place of business; (v) compensation to
sharecroppers for loss of earning; and (vi) an interest of 12% on the market value from the date of
notification of award.
Both the LA Act and the NHAI Act do not address many of the social and economic issues
associated with displacement and resettlement of illegal or non-titled informal settlers/squatters.
However, in many donor-funded projects, NHAI assists affected persons even without any legal titles.
As presented in Chapters A and B, the impacts of the present project are also on the roadside
SBEs/households people who are non-titled informal dwellers and encroachers.
National Rehabilitation and Resettlement Policy, 2007
The Ministry of Rural Development, Government of India (GOI) in October 2007 approved a National
Rehabilitation and Resettlement Policy (NRRP, 2007). It recognizes the following essential features:
That project affected families (PAF) not only lose their lands, other assets and
livelihoods,
they
also
experience
adverse
psychological
and
social/cultural
consequences;
That cash compensation alone is often inadequate to replace lost agricultural land,
homesteads and other resources. Landless labourers, forest dwellers, tenants, artisans
are not eligible for cash compensation;
The need to provide relief especially to the rural poor (with no assets), small and
marginal farmers, SCs/STs and women;
The importance of dialogue between PAFs and the administration responsible for
resettlement for smoother implementation of projects and R and R.
The policy is in the form of broad guidelines and executive instructions and will be applicable to
projects displacing 400 families or more in plain areas and 200 families or more in hilly areas.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-15
As far as the present project is concerned the NRRP states (Para 7.19) that in case of linear
acquisitions, in projects relating to railway lines, highways, transmission lines, laying of pipelines and
other such projects where in only a narrow stretch of land is acquired for the purpose of the project or
is utilized for right of way, each Khatedar in the affected family shall be offered by the requiring body
an ex-gratia payment of such amount as the appropriate Government may decide, but not less than
20,000 rupees, in addition to the compensation or any other benefits under the Act or programme or
scheme under which the land, house or other property is acquired. Further it says that if as a result of
such land acquisition, the land-holder becomes landless or is reduced to the status of a small or
marginal farmer, other rehabilitation and resettlement benefits available under the policy shall also
be extended to such affected family.
The benefits for PAFs who after land acquisition become landless or small or marginal farmer include
allotment of land extent of actual land loss subject to a maximum of one hectare of irrigated land or
two hectares of un-irrigated land or cultivable wasteland, if Government land is available in the
resettlement area and one-time financial assistance of Rs 15,000 and Rs 10,000 for land
development in case of allotment of waste land/degraded land and agricultural and respectively. If
the PAFs are not provided with alternative land they will be given rehabilitation grant equivalent to
750 days of minimum agricultural wages.
The benefits extended to the displaced families owning house include free house site to the extent of
actual loss but not more than 250 square meters in rural areas and 150 square meters in urban
areas. Other benefits such as shifting allowance, subsistence allowance and assistance for small
trader and artisan are also extended to the displaced families.
The policy does recognize some significant principles. It requires projects to (a) minimize
displacement and to identify non-displacing or least-displacing alternatives; (b) plan the resettlement
and rehabilitation of APs including special needs of tribals and vulnerable sections; (c) provide a
better standard of living to PAFs; and (d) facilitate harmonious relationships between the requiring
body and PAFs through mutual cooperation.
Minimization of Impact
Based on the impact on the properties and the land required and the consultations certain measures
are proposed to reduce and minimize the impact. Distinct design approach is adopted for open rural
areas. There are very few built up places at the starting point of the newly proposed bypass. So in
these locations the widening and approach to the bypass road may have to be restricted to reduce
the negative impact by constructing retaining/RE wall for identified underpasses etc. However, during
preparation of the detailed project report, due consideration needs to be given to minimizing negative
impacts within the limitations of technical requirements and cost effectiveness.
Preliminary Costs and Budget
The preliminary costs estimated mainly include land cost, structure cost and R&R assistance costs.
The land price is calculated based on prevailing market price in the road side across different villages
falling under the project road. The average price across the roads is considered for the estimates.
The structure cost is estimated based upon the rates of the Roads and buildings Department,
Government of Andhra Pradesh. As the proposed bypass is entirely new there is no impact on other
assets such as open well, bore well etc. Table below presents the details of the unit cost for the
various heads.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
19-16
Unit
Land
Land price
Structure
Pucca Structure (RCC structure pillared)
Semi Pucca Structure (Tiled/asbestos roof)
Kutcha (Thatched)
Compound wall (running length)
Other Assets
Agri. Pump-Sets with pipe lines
Acre
1200000
Sq.Ft
Sq.Ft
Sq.Ft
Meter
512
275
130
400
One
120000
On the basis of above, an estimation of preliminary resettlement and rehabilitation budget has been
worked out. The estimated budget for land acquisition and other R&R cost is about Rs 236.707
crores. The details are presented in Table below.
Table: Preliminary Cost Estimates and R&R Budget
Sl No
1
Item
Quantity
Rate (Rs)
Amount (Rs )
1272.747
1200000
1527296400
5510
565013473
2960
84306957
1400
11702474
400
1020060
120000
2400000
Units
Acres
Lumpsum
175339149
Total (1+2+3+4)
2367078513
Note: Land cost per acre was calculated as per the average prevailing market value obtained
from local villagers.
* R&R assistance as per the National Rehabilitation and Resettlement, 2007 is Rs 20,000
per Project Affected Family. In the absence of information on number of Title holders loosing
agricultural land, the figure is estimated, assumed to be equivalent to the R&R assistance to
be extended as per NRRP and inclusive of the benefits extended to the eligible displaced
families.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
2-1
Chapter 2: Contents
2.
2.1
RECENT HISTORY ........................................................................................................................ 2
2.1.1 General .................................................................................................................................. 2
2.2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
2-2
2.
2.1
RECENT HISTORY
2.1.1 General
This section of National Highway No. 5 was widened over the period 1997 to 2004 from 2 to 4 lanes
[it had previously been 2 lanes in width for many years]. The majority of the widening was done on
line, but some new bypasses were created. Brief details are given below.
The existing road before taking up 4-laning works consist of 2-lane carriageway of width varying from
6.5 to 7m except for some isolated built-up section where the carriageway width varies from 10 to
14m. The existing pavement is of flexible type with thin bituminous surfacing at the top developed
since ages. The average pavement thickness is of the order 600mm. The project road over different
sections was strengthened and widened 20 years back. In recent past 1 complete new alignments
(Eluru bypass) were developed to 4-lane configuration.
The project road follows different chainage systems as it has developed under different contracts
over different periods. For easy reference the chainage equations over the entire project road section
is given in table 2.1.1.
Table 2.1.1: Chainage Equations
From
To
Km 0+000
Km 47+880
(Existing NH-5
Km 422+800,New Ch
1112+044)
Chainage Km
1076+480)
Km 1076+480
Km 1060+800
(Existing NH-5
Km 1060+800)
Chainage Km
1055+650)
Km 1055+650
Km 1022+480
2.2
Section
47.88
15.68
Gannavaram-Hanuman
Junction (Existing NH-5)
Km 6+720
Km 0+000
(Existing NH-5 Chainage
Length (km)
6.72
33.17
103.59
RELEVANT DOCUMENTS
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
2-3
Very important documents were then copied; less important documents were just listed and returned
to NHAI [where they are still available at NHAI if needed in the future concession company design
work].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
20-1
20.1
GENERAL..................................................................................................................................................2
20.2
20.3
QUANTIFICATION .....................................................................................................................................2
20.4
20.5
PROJECT COSTING...................................................................................................................................3
20.5.1
Road .................................................................................................................................................3
20.5.2
20.5.3
20.5.4
20.5.5
20.6
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
20-2
20.
20.1
GENERAL
This section describes, at this feasibility stage, the method of costing and gives the cost estimates.
Cost estimation is an important component of the feasibility study as it provides vital input to financial
evaluation. The cost estimates have been prepared for widening the existing 4 lane divided
carriageway with 1.5m paved shoulder and 1m earthen shoulder into 6 lane divided carriageway with
1.5m paved shoulder and 2m earthen shoulder.
This includes overlay of 40mm by bituminous concrete on the existing pavement, widening of cross
drainage structures, providing service roads, longitudinal drains, road furniture, bus bays, Toll plaza,
Interchanges/Intersections etc.
20.2
QUANTIFICATION
The quantification of most of the items which are uniformly occurring are calculated on per Km basis,
derived from typical cross sections. The quantification of structures is based only on Square meters
of widening, re/new construction for each structure and lump sum provision for rehabilitation on
square meter basis.
The construction items covered in cost estimates are: site clearance, earthwork in case of widening
and raised pavement, Pavement in carriageways and shoulders, bridges and culverts, and
miscellaneous items such as side drains, road furniture, interchanges / intersections, bus bays, Toll
Plazas, HTMS and utility relocations etc.
20.3
The rate analysis for the Construction Items has been done based on standard data book published
by MORT & H and the basic rates are taken from Common Standard Schedule of Rates 2010-11,
Govt of Andhra Pradesh. The machinery rentals of 2001-2002 are considered from Standard Data
Book and Increased @5% per year to bring it to the current date.
The unit rates adopted in Preliminary Cost estimate are presented in Table 20.1
Table 20.1: Adopted Unit Rates
Items Description
Clearing & Grubbing
Unit
Ha.
Rate:
Rs.
42722
Cum
208
Cum
99
4
5
6
7
8
Cum.
Cum.
Cum.
Sqm.
Sqm.
244
1334
1782
22
8
S. No
1
2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
S. No
9
10
11
12
13
14
15
16
17
20.4
Reports Code
Page
Rev.
20-3
Items Description
Dense Bituminous Macadam
Bituminous Concrete
Kerb
Slab/Box Culvert
Bridges
Underpass
Long viaduct
Major Bridge
ROB
Unit
Cum.
Cum.
Rm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Rate:
Rs.
6583
7313
219
30000
30000
30000
30000
60000
40000
PROJECT COSTING
20.4.1 Road
The cost of the road portion has been worked out on a per km basis separately for widening and
overlaying of the existing road in rural and urban sections. This cost is based on typical cross
sections given in Drawings [and accompanying annex].
20.4.2 Bridges and Culverts
The cost of new/Widening of structures has been calculated on the basis of running metre cost for
pipe culverts and square metre cost for Slab culvert, Box Culvert and Bridges of different spans. For
widening of structures, dismantling and other preparatory works, lump sum cost is added to the
above-mentioned rates.
20.4.3 Maintenance during Construction Period
Provision has also been made for maintenance of existing road items such as pot hole and Renewal
Coat for road maintenance are considered under this bill. It is also assumed that out of the whole
existing road approximately 3% length of the road has potholes depending on the road condition and
25 % length of the road for renewal coat.
20.4.4 Land and Structure acquisition
Provisional land acquisition requirement is assessed based on the typical cross section types to be
adopted with additional area for the locations of junctions and interchanges.
20.4.5 Miscellaneous Items
The cost for providing major and minor junctions, overhead signs, bus bays, bus shelter, Toll plaza,
HTMS, Median Drain, RE Wall, Crash Barrier, Stone Pitching etc. have been worked out and
included in the total cost estimate.
Contingencies are not added in the total construction cost. Engineering design and supervision cost
is taken as 4% of the construction cost.
Escalation has been calculated on the assumption that the project duration is 30 months. Escalation
taken for the 1st year is 5%, second year 10% and third year 15%. The progress considered during
the first year is 20%, second year 40% and third year 40%.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
20.5
Reports Code
Page
Rev.
20-4
CONSTRUCTION COST
The overall construction cost of the Project works out to Rs. 1427 Crores.
Abstract of the cost for Vijayawada - Gundugolanu Sections including Vijayawada and Hanuman
Junction Bypass and Major Bridge on Krishna River) are tabulated below.
Abstract of Cost for Vijayawada Gundugolanu Section (including Bypasses)
VIJAYAWADA
GUNDUGOLANU
Bill
No.
Description
Amount (Rs .in figures )
Site Clearance
Earthworks
1,352,686,776
1,496,031,697
Bituminous Works
2,309,555,551
23,924,318
334,047,290
6,341,437,708
52,027,973
1,285,887,222
Junctions
252,107,618
104,885,248
82,937,686
Micsellaneous works
11 Truck Lay-byes & Bus bays
12 Lightings Urban Areas, Major intersections, flyover and toll Plaza
14,305,700
163,199,999
13 Toll Plaza
84,228,666
14 Avenue Plantation
52,515,364
48,990,000
16 Rest areas
10,000,000
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
20-5
17 Photographs
815,910
TOTAL AMOUNT OF BILLS
14,009,584,725
The Additional cost for pre-construction activities to be incurred by NHAI is as under (in Crores)
LA & RR Cost
Utility Shifting Cost
Environmental Mitigation
Total
= `236.707
= `87.94
= `2.357
= `327.004 Crore
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
1,401
13.52
103.590
Reports Code
Page
Rev.
21-1
MAINTENANCE ....................................................................................................................... 2
21.1
INTRODUCTION. 2
21.2
M AINTENANCE 2
21.2.1 Purpose and Scope................................................................................................................2
21.3
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-2
21.
MAINTENANCE
21.1
INTRODUCTION
This Chapter outlines the normal Maintenance Requirements of a Highway [in Section 21.2] and
what should go into the Highway Maintenance Plan [that will have to be drawn up by the
Concessionaire], then mentions the additional requirements that pertain to a toll road [in Section
21.3].
Obviously the maintenance will be carried out by the Concessionaire, under the requirements of the
Concession Agreement.
Our current observations are that:
In isolation, the approaches of major bridges constructed by BOT operator, are still a 2-lane
road of history
Virtually no lighting placed, except some high mast at toll plaza locations
Maintenance [if done fully and properly] generally [when averaged out] often represents about 2.5%
[annually, including labour, and all necessary works] of the value of the roads and bridges. Usually
the costs follow a rough cycle, annually lower when no major pavement or reconstruction works are
done on the highway (say years 1 to 4, 6 to 9 etc. when major overlays are done every 5 years or
so), then with major increases every time a pavement overlay is carried out (say every 5 years or
so). However this is not the only cost cycle, as over time one also has to consider maintenance [and
eventual replacement] of electrical [including lighting], toll collection, and communication equipment,
and then there are other cost cycles, some completely unpredictable like weather damage,
emergencies and the like, and some more predictable like replacement of road markings. Additionally
with a road of this length [183.7km] the cycle is not necessarily the same on every km section, so
figures tend to get more averaged [and also depend to some extent on the implementation schedule
of the 6 laning], rather than being relatively low 4 years out of 5 then with sharp peaks every 5 years
or so.
21.2
MAINTENANCE
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-3
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-4
Routine
-
Programmed
-
Regulatory
-
Highway register
Management of utilities
Flooding
High winds
High temperatures
Other emergencies
The Concessionaire will need to set up [and thereafter implement to an acceptable standard] a
Maintenance Plan that carries out the above mentioned activities. Some selected recommendations
as to what goes into this plan follow.
Comprehensive and Accurate Records
Comprehensive and accurate records should be kept of all highway maintenance activities
undertaken, particularly safety and other inspections, identifying the time and nature of any response,
including nil returns, and subsequent required follow up action.
Coordination of Records
Arrangements should be established to ensure the effective coordination of all highway
maintenance records with other relevant record systems, including road accident information,
together with a programme for regular review. The use of a relational database and GIS is desirable.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-5
Special arrangements for frequent inspection of areas that may be particularly susceptible to
risk of flooding either from topological factors outside the highway or from frequent silting of
systems. Frequency of these inspections will depend on local circumstances but could form
part of safety inspections. They should be carried out during or immediately following periods
of heavy rain as opportunity allows;
Gullies in other areas should be cleansed annually and arrangements made for non
functioning gullies to be recorded for more frequent or detailed attention. Grips and ditches,
which may be obstructed by the growth of vegetation or damaged by traffic should be
cleared of vegetation and dug out when required. In most cases the responsibility for
maintenance of ditches will rest with the adjoining landowner;
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-6
Culverts under roads, where there is a need to inspect for structural damage and blockages.
Culverts and manholes should be inspected every year, more frequently in wooded areas,
and cleaned when required ;
Piped drainage, which includes a wide variety of conduits and filter drains, which may be
susceptible to siltation or blockage. Piped drainage soakaways and associated systems
should be inspected and cleared when required, but at not more than 5 year intervals. Where
the serviceability of such piped drainage is critical to flood prevention or there is evidence
that more regular attention is necessary then the frequency may need to be significantly
increased;
Surface boxes and ironwork for both drainage and nondrainage applications, which should
be inspected during safety and service inspections for carriageways, footways and service
roads.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-7
Special signing schemes may deteriorate more quickly than conventional signing. They are also
likely to have been installed to improve network safety and inspection arrangements should reflect
this. Block work chevrons are likely to need inspecting and cleaning annually.
The condition of nonilluminated traffic signs should be inspected at least every two years in daylight,
and repeated at night for degradation of colour, retroreflectivity, deteriorating fittings, legibility
distance, and average surface luminance, after cleaning. More frequent inspections may be
necessary for strategic routes and main distributors, where more consistent high standards are
desirable. Cleaning may be necessary annually or more frequently where subject to heavy soiling.
Optical inspections and cleaning of illuminated signs should be carried out at regular intervals of no
greater than one year. A visual inspection of the sign supports should be carried out at the same
time. Nighttime inspections should be undertaken in conjunction with those for street lighting faults.
It is recommended that a group lamp replacement strategy be adopted for illuminated traffic signs.
The lamp period replacement period will depend upon the type of lamp and its annual burning hours.
Inspections should initially be visual. . Any suspect areas identified by the visual inspection should be
noted and further testing instigated. The coefficient of retroreflection of sign face sheeting is a
specialist site test that may require the services of a specialist organisation. The acceptable level of
retroreflection is 80% of the as new value where higher performance materials are used.
Inspection of signs at minor roads should be included in the inspections of signs on the major road to
which they control entry.
Service Inspection of Road Markings and Studs
Inspections in respect of wear, spread, colour, skid resistance and retroreflectivity should be
undertaken at intervals of one year for paint markings and two years for thermoplastic markings.
Inspections for reflective conspicuity should be carried out at intervals of one year during the hours of
darkness. Inspections should initially be visual. Any suspect areas identified by the visual survey
should be considered for more detailed technical investigation depending on circumstances.
Service Inspection of Traffic Signals
Service inspections of road traffic signals may not be necessary in relation to the functioning of the
internal equipment as this may be provided through remote monitoring of the installation. The remote
monitoring system may also identify the need for lamp replacement but bulk changing is likely to be
preferred. Signal lenses should be cleaned at minimum annually.
Service inspections of the physical condition of controller and auxiliary equipment cabinets and of
other site hardware should be carried out at intervals of one year, and inspections in respect of
electrical safety should be carried out at intervals of five years. Inspections should be visual, by
remote monitor, or by approved test equipment.
Electrical safety Inspections should be undertaken at a frequency no greater than every six years.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-8
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
21-9
NHAI should ensure that all standards are formally adopted [by the Concessionaire] and published
as part of a Highway Maintenance Plan. They will also need to be consistently applied and reviewed
at intervals in the light of changing circumstances.
21.3
Service Roads
Roadside furniture
Special maintenance plans will be necessary [from the Concessionaire] for the toll plazas and
associated equipment and the Highway Traffic Management System.
Some general comments on this are given below.
Toll Plazas and Associated Equipment
The buildings and toll booths will be in constant [generally 24 hr a day] use. Furniture and equipment
will need to be constantly cleaned and maintained. Additionally it is likely that intermittently the whole
electrical/communication/collection equipment associated with toll collection systems will need to be
upgraded or replaced [as it becomes obsolescent] as a rough rule of thumb this might be at 10 year
intervals.
Highway Traffic Management System
The Highway Traffic Management System will need to be staffed and maintained, and sufficient fuel
provided for associated vehicles to operate. Maintenance of the electrical /communication /
observation / counting equipment is to some extent a specialist activity, and possibly the
maintenance of major portions might be done by the original supplier, or by a specialist company in
this field.
All vehicles purchased for the Highway traffic management system will need to be maintained, and
replaced once they get too old for practical use. Obviously the life expectancy of vehicles varies by
type and usage, but several vehicle fleets will likely need to be purchased [and later sold off when to
old] at various times during the Concession Agreement.
The whole electrical/communication equipment associated with the Highway Traffic Management
System will need to be upgraded or replaced [as it becomes obsolescent] as a rough rule of thumb
this might be at 10 year intervals.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
3-1
Chapter 3: Contents
3.
3.1
3.2
BYPASSES ................................................................................................................................................ 2
3.3
3.4
TRAFFIC .................................................................................................................................................. 3
3.5
PAVEMENT .............................................................................................................................................. 3
3.6
3.6.1
Bridges .................................................................................................................................................... 4
3.6.2
Drains...................................................................................................................................................... 4
3.6.3
3.7
3.8
3.9
3.10
ROADSIDE FEATURES [REST AND SERVICE AREAS, PETROL STATIONS, OTHERS] ................................. 5
3.11
SAFETY .................................................................................................................................................... 5
3.12
3.13
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
3-2
3.
3.1
GENERAL OVERVIEW
In this Chapter we describe the existing road, and its specific features. Some further details are also
given in Chapter 4. The location map of project highway is shown in Figure 3.1.
BYPASSES
Major settlements/ towns along the project road are: Vijayawada, Gannavaram (houses airport for
Vijayawada), Hanuman Junction, Eluru. A number of bypasses exist along the corridor, the list of
towns for which bypasses are constructed are as below:
Existing Bypasses along the project highway
Sl. No
Name of Bypass
Location
Length
Remark
Eluru Bypass
North of town
17 km
New Alignment
17 km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
3-3
Design Standards
S. No.
Description
Details
Design Speed
100/80 Kmph
Lane width
3.5 m
4.5m
2-Lane carriageway
7.25m
Paved
1.5m
Earthen
1.0m
Shoulder
Service road
5.5/7.0m
The ten typical cross sections have been developed to upgrade the 2 lane project highway into
existing 4 lane divided carriageway.
3.4
TRAFFIC
In general traffic levels are higher to the south than the north [see figure traffic characteristics on
next page]. On the last 120km [north end] traffic levels are significantly lower than on the southern
78km section since a considerable amount of traffic diverts off the road at the junction as the
alternative route to Rajahmundry is shorter [see plan Competing Corridors two pages on]. The road
is not that busy, traffic levels as such that in capacity terms and for some sections [for a reasonable
level of service] 6 Laning is not really necessary for many years.
3.5
PAVEMENT
The existing pavement details are presented in Chapter 11 of this report separately.
The recent 4-lane construction of the project highway consists of mainly following type of pavement
composition:
a) Overlay on the existing 2 lane road
b) Widening for shoulder/part of carriageway and
c) Realignment or New Carriageway
c) Re construction of the existing 2 Lane road
From the pavement structure details as-built and DPR Study reports, it is evident that the pavement
structure along the entire Project Highway is varying; the resulting pavement structure over the main
carriageway is as follows;
Pavement thickness
No.
Road Name
VijayawadaEluru
Over
Existing
BC
DBM
BC
DBM
WMM
GSB
SG
BC
DBM
WMM
GSB
SG
40
130/
150
40
130/
150
300
300
500+
40
130/
150
300
300
500
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
No.
Reports Code
Page
Rev.
3-4
Road Name
Over
Existing
BC
2
3
DBM
BC
DBM
Eluru Bypass
EluruGundlagolanu
WMM
GSB
40
160
40
160
300
300
500
BC
DBM
WMM
GSB
SG
40
130/
150
300
300
500
40
160
300
300
500
To
Width (m)
Pavement type
1076+480
1061+080
1.5
Same as main CW
1056+080
1022+480
1.5
Same as main CW
3.6
STRUCTURES [BRIDGES]
3.6.1
Bridges
Refer to Chapter 13. It is very important to note that virtually no structure [on this 49.000 Km section]
was built to allow for future widening to 6 lanes.
Hence every structure requires widening [of if unwidenable then replacement for full 6 laning to
occur.
3.6.2
Drains
About 13km of lined drain exists along the Project Highway mainly at built-up areas where the
service roads are provided. The schedules of the lined drains are given in below.
3.6.3
From km
To km
Offset
from CL
Remark
From km
1034+080
1022+880
15-20 m
Irrigation
Channel
1033+380
RHS
Offset
To km
from
CL
1022+480
13-30 m
Remark
Major Canal
There are two toll plazas located along the corridor [albeit these are short term affairs the
permanent plazas are not yet constructed]. The toll plaza locations and the associated road sections
are presented in the table below:
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Sl. No
3.8
Reports Code
Page
Rev.
3-5
Section
Location
Chainage, km
After Gannavaram
1072+230
1050+720
Most of the Project Highway is at grade 4 lane with some grade separated structures exist on the
new bypasses. Three bypasses exist [two built on new alignments and one is on the alignment of a
previous 2-lane road, which was widened to 4 lanes in the 1997 to 2004]. Some service roads exist
in major towns. In a few places [on Eluru bypass] there are grade separated interchanges. The
typical as built drawings are presented in the following pages.
3.9
There are about 35 median gaps on the project road. The locations of the existing Median gaps /
cross road junctions and T junctions [crossing the median] exist.
There are many side accesses to the highway. There are no access control measures in place, and
as such many buildings/factories etc are built [and still being built] with direct access to NH5.
Additionally every town and village passed, except where frontage roads have been built; have many
local roads feeding into the mainline except where service roads are currently provided.
3.10
There are about several petrol stations along the road and several rest and service areas [under
construction in fact near finished but not yet all opened]. The rest areas include a 2 full fledge
amenity centres that are [end February 2007] now partly open.
3.11
SAFETY
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
3-6
Bullock carts, motorcycle, bicycles, and a government car all going down the fast lane [in the
wrong direction!]
The road is much less safe currently than it should be for the following reasons:
There is no access control [except where some frontage roads are provided, generally in
towns] the road has far too many access points [so you can and do drive straight into a
high speed road.
The road mixes short distance [very local including animals herded on the road in more
rural areas] and long distance traffic so there are many movements [entering the road, U
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
3-7
turning in the medians, driving the wrong way down the road , grazing in the median] which
are incompatible with the high speed long distance facility this road is supposed to provide.
The main junctions [mostly at grade] have poor advance signing, and should [in some cases]
be grade separated.
Little thought has been given in villages and towns crossed as to how the local population
cross the main National Highway [other than by praying first then running very quickly]. With
this standard of road crossing points should all be grade separated [up or down from the
highway] and with sufficient barriers [or fences] to force people to use the longer grade
separated access rather than the faster run across the road approach.
Guardrail [and barriers at approach to some bridges] is lacking in places, and hanging lose in
others. With the guardrail this might be in places because it appears the bolts get frequently
stolen.
3.12
Street lighting exists on the following sections [generally town section, or toll plazas. Virtually no
junctions, other than in some urban areas, have lighting provided]:
From Vizir chainage
To Vizir chainage
From Km post
To Km post
1072+280
1072+180
1050+780
1050+680
For instance having bullock carts walk down the fast lane [for a few km] at night in the wrong direction into
incoming traffic happens frequently, as does pedestrians crossing the road at night in dark areas drivers have
to be alert on this road [if not they will hit something].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
4-1
Chapter 4: Contents
CHAPTER 4: CONTENTS .................................................................................................................... 1
4.
4.1
4.2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
4.
Reports Code
Page
Rev.
4-2
4.1
INCEPTION REPORT
The Inception Report was the first significant report to be submitted under this Study, and was
submitted in early December 2006 (Vijayawada-Gundugolanu), July 2010 (Vijayawada Bypass),
August 2010 (Hanuman Junction Bypass). Selected relevant extracts from the Executive Summary of
this Inception Report are given below.
4.1.1
Cattle [and other livestock] are intermittently walked down the road [in either direction]
Most if not all of the road was recently built / widened of the previous 2 lane road [mostly by
one side widening [by adding 2 more lanes], with the old 2 lane carriageway now buried
under one side of the 4 lane road, but some new alignment bypasses were also built as well]
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
4-3
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
4-4
Rest and service area 2 of these exist along the project section. There are also a lot of petrol
stations with direct access to NH5
In very many places the current corridor right of way is insufficient for 6 laning [including
service roads]. This is especially so in the 3 more major urban areas crossed by the
project [where the current right of way appears to be just 23 m at minimum in places], but
also occurs in many villages passed through, and elsewhere.
All existing structures are for the current 4 lane situation. For full 6 laning all structures
[culverts, small bridges, long bridges] would need to be widened. Technically it is likely not to
difficult to widen the culverts, and probably some of the smaller bridges. However widening
of some of the smaller bridges, plus most if not all of the longer bridges [and this includes 3
substantial river crossings] looks difficult [if not impossible]
One of the existing long bridges, 2 lanes each direction [2 separate structures]
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
4-5
Apart for possible land take [and bridge] problems widening to 6 lanes [plus some
intermittent frontage roads, as they will not everywhere be needed in the rural areas] is likely
to be achievable especially in rural areas.
Rural sections
The current 4 lane situation with U turns is dangerous. In daytime [worse at night] local traffic
[bicycle, motorbike, car, lorry and bus, tractor towing hay etc.] drives the wrong way down the
carriageway to save a longer trip via the official route. At day and worse at night pedestrians
crossing the road are significantly at risk. However provision of service roads as necessary
[including if one wants to keep pedestrians of the 6 laning a lot of fencing], plus local access
from one side to the other, either over or under the current road is going to be difficult
[sometimes impossible], and in all events costly, especially as the majority of road [except for
one recent bypass] is on relatively flat ground, sometimes with lengths of canal alongside.
Even with frontage roads driving through these villages, especially at night, is dangerous due to
pedestrians crossing [and vehicles going the wrong way]
Vehicles drive both ways on the existing carriageway, not very safe
Many sections of the road are built adjacent to canals and drainage channels, this creates
difficult access problems where bridges over the canal exist
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
4-6
Canal [many km long] to left of parts of NH5, making widening slightly difficult [and frontage roads
virtually impossible here]
Whilst it is possibly to convert this section of road to a 6 lane section, along with new interchanges,
and service roads as needed, it is not an easy task. If everything is done then much land take and
property demolition will be needed [and this directly contradicts part of the basis project
requirements], and costs are likely to be much higher than the global cost of 5.78 crores / km [note:
this is a subjective assessment, we have not done the work needed yet to prove this].
Review of Project Objectives following Initial Assessment
Government basically wish this portion of NH5 to be widened to 6 lanes. However to achieve this
objective via a DBFO concession a number of parameters have to be met:
The project has to be financially viable (so the works and land take have to be affordable);
The project has to be acceptable [the Consultant thinks major demolition in every town and
village passed through is unlikely to be acceptable];
The project has to meet the desired objectives [including safety, local access needs etc.].
We suspect the cost of doing everything desired will be too high for a sensible concession
agreement to be negotiated and let. So the likely choice for Government is to compromise on some
of the desired objectives and standards [i.e. find ways to minimise cost and lessen the land take
problems, which may include even town detour / bypass roads if at all possible]. The Client has to
decide [as the study evolves] what requirements are sacrosanct and which may be varied, given a
likely desirable ceiling to the overall average cost per km. In the particular case of this project some
requirements that will need to be locally considered as the study evolves are likely to be;
How many interchanges and grade separated U turns and accesses are to be provided
[these are individually large cost items, and some interchange grade separations may be
quite expensive and involve possibly significant land take].
Is full on line widening through the major town areas [the available ROW in places drops
well below 30m] really a sensible option [a site visit by NHAI is highly recommended]. Bypass
alternatives may need to be studied, and this may require additional time and resources.
What to do with the major bridges [> 60m in length], leaving them as 4 lanes defeats the
objectives of everywhere widening to 6 lanes [and creates pinch points which are likely in
time going to be bottlenecks and also safety hazards]. Maybe more provision of service
roads to keep local and through traffic completely separated and less 4 to 6 general lane
widening may be a way forward.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
4-7
The above requirements are applicable to areas with adjacent constraints [towns, bridges, potential
interchange locations]. In rural locations the real constraints are predictable [carriageway and
embankment needs widening from 4 to 6 lanes, all structures and culverts need widening, limited
frontage roads will be needed], with one problem to sort out which is how cross access is provided.
4.2
The Draft Feasibility Study Report was submitted in early February 2007 (Vijayawada-Gundugolanu),
December 2010 (Vijayawada Bypass) and January 2011 (Hanuman Junction Bypass).
This Final Feasibility Report is essentially an update of the Draft report, with one scheme for 4/6
laning presented.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-1
Chapter 5: Contents
CHAPTER 5: CONTENTS .................................................................................................................... 1
5.
5.1
DATA COLLECTION ...................................................................................................................... 2
5.1.1 As-Built Drawings validation .................................................................................................. 3
5.2
5.3
5.4
5.5
5.6
5.7
5.7.1
5.8
5.9
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-2
5.
5.1
DATA COLLECTION
Documents and as-builts were obtained from NHAI, refer Chapter 2 for details.
Where they exist in reasonable quality aerial photography [via Google earth] was copied a brief
selection follows. It should be noted that the Google earth photographs seem to be in a constant
state of improvement [better definition], the pictures [or more correctly this source of data] may be
useful in future detailed design. Many digital photographs of the road were also taken [and
referenced].
Alignment Sheets
Existing Vijayawada-Gundugolanu NH
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-3
Most of the as-built drawings are available in electronic form; however there are a few hard copies
are also available and collected by the consultants.
KEY FINDINGS
The Terms of Reference specifies that The consultant shall also be fully responsible for the
accuracy of the physical and ground details, such as alignment, grade, right of way details, abutting
land use, and features existing within the right of way (such as service roads, drains, retaining/RE
walls, slope protection, culverts, bridges, junctions, subways/overpasses, grade separators, road
over bridges), pedestrian/cattle crossing facilities, bus/truck lay byes, utilities (like telephone, HT/LT
lines, water supply drainage/gas lines and OFC cables), plantation, road furniture, access to
properties/fuel stations, median openings, etc. The primary source of the existing ground and
physical features will be the as-built drawings of the existing four-lane highway.
The as-built drawing shows only the lane edges, some alignment details and does not have the
details of physical features, right of way, abutting land use and utility services and other important
features of roadway. The consultants have collected many missing details and presented these
details in the Strip Plans.
The cross sections drawings are complete with respect the setting details. The Cross Drainage works
drawings are also complete with respect to the setting details. However the horizontal and vertical
layout details presented in the as-built drawings are not sufficient for setting out geometry. The
Vertical Bench Mark details are given but the horizontal alignment details in terms of HIP and
coordinates are completely missing. The concessionaire has to carryout detail topographic surveys
including levelling for detailed design and sub-sequent layout in the field.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-4
Characteristic/Location Description
Objective of validation
Bench Marks
Bridges
New Flyovers
New Underpasses
Urban/village locations
FIELD SURVEYS
Bench Marks
The Bench Marks for levels were given in the as-built drawings; however there is no details given on
traverse points/horizontal control pillars. The vertical control reference points (TBM) are marked
either on Median Kerb top, Bridge Kerb top, Culvert Head Wall/Parapet or on KM post, indicating with
paint. Many of the TBM marks are not visible on site, hence cannot establish validation. There is no
permanent type of control pillars observed along the entire project road. The complete list of TBM
details are presented in the DPR documents.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-5
To inspect appropriate skew angles to cross railway lines, majors highways, major
rivers
The topographic survey is one of the most important and crucial field tasks under the project. The
detailed field surveys are carried out using high precision instruments i.e., Total stations. The data
from the topographic surveys will be available in (x, y, z) format for use in a sophisticated digital
terrain model (DTM).
A pair of GPS control points has been established by using DGPS at every 5km interval. The
Traversing has been carried out in-between 2 GPS points located at an interval of 5Km and error has
been adjusted on all the Control points. The GTS benchmarks have been transferred to Benchmark
Pillars along the alignment by DT leveling.
The detailed topographic surveys are being carried out based on the control points established on
the side of the proposed corridor. Longitudinal and Cross section will be picked up at every 25m
interval for the survey corridor for a width of 50 m on either side of centerline. The topographic details
like cross Roads, Rail, Bridges, Culverts, Trees, Buildings, Religious monuments, Graveyards,
Pipelines, Traffic Signs, Waterways, Electric Poles, Telephone Poles, important structures found at
site will be taken within the survey corridor. All the main Junctions of NH and SH have been
surveyed for in detail for junction improvements/ interchanges.
At locations where developments have resulted in a requirement for adjustments in the alignment,
survey of existing alignment to be improved through minor adjustments by widening the width of
corridor, the Survey will extend a minimum of 200m either side of the center line and will be of
sufficient width to allow improvements, including at-grade intersections, to be designed where
existing roads cross the alignment. For roads proposed to be improved, the longitudinal sections
levels along the proposed centerline would be taken at every 25m interval.
The longitudinal sections and cross-sections are being surveyed for the streams crossing the
alignment to the extent depending on their catchment area. In general for all the Major bridge
locations the survey will be carried out for 500m on upstream and 500m on downstream side by
taking of cross-sections at 0m, 50m, 100m, 200m, and 500m on both sides and for the Minor bridge
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-6
locations the survey will be carried out for 300m upstream and 300m downstream side by picking
cross-sections at 0m, 100m, 200m, and 300m on both sides.
The survey data will be utilized to develop DTM useful for final design of bypass, earthworks and
other quantities for detailed cost estimates.
Project centerline has been designed to proper geometry. Revenue maps are being collected along
the project corridor and significant land marks/plot boundaries identified on the ground and coordinates will be picked up on these control points. Digitization of Revenue maps will be done
simultaneously and with the help of co-ordinates picked up on control points, these revenue maps
will be oriented to extrapolate on the project centre line. The corridor of impact on revenue maps will
thus be established and Land acquisition Plans will be developed. Schedules for Land acquisition will
be prepared by collecting the revenue records from local revenue offices to know the title holders of
each plot. The LA schedules will be prepared showing the Plot No, Name of the Title holder and
extent of land affected.
Horizontal Alignment
Sufficient details were collected at horizontal curve location at selected chainages to assess and
validate the geometric characteristics for Vijayawada-Gundugolanu section. The following table
summarise these geometric characteristics.
Validation of Horizontal Alignment
S. No
HIP/ Chainage
As-Built Details
Validation
R= 300, Ls=75m
R= 300, Ls=75m
=17 03 57
=17 01 26
R= 800, Ls=42m
R= 800, Ls=42m
=7 39 30
=7 39 40
R= 350, Ls=60m
R= 350, Ls=60m
=18 22 29
=18 22 45
R= 300, Ls=40m
R= 300, Ls=40m
=28 11 52
=28 10 19
R= 300, Ls=80m
R= 300, Ls=80m
=49 52 49
=49 52 00
R= 500, Ls=45m
R= 500, Ls=45m
=9 00 57
=9 01 18
R= 250, Ls=60m
R= 250, Ls=60m
=19 37 56
=19 36 45
Remark
Vijayawada Gundanagolu
1
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Coincide
Coincide
Coincide
Coincide
Coincide
Coincide
Coincide
Reports Code
Page
Rev.
5-7
S. No
HIP/ Chainage
As-Built Details
Validation
Remark
R= 360, Ls=60m
R= 360, Ls=60m
=19 14 38
=19 13 55
R= 1200
R= 1200
=4 00 00
=4 01 18
Coincide
Coincide
From the above table it is evident that most of as-built details of horizontal alignment in terms of
bearing, distances and other geometric parameters are very close to results of validation survey. The
road was built four years before hence there could be slight variation in the details obtained when
compared to the as-built and variation could also be possible due to various type of surveys
instrument and time of surveys.
Vertical Alignment
Sufficient details were collected at vertical curve location at selected chainages to assess and
validate the geometric characteristics for Vijayawada-Gundugolanu section. The following table
summarise these geometric characteristics.
Validation of Vertical Alignment
S. No
Chainage
As-Built Details
Validation
Remark
VIP 1036+080
IN: 0.236%
IN: 0.251%
Coincide
Eluru Bypass
Lvc=198.162m
Lvc=198.162m
IN: 3.077%
IN: 3.047%
Lvc=438.449m
Lvc=438.449m
OUT: 2.858%
OUT: 2.885%
Vijayawada Gundanagolu
1
As mentioned in the earlier chapter on As-Built drawings validation the alignment and profile details
in the as-built drawings are insufficient to check the layout characteristics. Hence the validation no
vertical alignment is limited to verifying the grades as-built and curve length if the details available.
From the above table it clear that there is not much variation in the results found compared to the
details given in the as-built drawings.
5.2
TRAFFIC SURVEYS
The Reconnaissance survey which was conducted which helped in identification and understanding
of homogeneous traffic sections, visible travel pattern on the corridor, major traffic generators/
attractors along and off the project road, major intersections etc. Accordingly various traffic surveys
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-8
were then planned to capture the traffic and travel characteristics on the sections of the project
corridor. The surveys conducted include, classified traffic volume count surveys, origin-destination
surveys, intersection turning movement count surveys, pedestrian count surveys, speed & delay etc.
th
th
The first traffic surveys were conducted between 10 Dec 2006 and 8 Jan 2007, under the
supervision of traffic engineer. The results from these traffic studies including traffic projections are
th
discussed in detail in Chapter 6 of this report. Further traffic surveys were carried out between 25
th
February and 6 March 2007 (Vijayawada-Gundanagolu section), and during this second period axle
load surveys were carried out in 1 location (Vijayawada-Gundanagolu section) [48hrs each location,
th
traffic both ways weighed]. Further traffic surveys were carried out between 7 December and 13
December 2010 (Vijayawada Bypass).
5.3
th
The Right of Way details (roadway width in meters) collected from the NHAI local offices [in
December 2006] are presented in the following sections. Discussions with local NHAI and Revenue
officers reveals that the recent land-take for 4-laning of project road was restricted [when 4 laning
was undertaken in the 1990s] only to the minimum required for the construction of additional 2 lanes
on the sections other than bypasses. Further these offices do not hold the up-dated revenue records
after the acquisition for 4-laning project except for some revenue divisions. It is also learned that the
RoW boundary stones established in some sections are destroyed locally by the public for various
reasons including farming. Subsequently the details collected were randomly verified on the field
wherever possible and found to be relatively close to the widths provided by these organisations.
See Chapter 12 for more details.
5.4
The utility surveys will be carried out to identify the sewers, gas/oil pipes, crossings, electric, and
telephone lines (O/H & U/G) and poles, optical fiber cables (OFC) etc. The survey covers the entire
right-of-way of the road on the adequate allowance for possible shifting of the central lines at some of
the intersections locations.
Utilities Agencies have various degrees of authority to install their lines within the right of way of
roads. Depth, size, etc of utilities are based on the IRC98-1997 guidelines.
Coordinates of all the surface utilities, which include electric poles, telephone poles, towers,
transforms, over head electric and telephone lines etc., will be picked up during the detailed
topographic surveys. The details of underground utilities will be collected from the concerned
departments. The utility information from these sources will be drawn on the base plan to develop
utility shifting plans.
The information collected during reconnaissance and field surveys will be shown on a strip plan so
that the proposed improvements can be appreciated and the utilities required to be shifted for each
type can be assessed and suitable actions can be initiated.
Land Acquisition Surveys also done for 3(a), 3A and 3D publication.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
5.5
Reports Code
Page
Rev.
5-9
The pavement condition survey, along with a roughness survey was carried out in the last 2 weeks of
December 2006 for Vijayawada-Gundugolanu section. Full details are given in Chapter 11 and
Annex 3.2. The survey included a road inventory, plus IRI [roughness measurements].
5.6
MATERIALS INVESTIGATIONS
An initial materials investigation was carried out, see Chapter 11 for Vijayawada-Gundugolanu
section.
For Vijayawada/Hanuman Junction Bypass
The sources of materials, quarry sites, borrow areas and fly ash will be identified and field/laboratory
testing of these materials will be carried out to determine their suitability for various components of
the work and to establish quality & quantity of various construction materials and to recommend their
use on the basis of techno-economic principles. The mass haul diagram for haulage purposes will be
prepared giving quarry charts indicating the location of selected borrow areas, quarries and the
respective estimated quantities.
Environmental restrictions, if any, and feasibility of availability of these sites to prospective
concessionaires, will be duly taken into account while selecting new quarry locations.
Suitable recommendations will be made regarding making good the borrow areas and quarry areas
after the exploitation of materials for construction of works.
The Material Investigation aspect will include preparation and testing of bituminous mixes for various
layers and concrete mixes of different design mix grades using suitable materials (binders,
aggregates, sand filler etc.,) as identified during Material Investigation to conform to latest MORT&H
specification.
5.7
5.7.1
The following details have been collected for the Vijayawada/Hanuman Junction Bypasses project:
Catchment area
An index map to a suitable scale. i.e., Topo sheets in scale of 1:50000, showing the
alignment, location of proposed bridges etc. Drainage area mapping is done based on the
topo sheets, contours available from Bhuvan maps and Google maps.
Assessment of ground water condition (Water Table).
Reports from CWC and IMD for Flood Estimation
Flood Estimation reports from CWC for small catchments. This report forms the base for
preparing the synthetic unit hydrographs for the purpose of flood estimation.
Rainfall Isohyets for rainfall data for various return periods
Floods and Discharge Data
History of floods, if any and Survey of observed Maximum flood levels (OMFL) or High
Flood Level (HFL) with reference to GTS bench marks
Discharge details of canals from respective departments.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-10
Survey Data
Geological information
Topo surveys data including the alignment survey
Bridge locations - Cross and Longitudinal Sections
5.8
The Senior Bridge Engineer along with a team of bridge / field engineers carried out the inventory
and condition survey of the complete project road. Visual inspection was done to find out the
deficiencies in the structures. At some bridge locations, due to water logging in the entire waterway, it
was not possible to inspect the structure. Type of expansion joints in the old existing bridges could
not be ascertained as they are covered with bituminous overlays at most of the bridge locations.
There are 333 (Km 1076+480 to Km 1061+080 and Km 1056+08 to 1022+480) numbers of
structures (existing minor / major bridges, RoBs, and underpasses) of all 2lane configurations each
side and 128 (Vijayawada and Hanuman Junction Bypass) numbers of structures (minor / major
bridges, RoBs, and underpasses) on proposed bypasses. Out of which the total number of RoBs are
5. The list of the RoBs is given in the following table.
Rail Over Bridges
S. No
ChianageProgressive
Kms
ROB
Structure
No.
Length
(m)
LHS
CW
Width (m)
Remark
Length
(m)
RHS
CW
Width (m)
Remark
Vijayawada Bypass
1
Km 2+500
112
12
Proposed
Bypass
112
12
Proposed
Bypass
Km 20+590
552
12
Proposed
Bypass
552
12
Proposed
Bypass
Km 45+870
378
12
Proposed
Bypass
378
12
Proposed
Bypass
1049+527
(Eluru
Bypass)
1033+824
(Eluru
Bypass)
55/2
71.2
7.5
New
71.2
7.5
New
70/7
89.25
7.5
New
89.25
7.5
New
The following typical defects were noticed in the structures based on the visual inspection:
Settlement of approach slab
Damaged Hand Railing
Vegetation growth at up-stream and down-stream
Damaged metallic crash barriers in approaches
Missing / non uniform structure numbers and chainages
Debris on pier and abutment caps
Debris on bridge deck / expansion joints
Missing / damaged blocked drainage spouts
Un dismantled False steining of well foundations
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
5-11
5.9
The preliminary Environmental Examination for the proposed project has been undertaken as a
parallel exercise with the Engineering Analysis, so as to bring out the environmental concerns in
planning and the proposed design. The basic aim of the present study is to assess the magnitude of
actual and potential environmental concerns due to conversion of the existing 4 lane National
Highways into six lanes. This is also to ensure that the environmental considerations are given due
weightage, in the design of proposed highway improvements being studied. Basic idea is to minimize
adverse environmental and social impacts with best possible engineering solutions at the optimal
cost to make development environmentally sound and sustainable.
Environmental Screening of the study area has the following major objectives:
To delineate the major environmental issues and identify the potential hotspots, which
requires further study i.e. scope for EA,
The detailed analysis and results of Environment and Social Surveys are presented in chapter 19.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-1
Chapter 6: Contents
CHAPTER 6: CONTENTS ............................................................................................................................ 1
6
6.1
GENERAL ............................................................................................................................................ 2
6.2
6.3
6.2.1
6.2.2
6.2.3
6.3.2
6.3.3
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-2
6.1
GENERAL
The present project is development of new bypasses for the Vijayawada city and Hanuman Junction town
and four lane to six laning of Vijayawada-Gundugolanu section of NH-5. Vijayawada is thirty fourth largest
urban agglomerations in the country and comprises of Vijayawada Municipal Corporation (VMC),
Mangalagiri Municipality, 4 Panchayats and outgrowths. Vijayawada is the third largest city of the State of
Andhra Pradesh. The population of the city as per the 2001 census is 8,45,217 and is growing at an
average decadal growth rate of 39.72.
The existing NH-5 passes through the city. Two National Highways NH-5 and NH-9 intersect in the city.
NH-9 connects the city with Hyderabad, Capital of Andhra Pradesh and Machilipatnam, port town. NH-5
leads to Visakhapatnam and Chennai two of the busiest ports of India. Figure 6.1 presents the details.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-3
The 47.88 km long project corridor starts after Kaza toll plaza and continues to West of Vijayawada and
ends after Gannnavaram but before the Pottipadu toll plaza. The present project involves evaluation of
the technical feasibility of Vijayawada bypass with the 6 lane facility with partial/full access control through
provision of service roads, grade separation etc to ensure safety and the assessment of cost of
development. This Chapter discusses the traffic surveys conducted, traffic estimate for the bypass and
traffic projections etc.
Traffic surveys have been conducted in the 2007 for the project Feasibility Study for 6 Laning of
Vijayawada-Rajahmundry section, NH-5 and also Feasibility Study for 6 laning of ChilakaluripetVijayawada section, NH-5. For the above studies, 7 days TVC count and 24 hours OD surveys has been
conducted at number of locations as per the requirements of NHAI. Detailed analysis of the traffic has
been presented in the Feasibility Report for the above projects. However, for the present study the traffic
data on either side of the bypass in the immediate vicinity has been used. The survey locations data
which is used in the present study are presented below at Table 6.1.
Table 6.1: Traffic Survey Locations
Sl. No.
Survey
Origin-Destination Survey
Location
Kaza Toll Plaza (Km 1114+044)
Pottipadu Toll Plaza (Km
1072+580)
On NH 9 near Gollapudi
Kaza Toll Plaza (Km 1114+044)
Pottipadu Toll Plaza (Km
1072+580)
On NH 9 near Gollapudi
Remarks
7 Days
24 Hrs
AADT Traffic at the Kaza & Pottipadu Toll Plaza locations is presented in the Table 6.2 below.
Table 6.2: AADT at Survey Locations
Vehicle Classification
Two Wheeler
Auto Rickshaw
Car/Jeep/Van
Tempo
Bus
Mini Bus
Bus
LCV
2 Axle
3 Axle Rigid
MAV
Without Trailer
Agri. Tractor
With Trailer
Total Motorized Vehicle (MV)
Trucks
Pottipadu Toll
Plaza
(Km 1072+580)
2,225
606
2,563
507
52
1,161
Kaza Toll
Plaza
(Km 1114+044)
5,784
1,022
3,960
1,006
77
1,734
470
1,633
2,249
276
10
56
11,808
569
1,952
2,199
216
20
84
18,623
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Gollapudi
NH 9
6,783
2,379
6,279
1,815
372
2,726
1,451
5,788
3,505
368
74
49
31,589
Reports Code
Page
Rev.
6-4
Vehicle Classification
Animal/Hand Drawn
Cycle
Cycle Rickshaw
Others
Total Non Motorized Vehicle
(NMV)
Total AADT (Vehicles)
Total AADT (PCU)
6.2
6.2.1
Pottipadu Toll
Plaza
(Km 1072+580)
6
390
51
Kaza Toll
Plaza
(Km 1114+044)
11
520
44
37
450
584
968
12,258
22,557
19,207
29,339
32,557
56,695
Gollapudi
NH 9
46
885
Total 6 alignment options were studied, but they basically fall into two categories westerly alignment and
easterly alignment. The Western side alignment is providing connectivity to Hyderabad and the other on
Eastern side is providing connectivity to Machilipatnam. The alignment options studied are presented in
Figure 6.2.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-5
The length details of the different options studied are presented in Table 6.3.
Table 6.3: Bypass Options
S.N.
Option
Length, Km
Option - 1
39.900
Option 2
31.700
Option 3
26.800
Option 4
25.800
Option 5
39.170
Option 6
47.880
Sec 1
Sec 2
305
535
Mini Bus
Bus
LCV
283
213
2 Axle Truck
952
1,502
3 Axle Truck
1,112
700
127
140
HCM/ EME
2,779
3,090
MAV up to 6 Axle
Total Vehicles
The directional distribution of traffic for the year 2010 is presented graphically below:
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
6.2.3
Reports Code
Page
Rev.
6-6
Growth Rates
Growth rates estimated for the Feasibility Study for 6 laning of Chilakaluripet-Vijayawada, NH-5 are
suitably modified in the light of four laning of the Hyderabad-Vijayawada section and adopted for the
present study. Detailed analysis of the growth rates estimation is presented in the Feasibility study for 6
laning of Chilakaluripet-Vijayawada, NH-5. The growth rates estimated for the study are presented for the
realistic scenario. The estimated growth rates for different vehicle types are as below:
Table 6.5: Proposed Growth Rates (%)
Period
Two
Wheeler
Car
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
2011-15
8.7
7.0
5.5
5.5
6.6
6.6
6.6
MAV up
to 6
Axle
6.6
2016-20
7.1
6.5
5.5
5.5
6.6
6.6
6.6
2021-25
5.3
6.0
5.0
5.0
6.1
6.1
>2025
5.3
5.0
5.0
5.0
5.0
5.0
MAV >6
Axles
HCM/
EME
6.6
6.6
6.6
6.6
6.6
6.1
6.1
6.1
6.1
5.0
5.0
5.0
5.0
For other vehicle types, a nominal growth rate of 2% per annum has been assumed for the study. As the
immediate influence area is agriculturally rich, the agricultural vehicles (non-motorised) are not expected
to diminish.
Estimated traffic of the Vijayawada bypass has been projected with 5% growth rate and presented for
the year 2010 and cardinal years in the Table below:
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-7
Table 6.6: Projected Traffic for the Western Alignment Vijayawada Bypass Section 1
Year
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV up
to 6
Axle
MAV >6
Axles
HCM/
EME
Total
PCUs
2007
305
283
952
1,112
127
7,493
2008
320
297
1,000
1,168
133
7,868
2009
336
312
1,050
1,226
140
8,262
2010
353
328
1,103
1,287
147
8,677
2011
371
344
1,158
1,351
154
9,107
2012
390
361
1,216
1,419
162
9,566
2,013
410
379
1,277
1,490
170
10,045
2014
431
398
1,341
1,565
179
10,552
2015
453
418
1,408
1,643
188
11,079
2016
476
439
1,478
1,725
197
11,630
2017
500
461
1,552
1,811
207
12,212
2,018
525
484
1,630
1,902
217
12,824
2,019
551
508
1,712
1,997
228
13,466
2,020
579
533
1,798
2,097
239
14,139
2,021
608
560
1,888
2,202
251
14,848
2,022
638
588
1,982
2,312
264
15,590
2,023
670
617
2,081
2,428
277
16,369
2024
704
648
2,185
2,549
291
17,188
2025
739
680
2,294
2,676
306
18,046
2026
776
714
2,409
2,810
321
18,949
2027
815
750
2,529
2,951
337
19,897
2028
856
788
2,655
3,099
354
20,893
2029
899
827
2,788
3,254
372
21,940
2030
944
868
2,927
3,417
391
23,038
2031
991
911
3,073
3,588
411
24,190
2032
1,041
957
3,227
3,767
432
25,403
2033
1,093
1,005
3,388
3,955
454
26,673
2034
1,148
1,055
3,557
4,153
477
28,007
2035
1,205
1,108
3,735
4,361
501
29,410
2036
1,265
1,163
3,922
4,579
526
30,880
2037
1,328
1,221
4,118
4,808
552
32,422
2038
1,394
1,282
4,324
5,048
580
34,043
2039
1,464
1,346
4,540
5,300
609
35,744
2040
1,537
1,413
4,767
5,565
639
37,528
2041
1,614
1,484
5,005
5,843
671
39,404
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-8
Year
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV up
to 6
Axle
MAV >6
Axles
HCM/
EME
Total
PCUs
2042
1,695
1,558
5,255
6,135
705
41,375
2043
1,780
1,636
5,518
6,442
740
43,444
2044
1,869
1,718
5,794
6,764
777
45,617
2045
1,962
1,804
6,084
7,102
816
47,898
2046
2,060
1,894
6,388
7,457
857
50,293
Year
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV up
to 6
Axle
MAV >6
Axles
HCM/
EME
Total
PCUs
2007
535
213
1,502
700
140
8,091
2008
562
224
1,577
735
147
8,496
2009
590
235
1,656
772
154
8,920
2010
620
247
1,739
811
162
9,370
2011
651
259
1,826
852
170
9,839
2012
684
272
1,917
895
179
10,334
2,013
718
286
2,013
940
188
10,852
2,014
754
300
2,114
987
197
11,394
2,015
792
315
2,220
1,036
207
11,964
2,016
832
331
2,331
1,088
217
12,562
2,017
874
348
2,448
1,142
228
13,192
2,018
918
365
2,570
1,199
239
13,848
2,019
964
383
2,699
1,259
251
14,542
2,020
1,012
402
2,834
1,322
264
15,271
2,021
1,063
422
2,976
1,388
277
16,035
2,022
1,116
443
3,125
1,457
291
16,836
2,023
1,172
465
3,281
1,530
306
17,680
2024
1,231
488
3,445
1,607
321
18,564
2025
1,293
512
3,617
1,687
337
19,490
2026
1,358
538
3,798
1,771
354
20,465
2027
1,426
565
3,988
1,860
372
21,492
2028
1,497
593
4,187
1,953
391
22,566
2029
1,572
623
4,396
2,051
411
23,697
2030
1,651
654
4,616
2,154
432
24,886
2031
1,734
687
4,847
2,262
454
26,135
2032
1,821
721
5,089
2,375
477
27,441
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-9
Year
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV up
to 6
Axle
MAV >6
Axles
HCM/
EME
Total
PCUs
2033
1,912
757
5,343
2,494
501
28,813
2034
2,008
795
5,610
2,619
526
30,255
2035
2,108
835
5,891
2,750
552
31,768
2036
2,213
877
6,186
2,888
580
33,361
2037
2,324
921
6,495
3,032
609
35,027
2038
2,440
967
6,820
3,184
639
36,778
2039
2,562
1,015
7,161
3,343
671
38,616
2040
2,690
1,066
7,519
3,510
705
40,549
2041
2,825
1,119
7,895
3,686
740
42,577
2042
2,966
1,175
8,290
3,870
777
44,705
2043
3,114
1,234
8,705
4,064
816
46,944
2044
3,270
1,296
9,140
4,267
857
49,292
2045
3,434
1,361
9,597
4,480
900
51,757
2046
3,606
1,429
10,077
4,704
945
54,345
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-10
Table 6.8: Projected Traffic for the portion from Vijayawada Bypass to Gundugolanu
Year
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2
Axle
Truck
3 Axle
Truck
MAV
up to
6
Axle
MAV
>6
Axles
HCM/
EME
Two
Wheeler
Auto
Ricksh
aw
Temp
o
Agri
Tract
or
Agri
Tractor
&
Trailor
Animal
Hand
drawn
Cycle
Cycle
Ricks
haw
Other
s
Tollable
Traffic
PUCs
Total
PCUs
2007
2,605
48
1,008
490
1,440
2,178
326
2,482
572
527
14
55
293
21
18,757
21,605
2008
2,735
50
1,058
515
1,512
2,287
342
2,606
601
553
15
58
308
22
19,693
22,682
2009
2,872
53
1,111
541
1,588
2,401
359
2,736
631
581
16
61
323
23
20,679
23,816
2010
3,016
56
1,167
568
1,667
2,521
377
2,873
663
610
17
64
339
24
21,714
25,005
2011
3,167
59
1,225
596
1,750
2,647
396
3,017
696
641
18
67
356
25
22,798
26,251
2012
3,325
62
1,286
626
1,838
2,779
416
3,168
731
673
19
70
374
26
23,938
27,560
2,013
3,491
65
1,350
657
1,930
2,918
437
3,326
768
707
20
74
393
27
25,135
28,937
2014
3,666
68
1,418
690
2,027
3,064
459
3,492
806
742
21
78
413
28
26,396
30,386
2015
3,849
71
1,489
725
2,128
3,217
482
3,667
846
779
22
82
434
29
27,714
31,901
2016
4,041
75
1,563
761
2,234
3,378
506
3,850
888
818
23
86
456
30
29,097
33,489
2017
4,243
79
1,641
799
2,346
3,547
531
4,043
932
859
24
90
479
32
30,552
35,160
2,018
4,455
83
1,723
839
2,463
3,724
558
4,245
979
902
25
95
503
34
32,079
36,918
2,019
4,678
87
1,809
881
2,586
3,910
586
4,457
1,028
947
26
100
528
36
33,682
38,762
2,020
4,912
91
1,899
925
2,715
4,106
615
4,680
1,079
994
27
105
554
38
35,364
40,694
2,021
5,158
96
1,994
971
2,851
4,311
646
4,914
1,133
1,044
28
110
582
40
37,134
42,727
2,022
5,416
101
2,094
1,020
2,994
4,527
678
5,160
1,190
1,096
29
116
611
42
38,994
44,866
2,023
5,687
106
2,199
1,071
3,144
4,753
712
5,418
1,250
1,151
30
122
642
44
40,945
47,109
2,024
5,971
111
2,309
1,125
3,301
4,991
748
5,689
1,313
1,209
32
128
674
46
42,994
49,465
2,025
6,270
117
2,424
1,181
3,466
5,241
785
5,973
1,379
1,269
34
134
708
48
45,143
51,932
2,026
6,584
123
2,545
1,240
3,639
5,503
824
6,272
1,448
1,332
36
141
743
50
47,398
54,525
2,027
6,913
129
2,672
1,302
3,821
5,778
865
6,586
1,520
1,399
38
148
780
53
49,765
57,247
2,028
7,259
135
2,806
1,367
4,012
6,067
908
6,915
1,596
1,469
40
155
819
56
52,253
60,106
2029
7,622
142
2,946
1,435
4,213
6,370
953
7,261
1,676
1,542
42
163
860
59
54,863
63,107
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-11
Year
Car/
Jeep/
Van
Mini
Bus
Bus
LCV
2
Axle
Truck
3 Axle
Truck
MAV
up to
6
Axle
MAV
>6
Axles
HCM/
EME
Two
Wheeler
Auto
Ricksh
aw
Temp
o
Agri
Tract
or
Agri
Tractor
&
Trailor
Animal
Hand
drawn
Cycle
Cycle
Ricks
haw
Other
s
Tollable
Traffic
PUCs
Total
PCUs
2030
8,003
149
3,093
1,507
4,424
6,689
1,001
7,624
1,760
1,619
44
171
903
62
57,610
66,263
2031
8,403
156
3,248
1,582
4,645
7,023
1,051
8,005
1,848
1,700
46
180
948
65
60,488
69,572
2032
8,823
164
3,410
1,661
4,877
7,374
1,104
8,405
1,940
1,785
48
189
995
68
63,512
73,046
2033
9,264
172
3,581
1,744
5,121
7,743
1,159
8,825
2,037
1,874
50
198
1,045
71
66,689
76,694
2034
9,727
181
3,760
1,831
5,377
8,130
1,217
9,266
2,139
1,968
53
208
1,097
75
70,023
80,528
2035
10,213
190
3,948
1,923
5,646
8,537
1,278
9,729
2,246
2,066
56
218
1,152
79
73,527
84,553
2036
10,724
200
4,145
2,019
5,928
8,964
1,342
10,215
2,358
2,169
59
229
1,210
83
77,203
88,778
2037
11,260
210
4,352
2,120
6,224
9,412
1,409
10,726
2,476
2,277
62
240
1,271
87
81,060
93,209
2038
11,823
221
4,570
2,226
6,535
9,883
1,479
11,262
2,600
2,391
65
252
1,335
91
85,113
97,867
2039
12,414
232
4,799
2,337
6,862
10,377
1,553
11,825
2,730
2,511
68
265
1,402
96
89,370
102,762
2040
13,035
244
5,039
2,454
7,205
10,896
1,631
12,416
2,867
2,637
71
278
1,472
101
93,842
107,900
2041
13,687
256
5,291
2,577
7,565
11,441
1,713
13,037
3,010
2,769
75
292
1,546
106
98,536
113,296
2,042
14,371
269
5,556
2,706
7,943
12,013
1,799
13,689
3,161
2,907
79
307
1,623
111
103,465
118,962
2,043
15,090
282
5,834
2,841
8,340
12,614
1,889
14,373
3,319
3,052
83
322
1,704
117
108,639
124,907
2,044
15,845
296
6,126
2,983
8,757
13,245
1,983
15,092
3,485
3,205
87
338
1,789
123
114,071
131,150
2045
16,637
311
6,432
3,132
9,195
13,907
2,082
15,847
3,659
3,365
91
355
1,878
129
119,773
137,702
2046
17,469
327
6,754
3,289
9,655
14,602
2,186
16,639
3,842
3,533
96
373
1,972
135
125,763
144,587
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
6-12
IRC: 64 - 1990 stipulates a design service volume of 40,000 PCU per day for a four lane divided
carriageway with paved shoulders at level of service B and plain terrain. This can be further increased
upto 60,000 PUCs by adopting LOS C.
The Vijayawada bypass crosses 40,000 PCUs in the year 2042 and 2040 for the sections 1 & 2
respectively. Hence it may be prudent to consider them for four laning only.
The section between Vijayawada bypass to Gundugolanu reaches the 40,000 PCUs in the year 2020 and
60,000 PUCs in the year 2028. Hence it is necessary to consider it for 6 laning now itself.
6.3
TOLLING STRATEGY
Tolling strategy in the present context is the identification of toll plaza locations and tolling sections, which
can fetch maximum revenue with minimum leakage and cost within the given constraints. Open tolling
system is to be adopted for the corridor. This means, flat toll rates calculated for the length of tolling
section(s) shall be charged at the respective toll plazas giving concessions/discounts as applicable to
local / frequent users as decided by authority.
The present package starts from the take off point of Vijayawada bypass 2.1 km after Kaza toll plaza (Km
422+800 new chainage) of Chilakaluripet-Vijayawada section to Gundugolanu (Km 1022+480) of
Vijayawada-Visakhapatnam section of NH-5. This comprises of Vijayawada bypass and Hanuman
Junction Bypass and existing Eluru bypass.
Vijayawada Bypass
The total length of the Vijayawada bypass is 47.880 km having two sections. The first section takes off 2.1
km after the Kaza toll plaza (Km 1112+044 new chainage) towards Vijayawada and joins NH 9 near
Gollapudi and is having a length of 18.650 km. The first section consists of bridge on Krishna river with a
length of 3.144 km. The second section starts from NH-9 and joins NH 5 at (Km 1076+480,
Chinnaautupalli) towards Eluru after Gannavaram and is having a length of 29.23 km. The distance
between the end of the bypass and Pottipadu toll plaza is 3.90 km.
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Reports Code
Page
Rev.
6-13
Chainage, km
Section
1114+044
1072+580
1050+780
Km 1182+804 - Km 1100+184
Km 1100+680 - Km 1061+580
Km 1061+580 Km 1022+480
Length,
km
81.6
39.1
39.1
The Kaza toll plaza is collecing toll from Km 355.0 to Km 434.15 till the end of ongoing 6 laning, which
includes 15.25 km from the takeoff point of Vijayawada bypass to Kanakadurga Varadhi on the existing
NH 5 towards Vijayawada town. It is desirable not to disturb the existing concession of Kaza toll plaza.
The road users who desire to use the bypass road of section 1 will not be using the 12.5 km of the
existing NH 5 for which toll is already paid t toll at Kaza toll plaza and hence need not be double charged.
This point needs to be taken in to consideration.
Similarly the Pottipadu toll plaza is collecting toll from Km 1100+680 (Kanakadurga Varadhi) to Km
1061+580 which includes 24.2 km from the joining point of Vijayawada bypass to Kanaka durga Varadhi
on the existing NH 5 towards the Vijayawada town. The road users who desire to use the bypass road of
section 2 will not be using the 24.2 km of the existing NH 5 for which toll is already paid t toll at Pottipadu
toll plaza and hence need not be double charged. This point needs to be taken in to consideration.
The Kalaparru toll plaza is collecting toll from Km 1061+580 (Veleru town) to Km 1022+480
(Gundugolanu). The proposed toll plaza on section 2 of Vijayawada Bypass and Pottipadu toll plaza are
close by and hence it is proposed to do away with the Pottipadu toll plaza. Even the Pottipadu toll plaza
and Kalaparru toll plaza are close by.
Finally it is proposed to have total three toll plaza two on the Vijayawada Bypass , one on section 1, one
on section 2 and retaining the existing toll plaza at Kalaparru.
The details are provided at Table 6-10 below :
Table 6.10: Proposed Tolling Sections
S.No.
Tolling Section
Remarks
Km 11+500
on proposed Vijayawada
Bypass
Kaza to Gollapudi
Km 0 to Km 18+650
(15.25 km of NH-5 is
adjusted in the toll rate )
Km 35+000
on proposed Vijayawada
Bypass
Gollapudi Chinnaavutapalli
Km 18+650 to Km 47+880
(24.2 km of NH-5 is
adjusted in the toll rate)
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Reports Code
Page
Rev.
6-14
Km 1050+780
on Existing Vijayawada
Gundugolanu section
Kanakadurga Varadhi
Gundugolanu
Km 1100+680 to Km
1022+480
Includes Hanuman
Junction (6.7 km) Bypass
As per the toll policy all the structures and bypasses costing more than Rs 10 crores need to be charged
separately at the toll rates specified in the policy. Since cost of the two sections of Vijayawada bypass and
the Hanuman Junction bypass are more than Rs 10 Crores each of them will be charged separately.
6.3.1
The Toll Policy specifies four categories of traffic for the purpose of tolling and toll discount and they are:
Local Traffic means vehicles used for non-commercial purpose and includes personal vehicles of
residents of villages/towns/cities on Project Highway whose boundary falls within radius of 20 Kms of Toll
Plaza.
Frequent Travelers When the same mechanical vehicle has to use the said section frequently for the
entire month, the vehicle owner may obtain a monthly pass on the payment of charges equivalent to 2/3
rd the 50 single trip rates applicable to it.
Return Trips When the same mechanical vehicle has to cross the section more than once in a day, the
user shall have the option to pay the fee for the multiple trips at the rates one and half times the single trip
rate.
Normal Traffic Other than local, frequent travelers, return trips
Exempt Vehicles Two wheelers, three wheelers, animal drawn vehicles and tractors with or without trailor
or trolley and other slow moving vehicles would not be allowed to use the main highway.
Accordingly traffic under different categories has been estimated from the OD Analysis. This information is
used for estimating the toll revenue under three different scenarios realistic, optimistic, and pessimistic.
6.3.2
Toll Rate
The tolling rates are as per the notification issued under Section 8A of the National Highways Act, 1956
(48 of 1956), read with Rule 3 of the National Highways Fee (Determination of Rates and Collection)
Rules, 2008. The base toll rates for the different modes per km are given below:
Table 6.11: Toll rates for the different Categories of vehicles
S.No.
Category of Vehicle
0.65
1.05
Bus/Truck
2.20
3.45
4.20
The aforesaid rates are based on wholesale price index (WPI) for the month of December, 2007, which is
216.4.
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Reports Code
Page
Rev.
6-15
WPI A is the WPI of the week ending on or subsequent to 1 January immediately preceding the
date of revision under their rules; and
WPI B is the WPI for the month of December, 2007 i.e. 216.4.
Local users:
Local traffic is defined as ones whose boundary falls within 20 Km of fees collection booth. The toll rates
for local users Rs 150/- per month with reference to the base year 2007-08 to be revised annually to
reflect the variation in WPI and then rounded off to the nearest 5 (five) rupees.
Return Trip
The return trips are charged at the rate of 1.5 times the single journey toll rate and will be valid for any
number of trips undertaken during that day of 24 hours.
Frequent Travelers
The frequent travelers are charged at the rate of 2/3rds of the 50 times the single journey toll rate.
WPI
Data from Central Statistical Organization has been collected and analyzed for long term trend. It is
observed that the long term growth in the WPI to be 5 %.
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Reports Code
Page
Rev.
6-16
The toll rates will be calculated for each of the tolling sections and will be rounded off to the nearest 5
rupee. The discount toll rates will be calculated as discussed above. Projected toll rates for each of the toll
plaza are presented in Table 6-13.
Table 6.12: Toll Rates on different sections
Car/
Jeep/
Van
Tolling Section - 1
Financial
Year
Mini
Bus
Bus
LCV
2 Axle
Truck
3 Axle
Truck
MAV up
to 6 Axle
MAV >6
Axles
HCM/EME
2015-16
10
20
40
20
40
65
65
80
65
2020-21
15
25
55
25
55
85
85
100
85
2025-26
20
35
70
35
70
105
105
130
105
2030-31
25
40
90
40
90
140
140
170
140
2035-36
35
55
115
55
115
180
180
215
180
2040-41
45
70
150
70
150
230
230
285
230
Tolling Section - 2
2015-16
20
30
65
30
65
100
100
125
100
2020-21
25
40
85
40
85
130
130
160
130
2025-26
30
50
105
50
105
165
165
200
165
2030-31
40
65
135
65
135
215
215
260
215
2035-36
50
85
175
85
175
275
275
335
275
2040-41
70
110
230
110
230
360
360
435
360
Tolling Section - 3
2015-16
80
130
275
130
275
430
430
525
430
2020-21
105
165
350
165
350
550
550
670
550
2025-26
130
215
450
215
450
705
705
855
705
2030-31
170
275
575
275
575
905
905
1,100
905
2035-36
220
355
745
355
745
1,170
1,170
1,425
1,170
2040-41
285
460
970
460
970
1,520
1,520
1,850
1,520
6.3.3
Toll Revenue
Toll revenue is calculated by multiplying the projected tollable traffic by category and the toll rates. The toll
rates are revised annually for the normal traffic and rounded to the nearest rupee. The local traffic toll
rates are revised every year and rounded to the nearest 5 rupees. The year wise toll revenue at each toll
plaza for each option is presented in Table 6-14. Since the toll rates for the bypasses are same
(irrespective of the cost of the bypass), the toll revenue for all the three options will be same. Hence one
revenue table is presented at Table 6-14.
Table 6.13: Year wise and section wise Toll revenue for all the four options
Section 1
Section 2
Section 3
Total
Daily
Yearly
Daily
Yearly
Daily
Yearly
Daily
Yearly
Rs '000s
Rs Millions
Rs '000s
Rs Millions
Rs '000s
Rs Millions
Rs '000s
Rs Millions
2014-15
167.34
61.08
243.30
88.80
2,480.45
905.36
2,891.08
1,055.24
2015-16
175.60
64.27
271.55
99.39
2,739.59
1,002.69
3,186.74
1,166.35
2016-17
202.02
73.74
302.49
110.41
3,023.35
1,103.52
3,527.86
1,287.67
Year
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Reports Code
Page
Rev.
6-17
Section 1
Section 2
Section 3
Total
Daily
Yearly
Daily
Yearly
Daily
Yearly
Daily
Yearly
Rs '000s
Rs Millions
Rs '000s
Rs Millions
Rs '000s
Rs Millions
Rs '000s
Rs Millions
2017-18
212.15
77.43
325.36
118.76
3,328.36
1,214.85
3,865.87
1,411.04
2018-19
242.86
88.64
360.92
131.73
3,675.98
1,341.73
4,279.76
1,562.11
2019-20
265.14
97.04
410.85
150.37
4,070.90
1,489.95
4,746.88
1,737.36
2020-21
298.24
108.86
452.32
165.10
4,474.53
1,633.20
5,225.09
1,907.16
2021-22
324.54
118.46
482.91
176.26
4,932.94
1,800.52
5,740.39
2,095.24
2022-23
364.65
133.10
540.17
197.16
5,429.82
1,981.88
6,334.64
2,312.14
2023-24
384.88
140.87
594.18
217.47
5,983.23
2,189.86
6,962.29
2,548.20
2024-25
427.70
156.11
660.53
241.10
6,611.84
2,413.32
7,700.08
2,810.53
2025-26
476.98
174.10
720.25
262.89
7,308.71
2,667.68
8,505.94
3,104.67
2026-27
530.63
193.68
801.93
292.70
8,059.41
2,941.68
9,391.97
3,428.07
2027-28
584.07
213.77
882.19
322.88
8,871.49
3,246.96
10,337.74
3,783.61
2028-29
648.95
236.87
990.43
361.51
9,807.88
3,579.87
11,447.26
4,178.25
2029-30
711.72
259.78
1,087.83
397.06
10,849.01
3,959.89
12,648.57
4,616.73
2030-31
796.55
290.74
1,191.75
434.99
11,972.20
4,369.85
13,960.50
5,095.58
2031-32
874.40
320.03
1,325.22
485.03
13,216.97
4,837.41
15,416.59
5,642.47
2032-33
975.65
356.11
1,449.31
529.00
14,636.09
5,342.17
17,061.05
6,227.28
2033-34
1,065.28
388.83
1,617.51
590.39
16,164.45
5,900.02
18,847.24
6,879.24
2034-35
1,178.92
430.30
1,763.53
643.69
17,906.70
6,535.94
20,849.15
7,609.93
2035-36
1,311.03
479.84
1,958.54
716.83
19,767.43
7,234.88
23,037.01
8,431.54
2036-37
1,442.76
526.61
2,175.09
793.91
21,835.51
7,969.96
25,453.37
9,290.47
2037-38
1,590.20
580.42
2,407.37
878.69
24,152.93
8,815.82
28,150.50
10,274.93
2038-39
1,772.97
647.13
2,667.92
973.79
26,702.94
9,746.57
31,143.83
11,367.49
2039-40
1,937.92
709.28
2,939.13
1,075.72
29,605.04
10,835.45
34,482.10
12,620.45
2040-41
2,150.17
784.81
3,283.45
1,198.46
32,802.02
11,972.73
38,235.64
13,956.00
2041-42
2,380.85
869.01
3,610.58
1,317.86
36,237.80
13,226.79
42,229.23
15,413.66
2042-43
2,656.88
969.76
4,012.52
1,464.57
40,198.07
14,672.29
46,867.47
17,106.62
2043-44
2,916.69
1,067.51
4,446.49
1,627.42
44,466.56
16,274.76
51,829.75
18,969.69
2044-45
3,231.63
1,179.54
4,938.16
1,802.43
49,343.55
18,010.39
57,513.33
20,992.36
Year
The NPV @ 10%, 12% and 15% for all the four options is also calculated for 30 years and presented at
Table 5.18. This NPV refers to the toll revenue streams only.
Table 6.14: NPV for different discount rates
(Rs in Millions)
NPV
10%
12%
15%
NPV
30,308.39
23,075.82
16,157.01
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Reports Code
Page
Rev.
7-1
Chapter 7: Contents
Chapter 7: Contents ....................................................................................................................... 1
7
7.1
INTRODUCTION ...................................................................................................................... 2
7.2
7.3
ACCIDENT DATA..................................................................................................................... 5
7.4
7.5
CONCLUSIONS ....................................................................................................................... 7
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
7-2
7.1
INTRODUCTION
Initially, the corridor was widened to a four lane carriageway, with limited safety features included
in the design. Later in the year 2003, a study was commissioned to identify and design Minor
Improvements to National Highways by Span Consultants and Baptie India Jv.
The study identified projects such as crash barriers, improvements to lane markings, signage etc
and the recommendations of this study are under implementation. The project corridor is
proposed for improving to a six laning with access control and enhanced safety.
With this background, the consultants have conducted a safety issue analysis for the project
corridor based on accident information collected from the police department, site analysis etc.
This chapter discusses the identified safety issues, accident data analysis and proposed
measures to address the safety issues.
7.2
SITE VISIT
The consultants have conducted a site visit to identify safety issues and potential safety issues.
Some of these are as below:
Wrong Side Driving
It has been observed that driving on the wrong side is a more prominent and common problem on
the project road. Further to it, driving in the fast lane is more common than using the shoulder
portion. This is a major issue which could result in more severe accidents. The photographs
present some cases of wrong side driving. Such unexpected traffic situations on the road result in
avoidable accidents.
Over Loading
The overloading of vehicles is another problem on the project road and results in the poor visibility
for the traffic. Such overloading is more prominent in case of slow and agricultural vehicles. This
would not only obstruct the visibility but also reduce the lane width available for vehicles
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
7-3
overtaking and affect the level of service on the project road. The photographs below exhibit
some overloaded vehicles observed on the project road.
Uncontrolled accesses
There are many access points on to the project road and there is no control over the traffic
entering the project corridor. Most of the intersections are uncontrolled and those in the urban
areas are controlled through fixed time traffic signals or by police in the peak periods.
The above photographs present some typical intersections on the project corridor. Such
uncontrolled intersections pose a threat to safe movement of traffic on high speed corridors.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
7-4
These need to be addressed while upgrading the project corridor to a six lane access control
facility.
Pedestrian Interference
There are a number of settlements along the project road. Though the share of pedestrian
involved accidents is low but the interference with traffic is considerable. The following photos
illustrate the pedestrian interference with fast motorised traffic. Such interference will also affect
the smooth flow of traffic and may some times lead to accidents often fatal. Though there are
pedestrian over bridges at few locations, these are not being used and have now become a rest
place or restroom.
There is no access control [except where some frontage roads are provided, generally in
towns] the road has far too many access points [so you can and do drive straight into a
high speed road.
The road mixes short distance [very local including animals herded on the road in more
rural areas] and long distance traffic so there are many movements [entering the road, U
1
turning in the medians, driving the wrong way down the road , grazing in the median]
which are incompatible with the high speed long distance facility this road is supposed to
provide.
The main junctions [mostly at grade] have poor advance signing, and should be grade
separated.
For instance having bullock carts walk down the fast lane [for a few km] at night in the wrong direction into
incoming traffic happens frequently, as does pedestrians crossing the road at night in dark areas drivers
have to be alert on this road [if not they will hit something].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
7.3
Reports Code
Page
Rev.
7-5
Little thought has been given in villages and towns crossed as to how the local population
crosses the main National Highway [other than by praying first then running very quickly].
Guardrail [and barriers at approach to some bridges] is lacking in places, and hanging
loose in others.
ACCIDENT DATA
The consultants are in the process of collecting the accident information for the project corridor.
However, accident data was made available for part of the corridor. This data has been analysed
to assess the accident trends, major causes for accidents, accident types for majority of accidents
etc. Though this part data could not provide on the magnitude of accidents on the corridor, but
this can definitely provide some vital information on the safety issues. Following paragraphs
present the results of accident analysis.
The accident data collected for part
of the corridor does not show any
70
Fatal
60
% to Total
Major
Minor
50
40
30
20
10
The
Figure
7.1
presents
the
2003
2004
Year
2005
2006
there has been apparent drop in share of fatal accidents while the share of major accidents has
shown steady increase between
2004 and 2006.
35
30
20
10
minimised
through
proper
2005
2006
ea
d
O
ea n
r
it
E
fr
om nd
S
Si
de ide
S
O
w
ip
ve
e
r
H
t
u
it
r
F
n
H
ix
in
it
g
pa ed
O
rk
b
e
je
c
H dV
it
eh t
Pe
c
cd ile
es
tr
ia
H
n
it
A
ni
m
al
O
th
er
be
2004
15
2003
25
Over speeding is the major cause of accident with more than 90 percent share in the total and the
balance are vehicle getting out of control of the driver.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
7-6
The data when analysed for type and location of accident revealed that about 30% of head on
collisions taking place in village areas and in curves and the rest at intersections which a major
issue is considering the existence
of divided carriageway. This clearly
40
for
20
Fi
in
xe
g
pa d O
bj
rk
ec
ed
t
H
V
it
eh
Pe
ci
le
cd
es
tr
ia
n
O
th
er
ip
e
ur
n
Sw
ve
rt
it
H
it
Si
de
de
Si
En
d
m
ro
n
O
d
ea
H
happened to be at intersection
(Figure 7.3).
it
f
calls
60
ea
r
which
Curve
Bridge
80
intersection
100
Intersection
Village
Others
120
7.4
PROPOSED FACILITIES
Highway Patrol
Traffic Enforcement
In order for these facilities to bring an improvement the following principles should be followed:
A proper access control system should be put in place. This includes an access system
(service roads providing access to the abutting properties and possibly to the local traffic,
safe and comfortable grade separated crossings for motorised as well as non motorised
users, ramps and interchanges) and as a general principle features preventing access
(fences, curbs and barriers,).
A treatment of the median in order to prevent front collision and wrong side driving as well
as limit head light glare
A proper signage in order to deliver adequate information to the user. This should
encompass the direction signs, as well as their coordination with markings. Markings
should be treated with sufficient care and maintained with a high level of performance as
they contribute significantly to improved traffic safety.
An adequate geometry on ramps with adequate design speeds. Essential features like
acceleration / deceleration / shelter / storage lanes, pedestrian / cattle / vehicular
underpasses and their approaches, bus bays / bus stops and truck laybys; Proper turning
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
7-7
radii at the entry / exit of vehicular underpasses; Service road (minimum 5.5m width)
considered essential for circulation, merging and diverging of local traffic.
7.5
CONCLUSIONS
The general objectives are for the Concession Company to make the main NH5 road [and the
service roads] as safe as possible for all users.
The Concession Company shall follow [and shall also show it has followed] all relevant Indian
publications on road safety, especially The Manual for Safety in Road Design (A guide for
Highway Engineers) prepared in September 1998 for MOST.
A formalised safety audit procedure must be followed [to optimise the safety process, and ensure
safety is properly and formally considered] by the Concession Company during the detailed
design [and during the Construction and post construction periods].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-1
Chapter 8: Contents
CHAPTER 8: CONTENTS .................................................................................................................... 1
8.
8.1
8.1.1
8.1.2
8.1.3
8.1.4
8.2
IMPACT....................................................................................................................................................12
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-2
8.
PUBLIC UTILITIES
8.1
EXISTING UTILITIES
Almost all kinds of utility services that can be located along roads are present in the entire project
road stretch including crossings. These services were mostly re-located in the recent 4-laning civil
works contracts, however are still present in roadway itself. Some services are just located at the
edge of the shoulder and some at the toe. Ducts in median are also found in a few locations.
8.1.1
Electricity Lines
Electric Lines: The electric lines in some location are located on the edge of the right of way.
Generally these electric lines are present all along the project road on either side within 20/25 m from
the median centreline. There are also some underground electric services found in urban areas. A
few pylons are located in the island at major junctions and few just on the embankment and just out
side the right of way (potentially impacted in 6-laning). There are about 4 numbers of pylons to be
shifted for widening the road to 6 lanes.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-3
The length of the electric services present are summarised in the following table.
S. No
8.1.2
Road Section
Vijayawada Bypass
LHS
71 (Nos)
RHS
70 (Nos)
43 (Nos)
45 (Nos)
3.5
1.4
1.2
Other Utilities
Vijayawada Bypass:
The electric poles are very close at some locations and generally located on the edge of the right of
way. The electric line crosses the project highway at about 10 locations. The chainages and offset
distances from centre line are given in below table.
The Chainages and Offset distance form Centre Line
LHS
RHS
PCL Chainage
Offset from
PCL (m)
Min. Shift
Reqd. (m)
Offset from
PCL (m)
Min. Shift
Reqd. (m)
0+050
15.337
23.663
0+135
22.186
16.814
0+175
20.589
18.411
0+275
7.108
31.892
0+365
27.124
11.876
0+640
12.806
26.194
0+780
16.801
22.199
0+795
25.356
13.644
0+795
5.959
33.041
25.512
13.488
1+815
15.516
23.484
1+820
17.664
21.336
1+855
35.654
3.346
34.944
4.056
30.075
8.925
0+690
23.193
15.807
0+795
32.987
6.013
0+795
13.463
25.537
1+240
1+260
25.621
13.379
1+815
5.231
33.769
2+465
14.558
24.442
2+500
27.931
11.069
2+500
2+510
2+510
28.374
10.626
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-4
LHS
RHS
PCL Chainage
Offset from
PCL (m)
Min. Shift
Reqd. (m)
Offset from
PCL (m)
Min. Shift
Reqd. (m)
2+525
26.037
12.963
2+535
30.351
8.649
2+725
16.469
22.531
3+960
5.374
33.626
7+930
28.342
10.658
14.094
24.906
7+960
7.568
31.432
7+980
28.509
10.491
7+990
16.828
22.172
8+040
9.235
29.765
11+570
4.648
34.352
12+325
20.591
18.409
3.782
35.218
12+615
33.24
5.76
12+765
17.256
21.744
12+780
8.125
30.875
35.875
3.125
13+280
4.451
34.549
13+310
12.768
26.232
13+340
22.861
16.139
13+375
30.937
8.063
13+490
16.35
22.65
13+490
15.037
23.963
0.579
38.421
5+670
8+220
26.124
12.876
12+350
8.375
30.625
12+375
34.124
4.876
12+395
12+600
6.87
32.13
12+850
35.407
3.593
12+890
31.748
7.252
12+930
31.935
7.065
12+970
31.298
7.702
13+095
37.642
1.358
12+975
13+140
33.734
5.266
13+180
29.394
9.606
13+230
10.497
28.503
13+500
32.632
6.368
13+500
37.533
1.467
13+540
32.832
6.168
13+540
13+575
8.32
30.68
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-5
LHS
Offset from
PCL (m)
Min. Shift
Reqd. (m)
29.356
9.644
13+645
26.048
12.952
13+690
5.421
33.579
13+725
18.243
20.757
13+750
28.111
10.889
32.182
6.818
24.74
14.26
17+345
34.513
4.487
17+830
36.475
2.525
18+705
38.22
0.78
18+720
23.935
15.065
17.633
21.367
19+780
27.869
11.131
20+580
8.682
30.318
20+595
8.092
30.908
24+700
14.174
24.826
33.167
5.833
26+575
22.074
16.926
30+210
12.721
26.279
PCL Chainage
Offset from
PCL (m)
RHS
Min. Shift
Reqd. (m)
13+575
13+590
31.461
7.539
13+590
34.831
4.169
13+630
35.78
3.22
13+650
9.302
29.698
13+660
36.401
2.599
13+680
37.823
1.177
13+705
3.681
35.319
13+725
38.012
0.988
13+880
31.084
7.916
13+910
22.738
16.262
14+000
14+025
18.611
20.389
14+140
14+275
6.569
32.431
14+575
7.86
31.14
17+345
13.963
25.037
18+720
12.178
26.822
18+760
21.263
17.737
18+760
19+720
25.732
13.268
19+720
24.277
14.723
25+570
9.188
29.812
25+570
26+550
30+220
10.483
19.375
28.517
19.625
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-6
LHS
RHS
PCL Chainage
Offset from
PCL (m)
Min. Shift
Reqd. (m)
Offset from
PCL (m)
Min. Shift
Reqd. (m)
30+280
18.315
20.685
30+280
23.409
15.591
30+565
3.728
35.272
31+180
12.908
26.092
31+180
13.422
25.578
31+190
16.007
22.993
27.243
11.757
33+985
5.703
33.297
34+030
30.878
8.122
35+690
30.563
8.437
43+365
1.796
37.204
43+400
19.072
19.928
45+820
29.589
9.411
45+855
38.023
0.977
46+870
35.995
3.005
46+870
26.535
12.465
47+520
24.921
14.079
47+595
35.446
3.554
47+620
28.175
10.825
47+690
17.667
21.333
47+725
14.96
24.04
47+740
15.666
23.334
47+760
15.79
23.21
47+795
15.955
23.045
31+210
34.124
4.876
33+620
33+640
9.249
29.751
33+940
24.655
14.345
35+700
26.332
12.668
36+685
3.853
35.147
36+720
4.306
34.694
39+775
19.057
19.943
43+295
35.293
3.707
46+870
18.296
20.704
47+110
33.659
5.341
47+130
25.471
13.529
47+695
37.334
1.666
47+705
18.54
20.46
47+720
25.319
13.681
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-7
The HT Pylons are very close at some locations and generally located on the edge of the right of
way. The chainages and offset distances from centre line are given in below table.
The Chainages and Offset distance form Centre Line
PCL
Chainage
Offset from
PCL (m)
Min. Shift
Reqd. (m)
Side of CL
17+350
17+350
Crossing
36.238
2.762
Right
19+200
Crossing
20+090
Crossing
22+775
Crossing
22+850
Crossing
23+120
Crossing
23+750
Crossing
24+360
Crossing
24+675
Crossing
30+250
Crossing
32+550
Crossing
32+980
Crossing
36+550
Crossing
Utility Description
HT line ( Vertical clearance
need to be raised)
Pylon
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
HT line ( Vertical clearance
need to be raised)
PCL
Chainage
LHS
RHS
Offset from
PCL (m)
Min. Shift
Reqd. (m)
18+730
25.243
13.757
18+770
27.261
11.739
20+580
Offset from
PCL (m)
Min. Shift
Reqd. (m)
16.562
22.438
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-8
20+595
30.849
8.151
OFC
The chainages and offset distances of OFC from centre line are given in below table.
Chainages and Offset distance of TPOFCform Centre Line
LHS
PCL
Chainage
Offset from
PCL (m)
RHS
Min. Shift
Reqd. (m)
47+790
Offset from
PCL (m)
12.23
Min. Shift
Reqd. (m)
26.77
RHS
Offset
from PCL
(m)
Min. Shift
Reqd. (m)
0+086
16.45
22.55
0+105
19.0842
19.9158
0+165
23.11
15.89
0+240
25.95
13.05
0+295
8.328
30.672
0+410
17.016
21.984
0+750
24.111
14.889
0+780
7.457
31.543
16.167
22.833
0+080
0+175
Offset
from PCL
(m)
Min. Shift
Reqd. (m)
23.103
15.897
27.52
11.48
0+365
10.402
28.598
0+415
23.389
15.611
1+50
30.318
8.682
1+70
1+85
4.3932
34.6068
1+830
13.508
25.492
1+870
31
1+950
30.634
8.366
1+955
18.761
20.239
2+025
16.9809
22.0191
2+160
7.29
31.71
2+580
17.37
21.63
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-9
LHS
PCL
Chainage
Offset
from PCL
(m)
RHS
Min. Shift
Reqd. (m)
Offset
from PCL
(m)
Min. Shift
Reqd. (m)
2+650
10.05
28.95
2+775
5.054
33.946
27.153
11.847
24.4041
14.5959
5.387
33.613
7.951
31.049
21.747
17.253
2+795
17.948
21.052
2+840
19.8171
19.1829
2+860
33.785
5.215
2+980
2+980
21.643
17.357
3+005
3+005
3+010
35.471
3.529
3+010
13.0998
25.9002
3+011
15.0998
23.9002
3+060
3+725
3.816
35.184
3+730
3+740
7.622
31.378
3+740
32.575
6.425
4+215
22.797
16.203
4+240
1.641
37.359
4+2620
26.315
12.685
4+265
12.46
26.54
4+310
3.278
35.722
4+335
10.126
28.874
4+340
26.924
12.076
13.1
25.9
24.834
14.166
4+360
6.539
32.461
4+420
17.793
21.207
4+420
4.646
34.354
4+425
12.811
26.189
4+425
4+450
21.0134
17.9866
4+480
16.632
22.368
4+480
2.263
36.737
4+500
35.2854
3.7146
4+500
17.674
21.326
4+530
4+540
28.095
10.905
4+545
14.354
24.646
4+545
11.229
27.771
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-10
LHS
PCL
Chainage
RHS
Offset
from PCL
(m)
Min. Shift
Reqd. (m)
33.305
5.695
14.76
24.24
6+035
14.068
24.932
6+040
4.078
34.922
6+070
8.782
30.218
6+080
8.636
30.364
6+185
32.817
6.183
6+235
10.85
28.15
6+240
18.605
20.395
13.735
25.265
6+535
17.515
21.485
6+595
19.518
19.482
6+630
21.402
17.598
6+630
26.053
12.947
6+640
21.396
17.604
4+635
Offset
from PCL
(m)
Min. Shift
Reqd. (m)
29.968
9.032
5+060
5+065
0.137
38.863
5+300
14.201
24.799
5+740
22.3
16.7
5+770
5+820
10.22
28.78
5+975
36.074
2.926
6+020
30.276
8.724
6+285
20.284
18.716
6+290
13.639
25.361
6+365
6+370
13.713
25.287
6+375
0.233
38.767
6+395
35.1423
3.8577
6+640
29.043
9.957
Offset from
PCL (m)
Min. Shift
Reqd. (m)
4+065
17.0404
21.9596
6+270
34.646
4.354
4+000
Side of CL
Utility Description
Crossing
LHS
Pylon
LHS
Pylon
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-11
Telephone poles
The chainages and offset distances from centre line are given in below table.
Chainages and Offset distance of TP form Centre Line
PCL
Chainage
LHS
RHS
2+300
Offset from
PCL (m)
34.787
Min. Shift
Reqd. (m)
4.213
2+780
21.803
17.197
2+800
26.6615
12.3385
Offset from
PCL (m)
Min. Shift
Reqd. (m)
OFCs
The chainages and offset distances of OFC from centre line are given in below table.
Chainages and Offset distance of TP form Centre Line
LHS
PCL
Chainage
RHS
Offset from
PCL (m)
Min.Shift
Reqd. (m)
27.2
11.8
0+085
0+175
0+180
8.1.3
0+325
6.308
32.692
0+350
10.434
28.566
1+40
35.453
3.547
Offset from
PCL (m)
Min. Shift
Reqd. (m)
13
26
13.19
25.81
Water Supply
Water Supply: There are a few water supply pipe lines present along the project road, mainly in
habituated areas. In non-urban areas the presences of water supply pipelines is very minimal or
almost does not exist. However there are a number other water supply sources like tube wells, hand
pumps and open wells present all along the project road within the road way width.
8.1.4
Fibre Optic Cable: Fibre Optic Cable is present all along the project road on either side. In the recent
4-laning civil works a number of ducts were provided to shift these cables. The ducts provided in the
initial 80 km of the road section are summarised in the following table.
Name of the Operator
DoT
M/s. Tata Tele Services Ltd.
Road Section
From Km
To Km
Vijayawada-Gundugolanu section
Eluru Bypass
Km 1042+280
1076+480 1061+080
No. of
Ducts laid
Capacity /
Specifications
1
2
OFC
HDPE Pipes
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
8-12
Road Section
VijayawadaGundugolanu
VijayawadaGundugolanu
From Km
To Km
1056+080
1037+080
No. of
Ducts laid
2
1076+480
1061+080
1056+080
1024+080
Capacity /
Specifications
HDPE Pipes
40mm dia HDPE
ducts
40mm dia HDPE
ducts
Besides these ducts the Fibre Optic Cable also present buried in the ground in the road way width.
8.2
IMPACT
An important part of the later detailed design will be to fully determine impacts and design, in
conjunction with utility companies, the diversions or strengthening or crossing (via pipe crossings to
be provided under the roadworks contract) locations and works. It is also very important to note that
in urban road projects service relocations are an important part of the preplanning, both on the
actual work [definition and phasing] and especially on the material procurement side, as in simplistic
terms one cannot relocate power lines, telephone lines and waterlines without at least a reasonable
amount of cable, pipes and fittings already in stock and immediately available.
Some installation of cross-ducting at standard intervals in urban and rural areas [for possible future
utility use] will also be necessary.
It should be noted that there may be additional land requirements identified in the final design as the
available ROW is insufficient to accommodate the moving of utility services and the tree planting
proposals.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
9-1
Chapter 9: Contents
CHAPTER 9: CONTENTS .................................................................................................................... 1
9.
9.1
HYDROLOGY................................................................................................................................ 2
9.2
9.3
9.3.1
9.3.2
9.4
9.4.1
9.4.2
9.4.3
9.4.4
9.5
SUMMARY OF HYDROLOGICAL STUDIES ........................................................................................ 6
9.5.1 River crossing - Hydrological Study ...................................................................................... 6
9.5.2
9.6
9.7
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
9-2
9.
9.1
HYDROLOGY
Hydrology is one of the important aspects for design of bridge structures across streams. The main
objective is to determine the anticipated floods and other parameters such as design discharge, flow
velocity, HFL, scour depth, etc. The bridge structure should be designed such that it can pass the
anticipated floods without endangering the structure. The hydrological and hydraulic studies have
been carried out in accordance with IRC Special Publication No. 13-2004 (Guidelines for the Design
of Small Bridges and Culverts) and IRC: 5-1998 (Standard Specifications & Code of Practice for
Road Bridges, Section I General Feature of Design).
A long list of structures [mostly for drainage, canal crossings, rivers etc.] is given in Chapter 13,
section 13.2. Additionally quite a lot of smaller size crossing pipe and slab culverts exist.
The project influence area covered by the project road receives low to medium rainfall. The terrain is
generally plain. The soil is predominantly black cotton and clayey soils.
There is one major river (Krishna, tributaries of River Krishna, each crossed by long structures) and
many streams and canals are crossed by the project road.
There are a number of canals running parallel to the road and at right angles to these streams. At
some locations the streams terminate in the canals which obstruct the free flow of flood waters. This
arrangement leads to heading up of water and flooding on the up stream side.
The length of the structures present across these major rivers is presented in the following table.
Table 9.1 Lengths of Major Bridges Crossing Rivers
Chainage
River Crossing
Km 15+970
Krishna
3144m
It was noticed [during our recent inspections] most if not all of the smaller pipe culverts are blocked,
and this obviously may cause local problems in the wet season. These culverts must be cleaned out
and kept clean as necessary..
The widening of the road [to 6 Lanes] plus the addition of service roads will require more [and larger
capacity] longitudinal drainage. This must be included by the Concession Company in their detail
designs.
There are canals and irrigation channels running in close proximity to NH5 at a number of locations.
The details of canals running parallel along the project road in Vijayawada-Gundanagolu section are
given in the following table.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
9-3
To km
Offset
from CL
Remark
From km
1034+080
1022+880
15-20 m
Irrigation
Channel
1033+380
RHS
Offset
To km
from
CL
1022+480
13-30 m
Remark
Major Canal
SURFACE DRAINAGE
Proper and adequate drainage of a road is very important for preventing damage to pavement
structure and for its efficient functioning. The main elements which contribute for drainage of the road
are:
i) Cross drainage
ii) Roadway including pavement surface drainage and
iii) Drainage at superelevated section.
There exist cross-drainage culverts and bridges on the existing road network. The adequacy of the
existing waterway has been examined in detail in respect of the existing road sections. However it
may be stated here that for the culverts having, inter-alia, inadequate waterway width it is proposed
that the Concession Company must examine in detail the all problems and propose new ones with
adequate waterway, vertical clearance and width suiting to the 6-lane facility.
The road surface drainage is achieved by providing appropriate cross fall/camber leading to
longitudinal drains with proper outfall. Earthen longitudinal drains at isolated locations are present on
both sides at the end of ROW and have adequate section to cater to the requirements for efficient
drainage and suitably connected to proper outfall in the streams. However in the widening these
drains have to be re-built with proper outfalls. The lined drains are provided in the built-up areas
having a width varying from 1.2 to 2m and a depth of 1m covered with concrete blocks. Generally all
concrete drains in the project road are in good condition. Further widening of road will required the
shifting of these concrete drains to the extreme edge of the new carriage way.
9.3
There is one major (Krishna) river crossing and 10 stream crossings on this bypass alignment.
Accordingly the data needed for both the structures was collected from field observations, surveys
and statistics (from concerned govt. dept), topo-sheets etc. The alignment is crossing the river
Krishna at approximately 5.8Km upstream of the Prakasam barrage. As per the norms of NHAI past
50 years maximum flood data was collected and it is observed that the flood that was observed in
October, 2009 is the maximum in the past 50 years. So, that flood was considered as the design
flood for fixing the MFL for the present river crossing. The catchment area of the streams is
calculated from the Topo-sheets available on a scale of 1:50000 and 1:250000. Basing on the
catchment area obtained, using various methods the maximum discharge is calculated.
9.3.1
As per IRC: 5 1998 (Standard Specifications and Code of Practice for Road Bridges, Section 1,
General Features of Design) the bridge is to be designed for a period of not less than 50 years. A
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
9-4
flood of this specified return period should pass easily through the structure, while an extraordinary
and rare flood may pass without doing excessive damage to the structure or the road.
The 50-year, 24-hour rainfall for the zone under consideration is 240mm. (Ref: Flood Estimation
Report for Eastern Coast Region (upper, lower & south), sub-zone 4 (a, b & c)), published by the
CWC). Catchment areas are marked on Topographic maps from Survey of India of 1:50,000 and
1:2, 50,000 scales.
9.3.2
For the calculation of discharge of the river and streams by Area-Velocity method, topographical
survey including leveling surveys were carried out across and along the watercourses to determine
the cross-section and the slope. A number of cross-sections have been taken at regular intervals on
both upstream and downstream side of the structure, including one at the proposed location of the
structure in accordance with IRC specifications.
The following assumptions are made during peak discharge calculation:
For locations where water spreads over the banks, the cross-sections shall be extended up
to the HFL, in order to calculate the effective cross-section of flow.
The longitudinal section, to determine the bed slope, shall be taken at an approximate
regular interval following the channel course extending on both upstream and downstream
sides of the structure. Caution shall be exercised by following the curved flow line for
longitudinal gradient, rather than a straight line.
9.4
9.4.1
Basing on the past records of the floods observed at barrage, the design flood (maximum flood) will
be decided and basing on the MFL observed at the barrage, approximate water level at the required
location will be estimated. If the location of the river crossing is within the impounded water zone the
same level observed at the barrage with some velocity head due to the inflow will be taken as the
MFL. If it is out of the impounded water zone, the flow depth for that particular discharge will be taken
as the MFL at the required location. Thereafter afflux will be calculated and the final MFL will be
fixed.
9.4.2
The peak discharge and the HFL shall be calculated by following methods
2/3
1/2
x (S) ]
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
9-5
Where
Q = the discharge in cumecs;
A = Area of the cross section in sq. m.;
V = Velocity in m/sec;
R = Hydraulic mean depth in m. = A / P;
P = Wetted perimeter of the stream in m.;
S = Bed slope of the stream; and
n = Rugosity Co-efficient.
Empirical Methods
Dickens Formula which is as under as per IRC SP-13.
Q=CM
3/4
Where
Q = Peak run-off in m/sec
M = Catchment area in sq.km.
C = Coefficient of run-off, depends upon annual rainfall
The catchment area M can be determined from the toposheets or contours generated, Coefficient of
run-off C can be determined from IRC SP-13 depending upon the intensity of rainfall. This formula
gives a simplified approach and results are approximate. Comparison should also be made with
alternative methods for important structures.
Ryve's formula which is as under as per IRC SP-13.
Q = CM
2/3
Where
Q = Peak run-off in m/sec
M = Catchment area in sq.km.
C = Coefficient of run-off, depends upon annual rainfall
The catchment area M can be determined from the topo-sheets or contours generated, Coefficient of
run-off C can be determined from IRC SP-13 depending upon the intensity of rainfall. This formula
gives a simplified approach and results are approximate. Comparison should also be made with
alternative methods for important structures.
9.4.3
In hydraulic analysis, the Design HFL shall be calculated corresponding to the Design Discharge by
Mannings Equation at the bridge site, as described above.
9.4.4
Afflux Calculation
When the waterway area of the opening of a bridge is less than the unobstructed natural waterway
area of the stream, i.e. when bridge contracts the stream, afflux occurs. The afflux will be calculated
using Molesworth formula as given below: -
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Reports Code
Page
Rev.
9-6
V2
h
( A / a)2 1
17.88 0.015
Where,
h = afflux in meters
V = average velocity of water in the river prior to construction in m/sec
A = Unobstructed sectional area of the river at proposed site in sq.m.
a = Constricted area of the river at the bridge in sq.m.
9.5
The hydrological studies mainly comprise of two components namely the river crossing calculations
and the stream crossing calculations.
9.5.1
As mentioned earlier, the maximum flood is observed on Oct 2009. But as per the records there is
another similar flood that was observed in 1903 for which higher MFL (approx. 2 ft more than 2009
flood level) was recorded. Since the difference is not much we have considered 1903 flood levels to
be on the safer side. Basing on the calculations it is observed that the river crossing is coming into
the impounded water zone. Calculations are given below.
Maximum Flood Level Calculations
C/S Area for the design flow
12125.22845
sq.m
2627.65757
933.023
0.035
Hydraulic Radius
4.614462928
2.592586299
m/s
31435.70114
Cum/sec
1110142
Cu.ft /sec
1110104
Cu.ft /sec
19.590
1.057
MFL due to the flow alone (not in the impounded water zone)
20.647
0.343
0.350
21.500
21.500
21.850
Basing on the above calculations, the MFL at the river crossing is fixed. Basing on this the structure
will be designed.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
9.5.2
Reports Code
Page
Rev.
9-7
In present case Discharge is calculated by Area Velocity Method and Empirical Methods also.
Maximum of the discharge obtained by these methods is taken as Design Discharge. HFL is fixed to
match this Design Discharge with given cross section of the stream. Average depth of stream from
given cross section is considered and Vent-way is provided to cater this Design Discharge.
The calculations are given below in table for a brief glance.
SUMMARY OF BRIDGES
S.No.
Design
Chainage
Catchment
Area (km2)
Design
Discharge
(cumecs)
Affluxed
HFL (m)
Average
Velocity,
(m/sec)
Design
Ventway
(m)
Design
Depth
(m)
Vijayawada Bypass
1
3+360
0.000
29.624
27.500
1.159
30.000
0.919
8+210
99.015
345.278
21.381
2.524
36.000
3.886
21+240
22.650
194.347
21.900
2.270
20.000
4.376
23+350
14.575
82.054
18.961
2.203
25.000
1.553
30+565
2.163
19.619
20.660
2.013
10.000
1.036
33+250
2.073
19.006
19.268
1.562
15.000
0.924
34+250
0.000
19.307
21.000
1.648
10.000
1.367
36+500
0.659
8.046
21.887
1.017
12.000
0.800
40+900
3.230
26.503
22.195
2.096
10.000
1.539
10
43+250
40.323
2.502
50.000
1.628
11
5+391
10.000
1.883
32.000
2.522
196.117
21.915
Hanuman Junction Bypass
78.728
100.625
NOTE:
Catchment Area is considered 0 sq km since topo sheets received from GSI contains no stream at
that particular chainage.
9.6
SURFACE DRAINAGE
Proper and adequate drainage of a road is very important for preventing damage to pavement
structure and for its efficient functioning. The main elements which contribute for drainage of the road
are:
i)
ii)
iii)
Cross drainage
Roadway including pavement surface drainage and
Drainage at super elevated section.
The road surface drainage is achieved by providing appropriate cross fall/camber leading to
longitudinal drains with proper outfall. Earthen longitudinal drains at isolated locations are present on
both sides at the end of ROW and have adequate section to cater to the requirements for efficient
drainage and suitably connected to proper outfall in the streams.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
9.7
Reports Code
Page
Rev.
9-8
High embankment drainage particularly on high embankment approaches to bridges and road over
bridges have problems of erosion of embankment, side slopes and surface drainage in view of steep
longitudinal gradients on the approaches and roadway cross fall towards the embankment slopes.
This problem is proposed to be tackled by providing kerb and channel longitudinal drains at the end
of the paved shoulder and chutes at suitable intervals along the embankment. Embankment slopes
are proposed to be pitched as necessary to prevent rain cuts and erosion.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Design ESA
in Million
LCV
2-Axle
Truck
3-Axle
Truck
MAV
VDF values
0.62
0.62
2.43
6.46
18.13
2010
1,167
568
1,667
2,521
2011
1,225
596
1,750
2012
1,286
626
2013
1,350
2014
Total
Year Wise
377
6300
3.87
2,647
396
6614
4.06
1,838
2,779
416
6945
4.26
657
1,930
2,918
437
7292
2.28
1,418
690
2,027
3,064
459
7658
1.94
2015
1,489
725
2,128
3,217
482
8041
3.95
2016
1,563
761
2,234
3,378
506
8442
4.15
2017
1,641
799
2,346
3,547
531
8864
4.35
2018
1,723
839
2,463
3,724
558
9307
4.57
2019
1,809
881
2,586
3,910
586
9772
4.80
2020
1899
925
2715
4106
615
10260
5.04
2021
1,994
971
2,851
4,311
646
10773
5.29
2022
2,094
1,020
2,994
4,527
678
11313
5.56
2,023
2199
1071
3144
4753
712
11879
5.83
2024
2,309
1,125
3,301
4,991
748
12474.00
6.13
2025
2,424
1,181
3,466
5,241
785
13097
6.43
2026
2,545
1,240
3,639
5,503
824
13751
6.75
2027
2,672
1,302
3,821
5,778
865
14438
7.09
2028
2,806
1,367
4,012
6,067
908
15160
7.45
2029
2,946
1,435
4,213
6,370
953
15917
7.82
2030
3,093
1,507
4,424
6,689
1,001
16714
8.21
2031
3,248
1,582
4,645
7,023
1,051
17549
8.62
2032
3,410
1,661
4,877
7,374
1,104
18426
9.05
2,033
3581
1744
5121
7743
1159
19348
9.50
ms of MSA
ndugilanu)
New
Pavement
Remarks
(2015 -2034)
Awarding &FC
4.06
Construction
period of 3yrs
8.32
10.60
12.54
1.94
16.49
5.89
20.64
10.0
24.99
14.4
29.56
19.0
34.36
23.8
39.40
28.8
44.70
34.1
50.25
39.7
56.09
45.5
62.21
51.61
68.65
58.0
75.40
64.8
82.49
71.9
89.94
79.33
97.75
87.15
105.96
95.36
114.58
103.98
123.63
113.03
133.13
122.53
6-lane facility