Sunteți pe pagina 1din 38

United States Department of the Interior

National Park Service

Class A Construction Cost Estimate

BASIS OF ESTIMATE
PROJECT INFORMATION
Project:

Oso Comida Trailhead Improvements:

Park:
Park Apha:
PMIS:
Estimate Date:
Prepared By:
Company:
Address:
City, State Zip:
Phone:

Bear Arbor NRA


BEAR
XXXXXX

1/12/2011
YtB
NPS Bear Arbor NRA
123 Bruin Meadows Rd.
Grizzley Hollow, CA 96023
(555) 123-4567

BACKGROUND SUPPORTING MATERIAL (Scope of Work):


Existing parking lot will be upgraded, re-configured within existing disturbed area, for 40 car spaces, 5 ADA Spaces, 2 van
spaces, 10 RV pull throughspaces, and paved. Existing pit toilets will be removed and replaced with a wet comfort station
including septic system with in tank bio reactor treatment, and liquid disposal field; NEW WATER WELL NOW REQUIRED.
The existing picnic area will be rehabilitated and modified to meet ABBAS accessibility standards. Trail connections will be
formalized and upgraded; portions will be made accessible to facilitate access to Bruin Meadows overlook. Existing
uncontrolled social trails will be restored to natural and a channelizing seat-resistant wood rail fence added to direct
movement from parking area to trail connection. The septic system incorporates a new technology in-tank sanitary treatment
process that will be pre ordered and supplied by NPS as GFP. Puchase cost of tank and treatment materials is included in
direct cost estimate.

SOURCE OF COST DATA:


Comfort Station unit costs are based a combination of sources that include actual material take-offs and vendor quotes,
review of actual final costs and project labor records for a similar facility constructed in 2009 at neighboring Ursa Hollow park.
Parking lot costs are based on actual contract prices from Spring 2010 FHWA road project on Bruin Meadows Road adjacent
to the site adjusted to remove previous O&P. Purchase price for the prefabricated Septic-King is an actual vendor quote
FOB park warehouse. Supplimental cost were obtained from RS Means, Facilites Cost Data (FCCD), 25th Annusal Edition.
WHENEVER RSMEANS BARE UNIT COSTS WERE USED FROM THE FCCD DATA, 10% WAS ADDED TO MATERIALS &
EQUIPMENT AND 60% TO LABOR TO ACCOUNT FOR INSTALLER (SUB) O&P

ESTIMATE ASSUMPTIONS:
Estimate assumes that all improvements will be constructed as a singe project during one construction season. East half of
existing dirt parking area and trailhead will remain in operation until new paved lot and walk connections are completed. 2nd
half of existing lot will be available for contractor laydown/equipment area, but contractor's labor force must park at
maintenance yard 5 miles away and be shuttled into site. Shuttle costs and additional portable toilet cost impacts are
included in Government Special Conditions. Septic-King system will be preordered by the Park to avoid long lead time from
impacting installation schedule.

MAJOR CHANGES FROM PREVIOUS ESTIMATE:


Parking lot configuration changed slightly to accommodate RV pull through spaces. Existing dirt parking area will be gravel
surfaced for use as overflow parking and equestrian staging area. Photo-voltaic system has been deleted for budgetary
purposes, viewshed impacts, concerns over viewshed impacts and negative results of net life-cycle payback analysis. Water
is not avialable in road; well added to service wet comfort station - assumes 1200 VLF depth.

BEAR Trailhead - 100% Draft Class A Cost Estimate


Basis of Estimate

Page 1 of 38

Print Date: 1/24/2011

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

BASIS OF ESTIMATE
PROJECT INFORMATION
Project:

Oso Comida Trailhead Improvements:

Park:
Park Apha:
PMIS:
Estimate Date:

Bear Arbor NRA


BEAR
XXXXXX

1/12/2011

DESCRIPTION OF MARK-UP & ADD-ONS:


Design Contingency:

2.00%

This is the 100% Draft CD submittlal, but a few design details


relating to septic and electric systems are stil changing.

Standard. General Conditions:

0.00%

Precentage mark-up not used. Please refer to itemized Genral


conditions estimate for each CLI

Government General Conditions:

3.00%

Most costs are covered in Standard GC. 3% additional as cost


offset to accommodate,creww shuttle, dignitary events and multilayer oversight disruptions.

Contractor Overhead:

8.50%

Anticipate using a small contractor with limitted fixed overhead


costs and austerity under current market conditons

Contractor Profit:

10.00%

Current construction market conditions expected to improve


modestly by 2013 project date.

Contracting Method Adjustment:

15.00%

Preliminary indications are that negotiated sole-source SBA


Section 8a or SDV procurement will be utilized.

Annual Inflation Escalation Factor:

3.60%

Time Until Project Midpoint (Months)

32

Projected annual inflation rate.


January 2011 estimate data date to mid-point of construction,
August 2013

OTHER COMMENTS:
Since new comfort station will have deepened grade-beam/strip footing on piers w/PT slab on grade construction,
insufficient spoils will be generated to backfill existing pits. After spoils from new septic system are exhausted, we
assumed 50% of total backfill quantity will be imported from NPS in park-stockpile. The balance of the on-site
grading appears to balance, pending verification of existing topo.

BEAR Trailhead - 100% Draft Class A Cost Estimate


Basis of Estimate

Page 2 of 38

Print Date: 1/24/2011

When usin

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

PROJECT COST SUMMARY


Project: Oso Comida Trailhead Improvements:
Park: Bear Arbor NRA
Park Alpha: BEAR
PMIS Number: XXXXXX

Bid Item No.

Bid Item Description

Total Material
Cost

Total
Equipment
Cost

Total Labor
Cost

Total Direct
Construction
Costs

Design
Contingency

General
Conditions

2.00%

Bid Item:

Replace Pit Toilets with New Comfort Station


A10
Foundations
A20
Basement Construction
B10
Superstructure
B20
Exterior Enclosure
B30
Roofing
C10
Interior Construction
C30
Interior Finishes
D20
Plumbing Systems
D30
HVAC
D50
Electrical
F20
Selective Building Demolition
G10
Site Preparation
G20
Site Improvements
G30
Site Mechanical
G40
Site Electrical
XX

Total - Bid Item

Bid Item:

G10
G20
G30
XX
Total - Bid Item

Bid Item:

Total - Bid Item

Standard General Conditions

Replace Pit Toilets with New Comfort Station


Construct New Parking Lot & Site Utilities

Site Preparation
Site Improvements
Site Mechanical
Standard General Conditions

Construct New Parking Lot & Site Utilities


Picnic Area & Trailhead Improvements

G10

Site Preparation

G20

Site Improvements

G30

Site Mechanical

XX

Standard General Conditions

Picnic Area & Trailhead Improvements

Total Bid Items 1-3

BEAR Trailhead - 100% Draft Class A Cost Estimate


Project Cost Summary

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

30,028
15,622
35,992
18,471
25,573
4,476
26,655
1,269
8,753
463
2,188
8,900
86,213
5,000
31,900
301,503

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

33,082
13,198
29,477
8,706
9,308
13,424
16,121
1,170
9,366
1,990
4,362
7,300
32,582
101,200
281,286

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

7,293
460
3,862
6,952
44,542
18,610
81,719

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

70,403
29,280
65,469
27,177
34,881
17,900
42,776
2,439
18,119
6,315
13,502
16,200
163,337
5,000
151,710
664,508

$
$
$
$
$
$

2,500
143,581
12,153
12,925
171,159

$
$
$
$
$
$

11,711
36,335
14,232
8,350
70,628

$
$
$
$
$
$

19,776
43,670
4,241
6,500
74,187

$
$
$
$
$
$

33,987
223,586
30,626
27,775
315,974

12,370

6,319

3.00%

18,926

9,669

Estimate By:
Date:

YtB
01/12/11

Reviewed By:
Date:

BBB
01/17/11

General
Contractor
Overhead

General
Contractor
Profit

Contracting
Method
Adjustment

8.50%

10.00%

15.00%

Inflation
Escalation

Bid Item Total

Month
s
3.60%
32
APR

TOTAL VALUE OF GOVERNMENT FURNISHED PROPERTY (if any):

46,000.00

92,813

1,031,234

TOTAL VALUE OF GOVERNMENT FURNISHED PROPERTY (if any):

55,233

64,980

122,403

44,742

TOTAL VALUE OF GOVERNMENT FURNISHED PROPERTY (if any):

28,217

33,196

59,006

497,123
-

$
$
$
$
$
$

59,448
2,125
5,775
67,348

$
$
$
$
$
$

11,860
25,960
2,275
7,550
47,645

$
$
$
$
$
$

4,845
12,270
330
2,500
19,945

$
$
$
$
$
$

16,705
97,678
4,730
15,825
134,938

2,699

4,129

12,050

14,177

25,199

19,107

212,299

540,010

399,559

175,851

1,115,420

21,388

32,724

95,500

112,353

206,608

156,662

1,740,656

Page 3 of 38

Print Date: 1/24/2011, 2:13 PM

United States Department of the Interior


National Park Service
Class A Construction Cost Estimate

BID ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS Number:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX
Bid Item Number
BID ITEM 1

Item
No.

WBS

1
2
3
4
5
6
8
9
10
11
12
13
14
15
16
17
18
19

A10
A20
B10
B20
B30
C10
C30
D20
D30
D50
F20
G10
G20
G30
G40
XX
XX
XX

Estimate By:
Date:
Reviewed By:
Date:
Asset / Project Element / Description
Construct Wet Comfort Station

Description
Foundations
Basement Construction - INC. IN FOUNDATION
Superstructure
Exterior Enclosure
Roofing
Interior Construction
Interior Finishes
Plumbing Systems
HVAC
Electrical
Selective Building Demolition
Site Preparation
Site Improvements
Site Mechanical Utilities
Site Electrical Utilities
General Conditions

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Subtotal Direct Construction Costs $

Material
Cost/Unit
30.03
15.62
35.99
18.47
25.57
4.48
26.65
1.27
8.75
0.46
2.19
8.90
86.21
5.00
31.90
301.50

Total Material
Cost
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

Total Value of Government Furnished Property (GFP) Inc. in Direct Cost .


Direct Cost Subtotal without GFP . $
Design Contingency
2.00%
Total Direct Construction Costs
Standard General Conditions
Government General Conditions

0.00%
3.00%

30,028
15,622
35,992
18,471
25,573
4,476
26,655
1,269
8,753
463
2,188
8,900
86,213
5,000
31,900
301,501

Size/Count
1000

Units
SF

33.08
13.20
29.48
8.71
9.31
13.42
16.12
1.17
9.37
1.99
4.36
7.30
32.58
101.20
281.28

$46,000.00
255,501

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

33,082
13,198
29,477
8,706
9,308
13,424
16,121
1,170
9,365
1,990
4,362
7,300
32,582
101,200
281,284

$
$

281,284

Applied to Total Direct Construction Cost less GFP


Applied to Total Direct Construction Cost less GFP

Subtotal NET Construction Cost


Overhead
Profit

8.50%
10.00%

Estimated NET Construction Cost


Contracting Method Adjustment
Inflation Escalation

15.00%
32

Equipment
Cost/Unit

Labor Cost/Unit Total Labor Cost


$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

YtB
01/12/11
BBB
01/17/11

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

7.29
0.46
3.86
6.95
44.54
18.61
81.72

Total Equipment
Cost

Direct
Cost/Unit

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

7,293
460
3,863
6,952
44,543
18,610
81,720

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

70.40
29.28
65.47
27.18
34.88
17.90
42.78
2.44
18.12
6.32
13.50
16.20
163.34
5.00
151.71
664.50

$
$

81,720

46,000

Total Direct
Costs
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

70,402
29,279
65,469
27,176
34,881
17,900
42,776
2,438
18,118
6,315
13,502
16,200
163,337
5,000
151,710
$664,505

NET Cost/Unit

Total NET Costs

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

109.26
45.44
101.60
42.17
54.13
27.78
66.38
3.78
28.12
9.80
20.95
25.14
253.48
7.76
235.44
1,031.23

109,256
45,438
101,600
42,174
54,131
27,778
66,383
3,784
28,117
9,800
20,953
25,140
253,479
7,759
235,435
$1,031,229

$46,000 In most cases GFP is normally zero see footnote$618,505


$12,370 Notes & Comments:
$676,875 Building only direct cost = $308.44/sf
$0 Building total NET cost = $474.28/sf
$18,926 GFP Septic King Treatment System
$695,801 Pre-Purchased by Government =
$55,233 $46,000
$64,980
$816,014
$122,402

Months

Annual Rate =

Total Estimated NET Cost of Construction

3.60%

$92,812
$1,031,229

GFP costs only apply when the Government pre-purchases items, or provides other materials out of Government inventory, to be installed by contractor. Adjustments and Markup on GFP only include Inflation Escalation; No other
adjustment factors or O&P markup have been applied.

BEAR Trailhead - 100% Draft Class A Cost Estimate


Bid Item 1 Summary

Page 4 of 38

Print Date: 1/24/2011, 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: A10 Foundations

Total Cost:
MATERIAL

Uniformat II WBS
Code
A1010

YtB
01/12/11
BBB
01/17/11

Description

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$70,402

TOTALS
Total
Cost/Unit

Total Cost

STANDARD FOUNDATIONS

31.23.15
03.15.05
03.11.13
03.21.10
03.30.53
03.30.53
03.11.13
03.35.29
07.27.13
31.23.23

SUBTOTAL

Excavate Grade Beam 140'x48", Column


footings, overdig 25%, spread spoil onsite
Furnish & Install 6" crushable void form
Fabricate & Erect Outside forms
Furnish & Install Steel Reinfocement
Furnish & Pour Concrete 42"x12"
Concrete Waste Factor 10%
Strip, & clean forms
Dry Finish top 12"
Furnish & Install 2" EPS insulation Board
Backfill w/ Hand compact - select import

40
140
560
3200
18
1
560
140
560
16

CY
LF
SF
LB
CY
Allow
SF
SF
SF
CY

$
$
$
$
$
$
$
$
$
$

2.25
0.66
95.50
171.90
1.03
32.75

STANDARD FOUNDATIONS

1000

SF

5.42

$
$
$
$
$
$
$
$
$
$

57.78
0.36
4.14
3.93
25.66
0.52
3.79
0.58
163.70

$5,419 $

21.48

$0
$315
$0
$2,112
$1,719
$172
$0
$0
$577
$524

MATERIAL
Uniformat II WBS
Code
A1020
03.63.26
31.23.23

SUBTOTAL

Description

SPECIAL FOUNDATIONS
Drilled Caisons - 10' OC x 25' -Subcontract
Pick up & spread spoil onsite

SPECIAL FOUNDATIONS

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1 - A10 - Foundations

Quantity

Unit

Material
Cost/Unit

$
$
$
$
$
$
$
$
$
$

13.85
48.50

$554
$0
$0
$0
$0
$0
$0
$0
$0
$776

$
$
$
$
$
$
$
$
$
$

71.63
2.61
4.14
4.59
121.16
171.90
0.52
3.79
1.61
244.95

$2,865
$365
$2,318
$14,688
$2,181
$172
$291
$531
$902
$3,919

$21,484 $

1.33

$1,330 $

28.23

$28,232

$2,311
$50
$2,318
$12,576
$462
$0
$291
$531
$325
$2,619

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

16
50

EA
CY

$
$
$

1,120.00
-

$17,920 $
$0 $
$0 $

140.92
19.30
-

$2,255 $
$965 $
$0 $

335.00
6.65
-

$5,360 $
$333 $
$0 $

1,595.92
25.95
-

$25,535
$1,298
$0

1000

SF

17.92

$17,920 $

3.22

$3,220 $

5.69

$5,693 $

26.83

$26,832

5 of 38

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: A10 Foundations

Total Cost:
MATERIAL

Uniformat II WBS
Code
A1030
03.11.13
31.23.23
31.23.23
07.27.13
03.23.05
03.23.05
03.30.53
03.35.22
03.39.23
03.30.53

SUBTOTAL

YtB
01/12/11
BBB
01/17/11

Description

SLAB ON GRADE - 6" Post tentioned


Edge form Included in std. foundation
F & I Crushed Aggregate Base - 6"
Fine Grade & Install 4" leveling sand
F & I Rigid EPS and Vapor Barrier
Furnish & Install Pre-stressing Tendon
F & I Supplimental Reinforcing Mesh
Furnish & Pour concrete - Quantity includes 6"
topping on grade beam
Power trowel finish
Misc. ST&S (cure, etc.)
Concrete Waste Factor 10%

SLAB ON GRADE - 6" Post tentioned

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

0
50
1000
1000
1000
1000

Unit
Tons
SF
SF
SF
SF

$
$
$
$
$
$

22.75
0.55
1.09
0.78
0.30

$0
$1,138
$550
$1,090
$780
$300

$
$
$
$
$
$

36.82
1.40
0.58
0.47
0.36

$0
$1,841
$1,400
$580
$470
$360

$
$
$
$
$
$

26
1000
1
1

CY
SF
Allow
LS

$
$
$
$
$

95.50
100.00
248.30
-

$2,483
$0
$100
$248
$0

$
$
$
$
$

118.56
0.58
65.00
-

$3,083
$580
$65
$0
$0

$
$
$
$
$

6.55
0.10
-

1000

SF

6.69

$6,689 $

8.38

$8,379 $

0.27

$70,402

TOTALS
Total
Cost/Unit

Total Cost

$0
$0
$0
$0
$0
$0

$
$
$
$
$
$

59.57
1.95
1.67
1.25
0.66

$0
$2,979
$1,950
$1,670
$1,250
$660

$170
$100
$0
$0
$0

$
$
$
$
$

220.61
0.68
165.00
248.30
-

$5,736
$680
$165
$248
$0

$270 $

15.34

$15,338

Summary Item: A10 Foundations


MATERIAL
Uniformat II WBS
Code

A10

Description

Foundations

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1 - A10 - Foundations

Quantity

Unit

1000

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

30.03

6 of 38

Labor
Cost/Unit

$30,028 $

33.08

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$33,082 $

7.29

TOTALS
Total
Cost/Unit

$7,293 $

70.40

Total Cost

$70,402

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: B10 Superstructure

Total Cost:
MATERIAL

Uniformat II WBS
Code
B1010

Description

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$29,279

TOTALS
Total
Cost/Unit

Total Cost

FLOOR CONSTRUCTION

SEE FOUNDATION - SLAB ON GRADE

SUBTOTAL

FLOOR CONSTRUCTION

1000

Unit

$0 $

$0 $

$0 $

$0

SF

$0 $

$0 $

$0 $

$0

MATERIAL
Uniformat II WBS
Code
B1020
06.17.53
06.16.36
06.13.23
05.12.23
06.05.23
04.43.10
06.17.53

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

ROOF CONSTRUCTION
Furnish & Install Wood Trusses 25' span
F&I Plywood sheating - 5/8 CDX
6x12 Rough Sawn Beams
4x4 x 1/4 HSS steel posts w/ Beam Bracket
Hurricane Clips
Stone Veneer on End Columns 24"x24"x8'
Temp Bracing & Blocking Allowance

36
1960
300
4
72
320
1

EA
SF
BF
EA
EA
SF
LS

$
$
$
$
$
$
$
$

151.00
0.72
1.88
194.00
5.20
20.50
500.00
-

$5,436
$1,411
$564
$776
$374
$6,560
$500
$0

$
$
$
$
$
$
$
$

75.11
0.77
1.11
195.00
2.34
23.76
100.00
-

$2,704
$1,509
$333
$780
$168
$7,603
$100
$0

$
$
$
$
$
$
$
$

10.00
25.00
-

$360
$0
$0
$100
$0
$0
$0
$0

$
$
$
$
$
$
$
$

236.11
1.49
2.99
414.00
7.54
44.26
600.00
-

$8,500
$2,920
$897
$1,656
$543
$14,163
$600
$0

ROOF CONSTRUCTION

1000

SF

15.62

$15,622 $

13.20

$13,198 $

0.46

$460 $

29.28

$29,279

Summary Item: B10 Superstructure


MATERIAL
Uniformat II WBS
Code

B10

Description

Superstructure

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-B10 Superstructure

Quantity

Unit

1000

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

15.62

7 of 38

Labor
Cost/Unit

$15,622 $

13.20

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$13,198 $

0.46

TOTALS
Total
Cost/Unit

$460 $

29.28

Total Cost

$29,279

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: B20 Exterior Enclosure

Total Cost:
MATERIAL

Uniformat II WBS
Code
B2010
06.11.10
06.16.36
06.11.01
07.21.16
07.46.23
04.43.10
04.72.10
06.11.10
06.16.36
07.25.10

SUBTOTAL

Description

EXTERIOR WALLS
2"x6"x8' studwall , 16" OC
Exterior Sheating 1/2" CDX Plywood
Headers, Blocking, Bracing, & Bridging
R-21 Batt Insullation
Vertical B&B Rough Sawn Cedar Siding
Stone Wainscot
Precast Wall Coping
2"x4"x4' Privacy Panel framing
2"x4"x4' Privacy Panel Sheating 1/2" CDX
Plywood - 2 sides
Building Wrap

EXTERIOR WALLS

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

140
1120
1
1120
450
560
130
40

LF
SF
LS
SF
SF
SF
LF
LF

$
$
$
$
$
$
$
$

3.72
0.78
500.00
1.24
5.62
20.50
13.20
1.70

320
1120

SF
SF

$
$

1000

SF

Labor
Cost/Unit
$
$
$
$
$
$
$
$

7.96
0.88
500.00
0.41
1.57
23.76
10.24
7.96

0.78
0.32

$250 $
$358 $

19.68

$19,684 $

$521
$874
$500
$1,389
$2,529
$11,480
$1,716
$68

MATERIAL
Uniformat II WBS
Code
B2020

Description

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

Total Labor
Cost

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

11.68
1.66
1,000.00
1.65
7.19
44.26
23.44
9.66

$1,635
$1,859
$1,000
$1,848
$3,236
$24,786
$3,047
$386

0.88
0.18

$282 $
$202 $

$0 $
$0 $

1.66
0.50

$531
$560

19.20

$19,204 $

$0 $

38.89

$38,888

$1,114
$986
$500
$459
$707
$13,306
$1,331
$318

LABOR

Total Material
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$65,469

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

EXTERIOR WINDOWS

08.52.10
06.22.13

SUBTOTAL

Wood Awning Windows, 34"x22", Dbl. pane,


extra width sill, pre-finished custom color
Interior and Exterior trim packages

EXTERIOR WINDOWS

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-B20 Exterior Enclosure

16
16

EA
ea

$
$

416.00
92.00

$6,656 $
$1,472 $

220.48
162.24

$3,528 $
$2,596 $

$0 $
$0 $

636.48
254.24

$10,184
$4,068

1000

SF

8.13

$8,128 $

6.12

$6,124 $

$0 $

14.25

$14,252

8 of 38

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: B20 Exterior Enclosure

Total Cost:
MATERIAL

Uniformat II WBS
Code
B2030
08.12.13
08.13.13.
08.71.20
08.71.20

SUBTOTAL

Description

EXTERIOR DOORS
Hollow Metal Door Frames,14 Ga., 8-3/4 deep,
7-0x3-6
Hollow metal Door, Insulated 1-3/4 thick full
panel, 18 ga., 7-0x3-6
Door Closer Heavy duty top jamb mount
Door hardware, deadbolt, lock set, etc.

EXTERIOR DOORS

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

EA

356.00

$1,780 $

117.10

5
5
5

EA
EA
EA

$
$
$
$
$
$
$

670.00
274.00
336.00
-

$3,350
$1,370
$1,680
$0
$0
$0
$0

$
$
$
$
$
$
$

88.82
549.12
74.88
-

1000

SF

8.18

$8,180 $

4.15

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$65,469

TOTALS
Total
Cost/Unit

Total Cost

$586 $

$0 $

473.10

$2,366

$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$

758.82
823.12
410.88
-

$3,794
$4,116
$2,054
$0
$0
$0
$0

$4,150 $

$0 $

12.33

$12,330

$444
$2,746
$374
$0
$0
$0
$0

Summary Item: B20 Exterior Enclosure


MATERIAL
Uniformat II WBS
Code

B20

Description

Exterior Enclosure

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-B20 Exterior Enclosure

Quantity

Unit

1000

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

35.99

9 of 38

Labor
Cost/Unit

$35,992 $

29.48

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$29,477 $

TOTALS
Total
Cost/Unit

$0 $

65.47

Total Cost

$65,469

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: B30 Roofing

Total Cost:
MATERIAL

Uniformat II WBS
Code
B3010

YtB
01/12/11
BBB
01/17/11

Description

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$27,176

TOTALS
Total
Cost/Unit

Total Cost

ROOF COVERINGS

07.41.13
07.41.13
07.65.23
07.65.23
07.71.23
07.71.23
07.71.23
23.34.23

SUBTOTAL

22 Ga. Raised seam steel roof - standard finish


Roof Ridge Cap
Ice And Water Shield - 3' at all edges
Flashing allowance
5" Galvanized Gutters
Downspouts
Downspout Elbows
Roof Jacks at Plumbing penetrations

1960
70
500
1
140
56
12
1

SF
LF
SF
LS
LF
LF
EA
Allow

$
$
$
$
$
$
$
$

7.85
4.95
2.92
500.00
2.10
2.65
7.15
250.00

ROOF COVERINGS

1000

SF

18.47

$
$
$
$
$
$
$
$

3.04
4.99
1.82
150.00
6.19
4.12
7.55
150.00

$18,471 $

8.71

$15,386
$347
$1,460
$500
$294
$148
$86
$250

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

10.89
9.94
4.74
650.00
8.29
6.77
14.70
400.00

$21,344
$696
$2,370
$650
$1,161
$379
$176
$400

$8,706 $

$0 $

27.18

$27,176

$5,958
$349
$910
$150
$867
$231
$91
$150

Summary Item: B30 Roofing


MATERIAL
Uniformat II WBS
Code

B30

Description

Roofing

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-B30 Roofing

Quantity

Unit

1000

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

18.47

10 of 38

Labor
Cost/Unit

$18,471 $

8.71

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$8,706 $

TOTALS
Total
Cost/Unit

$0 $

27.18

Total Cost

$27,176

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: C10 Interior Construction

Total Cost:
MATERIAL

Uniformat II WBS
Code
C1010
09.29.1
06.11.10
06.11.10
09.29.10
06.22.13
06.22.13

SUBTOTAL

Description

INTERIOR PARTITIONS
5/8" Gypsum; Mold resistant; on inside of
exterior walls; Level 5 tape & skim coat
Interior partition framing - 2x4 x8' @ 16" O.C.,
single bottom & double top plate
Add Pressure Treated Bottom Plate 2x4
5/8" Gypsum; Mold resistant; on finish side of
interior partions; Level 5 tape & skim coat
Wood Base Molding
Wood Rail Molding

INTERIOR PARTITIONS

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

C1030

Description

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$34,881

TOTALS
Total
Cost/Unit

Total Cost

1120

SF

0.82

$918 $

1.65

$1,848 $

$0 $

2.47

$2,766

40
40

LF
LF

$
$

3.11
0.86

$124 $
$34 $

10.66
1.32

$426 $
$53 $

$0 $
$0 $

13.77
2.18

$551
$87

320
156
140

SF
LF
LF

$
$
$

0.82
2.85
1.89

$262 $
$445 $
$264 $

1.65
3.20
2.36

$528 $
$499 $
$331 $

$0 $
$0 $
$0 $

2.47
6.05
4.25

$790
$944
$595

1000

SF

2.05

$2,048 $

3.68

$3,685 $

$0 $

5.73

$5,733

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

FITTINGS

10.21.13
10.21.13
10.21.13
10.21.13
05.50.00
12.36.61
10.28.13

SUBTOTAL

Toilet Partitions F&C dual hung, Stainless Steel


Handicap Addition
Unrinal Screens, Floor mounted, Stainless Stl.
Entrance Screens
Fabricated Metal counter supports
Engineered Stone/Concrete Counter top
Toilet Accessories

FITTINGS

5
2
2
2
2
16
1

EA
EA
EA
EA
Allow
LF
Allow

$
$
$
$
$
$
$
$

2,151.39
404.89
815.00
1,180.00
450.00
98.00
5,500.00
-

1000

SF

23.52

$
$
$
$
$
$
$
$

255.36
210.00
88.00
265.00
115.00
1,380.00
-

$23,525 $

5.62

$10,757
$810
$1,630
$2,360
$900
$1,568
$5,500
$0

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

2,406.75
404.89
1,025.00
1,268.00
715.00
213.00
6,880.00
-

$12,034
$810
$2,050
$2,536
$1,430
$3,408
$6,880
$0

$5,623 $

$0 $

29.15

$29,148

$1,277
$0
$420
$176
$530
$1,840
$1,380
$0

Summary Item: C10 Interior Construction


MATERIAL
Uniformat II WBS
Code

C10

Description

Interior Construction

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-C10 Interior Construct.

Quantity

Unit

1000

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

25.57

11 of 38

Labor
Cost/Unit

$25,573 $

9.31

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$9,308 $

TOTALS
Total
Cost/Unit

$0 $

34.88

Total Cost

$34,881

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: C30 Interior Finishes

Total Cost:
MATERIAL

Uniformat II WBS
Code
C3010
09.96.56
09.91.23
09.91.23
09.91.23

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

WALL FINISHES
Epoxy Wall Coating, High Build 50 mil
Miscelaneous Interior paint
Interior Trim Painting
Interior Window Casing Painting

1280
1280
650
16

SF
SF
LF
EA

$
$
$
$

1.48
0.15
0.16
2.85

WALL FINISHES

1000

SF

2.24

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$

4.20
1.75
60.00

$2,236 $

7.47

$1,894
$192
$104
$46

MATERIAL
Uniformat II WBS
Code
C3020
03.35.29

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

C3030
09.29.10
09.22.36
09.91.23

SUBTOTAL

Total Labor
Cost

Total Material
Cost

Labor
Cost/Unit

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$

$7,474 $

$5,376
$0
$1,138
$960

LABOR
Total Labor
Cost

$17,900

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$

5.68
0.15
1.91
62.85

$7,270
$192
$1,242
$1,006

$0 $

9.71

$9,710

$0
$0
$0
$0

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

FLOOR FINISHES
2 Coat Wpoxy Floor finish

1000

SF

$
$

0.32
-

$320 $
$0 $

0.85
-

$850 $
$0 $

$0 $
$0 $

1.17
-

$1,170
$0

FLOOR FINISHES

1000

SF

0.32

$320 $

0.85

$850 $

$0 $

1.17

$1,170

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

Description

Quantity

Unit

Material
Cost/Unit

CEILING FINISHES
5/8" Mold resistant Gypsum Drywall
Ceiling Lath
Paint Ceiling, Latex primer, 2 coats

1000
1000
1000

SF
SF
SF

$
$
$
$

0.82
0.72
0.38
-

CEILING FINISHES

1000

SF

1.92

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$

2.85
1.15
1.10
-

$1,920 $

5.10

$820
$720
$380
$0

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$

$5,100 $

$2,850
$1,150
$1,100
$0

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$

3.67
1.87
1.48
-

$3,670
$1,870
$1,480
$0

$0 $

7.02

$7,020

$0
$0
$0
$0

Summary Item: C30 Interior Finishes


MATERIAL
Uniformat II WBS
Code

C30

Description

Interior Finishes

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-C30 Interior Finishes

Quantity

Unit

1000

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

4.48
12 of 38

Labor
Cost/Unit

$4,476 $

13.42

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$13,424 $

TOTALS
Total
Cost/Unit

$0 $

17.90

Total Cost

$17,900

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: D20 Plumbing Systems

Total Cost:
MATERIAL

Uniformat II WBS
Code
D2010
22.42.13
22.42.13
22.42.13
22.42.13
22.41.16
22.41.16
22.42.39
22.42.16
22.42.16

SUBTOTAL

Description

PLUMBING FIXTURES
F&I Urinals, Waterless
Rough-in Urinals
F&I Water Closets
Rough-in Water Closets
F&I Vanity Sinks, Self Rimming SS
Rough-in F&I Vanity Sinks
Faucets. Automatic Sensor
Service floor sink
Rough-in Floor sink

PLUMBING FIXTURES

Quantity

Unit

Material
Cost/Unit

2
2
5
5
5
5
5
1
1

EA
EA
EA
EA
EA
EA
EA
EA
EA

$
$
$
$
$
$
$
$
$

510.00
305.00
640.00
1,306.25
460.00
332.64
488.00
920.00
115.00

1000

SF

18.80

LABOR

Total Material
Cost

Labor
Cost/Unit

D2020
22.11.13
22.11.13
22.34.36

SUBTOTAL

Description

DOMESTIC WATER DISTRIBUTION


Additional 1" water Distribution Pipe
Fitting Allowance 10%
Water Heater

DOMESTIC WATER DISTRIBUTION

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-D20 Plumbing

Quantity

Unit

Material
Cost/Unit

160
1
1

LF
Allow
EA

$
$
$
$
$
$

8.18
130.88
2,609.89
-

1000

SF

4.05

TOTALS
Total
Cost/Unit

Total Cost

72.00
372.48
240.00
390.67
225.00
624.00
130.00
325.00
880.00

$144
$745
$1,200
$1,953
$1,125
$3,120
$650
$325
$880

$
$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$
$

582.00
677.48
880.00
1,696.92
685.00
956.64
618.00
1,245.00
995.00

$1,164
$1,355
$4,400
$8,485
$3,425
$4,783
$3,090
$1,245
$995

$18,799 $

10.14

$10,142 $

$0 $

28.94

$28,942

LABOR

Total Material
Cost

13 of 38

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$42,776

$
$
$
$
$
$
$
$
$

$1,020
$610
$3,200
$6,531
$2,300
$1,663
$2,440
$920
$115

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

Labor
Cost/Unit
$
$
$
$
$

11.70
570.24
-

$4,050 $

2.44

$1,309
$131
$2,610
$0
$0
$0

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$

$0
$0
$0
$0
$0
$0

$
$
$
$
$
$

19.88
130.88
3,180.13
-

$3,181
$131
$3,180
$0
$0
$0

$2,442 $

$0 $

6.49

$6,492

$1,872
$0
$570
$0
$0
$0

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: D20 Plumbing Systems

Total Cost:
MATERIAL

Uniformat II WBS
Code
D2030
22.13.16
22.13.16
22.13.15
22.13.16

SUBTOTAL

Description

SANITARY WASTE
4" Waste Collection Trunk line
Floor drains
2" Waste Collection to Floor Drains
Fitting Allowance 10%

SANITARY WASTE

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

80
4
40
1

LF
EA
LF
Allow

$
$
$
$
$

17.92
349.87
13.83
419.77
-

1000

SF

3.81

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$
$

26.21
120.00
24.00
-

$3,806 $

3.54

$1,433
$1,399
$553
$420
$0

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$42,776

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$

$0
$0
$0
$0
$0

$
$
$
$
$

44.12
469.87
37.83
419.77
-

$3,530
$1,879
$1,513
$420
$0

$3,537 $

$0 $

7.34

$7,342

$2,097
$480
$960
$0
$0

Summary Item: D20 Plumbing Systems


MATERIAL
Uniformat II WBS
Code

D20

Description

Plumbing Systems

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-D20 Plumbing

Quantity

Unit

1000

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

26.65

14 of 38

Labor
Cost/Unit

$26,655 $

16.12

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$16,121 $

TOTALS
Total
Cost/Unit

$0 $

42.78

Total Cost

$42,776

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: D30 HVAC

Total Cost:
MATERIAL

Uniformat II WBS
Code
D3040
23.31.13
23.34.14
32.37.13
36.37.15
23.19.33

SUBTOTAL

YtB
01/12/11
BBB
01/17/11

Description

DISTRIBUTION SYSTEMS (HVAC)


Ductwork
210 CFM Exhaust Blowers
Intlet Grilles
Exhaust Louvers
Exhaust Controls

DISTRIBUTION SYSTEMS (HVAC)

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$2,438

TOTALS
Total
Cost/Unit

Total Cost

80
2
2
2
2

Lbs
EA
EA
EA
EA

$
$
$
$
$
$
$
$

0.66
402.06
46.55
59.25
100.00
-

$53
$804
$93
$119
$200
$0
$0
$0

$
$
$
$
$
$
$
$

8.99
91.20
42.24
26.98
65.00
-

$719
$182
$84
$54
$130
$0
$0
$0

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

9.65
493.26
88.79
86.23
165.00
-

$772
$987
$178
$172
$330
$0
$0
$0

1000

SF

1.27

$1,269 $

1.17

$1,170 $

$0 $

2.44

$2,438

Summary Item: D30 HVAC


MATERIAL
Uniformat II WBS
Code

Description

D30

HVAC

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-D30 HVAC

Quantity

1000

Unit

SF

Material
Cost/Unit

LABOR

Total Material
Cost

1.27

15 of 38

Labor
Cost/Unit

$1,269 $

1.17

Total Labor
Cost

$1,170

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
0

TOTALS
Total
Cost/Unit

$0 $

2.44

Total Cost

$2,438

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: D50 Electrical

Total Cost:
MATERIAL

Uniformat II WBS
Code
D5010
26.24.16

SUBTOTAL

Description

ELECTRICAL SERVICE & DISTRIBUTION


1phz. 225 Amp, 120/208V, Service Panel &
feeders
ELECTRICAL SERVICE &

DISTRIBUTION

Quantity

Unit

EA

$ 1,551.83

SF

1000

LABOR

Material Total Material


Labor
Cost/Unit
Cost
Cost/Unit

1.55

D5020
26.51.13
26.51.13
26.05.90
26.05.90
23.05.19
26.05.80
26.05.19

SUBTOTAL

Description

LIGHTING & BRANCH WIRING


Energy Saving Fluorescent lighting fixtures
Utility Chase lighting Fixtures
Receptacles GFCI
Switches
230V wiring to septic system
Wire Up Septic system
Additional Building Wiring

LIGHTING & BRANCH WIRING

Quantity

Unit

8
2
15
3
1
1
1

EA
EA
EA
EA
Allow
EA
Allow

$
$
$
$
$
$
$

349.13
160.00
64.19
38.87
800.00
45.00
500.00

1000

SF

5.54

$1,552 $

D5090
23.83.33
23.83.33
26.05.19

SUBTOTAL

Description

OTHER ELECTRICAL SYSTEMS


Baseboard Heaters for shoulder season
Wall thermostat
Wiring allowance

OTHER ELECTRICAL SYSTEMS

2.74

Material Total Material


Labor
Cost/Unit
Cost
Cost/Unit
$
$
$
$
$
$
$

235.00
235.00
70.08
52.80
350.00
220.00
350.00

$5,538 $

4.48

$2,793
$320
$963
$117
$800
$45
$500

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

Total
Cost/Unit

$0 $ 4,287.83

$2,736 $

$0 $

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$0
$0
$0
$0
$0
$0
$0

$4,480 $

$0 $

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$4,288

4.29

Total
Cost/Unit

LABOR

Total Cost

$4,288

TOTALS

$
$
$
$
$
$
$

$1,880
$470
$1,051
$158
$350
$220
$350

$18,118

TOTALS

$2,736 $

LABOR

MATERIAL
Uniformat II WBS
Code

Total Labor
Cost

$1,552 $ 2,736.00

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

Total Cost

$
584.13
$
395.00
$
134.27
$
91.67
$ 1,150.00
$
265.00
$
850.00

$4,673
$790
$2,014
$275
$1,150
$265
$850

10.02

$10,017

TOTALS

Quantity

Unit

10
3
1

Ea
Ea
Allow

$
$
$

126.78
106.98
75.00

$1,268 $
$321 $
$75 $

188.16
67.00
67.00

$1,882 $
$201 $
$67 $

$0 $
$0 $
$0 $

314.94
173.98
142.00

$3,149
$522
$142

1000

SF

1.66

$1,664 $

2.15

$2,150 $

$0 $

3.81

$3,813

Material Total Material


Labor
Cost/Unit
Cost
Cost/Unit

Total Labor
Cost

Total
Cost/Unit

Total Cost

Summary Item: D50 Electrical


MATERIAL
Uniformat II WBS
Code

D50

Description

Electrical

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-D50 Electrical

Quantity

Unit

1000

SF

LABOR

Material Total Material


Labor
Cost/Unit
Cost
Cost/Unit
$

8.75
16 of 38

$8,753 $

9.37

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$9,365 $

TOTALS
Total
Cost/Unit

$0 $

18.12

Total Cost

$18,118
1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: F20 Selective Building Demolition

Total Cost:
MATERIAL

Uniformat II WBS
Code
F2010
02.41.19

SUBTOTAL

Description

BUILDING ELEMENTS DEMOLITION


Demo structures- haul to dump;

BUILDING ELEMENTS DEMOLITION

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

F2020
02.81.20
31.23.23

SUBTOTAL

Description

HAZARDOUS COMPONENTS ABATEMENT


Pump & Flush Existing pit toilets
Import & Backfill pits

HAZARDOUS COMPONENTS
ABATEMENT

$6,315

TOTALS
Total
Cost/Unit

Total Cost

Day

$
$
$

$0 $
$0 $
$0 $

1,650.00
-

$1,650 $
$0 $
$0 $

3,250.00
-

$3,250 $
$0 $
$0 $

4,900.00
-

$4,900
$0
$0

1000

SF

$0 $

1.65

$1,650 $

3.25

$3,250 $

4.90

$4,900

MATERIAL
Uniformat II WBS
Code

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

1
50

LS
CY

$
$
$
$

9.25
-

1000

SF

0.46

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$

165.00
3.50
-

$463 $

0.34

$0
$463
$0
$0

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$

375.00
4.75
-

$340 $

0.61

$165
$175
$0
$0

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$

540.00
17.50
-

$540
$875
$0
$0

$613 $

1.42

$1,415

$375
$238
$0
$0

Summary Item: F20 Selective Building Demolition


MATERIAL
Uniformat II WBS
Code

F20

Description

Selective Building Demolition

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-F20 Selective Demo.

Quantity

1000

Unit

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

0.46

17 of 38

Labor
Cost/Unit

$463 $

1.99

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$1,990 $

3.86

TOTALS
Total
Cost/Unit

$3,863 $

6.32

Total Cost

$6,315

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G10 Site Preparation

Total Cost:
MATERIAL

Uniformat II WBS
Code
G1010
31.13.13
31.13.13
31.13.13
31.14.13

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

G1030
31.23.23
31.23.16
31.22.16
31.22.16
31.23.23

SUBTOTAL

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

SITE CLEARING
Brush Mowing for Building Pad Area
Selective Tree Removal
Stump Removal
Strip & Stockpile Topsoil

1
3
3
1000

Acre
Ea
Ea
CY

$
$
$
$
$

$0
$0
$0
$0
$0

$
$
$
$
$

452.64
178.75
36.22
0.79
-

$453
$536
$109
$787
$0

$
$
$
$
$

265.32
154.44
94.38
1.37
-

SITE CLEARING

1000

SF

$0 $

1.88

$1,885 $

2.38

MATERIAL
Uniformat II WBS
Code

Description

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

SITE EARTHWORK
Imported fill for building Pad
Onsite Cut to fill
Fine Grade Building Pad
Clean-up and Fine Grade around Building
Backfill & Compact existing pits

250
500
2000
5000
50

CY
CY
SF
SF
CY

$
$
$
$
$
$

8.75
-

SITE EARTHWORK

1000

SF

2.19

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$
$
$

4.55
1.25
0.12
0.07
2.50
-

$2,188 $

2.48

$2,188
$0
$0
$0
$0
$0

Total Labor
Cost

6.55
3.55
0.24
0.10
3.50
-

$2,478 $

4.57

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$

717.96
333.19
130.60
2.16
-

$718
$1,000
$392
$2,160
$0

$2,385 $

4.27

$4,269

$265
$463
$283
$1,373
$0

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$
$
$

$1,138
$625
$240
$350
$125
$0

$13,502

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$

19.85
4.80
0.36
0.17
6.00
-

$4,963
$2,400
$720
$850
$300
$0

$4,568 $

9.23

$9,233

$1,638
$1,775
$480
$500
$175
$0

Summary Item: G10 Site Preparation


MATERIAL
Uniformat II WBS
Code

G10

Description

Site Preparation

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-G10 Site Preparation

Quantity

1000

Unit

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

2.19

18 of 38

Labor
Cost/Unit

$2,188 $

4.36

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$4,362 $

6.95

TOTALS
Total
Cost/Unit

$6,952 $

13.50

Total Cost

$13,502

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G20 Site Improvements

Total Cost:
MATERIAL

Uniformat II WBS
Code
G2030
32 06 10

SUBTOTAL

Description

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

PEDESTRIAN PAVING
Concrete Flatwork at Building

2000

SF

$
$
$
$
$
$
$
$

4.45
-

PEDESTRIAN PAVING

1000

SF

8.90

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$
$
$
$
$

3.65
-

$8,900 $

7.30

$8,900
$0
$0
$0
$0
$0
$0
$0

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$16,200

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

8.10
-

$16,200
$0
$0
$0
$0
$0
$0
$0

$7,300 $

$0 $

16.20

$16,200

$7,300
$0
$0
$0
$0
$0
$0
$0

Summary Item: G20 Site Improvements


MATERIAL
Uniformat II WBS
Code

G20

Description

Site Improvements

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-G20 Site Improvements

Quantity

1000

Unit

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

8.90

19 of 38

Labor
Cost/Unit

$8,900 $

7.30

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$7,300 $

TOTALS
Total
Cost/Unit

$0 $

16.20

Total Cost

$16,200

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G30 Site Mechanical Utilities

Total Cost:
MATERIAL

Uniformat II WBS
Code
G3010
33.21.13
33.21.13
33.21.13
33.21.13
22.11.13
22.11.19
33.21.13

SUBTOTAL

Description

Quantity

Unit

WATER SUPPLY
Drill water well
Install 8" Casing
Install 2" Well pump
2" HDPE pump riser
2" Supply Line to building
Pressure equilization tank in Building
Pump control system with alarm

1200
1200
1
1200
150
1
1

VLF
VLF
EA
VLF
LF
Ea
Allow

WATER SUPPLY

1000

SF

Material
Cost/Unit

$
$
$
$
$
$
$

22.50
641.89
3.50
3.50
250.00
250.00
-

32.87

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$
$
$
$
$

14.39
2.50
150.00
2.50
100.00
100.00
-

$32,867 $

20.99

$0
$27,000
$642
$4,200
$525
$250
$250
$0

MATERIAL
Uniformat II WBS
Code
G3020
33.36.13
33.36.13
33.36.13
33.36.13
33.36.13
36.31.13

SUBTOTAL

Description

SANITARY SEWER
Install Septic King Tank & Treatment system
Excavate Leach Field
Install Leach Field Chamber System
Backfill with Drain Rock
Common Backfill Leach Field Mound
Sewer outfall from building

SANITARY SEWER

Quantity

Unit

1
90
16
25
90
75

LS
CY
EA
Tons
CY
LF

1000

SF

Material
Cost/Unit

$
$
$
$
$
$

395.00
23.50
5.85
-

53.35

$
$
$
$
$
$
$
$

31.68
0.75
100.00
4.00
50.00
50.00
-

$20,990 $

39.72

$17,265
$3,000
$150
$0
$375
$100
$100
$0

LABOR

Total Material
Cost

$ 46,000.00

Total Labor
Cost

Labor
Cost/Unit
$
$
$
$
$
$
$
$

4,500.00
11.20
265.00
19.50
11.20
4.65
-

$53,346 $

11.59

$46,000
$0
$6,320
$588
$0
$439
$0
$0

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

Total Labor
Cost

2,500.00
3.80
72.50
8.50
3.80
3.60
-

$11,592 $

4.83

$163,337

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

46.07
25.75
891.89
3.50
10.00
400.00
400.00
-

$55,281
$30,900
$892
$4,200
$1,500
$400
$400
$0

$39,716 $

93.57

$93,572

$38,016
$900
$100
$0
$600
$50
$50
$0

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$
$
$
$
$

$4,500
$1,008
$4,240
$488
$1,008
$349
$0
$0

YtB
01/12/11
BBB
01/17/11

$2,500
$342
$1,160
$213
$342
$270
$0
$0

TOTALS
Total
Cost/Unit

Total Cost

$ 53,000.00
$
15.00
$
732.50
$
51.50
$
15.00
$
14.10
$
$
-

$4,827 $

$53,000
$1,350
$11,720
$1,288
$1,350
$1,058
$0
$0

69.77

$69,765

Summary Item: G30 Site Mechanical Utilities


MATERIAL
Uniformat II WBS
Code

G30

Description

Site Mechanical Utilities

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-G30 Site Mechanical

Quantity

1000

Unit

SF

Material
Cost/Unit

LABOR

Total Material
Cost

86.21
20 of 38

Labor
Cost/Unit

$86,213 $

32.58

Total Labor
Cost

$32,582

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
44.5425

TOTALS
Total
Cost/Unit

$44,543 $

163.34

Total Cost

$163,337
1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G40 Site Electrical Utilities

Total Cost:
MATERIAL

Uniformat II WBS
Code
G4010
33.71.19
33.71.19

SUBTOTAL

Description

ELECTRICAL DISTRIBUTION
Electrical Service Drop by utility company
Transformer & Main disconnect

ELECTRICAL DISTRIBUTION

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

1
1

LS
EA

$
$
$
$
$
$
$
$

2,500.00
2,500.00
-

1000

SF

5.00

LABOR

Total Material
Cost

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$5,000

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

2,500.00
2,500.00
-

$2,500
$2,500
$0
$0
$0
$0
$0
$0

$5,000 $

$0 $

$0 $

5.00

$5,000

$2,500
$2,500
$0
$0
$0
$0
$0
$0

Summary Item: G40 Site Electrical Utilities


MATERIAL
Uniformat II WBS
Code

G40

Description

Site Electrical Utilities

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1-G40 Site Electrical

Quantity

1000

Unit

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

5.00

21 of 38

Labor
Cost/Unit

$5,000 $

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$0 $

TOTALS
Total
Cost/Unit

$0 $

5.00

Total Cost

$5,000

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Summary Item: XX

Estimate By:
Date:
Reviewed By:
Date:

General Conditions

Total Cost:
MATERIAL

Uniformat II WBS
Code
01 31
01.31.13
01.31.13
01.31.13
01.31.13
01.31.13
01.31.13
01.31.xx
01.31.xx

SUBTOTAL

Description

Quantity

Unit

Project Management & Coordination


Project Superintendent
Project Manager - Half Time
General Pupose Laborer - Part Time
Builders Risk Insurance
General Liabiity Insurance
Payment & Performance Bond 1.5%
Labor down time due to payroll interviews
Certified Payrol Costs

20
18
15
1
1
1
1
0

Weeks
Weeks
Weeks
LS
LS
Unit
LS
Unit

Project Management & Coordination

1000

SF

Material
Cost/Unit

Total Material
Cost

$
$
$
$ 3,500.00
$ 2,000.00
$ 15,000.00
$
$
-

LABOR

$
$
$
$
$
$
$
$

2,500.00
750.00
1,500.00
3,500.00
500.00

$20,500 $

89.50

$0
$0
$0
$3,500
$2,000
$15,000
$0
$0

20.50

Labor
Cost/Unit

MATERIAL
Uniformat II WBS
Code
01 32
01.32.13
01.32.13
01.32.13
01.50.00

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

Scheduling & Documentation


Prepare Initial Schedule
Schedule Updates
Schedule Printing & Reproduction
Prepare SWMPP

1
13
1
1

LS
EA
Allow
LS

$
$
$
$

300.00
50.00

Scheduling & Documentation

1000

SF

0.35

Total Material
Cost

Labor
Cost/Unit
$
$
$
$

3,000.00
250.00
1,500.00

$350 $

7.75

$0
$0
$300
$50

01 45
01.45.23
01.45.23
01.45.23
01.40.00

Description

Quality control
Concrete Testing
Compaction Testing
Other Testing
Special Inspections

Quantity

5
10
1
1

Unit

EA
EA
LS
Allow

Material
Cost/Unit
$
$
$
$

SUBTOTAL

Quality control

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1 General Conditions

1000

SF

150.00
75.00
500.00
-

2.00

22 of 38

$0
$0
$0
$0
$0
$0
$0
$0

$89,500 $

$0 $

Total Labor
Cost

Labor
Cost/Unit
$
$
$
$
$

1,500.00
-

$2,000 $

1.50

$750
$750
$500
$0
$0

Total Cost

$ 2,500.00
$
750.00
$ 1,500.00
$ 3,500.00
$ 2,000.00
$ 15,000.00
$ 3,500.00
$
500.00

$50,000
$13,500
$22,500
$3,500
$2,000
$15,000
$3,500
$0

110.00

$110,000

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$

$0
$0
$0
$0

$
$
$
$

3,000.00
250.00
300.00
1,550.00

$3,000
$3,250
$300
$1,550

$7,750 $

$0 $

8.10

$8,100

$3,000
$3,250
$0
$1,500

LABOR

Total Material
Cost

Total
Cost/Unit

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$151,710

TOTALS

$
$
$
$
$
$
$
$

$50,000
$13,500
$22,500
$0
$0
$0
$3,500
$0

LABOR

MATERIAL
Uniformat II WBS
Code

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

YtB
01/12/11
BBB
01/17/11

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$

$0
$0
$0
$0
$0

$
$
$
$
$

150.00
75.00
500.00
1,500.00
-

$750
$750
$500
$1,500
$0

$1,500 $

$0 $

3.50

$3,500

$0
$0
$0
$1,500
$0

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Summary Item: XX

Estimate By:
Date:
Reviewed By:
Date:

General Conditions

Total Cost:
MATERIAL

Uniformat II WBS
Code
01 51
01.51.13
01.51.13
01.51.13

SUBTOTAL

Description

Temporary Utilites
Install Temporary Power
Temporary Electricity
Chemical Toilets

Temporary Utilites

Quantity

1
7
12

1000

Unit

Material
Cost/Unit

LS
$
Month $
Ea-Mo. $
$

500.00
150.00
175.00
-

3.65

SF

LABOR

Total Material
Cost

Labor
Cost/Unit

01 52
01.52.13
01.52.13
01.52.13
01.52.13
01.52.13
01.52.13
01.54.16
01.52.13

SUBTOTAL

Description

Construction Facilities
Office Trailer Set Up
Trailer Rental
Storage Bin Rental
Temporary Fence
Gravel Surrface For Yard
Erosion control
Sky Trac Fork Lift Rental
Miscelaneous Facilties

Construction Facilities

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1 General Conditions

Quantity

Unit

Material
Cost/Unit

1
7
15
300
50
1
6
1

LS
Month
Ea-Mo
LF
Tons
LS
Months
Allow

$
$
$
$
$
$
$
$

18.00
2,000.00
2,500.00

1000

SF

5.40

TOTALS
Total
Cost/Unit

Total Cost

$0
$0
$0
$0

$
$
$
$

$0
$0
$0
$0

$
$
$
$

500.00
150.00
175.00
-

$500
$1,050
$2,100
$0

$3,650 $

$0 $

$0 $

3.65

$3,650

LABOR

Total Material
Cost

23 of 38

$151,710

$
$
$
$

$500
$1,050
$2,100
$0

MATERIAL
Uniformat II WBS
Code

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

YtB
01/12/11
BBB
01/17/11

Labor
Cost/Unit
$
$
$
$
$
$
$
$

1,200.00
5.00
1,000.00
-

$5,400 $

2.45

$0
$0
$0
$0
$900
$2,000
$0
$2,500

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

300.00
380.00
75.00
6.50
7.50
500.00
700.00
-

$300
$2,660
$1,125
$1,950
$375
$500
$4,200
$0

$
$
$
$
$
$
$
$

1,500.00
380.00
75.00
6.50
30.50
3,500.00
700.00
2,500.00

$1,500
$2,660
$1,125
$1,950
$1,525
$3,500
$4,200
$2,500

$2,450 $

11.11

$11,110 $

18.96

$18,960

$1,200
$0
$0
$0
$250
$1,000
$0
$0

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Summary Item: XX

Estimate By:
Date:
Reviewed By:
Date:

General Conditions

Total Cost:

MATERIAL
Uniformat II WBS
Code
01 54 36
01.54.36
01.54.36

SUBTOTAL

Summary Item: XX

Description

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

Mobilizaton
Mobilization
Demobilization

1
0

Allw
Unit

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

7,500.00
5,000.00
-

Mobilizaton

1000

SF

$0 $

$0 $

7.50

XX

$151,710

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

7,500.00
5,000.00
-

$7,500
$0
$0
$0
$0
$0
$0
$0

$7,500 $

7.50

$7,500

$7,500
$0
$0
$0
$0
$0
$0
$0

General Conditions
MATERIAL

Uniformat II WBS
Code

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

YtB
01/12/11
BBB
01/17/11

Description

General Conditions

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 1 General Conditions

Quantity

1000

Unit

SF

Material
Cost/Unit
$

LABOR

Total Material
Cost

31.90

24 of 38

Labor
Cost/Unit

$31,900 $

101.20

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$101,200 $

18.61

TOTALS
Total
Cost/Unit

$18,610 $

151.71

Total Cost

$151,710

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service
Class A Construction Cost Estimate

BID ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS Number:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX
Bid Item Number
BID ITEM 2

Item
No.

WBS

Description

1
2
3
4

G10
G20
G30
XX

Site Preparation
Site Improvements
Site Mechanical Utilities
Bid Item 2 General Conditions
Subtotal Direct Construction Costs

Estimate By:
Date:
Reviewed By:
Date:
Asset / Project Element / Description
New Parking Lot & Site Utilities

Material
Cost/Unit
$
$
$
$
$

2,500.00
143,581.04
12,153.36
12,925.00
171,159.40

Total Material
Cost
$
$
$
$
$

Total Value of Government Furnished Property (GFP) Inc. in Direct Cost .


Direct Cost Subtotal without GFP . $
Design Contingency
2.00%
Total Direct Construction Costs
Standard General Conditions
Government General Conditions

0.00%
3.00%

2,500
143,581
12,153
12,925
171,159

Size/Count
1

Units
LS

11,710.58
36,335.00
14,232.07
8,350.00
70,627.65

$0.00
171,159

$
$
$
$
$

11,711
36,335
14,232
8,350
70,628

$
$

70,628

8.50%
10.00%

Estimated NET Construction Cost


Contracting Method Adjustment
Inflation Escalation

15.00%
32

$
$
$
$
$

19,775.94
43,670.00
4,240.55
6,500.00
74,186.49

Total Equipment
Cost

Direct
Cost/Unit

$
$
$
$
$

19,776
43,670
4,241
6,500
74,186

$
$
$
$
$

$
$

74,186

Total Direct
Costs

33,987
223,586
30,626
27,775
315,974
-

$
$
$
$

NET Cost/Unit

Total NET Costs

33,987
223,586
30,626
27,775
$315,974

$
$
$
$
$

$
$
$
$

$0
$315,974
$6,319
$322,293

In most cases GFP is normally zero see footnote-

53,471.16
351,769.04
48,184.01
43,698.55
497,122.76

53,471
351,769
48,184
43,699
$497,123

$0
$9,669
$331,962

Applied to Total Direct Construction Cost less GFP


Applied to Total Direct Construction Cost less GFP

Subtotal NET Construction Cost


Overhead
Profit

Equipment
Cost/Unit

Labor Cost/Unit Total Labor Cost


$
$
$
$
$

YtB
01/12/11

$28,217
$33,196
$393,375
$59,006
Months

Annual Rate =

Total Estimated NET Cost of Construction

3.60%

$44,742
$497,123

GFP costs only apply when the Government pre-purchases items, or provides other materials out of Government inventory, to be installed by contractor. Adjustments and Markup on GFP only include Inflation Escalation; No other
adjustment factors or O&P markup have been applied.

BEAR Trailhead - 100% Draft Class A Cost Estimate


Bid Item 2 Summary

Page 25 of 38

Print Date: 1/24/2011, 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G10 Site Preparation

Total Cost:
MATERIAL

Uniformat II WBS
Code
G1010
31.25.13
31.13.13
31.13.13
31.13.13
31.13.13

SUBTOTAL

Description

SITE CLEARING
Erosion Control
Clear & Grub Parking Area
Selective Tree Removal
Stump Removal
Strip & Stockpile Topsoil

SITE CLEARING

Quantity

Unit

Material
Cost/Unit

1
40000
7
7
1500

LS
SF
Ea
Ea
CY

$
$
$
$
$
$

LS

$ 2,500.00

LABOR

Total Material
Cost

2,500.00
-

$2,500
$0
$0
$0
$0
$0

Labor
Cost/Unit
$
$
$
$
$
$

G1030
31.23.16
31.23.13

SUBTOTAL

Description

SITE EARTHWORK
Onsite Cut to Fill
Scarify & Recompact Parking area

SITE EARTHWORK

Quantity

Unit

Material
Cost/Unit

Total Labor
Cost

1,450.00
0.12
178.75
36.22
0.79
-

$1,450
$4,800
$1,251
$254
$1,181
$0

$2,500 $ 8,935.58

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

Labor
Cost/Unit

1500
30000

CY
SF

$
$
$

$0 $
$0 $
$0 $

LS

$0 $ 2,775.00

$
$
$
$
$
$

1,250.00
0.19
154.44
94.38
1.37
-

$8,936 $ 12,650.94

LABOR

Total Material
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

Total Labor
Cost

1.25
0.03
-

3.55
0.06
-

$2,775 $ 7,125.00

TOTALS
Total
Cost/Unit
$
$
$
$
$
$

Total Cost

5,200.00
0.31
333.19
130.60
2.16
-

$5,200
$12,400
$2,332
$914
$3,240
$0

$12,651 $ 24,086.52

$24,087

$1,250
$7,600
$1,081
$661
$2,059
$0

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$1,875 $
$900 $
$0 $

$33,987

TOTALS
Total
Cost/Unit

$5,325 $
$1,800 $
$0 $

Total Cost

4.80
0.09
-

$7,200
$2,700
$0

$7,125 $ 9,900.00

$9,900

Summary Item: G10 Site Preparation


MATERIAL
Uniformat II WBS
Code

G10

Description

Site Preparation

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 2-G10 Site Preparation

Quantity

Unit

LS

Material
Cost/Unit

LABOR

Total Material
Cost

$ 2,500.00

26 of 38

Labor
Cost/Unit

$2,500 $ 11,710.58

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$11,711 $ 19,775.94

TOTALS
Total
Cost/Unit

$19,776 $ 33,986.52

Total Cost

$33,987

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G20 Site Improvements

Total Cost:
MATERIAL

Uniformat II WBS
Code
G2020
31.21.16
32.11.23
32.12.16
32.17.23
32.17.23
10.14.53
32.16.13
32.17.23

SUBTOTAL

Description

PARKING LOTS
Subgrade Prep Parking Lot
Furnish & Install 6" Roadbase
Furnish & Install 3" Asphalt Paving
Striping
Accessible spaces
Sign Allowance
Curb & Gutter
Striping - RV Spaces

PARKING LOTS

Quantity

Unit

4500
4500
4500
40
7
1
1000
10

SY
SY
SY
Spaces
EA
Allow
LF
EA

LS

Material
Cost/Unit
$
$
$
$
$
$
$
$

LABOR

Total Material
Cost

6.79
11.85
14.11
92.00
2,500.00
12.83
98.00

$0
$30,543
$53,325
$564
$644
$2,500
$12,825
$980

$ 101,381.04

G2030
03.30.53

SUBTOTAL

Description

PEDESTRIAN PAVING
Pedestrian Sidewalks at parking lot

PEDESTRIAN PAVING

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 2-G20 Site Improvement

Quantity

Unit

Material
Cost/Unit

3500

SF

$
$

5.20
-

LS

18,200.00

Labor
Cost/Unit
$
$
$
$
$
$
$
$

Total Labor
Cost

0.07
1.25
1.28
27.00
145.00
500.00
4.50
47.00

$315
$5,625
$5,760
$1,080
$1,015
$500
$4,500
$470

$101,381 $ 19,265.00

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

27 of 38

Labor
Cost/Unit

3.12
$18,200 $
$0 $
$
10,920.00
$18,200

$
$
$
$
$
$
$
$

0.75
3.15
3.15
8.00
35.00
8.00
18.00

$19,265 $ 40,470.00

LABOR

Total Material
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

Total Labor
Cost

TOTALS
Total
Cost/Unit
$
$
$
$
$
$
$
$

$10,920 $

Total Cost

0.82
11.19
16.28
49.11
272.00
3,000.00
25.33
163.00

$3,690
$50,343
$73,260
$1,964
$1,904
$3,000
$25,325
$1,630

$40,470 $ 161,116.04

$161,116

$3,375
$14,175
$14,175
$320
$245
$0
$8,000
$180

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$10,920 $
$0 $

$223,586

$0 $
$0 $
$0 $

TOTALS
Total
Cost/Unit

Total Cost

8.32
-

$29,120
$0

29,120.00

$29,120

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G20 Site Improvements

Total Cost:

MATERIAL
Uniformat II WBS
Code
G2050
32.90.00
32.93.43

SUBTOTAL

Description

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

Material
Cost/Unit

LANDSCAPING
Parking lot landscape allowance
Install Selective Trees

1
20

LS
EA

$
$

17,500.00
325.00

LANDSCAPING

LS

24,000.00

LABOR

Total Material
Cost

Labor
Cost/Unit

$17,500 $
$6,500 $

Total Labor
Cost

4,250.00
95.00

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$4,250 $
$1,900 $

$24,000 $ 6,150.00

2,500.00
35.00

$6,150 $ 3,200.00

$2,500 $
$700 $
$3,200 $

$223,586

TOTALS
Total
Cost/Unit

Total Cost

24,250.00
455.00

$24,250
$9,100

33,350.00

$33,350

Summary Item: G20 Site Improvements


MATERIAL
Uniformat II WBS
Code

G20

Description

Site Improvements

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 2-G20 Site Improvement

Quantity

Unit

LS

Material
Cost/Unit

Total Material
Cost

$ 143,581.04

28 of 38

LABOR
Labor
Cost/Unit

$143,581 $ 36,335.00

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$36,335 $ 43,670.00

TOTALS
Total
Cost/Unit

$43,670 $ 223,586.04

Total Cost

$223,586

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G30 Site Mechanical Utilities

Total Cost:
MATERIAL

Uniformat II WBS
Code
G3030
33.41.13
33.41.13
33.41.13
33 44 13

SUBTOTAL

Description

STORM SEWER
18" Reinforced concrete Pipe
18" Flared End Section
Water Quality Detention Pond
Storm Drain inlets

STORM SEWER

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

300
3
1
2

LF
EA
Allow
EA

LS

Material
Cost/Unit
$
$
$
$
$
$
$
$

LABOR

Total Material
Cost

26.03
86.95
1,500.00
1,292.00
-

$7,809
$261
$1,500
$2,584
$0
$0
$0
$0

$ 12,153.36

Labor
Cost/Unit
$
$
$
$
$
$
$
$

Total Labor
Cost

24.29
11.89
3,500.00
1,705.00
-

$7,286
$36
$3,500
$3,410
$0
$0
$0
$0

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$
$
$
$
$

3.50
6.85
3,000.00
85.00
-

$14,232 $ 4,240.55

$12,153 $ 14,232.07

$30,626

TOTALS
Total
Cost/Unit
53.82
105.69
8,000.00
3,082.00
-

$16,145
$317
$8,000
$6,164
$0
$0
$0
$0

$4,241 $ 30,625.98

$30,626

$1,050
$21
$3,000
$170
$0
$0
$0
$0

$
$
$
$
$
$
$
$

Total Cost

Summary Item: G30 Site Mechanical Utilities


MATERIAL
Uniformat II WBS
Code

G30

Description

Site Mechanical Utilities

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 2-G30 Site Mechanical

Quantity

Unit

LS

Material
Cost/Unit

LABOR

Total Material
Cost

$ 12,153.36

29 of 38

Labor
Cost/Unit

$12,153 $ 14,232.07

Total Labor
Cost

$14,232

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
4240.55

TOTALS
Total
Cost/Unit

$4,241 $ 30,625.98

Total Cost

$30,626

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Summary Item: XX

Estimate By:
Date:
Reviewed By:
Date:

Bid Item 2 General Conditions

Total Cost:
MATERIAL

Uniformat II WBS
Code
01 31
01.31.13
01.31.13
01.31.13
01.31.13
01.31.13
01.31.13
01.31.xx
01.31.xx

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

Project Management & Coordination


Project Superintendent
Project Manager - Half Time
General Pupose Laborer - Part Time
Builders Risk Insurance
General Liabiity Insurance
Payment & Performance Bond 1.5%
Labor down time due to payroll interviews
Certified Payroll Costs

2
1
1
1
1
1
1
0

Weeks
Weeks
Weeks
LS
LS
Unit
LS
Unit

$
$
$
$
$
$
$
$

500.00
250.00
7,500.00
-

Project Management & Coordination

1000

SF

8.25

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$
$
$
$
$

2,500.00
750.00
1,500.00
500.00
150.00

$8,250 $

7.75

$0
$0
$0
$500
$250
$7,500
$0
$0

MATERIAL
Uniformat II WBS
Code
01 45
1.45.23
01.45.23
01.45.23
01.45.23

Description

Quality control
Concrete Testing
Compaction Testing
Other Testing
Special Inspections

Quantity

12
25
1
1

Unit

EA
EA
LS
Allow

Material
Cost/Unit
$
$
$
$
$
$
$

SUBTOTAL

Quality control

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 2 General Conditions

YtB
01/12/11
BBB
01/17/11

LS

$ 4,675.00

30 of 38

Labor
Cost/Unit
$
$
$
$
$
$
$
$

600.00
-

$4,675 $

600.00

$1,800
$1,875
$1,000
$0
$0
$0
$0
$0

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

2,500.00
750.00
1,500.00
500.00
250.00
7,500.00
500.00
150.00

$5,000
$750
$1,500
$500
$250
$7,500
$500
$0

$7,750 $

$0 $

16.00

$16,000

$5,000
$750
$1,500
$0
$0
$0
$500
$0

LABOR

Total Material
Cost

150.00
75.00
1,000.00

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$27,775

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$600 $

$0 $ 5,275.00

$0
$0
$0
$600
$0
$0
$0
$0

$
$
$
$
$
$
$
$

150.00
75.00
1,000.00
600.00
-

Total Cost

$1,800
$1,875
$1,000
$600
$0
$0
$0
$0

$5,275

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Summary Item: XX

Estimate By:
Date:
Reviewed By:
Date:

Bid Item 2 General Conditions

Total Cost:

MATERIAL
Uniformat II WBS
Code
01 54
01.54.36
01.54.36

SUBTOTAL

Summary Item: XX

Description

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

XX

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

Mobilizaton
Mobilization
Demobilization

1
0

Allow
Unit

$
$
$
$

$0
$0
$0
$0

$
$
$
$

$0
$0
$0
$0

Mobilizaton

LS

$0 $

$0 $ 6,500.00

$
$
$
$

6,500.00
4,000.00
-

$6,500
$0
$0
$0

$27,775

TOTALS
Total
Cost/Unit
$
$
$
$

Total Cost

6,500.00
4,000.00
-

$6,500
$0
$0
$0

$6,500 $ 6,500.00

$6,500

Bid Item 2 General Conditions


MATERIAL

Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

Description

Bid Item 2 General Conditions

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 2 General Conditions

Quantity

Unit

LS

Material
Cost/Unit

LABOR

Total Material
Cost

$ 12,925.00

31 of 38

Labor
Cost/Unit

$12,925 $ 8,350.00

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$8,350 $ 6,500.00

TOTALS
Total
Cost/Unit

$6,500 $ 27,775.00

Total Cost

$27,775

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service
Class A Construction Cost Estimate

BID ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS Number:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX
Bid Item Number
BID ITEM 3

Item
No.

WBS

1
2
3
6
7
8

G10
G20
G30
XX
XX
XX

Estimate By:
Date:
Reviewed By:
Date:
Asset / Project Element / Description
Picnic Area & Trailhead Improvement

Description
Site Preparation
Site Improvements
Site Mechanical Utilities
Bid Item 3 General Conditions

$
$
$
$
$
$
Subtotal Direct Construction Costs $

Material
Cost/Unit
59,447.50
2,124.73
5,775.00
67,347.23

Total Material
Cost
$
$
$
$
$
$
$

Total Value of Government Furnished Property (GFP) Inc. in Direct Cost .


Direct Cost Subtotal without GFP . $
Design Contingency
2.00%
Total Direct Construction Costs
Standard General Conditions
Government General Conditions

0.00%
3.00%

59,448
2,125
5,775
67,347

Size/Count
1

Units
LS

11,860.00
25,960.00
2,274.65
7,550.00
47,644.65

$0.00
67,347

$
$
$
$
$
$
$

11,860
25,960
2,275
7,550
47,645

$
$

47,644.65

8.50%
10.00%

Estimated NET Construction Cost


Contracting Method Adjustment
Inflation Escalation

15.00%
32

$
$
$
$
$
$
$

4,845.00
12,269.50
330.37
2,500.00
19,944.87

Total Equipment
Cost

Direct
Cost/Unit

$
$
$
$
$
$
$

4,845
12,270
330
2,500
19,945

$
$
$
$
$
$
$

$
$

19,944.87

Total Direct
Costs

16,705
97,677
4,730
15,825
134,937
-

$
$
$
$
$
$

NET Cost/Unit

Total NET Costs

16,705
97,677
4,730
15,825
$134,937

$
$
$
$
$
$
$

$
$
$
$
$
$

$0
$134,937
$2,699
$137,635

In most cases GFP is normally zero see footnote-

26,282.06
153,675.72
7,441.34
24,897.55
212,296.67

26,282
153,676
7,441
24,898
$212,297

$0
$4,129
$141,765

Applied to Total Direct Construction Cost less GFP


Applied to Total Direct Construction Cost less GFP

Subtotal NET Construction Cost


Overhead
Profit

Equipment
Cost/Unit

Labor Cost/Unit Total Labor Cost


$
$
$
$
$
$
$

YtB
01/12/11
BBB
01/17/11

$12,050
$14,176
$167,991
$25,199
Months

Annual Rate =

Total Estimated NET Cost of Construction

3.60%

$19,107
$212,297

GFP costs only apply when the Government pre-purchases items, or provides other materials out of Government inventory, to be installed by contractor. Adjustments and Markup on GFP only include Inflation Escalation; No other
adjustment factors or O&P markup have been applied.

BEAR Trailhead - 100% Draft Class A Cost Estimate


Bid Item 3 Summary

Page 32 of 38

Print Date: 1/24/2011, 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G10 Site Preparation

Total Cost:
MATERIAL

Uniformat II WBS
Code
G1010
31.11.10
31.13.13

SUBTOTAL

Description

SITE CLEARING
Misc. Site Clearing
Hand Clear New Trail Alignment

SITE CLEARING

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

Labor
Cost/Unit

1
500

LS
LF

$
$

$0 $
$0 $

LS

$0 $ 5,300.00

MATERIAL
Uniformat II WBS
Code
G1020
02.41.13
02.41.13

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

G1030
31.22.16
31.22.16
31.23.23
31.23.23

SUBTOTAL

2,200.00
6.20

Total Material
Cost

Labor
Cost/Unit

SITE DEMOLITION & RELOCATIONS


Misc. Site Demolition
Remove Existing Picnic Tables & Grills

1
1

LS
LS

$
$

$0 $
$0 $

SITE DEMOLITION & RELOCATIONS

LS

$0 $ 3,620.00

Description

SITE EARTHWORK
Fine Grade & Compact Picnic subgrades
Hand Grade Trail
Scarify & recompact existing dirt parking lot
Scarify Existing Trail 500' x 3'

SITE EARTHWORK

Quantity

Unit

Material
Cost/Unit

Total Labor
Cost

Total Labor
Cost

1,270.00
2,350.00

Labor
Cost/Unit

3500
3000
10000
1500

SF
SF
SF
SF

$
$
$
$

$0
$0
$0
$0

$
$
$
$

LS

$0 $ 2,940.00

1,650.00
1.25

$5,300 $ 2,275.00

485.00
500.00

$3,620 $

985.00

Total Labor
Cost

0.15
0.58
0.03
0.25

$525
$1,740
$300
$375

0.20
0.05
0.06
0.09

$2,940 $ 1,585.00

Total
Cost/Unit

Total Cost

3,850.00
7.45

$3,850
$3,725

7,575.00

$7,575

TOTALS
Total
Cost/Unit

$485 $
$500 $

Total Cost

1,755.00
2,850.00

$1,755
$2,850

$985 $ 4,605.00

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$

$16,705

TOTALS

$1,650 $
$625 $
$2,275 $

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$1,270 $
$2,350 $

LABOR

Total Material
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$2,200 $
$3,100 $

LABOR

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

$700
$150
$600
$135

$4,605

TOTALS
Total
Cost/Unit
$
$
$
$

Total Cost

0.35
0.63
0.09
0.34

$1,225
$1,890
$900
$510

$1,585 $ 4,525.00

$4,525

Summary Item: G10 Site Preparation


MATERIAL
Uniformat II WBS
Code

G10

Description

Site Preparation

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 3-G10 Site Preparation

Quantity

Unit

LS

Material
Cost/Unit
$

LABOR

Total Material
Cost

33 of 38

Labor
Cost/Unit

$0 $ 11,860.00

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$11,860 $ 4,845.00

TOTALS
Total
Cost/Unit

$4,845 $ 16,705.00

Total Cost

$16,705

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G20 Site Improvements

Total Cost:
MATERIAL

Uniformat II WBS
Code
G2030
32.06.10
31.32.13
03.30.53

SUBTOTAL

Description

PEDESTRIAN PAVING
Furnish & Install Decomposed Granite DG
Mix, spread, finegrade & compact organic
binder
Pedestrian Sidewalks-Trial Connection

PEDESTRIAN PAVING

Quantity

Unit

Material
Cost/Unit

170

Tons

76.75

6500
1500

SF
SF

$
$
$

1.30
5.13
-

LS

$ 29,192.50

LABOR

Total Material
Cost

Labor
Cost/Unit

$13,048 $

G2040
32.31.29

SUBTOTAL

Description

SITE DEVELOPMENT
Install new seat resistant single rail fence

SITE DEVELOPMENT

Quantity

Unit

Material
Cost/Unit

500

LF

$
$

$1,955 $

8.35

0.72
$8,450 $
3.10
$7,695 $
$0 $
$
11,285.00
$29,193

$4,680 $
$4,650 $
$0 $

0.15
0.25
-

LS

$ 16,000.00

Labor
Cost/Unit

$16,000 $
$0 $

G2050

Description

Quantity

Unit

Material
Cost/Unit

Total Labor
Cost

5.50
-

$2,750 $ 1,000.00

LABOR

Total Material
Cost

Labor
Cost/Unit

2.00
-

Total Labor
Cost

$97,677

TOTALS
Total
Cost/Unit

$1,420 $

Total Cost

96.60

$16,422

2.17
$975 $
8.48
$375 $
$0 $
$
43,247.00
$2,770

$14,105
$12,720
$0

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$2,750 $
$0 $

$16,000 $ 2,750.00

MATERIAL
Uniformat II WBS
Code

$11,285 $ 2,769.50

LABOR

Total Material
Cost

32.00
-

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

11.50

MATERIAL
Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

$43,247

TOTALS
Total
Cost/Unit

Total Cost

39.50
$1,000 $
$0 $
$1,000 $ 19,750.00

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$19,750
$0

$19,750

TOTALS
Total
Cost/Unit

Total Cost

LANDSCAPING

32.90.00
32.90.00
32.91.13
32.32.60
32.93.33

SUBTOTAL

Picnic Area landscape repairs & improvements


Trail landscape repairs & improvements
Soil amenders
Place Barrier Rocks
Install native shrubs

LANDSCAPING

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item -G20 Site Improvement

1
1
11500
1
150

LS
LS
SF
Allow
EA

LS

$
$
$
$
$
$

500.00
500.00
0.13
36.50
-

$ 7,970.00

34 of 38

$500
$500
$1,495
$0
$5,475
$0

$
$
$
$
$
$

1,800.00
1,600.00
0.05
500.00
12.00
-

$7,970 $ 6,275.00

$1,800
$1,600
$575
$500
$1,800
$0

$
$
$
$
$
$

600.00
750.00
0.10
2,000.00
5.00
-

$6,275 $ 5,250.00

2,900.00
2,850.00
0.28
2,500.00
53.50
-

$2,900
$2,850
$3,220
$2,500
$8,025
$0

$5,250 $ 19,495.00

$19,495

$600
$750
$1,150
$2,000
$750
$0

$
$
$
$
$
$

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G20 Site Improvements

Total Cost:

MATERIAL
Uniformat II WBS
Code
G2060
12.93.43
12.93.43

SUBTOTAL

Description

YtB
01/12/11
BBB
01/17/11

Quantity

Unit

SITE FURNISHINGS
Misc Site Furnishings
Reinstall Site Furninshings at Picnic area

1
1

Allow
LS

SITE FURNISHINGS

LS

Material
Cost/Unit
$
$
$
$

LABOR

Total Material
Cost

1,685.00
4,600.00
-

$1,685
$4,600
$0
$0

$ 6,285.00

Labor
Cost/Unit
$
$
$
$

Total Labor
Cost

1,150.00
4,500.00
-

$1,150
$4,500
$0
$0

$6,285 $ 5,650.00

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
$
$
$
$

250.00
3,000.00
-

$5,650 $ 3,250.00

$97,677

TOTALS
Total
Cost/Unit

Total Cost

$ 3,085.00
$ 12,100.00
$
$
-

$3,085
$12,100
$0
$0

$3,250 $ 15,185.00

$15,185

$250
$3,000
$0
$0

Summary Item: G20 Site Improvements


MATERIAL
Uniformat II WBS
Code

G20

Description

Site Improvements

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item -G20 Site Improvement

Quantity

Unit

LS

Material
Cost/Unit

LABOR

Total Material
Cost

$ 59,447.50

35 of 38

Labor
Cost/Unit

$59,448 $ 25,960.00

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$25,960 $ 12,269.50

TOTALS
Total
Cost/Unit

$12,270 $ 97,677.00

Total Cost

$97,677

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Estimate By:
Date:
Reviewed By:
Date:

Summary Item: G30 Site Mechanical Utilities

Total Cost:
MATERIAL

Uniformat II WBS
Code
G3030
33 41 13
33 41 13

SUBTOTAL

Description

YtB
01/12/11

Quantity

Unit

Material
Cost/Unit

STORM SEWER
12 CMP" Trail Crossing Culverts
12" Flared End Sections
Misc Drainage Improvemments

60
12
1

LF
EA
LS

$
$
$
$
$
$
$
$

STORM SEWER

LS

$ 2,124.73

LABOR

Total Material
Cost

17.35
77.80
150.00
-

$1,041
$934
$150
$0
$0
$0
$0
$0

Labor
Cost/Unit
$
$
$
$
$
$
$
$

EQUIPMENT

Total Labor
Cost

15.77
85.69
300.00
-

$
$
$
$
$
$
$
$

2.13
12.74
50.00
-

$2,275 $

330.37

$946
$1,028
$300
$0
$0
$0
$0
$0

$2,125 $ 2,274.65

Equipment
Cost/Unit

$4,730

TOTALS

Total
Equipment
Cost
$128
$153
$50
$0
$0
$0
$0
$0

Total
Cost/Unit
$
$
$
$
$
$
$
$

Total Cost

35.25
176.23
500.00
-

$2,115
$2,115
$500
$0
$0
$0
$0
$0

$330 $ 4,729.75

$4,730

Summary Item: G30 Site Mechanical Utilities


MATERIAL
Uniformat II WBS
Code

G30

Description

Site Mechanical Utilities

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 3-G30 Site Mechanical

Quantity

Unit

LS

Material
Cost/Unit

LABOR

Total Material
Cost

$ 2,124.73

36 of 38

Labor
Cost/Unit

$2,125 $ 2,274.65

Total Labor
Cost

$2,275

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost
330.368

TOTALS
Total
Cost/Unit

$330 $ 4,729.75

Total Cost

$4,730

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Summary Item: XX

Estimate By:
Date:
Reviewed By:
Date:

Bid Item 3 General Conditions

Total Cost:
MATERIAL

Uniformat II WBS
Code
01 31
31.23.15
03.15.05
03.11.13
03.21.10
03.30.53
03.11.13
03.35.29
07.27.13

SUBTOTAL

Description

Quantity

Unit

Material
Cost/Unit

Project Management & Coordination


Project Superintendent
Project Manager - Half Time
General Pupose Laborer - Part Time
Builders Risk Insurance
General Liabiity Insurance
Payment & Performance Bond 1.5%
Labor down time due to payroll interviews
Certified Payroll Costs

2
1
1
1
1
1
1
0

Weeks
Weeks
Weeks
LS
LS
Unit
LS
Unit

$
$
$
$
$
$
$
$

200.00
125.00
3,000.00
-

Project Management & Coordination

1000

SF

3.33

LABOR

Total Material
Cost

Labor
Cost/Unit
$
$
$
$
$
$
$
$

2,500.00
750.00
1,500.00
25.00

$3,325 $

7.25

$0
$0
$0
$200
$125
$3,000
$0
$0

MATERIAL
Uniformat II WBS
Code
01 45
01 45 23
01 45 23
01 45 23
01 40 00
MF-2004 Code
MF-2004 Code
MF-2004 Code
MF-2004 Code

SUBTOTAL

Description

Quantity

Unit

Quality control
Concrete Testing
Compaction Testing
Other Testing
Special Inspections
Description
Description
Description
Description

8
10
1
1
0
0
0
0

EA
EA
LS
Allow
Unit
Unit
Unit
Unit

Quality control

LS

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 3-General Conditions

YtB
01/12/11
BBB
01/17/11

Material
Cost/Unit
$
$
$
$
$
$
$

$ 2,450.00

37 of 38

Labor
Cost/Unit
$
$
$
$
$
$
$
$

300.00
-

$2,450 $

300.00

$1,200
$750
$500
$0
$0
$0
$0
$0

TOTALS
Total
Cost/Unit

Total Cost

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$
$
$
$
$
$
$
$

2,500.00
750.00
1,500.00
200.00
125.00
3,000.00
25.00

$5,000
$750
$1,500
$200
$125
$3,000
$0
$0

$7,250 $

$0 $

10.58

$10,575

$5,000
$750
$1,500
$0
$0
$0
$0
$0

LABOR

Total Material
Cost

150.00
75.00
500.00

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$15,825

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

TOTALS
Total
Cost/Unit

$
$
$
$
$
$
$
$

$0
$0
$0
$0
$0
$0
$0
$0

$300 $

$0 $ 2,750.00

$0
$0
$0
$300
$0
$0
$0
$0

$
$
$
$
$
$
$
$

150.00
75.00
500.00
300.00
-

Total Cost

$1,200
$750
$500
$300
$0
$0
$0
$0

$2,750

1/24/2011 2:13 PM

United States Department of the Interior


National Park Service

Class A Construction Cost Estimate

LINE ITEM COST SUMMARY


Project:
Park:
Park Alpha:
PMIS:

Oso Comida Trailhead Improvements:


Bear Arbor NRA
BEAR
XXXXXX

Summary Item: XX

Estimate By:
Date:
Reviewed By:
Date:

Bid Item 3 General Conditions

Total Cost:

MATERIAL
Uniformat II WBS
Code
01 54 36
01 54 36.5

SUBTOTAL

Summary Item: XX

Description

Quantity

Unit

Material
Cost/Unit

LABOR

Total Material
Cost

XX

Labor
Cost/Unit

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

Mobilizaton
Mobilization
Demobilization

1
0

Allow
Unit

$
$
$
$

$0
$0
$0
$0

$
$
$
$

$0
$0
$0
$0

Mobilizaton

LS

$0 $

$0 $ 2,500.00

$
$
$
$

2,500.00
1,500.00
-

$2,500
$0
$0
$0

$15,825

TOTALS
Total
Cost/Unit
$
$
$
$

Total Cost

2,500.00
1,500.00
-

$2,500
$0
$0
$0

$2,500 $ 2,500.00

$2,500

Bid Item 3 General Conditions


MATERIAL

Uniformat II WBS
Code

YtB
01/12/11
BBB
01/17/11

Description

Bid Item 3 General Conditions

BEAR Trailhead - 100% Draft Class A Cost Estimate, Item 3-General Conditions

Quantity

Unit

LS

Material
Cost/Unit

LABOR

Total Material
Cost

$ 5,775.00

38 of 38

Labor
Cost/Unit

$5,775 $ 7,550.00

Total Labor
Cost

EQUIPMENT
Total
Equipment
Equipment
Cost/Unit
Cost

$7,550 $ 2,500.00

TOTALS
Total
Cost/Unit

$2,500 $ 15,825.00

Total Cost

$15,825

1/24/2011 2:13 PM

S-ar putea să vă placă și