I-91 Viaduct Public Information Briefing


Project File No. 607731
MassDOT Contract No. 85020
Briefing no. 5
June 27, 2016

Agenda
Welcome and Presenter Introductions
Update on Construction and Demolition Activities
(Stage 1B)
Next: Stage 2 Starts in Early Winter 2016
Traffic Management & Mitigation
Public Involvement and Outreach

6/27/2016

Project Purpose
To replace the bridge deck of the I-91 Viaduct in
Springfield, due to its poor condition. The result will be a
more reliable and dependable highway.

Project Limits

6/27/2016

Project Scope

Rehabilitation includes the following:

Complete deck replacement


Painting of structural steel, replacement of bearings,
structural steel repairs, concrete substructure repairs
Improved bridge drainage and highway lighting (on the
highway, surface streets under the viaduct, upper levels of
the north and south garage, and the Columbus Avenue
railroad underpass)
Other safety improvements, such as at the I-291/I-91 merge

Comprehensive Traffic Management

Fast Facts

Viaduct length is approximately mile

15,000 cubic yards of concrete for bridge deck and barriers


1,500 cubic yards placed to date

Over 7 million pounds of reinforcing steel


710,000 pounds placed to date

Over 450 bearing replacements


over 63 replaced to date

23 subcontractors to date

Approximately 100 workers per day of which over 20 are from Springfield
and over 80 are from the Greater Springfield area and Western Mass.

6/27/2016

The Joint Venture Constructing the Project

J.F. White Contracting Co. A General Contractor


performing heavy civil work in Massachusetts for over
90 years.
Schiavone Construction Co. A General Contractor
performing heavy civil work in the northeast region
for over 50 years.

Construction Schedule
Milestone
Stage 1A

ContractorForecasted
Date
Complete

ContractRequired
Date
N/A

Stage1B

Ongoing

N/A

Stage2Start

EarlyWinter2016

N/A

FullBeneficialUse

LateFall2017

August6, 2018

Substantial Completion LateFall2018

November 6,2018

FieldCompletion

February 4,2019

January2019

6/27/2016

Definition of Full Beneficial Use


I-91, I-291 & Assoc. Ramps
Themajorityofthecontractworkhasbeencompletedand
theasset(s)hasbeenopenedforfullmultimodal
transportationuse,exceptforlimitedcontractworkitems
thatdonotmateriallyimpairorhindertheintendedpublic
useofthetransportationfacility.Allanticipatedlanetakings
havebeencompleted.Thisincludescompletionof
superstructurework,bridgebarrier,permanentguardrail,
removaloftemporaryconcretebarriers, finalpaving,
permanenttrafficmarkingsandsignage, permanentlighting.

Definition of Substantial Completion


Themajoritytheroadwayandutilityworkiscompleteonthe
municipalstreetsandtheremainingworknotdirectly
requiringlanestakenontheI91,I291,andtheassociated
lanesiscomplete.Completedworkincludesallstructural
steelrepairs,paintingofstructuralsteel,bearing
replacements,installationofmunicipalstreetlighting,final
pavingandtrafficmarkingsatthemunicipalstreetlevel,
Restorationofalldisturbedareas.

6/27/2016

Definition of Field Completion


AllphysicalcontractWorkiscompleteincludingpunchlist.
TheContractorhasfullydemobilizedfromfieldoperations.

Now: Stage 1B Construction

Inner lanes and median closed for construction of new median and highspeed lanes

Traffic moved to right/outer lanes

Reconstruction of I-291 westbound on-ramp to I-91 South

Ramp closures and detours (maps and directions handout available):

On-ramp from Birnie Ave/Rte.20 Connector to I-91 South

Exits 6 and 7 on I-91 South (detour to temporary ramp north of Exit 8)

On-ramps to I-91 North from State St and Union St (detour to East Columbus
Ave)

Closure of north entrance to North Parking Garage, exit remains open

6/27/2016

Now: Deck Demolition and Reconstruction

Began in February

Northbound Stage 1B
demolition complete

Southbound to begin next


month

Two shifts: (7:00 AM to 5:00 PM)


and (3:30 PM to midnight)

Noise mitigation: noise control


curtains, special back-up alarms
for equipment

Hotel area: no demo work


Friday-Sunday, delayed start time
(8:00 AM)

Traffic - Traffic Management (Stage 1B)


*

*OnsectionsnorthofI291,NBandSBareseparatedbygrade.

6/27/2016

Stage 1B Progress Photos

Stage 1B Progress Photos

6/27/2016

Stage 1B Progress Photos

6/27/2016

10

6/27/2016

Stage 1B Progress Photos

Stage 1B Progress Photos

11

6/27/2016

Stage 1B Progress Photos

Stage 1B Progress Photos

12

6/27/2016

Remaining Stage 1B Work

Continuing demolition of all Stage 1B decks

Clean, prime & paint beam top flanges

Install stay-in-place (SIP) forms & rebar

Replace bridge bearings and pin & hanger connections

Pour new concrete decks & barriers (45 spans in each


direction)

Install membrane waterproofing & pave deck

Install new signage

Install Stage 2 traffic pattern and prepare for Stage 2.

Traffic Management

To maximize work space, safety and limit confusion, there will


be two major phases of work. Each phase will result in a
reduction of one lane from the existing configuration.

The project maintains access to/from I-291.

Designated on/off ramps remain closed until late fall of 2017 for
operational/safety reasons and to expedite construction.

Access to downtown and local businesses will be maintained


using East and West Columbus and Hall of Fame Avenues.

Continuing analysis of traffic conditions and response to issues


as they arise.

13

6/27/2016

Traffic Management (Stage 1B)

Traffic Mitigation

Initial testing of detours took place to observe and make adjustments,


if needed.

Repairs to signals at State St/Columbus and Boland Way/Columbus.

Police details are provided at critical intersections during peak periods,


if needed.

Comprehensive monitoring program of key corridors/intersections


traffic plan is updated when needed, based on impacts.

Monitoring cameras are tied into the City of Springfield.

Real Time Traffic Management System (RTTM) continuously updated


message boards to deliver information in real-time.

Incident Response Operations (IRO)

14

6/27/2016

Next: Stage 2

Traffic Management Approach (Stage 2)

15

6/27/2016

Traffic Management Approach (Stage 2)

Improvementstomergeareas

Traffic Mitigation - RTTM

16

6/27/2016

Traffic Mitigation - RTTM

Message boards w/ live traffic updates

Traffic alerts to key personnel

Aid Emergency Responders for efficient response

Highway Advisory Radio 530 AM

Traffic Mitigation RTTM Screen

17

6/27/2016

Traffic Mitigation RTTM Screen

Detour signs for Downtown and attractions

18

6/27/2016

Speed Limits

Speed reduced from 50 to


45 MPH approaching the
work zone, with 40 mph
limit in the zone

Double fines in the work


zone

State Police enforcement


for driver and
construction team safety

Travel Without Limits


Taylor Rock

19

6/27/2016

MassRIDES Programs

Online Ride Matching


Commuter Incentives
Emergency Ride Home

NuRide.com/MassRIDES

Encouraging Mode Shift


MassRIDES = Statewide Travel Options Program

Carpool, vanpool, transit, bike, walk, telework


Reduce traffic congestion
Reduce emissions
Employers - outreach and worksite services
Commuters - ridematching, incentives, promotions and
marketing

20

6/27/2016

MassRIDES Outreach

325+ partner organizations, including:

MassMutual, Baystate Medical Center, American International


College, City of Springfield, Peter Pan Bus Company, Pioneer
Valley Planning Commission, Pioneer Valley Transit Authority,
Springfield Technical Community College, United PersonnelSpringfield, Western New England University, Westfield State
University

465,000+ commuters
Worksite focus commute travel

Taylor Rock
taylor.rock@dot.state.ma.us
857-368-8654

www.commute.com

21

6/27/2016

Public Involvement

Quarterly update meetings

Regularly updated project website:


www.mass.gov/massdot/I91ViaductRehab

Project fact sheets & community briefings

Notices and e-blasts on traffic changes during construction and


responses to inquiries

Project updates on social media

English and translated materials and interpreters available upon


request

How to Contact Us
Sign up on the project website for email information
and updates:
www.mass.gov/massdot/I91ViaductRehab
Send questions or concerns to:
i91viaduct@state.ma.us

22

6/27/2016

THANK YOU!
Questions?

23