Documente Academic
Documente Profesional
Documente Cultură
Of
Generators & Transformers
COURSE OBJECTIVES:
India is a vast country which spreads over 3.28 million Sq. KM area & 28 states. While some states have fossil fuel in abundance
&few are blessed with rivers of high hydro power potential,many of states have no coal deposits & have low hydro power
potentials. Therefore location of a thermal or hydro power station is critically decided. However need of reasonably better
quality of power with good voltage at major load centers located in any part of India and low `System Technical Losses' warrant a
strong transmission network.
In view of developing generation capacity Central Power Research Institute (CPRI) & other research institutes, National Thermal
Power Corporation Ltd. (NTPC), individual State government owned power generation companies and a few major private
companies are trying hard to enhance country's installed generation capacity. Government of India has approved many Ultra
Mega Power Plants (UMPP) and Super Critical Technology based thermal power stations to meet growing power demand.
To handle more than 250,000 MW of generated power and extend it to widely distributed load of domestic, irrigation,
commercial, industries, railways etc., India with the combine efforts of State power Transmission companies, Rural Electrification
Corporation & Power Grid Corporation (I) Ltd. (PGCIL) etc, has developed a very strong network of High Voltage (11kV & 33kV)
and Extra High Voltage (110kV, 132 kV, 220kV, 400kV)network system. The country has already embarked on765kV voltage as
new generation transmission voltage and quite a few 765kV substations & Transmission lines are already commissioned. While
lines & substations up-to 33 kV are managed by Distribution companies, the transmission lines & substations of higher voltage
ratings are managed by State Power Transmission companies & PGCIL.
Though many types of generators & transformers are in use but for larger capacity of Power Synchronous GENERATORS & Power
TRANSFORMERS are most commonly used equipments. These Generators and Transformers are very critical, costly still very
unpredictable equipments of electricity generation & transmission system. With the help of transformers the generated power is
stepped up to Extra High Voltage [EHV]. While in transmission & distribution companies the voltage levels are gradually reduced
at the required utilization voltage ratings. Smallest negligence to understand the Power Synchronous Generators & Power
Transformer screates great catastrophic national emergency in the generation / transmission system and causes huge loss of
production. Therefore they need extra care, study, condition monitoring & proper decision at each step of activities like
requirement, design, manufacturing, stage inspection, final inspection, packing, transport, erection, assembly, alignment, gas &
oil filling, drying out, site testing, thorough review of protection setting, commissioning, synchronizing, operation and
maintenance.
This program will make aware & train the available `Human Resource' to look-after these equipments in improved manner to
run generation & transmission system more efficiently and economically. Mr. Gurbaksh Singh & Mr. S. R. Chavhan our experts
shall cover possibly each & every aspect of the above equipments in detail in 2 days as per the program Schedule.
Tel
Mob
: +91 9769545325
Sectors:
It shall be a great event when Participants from Generator & Transformer Manufacturers, Power Generation, Transmission
& Distribution industries such as Cement, Steel, Aluminium, Construction, Mining, Chemical, Automobile, Sugar,
Petrochemical, Oil & Gas, Pharmaceutical, Fertiliser, Petroleum and with other large captive generating units.
Meet Your Expert Coaches: Mr. Gurbaksh Singh & Mr. S. R. Chavhan:
Mr. Gurbaksh Singh
He is a mechanical engineering graduate of 1970, with meritorious educational background, having more than 42 years of
professional &management experience. Prior to his retirement, he served Bharat Petroleum Corporation Limited (BPCL) for
over 26 years and led various departments including Major Projects, Engineering &Construction, Materials, Energy &
Environment and Advisory Engineering. Lastly he was Corporate Entity Head of HSE in the rank of General Manager. During
tenure with BPCL, he was Project Manager to procure & install a combined cycle Captive Power Plant (Two Units of Gas Turbine
Based Generators with HRSGs) under World Bank financing.
Prior to joining BPCL, for about 12 years he worked for Bharat Heavy Electricals Limited (BHEL), with its Power Projects
department. While in BHEL he was engaged inconstruction, erection and commissioning of Thermal Power Plants in the
country. This experience was very intense.He was associated precisely with installation, commissioning of Steam Turbines &
Generators. He was also associated with sorting out post commissioning problems on TG Sets. He had opportunity to work on
TG Sets of varying capacities of individual machines from 30MW to 500 MW with its associated auxiliaries at different locations
within the country.
While in BHEL, he worked on TG Sets for 30 MW Parli TPS, Maharashtra; 120 MW Santaldih TPS,West Bengal; 220 MW RAPP,
Kota, Rajasthan; 120 MW Chandrapura TPS, DVC; 210 MW Bandel TPS, West Bengal and 500 MW Trombay TPS, Maharashtra.
For six months he underwent a training programme for Erection of large size Steam Turbine /Generator sets at M/s KWU in
West Germany, wherein he was exposed to an individual machine of 800MW.
The core competency of Mr. Singh is his ability to offer an array of best in class training with accent on real life situations using
techniques like case-studies, simulation exercises and various other structured or spontaneous pedagogic tools.
Mr. Singh is a qualified Assessor for Sustainability Excellence, based on the material from European Foundation for Quality
Management. He has passion for Water conservation. He worked with M/s Det Norske Veritas(DNV) as a Consultant& Safety
Auditor, DNV's Energy-India (Region Asia &Middle East).
He serves as Panel member on many Government & non-Governmental committees. He chaired sessions in National &
International seminars on varying subjects.His passion for quality during installation made him to be one of the co-authors to
develop the first ever Field Quality Assurance manual for TG sets.
He has been a regular speaker in Conferences /Seminars around the world.
Meet Your Expert Coaches: Mr. Gurbaksh Singh & Mr. S. R. Chavhan:
Mr. Shivaji Rao Chavhan
After completing graduation in Electrical Engineering he joined in MP Electricity Board, a very prestigious power utility company
of India in the year1970 and worked as Assistant Engineer, Executive Engineer, Superintending Engineer and as Chief Engineer.
He started his career from 300 MW Satpura Thermal Power Station Sarni. When he joined 3 units were already commissioned
and erection & construction of 4thunit was in progress. Mr. Chavhan joined in the Construction Division where he took-up the
work of installation of 3 Nos. compressor units &installation of hydrogen plant and coordinated with the team of installation of
TG. Subsequently 4th unit of 62.5 MW was rolled and synchronized. There after he was posted in transmission wing of MPEB and
gained experience &expertise of specification, selection, testing, setting, commissioning, operation, repairs & maintenance of
EHV protective relays. Since initial stagehe was associated with condition monitoring of the large transformers and developed
thorough expertise while working with experts from Mitsubishi Japan, BHEL Bhopal & CGL Mumbai to take up repair of power
transformers installed in 220kV & 132kV substations. While in-charge of 400kV substation he attended many emergencies of
315 MVA transformers & also reactors. By his initiatives MPEB agreed for reconditioning of 160 MVAtransformer with great
success. He played key role in life enhancement of many power transformers in service. As Executive Engineer, in addition to the
responsibility of more than 30 power transformers, a 30 MVAR Mitsubishi Synchronous machine [A huge rotating m/c] was also
in service. This m/c was thoroughly repaired & reconditioned and again taken into service successfully.
He carried out factory Surveillance inspections. He witnessed type, routine and acceptance tests of extra high voltage
equipments like power transformers of 400kV, 220kV & 132 kV ratings & protective relays at the works of ABB, CGL, BHEL, Alstom
and English Electric etc. He has excellent knowledge of Indian Standards, IEC etc. He was a member of sub-committee of
Protection Committee of Western Region Electricity Board at Mumbai to analyze and to suggest relay settings of transmission
system [400 kV & 220 kV].
He has excellent practical knowledge of 400 / 220 / 132 kV systems, protective relay testing, commissioning of EHV transformers,
CBs, capacitor banks etc. and played vital role in developing automation of EHV substation. As a testing & communication field
engineer He has controlled huge team of engineers, Planned, supervised the inspection activities, ensured quality procedures,
executed works and achieved targets of many sites against normal development and number of ADB supported projects.
He is a fellow of Institute of Engineers and a Chartered Engineer and attended workshops / training courses on ISO 17020 & ISO
17025 on 'Criteria for Inspection Bodies' and 'Laboratory Quality System & Internal Audit' organized by Quality Council of India &
Indian Institute of Quality Management, Government of India and many other technical workshops & seminars.
He worked in a reputed consulting organization, which deals in `Alternative Sources of Energy' and gained experience of wind,
solar, bio-mass, small hydro based generation schemes. He studied & prepared DPRs for Rural Electrification schemes
associated with Small Hydro Projects installed on canal-fall. He has passion for reducing our Carbon Footprint.
His CV was approved by Saudi Electricity Company-COA as authorized Inspecting Engineer for SGS to carry-out inspection of 5
nos. EHV power transformers and 2 nos. auxiliary cum earthing transformers at the works of CGL. The job is complete.
As a freelance Senior Inspecting Engineer. He is working with Inter tek India, UIS & Inspection Consulting Services and carried out
factory surveillance evaluation, inspection of 33 kV power cables, 22 kV & 11 kV distribution transformers. M P State Electricity
Regulatory Commission has appointed him as `Metering Consultant'. He studied metering codes issued by CEA and submitted
observations & recommendations to MP Electricity Regulatory Commission. He is `Expert Professional' on the panel of Central
Power Research Institute. He has completed his tenure of Advisor (Technical) in Central Zone Distribution Company, MP Bhopal.
Tel : +91 22 6711 2444
+91 9769545325
His latest job as Project Director inMob
K R :Energy
Services Pvt. Ltd. has completed in Nov, 2012.
Day 1
INTRODUCTION:
Session covers general development of generators &
transformers, Progress of India in manufacturing of Power
Transformers, Present status of power generation &
transmission in various states in India.
RELAY CO-ORDINATION:
Generator's Protection.
Generator's Relay Co-ordination.
Day 2
INTRODUCTION&BASIC PRINCIPLES OF TRANSFORMER:
General development of Transformers, progress of India in
manufacturing of Power Transformers. Present scenario of
power generation, transmission & distribution companies in
India. The electro-magnetic theory & basic laws employed for
transformer.
TRANSFORMER RATINGS & SPECIFICATIONS:
Technical specification to some national or international
standards to evolve required specification to procurement a
quality Transformer.
BASIC PROPERTIES OF MATERIALS AND DESIGN:
Design of power Transformer & Selection of material and
design of size & shape of core, Winding, tank & Quantity of oil
& cooling system etc.
DESCRIPTION OF MAIN COMPONENTS OF TRANSFORMERS:
Design of core, Winding, Tap-changer, Main-tank, Cooling
System & important secondary equipments used in
transformers.
SHOP TEST OF TRANSFORMER:
Assembly of transformer is subjected to routine, type &
special test as per relevant ISS or international standards. The
procedure of important tests carried-out at works.
PACKING, TRANSPORT, & FIELD ERECTION OF
TRANSFORMERS:
Packing & Transportation of power transformer is critical due
to its large dimension & heavy weight. Any improper handling
may cause problems like, leakage of dry gas & ingress of
moisture etc.Discuss field assembly, erection, oil filling&
Drying-out process.The procedures of packing, loading,
transport, unloading etc. for Transformers.
Discussion on assembly of bushings, radiator, OLTC, cooling
fans, on-line monitoring equipmentetc.
Tel
Mob
: +91 9769545325
Programe Schedule
09:00 am
09:30 am
Workshop Commences
11:00 am to 11:15 am
Tea Break
01:00 pm to 02:00 pm
Lunch
03:30 pm to 03:45 pm
Tea Break
06:00 pm
Course Ends
Register Now
Position:
E-mail:
Name:
E-mail:rishab@hmg.org.in / hrdind@hmg.org.in
Position:
Position:
E-mail:
Organisation:
Payment Method
Address:
Demand Draft
Cheque
Credit Card
Town:
Tel: (
State
)
Postcode
Fax: (
Visa
Mastercard
Amex
Diners
Nature of Business:
Security Code:
Authorization
Signature:
Expiry Date:
/
M
Confirmation Details: After receiving payment a receipt will be issued. If you do not receive a letter
outlining joining details two weeps prior to the event please contact the training coordinator at HMG training.
Nature:
Position:
Date:
Signature:
HMG