Documente Academic
Documente Profesional
Documente Cultură
IN MV DISTRIBUTION NETWORKS
G. Celli, Member, IEEE, F. Pilo, Member, IEEE
Department of Electric and Electronic Engineering
University of Cagliari
Piazza dArmi 09 123 Cagliari, Italy
permits the best location of generators to be found so that
power losses in an existing distribution network are minimized,
and investments for electric grid upgrade, due to the growth of
the energy demand of loads, can be deferred or reduced.
Furthermore, the voltage profile and the three phases short
circuit currents are checked and only those solutions able to
remain within the range imposed by the planner are accepted.
In order to perform this optimization a new software
procedure, based on a Genetic Algorithm (GA), has been
developed and tested on real size MV distribution networks.
The structure of the paper is the following: in section I1 the
most important features of DG are briefly described, in section
111 some generalities on Genetic Algorithms are provided, in
section IV the proposed GA for the optimal allocation of DG
units is presented and, finally, in section V some results are
shown and discussed.
I. INTRODUCTION
Distributed Generation (DG) includes the application of
small generators, scattered throughout a power system, to
provide the electric power needed by electrical customers. DG
often offers a valuable alternative to traditional sources of
electric power for industrial, commercial and residential
applications. DG makes a large use of the latest modern
technology and can be efficient, reliable, and simple to own
and operate that it can compete with electrical power systems.
In some cases DG can offer significantly lower cost and higher
reliability than a customer can obtain from the electrical grid.
In others, it can augment the grid so that the combination of
grid and DG can provide higher performance than either could
alone. But regardless, it offers an alternative that utility
planners should explore in their search for the best solution to
electric supply problems [ 1-31.
Power system planning involves identification of the best
equipment, along with its locations, manner of interconnection
to the system, and schedule of deployment. Since cost is an
important attribute in power planning, almost invariably one of
the planners chief goals is to minimize overall cost [3, 41.
Whatever planning philosophy or paradigm is adopted for
planning a power system, DG can influence other resources
(i.e. transmission and distribution) and its correct impact is of
the greatest importance to take the right decisions. In this
paper, the important task of planning the optimal number and
position of DG generators has been faced. This optimization
0-7803-6681-6/01/$10.00 02001 IEEE
81
Population
SELECTION
CROSSOVER
Parents
Offspring
Fig. 1. GA operators
82
MUTATION
0
1, ... ,NDG
B. GA Implementation
In the first phase, an initial population of possible solutions
is randomly generated by means of the following procedure:
for each solution a value of DG penetration is chosen
between 0 and a maximum limit of DG penetration, fixed
by the planner on the ground of economical and network
security justifications;
a number of DG units of different sizes is randomly
chosen until the total amount of power installed reaches
the DG penetration level assigned;
the DG units are randomly located among the nodes of
the network;
83
-N ,
COG =
C c o j
j=l
(1)
where N T is
~ ~the number of network nodes, Ncp is the
number of substations, NTorNcpthe number of branches in the
network and C, the present cost of thej branch.
The cost of every branchj is the sum of the construction,
residual, management costs, and cost of losses in the
subperiods, transferred to the cash value at the beginning of the
planning period by using economical expressions based on the
inflation rate, the interest rate and the load growth rate (all of
them constant) [7] .
The cost of every branch can be expressed by using:
k=l
(3):
Coil = ej. . ( c o c j - Roj ) + C0g-j
(3)
=CkWh.(38760.coeffrj.Lj.ccpj z : k )
4k
Emergency connection
<2>
Emergency connection
(4)
where:
- Ckwhis the cost of kWh,
E. TechnicalConstraints
Each individual produced by GA operators has to comply
with all technical constraints usually adopted by planning
engineers, i.e. the voltage profile along the network trunks and
the three-phase short circuit currents in the network nodes [ 11,
121. Indeed, the presence of generation nodes in the
distribution system can cause a voltage drop or an overvoltage
in some points of the network. This situation depends
particularly on the transformer control system used. Generally
speaking, the connection of a generator to a network can result
in an increase in the voltage that depends on the power
supplied by the generator. For this reason, in the proposed
methodology the voltage profile is checked and only those DG
allocations able to maintain the voltage within prefixed ranges
both in normal and emergency situations are evaluated.
Calculations are performed by determining the impedance
matrix 2 of each feeder examined and by calculating the
voltage in each node of the network. The calculation of Z can
be noticeable simplified considering the particular network
architecture (open loop network).
The presence of DG can change the magnitude, duration,
and direction of the fault current. The fault current is modified
since the connection of rotating generators modifies the
characteristics (impedance) of distribution networks. In this
context, one needs to verify that the alteration in magmtude,
duration and direction of the fault current due to dispersed
generation groups does not affect the selectivity of protection
devices. In fact, the selectivity must be checked for each
connection of a new generator to the distribution network. In
the paper, fault currents are calculated for each DG
configuration examined by using the diagonal elements of the
short circuit matrix and the voltages in each node. Again all
those situations which do not comply with this technical
constraint cannot be accepted.
I Total cost
85
With DG
1,000,000 US$
5,000 US$
626,000 US$
486,000 US$
1,626,000 US$
491,000 US$
VI. CONCLUSIONS
DG is predicted to play an increasing role in the electric
power system of the near future. In fact, studies have predicted
that distributed generation may account for up to 20% of all
new generation going online by the year 2010. With so much
new distributed generation being installed, it is critical that the
power system impacts be assessed accurately so that these DG
units can be applied in a manner that avoids causing
degradation of power quality, reliability, and control of the
utility system. On the other hand, DG has much potential to
improve distribution system performance and it should be
encouraged. For this reason, it is really important that
distribution planners can have useful and efficient tools to take
into account the opportunities of DG, avoiding costly and time
consuming impact studies. On the basis of these
considerations, the paper deals with the important task of
finding the optimal siting and sizing of DG units for a given
network so that the cost of power losses during a prefixed
period of study can be minimized and investments for grid
upgrades can be deferred. As shown in the discussion, the GA
developed by the authors can be successfully applied in real
size scenarios with several hundreds of nodes. The examples of
application show that considerable savings can be achieved
simply by adding some generation units in the right position.
Further studies will deal with the development of new models
for DG units that can consider not only synchronous
generators, but also generation units with electronic power
conditioners for network interfacing.
VIII. BIOGRAPHIES
Gianni Celli (M 1999) was bom in Cagliari,
Italy, in 1969. He graduated in Electrical
Engineering at the University of Cagliari in 1994.
He became Assistant Professor of Power System
in 1997 at the Dept. of Electrical and Electronic
Engineering of the University of Cagliari. Current
research interests are in the field of MV
distribution network planning optimization,
power quality and use of neural Networks in the field of Power
System. He is IEEE member.
VII. REFERENCES
[l] CIGRE WG 37-23: Impact of increasing contribution of
dispersed generation on the power system - Final Report. Electra,
September 1998.
[2] CIRED WGO4: Dispersed generation - Preliminary Report,
CIRED'99, Nizza (Fr), 2-5 Giugno1999.
[3] H. L. Willis, W. G. Scott, Distributed Power Generation, Marcel
Dekker, New York, 2000.
[4] Muscas, F. Pilo, W. Palenzona: Expansion of large MV
networks: a methodology for the research of optimal network
configuration, Proc. of CIRED96 Conference, Buenos Aires,
Argentina, pp. 69-74.
[5] D. E. Goldberg, Genetic Algorithms in Search, Optimization &
Machine Learning, Addison Wesley, 1989.
86