Documente Academic
Documente Profesional
Documente Cultură
A F F O R D A B L E
H O U S I N G
Address : 402,Street no 1,
Himayatnagar behind Tanishq,siri
vennela apartment, Hyderabad
pincode: 500029
The light gauge steel frame is designed to with stand dead, live and wind loads.
Framing was installed with anchor bolts 12mm dia. in 2 days.
Mesh jolly is used for cladding the wall frames at day 5. Mean while clay tiled GI roof
sheeting is fixed for trusses with aluminum foil bubble sheet for acoustic insulation.
Concreting and plastering works started from day 8 and continued till day 20
including elevation strips
Also internal brick work for modular kitchen and bathrooms were started on day 8 and
finished on day 20 with internal plastering.
The provisions for windows and doors were given in the steel frame itself. the frames
are made accordingly.
The false ceiling furring channels are fit after the roofing was done in 2 days.
Also the gypsum board fitting started on day 21 after plastering and continued for 11
days with designer patterns specific for living, kitchen and bedrooms.
Once the painting work is done completely, on day 38 Vitrified tiles are laid for 4 days
along which the main teak door and interior flush doors are fit.
Touch up and cleaning is done and the site is left for mutual inspection with client for
final check of dimensions and geometry.