Documente Academic
Documente Profesional
Documente Cultură
INTERNATIONAL DEVELOPMENT
PERFORMED FOR
NOVEMBER 1993
EXECUTIVE SUMMARY
The Jamshoro Thermal Power Station (JPS) consists of four steam turbine generating
units with a total installed capacity of 880 MW. These units were commissioned
between 1989 arid 1991.
The JPS nas been the subject of evaluation as a preliude to either commercialization
and/or privatization. This report includes the Technical Due Diligence analyses that
have been conducted at this facility.
The initial report, entitled Equipment Condition Assessment
November 1991. The purpose of this study was to provide
the major systems, components and structures necessary
generation of electricity. The findings of this report are as
1)
The systems and components reviewed at the Janshoro Power Station should
be suitable for contintied operation for the next 20 years.
2)
3)
The second report, entitled Final Technical Due Diligence was completed in September
1992 and was conducted to update the previous study and investigate any new
issues that might have arisen. The principal findings of this study are as follow:
1)
Fundamentally, the major components and systems at the plant are sound and
incorporate proven design concepts and technology.
2)
The plant support equipment and facilities are adequate in design and number,
although a few prublems remain to be resolved.
3)
4)
The units were built to currently applicable codes established in the country
from which the unit was purchased.
5)
The single largest area for improvement is in the area of site facilities and
personnel management, a situation most likely related to the newness of the
plant and the relative inexperience of the technical staff.
In February 1993 a follow-up Site visit was made by the author of the September
1992 report. The observations are included in this report. Responses from plant
management to these observations are also included.
In October 1993 a third Technical Due Diligence analysis for Jamshoro was
completed. Its purpose was to review the findings of the previous reports and to
provide an update to their findings. This information was required to expedite the
privatization of the Jamshoro Power Station. The conclusions of this report are as
follow:
1)
The plant was found to be in generally good condition and was operating in a
normal fashion for a plant of its relative youth.
2)
One area that needed attention is the recurrent plugging of steam generator
components caused, in part, by the high levels of sulphur and vanadium in the
furnace oil.
3)
A second identified problem was the overflow of plant waste water into
neighboring fields caused by the undersizing of plant settling ponds.
4)
The plant staff has programs underway which are designed to alleviate each of
these problem areas.
al
FINAL REPORT
PERFORMED FOR
INTERNATIONAL RESOURCES GROUP, LTD.
SUBMITTED BY:
DENNIS W. EVANS
JOHN T. BOYD CO.
AND
DR. J.D. GUY
I.R.G.
OCTOBER 1993
SECTION
TABLE OF CONTENTS
SECTION
DESCRIPTION
TABLE OF CONTENTS
II
III
FINDINGS
IV
UNIT 15
VI
UNIT 2, 3 & 4
VII
VIII
MAINTENANCE PRACTICES
IX
STAFFING
PAGE
The purpose of this work effort is to review the findings of the two
previous Technical Due Diligence reports and to provide an update to
their findings. This update is required to expedite the privatization of the
Jamshoro Power Station on a fast-track as directed by the Privatization
Commission of the Government of Pakistan.
A team composed of Dennis W. Evans of John T. Boyd Co. and Dr. J.
D. Guy of IRG Ltd. visited the power station beginning on September 25,
1993 and lasting through September 28, 1993 to conduct the
evaluation. This time was spent touring the plant facilities, holding
discussions with key plant staff and reviewing and analyzing plant
operating data supplied by the staff.
The team also undertook a review of previous Due Diligence reports
provided by Ebasco Services, Inc. in 1991 and by John T. Boyd Co. in
1992. These two reports provided a background and a framework for
the update contained in this report. For that reason some of the detailed
plant descriptions are riot included in this report arid can be found in one
or both of the other reports.
The team was able to observe the responses by plant management to
the recommendations suggested by the previous reports. The team also
evaluated any additional problems that may have arisen since the last
previous report had been completed.
FINDINGS
The team found the plant to be in generally good condition and operating
in normal fashion for a plant of its relatively young age. There are two
areas which need attention: (1) d( to the high Stlphulr and vanadium
content of th oil b)urned in Unlit 1, aind in Units 2, 3, and 4 when gas is
unavailable, there is considerable )ltjgi (ig of many of the steam
generator components iMithe furnace, and (2) due to the undersizing of
the settling porids, there is a discharge of waste water from the plant
inIto surrounding fields.
Normal mainternance activities are undertaken at the plant for all four
units and there does not appear to be other problems of an, significance.
The table below summarizes the Jamnshoro Power Station with regard to installed units
and includes various relevant operating data for the past two years. The operating
statistics were taken from Form E reports provided by the plant staff; however, the
capacity factor information was recalculated to reflect the methods which are in more
common usage in the West.
PLANT DESIGN DATA
Unit 1
Unit 2
Unit 3
Unit 4
250
210
210
210
250
200
200
200
Date Commissioned
1/90.
12/89
6/90
1/91
Country of Origin
Japan
China
China
China
Fuel Type(s)
Oil
Gas/Oil
Gas/Oil
Gas/Oil
9,063
10,254
10,254
10,254
Y (a
A h) l 1h~l
'41/2
12/93
91/92
Q2193
91192
.3S2
10.)4(0
().002
9.Q-)3
9.500
9F2/93
1).063
4
91/92
92/93
95.S5
9.937
RaIc (lit/Kwh)
A% I:lui)
caII t
kIct
:lr( 'g
(1
901
65.2
77.4
59.0
74 6
57.0
55.3
6137
701
48.8
Ss 9
47.0
is'
44 4
38.0
The chart shows that all of the units at the plant are relatively new, the oldest is not
yet four years old. On': '.would expect the performance parameters shown in the
operating data table to improve considerably as the plant staff moves Up the learning
curve and the normal to-be-expected unew construction problems are resolved.
HEAT RATES -- The actuial heail
rato for Unit# 1 is on average about 7 % higher than
wh a t has been described as the; design heal rate while the actual heat rates for the
other tuits are oii average alri rust 5% less tha the design values. The team was not
able to review thu Uti # 1 icceptiace report to reterjirie if the unit had achieved
the design heat rate at the 11011! Of the !st. It should be noted that the actual heat
rate (Jata are calculated tsisg aveir ! operatling data over an entire year, which will
include the entire raige of Linit operations. Ho wever, the design heat rate would likely
reflect a specific set of controlled operatirg conditiois and may also be at a specific
point of IlWLe unil's operatingq cu rve. It would be desirable that each unit be subjected
to a heat rate test to (lt. ri iie the actual h eat rates at various points on the
operating curve. These data wonld provide a better basis for comparison to the design
criteria.
AVAILABILITY --The low availabilities of Units 2, 3 and 4 are accounted for by
extended outages related to r guired scheduled inspections. In particular, Unit# 4 was
out of service for about five monr1ths in 1992 for its first inspection. Ordinarily these
inspections are of 90 day duration but in this case it was longer due to the
unavailability of reguired replace(?iCut parts. This extended outage adversely affected
the unit's availahility in b)ot the years for which data are reported.
CAPACITY FACTOR --The capacity factor results are determined by: (1) the
availability of the units to be operated arid (2)the actual dispatch decisions of the
system dispatcher at N.C.C. in Islamabad. The last factor is beyond the control of the
Jamshoro plant management and should not be considered necessarily reflective of
the plant's potential performance. The actual dispatching decisions are driven by
relative unit fuel costs, overall system load requirements, arid individual unit response
rates.
UNIT 1
This unit has a nominal rating of 250 MW and was designed and constructed by
Tokyo Electric Power Service, Ltd. It was commissioned on January 27, 1990. The
unit appears to well designed and constructed and the operating records bear this out.
The major problem associated with this unit is caused by the poor quality of tile
furnace oil that is burned ii the boiler. This fuel contains high levels of sulphur arid
vanadium and the exhaust from the conbustion of the fuel causes excessive plugging
of the boiler componens. There was no provision in the unit's design for automatic
washing of these components which means that the unit must be taken out for
service for an extended time for washing by hand. The plant engineers are evaluating
the Use of a fuel additive which should reduce the rate of pluggage of the unit. That
evaluation has not been concluded at this time. It may also be possible to modify the
unit by installing an a u toniat ic washing system which has been included on similar
Japanese units of th e sane design.
It is also possible To convert the ln it to burh gas if that fuel is available in sufficient
quantity. This conversioni would completely mitigate the plugging problem. However,
an estimate provided by the constructor of tile cost of conversion was approximately
equal to the cost of an entire new boiler. It may be desirable to have the constructor
re-evaluate this estimate.
UNITS 2, 3 &4
These units, all 210 MW each, were designed and constructed by North East Electric
Power Design Institute, Ministry of Water Resources and Electric Power, ChangchuPeoples Republic of China and were commissioned on December 9, 1989, January
27, 1990 and January 21, 1991, respectively. These units to riot appear to be as well
designed and constructed as Unit II 1 arid the operating data bear this out, at least in
the first years of operation. These units also require frequent shutdowns to manually
wash the boilers wheii bnirninq furnace oil.
These units are highly labor intensive since they are currently incapable of operating
in a completely autoriated mode because of the unreliable instrumentation. The
operation arid maintenance Manuals supplied by the constructor are not as complete
as those provided for Unit 1 aid staff training has suffered due to communication
difficulties. Similarly, riaiiteriince activities have been made more difficult due to the
lack of as-built drawings.
Many of the deficiericies noted inthe previous due diligence reports are still prevalent
and will contribute to higher nuainitenance costs inthe future unless corrected. Some
of these, such as open cable trays arid exposed wiring on instrumentation, could be
ameliorated with expanded efforts during planned overhauls.
MAINTENANCE PRACTICES
All of the units at Jamshoro have undergone at least one 90-day inspection outage
since commissioning. The recommended scheduled interval between major inspections
and overhauls is between 30,000 and 35,000 hours of operation. Tile next major
overhaul for any unit at the plant should not occur for at least three years unless some
unusual circumstance arises. The table below shows for each unit the number of
operating hours since the last major overhaul.
Routine maintenance is conducted by plant staff on a regular time frame if the
maintenance items can be accomplished without bringing the unit off line. A list of
maintenance items which do require a unit shut-down are accumulated until the shut
down can be scheduled wtdho,, adversely affecting WAPDA system reliability. When
the unit is available for maintenance, the list of items is prioritized so that the most
important items are accomplished during the relatively short outage time, typically 10
12 (lays. The station submits a proposed schedule for these short-term maintenance
iteflI in June of each year and expects to have them completed by November of that
year. Except for planned major overhauls and unexpected forced outages, the plant
is expected to be available throughout the remainder of the year.
Unit
4076
3884
5370
4721
STAFFING
From discussions with the senior management at the plant it became clear that one
of the most serious problems faced at Jamshoro is the lack of a sufficient number of
trained staff. Those who are assigned to the plant are required to work excessively
long hours to keep the units available for operation. There is a major risk of employee
burnout unless this oroblem is alleviated.
AddiLirnally, in the areas of craft labor, there is a serious shortage of qualified welders
at the plant; there are only two assigned there at this time. The WAPDA pay scales
for these positions are insufficient to attract welders away from privately owned
establishments.
On February 3, 1993 with the help of USAID Karachi, a follow up to the August
Technical Due Diligence assessment was done.
Met with Mr. M.M. Chandio, Resident Engineer Mechanical and Mr. Abdu Adil, Senior
Resident Engineer Cperations.
Prior to the visit a list of questions was sent to the station concerning outages and is
attached as part of this report.
Things have not changed, plant is still in a crisis management type of operation. Was
told that WAPDA will not authorize additional expenditures as this will be privatized.
There has recently been two criminal law suits filed by property owners and tile
highway department. Was rot able to obtain copies but have informed Hunton &
Williams so they can pu]rsue from their end.
To (late they are still running without adequate spare parts, colony is not staffed,
shortage of vehicles, no maintenance shop arid staff is not adequate to run in this
mode of operation.
The Senior Engineers arid Junior Engineers are required to live in the Colony and
during any emergencies have to report to the plant, most of them are averaging
twelve to fourteen hour days as they can't get in touch with the personnel who live
in Hyderabad.
In addition new areas of concern have been identified and will add to the
indemnification that WAPDA will have to make to the new Co.
A list of these items will be part of this report.
Dennis W. Evans
Advisor, WPPO
//
Unit # 2 main steam stop valve will not close very dangerous, drifts close after
Waste water evaporation pond, original size too small, line to Indus river plugged
Unit # 1 coagulator design not right as identified in original report, can't get parts
Air pre heater motors modification needed to remove for maintenance without having
Units 2, 3 and 4 main turbine lube oil system needs a complete filter redesign.
H2
Units 2, 3 arid 4 24" supply line from Indus river made out of cast iron they are
To,
Egerton Road,Lahore
Phone: 6368790-93
From:-
(M)
TPS, Jamshoro
Abu Adil
R.E.
(0)
TPS, Jamshoro
Reference:
Our
comments on
the
items
needing
correction
at
Thank you.
01
MAINT-NANCE
NO
SliOP.
TOOLS
EQUIPMENT.
TOOA TF
Comments:
Ma--i nt.enance
shop
equipments
required
02.
AIR
tools,
but
RAS. EI .
OR
i t.
is
equj ipped
nt
wi th
equipped
with
UNIT
washing
done
in
facilities
OUTAGE _TO
shutdown.
days
elements
can
However
Intermed ate
UNTTS-23_
MONIH
CLEAN
Water
be
i n
an d
more
4 _I(OT
.&
Cold
replaced
replacement. require
03.
fully
,t.Caff.
REPLACE
Comments:
and
now
is
AJj r
en
1 '5
Preheater
,.:iy'-,
hot.
time may he
SPOTS. NEE()
-h'j t.down.
(Id
el emets
of) e M 0
-.h
T0_R PPL.ACF
IN Su LA T I.ON
Commrient-s
Some
but
of
hot
the
would be
spots
done
are
in
still
without
insulation
to 20.01.1993.
04.
UNIT
NOT
CLOSE
MACHINE
Comments:
No such
05.
UNITS-I
CIRCUITING
Comments:
DURING
Unit-I
have
MAIN
VERY
HAS
RAINY
has
the
STOP
DANGEROUS,.DRIFTS
COOLED
problem
.2.3
STEAM
VALVE
WILL
CLOSE
AFTER
DOWN-
now
&
EXPERIENCING,
SHORT
SEASONS-
no
such
problem
necessary works of
problem.
specially
However
on
Units-2,3
boiler
for
&
-1
which
are
in progress.
06_
WASTE
WATER
EVAPORATION
PONDORIGINAL -SIZF
ro--- SMALl
LINE
TO
INDUS
RIVER
PLUGGED
OVERFIOW'S
INTO
Comments:
The waste
water
line
is
to overcome
this
open
channel
being
07.
UNIT
I-
IDENTIFIF
silt
IN
is
BE
Case
,:
AIR
water
be
and
of
pond
to
If
it
providing
river
is
is
found
startled.
DESIGN
NOT
RIG1T
AS
REPORT._
CANNOT
GET
TIE
10
UNITS-2.3
&
4_
int.ake we.te;
has been
made
accumulated
fully.
However
case
study
0RIGINnA_
TO
MAKE
Units- I ,,
1"
INSTRUMFENT
TO
Comments:
ill
Interconnection of
R ive;
among
08.
rk
w
plugged
consultLant..
COAGULATOR
PARTSNEEDED
Comments:
waste
the
t.he c
not'
problem a
from
done
by
workable,
FARM
FIELDS
s
is
DRYERS
regards
to be
ON
co-agulators,
removed
manually.
UNTS-2.3&4
NEED
REPLACED-
for
procurecrient
of
Refrigerant
type
drier
is
in process.
09.
AIR
PRE
TO
REOVE
I EATE R
FORI IAI
MOTORS
MODIFICATION
NTENIANCE
WITHIOUT
NEEDED
HAVING
TO
SHUT UN I-T
-DONN..
Comments:
Already modified.
(3)
10.
utS-?
_3
VnLVES
Coiner:.
,an
T-IRUST
puMPs
thrust
operation
of
about
mal function
of
gar)
between
lubrication
Chinese
are
carrying
done ,t
one
pilot
,orIle
After
bearings
governing
plate.
units.
BEAN
SAND.-sA
PILOT
the
I1 .
get
year
system
valve
successful
)hi ch
due
and
problem
out
damage
Lo
results
increase
governor
is
there
modification
result,
af ter
buffle
for
on
in
which
t-heir
own
the
same
will
TO
HAVE
GREASE
be
Janishoro-
UNIT-.S-?_A3
& 4
ALL
PUMPS
NEED
FITTINGS ADDED
Comments:
Which
pumps
provided
12.
Comments:
&
However
MAIN
COMPLETE
Addi tiona]
Units-?
clear.
properly on some of
UHITS-2_
NEEDS
not
FILTER
For
nipples
not
the pumps.
TURBINE
centrifuges
& 3.
-rease
LUBE
OIL
SYSTEM
REDESIGN
have
been
installed
on
Unit-4
it
is
under procurement.
Chinese purification plant
on
each unit is also in
service.
With
these
measures
H12
COMPRESSOR
TO BE
Comments:
the
problem
has
been
level.
SEALED
UNITS W4OLE
UNIT HAS
REPLACED
Yes
(4)
1.4-
Unit
s-2_. 3
&
MADE
RIVER
COST
REPLACED
Comments:
The
LOTS
ITEN
LINE
INDUS
FROM
CAST
IRON
THEY
DAMAGE
THIS
COULD
HlAS
-WHOLE-LIN-E
ARE
BE
A
BE-
TO
of
damage
of
interconnections
which
the
OF
IF
frequency
made
SUPPLY
OUT 1OF
EXPERIENCING
BI-G.
24-
all
may
Unit..The
damage
the
not
pipe
has
four
uniLs
affect
length
reduced
the
is
and
have
been
operation
being
of
replaced
with M.S.pipes.
DIR_1EC T
ROAD
EASIER
ACESS.
Comments:
Already
under
16.
NEED
15.
RIVER
Comments:
TO
FROM
PUMPING
FAILURES_
The
scheme
is
TO
STATION
FOR
construction
UNDERGROUND
R-PLACE
OF
COLONY
STATION
under
WITH
consideration,
6-6
KV
LINE
OVERHEAD-
but
TO
__LOTS
has
not been
BETWEEN
POWER
finalized.
17.
SUB-WAY
STATION
WHOLE
Comments:
Not
TO
&
POW ER
BE
PROVIDED
PRETREATMEN-T
PLANT
TO_ CONTROL
STATION
initiated
ABU ADIL
R.E.(O)
TPS, JAMSHORO
M.M. CHANDIO
R.E. (M)
TPS, JAMSHORO
I "
UNITS 1, 2, 3 ANT) 4
FINAL REPORT
SUBMITTED BY
AND
S1XTIION I
'ale of C(IonIt{IlS
S'CT'I()N I
'I II
ON
.l*[I.f)N
III
Ml1(l(\
IV
"rfble of contenits
C\'I' 1.3S.(0
OVEALl. CONCLUSIONS
\I11()
OI
T()IASIk
SI-CTION
SIECTION VI
II
SICIION \II
I?
IKCTION \11I
SICTION IX
ATTACIIIENT I
PLANT COLONY .
ATTAC II IENT 2
PLANT STORES
ATTACI01 ENT 3
A ITI :NI) X A
AIlIl'NI)IX B
17
........
2!
27
or
e t
W i.
Shah !d
I'I .
apiJ Ii
le
I :,Ja
*,,
.
,,I ;
,V:ct
, ., ,
t,.:'lCc
fl.
&h'?
-m
-a I..nI
hose:
l.
;<
a)
'(<"')
,ai
,-"
%"
.T,: rt
,c I .r C!
a Ifl
(
','(
1
a a,
;h,:.
(l
,-i
,. .. ,
,:;eC I "
9l
Il-
eI
(! I
ISI ?:rV
o.(VO|
0!
e
L e".
conformance
'0'
S"
(f
0pc
&rl
ta~-l'_sbt:'
Name
x I-
Robert
of. Short
E.
-aA
.'.
i;,a
. .-- ]I
.lo55L.a
-o
'
Name of
Lnecy.
(Teal)
ESI
Evans
5,'yd Cro.,
"
'
I
r)in'
a.
,:'' .........
- ESI,
..
I,
.:;a
-,
I.
o.-!
Cneigy ,-h.CI
Joli)
T.
Co.
5.
commencinq a13eot.
Estimated period of performance
September 1, 1992.
1992 and compe-ting about
;.
Scope
(a)
.-.
.lohn ":'
Boy6
I.
a-
. C
Term Consult-ants
Dennis W.
If.-,
1.
ChieC of Prry I
Gri ils a.', -R.-si~derl P
sible Advisor
>?.
::
,1IS)
.d
a,..
Ion IiUmb.
c
n t.o i icat
.'.a
"
'
cI,
(.
'.,(.
I
II-
4C.
a, i
.'; G
aa
,)c
.[,.il
in IaI
ushoro
:;i-
1 :".,]i.!
'"
I'* Ie)
i:03:,J
A
& (appro"
._
]. v ,;
Cd
CICier;a,
(c
Jam-'
I ir
o pe r a
ri
1
1 03
iei
i..
'*
.Jla~II ,ll
.LkC2
(-W
i II o
I
,
,I,
(imJ.
T.echrllce.i
l S,L mnj
1. 2.stud.,3,
c<e
n
Uo
01.'<.-t L~'I
)t u
r<~
a!a M.dakIr
(-Ina
the
1 :
I . 38; 0
C(WP
Piocj
fA.hirad,
za-tioi'
c:orra.a;
l e-c0
r or Z: I I L)ciI
(. [
,a
lo-r
pe
..L.['
!:
Poll-, I d
oat t
,h ,
Anqustl
of Work_:
obseJvdati.ons
study and copare j.t;
Examine the axist3Yg pr.esent plant condition-'-, codes
and conclusions
with
and conStrICt.orn documents.
-1
~r
nr
r)t
rl
Ib l ) i; I
rec or (;
i'dc l I (.i,
( m) -' rJ
)W-;t',"
L.:alii
[) 1(-V(! I I. i
'I I-ld
J)i
'r-
,id
ReviLeu
(d)
r'tie
heat
ro
w rit
( 1
' 2F L
l, (
opc-r'!l I
arld pl..,1
i I
u me n z
0
!i
'n..,
t.q
L/aror
00o.
opinion
Alo
in
the
in
a srecia.
or
the ;:
Teams
L-.n
... L.
"!.e
i-_ - contract
contained Ar-fin.c the
Contract
"
"s
..
inl
i.oar
ad
:
sha r
i .lt a
it,:
c-el.av
a d
's
-. ::
.- L.."P",',
a;, d
,n
eaLe ,
Uha z,
i w2
I-t.in
nitioo
Lhou
- Lhe
,:
OlS
i:
I-. lity,
,1
nd
r;
her. -,I
L on
',
J t'05
fVcopCA
n
o
Lt
: -q
'w'1 1I
iU:
C'
fn'I
C Ot r e
:,z
I1i
IS
r
F, alIuate the
nezn t.
I .qi i r
:I .:
r
oc:cL
pn
1 !
10 1 S h i;', beL..e e r
;aLer
1:.
.
,: .;or
ZijOns,
!on,
..
IcI
r la
(,1Cel
I.
plant
ccnS,,
io1
I I ri
n )
evalua(e
c )
2 ' c O[
leve l or
expe lain
::
aCL
a
to
-Studies.
ADp r C.',: -
Stijl",ULed
Chinf
Private
Robert
by
PoveC
Sector
Z.
Mnagqo
(.,
Party
of
Grish
.-'
:wo)ycz
.PPO
Ml. i
--
.n :
osara:
Approved by
Progr am
orm-uI
pet
Val i Fy
t I)
n.,y;n .Il,
,Spec if Icat
iqnl
W'dr
conpi. ionce with
h,I
(
i ii )l~~I
.] '.'c % (2( I
'ot
EvJEIltua
( C)
:*c
ci
l; t
- r,.-'1)
I onc
Manager
USA_1I) 0/PE-N
Mian Shahid
SI1,:I'ION III
OVERAI1. CONCLUSIONS
SECTION WV
A PI R()A Ci I T)
'I'ASI(
Ile ap)proach R) task tken by eamn was to meet with Mr. Gritshaw, k,A. WAIPI)A, M Ant,
A. 7Zaidi, G M., WPPO and Mr. Malik M. Ashraf, M.I)., WPPO hur an overview and
additional directon concerning the assignntCl
The team IOhn travelled to the Plant site wilh
MIr Griinshaw For a meeting with the Plant Management team and an e.xinsive two-day plan[
(liilpment lour wilh qluestiOns and answers from plant operating personnel
The leam then
ievcwcd he te)Oi I froi ibasco
SCrvices Inc., preparcd in response t ( I' I 23 0 ini Wl
to verify plant e(lilipinent and ,),teins
As the Hhasco feport was II ioiths ago, the taim used it as a gU(itde io! (lescription of plant
c'.(lii)liieiit aiid systeis lic (li.scepancies ioted at that time were c:),li,:n
reatl detail tw
deterine which had been corrected since that study. Also, a thorough rie ew of plant records,
observation ol operation a di imraililenance practices, personnel interviews and plant walkd ns
were imtade to dee'iine if 'ainy new conditions or problems had evil ed
The coitib intd
x l),rence of the
t
amie)eeit
mitore than 55 years in virtually all phrases of j)arating pow('
1)hiiit.
This hackground prou\ed helpful iii efforts to understald thAnt c;o s
conitIiOlS observed.
f indis\
l)uring the 12 day plant visit, Uidits I, 2 and 3 were operating, and Ui in' v.as on lof sCrviec.
for the First annual inspection oh coinponlents by CMEC i)ersoniol. While ;he team was oit site,
they obser,,ed a forded outage when Unit 2 tripped from 180 MW' due to low vacuumn caused
by a failed turbiine drain line. The team was able to observe the operator response, maintenancc
activities and rein to se.vice tirocess. These observations helped to crif,, findings froitt plant
record reviews
Ire taitt alo went beynnd he ,cope of equi pnent technical due dilieltce antd made 1t
Ii0timiis
it other )lant areas. A thOroulh review of the eml)loyee colony was ittade. Observattons on
)hant acilities, toolin, rollig stock, personnel issues and practices wer also ,atlliredI '[li
reirtindei of this repor will save to docuireent the Ltean's findings and tecoinlitelidatotts otil tre
technical due diligence iii response to CWP 1.38.0.
Included as attachments are gerreral
continents relating to tIre ancillary issues.
FINI)INGS, (Wij
6.a)
6(a)
uJNIT IN(.
I'RI.-FNT AS"-.MIKNT
;i have
All weals vlcCreCTlaCcd
Kid
aII
3ctlo
Yt
performeci
(:ondnsci
Scaling
has
Coagulation U:nits
up waler [or
entire plant____
Tube Lcak
in Lcorronizer Section
.al
eInssei11rlI[
UJNlT NO. 2
ORIGINAL ASS EM ENT
___
l)Ccks
i'____T________N
i:nalItenalice oi 0is
B (
PleUl atlC Tit drive Io crn r I,.
and D out of Iservice
tle io:.,
H-ydIran I
,\5,eIf
occasions.
Preventive inaintenance
was told
application
iiotor
iew/dillerent
installed.
problein
ORIGINAI, ASSEMENT
AuI liilti will not operat
in Aulo
It01(
I:l(
Watr
l t l'lukill
TIn!)
,id
-I
immediate attention.
This
problem has been corrected, and
all systemlis are capable of auto
operation.
Coaguilation1
(Manual Operation).
Trialili
date.
protection.
Single li'ha;
I and 4.
Temperature
Controls.
In Service now
In Service now.
Service.
All in Service.
toses are
available at
All Fire Base Cabinets (to not have Fire Still the case.
the fire station.
Hoses.
Still the same. No apparent problems
Power Cable., instrument cables and
vet, but should he addressed long term.
ligliting cbles all in same
cable trays
and ducts.
ORIGINAL ASSI-'
ENI
may even be
Better hooisc' cpir,' rxlJuirCd in
w0I sc
jthi,
aire'a
I0(
SLC'ITION VI
IINI)INGS, CW'
6.1)
6(b)
lellance
ininf
l'eveli\t
e klaiilei' ice
There ts IttIle or ito prevenliVe maintetance on the equipment at this time. Although
many people appear to understand the requirement for a formalized program, tile mait
focus is still oin workini trouble maintenance jobs.
LnIi2 Teltill Relmir Pr..jLra mu
At )resenlt each of the units have undergone an inspection by the mann facturer after one
year in service. This was part of the contract to construIct the units. A request to make
a scheduled outage on Unit I for 30 days and Units 2 and 3 for 15 days each has been
made to WA PDA. The.time for hese outages, if approved, is October and November,
1992. A detailed plan of work to be done and verificalion of spare pArts availability has
not been madc. No plans were evident beyond 1992.
II
S<E"' 0N \'Il
SEC'I'()N
IN1) IN(;S, (VP
6.c)
6(c)
lvaluate Plant Systents to veril y pel forlMiilCe ISIi coltipllance wIth ksig1 specIficallons.
Evaluate tie potential adverse impact oI both financial ,cquirements and plant operation
W!A\ Ice.
The calculated average heat rates for each Unit was Used as a IasiS for evaluation, as
perlormance tests are not run on tile trn its. From annual :orm E data, the heat rates itn
UNIT NO.
AVERAGE HEAT
RATE
2284
2363
.79
2584
2418
+,166
2584
2392
-192
2584
2414
--170
FillI datd 'ulo indicate Urtit is opetatirtg ,,ightly %ll Illll desi.ll, antd Untits 2, 3
and 4 are operating beiter Ihan design. However, the conditions for design are unknown
(such as load. fuel type, ambient conditions, etc.), therelore it is dilfficult to iraw any
ieaningful conclusiorns. Tie team would recommend each uudi undergo a periodic
performance test at design conditions. When this is completed, an estimate of finarncial
impact cart be better calculated.
Unit No. I has a six cell dourble flow cooling tower and Units 2, 3 and 4 have 12 cell
double lov, cooling towers, temperature was greater thanl 1001: when observation Was
made and circulating water ternl)erature were running 730TF inlet and 76F outlet.
The control systems on thte lits n.tuin rig were ObServe( to be operating in tie antonatic
mode, interviews with operation staff coni-rmed (EC) electrical hydraulic control and
the (CCS) coordinated control system are working properly. Units 2 and 3 were on gas
they hiv(:
c
lfl IndicateI
I 1i1ii load
nlerg dic.'l
in(hicaieC ti
'eraio
oiln
Jlirs
illirc;d 0il
%iccesSfully.
IJiiii'% 2, , , ( I
t;i [ih s point.
Ij
l ijn
.ei e
iiie!,
i i li.i
"c
S ICTION VIII
FINDINGS, CWI' 6(d)
( (I) IPlan ol)eraltios, availalliliiy, p)erlormance, water chemistry and control and Instrumen
WS ol atempts to iilpiove.
Fuel consumption is also an area that has concern only to the extent the storage tanks
don't run dry. There appears to be no effort to focus on reduction of fuel usage. This
area is one witlh a verq high potential for improveIlents, as wise usage of fuel translates
directly to improve hem ras. re sulting in a better financial picture overall
Water cheilistrv and control appears to be adequate. The pretreatment systems all
fuictioi per design, with some labor-intensive processes in place. The result is an
adequate supply of silt-free filtered water to meet tile needs of the demillleralizers, cooling
towers, plant service water, and colony constinlptioil.
iaiil
v.o-d
variable feed rates adjusted as required based on laboratory water analysis. In general,
tlie water chemistry and control appears to be il line with prudent practices, designed to
prevent boiler pressure parts from early failure, as well as protecting tile turbine from
early stage solid particle erosion or later stage efficiency-robbiig deposits.
1H
The instrumentation pioblcnis all appear to be on Unis 2, 3 and 4 All of the problems
appear to be solvable and well within today's technology. It will take some time, money
and foctus to bring the inst ru mentation an(l controls systems o a desirablc level that
would he considercd acceptable for ciniInued reliallc opcration The problems can be
ilioken down into five main areas (I) Design, (2) [)ocuimnlatioii. (3) Construction,
(4) Pci sount. and (5) I'raining.
Instrument air lines are carbon steel and have rust and plugging probleis. Some
other menial tasks. Due to the excessive hours worO:ed. 110 One is available for
call-outs.
SVHC'rI )f\'
6. e)
levels.
ketiril all
Contilue i)lOgi aii ofl marking wiring terminations behind BTG board and im
cabinets.
Repair sheet iieial lagging oil No. 2 boiler fhue gas duct work. Reinforce pop
rivels elsewhere
Replace bi u
Repair boiler t,.ilny cracks causing gas leaks and hot spots on No. ?. 3 and ,'1
boilers.
Investigate boiler slag build-up on Unit one superheater elements and formulate'
l)lans to desensitize the effect.
Perforit survey io ensure adequate spare parts are available to support
inai ntenance progra n.
Continue efforts to provide as-built drawings and documents oil all equilpiment
Theleamn also feels, ill tIei r opinion, there is no significant expected condition that woul(
require JPC to mainlain a level of' financial reserves greater' than normally expected.
IIT
CN
OMMINIATI(N OR
IIC)
RET
CORREICTION
Units 2, 3 and 4 have majol control
problems on coinhust lol control,
sieai letp controls ald
f-fwI c r/(IrIlr
I vel (0:o11it'1
*
6
(A I1ROX)
120,00(
65,000
, ,.000
0
aid training
Provide shielded cable in
separate conduit for all
instrument signals
water.
i6.000
48.000
hInstrument air
Pre-treated water
35,0X0
35,000
*
*
*
Demineralized water
Hydrogen gas
Emergency diesel bus
Service air
35,000
35,000
35,000
35,000
unit relabiliit
15,000
I'")ONI'NI)ATION I"(OR
CO)NI)ITION
(O R R
N() loririal miaintCnance irograin
hwymid n~ouleh resonse
TI'IK) N
(A I1PR() X)
S
*
*
80,000
for
it stall ati on
and trainillno
Only
Assumption
thai hardware
and software
have bece
procured and
are available.
TTotal Approx
No additional
cost, as
positions will
replace
existinrg
posts,
50,200
677,000
AVI'TACHMIENT I
I'A
0 NY
.i"'
The plant colony is adjaceit to Ole power slaltO, located north of the RO unloading facilities.
The purpose of the colony is to provide adequate housing and living requirements for the plant
employees. The concept includes all necessiies; however many facilities are under construction
or not yet saffed
The plant colony is about 25 30% occupied as of this date, largely [ie to the )oow facilities
available The majority of current residents are plant management and supervision, as these
employces are given stroiig urgTii to live there The rest of tie iiployees live in Hyderabad
City, or nearby villages.
San tation is ver) pooi with sewage dsclhiarged IIIo open trenchies, and no rubbish or garbag
disposal area. 'here is no l)Lblic transportatn i for [ainilies to travel for school, shopping o)i
other needs. There is a hospi:al, college, boys school, girls school, post office, bank and market
area for the employees. None ol these facilities are staffed, however, and are not available foi
use by residents. There are plans lot iecrcation facilities, but they have not been completed
There is a bus ava Ilable to transport workers to and froii the i)lait at shilt change times.
The potential for the colony is very great It should be completed and cleaned up soon. Priority
needs to be put on hiring tlie proper stall t open existing facilities.
A'I I'ACI1\4ENT 2
PIANT STOR I-S
I'
I [)I recqitc ld 1))y RCsident Advisor cvaluateci Ilie stores department.
The plant has four large warehouses on site, esimiated to be about 3600 square feet per unit
They are in tle process of seeing tIU) some control. Observe twenty large containers not opened
that coniained spare parts for Unit No. I. Was told by manager they have only received
appoxiIuately 20% of the spares for Units 2, 3 and 1
Appears tile), -ire handica)ped by lack of trained stores p'oinncl, no inivclllory control and lack
of cqipment iIeeed !ohandel large and heavy spares
(o;stiiinables
for everyday opcaioll u a large powei plail were not avalhibhl., they purclasc
One
Stores is res)ollSible for fuel accountability including unloading, indication this is talking a lot
of manpower.
Conclusioni tiley have more than enough storage area, addition of an invenlory control, some fire
protection, equipment for Iraiisporti ng and training is needed to enstire plant is supplied as
required.
21
A'I'A(C[IMIKN'I' 3
%I'AI,N(;PRO' OS \ I.
,1l(
Pla
tllC olOn y a~ltI I
operations actvit
lm
c,:ratle Iroin
,ilnld iwtsl
" ,
\!if
lai lli
111ct1C11o,1
Procurement, in venltory
control and fuel sup)l)ly
normal plant operations and maintenance;
rmpIC:
":llrdlC
ar
separate Irol
Ii ;i l)lant oelratron,
,.
wi bc
som ie
complemi.
Since the proposed comp:leimlent is about one-third
of existing
I am
training.
is attrition through
required to achieve these levels. The key to this transition
proiposal to reduce the laboi force,
but
aware of the sensitivity that will necessarily accompaly a
it \ ill eventuall' be offset b imlprved employee net worth
_liOn
)OF
.O
DIPECTOR5,1()
1O
Ic
EYEcuTIuE
SECRETARY?
PVmAgl
UP
PIOCUR1EM
l
EP[SURCES
A IllU[IITORY
SI
PLANI
VP
OPERAT10 6
FitNANCE
II
Un*tit
?tb
nairtn;Cs
'L
oi t;
0_..J
P:I t
LR :,r
* triat.d iplot~
Ech iv.
4
Acu;a
ln..(.-I.flow
PI..,ic.
lan
()
3tt Eous." .- .
'l;.lt
'" ,.
rh.k f-t
..
i
t
IU,
,
(,..
,t..yr,
23
UP PLANT
OPERAT ION
ARA~ i
I ~NS
'
8E
OPERATIONS
A I{ E AH E
SUJPERINTENDENT
SUPERVISOR
(IiII
itmi
*
I
SI
i t (g
.t;i:ords
i i t .,
-1 *CC,.I
Sro..1r am
(~
,: . :.,,
,
.1
,,,.,,,,
Li
SKAINITFHCE
SUPI.
IASST. SUPt.
]
ASSI. SUPI.
PECKNiICAL
ASST. SUPT.
ELECTRICAL
ASST. SUPT.
IISTR/CONTROL
PLAIiI,,GI
FACILTIES
Kn
!.c.~~
'Intr
ItcIrt
OPERAT I OHS
SIIPERIMTEINDENI
Ii-,.
T&1
L
_1___
OPERATOR
IRA 1 IIMG
ASSI.
AIOOPIis.
OPHS.
ASSI.
3 A4
SUPERUISOR
...
.. ..
r
i:
(I
I~I
i~r
,:r
:,6
APPIENI)IX A
aeater
Src;e
.
, ,."
of
'ilce:
j;/-1-;
No. 2
I
.stuct
1er
on
Co
~-
Group
3
Gp-ou: >-IcA..:O_,N
Ai
",j...
2 s%3-LF
- -
'-
,
.
C-N
__
..
..
.L
",.'
/
____.._-..
_'
"
i
r t
L_, .
& Technical
:ceptanlce
)des of glecr'ic Power"
n5tructiofl
.....
for
'
":'\
-.
.....
B3oiler
IL.."Ji
.....
....................._
.
.......................................
m
NG:Sb N
.-
H:- b :'.
..
"
~L~TR1
e r.Pc t ion
.
NJO
OAV. Ifk'-
lT
i;n,,I
o 'En
/-oq
rW
ACIGN-
POEA~CONSTIUC71Ne
of co l1 ' relda t
ste a - p fpin g
-
C~b 0
UA7~
Sep.i
AA
acc pt
mc
as
'2/
..
d c
P'
................................................................................................................................
d-rawin
3,,-
----
acceptanc
gi
kep
kg/m-I_
kg
Z717'
-.
--
Moealc
or5mn-te
olaocwifud
z-~tc=w3rnz
---
st
the~~ ~
requirent
a ~i~oCccz
~~~~~BS
aea
E rz
~~
cx
L u
A-ae
S No.
'rullltr
eficiency
,
Frqucnt iroblem%
iicuinjtlAC a;ltuJtir -- I
Ircmpoal/Rltit'itif dalin
Ci
EC"- .,
I liouaufaclulcl.
rklorl
lvctgwdtiiil\ .11(
rtit~ciI/tlei
III',
Action by
CE (O &M)
that ic lugg
was due to the
Ol'Coratlin of actuator
qridili i1" theertall
el lrii
11ild stel
to stil.
III
assOCiUtII
wilth CM E:.("
IFllst cirm, I
cill~coll Iil
bl to (fl d
;l i
I 0
od
sslc. 1,
"
The
29
.57
S No
Ir-r
e' ic n "r
InIP IC
I/)ei
Owi;rliy of l1151,icnrial
, o)l l', ito achltlat10 % i% no{it
lI
.,larrcps
1de
iiiadl
ill
tllosec on Unit?? wi
qualily of
;Ill
Jalrslh
asociationi
Il)
for UJniit ? it co hlit
(if
COipleCtui due- to )il availability
.ith CM [1(
must risuirc
cOmictitoi
uill
',l ii th'
Shut(w(
itfirirni
oh
TIi,:
s pplirci by \byVAlII)A
e'irhliwued-i
wui'
hi
(:o1iri"ilittet
C ,41-( tih;it conier'r g' in d rt Lilirlis%
should tie
air oil
Inmt
i l l
l1owever
lo l l
UnitIl
stipcl piin
(T". (O&M)
A cti l n
rt Sr(
I
l
ll ( ;ltO
I I I Ii 1:
(I
il'!
tei C I,tt
stec i
(t
enrsure coripletlo
I)'fcctrve cl.'cocillu'll
ire-;icrf
l li
The Co- -rti
htile l
ilstmet
I ill te
carltl
'lers
of Ite rrt
'ene-rator Iire.iril
Vil'r.lili:1 rcc
cl
ltI
Coniiltr
uuS l1 reicit
Ti1
liew
rtr'gLItl
(OlolM)
l
o litir
lurilih
Icailite t ill I
tei required
meters iy cnt
!
replaced in tire office of GM Thcri
l
remlnt
eic
iroi
Itheir
of
ent
for i rrantell
Of Oc't 9?
I
CE (O &M ) ilia), kindly bc advised ill
.tdy the inodificatOlnS%ploprscd b%
viihr
tie Cornlllillitee ini .stICs ritI 5 Witt
(E
li1%rit ctioi Io
hi% staff
tor arrar-i
rci
t tt
ilz
.i*.
i,
.,
'd th.!i
a ll
suchlrititle tire V'rr rr l.eofd ,rsi"
replaced with licel qualir tire P-r,71
Station Matrere/p~ii~t--f
Ow.itcb
,; tir"
.,hiuld k ,.tll st ret
viliratrort rc hirr's in all tieix3 ililit
Porl.blte Vsiratrini lirte
lay tir
I
1
i ,wd
. ...
(O&M)
Jarrtshoro to
"'Ir Colililrii,
r cr t\pe
reiC
)
d to
midvibe
(O Mi ira)'
Pik"
CfutdiCE
Stui)dy tire indificalirs11 Irlnnps d ill)r
tire Cilllitute in . issi ,,iil wilh
t i ucin i~ i :
C tMI T.CS lj ec.ii sl
specification annd illicrr itinril detill,
tle l iht
I e ira c
Unreltable tirio
iLlI
ie ad' is d 1.r
occessary
S No.
l'riiji(iSa/lRC-liikV
Overlhratiri/ulO~iiiiig i,
'
Col if Iihc
hcrcliroyldfa,iit
n
,'0. r{,
Iresent St ts
C0 iie" tilo
iii )
Pr iI I In/l) 'fric
to Mcliaiiiel goverll
ction by.
.....
taken
"
their
viLL! ver,a and will %utmini(
ardillg
t l
of 1lic C( 1iiriirliik.
by
end of
Scpteinlrc
proposal
solve tli%
hi'roblei
inalt.lurin
S{ofart CM[C have
dIown, oIn" l 9
syseiri :iod
truwt
CMC
govcrnor of
1992
xcep
lie cond
1r11111
Irforltil that
(iitlet%-llfal|) Ho.iwever the
i i%
tivericJrtiiig,/ hIwririii i l I :1 of Unit
and
lidilc
is mtill
that the.
ilos',.l
e
lla
Icy riv
by 31st
ss'uld suitIriIl a dtiill lk )ri1
',study
July 1992
,oni:
places flexible
('N EC .
l,'S
Ciitillte
I
t:os(.i.I Ill IhI
r tlie,'d
tlicrlol
*
'
itL- wih
cx it is ll'le
(1s Cl 1.
I
, .lliCIC
e iw ll le :Likcii
ICIII'ri .1d SiniLlf SI
, _
00 Ul'2
r . I.I i
ii
IC
lup icr
anrd
d
1 g % lin
of:
C~rrf:l:
fin
tact:
tion
%nstro
IIg
Iris staff
keep strict
watch
tu;sth.Ms~Ius
SrL.'
Ir
Z Cr
riire ardin
in
I li
Ill1iitrllart'e amid
CM EC will
I.;ecialhsts to
deirolnstrated b) C\[C
id row%,
sta
tice
11ai11etia
\VAPDA
Th," CtiIIrlItt.e
Ic.-clihies.i.tslis
ietr urL~ik,
hI
rsitirCnerdC
d thl:il thre
Ir.rcilLced wstt
iit s
ctrttitnettts/recoitnieitd:|tii\s
]titlc
rsfaclorli\
tlh:it
CM:ilC: infilillild
i,,1,dll
iii In
yI Sill
1912
CE (O&M )
!%fit)
ilh;,:
: 1 . ..
,:tls
coordinaitt
ChilF.C tllprovide
job with
CMEC &
1992. v.hci
ii:HIImtcnIIcc ltaft I Aui..;ir scat
site,C 1
rihl
t
tleli Speciali
irfori
(O&e.s)
CMIIFC
310
ah
Jiishoro
arid pro:ler
lt
requircLitii 1ous
ritarnlnrce
Job attended
by CM EC
!i% attendril
tile
job
ituirelts
thce..'i!
o :r
alsI b e:er iade
;I selilmii
:I
by CNI FEC
i." hil
____ll
Ioh
.rill
.N11-.C
ceaur
ii thiiit
iiiral n I h r
iiiaill
JailisOro to
on
2
rave
Sorr"
1)
2
lit 3
reoccur aga
lChl.bilmt)
lI11
..
progress.
lI
lit
+No).
"'
Pr
Deic'
lieml(
I)
+I'IObiltvil
iiihit
.ql
.i
o
!wiI
" "U
II I e'lllII
iI
Ill
Pre
..
to irovide btitr
+tli.
i
thcIinicOIIIi:
.with wells
r rCvxtessjafy
ehve:ie
anid
iltndItior./+'a/"i.i
M1 1 ("Nil:(:
iiI.ililih
ss'IltI
,%iw il aciuil l, litllli\
ii*cd
rc
art,
ilic'riiiu-"ll
1
tu...on
"itlh
alshOl-o
"2ugCthlh
"
hirc
ill
CIF (O&M)
%VAP[)A
II;I .
i iil
St
....
en
iinfrmairlntloll
tltC
under Upcraifion in
cnillt-:
Thlc
.
\VAPI)A Systcn
clslor
l it I [loilll;c t)17
C~iiIIIIh;tM/ctl liht
l
CoIIIII 1mIi(-'llll
this jii
On duty On pursuanl
operating taIf.l
of thie CoitiiteCe CMF.C dcsired that
LJii-it4 duiil.
Is fir
irl
lrCCC.sary oi low
water/oil pipc Iies
therefore pleas
leclally till
timgrti
s m
C llahul
generator, F D
hai a:i
th' 11;1e
CMEC iave iforimed tlla!
already carried outl licc-,.
CE tOtsM)
Jailllorit IIliist
IfovideC it:eh
Sreh:ilihe aiid
of the reqrtii
s..lillfs III
1992
t cuel:
SlmCCi ll
''i
limlt
However lie conitnitce
ild
fCCct'tll
feed IputipiIS
ii
ciacier
scdill.
e
Ii'rrib,.ii
Iciilpe r
C l ll
CE lOkNi) ilia
tic idvs+ to pro'ide
II
('M FC so that
thcy ailny
[lower plants
old providt
lite rcquisl'i
It
that
Iics
scli
'rsare riot
ll
f, r re
Cod Of OcL
i llit
I': uro
'tuuul
Seeiricatiii
lnt
and transislor'
CMI+C -! re Iito'sc:
rcqueietd loipro%!,
lit' .ry
eer alth
'
sp1N'
laiitare
';::e
qu.alYir
Probleiti
indicators fr
Ilhevl
Dcrri
CMEC
(
. 11)9
i.ilcldtiiiln%hir15th J rllr
The
w iqtuir
\cill
providirt iclhlr:
tas.icnd
iit
ct
iC
l
foil
olhilw,:. I tis
liiil.
'llr:,ll(
, \
19)?
required
32
hi
I'
irleiri
end Of ScpI
S. No
Pull im
II' 111hlq/De'icleWnt'y
if Isnisictaii
Iit.
ici . l
11I
II,
"( "
(+MI
M/.
(IM 10 1
iifll+ts
agcd Ihat llst
iiii ha 1 ics
1C i'111
I
hdhii'
x
%1li(.'ji'l
1/ Ni/% (4MIz
i th
ark: cisidtic
rlig
tXl 11 i1
xiillriocoilfles
csleii'
p olcO._
li.iciltslloc
lulrin
tht lroblei
is
tlue
fcdl
onnictlmrlm
mmit.mll .
i'hck
(l
alcr ni
on HP exhast
,Ilc
WAI').\
id for curi|
m
h
IPelie
thcrtnocoulic
by cod of Oci
that
ull'u
iill .I
arr; I
ti:it
lllwiili
spccificattiii
of all
1992 so
.
(if -- hiii
)tler qualit
thferrrnoeir il,
kliih tic
could lie
in;ide
b clttlr
C
.
i, ,
;i,i c; III C kiE(
) m.+ay ilhcrelurc
take Icese
13
ni
afte-t
did nit.
;luld I',
tjiii
(Ok.
run
uils,,
ch
w lthC MI (
slio)uld c'llhi1
i11ittC
,c r li" i it
cc
n c
r1%
-l.uc i nt if bttler iu.lri'
11drCIrly
thi1i
Iby,
lrhr.tl,i trduier ,turk
h, ::ll in if r ,asurfIir hii:ir
,i
.r
I ihi,. . . t~i uumiu,.l by their ". u;mh ,t
,i li Il il-: .
'
lih -c
CMEC [3ijriug
with
rc~lacciiit oif 1lhr'uilcs
c+l.sl(jcfrd
li
u
ui1ut
tlI'c
icd
ni lsruh
1
.IIS
Unit
iide
thtie
they IIc
11arlc+
ilill+rilniciwitlds with
In tile
lic Inproveid
on
Action ht)
ti e s im ila r tytic
.'c
if
ofi
I'r-eent StaLtut,
replaced c
" . 3 I,
L,, Id 11,1 ti
I| iqtlit
. ,* .1 rlj
nm e n
+'
k eco
il
,J'
ti
'nl
CI. (OKhMi
Jainshlno tI
s crisi,:,
that tit:
4
:.ulrd then tll
Cormrirttee first om UI111
Unill. svlhcnivcr is pio',ildlc
proposed
teinll
record,i
lieinst;illcd 1,.
CMEC
specially oil
Unit 4 btefor,
end of INt
111+.lic ."1111
r, , ii ;ir, 1 ,erl
for
l,,riit d
of
corp+ci.:itlmi"
'","s
iprike tile %
I ,; oI tile
M4
Iw it 1
lrdilcin
dclc ,
l h:\ h
ii
k'lciml
Job Is .lhrrw,
coltlitlect i I
CM EC
0";,
rrs oitdi'i
ilittss av:il-ablc
sor,
I 'I
l)iil'crc',iC
rcjedii,
ir
Icvcl tdc:itrl
ii
unit.2
ii
tlh:
.:C
MI1S Cm
lt:r,
iodcr drumu
slic'ally
Ito
tii.h prolem
Unit.
tol h:itll
lhrec'r
ru;|gau
L
I
+tiler'Ilcm
coniditiorn havc
Aund tlIre
iiIrI-'ivccd "11srdcr\ilV
Job Ii,
ii':llltld
iplo
h111 C that it wvill oIt
h';ms;uge ii
furtlier with tieC
and their
33
No
N
idrltufi~lIIIII
No, plIIIP(
101
lll
on ontol'
aind dfI(crcmi
I, l
iiII:IlfsI
cxIlin
oi'
It
f11
I'epl~Ico
Ivm(rl
i'-ben
M/S CMFC
polt
w~~ll~
sIlIoi
-'
5l c 11thIIc1Clfiny
Icloil
1IilMIS
COI" 1%
of
IfrawtIng"
CMFC wcre
t of as
fi
suiicrfito
a)
b)
bilt
wvork O( 111
I-be
Regatrlin'
i,hil;1
n till-
no1
lool.i,~ 1i.1
agerncy fcC
(If L
Si~
l01051
CIIIIfiAce 111'
el'
nimediitr
adill
rqga rd
0L:1.11t
Tile ltoil
Illn
~'
CMi& 11111
opti
I
)od lbyfend
1992
W ji
20
i-ell.I
Ins"ItI
c~llf'il~ll
Stamie
.111
MYIS CNILL w~iiistdtigll
of
IIC
(iiIa
~ctiulc
(MiC
foil by
c(t14C
%U1,11)
I;4c
iI
iit:lfd
fl p(WIcV'
IniJW.lg CMfC
;15 I'll[(11
ofcI1IC:1lon
001
in Chla In pIIovlfel
ClosvsICZ
III)'
theylI~
110miRc
~llho:
li~
1
oil Um114
and
11, J( lo darkin,',
mnodiFied
%YAI'D)A
I
nill
imiil
el
1
that \VAi'iA
rcqocfIicdl
slil'iAti11
.
giv
proper
samet
.iI'tI
IldIotl
34
til
NMle.iaiicnt 1
.sNo
jRipid
Pr ili
Prfi i
(t'i i tilm'
ii ul C
cll':M
and li ci cioiig
1.1'
icipcrlitirc
t1011linc I', lt onnrv,(h
c~v,:rv %lilt(down
il
CMI
to stdy
St;tis
Illilt'
l
regard1i
it ii\ ....
i t.t.nillillli.
ititilc f.mlild i
II.Icc
laipid Ilkic~ iII
hot reasnuifte
tvillpcrllur diffcrntiatl (if LI, iasm, i,
not c-n+rinflllit y howeve
iit
il
ils
.3 aniid 4
tliito2,
'(iltl
iliplc
it
ii the iCtcii i
(lilt
carry
oi f tJliiit4
iulalliOll
If reqiuired
Action by
No
Ni (CSO/1 2791
Iclc
,
C head
(M (jicd I 6 9? [oin (from
which it
ofticc ia 1icr-i re'vcd ili
[iriimcd that tile
pIrolihemii of diffc4cnci
iifteipci
ill
t
hiric
Ilic iiiiittc
nlillcili pcI,,Iq
di
iil
itolcm and
Ihcy Ioul
a
stmtlil
(dctaiild rit+jmm
ii tils
lci
l2
(; lu di:
tihe
fctlerli
"
or
(i'fuitlicr
itire
iriti lii
ltudy of lilt.
" 1hc\
iowever Ciii utI.l
Of tile
have checked the Iitsttiliot!
Tlhe)
ocation0 0i
t3sigll.
Itrtine
OK
tlerincotiples and follud tlillill
era're betcei
TIic dfferctice of Itlie
upper and loier flng.ie ort iP and 1I'
+
llctr
c i
turtiile isnot du t cilhcl
.div.It l' tLCOtillic
or
iilof
i1 tatlil
Is
till 11it1:11uhilll oi the i Wen:tliii
acllhived. CE (0&M) Jaimhoro Ina\
, .l
ipret.+illuyilr
ci~;'liltc
of tile11
miid "ttltlliili
tIli,:
i olfh
inding of thiir
tcrcloic iilllorint-d
an
,l
I1% uIhitloll In
.',ti.
'I17 iili
wvhlichI% ,iko,
[ic
CM[L1C site oi-
tilil
,olvc (him
his
,.-i ,,
.i 1'
CNIMF(
slon+l-'.l
1id
t,',:4Vu "il.
SN.
l'rohlirldcitI1CY
Drain iliCs
" ihan
Ir(iftoslll((itiiiiet('ndttiis
.* htlthr
thi:it such
,t.,+d
1'..4. CMIS :
.'
hey
(I occur
of (draii piteleshoul
ol rIIIIriItltei: arid
"w. (1
a,;rct-d ,wllh Ill,
Htt.,1'
iii,,,l~ ftdi'-s-i,
strain lipinglii
tirrjirciiily iuis, I
tljl.,hthy (if
11
, ,r1icriall
svr1IIcivcigaletd
I roper claiolnigp vill litP
Siifll i'clt
,-,r.litio'i
Ih,. c.XitrIII
hL
li
Is/S CmI[C -Ill
ten grd will i. rit.ru.t tlc cq:l
dc..
I santhill
ilr., \,
They
willl
end of SqIt
1992
,s.
It
ato
2socatolln
with CMI:C
init
i will tic
to give
ll'illaitll
irsisirtm
Jaroshoro it
it:id l Iliic
+.rie-iisc
ll,'gcinIit, or
iirt
.rlliirt
A__________
C[- (O&M
.I
vhcrc cvcr reured oii lJnt
I[wcer for Unit 2 and 3 sinilar work
C;II tie carried (ut by WAIDA under
pr vdd
iu
Prset
I'rNo.S.(nt Slrtrirs
"Thi Miallurgical tc,,St rcl)rtls of
lune.
!99?
d
llripose thalt tre drain
The coIiittec
of Unt2 should also Irc diverted to
otsid turbiine tail triwards
CMEC mti
stiItit thi1
of Atig
199?
[carIll
colyII
wrt.r
Arl wterti.
arirfl.eirll is irccss!.rI
,
ur+r.rtiit oil' tie rurnl,1 eVe
to contitin
is%
itle
in casc co(llig/e.t1tig s.alr
,slaiit,_ed M/S CMEC ,h\,osd theti
inralily Io IlI W APDA in uriidirg
water 111itrl1
tid Tech
tixi.tirli.-"
det. ar+I:I
prolpr s.lreii
1992
Lir, od collai iitt
t and nosture
prt
Cntrantree prubler
toay exl'.rliti
PES to furitrli
their iro!mts.
detjils by cn
rf .\ugi 199'
;IrrIriIaciltlr
s'clletli I, I .l t,tr,'ine,
t,h t
.Iuiw'erlIr c t'U ttllitite r
ca.vaica it
oic.'t
l:nk ,I0 trl'
a sim
s
CE Project
I'1'
liii t!'i
t,"
.iitritrcio,
T're C.i.,rntitti.w.
pr,-tirc nw ,, .'tr :I'll h.
3 ard 4
its 21,
CE tO&N' I
Ja-10h1(u
enlsure
install; io
cttrtfurgc
I
un
Unit 2 and 3
bry end of
Aug. 1991 71,'
on Unit 4 Qr
end of Nu'
1992
,(5/
No.
,,ical
two
Ili
Unitanilt
oil cooler
CMI:(
Finai
by tIteirI Iy
Action by
Stt-is
I
- nrC((.isent
iiieIIItd
Prol Iil,%;, I/
I'rihlemildeicienry
,ici
CMEC inowi,'rd that sCal 4I
crc
chocks
was disirianltd and
CME[C Int
reporl by cond
of Autj, l
ctiergeicy dice l
,cncraltr set of Unit-,
0th Jrtite
I99?
CMEC
:ltcndinii
peciali ts ar
submit till%
199?
[he jot
CMEC taunt
conriri that
the jolt i"
attended by
themn
satisfactorily
[fictring cooling water
1ii11 rave
lt ;-cell
dispolm
N1M/S
10
c. ;
li0ittcc I't
tcL
t1
tlt t thicse
Tle
the
II
the
Frequent h:ik:e' if tl;.
'
,1 ,
I.,;,
-i '1 ..
I'll
CtI [C ilit
Clliorc takitli:
In servi c it,
restitlli of Unit*I
bearing
cooling wand
C rlnj 1, lic h.
of Oct 199'
CE (OKM )
Janllshort to
takc nce,,,,1r,
No
eItf1cocy
action
tic acccpted
order Itl
MI/S CM EC for imttercon :tIloll oh
illtake water pipe tines I:' kinidly Ie
expedited case is iii the o:;ice of GN;
W D)&OCE Projects Jamitort rma
l
c
foll"oi up
IillidIS t c advis td
_-
Approval o!
dlie variatlol:
ordec has lc'ii
granted by
IGM (D&D)
Thermal
C'J
,I
'I:auc lit
ctIIplclt til
1111c,
lhe c,,oiiittlCe rccinittitetids titt UnitI . 2. 3 inl 4 It, ctnrniected it) cistirc
addittiontal elahhiluty The wuirk cat lie
rti :citt IIy
i. truci tit ld plr:t
work by cod
of October
1992
C F (O&'l
Jam ,h ro
un':
ellmire
comitpleitii I1
the job by coid
of Dec. 199
12
IitiercuInetioiII
water talnks
lf Den.III
S:ilast
bove
- dtlto-
S No
ProlIl(.iii/d(r'i
tic5
calitc
]Tih ey Irly
l it(I t
lie ilr,:I
ducparlinrinta'ly
Aclitti hy
Irt's'rescil St -ltu
iI nI
atinvi:
avCd
Sute as
crllS
I yditirihl"ic ,Ior t
.111. ,S
14
ol
on:etinii
iit,,ercn
unlit
a nd 4
siS
rl-
c(li1iilIVItr
I~ t
I~ I{ ,tl
ll
ag(ainlt
trrhr,
(rttlif
cxtI.
rInI
Iistrtnllrtliia
J snI,*i
tatri
Ii
Ihlt
NoiIlii
confnccICl, I
i ass
:11"i.
('F
i
iii., '
..
ga t;an' ud
tlit 2. 3 :rir 4
II ydcOugCt
s.cl'
1991
I
(()& M )
ulthe -iUri
Iv.)rrK
rut Ir.
demtails
c I
,Icttruo.
rtl
(OI.iI
tilk
nvthI'iS tuid
( W, C III !
... '
hi,
Samei: as albn e
.i.
_;
.* I.
,Aik
s ItIitt
itiuinCtiiatei)
litcrcoiteltiklll dt
of at,
(W(J
(Mi (
,,
by cud
rel~ior
(,
'IN.
iiiML
OW,
twil
s.,iibmil their
(-
ItII)llti
lX,,;
('M [C ,nutt
, :
i,
', (, nh
"I II FtC)) hri
'Iliuril
-l.txIric'a lVroil
rcm.st
il)
No
fI: VI'CIID
'Ai
.iPply
Ahircmiil",,-'
iill River 1I0it:,k: il'ii '.
SNIIII
Action by)
nay
Jnshoro
1
O
propoal
Ilic
tudv
tf)
advici
be
k:0il]y
"
anid take action .oc'odnl
Chief l!,C-r
'cx
1i Ctisiri
'1 k[ty
iil aetI
the hine :I'ain,,t 1bib',
n tl e .tnOw ahtcrii:1tc t l
Io'pi
of the l h e i
lhncie
iih
otetkcrs hIavecl:c
uutch/d durmir the
io moilllee lprl1.
.1l,
end of SCpt
199-1
uCt
Lm K .1,11In m nl
1.C l. 5-
I.
I IhiitI00 K\V
14
riI, k Ir1.ll111%
IUIm
'
required
. ,.'iet
spare breakers hc
Ni/S
CMEC
r
further
tIwi
CiEC
the)' "'"oluld
M/S CMEC s1ttl:t11
s101ly ilte iu,,l'ci: in dclii ilnn'rith
rncc n d - IIl
\V A PD A EDc c'.i
i [au
MNorcouve
Ilic dcLails to
THE(O) for
a p proval by
inust submit
the o/o GM
holusc
CE (O&M)
' c
silbilutl their
rcl,)r
[)' cod
of Augist.
1992
InVesti.gati0on by
AI"ic.l tley
nIle,
kl licd
di:
plte.
NNU rjui n
iuu
nt
te i ti.h
Niit~m
ic ik,
lihcre is ;
lit t
1i drawtl
l
tg
termin
tcrinltu:i
niulmer
NiS CNIiEC
;I
ie
.,
u lc iiI
iou
i.m,,,-
Amit
-.!'uu Stp
','.,. -
., ,
.::,..,
i cCco lOpleted
l r
1 9,
1992
1cii
i1
It
will b I. i,
loe
li
Ulllt-2 .,nd
3 :IN allh v'hulei these utll%
NI/S CN4[_C remquested
are slhiddo,'u
uiuui
iIlll
Ill rhim.hilslch
otlV
NI/S
Te ct.i' nnliicml
I:i11e p
Ill [ti'hii
rc,
proge
%tif cqu
ctnhe'
199?
__Ni P r ;lic
ili/Dcm
~inci~:
ACtiofi by
I--.--
I/____-k II olnd
(It
II.N~
in'
ii
Sp~rI
chtic IIIiiprc
1: tnciAcsiriaiily
tcrii~hic\
carii
.1lo iutjiis
cisc:
i
ccl1101c CMNl:(
atiucii
prnl, Wcl1~i'il
ittiichcc
lc.i
III carry
vssii
smijhcic *iji
fo i 11
itile ininer
its,
hii
advised by
GM 1TH(O) (inl
27 7 92 to
slighitly mlodily
tilie CXistllnc'
fitting
arrangemnt.
Jainshorci mush
cnsurc thai hlic
comleted
:IcCnrdui1iNj
1St31
Ialinro
personally
iots
Iflb
%,-illCMiF(? D ljc III".ii
\VAI'lA fii
I
( I 1&M) Ina),
Il,
ic
Iciic
fm h
hY
11(
hciici
by ic Commniottee [iir
ploipncc C.Iriwr
;iran~i~l
(>igsd
FC
fii
shigirilys Lilii
-as
(IN
IE
lwN.
abi 1131hi
.iiil
hissp~ikii~
tcciceisd collIidh-(;ihily
Afic er tii
.'i
by)
end of Oct
992 fi Uii1is
ciiiaccoringly
2. 3 and 4
t ie
tli:it tutuCxgc.
lie battery iinnu[.ictuiirt511.
Iwo
tile
.1ii
1o 6
KV IfreaiK-
llicrc
lc csI
Ficta
actzio zuitd
r:cckcccci protilcitl id1t
wAPDA
11.1
suich
prolemlti
Mechlaical criahleul
hiiiiii
NcthcIiic
iit
1. i,
hoii
cii,
kiilv
lhcl
NV.,iivided and
Ncs.3ry Iraillit'
oicw
11it0t 1%Ito prittlew
1Iill,_'iliiliii lIl
and1. demn
titllh
ItWAD
Fircklocti lii~5I
i5 t
1C i0Ilil I0ittii
iItiIll'_
If
lc
Clii111,111
01 rc :, !I,
h.'s
ic y CM EC
11117sIlI
S til
prlchilcic
aui.A Ilic
lilIistcrilly
5
.,inico
iThrepir
N4etd ii
0;
1i iii
ivltir u1%~l3~~t
1hci
lit
dilleI
PrOici rimy -J
pay siccial
:Iiiiils/IIss-Cct 'Ac
call
Ws~i\AIDA %taff
p~iidtiili
toi
allcltn
with CMEC
It must bc
coinltI)C(d ISV
cold of Oct 92_
onl all tilec
i.f (. 1 Kv
Iliiiiii.c
iiit~h*tc~iiItile.
giigtc
till
Icireitiiylj
pcritjlrcIjjIt r
_______________________
work,
il
pli
cistonv'id
ttO'
.___.....___
No
I-ec itIII
lrupoa I/
I eli()
iiihii.r/
I'
.i
dl, ir
('
N/.IS;
3 and 4
fiii(-2,
irfit
CM [-IC
.IC list (1
ireI :
_ +,,grer I
ve
c1i:,lt;ri/ed 4/S CM[L-C to
cioinpreslior
ticsalcd
i,0
i''(uiC-
[i
""
'
i's
by cnd of
Sept
l uirIiig
wire
hc
fuinrslr the
comiinplete ist
1992
llrctl
r(
lo.eillly
'llr,i y oin ie
by
" ol,
CM H lU
,. rk Is in
ied llatth1,.
D,
ActlIoI
|'tnen't Statli.
' hl(ill"
'hi
is very
presently 11c
i1npoill it i
e haz3
condition is quilt
(l (O :M
Iisi
J;'lri
cinsurt
n :-
,,
aiii
i'iCi
;'e
,i,,3
in
irrixid . lto
le
CE (OkIM)
fak.
fire
(O&:M ) should i
r-n i',er
ii
[lie
,'~J
rl ilir?
Fire
ge
.a
;rrrai
lnghit 'i
take aciollt
kiiitll
itla'
' ,.
ti
(l'rr re I )
(CdvrserI
irrit ensure
:ccordit.eI v
i l
ent ifro e ly
et lii
it(
'
-,
'
itce rCCiiiili
.iiiImmiiiiit[
n" ii
, 'si:.rl
t
:i
iI.rcrnl~l~ .rct.;
\\I
is
Jilishoro.
freqetll
, ;\ivoiid lilt%
rtler~llll ilt it is irllosel that
orderr
h 1andwith C: F Pi'0 cs
le 11:ts I:Idl\ be ildvis'd
(A: 'rojeti
iIlIS1 cxpc.ltl
g, ihi rib
iro, oil
-i'e|liriii
lo ehxledite co
work
rmpinarran.ement be constructed at
Acli
from C IS tOM
ix
rLqtt e,d
CE (OISl
Jainshoro [trril;
ensure rr
-i
6
l.r
'learnorri tIre
nugrlitirrm lit
hr:r.rdois
it
,r:cclL
signri+atr;| "nn s.ie ail
t
Crrsi,ierti
techll e~il c:. l
e i'lh.plsr, kill
,licr:tioii
ol
trt:linirt
ille.i
lmpr octill'r
fi, liies
At:&T p
ci I Io;
g'i
l;
.I
Case Is
v.it
s l: lpeiuc :dll
',I
oftiltire
existl'
Arr.!
corld int
' tr itrr~
tEarc
42
LitiirrC
1I1gilf'u
,'% 1ipuil
v a ndsc (iif
lili.
ii
Ii
112
i
.ii
uI
111 Mdli I
1%pripi.'%ci
~uiuu
.,, kindly be
moM
oif
ilicsc
J.111,lioro Ilrtll
cnsurc ta t
i w l
jiiip
CEi (0& M
itrhuh
.111d
lend4i
on
th
its Ist
ins pcct torn
U. S. A(,IK'N( Y I()
I RIVATI
COINIRA CT NUMBER
391-0494- C-00- 0540-00
DRAFT IREPORT
In Association
iflt:
.JAMSI IOIt)
I'{)WIIZ STATION
tiNI'I'S 1, 2, 3 & 4
CON'ITNTS
Pagu No.
I(
1.I
12
2{)
Overall Assessment
Introduction
2.1
2.2
2.3
2.4
30
Sumrya
Purpose
Scope
Plant Background
Data Sources
12
24
37
69
86
104
139
.JAMSIIORO I'()\VEI-I
STATION
UNITS I, 2, 3 & 4
R I'ORIT
Powec
This report documcnts oUr equlpmlent condition assessmnent rcvlew of tli Jamlishoro
of Ilhe
Station Thc purpose of this revicw is to provide an overall condilion :lssessrleni
major systems, components and structures necessary for the safe andicliable gcneration
normally
of electricity. Also identified are repairs or replacemcnts of major components
are anlticipated
desigled io last 20 plus years but due to the current condition or operalionl
to faill within the neit 20 years
ic repoi
Secton 2 0 "Introduction" outlines the purpose and scope of work pieslnied in il
data used
together with background information on the generating station. ThC sources of
Concerns"
in our analysis are also identified. Section 3.0 "Overall Assessment and Gencral
provides performance data and lists concerns in the areas of opei3lion, maintenance,
quality of installation and housekeeping that should be addressed io provide safe and
rcliablh operation of the units. Following this section, details of our assessment for the
power plant major system and components are provided. Separate sections are provided
for the Unit I 3olier, Turbine-Generator and Balance of Plant -Systems and Components.
A similar breakdown is provided for Units 2, 3 & 4, (treated
as one) since the units are
duplicates. An additional section for the Common Facilities, is also piovided.
1.1
Overall Assessment
'he systems and components reviewed at the four units of the Jamshoro Power Station
should be suitable for conLinued operation for tile, next 20 years. li ojected repairs and
replacement of major components and sub-components of equipmeni that can reasonably
be expected to provide relatively trouble free service, by American standards, for 20 plus
years service are provided in Section 1.2. The assessments are based upon the newness
of the unils, the effects of the operation to date (September, 1991), projected operating
regimen, adherence to manufacturer's recommended operating and maintenance procedures
and resolution of curretIt deficiencies. The assessment assume all equilpmcnt currently in
place was designed, inanufactured and installed in accordance with applicable code and
standards and are of powei house quality. Verification that the above criteria have been
met was not part of the scope of this equipment condition assessment report.
In genelal, Unit 1 facility appears to be of superior quality arid exhibits better overall
.lAMSIMII()
I'O-'LI( S'TTION
iNI'TS I, 2, 3 & 4
lI:'Okl
1.2
ani ipated
lhe following tepairs and replacements of major components arc
two Unit I ant
Orl elit
Estimated cost is S275,000 per replacement.
corosion
Replacement of the cold end baskets due to corrosion of the two Units 2,
S275,000 per
3, & 4 air heaters at 5 year intervals. Estimated cost is
replacement per unit.
,ea.s
Major repairs, due to corrosion, of the Unit I outlet flue between the
2001-2011. Estimated cost of the repair is S250,000.
Major repairs, due to corrosion, of the Units 2, 3 & 4 outlet flues between
unit.
the years 1996-2011. Estimated cost of the repair is $250,000 per
Replacement of the DC batteries for Units 2, 3 & :!witlfin 5 years.
unit not including
Estimated cost [or new batteries is S100,000 pi
installation.
Note:
for
All costs are given in current (1991) US dollars and are based on costs
States of
similar repairs or replacements at plants operating in the United
Anerica.
are a number of
the report. Most
are items covered
be corrected prior
(JNI1'.S 1, 2, 3 & 4
-C.ION
2.1
.-
INTRODUC-I'ON
lPurpose
systems and
The equipment condition assessment applies to the bulk of the power plant
components necessary for safe and reliable operation of the units.
The current condition
of plant records.
and installed
It is assumed all equipment currently ;n place was designed, manufactured
power house quality.
in accordance with applicable codes and standards and are of
part of the scope of this
\'-'rification tlii the above criteria have been
met were not
report.
and sub
The projections for ft.urc repairs or replacements is limited to major components
components of equipment that can reasonably be expected to provide relatively trouble
Components and
free service, by Amc ican standards, for 20 plus
years service.
component parts subject to normal wearing mechanisms are usually handled as part of
JAMSIIOIR()
t()VS'I.R
STAION
tJNIIA'N- 1, 2, 3 & 4
EQUII'MEN
2.1
Purpose
Jaim,,htto Units 1, 2. 3 ,
The purpose of this equipment condition assessment report for
4 is to provide thc following:
A general overview of the power plant systems and cquipment
of major
Identification of anticipated future repairs and rclflaceMients
review of the
components based on tile current condition of the equipment,
and projected
current plant operating and maintenance records and prac:iccs
operating duty.
Estimated costs for repairs or replacements identified above.
Identification of general concerns noted during the review process.
2.2 Scope
plant systems and
The equipment condition assessment applies to the bulk of the power
condition
components necessary for safe and reliable operation of the units. The current
records.
plant
of
of the equipment is based on the information provided by our review
made duling
Hnterviews
with plant operating and maintenance personnel and observations
the site visit.
and installed
It is assumed all equipment currently in place was designed, manufactured
of power house quality.
in accordance with applicable codes and standards and are
part of the scope of this
Verification that the above criteria have been
met were not
report.
component parts subject to normal wearing mechanistms are usuaily handled as part
.JAMSIHORO tOFI
STATION
UNIIS I, ?, 3 & 4
EQUII'MENT CON)IION ASSESSME:NT R.IPI*
No.
No.
No.
No.
1
2
3
4
December 3, 1989
Units 1 and 2 have been turned over to WAPDA and are currently being operated and
maintained by WVAPDA personnel; Units 3 and 4 are under warranty and are currently
being operated and maintained by CMEC and \VAPDA personnel.
2>;
2.4
J)ata Sourccs
obtained by a team
The data required to perform the current condition asscssmel was
during a ten (10) day visit to the Jamshoro Station in September
of five Ebasco engineers
1991 The following sources of information were utilized
'21
.JAN
I I()Z()
t
E-Q
SEC-ION 3 0
3.1
Unit
(OWI( STAI)N
S I, 2, 3 &, 4
OVIERAILL A.Si"
Data from
Based upon review of selected Unit Daily Log Sheets and review of Summary
Commissioning to August 31, 1991, tie units arc capable of the following output
Continuous
Operation
Unit 1I
Unit /. 2
Unit # 3
Unit # 4
Demonstrated
Maximum
262 M\V
210 MW
250 MW
200 MW
200 N4\V
200 MW
210 MW
210 N{W
Unit #
1
2
3
4
Average
Design
2284
2584
2,584
2584
2441
2547
2594
2725
lie average heat rates above are plant operating personnel estimates based on fuel
consumed and power generated from Date of Commissioning to August 31, 1991. These
encompass all operating loads and start-ups and thus are exp ected to be above the Design
(guaranteed) Heat Rate at the best operating point - Economic Continuous Rating.
Performance acceptance tests for Units I & 2 have been completed and the units accepted
b,, WAPDA. As recorded in the Unit I Report on Performance Test, the actual
performance met the guarantee. The Unit 2 performance Test Report was unavailable
at the time of our site visit.
3.3
(Jnil Performance
Unit 2
Unit 3
Unit 4
83.02% Available
61.06% Available
Available
38% Available
.j/O
Unit I & 2 availability percentages include the 45 day and 57 day shljioowns respectively
for First Inspections. In addition, the Unit 2 availability suffered duc to a bowed high
pressure turbine rotor keeping the plant off line for 55 days. It is noied however, these
availability factors should not be considered indicative of future plant availability. The
start-ups of the units'are recent and low availabilities during the first year of operation are
normal until all equipment has been completely checked out.
3.4
Unit Operation
Per the plant personnel provided Summary Data, the hours of operation, capacity factor,
and total KI,-1 for each unit from commissioning through August 31, V)91 are as follows:
Unit Number
I
2
3
4
tHours of Operation
9,329
7,376
4,505
Capacity Factor
.63
.73
.76
.78
1.355,655
1.115,441
707,604
Operation of Unit I is satisfactory. The unit is capable of and normally operates in the
automatic mode on unit master load control. The operating instructions prepared by
Mitsui, the constructor, are comprehensive. In addition, plant personnel indicated an
extensive operator training program was conducted by Mitsui.
r/g
.JAM,1I()I,()1
I'()WI:
,' [ATION
S
IJN'I'." I, 2, 3 & 4
fEQ,
,,'i'r
(()N)ITION
ASSFV.SSMINT RE-I'O)I,
3.5 Maintenance
A long term maintenance program for all four units has not yet been established. Due to
the current shortage of power throughout Pakistan, plant maintenance personnel stated
these units will not be shut down for overhaul outages for at least 5 years. Maintenance
activities for all four units were directed by the suppliers for the first year of operation.
Maintenance fot Units I and 2 was only iecently turned over to WAIIA, wile Units 3
al intenance checks
andd mainte nance is currently .c ig coordinated by CMI C. Routi i
This
arc performed daily by WAPDA personnel and repairs made as required.
term
a
long
maintenance mode is acceptable based on the newness of the units; howver,
maintenance program should be established.
The Maintenance Manuals provided with Unit I are comprenlicnsive and Supply tile
necessary information for proper care. The manuals for Units 2, 3 & 4 however, are
sketchy at best. More complete manuals should be prepared for these units to aid the
maintenance staff in performance of their duties. In addition, maintenance and trouble
shooting activities will bc hindered on Units 2, 3 & 4 due to lack of "as built" rawigs.
These "as-bilt" drawings have been provided for Unit 1.
ILI
.JAM0IU
() I'()Wl.R STIA'TION
IJNIIS 1, ., 3 & 4
Cable trays that have no covers and arc exposed to tihe cl lontctil
have accumulated consirclable debris on and around the cables
Severlal ares
Incomplete lagging at each hackstay elevation at the corners of the boiler. The
blanket insulation is exposed to the weather, and in several at as the boiler tubes
are istible where Whe insulation is missing.
Much of
The we!lig oti iany suppo is is ver)i poo. The iller welds have cxcc.ss crown, are,
rlregular, and appear to have poor pienration.
The local control boxes located throughout the p. .lave no gaskets oil the access
door assembly to prevent moisture and dust from accumulating inside the control
boxes
6.
The wiring of various instru,ments is poorly termnlinated antd exposed to the clemenlts.
7.
aroulnd
Aside from tile external appea rance, a major concerti is these conditions may or limay 1iit
reflect the quality of workmanship that was used in the fabrication of equipment and
components not visually accessible during the walk-through inspectiotl
9
,JA
IEQtIJI l'
3.7
SII1, 1, 3 & 4
;cnetr l Ilouiscl,ccping
debris was
The General Housekeeping of the staton was relatively poor Construction
The residual ol
observed throughout the facility even though all units are operational
was
unloading area was especially lackin, in ,ood housekeeping placticc Oil spillagc
m
[his
c
in trenches anid on .!rade level
IIotd
commnonplacc wiih oil and wal'e iixtlc%
(:ICatus a SeIiOLS [ilc hiazard and should tn aigindcd tn rmIniCdia'lv ( :ood Ihot1sckccp III,,
in the uIIIS
p)iactices promote case of opeiationI mnd niaiiienaiCe and wIll hc HItllcte(d
availability and reliability
.3. Detailed Coudit
(iI
Assessments
during the
Ile general concerns discussed above were based upon the obseivations made
s tevisit and discussions with plant operating and maintenance pcisorniel These concerns,
as well as the items identified in the condition assessments for ile (.,ndividual system and
more
components, may nor reflect all curreni de ficiencies o piol)lcis, hut only the
a1)paret and serious ones uncovered duimn o on ireview. Ma ny o( these deficiencies have
ain adverse impact on o[peration and mainrenance, but may iot necessarily result in repairs
lead
oi replacements of the major components However, if false insti umentation readings
to maloperation of the equipment or result InI exceeding ille design margins of the
equipment, pteflruluic ailures may occui In is rCconed that the units have prily recently
Ite outstaiidiing_ pioblicis are commirlionily encountered d-iuig the
tarlted arnd aInIU, ,: [of
start-up phase o all units. Plant personnel are currently addressing most of the probleris
on Units I & 2. Since Units 3 and 4 are still under warranty, it is expected that problems
supplier.
for these units will be addressed by tilie
.IAMSII(O)
I'()WI.R STATION
UNITS 1, 2, 3 & 11
[Q UI PM IKNT CONDITION ASSI'SSM ENT REI'ORlT
Ihli
.lAMSII()I() IJNII I
STEIAM
;NIG'IN-RATOI
()M
ICONIN']I
&, S\'i;M
1 is equipped for
1h
,,1l
sys l'ls cvaluated
consist
Steam Generator
Superheater/Rehearcr - 'ub ng
Superheater/Reheater -Headeis
Supcrheater/Reheater Pipin!
PrnnnmTi,,,r Tnlrp
T4iPdrr
Steam Drum
Boiler Enclosure
Air Prehcatcs
House Boiler
Boiler Structure
.IAMSIIORO
UNIT I
l)cscrip ion
TIhe
(29'-6") deep.
Tile primary furnace is 13.38 meters (44 ft.) wide by 9.003 meters
Assessment
test of Unit #1 was conducted
Prior to the first year inspection, a complete performance
April, 1990. The results
by Mitsui, Fuji Electric and the Riley-MitsuIi Consortium during
or exceed contract
of the testing detcrm iuieCd that boiler pierformance and efficiency meet
requirements.
.1AI'1SIIO)4()
)JNIi I
Pfriiod o liic by
hs IIIolr caP he CxpectCd to immu,,(ldc Iiklhlc SCFVICC ovCr aui CXiClldC(
the manufacturer and by
operatung the kinit within
the paianjmtcer established by
pe-form ng routine iIain!tenaince anrd periodic inspections.
Very consel-vative
arid gs leaks
problems associated with a pressure
shutdowns are reeomnmended to prevent long range
hiied I)ollCr
14
rU
IF PC
,RLB
4 AVAI f,
rXIT
MesaI
) iion
I
wttdboxand provide
The ait and gas systems supply heated conibustion air to the boiler
stack. The major
:iconduit for conveyig flue gas (roti the boiler outlet 10 the
componetts of the ai
heaters, air
and gas systems consist of the forced draft fais, ait
[he staCk
to
flue, and the flue froml the ail hicater as oMtCl
boilet furiace as
the econolnizer outlet and reintroduces it into the
the supeiwlaic
a icanis of extending tie tCm perature control range of both
ll-
and recaie
(2)
inlet
Forced draft fans by Nakashirna Mfg Co Ail foil rotor dc.,ign, double
(2)
Steam coil air heaters by Seo Koa tin Kolgyo Co., Ltd
(2)
(2)
of the first
normal since returning the unit to service June 1,1991 following completion
year inspection.
Assessencrut
The
stack, the air and gas systems
were judged to be suitable for extended operation.
to the stack are
heating surface
of the air heater and the ilte connecting the air heater
JAMSIHORO UNIT I
IBOIL[I
COMBUSTION SYSTEM
This
Assessment
JAMSIlOW-) UNII
I)cscripion
100 and controls nine (9) burner pairs. The system is microprocessor based
Master Fuel Trip (MFT) circuit which consists of DC electromagnetic relays.
All top and middle level burners cal be manually staited and stopped in pairs
BTG board in the central control room and corresponding local control panels
as
front burners. -owever, six (6) burners at the lowest lcvcl, which also serve
burners, can be manually started and stopped either in pairs or individually from
board and individually only at local control p. hel
from the
near the
warm-up
the BTG
in pairs
The six (6) burners, at the lowest level arL automnancally started and stopped
depending on burner header pressure
The twelve (12) burners except those at the lowest level, are automatically stopped in
pairs in case of emergency condition, such a5. Fast Cut Back (FCB).
A master fuel trip pushbutton is available on BTG board to quick])' shutdown the boiler
in case of emergency.
This system provides of the following control functions:
Furnace purge sequence
Master fuel trip
Ignition fuel trip
Warm-up fuel trip
Oil fuel trip
Ignition burner start/stop
Oil burner start/stop
Gun purge
Fast cut back
Air resister open/close
Oil selection
Ignition burner header leak check
EST AVAILABLE
17
JAMSII()I() UNIT I
AUTOMATIC IIIRNIR SYSTEM (A HS)
Warm-up burne
Condition
Interviews with plant O&M personnel and rcvie.v of unit trip record indicated that the
unit tripped two tines, on lune 30, 1990 and March 7, 1991: due to the automatic burner
system. Both trips were due to human error while working on the system.
The automatic burner system appears to be in satisfactorily condition based upon the data
reviewed and unit walk-through inspection No unusual conditions were notcd.
,,-)scssnrtnt
Assuming proper selection of component, availability of spare parts and adherence to tle
manufacturer's O&M procedures, the automatic burner system should be suitable. for 20
years.
'
JAMSIORO
UNIT I
[)escri pt
ion
"11C
ail nl1c11C
'[he' systemi hardware consists of (2) field conti Dl stations, (1) terminal
board cubicle, (2)
naishalling c;abinct, (4)I/P converters, (7) 1/0 positioners,
(39) hand/auto stations, (I) unit
master %.il)ervisor panel, flow/lcvcl/pressure/differential pressure
iransitniers, flow
elemcnts, T/Cs, 0, analyzers, repulators, and 1IP turbine bypass control
valves
"lihe Automlatic Boiler Control System (ABC) is designed to control
hl.: :olr wllh
coordination between turbine, generator, and boiler. The AB3C pro\dcs
the following
functions
Unitn master control (including turbinc master and boiler master)
Automatic Combustion Control provides fuel oil flow control, flue gas 0.
control, air
flow control, a'nd residual oil pump discharge pressure control.
operation.
pl(rov(Ide
19
Y'
JAMSI(ORO UNIT i
AUTOMATIC [BOILER CONTROL SYSTE-1,M
(AIIC)
HIGH PIRESSURE/jLjOW pIRE SSU
T.-'URBINIEj If '('ASs SY)-'SITM
lnteivcwv
,platit pesonnel, walk-downs, and review of Unit I records,
indicated high
reliability and excellent performance.
Assessment
IHST AVAiLAL,. L
20
AUM t.
[)kscriplion
The major components of the boiler-side auxiliary steam systems consist of the house
boiler and the soot blowers serving the main boiler and the air prchca:ers.
lhe house boiler is a prcssurized furnace, shop.assembled, mcnbran" wall construction.
oil fired unit manufactured by I-1ydndai Heavy Industries Co., Ltd. Th:: boiler is rated at
20000 kg (44,100 lbs.) per hour of saturatcd stcam at 7 kgt, per cmn (10 0- psi) The boiler
iS equipped with one burner.
lhe soot blower system consists of twenty-eight(28) STR-8E long rctii, :..le and eight (8)
STR-SE half retractable soot blowers by Mitsubishi Heavy Industric, Lid., and two (2)
swng type cleaning devices for the air prehcaters supplied by Gadelii, 'K.K.
Complete inspection. of the auxiliary boiler and the soot blowers system %ereincorporated
in the first year inspection. All equipment checked out to be satisfac-ory.
Assessment
The auxiliary house boiler and the soot system are cxpected to operatc satisfactorily for
an extended period of time. Normal maintenance is anticipated to maintain the
equipment in good running order
replacement.
and
,JAMSII)RO UNIT I
IIOILE R
'R ,RJCIt[JI.,
tcsc riplll(in
22vilih
2.,JI
2.2/6)
. -, S.,C,
.JASIIORO UNIT I
01LER
I
STR UCTU RE'
A sscs~ Imef)t
Assumng pfOpf)E design and erection, the boiler building structure should be suitable for
the next 20 years of operation. -hc structural steel should be protected aga'inst corrosion
hy piopi mainit:nance at the req uired intervals.
23
(/
.AAf,'1qS1()l4()
TURIENI
-GI'NEATOI
IN I I
II I1 562/68-2 type
pw. 25p0
IIc U nIt I IIuirn-gcnrcator is a [ UJ I1:.c tIc (Japan)
n1do(01 nn111.The Itifbinc is a ,andem co[I pounnd, 3 casing, doubIlc-low cha us1, reaction,
wheat, condensing typc. I-he gencrator is a synchronous, 2 pole unit type which is
hydrfocn cooled. Thc urit has a static excitation system.
Iic turbin -genira tor components and systeins that weme
Ifollowing.
High Pressure Stalionaly Components:
IP Inner Casing
IP Stationary Blades
1-11B Rotor
1l Rotol
Rotor
1I1Rotating, I31ades
L) Outer Casing
lB) Inner CaIsing_, I
LB Inner Casing 2
LP Stationamu Blades
CrossarouLnd liping
Gencratm and l:ixcitatoii - ueictricai 6, Isolated Plhase Bus DUCI
24FT
"24
AVAILABLE DOCUM'Egr
(3enC
alofI
otirtrnp
(o(11(o)po
111
Nle.i:
llical
"''l>iil
Reulting Riligs
StIeICa I1
o
ol
teItI
lI'li
brnc l t ingS
"lrbine Aes(:5 tals
Performarnce
'he icrtinnt
BEST AVAIL,".~
25
.U
O()RINI
.JANIS
I )(scri pliorn
tills l
c a
afe Composed of tile followIing: Il1 ()iising,
four
with
arid
circumf~erential f]ariige at the exhaust
casing with a split biltd vetrca -l-ongittudinalJ(oint ,
oI
562/68-2 turbine
lIl.:cctric -HRI<
(of the. b rltel typc kv,,fh a vertical
11hii
u * lead Iipl
Ilead
pinig
Vic -Pl' (JutCI casin, Ill' ni11(1; casIn, ani IP irni casing are Chrornium-Miolybdenumstationary hlades ate 129/ Chronmum-nolybdunumVanadiun alloy steel IlP and I1'
Vanadiun stainless steel lhe cornhin d maittn stop and main steam control valves and the
comb1)ined reheat stop and inter(:cept valves ar e inade from Chroniun-M4olybde tILniVanadium alloy steel. ]hc IP and lB Iurbi: lead pipIng is from the steani valves to the
casings
Cnditiol
(Ioni nts arnd Cmrit GC
No 1)1oblenms were uncovered based on ilter'iews with Ja mshoro plant llairnteiance and
operaving personnel and the irvicw of tle first year inspection report on this unit. Duning
that First inspection th: 117 and lB sections of the tWirline were not operied; only the IB
I. rlSl)euctCd lat the nllt scheduled
section vis dismantled. 'l'v IIP ari IP sccti o <
,,,'ill
outage in about 5 yeas. (:uiititly tilrt I ;i,(C (1 ktuil ,itt)obleiiis with these lighlprCssure
stationary compotienits.
ol)tiCrits (described above) all aflpe;wt to be in good
'[he hlighI pressu re,C at totta y c
ancec problem
:ondition based ol tile pla lit personnel itetviews and t hle absete:" of intt
records.
26
.*AMII0O1()
111III
i1
1fiOr1
ile
13[,1 AVAIL, i F
27
.JAM'SI( )RO t
"I'JRIIINEROTATIN(; (0MIONIN'.
flow". tntb)lIC
lhc turtbine rotatintg conponeriltS on this 250 MW tanLdCm coHI)OUnd doubl
blades.
ototnf
assembled
P fotol, l1'rotor and L rotor and the
e oniprsed of ihc I1
awi
?(l I Ulcto1t stages.
;a single fhnov type with one impulse stage, followed by
The III' ltol
lotor is
,,on lhI ITeH
I eam
The 1 blot) IS also ; singlel flow ty)e with 17 ows of
en
a double fl.w type ,.tt / low of (ectioll Stages ()It c l(dh
y
.la 1(dthe
len u In - Va iadmur ilhmv 1,sc
The liP ctimm and the IB icutot ae (Qhromtiti i-N-Mll
Vanadumn stalc, ,tcl The
(omuICnl,,
litt,~e
lhcs
ii
i
28
l7,+].".
( ,
10 start-ups pcj
,
i,1 c
evaluation, the
ricw~ncss of the
sl
ow
iIll
olbtail
the twil;
qIa
we(:I)i (
ht lt the
i;l:( I
infOrmllatiOl
tillit,
4 hot), it
'51%
")rC
i(vi'd,.,5,
ICiS, 1ncl
l IPI )
(8l[()lnpone(II
it T e Ii 20li
oCntahl
asscnble:d f011 ing, hlidts shoui)ld h() s,
tern l
iliii
ll i0
maijOl r( txil', ind Icplc c niv
I I'
Ifio
' ith,,l+
ild
;nd tile
,(civiC.WS
IT
1 1I
tlit
IC
(i
ICt
(outa cs
a
shchduled II;t ilInc(
m i onl thi
vy
ro)l)
an( the
tl(i
rtmlm
wilioul
folliic
'i
(Uring
I) Ccri[liion
lhe low pi:ssure stationary components oil this FUJI L-ectricIlanidCto CoOunrld double
LP outer casing, LB inner casiHg 1, I nne{ casing 2, lB
[low tnrh ine are made up of '
Is a double [low
I at 0naly blades and the ciossaround piping. The low precssu[C S ctl()I
and downwaid exhatis (}th iclndenser. The
sVtCHOl With crosSarOund admlis.There ,are 2
(n Ii NI,{C
,lai{natiy blades arc syn~rnetil.i, aid opposite hand
(:r (S-aori H d [ipt(s; one on each SidC of ihie turbiriC
Ihere, w.ec no probl ms found with the low pressuie si-t l) /ary COIlonentS based oil the
inteiviews conducted with Jamshoro plant maintenance and opelations 1nersonnel and the
review of the first year inspection report of this unit During rltat ist 'cai inspection the
IL section was completely disassembled and inspected. No pitoblclt ,,Cre reported.
The low pressure stationary components
noted above all appear to be in satisfactory
condition based on the plant personnel interviews and the review of tirrnetenance records.
Assessment
No major problems on the low pressure stationary components weic (ound nor are they
anticipated in the future. This assessment is based on the information obtained from the
plant personnel interviews, maintenance records revie\ a industly crience with othe
similar low pressure stationary components. 'lhe low pi)CSSUIC siately cOi1}t)onCHnIS OfI
Unit I are expected to be suitable for 20 years of continued operation without major
repairs or replacements. Normal maintenance arid inspections should be regularly
performed at scheduled major maintenance outages.
JAMvSII(I() UNII I
I)cscription
conductor and rated 16.5 kV, 150 kV BIL, enclosure temperature rise 40 C, conductor
teniperature rise 65 C, aluminum enclosure The main bus circuit is rated at 12,000 Anl)
with symmetrical current of 80 kA. The su'b bus circuits are raicd 100 Amp with
syienictrical current of 160 kA.
Interview with plant personnel, walk-downs, and review of plant records, indicated that all
the above systems ar6 functioning satisfactorily.
Assessment
(V7
JAM. ISI(O)
[NIT //I
- MEC(ANICAIL
Description
[Tie generator rotating counponents-mcchanical on this FUJI Electric horizontal cylindrical
rotating field hydrogen cooled gencrator arc composed of the following; the generator rotor
forging and the generatorr e.ai(tlring rings The generator rotor forging is a singlc piece
forging with integral turbine-generator coupling and fail hubs. Thc generator retaining
rings are high strength high alloy non magncic steel shrunk on to the rotor body to contain
the rotor coil ends at operating speed,
No problems were discovered based on the interviews with Jamshoro plant maintenance
and operating personnel. Currently there are no known problems with tile generator
rotating conponents- mechanical
The generator rotating components- mechanical, the generator forging and the generator
retaining rings, appear to be in good condition based on the plant personnel interviews and
the absence of maintenance problcrn records.
Assessment
Based on the information obtained from personnel interviews, the generator rotating
componenrts-mechanical: the generator rotor forging and the retaining rings, should be
suitable for 20 years of continued operation without major repairs or replacements. The
condition of the generator retaining rings should be carefully monitored by nondestructive
examinations during regularly scheduled maintenance outages. Routine maintenance and
inspections should be performed on the generator rotor forging during scheduled
maintenance outages.
32
"URtt
Descriptio n
Eccentricity
Control valves positioji
Speed
Shaft vibration and position
Expansion
Differential expansion for HP, IP, and L) turbines
Bearing (metal, drain) temperature
Shell metal temperature
Assessment
Assuming proper selection of component, spare parts availability and adherence to
manufacturer's O&M procedures, the turbine supervisory system should be suitable for 20
years of service.
33
SI!IAM TJRBINEI.
C()NTIOI"
CONTR()
(,OVII.N()I
FLE(I'iR(IIYI)IRAtIJIC
1'.fI
I)escriplion
The steam turbine by Fuji EIcct ic, type iclicat condensing tandcr1 conpbund double
flow, is equipped with sol-state aid ana log ClcCI rohydral Ic control sysicin (EHC). T-he
The EPIC is
load control and protcction inicrlocL
El1-IC takes charge of speed(,
manufactuted hy [uji -lectric
Assessment
/'0~
UNIT I
JAMSI[OR1
I
BALANCE OF PLANT COMP'ON[ENTS & SYST EMS
D( Station Batteries
Ducts
Local Control Boxes, BTG Boardwiring Control Cables, Cable Frays and
Plant Computer System
lurbine and Central Control Buildings
l
]
rtJ'UI IN[--(;,IE.NIRIAT() I( AtU XIIIA It' (:()MIP()NI :NV 'S
'
1tITMS
I)c",cr I[) l lI
l
1 562/68
.l7,
Helcii i 1"-l
"Thetnt h ic eierator auxiliary componcints/sys t ns oll this f:tJJl
2 unit consis ofltile following: lubricating and hydraulic oil Syticll, ininig .equpflMenI,
Oil cooler
Oil conditionet
turning speed
The turning equipment is an oil hydraulic type turning gear which has a
raipe of 80-120 rpm.
niumber two bearing is a combined thrust and journal bearing. The thrust bearing is
Kingsbuiy type with straddle construction. The getnerCMtr has two journal bearings located
1-HP
in the end shields. There arC sliding turbine pedestals at the govetiot end of tile
the
section and belween the HP and IP sections. The turbine beating pedestal between
I1 and 1-1 section is of the fixed type.
.IAMSII)I () IINIT 1
TU ItIN-(;:NERATO I AjXIIIARY COMIPON-NTS/SYSI
IIMS
I)
Radial shaft sal,
Valves
(onnents
auxiliary compleonelts/systeills
There were no report(d problems with the turbine-generator
Assessment
turbine-cenerator auxiliary'
No major problems were found nor are they anticipated on the
interviews, the
components/systemns. This assessment is based on the plant personnel
with other similar turbine
results of the first year inspection and industry experience
auxiliary
turbine-generator
The
components/systems.
auxihary
generator
for 20 years ot continued
components/systems for Unit I are expected to be suitable
maintenance and Inspections
operation without major repairs or replacements. Normal
should be regularly performed at scheduled maintenance outages.
JAMNISIOI()
11AIANC-
UNIT I
instruelentation
a1)1
rn ro1l
and civil
l1e following:
l-eedvia-tesiei
puimlps
Coridensa tL'e
[cedwater lcateis
Dea ltor
Cooling towe
Circulating water pump
Condenser
le,. r
JAMSHIIOI,() tJNII
'II1.
l.l--D
SYS'II]
I)cscriptiou
'lic [cedwatet system conveys water fron the condenser outlet to the boiler econollize
otl seven srloes of.' hcating as
oul'h
Inct. It prheats the boiler inct water tem pera ttirc
ejec(clor Coolers and tnrhiie, gland steam
Well as condensing the stcarop in the steain jet allliis rtco rtarc Ole condensatt- pumps,
imlajor colm porelnts addressed in
lThe
condeinser
lps
fctedwatc hic, s, dcarator and boilcr feedwatcr ptju
lh tee 50% capacity [lotoI driven c.Clodenlsatc pumps aw provded Under normal
as
The condition of the major feedv.,ater system components,
feedwater systems.
as follows
documentated in the First Inspection Report, are summarized
'AII'T
,
SYSTEIM
13oile
r
FeedwatCI
1Boilei feedwatet
Assessment
,IAMISI 10R()
(O()IN(;
I JNI[ I
I
AIWAr
SYSTIEM
Descriptiol
coolers.
SeCtiOnl
The cooling
cross
u ilharical induced diafti multi-cell
is aIower
ow lype
T]hc structure
are
In :talnd-by. The circulatirw water pumps
pumps are operating and one pump is
and cast
lhe
pumps have stainless steel impellers
vertical, single suction mixed flow type.
iron casings.
box horizontal surface typc
ihe tube material
The condenser is a Iwo pass, divided water
and titanium in the air removal and exhaust
JANVSItI( ) IJNII I
Assess mcic
S'tt,
[) c {i Ip
IR<tj..u ,
ion
{itionl's
o d
n +,{
,\ ss es srin cii
43
I)cscript
of
(omments
Assessment
to the manufacturer's O&M
Assuming proper selection of components and adherence
without major repairs or replacement.
procedures, the system should have 20 years life
JAM.SIIR()
UNIT I
FIR 1, PROTECTION
)cscripion
Lach has a
each with
a capacity of 30
b) Two (2) fire water pumps manufactured by EBARA,
rn3/hr discharge pressure.
(54)
hand carried and
Portable fire extinguishing equipment, which includes fifty-four
tVo (2) wheel carried dry chemical extinguishers.
Condition
fire hoses for jse througlhout the plant were stored in a warehouse
45
/13
Asscssment
and adhcicnce to
Assuming proper sclection of components, periodic f-unctIonal tcsts,
for 20 yCars continued
manufacturers rccommendation, the system should be suitable
facility is ncedcd to
operation. Howcvcr, immediate clean-up of the fuCl oil unloading
the hosc racks providcd
avoid potcntial fire.
In addition, fire hoscs should bc reinstalled in
in order to ininimizc rcsponsc time and extensive fire damage
.JAMSI10I() UNIT I
Description
Condensate and fcedwaier arc chemically adjusted to prevent scale fo0n1ation, corrosion,
caustic embrittlcment, and contamination of steam, such as silica carryover which would
deposit oi the thurbinc blades. This chemical feed system, combined with boiler blowdown,
demincralized make-up water quality, and boiler manufacturer's recommendations provides
the basis for each Unit water cycle quality.
The system feeds chemicals to the boiler fcedwater to control the ph and to inhibit release
of oxygen in the boiler tubes, drum, supeheater, and economizer
Diluted hydrazine is added to remove dissolved oxygen contained in the feedwater and to
control the ph value.
However, during plant startup and shutdown, aiimonium solution0
is added to control the ph of the feedwater, and is injected in the condensate pump
discharge. During long terrn shutdown, concentrated hydrazine is used to protect the boiler
from rust.
The sodium phosphate solution is used [or inhibiting caustic ernbrittlenic-t, and to remove
The sampling rack supervises the quality of make-up water, condensate. feedwater, boiler
Tie c hemical feed system consists of the following equipment manufactured by Nikkso
Company Ltd.:
47
JIAMSII()1O UNIT I
SAMI'[[N(; RAC(K
indicated that
Intcrviews with O&M personnel, walk-downs, and reviev of plant records
as
the chemical feed and sampling rack are functioning on automatc/iifanual:operatiol
designed.
Assessment
O&M
.JAMNSIOR(
UNIT I
Description
fine suspended solids and organic matter carried from the coagulation-sedimentation
set is in rinse or
imldicated the
Interview with plant personnel, walk-downs, and
review of plant records
is functioning
The system components were included in the First Inspection Report. All components
B agitator
gear box and filter scrubber air blower A. The gear box was replaced and blower
finish was repaired.
//
JAMSIIOI(O
WATER
JNI[
ATMENT SYSTEM
II'AREFR
[he systern appears to be in satisfactory condition based upon the dala reviewed and uni
walk-through inspection. -owevcr, we have observed that when the coagulation tanks are
cleaned-up, the mud is dumped on top of the discharge pumps and pipcs which Will cause
increased maintenance for thcsc components.
Assessment
50
h1
IAMIHORO UNIT I
I)escription
aI
To facilitate the emptying process, a pressurized
pipc
Condition
51
.JAI'vSI[OIO UNIT I
COAGULATION SE)IMENTATION TANKS
A -s c s imcii I
lhese
frequent changing vet and dry conditions.
The internal metal cone is subjected to
and normal repairs of the internal eonc can be
conditions accelerate the corrosion process
high O&M costs arc also being incurred.
cxpected inI apprOximately 10 years. Abnormally
are
to determine if modification to the tanks
Itis recommended a study be performed
[casible to reduce these costs.
52
Description
regenrertion.
/Y1
,JAMSIIt1k() tJNI' I
SYSTEMS
WATER AND \VA 'EWAI'R "TRj [AIM[NT
diluted
by
steps
two
water is returned to sitoage pond.
and were
included in the First Inspection Report
The water treatment components were
of plant
plant personnel, walk-downs, and review
with
Interview
condition.
in satisfactory
are functioning satisfactorily on auto and
records, indicated that all the above systems
semi-automatic modes as designed
Assessment
.JAMSII()4O UNIT I
WAT'I'1
'ItRLATMENT
BIllLDING
)Cscription
grounds ol
thc main power plant
of Unit I is located inside
tanks
metal
ar
1he water treatniert buildingmain
there
building
this
In
post.
entry guard
the left sid just passed thce
water. Thc
are used to demineralized tile pretreated
with acids, anions, and cations, which
The corcle
as a concrete frame structure
vatet treatment budding is constructed
placed arc
are
paint. The floor where tile tanks
surfaces arc finished with mortar and
Outside
surroundings are raised in case of spills.
covered with acid resistant tiles and their
trenches
has a terrazzo finish. There are covered
of tile protected tank areas the floor
below the walkable floor level.
frame
exiernally or internally. The structural
No defects or deterioration were visible
the outside perimeter there were no signs
elements have mortar finish on them. Around
of settlement observed.
Assessment
55
,JAMSI Ot,()
JNI'I' I
5 compression
650 kW, 150 rpm, 12 cylinders. iL,
ilic diesel engine is type S12 NPTA,
b%
lithe diescl engines -,is .,nanufactured
systems.
combustion
Injection
direci
ratio with
Mitsubishi.
air compressol
control panel, air circuit breakci...,.
The diesel-gencrator isequipped with
equipment which include:
(I)
(1)
(2)
70 0 rpmn
mm stroke/
Vertical 2-stage air compressor of 70
3.7 .\W 380\1 electric motor, and
air ieccivers of 300x2 m" capacity
Assessment
and adherence to
Assuming proper
selection of components
20 years service.
nianufactturer's O&N4
POWIR TRANS1ORMLI ,S
outidoiti
on
I)r
oil
The: main power transformer is manufactured by Fuji Electric Company, outdoor,
294.2
-1
4.91% at
oil
l)y Fuji i ecilic Company, outd,: or,
o)
ufactur(d
Is is a na
Ltd., oil
10%
Current Condition
Assessmient
should be suitable
recommended O&M procedures, the transformers
operation.
.JAMSII(I0 () UNII
T
6.6 KV N I-IAI.CL
ZIS
400\V I'O\yt , CI N
S (MC(C)
CINIFI
400%, MOTOI, ('()NTN ()I.
flescription
Assessment
.IAMSiI C)I()
UNINTER|UITItILM
UNIT I
Description
400
UPS. The input voltages are 220 VDC and
Unit I has two sets of 30 kVA static type
One set is used for all the computer
VAC, and the output voltage is 110 VAC.
to supply 120 VAC for tc following, control
equipment, and the second set is used
ap plications:
o
o
o
o
o
o
o
o
Assessment
adherence
to the manufacturer's O&M
Assuming proper selection of components and
service.
59
JAMSII[OI (
tJNIT I
!) C,; ci ipt on
From Unit
kV switchyard
From Unit I1 startup transformer to the 220
Assessment
/.)
.IAMSIIORO
UNIT 1
Description
of the auxiliary transfdrmer, startThe 6.6 KV cables are used on the low voltage side
power centers, and as fccdcrs to tile 6.6 KV
up transformer, subfceders to tile 6.6 KV/400
motors The cables arc non-cornbustiblC type.
Assessment
JAMSHIO() UINII
I)C
l '
TATION BAFlRI S
l)escripthC)
l
The
by Furukawa (Ff' ) 2375)
manufactured
system
battery
VDC
220
a
Unit1 I has
rated
nominal voltage of each cell is 2 VDC,
hattcrics ac cad acid type, 110 cells;
capacity ;it10 hi. is 2000 amp-hir
200-230
thyristor type, self air cooled. S0O amp,
The uni has one three phase rectifier,
VDC
DC
review, of plant records indicated that the
Interview with plant O&M personnel and
batteries and chargers are in good working condition.
Assessment
62
JAMSIIIZ() UNHIi
IG OARWMI)RIN(;
LOCAL CONTROL I( X[ES,
CONTROl. CABII"', CA iii.I: TRAYS, AND [)UC I
Descrilion
shielded.
Assessment
and adherence
Assuming proper selection of components, covering the exposed manholes,
BTG boardWiring,
control
to the manufacturer O&M procedures, tile local control boxes,
cables, cable trays, and ducts should provide 20 years service.
63
JAMSII(O)() UNIT I
Assessment
64
.JAMS I101M()
UNIT I
FlUll
[)lN(S
F.*EL
on the extension
side but remained in place separating
corrugated sheet metal panels. The
65
,IAMSIIOR0
"lu
cC
JNI'
CONTROL 1UII)"INGS
& (:ICNTIIAI.
IN'Jlll'l"
concretC.
level aC raiscd [from the nat
equipment onthC ground floor
turbine pedestal.
on a reinforced concrcte
;re supported
common mat
the
for
except
and the gencratol
building
turbine
turbine
"'The
thc
lhe turbine pedestal is housed within
foundation.
top of the mat foundation
a solid limestone formation. The
rurbine
The mat foundation is built on
foundation is at El. -2.00 meters.
mat
the
of
bottom
ihe
is at El. -1.00 meter
at El. -3.2 meters and mat
at the mat foundation top is
area
condenser
and
)cdcestal
of mat was poured in ihree
605 meters. This thick portion
El
at
is
bottorn
foundation
layers.
of the turbine
looks like an "L" shaped extension
which
powerhouse.
main
Part of the
is re[erred to as the
on its own mat foundation.
It
located
is
view,
plan
in
the
building
is 26.0 meters
the North/South direction it
In
2.
and
I
Units
of
Central Control Building
direction itis 41.5
108, 201 and 207. In East[cst
107,
axes
column
the
wide b-twcen
and condensing
column P. It houses the chilling
through
J
column
from
long
meters
floor level there
at the ground level. At the mezzaninc
pumps and the air compressors
and showers
water analysis laboratory, lockers
rooms,
equipment
control
are battery rooms,
control room, computer
operating floor elevation, the
the
At
panels.
relay
and auxiliary
is 1.5 meters distance
with amenities arc located. There
room
shift
and
meeting
room,
control building. The two
building and the J axis of central
turbine
of
1-axis
the
bctwccn
roof. Th'e
jot,' from the foundation level to the
buildings are separated with an extension
to the turbine
The external walls arc similar
structure.
steel
a
as
designed
building is
concrete over
The floor slabs are cast in place
elements).
concrete
building (prefabricated
The roof covering is
with the welded studs onstcel.
the
steel beams compositely connected
Top of the roof is accessible from
building.
turbine
the
of
roof
the
also similar to
is a stair passageway
corner of the building. There
staircase located at the southeast
shaped extension.
building and the roof of its ""
bctween the roof of the turbinc
.JAM
"I'UIINl" & (-
I(ORO tJNIT I
ITAI CONTROI,
Secondary
bolted.
are
beam connections
or peeling
There were no signs of chipping
painted.
were
elements
elastic
no
have
to
joints seemed
underneath.
I '"
Proper corrective measures are required.
67
/.
%
cs
nl I
not
turbine building, including oundalliions should
The reinforced concrctc portion of the
'"1Vc steel structure should serve equally
deterioratc for the next 20 years of operation.
maintenance cxcepl to follow ood housekeeping
long withoul any anticipated repair or
work
Roof insulation may require partial epair
tjlts ind repailnt surfaccs when requircd.
aifter 10 to 15) years
?
l:CI-NERATOIR COMI'(NIN'S & S'SI'MS
.SIA
Boiler Works
were manufactured by the [latlbin
The Units 2, 3, & 4 steam generatois
steam jencralor
residual oil and natural gas The
The units are equipped for firing
of the following:
components and systems Cvaluated consist
Steam Generator
Superheater/RehCater Tubing
SuperhcaterfReheater
Headers
SuperheatrC/RcheatCr
Piping
Economizer Inlet
Header
Economizer Tubing
Steam Drum
Boiler Enclosure
Air Preheaters
Boiler Structure
BEST tVAILARI
69
COPY
.1AM .I(
)IR,()
INII ')
., 3 & 4
) cs( r 1i io
and
cssentially duplicate hoIcls d.csigned
are
gelciatmis
steam
4
and
3,
Units 2,
680
PRC. Each boiler is designed toproduce
Works,
Boiler
[larbin
the
by
manufactured
cm' (2000 psi) and 541"C
hr.) main stcani at 140 kg per
pi
lb.,
(1,500,000
hour
pet
tons
lb pci hi ) at 23,9 kg pet
The boilers
same plan cross-sC(iional dimensions
the
have
pass
convection
furnace and front upflow
is 982
rear, downflow concctlion pass
The
deep.
meters
9.66
and
9.82 ineters wvide
front
.a back-jo-back arrangeieilnt with the
forms
and
deep,
meters
6.14
and
meters wide
circuits are fully
reheater, boiler, and economize!
superheater,
All
pass.
convection
drainable.
oil o
currently equipped to fire either residual
are
and
fired
tangentially
are
The boilers
natural gas.
the
and the method of firing indicate that
generators
steam
the
of
design
The overall
Or they
of Combustion Engineering Corporation
licensee
a
either
is
Works
Boiler
H-arbin
Engineering. This
company affiliated with Combustion
have a technical interchange with a
Engineering for at least twenty-five years
is a proven design of boiler used by Combustion
for a significant number of units.
//2 boiler has
of time. Unit
short period operating
a relatively
for
time period
the
in
operated
been
have
currently
are
4
boilers
and
The
had the one-year inspection. Units 3
prior to the first year inspection.
One leak
in the boilers since initial operation.
There have been only two tube leaks
to
on June 9, 1990. The failure was attributed
occurred in an economizer tube on Unit 2
the
Since there have been no similar failures,
external abrasion of the tube at a support.
of a
be
an isolated incident which is not indicative
to
considered
is
leak
tube
economizer
generic design problem.
3;T
70
\.A'-
,P.0
NM) dtails
1991 in a su(pcrhe.lIcr tube 1in ln1 3
lhc wcond leak occurred Malch 10,
it is not considered W Dc ird lcalivc of a
are available concerning this [ailur,i howevei,
recurrig tube failure problen.
ycal
problems on boiler 2 I)O[ to. tie irst
There wee no reported major operating
Ihe
inspection as aliril)ulICd :O plug QaIeC of
ins peCion [he load limitation prior to (lh
Assessment
to achieve satisfactory
no planned modifications or major repairs required
71
2,
D)CSC1r i[tOll
gas
combustion air to tile boiler; direct flue
heated
providc
systems
gas
flue
and
The air
and iccirculatw
through the air hcater, and to the stack,
fiorn the outlet of the economizer,
the Jower furnace
economizer outlet and inject it into
a portion of the flue gas from tile
c
system is to exicnd the control ran,
recirculation
gas
the
of
purpose
Thc
of the boiler.
steam temperatures.
ot tile supcrheater and rcheatcr outlet
draft fans, two (2)
forced draft fans, two (2) induced
Major components include two (2)
air ducts,
vertical shaft regenerative air heaters,
steam coil air heaters, two 26-\11-1370
and the
joints,
fans arid ducts, dampers, expanson
recirculation
gas
(2)
two
windboxes,
130 meters
boiler outlet to the stack is approximately
Tile boiler outlet flue connecting the
(425 feet) in overall length.
Comments and
Current Conditions
unit load
on unit #2 that began 20 February 1991,
Prior to the first year inspection outage
limitation
because of an induced draft fan capacity
was limited to between 80 and 100 MW
a
maintain
to
open and tile fans were unable
wherein the fan dampers were 100 percent
gear box
a noise was heard in the auxiliary drive
negative furnace pressure. In addition,
of the B prcheater.
cold end
72
(,1
Avecsmcrit
/II
JAMSIHOR()
BOilER COM
IJN'S 2, 3 & 4
SYSTEM
.I
UST()N
)escription
Gas
exclusively since being placed- in service
Boiler #2 has been fired on residual oil
the unit is now capable of operation on natural
firing provisions have been completed and
on both gas and residual oil.
gas. Boilers #3 2nd #4 have been operated
the burner deck and via the control iooii!
Observations of burner operation from both
with either gas or oil operation. Fron
television monitors found no problems associated
oil leakage has occurred
at tle four corners
Assessment
tL Sr A\vACILALwI- .O?
74
*JAMSIOR(
UNITS 2, 3, & 4
[)eccri
piln
.........
.
.,,..
L.;.
Asscssmcn
of
increased O&M costs. Assuming repair
The above mentioned problems will cause
of component, and adherence to the
existing problems, proper design selection
6perating procedures, the system should be
manufacturer recommended maintenance and
suitable for 20 years continued operation.
BEST AVAILABLO
76
COFnYf
I1OfLER INSTRUMENTATION
AND CONTFROL SYSTI':
AND AUTO REGULATION
[)escrip1ion
by Xan Instfumcni Factuly, Type YSEach unit has a boiler control system manufactured
is designed
25% to 100% of full load. The system
Automatic control range is from
80.
within
I2 Kgcmzg, steam temperaiure selpoint
to maintain steam pressure setpoint within
mm
SC, and drum level serpoint within 75
functions:
to provide the following regulation
The boiler control system is designed
water drum level, utilizes
Feedwater regulat ion: which controls
element (wateir
Cle
77
oil.
Atomizing steam pressure regulation for fuel
2)
3)
4)
5)
6)
R.O. Flow
7)
8)
10)
11)
R. H. Spray Water-A
12)
13)
14)
15)
16)
R. H. Spray
Superheater
Superheater
S. 11. Spray
S. 1I. Spray
17)
18)
9)
Water-B
Sec: Spray-A
Sec: Spray-B
Water on Side-A
Water on Side-B
.1
IOILEIR INS'R
19)
20)
21)
22)
23)
24)
25)
26)
02 Station
Deacratoi Level Control I
Deacrator Level Control 2
Gland Scaling Steam Pressure Control
Condensc [xvcl Control
B.F.P. No. I Flow Control
B.F.P. No. 2 Flow Control
Assessment
to manufacture's recommended
Assuming proper selection of components and adherence
20 years life with higher than normal
O&M procedures, the system could be suitable for
inconsic'ency and auto regulation are
O&M costs.
Repairs of the instrumentation readings
needed for safe and reliable operation.
B-LoS
79
AV,"!AVI- COIY
JAMSI[OR() tJNITS
AUXILIARY STEAM SYSTEMS
, 3 & 4
-
IiI.E.
SI )I
[Description
Units
consist of a single house boiler sdrving
The boilcr-rclated auxiliary steam systems
tile main steam generators
2, 3 & 4 and the soot blower system for
2-drum, natural circulation, type SZYZO-10
The house boiler is a Harbin Boiler Works
boiler produces
Per CMEC Operating Manual, hc
boiler rated at 20 tons per hour.
located in
with light oil through two (2) burners
saturated stream at 169-C, and is fired
operates
forced draft and induced draft fans, and
the front wall. The unit is equipped with
at the
furnace. Trip/trouble alarm is available
with balanced draft maintained in the
the control room.
annunciator window on the BTG Board in
(16)
of the steam eenerators consists of stxteen
The steam soot blower system for each
(20) type CC-I long
short retract blowers and twenrty
type RC-111 furnace waterwall
rcheater, and economizer cavities, plus
retractable blowers located in the superheater,
source of soot blowing steam is tile crossover
two blowers serving the air preheaters. The
inlet
outlet and the secondary superheater
pipe between the primary superheater
downstream of the desuperheater.
80
(-"
CO",
JAMNI ()I(()
INIIS 2, 3 & 4
Asscssmcnt
Normal
arc suitable for exiended operation.
The house boiler and soot blower systems
icstoring
in good working order,
maintenancc is anticipated to keep the systems
reliability
boiler is recommended for saferv ahd
automatic operation of the, house
considerations.
*JAMSII( O)
UNI' S
, 3 & 4
1ZI.
I LEI, STIZ UCTU
Description
JAMSII)RO
"NIS 2, 3 & 4
Ai
much
T'he gussct plate at the end COflnction was
d to one
welde
This forced tile spacer platCs 10 be
thickness.
plate
spacer
tih
than
The two
thicket
tile spacers became ineffective"
Therefore,
angle.
other
the
;ingle, and not to
The member,
crossed section as was calculated
ingles are not forming a combined
'The spacers
thc forces for which it ,was designed
resisting
of
capable
not
is
ihereforc.
the proper thickness.
,hould be replaced with spacers of
structural
been connected arbitrarily to the
have
to
seem
supports
pipe
They are
by
supported
is
impression
members. This
ticd to each other
of the elements are not properly
some
of
ends
the
and
of the
long,
axis of channel section and some
weak
tile
using
formed
are
boxed
Cantilevered supports
continue tile
.JAMSII(OR()
URINE.([]NIIRATOI
UNITS 2, 3 & 4
Noz.zle Blocks
HP Diaphragms
Intermediate Pressure (IP) Outer Cylinder
IP Diaphragms
Main Steam Stop Valves
Control Valve Steam Chests
Reheat Stop Valves
Interce'ptor Valves (Shell Mounted)
Lead hping
-l1) Turbine Lead Piping and [P Turbine
IP Blades
..
LP Blades
86
L-L,_,.
.x1haust Hoods
L1
L Mid Cylinder
No. 6 Diaphragm Carricrs
LB Diaphragms
LP Crossover Pipes
Generator and Excitation - Electrical & Isolated Phase Bus Duct
Generator Rotating Components - Mechanical
Generator Rotor Forging
BOILER STRUTFURE
BF[ST AVA!L.AthFcl
85
+ ,,,.,-,r,.+,.CO
3 & 4
.JAMSIIOI'() UNITS 2,
UI
'
II1(;II Ip1IRss tJJ
STATIONAIRY COMPONENTS
I)cscriptioln
Ptrc
1eof ths
Har
ubneWr'
Turbine Works
for cach of thcse three Harbin
components
stationary
outer cyjinder with a
PIF
The high pressure
following:
81 5 38 turbines are composed of the
connections, -P
N210-132/53
four (4) main steam inlet
with
and
joint
for diaphragms-stages
conv nilonal bolted horizofttal
and the locating bores
blocks
nozzle
10-12, IPouter cylinder with
inner cylinder withI assembled
diaphragm carrier for diaphragms-stages
2 through 9, No.
integral to tle
valve bodies fabricated
interceptor
with
joint,
carriers
conventional bolted horizontal
No. 2, 3, 4 and 5 diaphragm
connections,
steam
reheat
and 22
cylinder and with four (4)
and 20 and, stages 21
stages 16-18, stages 19
for
13-15,
for diaphragms-sta'cs
with
fabricated integral
turbine lead piping
and
with Jamshoro plant maintenance
Interviews
the
during
No problems were reported
period. On Unit 2
are still in the warranty
from the review of the
operating personnel on Units 2, 3 & 4 which
and
interviews
the
were uncovered from
2 HAP inner and
no significant problems
was reported on the Unit
deformation
Some
Units #2, 3
first year inspection report.
6 & 7, 1991 (See Jamshoro
June
of
incident
thermal
reported were small and
outer casings after the
in good condition
noted above all appear to be
components
stationary
The deformation
The high pressure
and the maintenance reviews.
interviews
personnel
plant
as 4mm joint
based on the
2 (reported to be as much
No.
Unit
of
casings
with
of the HP outer and inner
to be excessive based on experience
appear
not
does
casing)
opening on the HP inner
similar components in secme.
'I
RE.S.SUR-
STATIONARY
-OMI'ON I"N r S
Assessment
Based on the evaluation performed using dcsign data, infornation obtairicd from the
similar
on Unit No. 2, industry expcfneCnGC with
interviews, reports on tile thermal incident
in the
units no major problems arc anticipated
dcsign units and the young age of these
to Units
practices as [or Unit No. 1 being applied
near future. Assuming similar operating
and the
metal life consumptions for the [4P casing
No. 2, No. 3 and No. 4, similar turbine
the same severity of start-ups for the next
main stop valve may be expected. Assuming
and
with a [minimum capacity factor of 60%
twenty-years and assuming base load operation
metal life
4 hot), it is expected that the turbine
10 start-ups per year (2 cold, 4 warm,
unit No. I
stop valves will be very low, similar to
consumptions for the IHP casing and main
at fuLurC
and' outer casings should be monitored
The distortion of the Unit No. 2 H-P inner
maintenance outages.
DY
C ('
'
TURBINE ROTA'IIN
'
N' S
l)escription
'.ssessient
rotors and the IP rotors may be roughly
The turbine metal life consumption of the HP
for Units No. 2, 3 & 4 as was
approximated by assuming similar operating practices
is the Unit No. 2 HP bowed rotor which
experienced on Unit No. 1. The one exception
replaced with
a new HP rotor with
experienced plastic deformation but it has since been
virgin material.
E &AVAILABI.E COPY
90
"'UIUl
3T AWVAILABI.iJ. 2..
3T
91
Description
Assessment
92
E-LECTIIICAL. &
ISOLATED I'IIASE BUS DUCT
Dcscrip(ion
50
247 MVA, Type GFSN-210-2, inanufaci!,red by IEEMW,
0.85
rpm,
Hz, 15.75 5%
kV, 9.056 kA rated cuY'ent, 3000
field current, class
exciter, 1165
Type JL-1165-4, manufactured by HEMW. AC
kW, 431V, 1562A. 0.91 pf. 160 -iz
exciter, 46
Type TFY-46-5a, manufactured by IlIW, AC
kW, 161/93V, 165-285.8 amp, 0 875 pl. 500 Hz.
by Fuxitn
The isolated phase bus duct is manufactured
enclosed bus factory, type GFM-20-1, aluminum conductor,
rise less
rated 20 k\', 150 kV BIL, conductor temperature
b'js circuit
than 600 C with aluminum enclosure. The main
current.
is rated at 10,000 Amp with 400 kA s\qnmetrical
560 kA
The sub bus circuits are rated at 2000 Amp with
symmetrical current.
.*AMSI[OIM()
UNITS 2, 3, & 4
-EL-cTRICAI- &
Assess ment
needed to
of carbon brushcs and slidc ring i
grinding
precise
as
such
repair
Normal
selection of
repairs arc made, proper design and
overcome the overhcating.. Assuming
recommended maintcnance and operating
components and adherence to the manufacturer
to
isolated phase bus duct arc expected
and
system
excitation
generator,
proccdurcs, the
be suitable for 20 years continued operation.
94
Dcsc' +plion
T-hc
generator
rotating components-mechanical
on the Harbin
Works QFSN-210-2
Assessment
& MONIIORIN(G
ItBINIE SUI'[:VIS()zY INSTRUJMENTATION
LFcceritricity or rotor
o
o
o
o
o
o
o
parameters:
The system provides.protection function of the following
Speed:
when over
Alarms when over than 110%, and trips turbine
116% of rated speed.
Axial Displacement:
at
Alarms at +0.8mm and -1.0mm, trips the turbine
& -1.2mm.
Vacuum Drop in
Condenser:
4-1.0mm
the AC
the lube oil pressure is lower than 0.6 Kg/Cm',
When
\
When lower than
motor driven oil pump automatically starts..
automatically starts
0.5 Kvf/Crr? the DC motor driven oil pump
oil pressure is lower
and the turbine is tripped. When the lube
of the turbine is
than 0.3 Kgf/Cm the rotor turning gear
KgfiCm2 is utilized.
stopped. Pressure regulator with range 0.2
ata the
Alarm at 0.25 ata, and when lower than 0.35
0-760mam Hg
turbine is tripped. Pressure regulator with rang
is utilized.
& MONI'I()IUN(;
"rURBINE StJP'ER[VISORY INSTRUMENTATION
personnel.
Specific problems on the units arc as follows:
Unit 2:
Unit 3:
Unit 4:
Assessiment
kAB LL C 0i.Y
B E S~/AlL"
CON'I'OLS
)escription
5 3 8 is equipped with both electrohydraulic (EHC)
The steam turbinc type N210-122/538/
A common actuatol is used for both
and mechanical-hydraulic control systems (MI-CG).
systenis. The
switching valve to transfer between the two
the El-IC and MHC with
over the full speed range from turning gear
speed-up system performs closed loop control
-0
Y*j~
CONTROLS
STEAM TUIR BINE"CONIIOILS AND COORDINATEID
The O&M personnel reported that tie tracking system of the MHC docs.not work,
to MC,
which means lhat in case of failure of the EL:-IC and automatic switchove
a 15
.,here
incidents
two
reported
MW upset takes place. The O&M )ersonncl
thc
activate
To
producing 150 M\v
MW bump was experienced while tie unit was
pilot valve at the turbirC
MiIC, the operator had to manually lift the changeover
front.
days
between MI-IC & EHIC once every two
The O&M manual calls for switching over
lack of records which support the
to prevent the convertor from jamming. Due, to
requested the plant opeation to demonstialc
unreliability of the Ef-IC & MI-C system, we
2 was on line. The plant operators dcclincd
the switchover from E-IC to M-IC while Unit
the bump would take place and did not want
our request on basis that they felt confident
to risk upsetting tile system.
Assessment
CCJH
iiiC;Ii
IYI'ASS
SYSTE'M
Dcstription
the
by Sulzer of Switzerland and onsiStS of
The turbine bypass system is manu(aciurcd
following:
DesupcrlhcatIg stations.
and
Assessment
100
1173 L
Description
3 8 53 8 type
Harbin Works N210132/5 /
The turbine-generator components/systems on this
indoor unit consist of the following:
Turning Equipment
Turbine Bearings
Turbine Pedestals
Oil Coolers
IBF'T AVAIL 1.
COPY
fixed type.
is the self aligning type and the other four (4) turbine bearings arc.
& 4
JAMSItOI(() UNITS 2, 3
'
\IS
"'Ul(l INN'-(;I-RN-I ATOR AUXILIARY COM'ONENI/SysI
Gas Analyzer
Control Panel
system that cools the generator stator.
separate
a
is
system
water
cooling
The generator
COMI ONI-,NS/SYS'EMS
IURBINE-GENERATOR AUXI-LARY
Assessment
/(
Feedwater System
Condensate pumps
Feedwater heaters
Dearator
Cooling tower
Condenser
Instrument Air-System
Fire Protection
Emergency Diesel-Generator
Power Transformers
(MCC)
400V Power Centers, 400V Motor Control CentersBESf
AVAILA
LE DOCLJINI '"
JAMSI{ORO UNIT I
SYSTEMS
BALANCE OF PLANT COMIAONENTS &
/ /)
I)cscription
economizer
from the condenser Outlet to the boile.r
The ecedwater system conveys water
steam jet air
well as condensing the steam in the
as
heating
of
stagcs
eight
inlet through
addressed
steam condenser. The major components
gland
turbinc
the
and
coolers
cjeclor
fccdwater
feedwater heaters. dearatol and boilr
in ihc report are the condensate pumps,
pumlps
foi each unit Under
condensate pumps are provided
driven
motor
capacity
50%
These
with the third
load, two pumps would be opeimng
normal operating conditions at full
with stainless steel
are vertical centrifugal nulr-stagc
pump in stand-by mode. The pumps
impellers and shafts.
heaters per unit.
three high pressure closed feedwai
Thre are four low pressure and
have
2,-2)
(1/ I &
type. The two lowest pressure hcatcr
All heaters are vertical "U" tube
high pressure
copper nickel alloy tubes; the ihrece
tin brass tubes. Heater
3 & 4 have
heaters have 15 Mo3 alloy tubes.
tank. The
mounted on a separate horizontal storage
The dearator is a cylindrical tray type
in the effluent not vieaier than 0.005 cc/I.
indicate any
of First Inspection of Unit 2 did not
A review of the rather sketchy Report
three trips
A review of the unit trip records noted
system.
feedwater
th1e
with
problems
operating and
feedwater pumps. DiscussionSs With
boiler
tile
by
caused
were
2
of Unit
valve.
trips were duc to a leaky fecdwater control
maintenance personnel indicated the
solved the
control valve was replaced and this
Maintenance personnel stated the feedwater
problem.
units.
problems with this system for all three
Ph,nt personnel indicates no other major
~ ~ ~ t.tC' '
;; ,.I , 'tl
4.J
and
condition based on the data reqviewed
The fcedwater system appears in satisfactory
noted.
unit walk-through inspection.
Assessment
and
proper design and selection of equipment
Based upon the age of the unit, assuming
operating procedure, the
recommended maintenance and
manufacturer's
the
to
adherence
be suitable [or 20
systems for all three units should
feedwater
the
of
components
major
major repairs or replacement
years continued operation without
.IAMSIIOR(
Dcscription
bearing
cooling water for the condenser and the
The cooling water system provides the
in the icporl are the cooling rowe'r, circulating
coolers. The major components addressed
a separate
towCi structure is covered in dctail in
ware p)ulmps and condenser. Thic cooling
section
is
draft multi-cell cross flow type Fhe structure
induced
mcchanical
is
towe
cooling
The
PVC.
reinforced concretC and the fill material is
conditions, two
pumps are provided. Under normal
Three 50% capacity ciculating water
water pumps are
in stand-by.
pumps are operating and one pump is
vertical, single suction mixed flow type.
The circulating
based
on the data reviewed and unit walkThe system appears in satisfactoiy condition
V2
C1.,
...
,.
through inspection. No unusual conditions were noted.
/1s
Assc,smenn
assuing proper
Bascd upon the newness of 1hc plant, correction of costing dcficicncics,
manufactureIrs rcommcndced
design and sclection of components, and adherence to the
thc cooling water systems
mainicnance and operating h)roccdure, the major components of
major rcpairs or replacement
should be suitable ror 20 ycars continued operation without
109/
tDescription
the same except for rmino differences
The cooling towers of all units are in general
I for
Refer to the Description given for Unit
between the Unit I and Units 2, 3 & 4.
details.
this
tower, there was nc obseivable damage. In
Except in one cell in the Unit 3 cooling
sloped fiberglass baffle
unit, a shaft between tile fan notor and gear broke damaging the
wall, fan stack and fan blade.
structurcs.
The concrete parts of the structures
indicate any major chipping, cracking or deterioration.
Assessnc nt
R-DO(/,I
BST AVAII.Atl
110
"
I)
teion
dlycl
control
air to the boiler control system, burner
The ail compressors provide instrument
extraction steam line
,,ystcm,and reverse current valves of turbine
Unit
review of Unit 2 trip report rodcated that
Interviews vrvth plant O&M personnel and
instrument air pressure. The maintenance
2 was tripped on May 19, 1991 due to low
pretreatment facility was out of service
personnel indicated that the transfer pump at the
the instrument air compressor through the
at that time which provided cooling water for
the compressors wich in turn tripped
clallficr.
The low level of clarifier water tripped
the unit.
BEST AVAIAU-F_1)lC0tI M
.JAMSIIORO
UNITS Z, 3, &' 4
Assessment
frequent
of components, normal repairs to alleviate
Assuming proper design and selection
operating
and
recommended maintenance
tripping, and adherence to the manufacturer
without majol
suitable for 20 years continued operation
be
should
system
the
procedures,
wilv increase the
cross-ticing the instrument air system
However,
replacement.
or
repairs
be installed.
FIRE PROTECI'ION
Description
The system
(3) l elighting
(2000
qulrment with Local/Remote capability
l
Lxtriguishing
Chemical
of
Diy
Sets
(6)
Kg each)
(3) File Protection Panels
(6)
each)
(1 6 2 ) Hand Carry Power Chcnical (8 Kg
Current Condition
Assessment
of the
hose racks provided. Immediate clean-up
the
in
reinstalled
be
should
hoses
Fire
of
avoid potential fire. Assuming proper selection
fuel oil unloading facility is needed to
recommended O&M instructions and
components, adherence to the manufacturer
continue to operate for 20 years.
perodical functional te',, the system should
...
L!
,, r.,
CHEMICAL
Description
release
feedwater to control the ph and to inhibit
The system feeds chemicals to the boiler
superheatcr, and economizer.
of oxygen in the boiler tubes, drum,
eedwater and
dissolved oxygen contained in the
Diluted hydrazine is applied to remove
an ammonium
during plant startup and shutdowi,
to control the ph value.
However,
of the feedwater.
boiler
equipment:
(0.66 liter/minute)
hydrazine recorders.
((k
Assessment
and
rack room. Repair of conductivity meters
Proper ventilation is needed in the :ampling
increased
essential. The current condition vkill cause
restoration of automatic functioning is
O&M
of components, adherence to manufacturer's
selection
proper
Assuming
cost.
O&M
20 years.
procedures, the system is expccted to last
~KfAVAILAM)d[F
nlOCjrr
Description
at the Indus River to water reccivirg tanKs
Ihe water is pumped form the intake structure
to
coagulant. The clarified water is pumped
to eliminate flocculation, then treated by
water tanks.
clarified water tanks then to the service
(9)
(6) Air Scrubbing Blower, Rotary Type (28 Nm'/min)
(6)
to 200 m:/hr)
Treated (Clarifted) Water Transfer Pumps (110
(6)
(3) NaOH Chemical Storage Tank (10
m
(3)
(9)
Series
(6)
(9)
(6)
(6)
(6)
(6)
(6)
(3)
(6)
RACK
CHIEMICAL F[IED SYSTEM & SAJIPLING
ptionl
formatior, corrosion,
nsate and feedwater are chemically adjusted to prevent scale
Which would
carryover
silica
as
such
c embrittlement, and contamination of steam,
with boiler blowdown,
it on the turbine blades. This chemical feed system combined
manufacturer recommendation provides
ieralized make-up
v.ater quality, and boiler
isis for each unit water cycle quality.
.A-
'
.JAMSIIORO
UNITS 2, 3, & 4
\VA'I'P-IR!I.EAMENT
(3)
(6)
(6)
SYSTEM
the third is
sedimentation tanks are in service, and
coagulation
three
of
out
two
Normally
once every year and requires
ie cleaning of the tank is done manually
on standby.
3 pneumatic control system of tile mechanical
approximately 3000 person hours. Unit
indicators.
miscellaneous pressure, flow, and local
filters is out of service as well as other
pumps we-.re
coagufation tank raw water transfer
(65
six
of
out
(1)
one
July
in
2,
On Unit
periodic
control and requires a high degree of
in serVice. The equipment runs on manual
to the service operating conditions.
maintenance and parts replacement due
Assessment
encountered.
117
JAMSIIORO
UNITS
2, 3 & 4
Description
The "coagulation
For each unit there arc three coagulation sedimentation tanks.
1, but there are some
sedimentation tanks externally look similar to the tanks of Unit concrete.
At the center
constructed of reinforced
arc
tanks
The
differences.
structural
diameter. The water
portion of the tank there is a cylindrical space with 7.8 meters inside
space. There is an agitator mounted on the
to be coagulated is pumped into this cylindrical
part. The platform is covered with an
cylindrical
tie
over
platlorm,
top
the
as
slab acting
covet
I tank does not have any slab or roof to
Unit
columns.
on
roof
concrete
elaborate
5.85 meters and the top of roof is at EL..
the agitator motor. The top of platform is a( EL
9.72 meters.
the
oriented wall like columns. Betw.Yeen
radially
on
supported
is
wall
The cylindrical
of the
into the shape of a cone. The bottom
radial walis, the cylindrical wall Bares up
of 15.60 meters is formed like a fat spherical
sedimentation tank with an inside diamctcr
pit. The
pump it out from the centrally located
bowl in order to collect the sludge and
of the
positioned troughs at the upper elevation
radially
the
on
collected
is
water
clean
trough
radial troughs are connected to a circular
coagulation sedimentation tank. All the
and
tank diameter at the top is 25.00 meters
which feeds the outlet pipe. The external
m thick
0.0 and El +3.50, the tank wall is 0.35
19.40 meters at the bottom. Between El.
and conical in shape.
or
tanks was fair. Therce were no criical leaks
The concrete forming of the coagulation
of the tanks reflected natural ground
seepage observable from tne walls. The surrounding
collect fine clay sediments and need to be
conditions with no pavement These tanks
Unit 1, but not as frequently. The automatic
routinely emptied similar to the tanks of
required
so that a long duration of down time is
sludge removal system is not functioning
During this process the walls and surrounding
in order manually to remove the sludge.
below the agitator is more difficult to access.
areas get dirty. The central cylindrical space
Assessment
They
tanks should all provide 20 years service.
Structurally the coagulation sedimentation
taaks of Unit 1 since they have less
are
superior to the coagulation sedimentation
structural steel parts to corrode and lesser dowitite due to sludging.,
)escription
less
produce treated water with conductivity of
The water trCalrilnt systcm is designed to
gcn
ox
of less than 0.015 ppm, and dissolved
than 0.5 us/cm at 25"C, with S102 (-,1licnn)
of less than 0.3 ppm.
per unit.
of demineralizing system arc installed
sets
(2)
two
t/hr,
25
is
capacity
design
hll
Boiler Works.
(6) Regeneration
Water PumpS (30.6
(6) Booster Pumps (30 6 to 64.1 ml/hr)
Injection Type
to 60 m'/hr)
(6) Demineralized Wzter Transfer Pumps (35
LIC systems
[or manual and automatic operation,
Even though the systems are designed
of operating
This requires the constant attention
only [unction in the manual mode.
in Units 2 and 3, all the alkaline concentration
personnel to keep it running. For example,
119
is out
order. Service water tank level indication
and silicon analyzer mecrs were out of
for tie NaOI-I njcctor-s arc out of
of service. Outict caustic soda concentration indicators
concentration indicators for the ICL
Additionally, outlet hydrochloric acid
sCr,,1cC
but the
4, the meters and indicator arc in SCtVice
injcctors arc out of service. In Unit
function
operators and can not cOMtnnLIOusly
systcl is operated manually by the
cally
ate
at(
required
repaired or replaced and the suipplicr be
Ic out of service instruments should be
operation
specification requirements for automatic
to make necessary modifications to meet
selection of
repairs are made, proper desimn arid
to reduce operating costs. Assuming
recommended maintenance and operation
components and adherence to the manufacturer
system should be suitabe of 20 years life
persincl, the water and wastewater treatment
I 'TAVIAILAEt.E DOCUNIMTN
120
Dcscription
(omments
Assessment
i121
g
DAVA
EP
EM El((G ENC
DI ES El(
-lAO R
It4T-N
Description
manufactured by Guizhou
Each of Units 2, 3, and 4 has ajl emergcncy dicel-g'cncrator
to 'hc Jnit I AOOV critical
Diesel Factory. The Unit 2 diesel generator is also connected
bus.
The diesel is
08 pover faril~.
The gcnerator is rated 500 kW, 50H1Z, 400\1, 903 Amp,
svsterl.
750 1-1P 6 cylinders, water cooled and with a coiptressed all stariint!
Thc diescl-gencrators were specified fot automatic start and autioiatic sop
whn
normal
per WA.PDA corresIn Unit 2 one of the two air compressors has been damaged
16, 1991. This has rendered the diesel
pondence PD/re(0)/OPER:-2/15419-20 dated June
enough pressure to roll
generator inoperable since one air compressor does not provide
of fune 6, 1991
the diesel engine. TYhis has complicated the events during tile shutdo\'i.1
generator breaker
in which the turbine rotor bow occurred. The operator opened the
bus was
while the automatic transfer from auxiliary transformer bus to startup transformer
of service and therefore Unit
not accomplished.
The emergency diesel generator was out
:o restore power. It is
2 was in
blackout until the operator took corrective measures
. are incapable of
400V AC critical loads will be out of service until operators start the
was not yet identified.
of the site visit, the root cause of this inability to start automatically
Assessment
to automatically feed
It is essential for any power plant to have a reliable diesel generator
2 that occurred
on
.JAMSI I(R()
['OWERI
JNITS 2, 3, & 4
TRANSFORMERS
Description
kV/6.9 10%
Manufactured by Shen,,ang Transfoimet Works, OFAF, 25 MVA, 220 .10%
1050/60 kV 131L
kV, wye/wye, high voltage ne::. by direct grounding, 11% impedance,
Seventh Oil Refinery.
5 cooling radiators, insulating oil type D13-25 GB2536-81
by Dalian
500C.
2 CTs 600/5 by SYTW, winding temperature rise 60C, oil temperature rise
123
U1nits 2, 3,
Inierve-ws with electrical maintenance and operating personnel and rc\,'cw oI
ion of
potat
to
dtuC
1991
July 11,
and 4 ou age record indicated that Unit 3 tripped on
personnel stated that the tij[) was due to
the inaul transformer protection relays. Plant
"Thecause of the tiansoimewr trip was not
opcation of the tiansformer pressure relay.
tile transfoi mci was retufned
de t1(-frtined noiwas damage, if any, assessed. Subsequently,
to Stnfvicc
Assessment
e'['ST AVA,
124
'
i
I)escription
switchgear assembhles manufactured
ihere arc five (5) sets of indoor, drip proof metalclad
kV, 2500 amp, 50 Hz, 31 5 kA. irntcrrupting
by I3cjing Swtchgear Factory and rated 6.6
breakcs iracd at 1 k\, 2500 amp,
capacity, 60 kV BIL. Sixty-four (64) vacuum circuit
load
time 0.075 sec, nl)inmp timic 0 06 scC, no
and 40 kA intcirupting capacity, interrupting
We svitchgear
voltage are proiddl Um ihliv
cloming tine 0 075 see, 220 VDC control
,assemnblies.
(oimcnts
Assesstmniti
assu"ing
Based upon the inewless of tile plaiit and
components, the 6.6 IV switcligear should be suitable
tie
without rnajo iepairs or replacetinent. However,
and
should receive training on protection relay settings
125
MOTORz
Description
3T AVAI 1'
126
J
(II
7NT
AssCssment
1F7
Description
Asse:.-ment
from
sheets should be obtained
cut
and component
drawing,
Adequate
the cause-of the UPS
CMES/manufacturer. Further investigation is needed to establish
failure, installation problems, or
low reliability. This could be a reslt of components
In any case, the current condition is causing
O&M procedures not being followed.
availability. Based upon resolving
increased O&M costs and i reducing Units 2, 3, and 4
proper design and selection of
current problems,
the newness of the plant, assuming
maintenance and operating
128
Description
switchyard
From main transformers of Units 2, 3, and 4 to the
Oil leakage
Sheath grounding
Lighting system
a=- i' ;
]-;Fv~~i
. -
,,;,"
_.,j/ :
c,;,
,~
Assessment
.jAMSIIOR()
UNITS 2, 3, & 4
Description
Assessment
LL
AVA~LA~
Description
Battqries Factory,
Each unit has a set of 220 VDC batterics manufactured by Shenyang
lead acid, 130 cells nominal voltage
located at the unit's battery room.
The batteries are
rate of 1600 amp-hr and maximum
Assessment
further investigation.
The deterioration could be a result of many factors which require
is expected in5 years for
However, based upon the current condition, replacement of cells
each unit.
U.S. excluding
Estimated cost of replacement for each unit is estimated at S100,000 F.O.B.
installation.
132
"
Descripiion
indicated the
Interview with O&M personnel, walk-downs, and review of documentalion
followi n:
o
The cable trays are congested and in some areas are loaded above the top of the
tray.
Some cable trays welded parts and surfaces have sharp edges which could damage
the cables.
Local control boxes located throughout the plant have no gaskets on the access door
assembly to prevent moisture and dust from accumulating inside control boxes.
or conduit
The control cables entering the boxes are installed without conduit
insulating bushings and thus the cables arc in direct contact with sharp edges of the
box.
BEST AVAILALL ujiw Y
The medium voltage cables, power cables and control cables run in the same
ductbank, and in some areas the manholes and duct covers are Idt open and
exposed to the elements.
I appears that the cable trays are not classified into high voltae tray, low voltage,
power and control cables tray, and low level signals tray. All the cables run togethcr
indiscriminately.
Thecre is no evidence that the instrumentation cables (4.20 ma. 0-1 ma, 0-SV, 0
10V) are shielded.
Cables and wiring of the BTG board in the control room arc not marked with
perrnanent identification tags and some of the temporary marked tags are already
faded away.
Assessment
During the 20 years life span, the above conditions will cause higher O&M cost as some
of the cables Aill be subject to failure. This will also cause unreliable control and
measurement of processes which has a direct affect on the availability and reliability of the
units. It is recommended that a maintenance program be established to test the cable
insulation integrity on a periodic basis in order that corrective action may be taken before
failure occurs. Without a detailed analysis of the ampacity of consideration for each circuit
it is not feasible time to predict the number cable of failures over a 20 year time frame.
I)escription
sequence
Each unit has a computer system which provides data logging, graphic displays,
The
of events,
turbine startup sequence monitor, alarming and performance calculation.
system consists of the foHowing:
(6)
(6)
(3)
(9)
(9)
(3)
(6)
(6)
(3)
(3)
(3)
48
272
16
48
Asscssmcnt
7,
CONTROL BUILDINGS
Description
The width of turbine building is 36.0 meters between axes A and GI. The 'height is 28.5
63
meters which is 1.4 meters .higher than Unit 1. The length of Unit 2 and Unit 4 is
meters and that of Unit 3 is 72 meters Between the ending and beginning axis of two
consecutive Units there are 2 meters spaces. The mezzanine Boor level is at EL +5.00
meters The operating floor level is at EL A-10.00 meters The dearator unit is at floor
elevation EL +18.00 meters There is only one gable wall at the south end of Unit 4.
There are two bridge cranes, each with 75/20 ton hook capacity. The top of the rail is EL
is 21.00 meters The bridee crane span is 26.00 meters
The walls along axes A and Gt, as well as the gable wall one metei south of the last
column axis 408 is covered by prefabricated reinforced concrete wall elements. The roof
is covered with cast-in-place concrete. The roof and floor slabs are finished using a metal
deck. There is bituminous insulation over the roof which is further protected by brick tiles.
The turbines and generators are supported on reinforced concrct: pedestals. Each turbine
pedestal is housed inside the turbine building below the operating floor level. The pedestals
are not connected with the steel structure of the turbine building except at their common
mat foundation. Each unit is separated with expansion joints from the foundation up to
the roof.
A common control building serves Units 3 and 4. This building is 40.0 meters long
between axes H to N in the North/East direction and 26.00 meters wide in the North/South
direction. From axes Glto 1 there is 1.50 meter distance.
3 & 4
in some cases, (here were no enough available bolts, welding was used instead. Normal
steel joint practice never combines the capacities of bolting and welding together since the
load transfer to tile bolts can only occur after weld receives its ultimate load and starts
failing.
A.nothcr poor detailing practice was observed at EL - 10.0 meters column row 17l Here
tile column splice location was selected too low, such that the flange splice plates on
column face looking towards G1, was cutting deep into the oncoming gusset plate, making
the erection difficult and that section of gusset plate not functional.
Furthermore, thc steepness of the vertical bracing between column A and BI. neat Unit
Plate
4 condenser entry, resulted in a gusset plate with a long narrow appearance
buckling consideration alone would probably not allow such a practice. At a nearby
location the diagonal member of vertical bracing was connected with a kinked gusset
plate, which creates torsion in columns.
Most of the welded erection joints had very rough and poor quality appearances. It is not
known if the welders of these joints were qualified welders or not. It is also questionable
if the erection practices followed resulted in safe and acceptable connections in the turbine
building vertical bracing system. The vertical bracing system transfers the horizontal loads
such as wind and earthquakes to the columns and foundation.
Assessment
Assuming proper design and construction, the reinforced concrete parts o the turbine
building of Units 2, 3 and 4 as well as the attached control room and amenities building
for Units 3 & 4 should be suitable for the next 20 years.
The erection practices observed cast some doubts about the actual strength of some
bracing joints. In the event of severe horizontal loads on the structure the ability of these
joints to perform their intended [unction is questionable. This is not to say that the overall
safety of the turbine building is in jeopardy since there should built-in redundancies in the
total frame work so that loads will redistribute along a stronger path if a one local joint
failure occurs.
A detailed evaluation of the bracing joints and implementation of corrective actions IS
required to assure a continued 20 years of suitability. Without this, major repairs may be
_OI"Y
BEST AVAI_.A12Li.
required.
.)
1:
COMMON FACILITIES
0 the following:
hc common components and structures evaluated consist
Stacks
Demineralized Water
and Service Water Storage Tanks
I:PY
Description
There are three major distinct parts for each stack. These are:
a)
b)
c)
a)
b)
Platfc . . . .-"
the
The reinforced concrete chimney is 147.00 n h igh from the top of
foundation to the top of chimney. At the base the external diameter is 15.20
is
meters with a wall thickness of 0.70 meters. The top external diameter
is
11.40 meters. and wall thickness reduces to 0.25 meters. The foundation
5.50 m thick and has the octagonal shape with 30.00 m external diameter.
The thickness of foundation tapers down to 2.00 in at the outside periphery
of the foundation. The stack foundation is built on the solid limestone
foundation. There is one opening for a steel door at the ground elevation
and two openings for the flue duct entry opposite to each other in the
North/South direction with the bottom
at EL 8.38 meters. The height of
these openings is 6.40 meters. The width is estimated to be 3.0 meters.
on the
There are t vo flues with an outside diameter of 4100 um. supported
STACKS
c)
at.every 6.00
A ladder attached to each flue provides
access to platforms
meters or less throughout the stack.
technique
Tle reinfoiced concrete chimneys were built using the slip form
where tile inside and outside forming was supported from the reinforcement
height of the
of the stack portion, already cast in place. Only a few feet
and tile
chimney is formed as a rng at one time. As this portion is built
to a new
concrete is sufficiently cured, the forming is raised as a unit up
a
height. This technique saves construction time, expense and provides
stacks
uniformly smooth and even surface. In the case of the Jamshoro
acceptable
both radial and vertical surface evenness was maintained to an
as tile
limit. Tle toundations support the weight of the structure as'well
dynamic effects of wind and earthquake forces on the solid limestone
foundation.
b)
The flues are supported and protected to some degree from external effects
were
by the reinforced concrete chimney. The materials used for the flues
selected to be resistant to the corrosive environment of the sulfurous gas
a
exiting the boiler. The internal surface of the flues is further coated with
draft
special lining to reduce the effect of tile hot gases. To provide good
is insulated
and to minimize the heat loss along
the path of flue, the flue
externally. The flues are in good functional cordition.
-kV5
1 i- hIL
L !
STACKS
c)
Assessment
a)
b)
c)
BEST
.JAMSIIO,)
UNITS 1, 2, 3 & 4
Description
There are two rectangular prismatic concrete tanks with a common rmiddlcwall.
They
tanks, chemical
store clarified water after it passes tile receiving tanks, sedimentation
long and
treatment and filter equipment. Each of the tanks is 21 meters wide, 40 meters
is 20 cm thick
6.9 mcters high. The walls and bottom slab is 50 cm. and the roof slab
Assessment
The clarified water storage tanks are suitable to last for the next 20 years of operation.
The leak problem should be solved by proper repair.
Description
Assessment
is difficult to estimate
The life span of the intake pipes, especially the underground portion
amount of sand sucked
since they are buried and not visible. Additionally, there is a high
pipes Will be under
in from the river and transported through the pipe. Externally the
will wear the pipe over
corrosion influence; internally the amount of sand flowing through
time.
.JAMSII()RO (NIIS
1, 2, 3 & 4
Description
Assessment
Desc riptiin
Assessment
Description
Thcre are two rectangular prismatic concrete tanks with a commol ,1iddlewall
They
tanks, chemical
store clarified water after it passes the receiving tanks, sedimcntation
40 meters long and
treatment and filter equipment. Each of the tanks is 21 meters wide,
cm thick
6.9 meters high. The walls and bottom sla) is 50 cm. and the loof slat) is 20
An attempt was
There was watci seepage at one of the pipe locations at the storage tank
exit and against
made to repaii the seepage by externally pouring concrete around pipe
the leak did
and
tank wall. Evidently, the tank was full when the repair was attempted
not stop.
observation was
No external scttlcment, cracks or deterioration were observed. No internal
made.
Assessment
operation.
The clarified water storage tanks are suitable to last for the next 20 years of
The leak problen, should be solved by proper repair.
1A-7
Iescription
For cach unit there arc two dcrmincralized water storage tanks each with 1000 cubic meter
capacity. Thcsc tanks arc located cast of thc water treatmcnt building of each unit.
the
There is an external stair*welded on the tank wall, leading to the tank entry at
sCrnisphcrical tank dome. Each tank is supported on a base containcd inside a concrete
cylindrical wall which elevates the tank above ground level.
Thc service water storage tanks arc located cast of the demincralized tanks. There are
two tanks for each unit. These tanks arc similar in size and shapc to those of the
dernincralized tanks for the corresponding units
The tanks were welded on location. The appearance of the exterior painting on the tanks
indicated quality work. Tlie paint on the tanks of Units 2, 3 and 4 are not as impressive
as the Unit I tanks. The welded seams arc not ground flush. The plate thickncss changes
are externally visible which gives an unev6n stepped surface. This, however, should not
affect service life. There are no external defects or settlements in any of the tanks.
Assessment
148
Description
o
o
o
pressure control valves. LOW pressure switches are installed on the punp discharges for
alarm purposes. Temperature sensors are installed to indicate temperature of residual oil
inlet/outlet, heating steam and drain.
Outdoor local control panels at the residual oil
transfer pump area and oil separator transfer pump area have the follow components:
o
o
o
o
o
Operating Swi.ches
Indicating Lamps
Ammeters
Strainer Differential Pressure Alarms
Motor Overload Alarms
The residual oil unloading area had considerable oil in trenches and on the ground.
(Reference Residual Oil Unloading Area Structures). This will lead to higher maintenance
costs and present a fire hazard. The area should be cleaned up. Interviews with plant
personnel, walk downs and review of plant records, indicated that the systems are in
working condition. However, plant personnel indicated difficulties are encountered in
unloading the rail cars especially in cold weather. Currently, oil is being delivered by truck
to a truck unloading facility.
4...
149
.3
, V,-ItSLL
JAMSII()l()
UNITS
I, 2, 3 & 4
Assessment
Assuming the area is cleanco up, good housekeeping practices are established, proper
- -. ponents and adherece to manufacturer's recommended
design and selection of sys
O&M procedures, the sys,,, snould be suitable for 20 years life.
Description
The residual oil unloading area is located at the west end of the power plant. It covers
the railroad unloading facilities and ->ceiving and transfer pump stations. Residual oil
unloading area facilities serve all [our units of the power plant. There are railroad tracks
running parallel to the North/South direction. Tracks arc numbered. 1 to #t4 from CasI
to west. The railroad unloading area is approximately 800 meters lonQ
Between rail tracks //3 and #4, there is a pipe trench below grade wiuch is almost 512
meters long capable of unloadig a total of 60 railroad tanker cars (30 cars per track) at
a time. The pipe trench is similar to a rectangular concrete underground tunnel with clear
inside dimensions of 3.20 meters width and 2.25 meters height. The trench bottom is sloped
from both ends towards the trench mid length. There are residual oil (R.O.) receiving
pipe, heating steam pipe, heating drain pipe, trace drain pipe, fire water pipe, air foam
pipe, an electrical conduit, a walk path and a saiall rain water trench inside the pipc
trench. At each railroad car park position, the top of pipe trench is 1.92 meters long and
has a full width access opening.
At the approximate midpoint, the pipe trench tunnel branches out wes(ward.and passes
nduits go through the tunnel then pass under the plant
under track #4. The pipes a:.
road through a concrete culvert and reach the residual oil receiving pump station area.
The oil pipe goes through the air separator units before entering the road culvert.
The residual oil pump station is a concrete structure built like a pit below road grade.
There are reinforced columns which support the reinforced concrete roof. There are no
walls above street lcvel. A smaller trench along the side of the road and the receivitn
pump station provide a catch basin for possible oil spill at street level and for rain. The
pumps in the receiving pump station transfer the arriving oil into four storage tanks each
designated for one power station unit. Next to the receiving pump station there is a
residual oil transfer pump station. The oil from the storage tanks is pumped through the
transfer pump station to the residual oil pump and heater area near the boiler units.
150
The residual oil unloading area is functional and intact. Thc reinforced pipct trench, the
connection tunnel undcr track //4, the culvert under plant road, the receiving and transfe
pump stations and, their walls, columns and roof appear in good condition. There were
no observable cracks, settlement or damage to any of the structures. During the site visit
there was no train unloading operation. Between and around the rail tracks there was
compacted soil with evidence of heavy oil spillage at most unloading locations. The spilled
oil, mixed with water, was several inches high throughout thc pipe ticnci. Thc oil spill
continued through the tunnel under the roadway around the rcceiving pump station area
but not inside the pump station itself
A truck unloading station is also provided. The tank trucks unload the residual oil to a
pump pit close to the receiving pump station. The pump pit is below the level of plant
road and protected on the road side by a concrete trench. There was oil and water
The trench is covered by grating made out of
standing inside this trench as well.
reinforced bars.
Assessment
The structures appear to be in satisfactory condition and should provide 20 years continued
operation. However, with the current condition there is a potential danger due to a major
fire. The area should be cleaned up immediately to remove this hazard.
ALE COF"'
.. gT V\JA
151
JAMSI
)I()() UNI
S I, 2, 3 & 4
1)C%c
C I11 1i 0nl
There are four residual oil storage tanks, each used for one of the units of the power
plant They are located west of the residual oil unloading area. The stotage tanks were
built on-site by welding steel plates. They are cylindrical in shape with slight spherical
(dolie roofs leach tank has 27,000 cubic meter oil storage capacity Each tank is almosi
Oine- metci above ground and supported on compacted soil placed Inside a clindrica l
concreice wall which forms, the hcight above ground. It is not known what kind of corrosion
plotect on of the steel base plate is provided as it is in direct contact with the base fill
A levee like stone wall is between tw,o neighboring tanks. Concrete walls protect tie
stn o0nding areas from oil spills. Tanks for Unit I and 2 are further separated from tile
tanks fo[f units I and 4 by a plant road oii three sides. All tanks are pain.ted
Assess
nicnt
The residual storage tanks appear to be in good condition and should provide satisfactory
service for 20 years assuming proper design and normal maintenance. Painted surfaces
cleaning may also be required. Inspection of the base plate for any corrosion damage will
be difficult. Therefore the tanks should be kept under surveillance to detect any leakage
at an early stage to minimize environmental damage.
152
,JAMSI I
l)cscl iption
bctwccn the residual oil transfC pump area and the water ireatment building for Unit 3,
aild flonir,. over the nieutal ground oinlthe north side of the plant inside i'(,
;1k Is four Meter', wide and simple span truss type steel bridge system elevated on hcav-y
spans froma 10 meters to 17 mcefs The bridge structire
steel coluins with vai),irii
stlpports the residual oil pipe from the transfer pump station to the heater and oil pump
arcat ncar the plant site. It further suppors the heating steam pipe , air, foamo and fire
\water tipcs, and clectilcal conduits fioma the )lant site to the residual oil unloading area
The Cast half of the bridge carries the pipcs and conduits to and from the vater tfeatmcril
building towarcs ic Illain powerhouse A secondary pipc rack hridP', perpcrldiculat i
the main pipe rack III North/South direction, starts from the main pipc rack and contiflles
southward onl the cast side of the plant street passing behind the boilc buildinig of each
unit. Tis pipe rack mainly carries the [uel SUl)ply lines to tile boiler units from the
csidural oil puinmp andi heater area. It also carries 1)ipcs used fo Gic tboilcr make up
watcr and the cable conduits.
The steel truss bridges and the supporting steel columns of the pipe rack appear
adequately designed and constructed. The columns arc supported on individual reinforced
concrete footing pedestals and foundations below grade. There w.ere no signs of settlement
or cracking. The pipe rack structure was painted and there was no evidence of peeling,
blisteting or cor-rosion.
Assessment
Assuming proper design and normal maintenance, the pipe rack bridgc system should be
suitable for the nex-t 20 years of operation
F 'jT.A\/,
[7
153
l.A
('l FV