Documente Academic
Documente Profesional
Documente Cultură
LEAD STATEMENT
Sl.No
Materials
Quarry
Unit
Lead in
K.M
Intial Cost
1 Cum
38.30
1300.00
1 Cum
38.30
1045.00
1 Cum
38.30
890.00
1 Cum
38.30
700.00
1 Cum
38.30
805.00
1 Cum
38.30
545.00
DHARANI KOTA
1 Cum
125.60
505.00
DHARANI KOTA
1 Cum
125.60
385.00
DHARANI KOTA
1 Cum
125.60
285.00
10
1 Cum
38.30
340.00
11
1 Cum
8.00
98.00
12
Cement
1.00 M.T
Local
4000.00
13
1.00 M.T
Local
46000.00
Certified that the leads are taken and corect to the best of my knowledge.
014-15
Deduct
Stacking
Basic Rate
Conveyance
Charges
Deduct
Contractor
Profit @ 14%
Total Cost
0.00
1300.00
470.00
57.72
1712.28
0.00
1045.00
470.00
57.72
1457.28
0.00
890.00
470.00
57.72
1302.28
0.00
700.00
470.00
57.72
1112.28
0.00
805.00
470.00
57.72
1217.28
0.00
545.00
470.00
57.72
957.28
0.00
505.00
1340
0.00
385.00
1340
0.00
285.00
1340
164.56
1460.44
0.00
340.00
470.00
57.72
752.28
0.00
98.00
116.00
14.25
199.75
4000.00
4000.00
46000.00
46000.00
164.56
164.56
1680.44
1560.44
80
80
300
300
90
960
1340
412.28070175
1175.4385965
470
1340
412.28
1175.44
57.72
164.56
MACHERLA MUNICIPALITY
WATER SUPPLY IMPROVEMENT SCHEME UNDER JnNURM -II
construction of Coffer dam for intake well in Bugga Vagu Reservoir
DETAILED CUM ABSTRACT OF ESTIMATE
Sl. Descriptio
No. n of item
1
No.
No.
Quantity
Rate
unit
2928.84
4200.00
7128.84
#REF!
cum
4200.00
2928.84
7128.84
#REF!
cum
Rs
rvoir
Total
#REF!
#REF!
#REF!
#REF!
Lakhs
Macherla Municipality
#REF!
Name of Sub Project :- Construction 10.00 m dia clear water sump at Existing 7.00 MLD WTP Head
water Works
Detailed cum Abstract of Estimate
S. No.
Description
Nos.
Quantity
Rate
unit
#REF!
cum
#REF!
cum
#REF!
cum
means
+155.00m-
3.80
430.10
440.00
0.30
33.96
34.00
Plain cement concrete (1:4:8) using 40mm m/c SS5 HBG including
machine mixing, laying, compacting, finishing, curing etc for
foundations
(+)151.50m-(+)151.80m
0.30
33.96
34.00
Raft (+)151.80m-(+)152.60m
0.80
84.61
85.00
10.30
0.30
3.00
10.30
0.30
0.20
(+)155.60m-(+)155.80m
d
0.30
0.30
2.90
Roof beams
1 3.14
4.00
0.30
0.30
1 0.786
3.70
0.15
3.70
#REF!
cum
#REF!
sqm
#REF!
cum
#REF!
10sqm
#REF!
10sqm
#REF!
kg
88.31
11.69
or say
100.00
1 3.142 10.60
1.00
33.31
100.00
133.31
140.00
Top of dome
cum
#REF!
1.61
2.00
sqm
77.55
78.00
#REF!
1.13
1.20
sqm
2.09
2.10
#REF!
1.94
2.00
1
cum
29.11
30.00
1 3.14
#REF!
20.00
40.00
Ladder
100.00
200.00
240.00
Raft
85.00
80
6800.00
Side walls
32.00
100
3200.00
Columns
2.10
120
252.00
Beams
1.20
120
144.00
Roof slab
11.70
80
936.00
Dome slab
2.00
80
160.00
11492.00
11500.00
#REF!
kgs
Rs
Total
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Lakhs
Basic Rate
conveyance charges
upto 5 km
conveyance charges
beyond 5 km upto 30 km
@ Rs 12.40/km
10
11
1.00 MT
Local
0.00
5840.00
0.00
0.00
0.00
0.00
0.00
M-005
1 cum
Prakkilanka
52.00
610.00
82.70
310.00
226.60
619.30
74.21
M -006
1 cum
Prakkilanka
52.00
677.00
82.70
310.00
226.60
619.30
74.21
M-004
1 cum
52.00
460.00
82.70
310.00
226.60
619.30
74.21
M- 050
1 cum
45.00
735.00
82.70
310.00
154.50
547.20
65.57
M- 051
1 cum
45.00
935.00
82.70
310.00
154.50
547.20
65.57
M- 052
1 cum
45.00
1097.00
82.70
310.00
154.50
547.20
65.57
M- 053
1 cum
45.00
1365.00
82.70
310.00
154.50
547.20
65.57
M- 054
M- 055
1 cum
Prakkilanka
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
45.00
1313.00
82.70
310.00
154.50
547.20
65.57
45.00
845.00
82.70
310.00
154.50
547.20
65.57
45.00
635.00
82.70
310.00
154.50
547.20
65.57
45.00
662.00
82.70
310.00
154.50
547.20
65.57
45.00
798.00
82.70
310.00
154.50
547.20
65.57
1
2 Sand for Concreate
292.00/50 kg bag
3 Sand for Mortor
Rs
10
11
12
13
1 cum
Aggregates 90 to 45mm graded
HBG
HBG IRC
IRC m/c
m/c metal
metal
graded HBG IRC m/c metal
M-039
1 cum
M- 038
1 cum
M- 042
1 cum
Deduct
13.615%
over
conveyance
charges
heads
SSR Code
SNo
on coveyance
charges
Lead
conveyance charges
beyond 30 km @
10.30/km
Source
Description of materials
Unit
Source
Lead
Basic Rate
conveyance charges
upto 5 km
conveyance charges
beyond 5 km upto 30 km
@ Rs 12.40/km
1 cum
KM 72/4 of
E.G.K.Road
45.00
704.00
82.70
310.00
154.50
547.20
65.57
M-021
1 cum
KM 72/4 of
E.G.K.Road
45.00
357.00
82.70
310.00
154.50
547.20
65.57
M-036
1 cum
45.00
872.00
82.70
310.00
154.50
547.20
65.57
M-016
1 cum
45.00
592.00
82.70
310.00
154.50
547.20
65.57
18
M-022
1 cum
45.00
438.00
82.70
310.00
154.50
547.20
65.57
19
(M 045)
1 cum
45.00
1210.00
82.70
310.00
154.50
547.20
65.57
45.00
875.00
82.70
310.00
154.50
547.20
65.57
45.00
557.00
82.70
310.00
154.50
547.20
65.57
45.00
1029.00
82.70
310.00
154.50
547.20
65.57
45.00
1145.00
82.70
310.00
154.50
547.20
65.57
21.00
103.00
82.70
198.40
0.00
281.10
33.69
(M 040)
20
21
22
(M 030)
(M 044)
Aggregate 40mm - 20mm
25
M -008
BMT-A-01
Deduct
13.615%
over
conveyance
charges
heads
1 cum
1 MT
Local
0.00
32000.00
0.00
0.00
0.00
0.00
0.00
1 MT
Local
0.00
40000.00
0.00
0.00
0.00
0.00
0.00
1000
Local
2.00
5200.00
69.80
0.00
0.00
0.00
0.00
1 cum
1 cum
1 cum
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
E.G.K Road
1 cum
23
KM 72/4 of
E.G.K.Road
KM 72/4 of
E.G.K.Road
on coveyance
charges
Unit
14
conveyance charges
beyond 30 km @
10.30/km
SSR Code
Description of materials
SNo
M- 041
1813.35
1.00 cum
1088.01
Mazdoor
320.00
1545.35
1.00 cum
231.80
Water
103.00
1383.35
1.00 cum
207.50
338.60
1183.35
1.00 cum
118.34
420.00
1645.65
Bar Bender
490.00
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Executive Engineer
Superintending Engineer
on coveyance
charges
Deduct
13.615%
over
conveyance
charges
heads
conveyance charges
beyond 30 km @
10.30/km
conveyance charges
beyond 5 km upto 30 km
@ Rs 12.40/km
conveyance charges
upto 5 km
Basic Rate
Lead
Source
Unit
SSR Code
Description of materials
SNo
28 Aggregates 20mm graded HBG SS5 m/c metal including seignoiorage, blasting charges, machine crushing charges Unit 1.00 cum
Total cost
12
5840.00
1155.09
1222.09
1005.09
1216.63
1416.63
1578.63
1846.63
1794.63
1326.63
1116.63
1143.63
1279.63
Total cost
1185.63
838.63
1353.63
1073.63
919.63
1691.63
1356.63
1038.63
1510.63
1626.63
350.41
32000.00
40000.00
5200.00
Total cost
456.20
Superintending Engineer
Description of item
MORTARS
Unit
BLD-CSTN-1
BLD-CSTN-1-4
A-MATERIALS
Cement
kg
480.00
5.84
2803.20
cum
1.05
1222.09
1283.19
cum
1.05
0.00
0.00
0.00
0.00
0.00
0.20
320.00
64.00
B- MACHINARY
Nil
C-LABOUR
Man mazdoor for mixing mortar
day
20% on labour
12.80
Grand total
2
4163.19
BLD-CSTN-1-5
A-MATERIALS
Cement
kg
360.00
5.84
2102.40
cum
1.05
1222.09
1283.19
cum
1.05
0.00
0.00
0.00
0.00
0.00
0.20
320.00
64.00
B- MACHINARY
Nil
C-LABOUR
Man mazdoor for mixing mortar
day
20% on labour
12.80
Grand total
3
3462.39
BLD-CSTN-1-6
A-MATERIALS
Cement
kg
288.00
5.84
1681.92
cum
1.05
1222.09
1283.19
cum
1.05
0.00
0.00
0.00
0.00
0.00
0.20
320.00
64.00
B- MACHINARY
Nil
C-LABOUR
Man mazdoor for mixing mortar
20% on labour
day
12.80
Grand total
4
3041.91
BLD-CSTN-1-7
A-MATERIALS
Cement
kg
240.00
5.84
1401.60
cum
1.05
1222.09
1283.19
cum
1.05
0.00
0.00
0.00
0.00
0.00
0.20
320.00
64.00
B- MACHINARY
Nil
C-LABOUR
Man mazdoor for mixing mortar
day
20% on labour
12.80
Grand total
5
2761.59
Plain cement concrete (1:4:8) using 40mm with concrete mixer mixing upto plinth level unit 1.00 cum
BLD-CSTN-2-5
A. MATERIALS
Cement
kg
162.00
5.84
946.08
cum
0.90
1326.63
1193.96
cum
0.45
1155.09
519.79
cum
0.90
0.00
0.00
cum
0.45
0.00
0.00
kl
1.20
103.00
123.60
hour
1.00
338.60
338.60
day
0.10
420.00
42.00
Mazdoor unskilled
day
1.39
320.00
444.80
20% on labour
97.36
Grand total
3706.19
504.60
4210.79
BLD-CSTN-2-14
Supply and placing of the design mix concrete corresponding to IS -456 using WEIGH BATCHER/MIXER
using 20 mm size graded machine crushed hard granite metal (coarse agggregate) from approved quarry
including cost and conveyance of all materials like cement,fine aggregate(sand),coarse aggregate ,water
etc to site and including seigniorage charges ,sales and other taxes on all materials including all
operational ,incidental and labour charges such as weigh batching ,machine mixing ,laying concrete
,curing etc complete but excluding cost of steel and its fabrication charges for finished item of work (APSS
NO 402) with minimum cement content as per IS Code from standard suppliers approved by the
deparment including pumping , centering,shuttering,laying concrete ,vibrating,curing etc M25 design mix
unit 1.00cum
A
0.80
cum
1645.65
1316.52
sand
0.40
cum
1155.09
462.03
0.133
day
420.00
55.86
0.267
day
375.00
100.13
Mazdoor unskilled
4.60
day
320.00
1472.00
B. LABOUR
20% on labour
325.60
C MACHINERY
Concrete mixer 600/400 Diesel
1.333
Hr
456.20
608.11
1.20
kl
103.00
123.60
Rate/cum
A.1
column footings
4463.85
4463.85
380.00
kg
5.84
2219.20
1.00
cum
750.00
750.00
centering charges
material charges+labour charges 277+473=750
20% on labour
94.60
7527.65
1024.89
8552.54
A-2
4463.85
380.00
kg
5.84
2219.20
1.00
cum
2476.00
2476.00
centering charges
material charges+labour charges 1335+1141=2476
20% on labour 1141.00
228.20
9387.25
1278.07
10665.33
A-3
4463.85
cement M25
380.00
kg
5.84
2219.20
1.00
cum
1068.00
1068.00
centering charges
material charges+labour charges 315+753=1068
20% on labour
150.60
7901.65
1075.81
8977.46
columns,lintels,water tanks,RCC walls in buildings excluding cement cost any grade mix
BLD-CSTN-2-14-B
A. MATERIALS
20 mm graded HBG metal
0.80
cum
1645.65
1316.52
sand
0.40
cum
1155.09
462.03
0.167
day
420.00
70.14
0.167
day
375.00
62.63
Mazdoor unskilled
5.60
day
320.00
1792.00
B. LABOUR
20% on labour
384.95
C MACHINERY
Concrete mixer 600/400 Diesel
1.333
Hr
456.20
608.11
1.20
KL
103.00
123.60
Rate/cum
B-1
4819.99
Columns GF upto 3.66m height cement content 380 kgs/cum M25 design Mix unit 1.00 cum
Rate of VRCC M25 design mix
cement M25
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2041.00
2041.00
centering charges
material charges+labour charges 341+1700=2041
20% on labour
340.00
9420.19
1282.56
10702.75
B-1-1 COLUMNS FF upto 3.66m height cement content 380 kgs/cum M25 design Mix unit 1.00 cum
Rate of VRCC M25 design mix
cement M25
centering charges
material charges+labour charges 341+1700=2041
20% on labour
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2041.00
2041.00
340.00
192.48
9612.66
1308.76
Total/cum
10921.43
COLUMNS 2nd floor upto 3.66m height cement content 380 kgs/cum M25 design Mix
B-1-2
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2211.00
2211.00
centering charges
material charges+labour charges 341+1870=2211
20% on labour
374.00
384.95
10009.14
B-1-3
1362.74
Total/cum
COLUMNS 3rd floor upto 3.66m height cement content 380 kgs/cum M25 design Mix
11371.89
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2381.00
2381.00
centering charges
material charges+labour charges 341+2040=2381
20% on labour
408.00
577.43
10405.62
B-2
1416.72
Total/cum
11822.34
Lintels GF upto 3.66m height cement content 380 kgs/cum M25 design mix
unit 1.00 cum
Rate of VRCC M25 design mix
cement M25
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2344.00
2344.00
centering charges
material charges+labour charges 1133+1211=2344
20% on labour
242.20
9625.39
1310.50
10935.88
B-2-1
LINTELS FF upto 3.66m height cement content 380 kgs/cum M25 design mix unit 1.00 cum
Rate of VRCC M25 design mix
cement M25
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2344.00
2344.00
centering charges
material charges+labour charges 1133+1211=2344
20% on labour
242.20
192.48
9817.86
B-2-2
1336.70
Total/cum
11154.57
LINTELS 2nd floor upto 3.66m height cement content 380 kgs/cum M25 design mix unit 1.00
cum
Rate of VRCC M25 design mix
cement M25
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2465.00
2465.00
centering charges
material charges+labour charges1133+1332=2465
20% on labour
266.40
384.95
10155.54
B-2-3
1382.68
Total/cum
11538.22
LINTELS 3rd floor upto 3.66m height cement content 380 kgs/cum M25 design mix unit 1.00
cum
Rate of VRCC M25 design mix
cement M25
4819.99
380.00
kg
5.84
2219.20
1.00
cum
2586.00
2586.00
centering charges
material charges+labour charges1133+1453=2586
20% on labour
290.60
577.43
10493.22
1428.65
Total/cum
11921.87
BLD-CSTN-2-14-C
A. MATERIALS
20 mm graded HBG metal
0.80
cum
1645.65
1316.52
sand
0.40
cum
1155.09
462.03
0.067
day
420.00
28.14
0.133
day
375.00
49.88
Mazdoor unskilled
3.077
day
320.00
984.64
B. LABOUR
20% on labour
212.53
C MACHINERY
Concrete mixer 600/400 Diesel
0.308
hour
456.20
140.51
1.20
kl
103.00
123.60
Total/cum
C-1
3317.85
RCC Slabs GF upto 3.66m height 0.075m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.075=0.075 cum
0.075
cum
3317.85
248.84
28.50
kg
5.84
166.44
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
836.68
113.91
950.59
C-1-1
RCC Slabs FF upto 3.66m height 0.075m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm1.00 x0.075=0.075 cum
0.075
cum
3317.85
248.84
28.5
kg
5.84
166.44
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
7.97
844.65
115.00
959.65
RCC Slabs 2nd floor upto 3.66m height 0.075m thick cement content 380 kgs/cum M25 design
C-1-2 mix unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm
0.075
cum
3317.85
248.84
28.5
kg
5.84
166.44
1.00
sqm
405.00
405.00
centering charges
material charges+labour charges
227+178=405.00/sqm.
20% on labour
35.60
15.94
871.82
118.70
990.52
C-2
RCC Slabs GF upto 3.66m height 0.125m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm1.00 x0.125=0.125 cum
0.125
cum
3317.85
414.73
47.50
kg
5.84
277.40
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
1113.53
151.61
1265.14
C-2-1
RCC Slabs
FF upto 3.66m height 0.125m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
0.125
cum
3317.85
414.73
47.50
kg
5.84
277.40
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
13.28
1126.81
153.42
1280.23
C-2-2
RCC Slabs 2nd floor upto 3.66m height 0.125m thick cement content 380 kgs/cum M25 design
mix unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.125=0.125 cum
0.125
cum
3317.85
414.73
47.50
kg
5.84
277.40
1.00
sqm
405.00
405.00
centering charges
material charges+labour charges
227+178=405.00/sqm.
20% on labour
35.60
26.57
1159.30
157.84
1317.14
C-2-3
RCC Slabs 3rd floor upto 3.66m height 0.125m thick cement content 380 kgs/cum M25 design
mix unit 1.00 sqm
Rate of VRCC M25 design mix
0.125
cum
3317.85
414.73
47.50
kg
5.84
277.40
1.00
sqm
421.00
421.00
centering charges
material charges+labour charges
227+194=421.00/sqm.
20% on labour
38.80
39.85
1191.78
162.26
1354.04
C.3
RCC Slabs GF upto 3.66m height 0.14m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.14=0.14 cum
0.14
cum
3317.85
464.50
53.20
kg
5.84
310.69
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
1196.59
162.92
1359.50
C.3.1
RCC Slabs
1.00 sqm
FF upto 3.66m height 0.14m thick cement content 380 kgs/cum M25 design mix unit
0.14
cum
3317.85
464.50
53.20
kg
5.84
310.69
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
15.94
1212.53
165.09
1377.61
C.3.2
RCC Slabs 2nd floor upto 3.66m height 0.14m thick cement content 380 kgs/cum M25 Design
mix unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.14=0.14 cum
0.14
cum
3317.85
464.50
53.20
kg
5.84
310.69
centering charges
1.00
sqm
405.00
405.00
20% on labour
35.60
31.88
1247.67
169.87
1417.54
C.3.3
RCC Slabs GF upto 3.66m height 0.15m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.15=0.15 cum
0.15
cum
3317.85
497.68
57.00
kg
5.84
332.88
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
1251.96
170.45
1422.41
C.3.4
RCC Slabs
1.00 sqm
FF upto 3.66m height 0.15m thick cement content 380 kgs/cum M25 design mix unit
0.15
cum
3317.85
497.68
57.00
kg
5.84
332.88
1.00
sqm
389.00
389.00
centering charges
material charges+labour charges
227+162=389.00/sqm.
20% on labour
32.40
15.94
1267.90
172.62
1440.52
C.3.5
RCC Slabs 2nd floor upto 3.66m height 0.15m thick cement content 380 kgs/cum M25 Design
mix unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.15=0.15 cum
0.15
cum
3317.85
497.68
57.00
kg
5.84
332.88
1.00
sqm
405.00
405.00
centering charges
material charges+labour charges
227+178=405.00/sqm.
20% on labour
35.60
31.88
1303.04
C.4
177.41
1480.45
RCC Slabs GF upto 3.66m height 0.20m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.20=0.20 cum
0.20
cum
3317.85
663.57
76.00
kg
5.84
443.84
1.00
sqm
399.00
399.00
centering charges
material charges+labour charges
233+166=399.00/sqm.
20% on labour
33.20
1539.61
209.62
1749.23
RCC Slabs FF upto 3.66m height 0.20m thick cement content 380 kgs/cum M25 design mix
C-4-1
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.20=0.20 cum
0.20
cum
3317.85
663.57
76.00
kg
5.84
443.84
1.00
sqm
399.00
399.00
centering charges
material charges+labour charges
233+166=399.00/sqm.
20% on labour
33.20
21.25
1560.86
212.51
1773.37
C-4-2
RCC Slabs 2nd floor upto 3.66m height 0.20m thick cement content 380 kgs/cum M25 design mix
unit 1.00 sqm
Rate of VRCC M25 design mix
quantity of concrete/sqm 1.00 x0.20=0.20 cum
0.20
cum
3317.85
663.57
76.00
kg
5.84
443.84
1.00
sqm
416.00
416.00
centering charges
material charges+labour charges
233+183=406.00/sqm.
20% on labour
36.60
42.51
1602.52
218.18
1820.70
C-5
RCC Sun shades 0.60m wide ,0.10m thick at fixed end and 0.05m at free end
height cement content 380 kgs/cum M25 design mix unit 1.00 Rmt
GF upto 3.66m
0.045
cum
3317.85
149.30
cement M25
380224+186
x0.045= =410.00/sqm =
centering
charges
17.10
kg
5.84
99.86
0.60
sqm
410.00
246.00
1.00
sqm
22.32
22.32
517.49
13.615% over heads and contractors profit -
70.46
587.94
C-5-1
RCC Sun shades 0.60m wide ,0.10m thick at fixed end and 0.05m at free end
height cement content 380 kgs/cum M25 design mix unit 1.00 Rmt
Rate of VRCC M25 design mix
quantity of concrete/Rmt = 1.00 x0.60
x(0.10+0.05/2)=0.045 cum
cement M25
380224+186
x0.045= =410.00/sqm =
centering
charges
0.045
cum
3317.85
149.30
17.10
kg
5.84
99.86
0.60
sqm
410.00
246.00
1.00
sqm
22.32
22.32
4.78
522.27
71.11
593.38
C-5-2
FF upto 3.66m
RCC Sun shades 0.60m wide ,0.10m thick at fixed end and 0.05m at free end
3.66m height cement content 380 kgs/cum M25 design mix unit 1.00 Rmt
2 nd floor upto
0.045
cum
3317.85
149.30
cement
380224+205
x0.045= =429.00/sqm =
centeringM25
charges
17.10
kg
5.84
99.86
0.60
sqm
429.00
257.40
1.00
sqm
24.60
24.60
9.56
540.73
73.62
RCC Sun shades 0.60m wide ,0.10m thick at fixed end and 0.05m at free end
C-5-3
3.66m height cement content 380 kgs/cum M25 design mix unit 1.00 Rmt
614.35
3 rd floor upto
0.045
cum
3317.85
149.30
cement
380224+223
x0.045= =447.00/sqm =
centeringM25
charges
17.10
kg
5.84
99.86
0.60
sqm
447.00
268.20
1.00
sqm
26.76
26.76
14.35
558.47
76.04
634.51
C-6
BEAMS GF upto3.66m height cement content 380 kgs /cum M25 desidn mix unit 1.00 cum
Rate of VRCC M25 nominal mix
cement M25
3317.85
380.00
kg
5.84
2219.20
1.00
cum
3428.00
3428.00
centering charges
material charges+labour charges
2002+1426=3428.00/cum
20% on labour
285.20
9250.25
BEAMS FF upto3.66m height cement content 380 kgs /cum M25 desidn mix
1259.42
10509.67
unit 1.00 cum
380.00
kg
5.84
3317.85
2219.20
1.00
cum
3428.00
3428.00
20% on labour
285.20
106.27
9356.52
1273.89
10630.41
C-6-2
BEAMS 2nd floor upto3.66m height cement content 380 kgs /cum M25 design mix unit 1.00 cum
Rate of VRCC M25 nominal mix
cement M25
centering charges
380.00
kg
5.84
3317.85
2219.20
1.00
cum
3571.00
3571.00
20% on labour
Lift charges (1062.66)x0.20
313.80
212.53
9634.38
1311.72
10946.10
C-6-3
BEAMS 3rd floor upto3.66m height cement content 380 kgs /cum M25 desidn mix unit 1.00 cum
Rate of VRCC M25 nominal mix
cement M25
centering charges
380.00
kg
5.84
3317.85
2219.20
1.00
cum
3713.00
3713.00
20% on labour
Lift charges (1062.66)x0.30
13.615% over heads and contractors profit -
342.20
318.80
9911.05
1349.39
11260.44
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel (MS)
steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works , including
labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges
such as cutting, bending, placing in position, tying including sales and other taxes on all materials etc.,
complete for finished item of work in all floors.( APSS No.126) (BLD-CSTN-2-18)
unit 1.00 MT
GF
Material
HYSD bars including 5% for overlaps and wastage
1.05
MT
32000.00
33600.00
6.00
kgs
70.00
420.00
10.00
day
420.00
4200.00
Mazdoor unskilled
10.00
day
320.00
3200.00
20% on labour
1480.00
42900.00
5840.84
48740.84
Rate /kg
b
48.74
first floor
Material
HYSD bars including 5% for overlaps and wastage
1.05
MT
32000.00
33600.00
6.00
kgs
70.00
420.00
10.00
day
420.00
4200.00
Mazdoor unskilled
10.00
day
320.00
3200.00
20% on labour
1480.00
0.00
42900.00
5840.84
48740.84
Rate /kg
c
48.74
2nd floor
Material
HYSD bars including 5% for overlaps and wastage
1.05
MT
32000.00
33600.00
6.00
kgs
70.00
420.00
10.00
day
420.00
4200.00
Mazdoor unskilled
10.00
day
320.00
3200.00
20% on labour
1480.00
0.00
42900.00
5840.84
48740.84
Rate /kg
d
48.74
3rd floor
Material
HYSD bars including 5% for overlaps and wastage
1.05
MT
32000.00
33600.00
6.00
kgs
70.00
420.00
10.00
day
420.00
4200.00
Mazdoor unskilled
10.00
day
320.00
3200.00
20% on labour
1480.00
0.00
42900.00
5840.84
48740.84
Rate /kg
48.74
Brick masonary in CM (1:5) with traditional size 23x11x7cm unit 1.00 cum
BLD-CSTN-3-1 -a-iii
Ground floor
materials
cement
57.60
kgs
5.84
336.38
512.00
1000 nos
5200.00
2662.40
0.20
cum
1222.09
244.42
0.24
day
420.00
100.80
0.56
day
375.00
210.00
Mazdoor unskilled
1.89
day
320.00
604.80
sand
labour
20% on labour
183.12
4341.92
591.15
4933.07
First floor
materials
cement
57.60
kgs
5.84
336.38
512.00
1000 nos
5200.00
2662.40
0.20
cum
1222.09
244.42
0.24
0.56
day
day
420.00
375.00
100.80
210.00
sand
labour
mason 1st class
mason 2nd class
Mazdoor unskilled
1.89
day
320.00
20% on labour
604.80
183.12
lift charges
materials 10% on labour 915.60
91.56
4433.48
603.62
5037.10
Brick masonary in CM (1:6) with traditional size 23x11x7cm unit 1.00 cum
BLD-CSTN-3-1 -a-iv
Ground floor
materials
cement
48.00
kgs
5.84
280.32
512.00
1000 nos
5200.00
2662.40
0.20
cum
1222.09
244.42
0.24
day
420.00
100.80
0.56
day
375.00
210.00
Mazdoor unskilled
1.89
day
320.00
604.80
sand
labour
20% on labour
183.12
4285.86
583.52
4869.38
First floor
materials
cement
48.00
kgs
5.84
280.32
512.00
1000 nos
5200.00
2662.40
0.20
cum
1222.09
244.42
0.24
day
420.00
100.80
0.56
day
375.00
210.00
Mazdoor unskilled
1.89
day
320.00
604.80
sand
labour
20% on labour
183.12
lift charges
materials 10% on labour 915.60
91.56
4377.42
595.99
4973.40
2 nd floor
materials
cement
48.00
kgs
5.84
280.32
512.00
1000 nos
5200.00
2662.40
0.20
cum
1222.09
244.42
0.24
day
420.00
100.80
0.56
day
375.00
210.00
Mazdoor unskilled
1.89
day
320.00
604.80
sand
labour
20% on labour
183.12
lift charges
materials 20% on labour 915.60
183.12
4468.98
608.45
5077.43
3rd floor
materials
cement
48.00
kgs
5.84
280.32
512.00
1000 nos
5200.00
2662.40
0.20
cum
1222.09
244.42
0.24
day
420.00
100.80
0.56
day
375.00
210.00
Mazdoor unskilled
1.89
day
320.00
604.80
sand
labour
20% on labour
183.12
lift charges
materials 30% on labour 915.60
274.68
4560.54
620.92
5181.45
10
Plastering with CM (1:3) 12mm thick GF to ceiling unit 10.00 sqm BLD-CSTN-6-1
Ground floor
Materials
Cement mortar (1:3)
0.15
cum
4163.19
624.48
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
scaffolding charges
111.84
0.00
1295.52
176.38
Rate/10sqm
1471.90
Rate/sqm
147.19
first floor
Materials
Cement mortar (1:3)
0.15
cum
4163.19
624.48
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
55.92
10
sqm
14.92
149.20
20% on labour
10
0.20
12.55
25.10
1525.74
207.73
Rate/10sqm
1733.47
Rate/sqm
173.35
2nd floor
Materials
Cement mortar (1:3)
0.15
cum
4163.19
624.48
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
111.84
10
sqm
20.01
200.10
20% on labour
10
0.20
17.64
35.28
1642.74
223.66
Rate/10sqm
1866.40
Rate/sqm
186.64
3rd floor
Materials
Cement mortar (1:3)
0.15
cum
4163.19
624.48
0.60
day
420.00
252.00
Labour
Mason 1st class
Mazdoor unskilled
0.96
day
320.00
307.20
20% on labour
111.84
167.76
10
sqm
25.10
251.00
20% on labour
10
0.20
22.73
45.46
1759.74
239.59
Rate/10sqm
1999.33
Rate/sqm
199.93
11
Ground floor
Materials
Cement mortar (1:5)
0.15
cum
3462.39
519.36
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
1190.40
1190.40
162.07
Rate/10sqm
1352.47
Rate/sqm
135.25
First floor
Materials
Cement mortar (1:5)
0.15
cum
3462.39
519.36
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
lift charges
10% onlabour 559.20
55.92
10
sqm
7.17
71.70
20% on labour
10
0.20
6.18
12.36
1330.38
181.13
Rate/10sqm
1511.51
Rate/sqm
151.15
2nd floor
Materials
Cement mortar (1:5)
0.15
cum
3462.39
519.36
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
lift charges
20% onlabour 559.20
111.84
10
sqm
9.77
97.70
20% on labour
10
0.20
8.78
17.56
1417.50
192.99
Rate/10sqm
1610.49
Rate/sqm
161.05
3rd floor
Materials
Cement mortar (1:5)
0.15
cum
3462.39
519.36
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
lift charges
30% onlabour 559.20
167.76
10
sqm
12.36
123.60
20% on labour
10
0.20
11.37
22.74
1504.50
204.84
Rate/10sqm
1709.34
Rate/sqm
170.93
12
Ground floor
BLD-CSTN-6-3
Materials
Cement mortar (1:5)
0.15
cum
3041.91
456.29
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
1127.33
153.49
Rate/10sqm
1280.81
Rate/sqm
128.08
First floor
Materials
Cement mortar (1:5)
0.15
cum
3041.91
456.29
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
lift charges
10% onlabour 559.20
55.92
10
sqm
7.17
71.70
20% on labour
10
0.20
6.18
12.36
1267.31
172.54
Rate/10sqm
1439.85
Rate/sqm
143.99
2nd floor
Materials
Cement mortar (1:5)
0.15
cum
3041.91
456.29
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
lift charges
20% onlabour 559.20
111.84
10
sqm
9.77
97.70
20% on labour
10
0.20
8.78
17.56
1354.43
184.41
Rate/10sqm
1538.83
Rate/sqm
153.88
3rd floor
Materials
Cement mortar (1:5)
0.15
cum
3041.91
456.29
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
lift charges
30% onlabour 559.20
167.76
10
sqm
12.36
123.60
20% on labour
10
0.20
11.37
22.74
1441.43
196.25
Rate/10sqm
1637.68
Rate/sqm
163.77
14
Ground floor
BLD-CSTN-6-3
Materials
Cement mortar (1:5)
0.21
cum
3041.91
638.80
0.94
day
420.00
394.80
Mazdoor unskilled
1.60
day
320.00
512.00
Labour
20% on labour
181.36
1726.96
235.13
Rate/10sqm
1962.09
Rate/sqm
196.21
First floor
Materials
Cement mortar (1:5)
0.21
cum
3041.91
638.80
0.94
day
420.00
394.80
Mazdoor unskilled
1.60
day
320.00
512.00
Labour
20% on labour
181.36
lift charges
10% onlabour 559.20
55.92
10
sqm
7.17
71.70
20% on labour
10
0.20
6.18
12.36
1866.94
254.18
Rate/10sqm
2121.13
Rate/sqm
212.11
2nd floor
Materials
Cement mortar (1:5)
0.21
cum
3041.91
638.80
0.94
day
420.00
394.80
Mazdoor unskilled
1.60
day
320.00
512.00
Labour
20% on labour
181.36
lift charges
20% onlabour 559.20
111.84
10
sqm
9.77
97.70
20% on labour
10
0.20
8.78
17.56
1954.06
266.05
Rate/10sqm
2220.11
Rate/sqm
222.01
3rd floor
Materials
Cement mortar (1:5)
0.21
cum
3041.91
638.80
0.94
day
420.00
394.80
Mazdoor unskilled
1.60
day
320.00
512.00
Labour
20% on labour
181.36
lift charges
30% onlabour 559.20
167.76
10
sqm
12.36
123.60
20% on labour
10
0.20
11.37
22.74
2041.06
14
277.89
Rate/10sqm
2318.95
Rate/sqm
231.90
BLD-CSTN-6-8
Materials
Cement mortar (1:3)
0.21
cum
4163.19
874.27
0.94
day
420.00
394.80
Mazdoor unskilled
1.60
day
320.00
512.00
Labour
20% on labour
181.36
1962.43
1962.43
15
267.18
Rate/10sqm
2229.61
Rate/sqm
222.96
Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD & 304
MORTH for foundations of cc drains unit 1.00 cum
RBR-FNDN-2(1)
Sand filling unit 1.00 cum
a) Labour
Mate
Mazdoor (Unskilled)
day
0.31
day
320.00
20% on labour
99.20
19.84
b) Material
Sand
1.00
cum
1,005.09
1005.09
water
0.10
KL
103.00
10.30
1134.43
1134.43
16
154.45
Total / Cum
1288.88
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated
suitable material as per Technical Specification 305 MORD / 304 MORTH RBR-FNDN-1 1(A) & SOR
-2013-14 CL-2-II
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of
MORT&H--ordinary soil--manual means upto 3m depth for foundations of buildings in restricted places
unit 1.00 cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor (Unskilled)
day
3.64
day
320.00
1164.80
20% on labour
232.96
873.60
2271.36
309.25
2580.61
258.06
17
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated
suitable material as per Technical Specification 305 MORD / 304 MORTH RBR-FNDN-1 1(A) & SOR
-2013-14 CL-2-II
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of
MORT&H--ordinary soil--manual means upto 3m depth for foundations unit 1.00 cum
Taking output = 10 cum
a) Labour
Mate
day
Mazdoor (Unskilled)
3.64
day
320.00
20% on labour
1164.80
232.96
1397.76
18
a
190.31
1588.07
158.81
Painting with Synthetic Enamel paints - Two Coats - For New Iron Work
ground floor
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British
Paints (I) Ltd. BMT-J-30
1.100
276.00
303.60
day
1.100
375.00
412.50
B. LABOUR
Painter
20% on labour
82.50
0.00
798.60
108.73
907.33
Rate/sqm
90.73
BLD-CSTN-10-6
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer BMT-J-03
0.70
142.00
99.40
day
0.70
375.00
262.50
B. LABOUR
Painter
20% on labour
52.50
414.40
0.00
414.40
56.42
470.82
Rate/sqm
47.08
Total 91.64+47.55=139.19/sqm
137.81
first floor
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British
Paints (I) Ltd. BMT-J-30
1.100
276.00
303.60
day
1.100
375.00
412.50
B. LABOUR
Painter
20% on labour
82.50
41.25
0.00
839.85
114.35
954.20
Rate/sqm
95.42
BLD-CSTN-10-6
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer BMT-J-03
0.70
142.00
99.40
day
0.70
375.00
262.50
B. LABOUR
Painter
20% on labour
52.50
26.25
440.65
0.00
440.65
59.99
500.64
Rate/sqm
50.06
Total 97.21+50.06=147.27/sqm
145.48
2nd floor
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British
Paints (I) Ltd. BMT-J-30
1.100
276.00
303.60
day
1.100
375.00
412.50
B. LABOUR
Painter
20% on labour
82.50
82.50
0.00
881.10
119.96
1001.06
Rate/sqm
Painting, Priming Coat on New Iron Work
100.11
BLD-CSTN-10-6
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer BMT-J-03
0.70
142.00
99.40
day
0.70
375.00
262.50
B. LABOUR
Painter
20% on labour
52.50
52.50
466.90
0.00
466.90
63.57
530.47
Rate/sqm
53.05
Total 101.89+53.05=153.15/sqm
153.15
3rd floor
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British
Paints (I) Ltd. BMT-J-30
1.100
276.00
303.60
day
1.100
375.00
412.50
B. LABOUR
Painter
30% on labour
123.75
82.50
0.00
922.35
125.58
1047.93
Rate/sqm
104.79
BLD-CSTN-10-6
0.70
142.00
99.40
day
0.70
375.00
262.50
B. LABOUR
Painter
20% on labour
52.50
78.75
493.15
0.00
493.15
67.14
560.29
Rate/sqm
56.03
Total 106.63+56.59=163.21/sqm
160.82
19
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water
proof compound per bag of cement laid over roof when it is green including cost of all materials,
seigniorage charges, excluding conveyance charges of materials and including all operational, incidental
and labour charges for mixing mortar, laying, rendering smooth and thread lining, curing, rounding off
junctions of wall and slab etc,, complete for finished item of work
BLD-CSTN-8-25
ground floor
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
cum
0.210
litre
2.000
day
0.660
nd
Mason 2 class
day
1.540
Mazdoor (unskiled)
day
3.70
4163.19
874.27
80.00
160.00
420.00
277.20
375.00
577.50
320.00
1184.00
B. LABOUR
20% on labour
407.74
3480.71
3480.71
473.90
Total/10 sqm
3954.61
Rate/sqm
395.46
first floor
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
cum
0.210
4163.19
874.27
litre
2.000
80.00
160.00
day
0.660
420.00
277.20
nd
Mason 2 class
day
1.540
375.00
577.50
Mazdoor (unskiled)
day
3.70
320.00
1184.00
B. LABOUR
20% on labour
407.74
203.87
3684.58
3684.58
501.66
Total/10 sqm
4186.24
Rate/sqm
418.62
2nd floor
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
cum
0.210
4163.19
874.27
litre
2.000
80.00
160.00
B. LABOUR
0.00
day
0.660
420.00
277.20
nd
Mason 2 class
day
1.540
375.00
577.50
Mazdoor (unskiled)
day
3.70
320.00
1184.00
20% on labour
407.74
407.74
3888.45
3888.45
529.41
Total/10 sqm
4417.86
Rate/sqm
441.79
3rd floor
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
cum
0.210
4163.19
874.27
litre
2.000
80.00
160.00
day
0.660
420.00
277.20
Mason 2 class
day
1.540
375.00
577.50
B. LABOUR
nd
Mazdoor (unskiled)
day
3.70
320.00
1184.00
20% on labour
407.74
611.61
4092.32
4092.32
557.17
Total/10 sqm
4649.49
Rate/sqm
464.95
20
ground floor
Material
MS flats,MS angles,etc
1.05
kg
40.00
42.00
1.00
kg
24.00
24.00
1.00
kg
4.00
4.00
5.60
75.60
10.29
Rate/kg
85.89
first floor
Material
MS flats,MS angles,etc
1.05
kg
40.00
42.00
1.00
kg
24.00
24.00
1.00
kg
4.00
4.00
20% on labour
5.60
2.80
78.40
10.67
Rate/kg
89.07
2nd floor
Material
MS flats,MS angles,etc
1.05
kg
40.00
42.00
1.00
kg
24.00
24.00
1.00
kg
4.00
4.00
20% on labour
5.60
5.60
81.20
11.06
Rate/kg
92.26
3rd floor
Material
MS flats,MS angles,etc
1.05
kg
40.00
42.00
1.00
kg
24.00
24.00
1.00
kg
4.00
4.00
20% on labour
5.60
8.40
84.00
21
11.44
Rate/kg
95.44
Supply, delivery and fixing of 110mm dia single socket PVC pipes 4 kg/sqcm prince/Sudhakar or any ISI
brand for rain water pipes with clamps - Building SSR - 2015-16 rates
Basic rate BMW-G-13
Rmt
3.00
484.00
161.33
Rmt
1.00
70.00
70.00
14.00
10.00
255.33
22
23
24
34.76
Rate/Rmt
290.10
supply of 110 mm dia - Door Bend 87.5 Degree - UPVC/SWR Pipe fittings
Basic rate BMW-G-60
107.00
14.57
Rate/each
121.57
supply of 110 mm dia - Double Tee with Door - UPVC/SWR Pipe fittings
Basic rate BMW-G-78
295.00
40.16
Rate/each
335.16
57.00
7.76
Rate/each
64.76
25
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing with aluminium
anodised sections of Jindal sections and outer frame top horizontals & both verticals of 2408 of size 101.6
x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of 4504 of size 44.45 mm x 47.62 mm x 3.18
and Middle lock rail of 4621 of size 49.91 x 44.45 x 3 mm with tinted-bronze/green glass 5 mm
thick(middle to top),MDF Board-exterior both sides laminaed 12mm thick(middle to bottom) fixed including
supply and fixing aluminium handles of 150 mm for each shutter and all labour charges for fixing the
fixtures with required no.of screws, bolts and nuts and including labour charges for fixing the frame in
position, fixing shutter to frame etc. completed for finished item of work - BLD-CSTN-11-31 & Item 11 of
Revised data
ground floor
UNIT 1 sqm
A) MATERIAL REQUIREMENT for 1.20x2.10m door
ALUMINIUM SECTION
vertical 2*2.10=4.20
no 2408
no 4504
horizantals 2*1.20=2.40
total 4.20+2.40=6.60 rmt*1.505kg=9.933
midle no 4621 1*1.20=1.20*1.505=1.806
total 12.98+9.933+1.806=24.719 kgs BMS.W.01
tinted-bronze/green GLASS 5mm thick
1.20*1.05=1.26 BMT.I.08
SILICON SEALANT
kg
24.719
321.00
7934.80
sqm
1.26
644.00
811.44
LS
150.00
RMT
6.60
2.00
13.20
Alum.Anodised.PC HandlesBMT-G-34
each
140.00
280.00
each
141.00
141.00
each
63.00
63.00
each
935.00
935.00
sqm
1.26
863.00
1087.38
11415.82
4530.09
B) LABOUR CHARGES
1st Class Carpenter
day
0.099
420.00
41.58
day
0.020
375.00
7.43
day
0.099
375.00
37.13
day
0.099
375.00
37.13
Unskilled Mazdoor
day
0.297
320.00
95.04
20% on labour
43.66
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
BMC.X.02
Hrs
0.793
125.00
99.13
Hrs
0.793
116.00
91.99
Nos
0.099
400.00
39.60
20% on labour
7.92
5030.67
1%
50.31
5080.98
691.78
5772.76
14547.35
12122.79
first floor
UNIT 1 sqm
A) MATERIAL REQUIREMENT for 1.20x2.10m door
ALUMINIUM SECTION
vertical 2*2.10=4.20
no 2408
no 4504
horizantals 2*1.20=2.40
total 4.20+2.40=6.60 rmt*1.505kg=9.933
midle no 4621 1*1.20=1.20*1.505=1.806
total 12.98+9.933+1.806=24.719 kgs BMS.W.01
tinted-bronze/green GLASS 5mm thick
1.20*1.05=1.26 BMT.I.08
SILICON SEALANT
1.495
kg
24.719
321.00
7934.80
sqm
1.26
644.00
811.44
LS
150.00
RMT
6.60
2.00
13.20
Alum.Anodised.PC HandlesBMT-G-34
each
140.00
280.00
each
141.00
141.00
each
63.00
63.00
each
935.00
935.00
sqm
1.26
863.00
1087.38
11415.82
4530.09
B) LABOUR CHARGES
1st Class Carpenter
day
0.099
420.00
41.58
day
0.020
375.00
7.43
day
0.099
375.00
37.13
day
0.099
375.00
37.13
Unskilled Mazdoor
day
0.297
320.00
95.04
20% on labour
43.66
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
BMC.X.02
Hrs
0.793
125.00
99.13
Hrs
0.793
116.00
91.99
Nos
0.099
400.00
39.60
20% on labour
7.92
25.79
5056.46
1%
50.56
5107.03
695.32
5802.35
14621.92
12184.93
2nd floor
UNIT 1 sqm
A) MATERIAL REQUIREMENT for 1.20x2.10m door
ALUMINIUM SECTION
vertical 2*2.10=4.20
no 2408
no 4504
horizantals 2*1.20=2.40
total 4.20+2.40=6.60 rmt*1.505kg=9.933
midle no 4621 1*1.20=1.20*1.505=1.806
total 13.72+9.933+1.806=25.459 kgs BMS.W.01
tinted-bronze/green GLASS 5mm thick
1.20*1.05=1.26 BMT.I.08
SILICON SEALANT
kg
24.719
321.00
7934.80
sqm
1.26
644.00
811.44
LS
150.00
RMT
6.60
2.00
13.20
Alum.Anodised.PC HandlesBMT-G-34
each
140.00
280.00
each
141.00
141.00
each
63.00
63.00
each
935.00
935.00
sqm
1.26
863.00
1087.38
11415.82
4530.09
B) LABOUR CHARGES
1st Class Carpenter
day
0.099
420.00
41.58
day
0.020
375.00
7.43
day
0.099
375.00
37.13
day
0.099
375.00
37.13
Unskilled Mazdoor
day
0.297
320.00
95.04
20% on labour
43.66
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
BMC.X.02
Hrs
0.793
125.00
99.13
Hrs
0.793
116.00
91.99
Nos
0.099
400.00
39.60
20% on labour
7.92
51.58
5082.25
1%
50.82
5133.08
698.87
5831.94
14696.50
12247.08
24494.16
3rd floor
UNIT 1 sqm
A) MATERIAL REQUIREMENT for 1.20x2.10m door
ALUMINIUM SECTION
vertical 2*2.10=4.20
no 2408
no 4504
horizantals 2*1.20=2.40
total 4.20+2.40=6.60 rmt*1.505kg=9.933
midle no 4621 1*1.20=1.20*1.495=1.794
total 12.98+9.933+1.794=24.707kgs BMS.W.01
tinted-bronze/green GLASS 5mm thick
1.20*1.05=1.26 BMT.I.08
SILICON SEALANT
kg
24.707
321.00
7930.95
sqm
1.26
644.00
811.44
LS
150.00
RMT
6.60
2.00
13.20
Alum.Anodised.PC HandlesBMT-G-34
each
140.00
280.00
each
141.00
141.00
each
63.00
63.00
each
935.00
935.00
sqm
1.26
863.00
1087.38
11411.97
4528.56
B) LABOUR CHARGES
1st Class Carpenter
day
0.099
420.00
41.58
day
0.020
375.00
7.43
day
0.099
375.00
37.13
day
0.099
375.00
37.13
Unskilled Mazdoor
day
0.297
320.00
95.04
20% on labour
43.66
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
BMC.X.02
Hrs
0.793
125.00
99.13
Hrs
0.793
116.00
91.99
Nos
0.099
400.00
39.60
20% on labour
7.92
77.37
5106.51
1%
51.07
5157.58
26
702.20
5859.78
14766.65
12305.55
Supply and fixing Aluminium Anodised Two/ Three Track Sliding Windows as per approved drawing with
aluminium anodised sections of Series C Jindal sections and outer frame top horizontals & both verticals
of 8774 of size 62 x 29.5 mm and bottom horizontal - two track frame of 8773 of size 62 x 29.5 mm,
Shutter frame top, bottom and verticals of 8304 of size 50 mm x 20 mm and Weather interlocking frame
of 8306 of size 50 x 20 with plain clear float glass 5 mm thick fixed including supply and fixing aluminium
handles of 100 mm for each shutter, nylon rollers assembly and all labour charges for fixing the fixtures
with required no.of screws, bolts and nuts and including labour charges for fixing the frame in position,
fixing shutter to frame etc. completed for finished item of work BLD-CSTN-11-30 - Item -10 of - Revised
data.
grond floor
UNIT 1 sqm
A) MATERIAL REQUIREMENT for 1.20x1.35m
BMS.W.01
kgs
8.544
321.00
2742.62
8774 1.35mx2=2.70
Total
8304
Total
2x2x1.35= 5.40
7.80 x 0.642=5.00
sqm
1.62
558.00
LS
903.96
50.00
Rmt
7.80
2.00
15.60
Each
75.00
150.00
3862.18
2384.06
day
0.096
420.00
40.32
day
0.289
375.00
108.38
day
0.096
375.00
36.00
day
0.096
375.00
36.00
Unskilled Mazdoor
day
0.289
320.00
92.48
20% labour
62.64
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Hrs
0.771
125.00
96.38
Hrs
0.771
116.00
89.44
Nos
0.096
400.00
38.40
20% labour
7.68
2991.77
1%
29.92
3021.68
411.40
3433.08
6179.55
4943.64
9269.33
first floor
UNIT 1 sqm
A) MATERIAL REQUIREMENT for 1.20x1.35m
BMS.W.01
Aluminiun sections frame
top horizantal 8774 1.20mx1=1.20
kgs
8.544
321.00
2742.62
verticals
8774 1.35mx2=2.70
Total
8304
Total
2x2x1.35= 5.40
7.80 x 0.642=5.00
sqm
1.62
558.00
LS
903.96
50.00
Rmt
7.80
2.00
15.60
Each
75.00
150.00
3862.18
2384.06
B) LABOUR CHARGES
1st Class Carpenter
day
0.096
420.00
40.32
day
0.289
375.00
108.38
day
0.0960
375.00
36.00
day
0.0960
375.00
36.00
Unskilled Mazdoor
day
0.2890
320.00
92.48
20% labour
62.64
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Hrs
0.7710
125.00
96.38
Hrs
0.7710
116.00
89.44
Nos
0.096
400.00
38.40
20% labour
7.68
35.16
3026.92
1%
30.27
3057.19
416.24
3473.43
6252.17
9378.26
2nd floor
UNIT 1 sqm
kgs
8.544
321.00
2742.62
sqm
1.62
558.00
903.96
8774 1.35mx2=2.70
Total
8304
Total
2x2x1.35= 5.40
7.80 x 0.642=5.00
LS
50.00
Rmt
7.80
2.00
15.60
Each
75.00
150.00
3862.18
2384.06
B) LABOUR CHARGES
1st Class Carpenter
day
0.096
420.00
40.32
day
0.289
375.00
108.38
day
0.0960
375.00
36.00
day
0.0960
375.00
36.00
Unskilled Mazdoor
day
0.2890
320.00
92.48
20% labour
62.64
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Hrs
0.7710
125.00
96.38
Hrs
0.7710
116.00
89.44
Nos
0.096
400.00
38.40
20% labour
7.68
70.32
3062.08
1%
30.62
3092.70
421.07
3513.77
6324.79
5059.83
9487.19
3rd floor
UNIT 1 sqm
A) MATERIAL REQUIREMENT for 1.20x1.35m
BMS.W.01
kgs
8.544
321.00
2742.62
sqm
1.62
558.00
903.96
8774 1.35mx2=2.70
Total
8304
Total
2x2x1.35= 5.40
7.80 x 0.642=5.00
LS
50.00
Rmt
7.80
2.00
15.60
Each
75.00
150.00
3862.18
2384.06
B) LABOUR CHARGES
1st Class Carpenter
day
0.096
420.00
40.32
day
0.289
375.00
108.38
day
0.0960
375.00
36.00
day
0.0960
375.00
36.00
Unskilled Mazdoor
day
0.2890
320.00
92.48
20% labour
62.64
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Hrs
0.7710
125.00
96.38
Hrs
0.7710
116.00
89.44
Nos
0.096
400.00
38.40
20% labour
7.68
105.47
3097.24
1%
30.97
3128.21
27
28
29
425.91
3554.12
6397.41
5117.93
Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the size 50 x 47mm with a wall
thickness of 5mm, made out of extruded 5mm rigid PVC foam sheet, mitre cut at two corners and joined
with 2nos. of 150mm long brackets of 15x15mm M.S. square tube. The two vertical door profiles are to be
reinforced with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be fixed to the wall using
65/100mm long M.S. Screws through the frame by using PVC fasteners. A minimum of 4nos. of screws to
be provided for each vertical member & minimum 2nos. for horizontal member etc. complete as per
manufacturers specification and direction of Engineer-in-Charge for finished item of work unit 1.00 RmtBuilding SSR- 2015-16
Basic rate BMT-N.01
325.00
44.25
Rate/Rmt
369.25
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame made out of M.S. tubes
of 19 gauge thickness and size of 19mm x 19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S.
frame shall have a coat of steel primers of approved make and manufacture. M.S. frame shall be covered
with 5mm thick heat moulded PVC C channel of size 30 x 50mm forming stiles, and 5mm thick, 75mm
wide PVC sheets for top rail, lock rail & bottom rail on either side, and 10mm (5mm x 2) thick, 20mm wide
cross PVC sheet as gap insert for top rail & bottom rail. Panelling of 5mm thick PVC sheet to be fitted in
the M.S. frame welded / sealed to the stiles & rails with 30mm wide x 5mm thick PVC sheet beading on
either side, and joined together with solvent cement adhesive etc. An additional 5mm thick PVC strip of
20mm width is to be stuck on the interior side of the C Channel using PVC solvent adhesive. Complete
as per direction of Engineer-in-charge, manufacturers specification & drawing for finished item of work
unit 1.00 sqm - Building SSR- 2015-16
2362.00
321.59
Rate/sqm
2683.59
Providing concrete for plain/reinforced concrete in open foundations using 40 mm nominal size Graded
hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including
curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203
MORD and 1500, 1700 & 2100 MORTH. unit 1.00 cum
Nominal mix 1:3:6- For Flooring-BLDCSTN-2-2
Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per item 11.4. P.C.C grade
M 10
(a) Material
Cement
220
5.84
1284.80
Coarse sand
0.45
cum
1155.09
519.79
0.90
cum
1794.63
1615.16
Water
1.20
kl
103.00
123.60
(b) Labour
Mate
day
0.10
day
420.00
42.00
Mazdoor (Unskilled)
1.39
day
320.00
444.80
20% on labour
97.36
(c) Machinery
Concrete mixer 300/200 Diesel
1.00
hour
338.60
338.60
4466.11
0.00
4466.11
30
608.06
Total/cum
5074.17
Providing concrete for plain/reinforced concrete in open foundations using 20 mm nominal size Graded
hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including
curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203
MORD and 1500, 1700 & 2100 MORTH. unit 1.00 cum
Nominal mix M20 - RBR-SBST-5(II)
cement concrete M20nominal mix. Rate may be taken as per item 11.4. R.C.C grade M 20
(a) Material
Cement
0.33
5.84
1.93
Coarse sand
0.45
cum
1155.09
519.79
0.90
cum
1645.65
1481.09
day
0.10
day
420.00
42.00
Mazdoor (Unskilled)
1.39
day
320.00
444.80
(b) Labour
Mate
20% on labour
97.36
(c) Machinery
Concrete mixer 300/200 Diesel
0.40
hour
Generator 63 KVA
0.40
hour
Vibrator
338.60
135.44
0.00
0.00
2722.40
10%
272.24
2994.64
407.72
Total/cum
3402.36
31
Providing & Placing on Terrace (at all floor levels) polyethylene water storage tank with Double layer
approved brand & manufacture with cover and suitable locking arrangement & making necessary holes
for inlet & outlets and over flow pipes but without fittings & base support for tanks unit 1.00 litre
Basic rate BMW-G.01
6.00
0.82
6.82
32
Supplying & Fixing Orissa Pan white glazed W.C 1st quality ISI marked conforming to IS:2556-Part-31981 with "P" or "S" trap Hindware/ Parryware/ Neycer - ISI Mark: 630 mm x 450 mm unit each
Basic rate BMW-D.05
1665.00
226.69
1891.69
33
Supplying & Fixing low down porcelain flushing tank 10 Lit Capacity Hindustan Sanitary ware/ parry/
Neycer with internal components unit each
Basic rate BMW-D.11
2534.00
13.615% extra
345.00
2879.00
34
35
Supplying & Fixing Indian make Flat Back Wash Hand Basin (HSW/Parryware/ Neycer) 1st quality
conforming to IS:2556-Part-4:1972 with waste fittings like rubber plug, chain, 32 mm nominal size C.P.
Fitting with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore
Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/ Senior/ Nice/ Esso or equivalent
complete with standard CI brackets including wooden block: 550 x 400 mm - Double C.P. Pillar cock unit
each
Basic rate BMW-D.25
2169.00
295.31
2464.31
Supplying & Fixing white glazed flat back Bowl urinals of size 440 mm x 265 mm x 315 mm with internal
flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to IS:2556-1995
unit each
Basic rate BMW-D.33
930.00
126.62
1056.62
36
Supplying of 110 mm dia 3 M single Socket PVC/SWR pipe - 6 Kg/sq.cm Prince/Sudhakar/Kisan/Supreme or any ISI Brand. unit each
Basic rate BMW-G.35
828.00
112.73
940.73
Rate/Rmt
37
313.58
Supply of 110 mm dia - Plain Bend 87.5 Degree - UPVC/SWR Pipe fittings
(Prince/Sudhakar/Kisan/Supreme or any ISI Brand) unit each
Basic rate BMW-G.57
83.00
11.30
94.30
38
Supply of 110 mm dia - Single Tee with Door - UPVC/SWR Pipe fittings (Prince/Sudhakar/Kisan/Supreme
or any ISI Brand)unit each
Basic rate BMW-G.72
130.00
17.70
147.70
39
Supply of 110 mm dia - double Tee with Door - UPVC/SWR Pipe fittings (Prince/Sudhakar/Kisan/Supreme
or any ISI Brand)unit each
Basic rate BMW-G.75
260.00
35.40
295.40
40
Supply of 110 mm dia - Coupler - UPVC/SWR Pipe fittings (Prince/Sudhakar/Kisan/Supreme or any ISI
Brand unit each
Basic rate BMW-G.93
57.00
7.76
64.76
41
Labour charges for laying, fixing and commissioning the PVC pipes including couplers/ bends/ tees etc
any diameter including fixing necessary fittings like bends, plugs, couplers, junctions, tees, etc with
solvent jointing as per standard practice unit 1.00 Rmt
Basic rate BMW-G.152
70.00
9.53
79.53
42
Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber up to
914.4 mm (3'0") and fitted with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover of 20
Kg. unit each
Basic rate BMW-B.06
3825.00
520.77
Rate/each
4345.77
43
44
45
Rmt
1.00
244.00
285.00
38.80
Total
323.80
Rmt
1.00
195.00
195.00
26.55
Total
221.55
Rmt
1.00
157.00
157.00
21.38
Total
178.38
S & F Gunmetal (GM) horizantal non return valve as per IS - Class - I, Indian make heavy type - 25 mm
NB Size unit each
Basic rate BMW-F.47
870.00
118.45
Rate/each
988.45
S & F Gunmetal (GM) Ball valve with SS Ball and SS Spindle as per IS - Class - I, Indian make heavy
type - 25 mm NB Size unit each
46
47
48
49
912.00
124.17
Rate/each
1036.17
S & F Gunmetal (GM) Ball valve with SS Ball and SS Spindle as per IS - Class - I, Indian make heavy
type - 20 mm NB Size unit each
Basic rate BMW-F.57
621.00
84.55
Rate/each
705.55
S & F Gunmetal (GM) Ball valve with SS Ball and SS Spindle as per IS - Class - I, Indian make heavy
type - 15 mm NB Size unit each
Basic rate BMW-F.55
476.00
64.81
Rate/each
540.81
S&F 12.7 mm N.P bib tap Indian make heavy dutys Seiko/ Senior/ Nice or equivalent unit each
Basic rate BMW-E.07
407.00
55.41
Rate/each
462.41
Supply and Transportation of 1.0HP Single phase ISI Mono block CI body motor pumpset (25x25mm).
Makes: Kirloskar / Crompton / Texmo / CRI / KSB / Havells Hi-flow V1 ELEC-5.4.53
Basic rate
7455.00
1015.00
Rate/each
8470.00
50
Supply and fixing of 20 mm dia 1.50 mm thick PVC pipe concealed in walls with all required accessories
including masonary work for light , fan and plug point with metal deep box including all labour chages
unit 1.00 Rmt BLD-ELEC-1-4
Ground floor
taking out put 100m
a.
Material
20mm
dia 1.50mm thick PVC pipe item100m
20.00
2000.00
100 nos
44.00
88.00
each
184.00
552.00
each
12
22.00
264.00
each
12
4.00
48.00
kg.
50
5.84
292.00
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
day
420.00
840.00
52 ELEC-1.2.1
1.00
m=20.00
U links
ELEC-8.1.7 100nos=44.00
10''x8'' Metal box ELEC-1.3.11
20mm dia 1,2,3,4 way deep junction box
ELEC-1.2.38
20mm PVC bends ELEC-1.2.43
cement
b.Labour charges
20% on labour
638.00
7072.00
sundries 1%
0.00
7072.00
0.00
Total
7072.00
Rate/Rmt
b
70.72
1st floor
taking out put 100m
a.
Material
20mm
dia 1.50mm thick PVC pipe item100m
20.00
2000.00
100 nos
44.00
88.00
each
184.00
552.00
each
12
22.00
264.00
each
12
4.00
48.00
kg.
50
5.84
292.00
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
day
420.00
840.00
52 ELEC-1.2.1
1.00
m=20.00
U links
ELEC-8.1.7 100nos=44.00
10''x8'' Metal box ELEC-1.3.11
20mm dia 1,2,3,4 way deep junction box
ELEC-1.2.38
20mm PVC bends ELEC-1.2.43
cement
b.Labour charges
20% on labour
638.00
0.00
7072.00
sundries 1%
0.00
7072.00
0.00
Total
7072.00
Rate/Rmt
c
70.72
2nd floor
taking out put 100m
a.
Material
20mm
dia 1.50mm thick PVC pipe item100m
20.00
2000.00
100 nos
44.00
88.00
each
184.00
552.00
each
12
22.00
264.00
52 ELEC-1.2.1
1.00
m=20.00
U links
ELEC-8.1.7 100nos=44.00
10''x8'' Metal box ELEC-1.3.11
20mm dia 1,2,3,4 way deep junction box
ELEC-1.2.38
each
12
4.00
48.00
kg.
50
5.84
292.00
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
day
420.00
840.00
cement
b.Labour charges
20% on labour
638.00
0.00
7072.00
sundries 1%
0.00
7072.00
0.00
Total
7072.00
Rate/Rmt
d
70.72
3rd floor
taking out put 100m
a.
Material
20mm
dia 1.50mm thick PVC pipe item100m
20.00
2000.00
100 nos
44.00
88.00
each
184.00
552.00
each
12
22.00
264.00
each
12
4.00
48.00
kg.
50
5.84
292.00
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
day
420.00
840.00
52 ELEC-1.2.1
1.00
m=20.00
U links
ELEC-8.1.7 100nos=44.00
10''x8'' Metal box ELEC-1.3.11
20mm dia 1,2,3,4 way deep junction box
ELEC-1.2.38
20mm PVC bends ELEC-1.2.43
cement
b.Labour charges
20% on labour
lift charges 30% on labour
638.00
0.00
7072.00
sundries 1%
0.00
7072.00
0.00
7072.00
70.72
51
Supply and fixing of 25 mm dia 2.00 mm thick PVC pipe concealed in roof slab with all required
accessories including masonary work all labour chages unit 1.00 Rmt BLD-ELEC-1-4-2-
Ground floor
taking out put 100m
a. Material
25mm dia 2mm thick PVC pipe item-55 ELEC-1.2.4
25mm dia 1,2,3,4 way deep junction box item 90
ELEC-1.2.39
100m
32.00
3200.00
each
12
25.00
300.00
each
12
6.00
72.00
Skilled electrician
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
b.Labour charges
20% on labour
470.00
6392.00
sundries 1%
0.00
6392.00
0.00
Total
6392.00
Rate/Rmt
b
63.92
first floor
taking out put 100m
a. Material
25mm dia 2mm thick PVC pipe item-55 ELEC-1.2.4
25mm dia 1,2,3,4 way deep junction box item 90
ELEC-1.2.39
100m
32.00
3200.00
each
12
25.00
300.00
each
12
6.00
72.00
Skilled electrician
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
b.Labour charges
20% on labour
lift charges 10% on labour
470.00
0.00
6392.00
sundries 1%
0.00
6392.00
2nd floor
0.00
6392.00
63.92
100m
32.00
3200.00
each
12
25.00
300.00
each
12
6.00
72.00
Skilled electrician
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
b.Labour charges
20% on labour
470.00
0.00
6392.00
sundries 1%
0.00
6392.00
0.00
Total
6392.00
Rate/Rmt
d
63.92
3rd floor
taking out put 100m
a. Material
25mm dia 2mm thick PVC pipe item-55 ELEC-1.2.4
25mm dia 1,2,3,4 way deep junction box item 90
ELEC-1.2.39
100m
32.00
3200.00
each
12
25.00
300.00
each
12
6.00
72.00
Skilled electrician
day
480.00
960.00
day
375.00
750.00
Helpers
day
320.00
640.00
b.Labour charges
20% on labour
lift charges 30% on labour
470.00
0.00
6392.00
sundries 1%
0.00
6392.00
0.00
6392.00
63.92
52
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated Flexible copper cable in existing
pipe with 6A siwtch, ceiling rose and 3 mm thick hyla sheet covering to switch control box including all
labour charges etc,., complet for light, bell , fan and exhaust fan points in non - residential building- for 6
points unit eachBLD-ELEC-2-1
Ground floor
100m
1051.00
1051.00
each
101.00
606.00
each
16.00
96.00
Skilled electrician
day
0.60
480.00
288.00
day
1.20
375.00
450.00
Helpers
day
0.60
320.00
192.00
b.Labour charges
20% on labour
186.00
2869.00
sundries
0.00
2869.00
0.00
Total
2869.00
Rate/each
478.17
first floor
out put 6 points
a. Material
14/0.3 mm PVC FR flexible copper wire ELEC-1.5.1
100m
1051.00
1051.00
each
101.00
606.00
each
16.00
96.00
Skilled electrician
day
0.60
480.00
288.00
day
1.20
375.00
450.00
Helpers
day
0.60
320.00
192.00
b.Labour charges
20% on labour
lift charges 10% on labour
186.00
0.00
2869.00
sundries
0.00
2869.00
0.00
Total
2869.00
Rate/each
478.17
2nd floor
out put 6 points
a. Material
14/0.3 mm PVC FR flexible copper wire ELEC-1.5.1
100m
1051.00
1051.00
each
101.00
606.00
each
16.00
96.00
Skilled electrician
day
0.60
480.00
288.00
day
1.20
375.00
450.00
Helpers
day
0.60
320.00
192.00
b.Labour charges
20% on labour
186.00
0.00
2869.00
sundries
0.00
2869.00
0.00
Total
2869.00
Rate/each
478.17
3rd floor
out put 6 points
a. Material
14/0.3 mm PVC FR flexible copper wire ELEC-1.5.1
100m
1051.00
1051.00
each
101.00
606.00
each
16.00
96.00
Skilled electrician
day
0.60
480.00
288.00
day
1.20
375.00
450.00
Helpers
day
0.60
320.00
192.00
b.Labour charges
20% on labour
lift charges 30% on labour
186.00
0.00
2869.00
sundries
0.00
2869.00
53
0.00
Total
2869.00
Rate/each
478.17
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated Flexible copper cable in existing
pipe with 6A modular siwtch control and 3/2 pin sockets fixing on board including all labour charges unit
each BLD-ELEC-2-1-3
Ground floor
out put 15 points
a. Material
14/0.3 mm PVC FR flexible copper wire ELEC-1.5.1
100m
1051.00
1051.00
each
15
101.00
1515.00
each
15
141.00
2115.00
Skilled electrician
day
1.50
480.00
720.00
day
1.50
375.00
562.50
Helpers
day
1.50
320.00
480.00
b.Labour charges
20% on labour
352.50
6796.00
sundries
0.00
6796.00
0.00
Total
6796.00
Rate/each
453.07
first floor
out put 15 points
a. Material
14/0.3 mm PVC FR flexible copper wire ELEC-1.5.1
100m
1051.00
1051.00
each
15
101.00
1515.00
each
15
141.00
2115.00
Skilled electrician
day
1.50
480.00
720.00
day
1.50
375.00
562.50
Helpers
day
1.50
320.00
480.00
b.Labour charges
20% on labour
lift charges 10% on labour
352.50
0.00
6796.00
sundries
0.00
6796.00
0.00
Total
6796.00
Rate/each
453.07
2nd floor
100m
1051.00
1051.00
each
15
101.00
1515.00
each
15
141.00
2115.00
Skilled electrician
day
1.50
480.00
720.00
day
1.50
375.00
562.50
Helpers
day
1.50
320.00
480.00
b.Labour charges
20% on labour
352.50
0.00
6796.00
sundries
0.00
6796.00
0.00
Total
6796.00
Rate/each
453.07
3rd floor
out put 15 points
a. Material
14/0.3 mm PVC FR flexible copper wire ELEC-1.5.1
100m
1051.00
1051.00
each
15
101.00
1515.00
each
15
141.00
2115.00
Skilled electrician
day
1.50
480.00
720.00
day
1.50
375.00
562.50
Helpers
day
1.50
320.00
480.00
b.Labour charges
20% on labour
lift charges 30% on labour
352.50
0.00
6796.00
sundries
0.00
6796.00
0.00
Total
6796.00
Rate/each
453.07
54
Supply and run of 2 of 36/0.3 mm. (1.5. sq.mm) Fire retardant PVC insulated Flexible copper cable in
existing pipe for mains including all labour charges etc.,unit 1.00 rmtBLD-ELEC-3-1-4
Ground floor
out put 100 Rmt
a. Material
36/0.3 mm 2.50 sqmm PVC FR flexible copper wire
100m
ELEC-1.5.10
2195.00
4390.00
b.Labour charges
Skilled electrician
day
0.67
480.00
321.60
day
2.00
375.00
750.00
Helpers
day
0.67
320.00
214.40
20% on labour
257.20
5933.20
sundries
0.00
5933.20
0.00
Total
5933.20
Rate/Rmt
b
59.33
first floor
out put 100 Rmt
a. Material
36/0.3 mm 2.50 sqmm PVC FR flexible copper wire
100m
ELEC-1.5.10
2195.00
4390.00
b.Labour charges
Skilled electrician
day
0.67
480.00
321.60
day
2.00
375.00
750.00
Helpers
day
0.67
320.00
214.40
20% on labour
lift charges 10% on labour
257.20
0.00
5933.20
sundries
0.00
5933.20
2nd floor
out put 100 Rmt
a. Material
0.00
5933.20
59.33
2195.00
4390.00
b.Labour charges
Skilled electrician
day
0.67
480.00
321.60
day
2.00
375.00
750.00
Helpers
day
0.67
320.00
214.40
20% on labour
257.20
0.00
5933.20
sundries
0.00
5933.20
0.00
Total
5933.20
Rate/Rmt
d
59.33
3rd floor
out put 100 Rmt
a. Material
36/0.3 mm 2.50 sqmm PVC FR flexible copper wire
100m
ELEC-1.5.10
2195.00
4390.00
b.Labour charges
Skilled electrician
day
0.67
480.00
321.60
day
2.00
375.00
750.00
Helpers
day
0.67
320.00
214.40
20% on labour
257.20
0.00
5933.20
sundries
0.00
5933.20
0.00
Total
5933.20
Rate/Rmt
55
59.33
supply and run of 1 of 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated Flexible copper cable in
existing pipe for earth continuity including all labour charges etc. unit 1.00 rmtBLD-ELEC-3-1-2
out put 100 rmt
a. Material
14/0.3 mm 1.00 sqmm PVC FR flexible copper wire
100m
ELEC-1.5.1
1051.00
1051.00
0.34
480.00
163.20
b.Labour charges
Skilled electrician
day
day
1.00
375.00
375.00
Helpers
day
0.34
320.00
108.80
20% on labour
129.40
1827.40
sundries 1%
0.00
1827.40
0.00
Total
1827.40
Rate/Rmt
18.27
supply and run of 4 of 6 sq.mm (7/18) WPSC alluminium cable along with No.10 SWG G.I barer wire
through PVC cleats with all accessories including all labour charges etc.,unit 1.00 rmt
56
BLD-ELEC-6-1-4
out put 100 rmt
a. Material
6 sqmm WPSC Aluminium cableELEC-1.6.2
100m
1497.00
5988.00
kg.
13.40
68.00
911.20
kg.
25.00
70.00
1750.00
100 nos
440.00
440.00
Skilled electrician
day
2.00
480.00
960.00
day
2.00
375.00
750.00
Helpers
day
2.00
320.00
640.00
ELEC-8.1.41
Binding wire
PVC cleats ELEC-8.1.16
b.Labour charges
20% on labour
470.00
11909.20
sundries
0.00
11909.20
0.00
Total
11909.20
Rate/rmt
57
S&F of 63 Amps 415 V TPN swich disconnector fuse unit cubical type without fuses of makes
Standard/Crystal/Havells/HPL unit each
Basic rate ELEC-2.1.2
Overheads & Contractors Profit13.615%
Each
58
119.09
each
2445.00
2445.00
0.00
2445.00
Providing independent earthing by excavating a trench toa depyh of 2.10m in all soils, as per size specied
in data ,using 40 mm dia B class GI pipe 2.50m long with necessary accessories with hume pipe ring duly
providing staggered holes including filling with equal proportion of salt and charcoal in layers and all
labour charges etc complete unit eachBLD-ELEC-5-1-1
a. Material
cum
1.75
139.78
244.61
61.15
rmt
2.50
381.00
952.50
each
80.00
80.00
each
16
6.00
96.00
set
13.00
52.00
each
275.00
275.00
kg.
40
9.00
360.00
salt ELEC-8.1.14
kg.
20
4.00
80.00
day
0.50
375.00
187.50
Helpers
day
0.50
320.00
160.00
b .Labour
20% on labour
69.50
2618.26
0.00
Total
59
2618.26
S&F of TPN distrubution board with IP 42 protection (metal door) suitable for 3 phase ELCB-RCCB-FP
isolator as incomer and 10 KA SP MCBS as out going including internal connection and labour charges
for surface-flush mounting etc -- 63 A FP isolator-1 no for incomer,6-32A SP MCBS -18 Nos for out
going unit each BLD-ELEC-4-4-4
output each
a. Material
6 way TPN D.B with IP-42 Protection IS 13032
suitable for 18 Nos SP outgoing 1 no 4 pole incomer
etc., ELEC - 2 -12-58
each
1900.00
1900.00
each
2947.00
2947.00
each
12
201.00
2412.00
Skilled electrician
day
0.50
480.00
240.00
day
1.00
375.00
375.00
Helpers
day
1.00
320.00
320.00
b.Labour charges
20% on labour
187.00
8381.00
sundries
0.00
8381.00
0.00
8381.00
Supply of 48" (1200mm) Sweep Ceiling Fan without Regulator.of makes Crompton High Speed / Bajaj
Ultima / Havells Velocity / Usha Astra / Orient Summer Pride unit each
1600.00
0.00
Total
61
1600.00
Supply of stepped type Electronic Regulator of makes GM G Home / Gold Medal Olive / Million Zoom /
Anchor Penta Cherry / Great white Omega unit each
Basic rate ELEC-1.7.12
198.00
0.00
Total
62
198.00
Supply of 1 x 36/40W Box type tube light luminaire powder coated CRCA sheet steel housing with
Electronic Ballast Chokes and all standard accessoriesof makes Wipro / G.E. / Phillips / Crompton / Bajaj.
Unit each
Basic rate ELEC-3.6.7
1173.00
45.00
1218.00
0.00
Total
63
1218.00
Supply of 32A TP Plug and Socket in SS enclosure. Makes: Gold Medal / Milltec / Sputnik / Bentec /
Sigma / Anchor Panasonic / V-Guard( for AC board) unit each
Basic rate ELEC-2.12.69
each
1300.00
1300.00
0.00
Total
1300.00
64
RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh & nominal reinforcement as
directed by Engineer-in-charge with dubara sponge finishing, including cost & conveyance of all materials
to site, seigniorage charges, sales & other taxes on all materials, operational & incidental, cost and
conveyance of cement, wire mesh, water to work site, centering, scaffolding and form work, lift charges
etc., complete for finished items of work but excluding cost of steel & its fabrication charges, for finished
item of work. (APSS No.403 & 903) BLDCTSN 6-11
Ground floor
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop)
BMT-F-28
Cement Mortar 1:3 for 25 mm thick
Dry Cement for making Lumps
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides
sqm
13.30
17.00
226.10
cum
kg
sqm
0.25
50.00
21.80
4163.19
5.84
134.81
1040.80
292.00
2938.81
kg
26.40
42.90
1132.56
day
8.00
420.00
3360.00
Miller Operator
day
1.00
0.00
0.00
Mazdoor (unskilled)
day
10.00
320.00
3200.00
20% on labour
1312.00
c) Machinery
Machine Mixing Mortar with Miller - Hire charges
Hrs
2.00
338.60
677.20
14179.47
1930.53
16110.00
Rate/sqm
1611.00
first floor
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop)
BMT-F-28
sqm
13.30
17.00
226.10
cum
0.25
4163.19
1040.80
kg
50.00
sqm
21.80
134.81
2938.81
kg
5.00
42.90
214.50
day
8.00
420.00
3360.00
Miller Operator
day
1.00
0.00
0.00
Mazdoor (unskilled)
day
10.00
320.00
3200.00
0.00
B) LABOUR CHARGES
656.00
20% on labour
1312.00
c) Machinery
Machine Mixing Mortar with Miller - Hire charges
Hrs
2.00
338.60
677.20
13625.41
1855.10
15480.51
Rate/sqm
1548.05
2nd floor
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop)
BMT-F-28
Cement Mortar 1:3 for 25 mm thick
Dry Cement for making Lumps
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides
HYSD Steel/ Mild steel & Binding wire
B) LABOUR CHARGES
sqm
13.30
17.00
226.10
cum
0.25
4163.19
1040.80
kg
50.00
sqm
21.80
134.81
2938.81
kg
5.00
42.90
214.50
0.00
day
8.00
420.00
3360.00
Miller Operator
day
1.00
0.00
0.00
Mazdoor (unskilled)
day
10.00
320.00
3200.00
1312.00
20% on labour
1312.00
c) Machinery
Machine Mixing Mortar with Miller - Hire charges
65
Hrs
2.00
338.60
677.20
14281.41
1944.41
16225.82
Rate/sqm
1622.58
BLD-CSTN-1-4
A-MATERIALS
Cement
kg
720.00
5.84
4204.80
cum
1.05
1222.09
1283.19
cum
1.05
0.00
0.00
0.00
0.00
0.00
0.20
320.00
64.00
B- MACHINARY
Nil
C-LABOUR
Man mazdoor for mixing mortar
day
20% on labour
12.80
Grand total
66
5564.79
0.15
cum
3462.39
519.36
0.60
day
420.00
252.00
Mazdoor unskilled
0.96
day
320.00
307.20
Labour
20% on labour
111.84
1190.40
67
0.15
cum
5564.79
834.72
0.60
day
420.00
252.00
Labour
Mason 1st class
Mazdoor unskilled
0.96
day
320.00
20% on labour
307.20
111.84
1505.76
68
69
70
1505.76
1190.40
Rate/10 sqm
1348.08
Rate/ sqm
134.81
Providing and fixing of IS 3564 marked Aluminium extruded section body tubulor type univercel Hydralic
door closer with double speed adjustment Hardwyn make(GAZEL) with necessary accessiores and
screws BMT -G-74 Umit each
Basic rate
1198.00
163.11
Rate/each
1361.11
Providing concrete for plain/reinforced concrete in open foundations using 20 mm nominal size Graded
hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including
curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203
MORD and 1500, 1700 & 2100 MORTH. unit 1.00 cum Nominal mix 1:3:6 - RBR-FNDN-4
Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per item 11.4. P.C.C grade M 10
(a) Material
Cement
0.22
5840.00
1284.80
Coarse sand
0.45
cum
1155.09
519.79
0.90
cum
1645.65
1481.09
1.20
kl
103.00
123.60
day
0.10
day
420.00
42.00
1.39
day
320.00
444.80
(b) Labour
Mate
20% on labour
97.36
(c) Machinery
Concrete mixer 300/200 Diesel
item -16
0.40
hour
338.60
135.44
0.13
hour
630.00
81.90
4210.77
168.43
4379.20
596.23
Total/cum
4975.43
71
RCC M-20 Nominal mix (cement,fine aggregate,coarse aggregate) corresponding to Table -9 of IS -456
using 20 mm size graded machine crushed hard granite metal (coarse agggregate) from approved quarry
including cost and conveyance of all materials like cement,fine aggregate(sand),coarse aggregate ,water
etc to site and including seigniorage charges ,sales and other taxes on all materials including all
operational ,incidental and labour charges such as machine mixing ,laying concrete ,curing etc complete
but excluding cost of steel and its fabrication charges for finished item of work,but including
centering,shuttering unit 1.00cum for culvert slabs RBR-SBST-5 A
A. MATERIALS
20 mm graded HBG metal
0.90
cum
1645.65
1481.09
sand
0.45
cum
1155.09
519.79
330.00
kgs
5.84
1927.20
0.10
day
420.00
42.00
1.39
day
320.00
444.80
Cement
B. LABOUR
20% on labour
97.36
C MACHINERY
Concrete mixer 300/200 Diesel
item -16
Generator 33 kva
hour
0.40
338.60
135.44
hour
1.40
0.00
0.00
4647.67
464.77
5112.44
72
696.06
Rate/cum
5808.50
Total/cum
5808.50
Providing concrete for plain/reinforced concrete in open foundations using 2/3 of 40 mm and 1/3 of 20mm
nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by
vibration including curing for 14 days complete as per drawings and technical specifications Clause 802,
803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH.Nominal mix 1:3:6 - RBR-FNDN-4
Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per item 11.4.P.C.C grade M 10
Unit = cum
(a) Material
Cement
0.22
5840.00
1284.80
Coarse sand
0.45
cum
1155.09
519.79
0.60
cum
1326.63
795.98
0.30
cum
1846.63
553.99
1.20
kl
103.00
123.60
day
(b) Labour
Mate
0.10
day
420.00
42.00
1.39
day
320.00
444.80
20% on labour
97.36
(c) Machinery
Concrete mixer 300/200 Diesel
item -16
0.40
hour
338.60
135.44
0.13
hour
630.00
81.90
4079.65
4.00%
4.00%
163.19
4242.84
73
577.66
Total/cum
4820.50
Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a prepared
sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and
appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel
channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the
formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed
and plate vibrators and finished in continuous operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge /
culvert and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing
compound (where specified) and water finishing to lines and grade as per drawing and Technical
Specification Clause 1501 MORD. item RBR-CCPV-5 of standard data
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
Mate
day
day
5.00
420.00
2100.00
day
5.00
375.00
1875.00
day
150.00
320.00
48000.00
day
6.00
320.00
1920.00
Surveyor
day
2.00
0.00
0.00
day
6.00
320.00
1920.00
day
1.00
0.00
0.00
20% on labour
11163.00
b) Machinery
Concrete mixer 600/400 Diesel item-18
hour
36.00
0.00
0.00
Needle vibrator
hour
9.00
175.40
1578.60
Screed vibrator
hour
9.00
0.00
0.00
hour
9.00
0.00
0.00
hour
4.00
0.00
0.00
hour
5.00
630.00
3150.00
hour
2.00
0.00
0.00
25 mm 2/3*67.5=45.00 cum
cum
45.00
1794.63
80758.19
12.50 mm 1/3*67.50=22.50
cum
22.50
1578.63
35519.10
cum
33.75
1155.09
38984.17
30.00
5840.00
175200.00
sqm
412.50
0.00
0.00
0.118
0.00
0.00
kg
5.00
0.00
0.00
litre
19.00
96.00
1824.00
90.00
0.00
0.00
90.00
0.00
0.00
No.
483.00
0.00
0.00
litre
122.00
0.00
0.00
litre
kl
131.25
18.00
0.00
0.00
0.00
0.00
sqm
3.00
902.00
2706.00
c) Material
Crushed stone coarse aggregates, grading will be as
per Clause 1501.2.4.1 (Table 1500.1) of specifications
@ 0.90 cum/cum of concrete (25 mm & 12.5 mm
blending) 67.50 cum
406698.06
d) Formwork @ 3% of (a+b+c)
12200.94
418899.00
57033.10
475932.10
6345.76
supply and fixing of pre cast RCC jollys of approved design 50mm thick
unit 1.00 sqm
Basic rate BMS.W.17
sqm
1.00
402.00
402.00
54.73
Rate/sqm
456.73
74
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and conveyance
of materials to work site & all operational, incidental, labour charges etc complete for finshined item of
work as per SS 911 for Internal walls unit 10.00 sqm
Ground floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.360
Nos.
480.00
172.80
0.840
Nos.
375.00
315.00
20% MAA
0.200
772.35
154.47
0.010
1470.22
0.00
1470.22
147.02
0.136
147.022
167.04
First floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.360
Nos.
480.00
172.80
0.840
Nos.
375.00
315.00
20% MAA
0.200
772.35
154.47
0.010
1470.22
0.00
77.24
1547.46
154.75
0.136
154.746
20.02
21.07
175.82
2 nd floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.360
Nos.
480.00
172.80
0.840
Nos.
375.00
315.00
20% MAA
0.200
772.35
154.47
0.010
1470.22
0.00
154.47
1624.69
162.47
0.136
162.469
22.12
184.59
3rd floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.360
Nos.
480.00
172.80
0.840
Nos.
375.00
315.00
20% MAA
0.200
772.35
154.47
0.010
1470.22
0.00
231.71
1701.93
170.19
0.136
170.193
23.17
193.36
75
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and conveyance
of materials to work site & all operational, incidental, labour charges etc complete for finshined item of
work as per SS 911 for external l walls unit 10.00 sqm
Ground floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
Mazdoor
1.500
Nos.
320.00
480.00
20% MAA
0.200
1049.10
209.82
0.010
1802.32
1802.32
180.23
0.136
180.232
First floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
Mazdoor
1.500
Nos.
320.00
480.00
20% MAA
0.200
1049.10
209.82
0.010
1802.32
0.00
56.91
1859.23
185.92
0.136
185.923
25.31
211.23
2 nd floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
Mazdoor
1.500
Nos.
320.00
480.00
20% MAA
0.200
1049.10
209.82
0.010
1802.32
0.00
113.82
1916.14
191.61
0.136
191.614
24.54
204.77
0.00
26.09
217.70
3rd floor
Cost of cement primer grade-I BMT.J.01
1.000
Kg
165.00
165.00
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
0.800
Ltrs
473.00
378.40
0.210
Nos.
480.00
100.80
0.490
Nos.
375.00
183.75
Mazdoor
1.500
Nos.
320.00
480.00
20% MAA
0.200
1049.10
209.82
0.010
1802.32
0.00
170.73
1973.05
197.31
0.136
197.305
76
26.86
224.17
Flooring with chequrred terrazzo tiles of 22 mm thick (medium shade) (precast terrazzo chequered tiles
conforming to IS: 13801 using marble aggregates of size 10 mm , sand, marble powder, white cement
pigments etc., with terrazzo topping not less than 6 mm of tiles overall size not less than 20 mm thick of
any coloured shades.) set over base coat of cement mortar (1:6) 12 mm thick over CC bed already laid or
RCC roof slab, including near cement slurry of honey like consistency spread @ 3.3.kgs per sqm &
jointed with neat cement to full depth mixed with pigment of matching shade including cost of all materials
like cement, sand water and tiles etc., complete, including seigniorage charges, complete for finished item
of work, but excluding the cost of conveyance of all materials.BLD-CSTN-7-4
Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22mm thick
(mediumshade)
(precast terrazzo chequered tiles
conforming to IS: 13801 using marble aggregates of
size 10 mm , sand, marble powder, white cement
pigments etc., with terrazzo topping not less than 6
mm of tiles overall size not less than 20 mm thick of
any coloured shades.) BMT.D.01
sqm
10.05
314.00
3155.70
kg.
28.80
5.84
168.19
kg.
33.00
5.84
192.72
kg.
6.00
5.84
35.04
Pigment
kg.
cum
0.12
1222.09
146.65
cum
0.12
0.00
0.00
0.00
B. MACHINERY
0.00
Nill
0.00
C. LABOUR
0.00
day
0.960
375.00
360.00
Man mazdoor
day
2.240
320.00
716.80
Mazdoor (unskiled)
day
3.30
320.00
1056.00
20% on labour
426.56
6257.66
62.58
Grand Total
6320.24
860.50
7180.74
Rate /sqm
718.07
77
Flooring with ceramic tiles,(Non-skid red or white full body Ceramic floor tiles of size 300 x 300 mm and
thickness between 7-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish in all shades and designs ) set over base coat of cement mortar(1:8), 12mm thick over
CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread
@3.3. kgs per sqm & jointed neatly with white cement paste of full depth mixed with pigment of matching
shade,including cost of all materials like cement,sand water and tiles etc.,complete, including seigniorage
charges, etc., complete for finished item of work,but including the cost of conveyance of all
materials.BLD-CSTN-7-6
Ground floor
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles(Non-skid red or white full body Ceramic
floor tiles of size 300 x 300 mm and thickness
between 7-8 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and
finish in all shades and designs BMT-C.54)
sqm
10.10
450.00
4545.00
kg
21.60
5.84
126.14
kg
33.00
5.84
192.72
kg
2.00
29.00
58.00
cum
0.12
1222.09
146.65
cum
0.12
0.00
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskiled)
day
3.30
320.00
1056.00
B. LABOUR
20% on labour
459.84
7827.55
1.00%
78.28
7905.83
1076.38
Rate/10sqm
8982.21
Rate/sqm
898.22
First floor
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles(Non-skid red or white full body Ceramic
floor tiles of size 300 x 300 mm and thickness
between 7-8 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and
finish in all shades and designs BMT-C.54)
sqm
10.10
450.00
4545.00
kg
21.60
5.84
126.14
kg
33.00
5.84
192.72
kg
2.00
29.00
58.00
cum
0.12
1222.09
146.65
cum
0.12
0.00
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskiled)
day
3.3
320.00
1056.00
B. LABOUR
20% on labour
459.84
229.92
8057.47
1.00%
80.57
8138.05
1108.00
Rate/10sqm
9246.04
Rate/sqm
924.60
2nd floor
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles(Non-skid red or white full body Ceramic
floor tiles of size 300 x 300 mm and thickness
between 7-8 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and
finish in all shades and designs BMT-C.54)
sqm
10.10
450.00
4545.00
kg
21.60
5.84
126.14
kg
33.00
5.84
192.72
kg
2.00
29.00
58.00
cum
0.12
1222.09
146.65
cum
0.12
0.00
0.00
B. LABOUR
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskiled)
day
3.3
320.00
1056.00
20% on labour
459.84
459.84
8287.39
1.00%
82.87
8370.27
78
1139.61
Rate/10sqm
9509.88
Rate/sqm
950.99
Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles )glazed red or white full
body ceramic wall tiles of size 200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and
designs for skirting ) 7.30 mm thick length equal to flooring stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished
item of work, but including the cost of conveyance of all materials unit 10.00 sqm BLD-CSTN-7-18
Unit = 10 sqm
Ground floor
A. MATERIALS:
Ceramic tiles ( glazed red or white full body ceramic
wall tiles of size 200 x 300 mm / 245 mm x 325 mm
and thickness 6 mm 1st quality conforming to
IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish in all shades and designs for skirting
BMT-C.74)
sqm
10.00
660.00
6600.00
cum
0.12
1222.09
146.65
kgs
57.60
5.84
336.38
kgs
33.00
5.84
192.72
kgs
6.00
29.00
174.00
cum
0.12
0.00
0.00
day
0.77
420.00
323.40
Mazdoor (unskiled)
day
0.80
320.00
256.00
20% labour
115.88
8145.03
1108.95
Total/10 sqm
9253.98
Total/ sqm
925.40
First floor
A. MATERIALS:
Ceramic tiles BMT-C.01
sqm
10.00
660.00
6600.00
cum
0.12
1222.09
146.65
kgs
57.60
5.84
336.38
kgs
33.00
5.84
192.72
kgs
6.00
29.00
174.00
cum
0.12
0.00
0.00
day
0.77
420.00
323.40
Mazdoor (unskiled)
day
0.80
320.00
256.00
B. LABOUR
20% labour
115.88
57.94
8202.97
1116.83
Total/10 sqm
9319.81
Total/ sqm
931.98
2nd floor
A. MATERIALS:
Ceramic tiles BMT-C.01
sqm
10.00
660.00
6600.00
cum
0.12
1222.09
146.65
kgs
57.60
5.84
336.38
kgs
33.00
5.84
192.72
kgs
6.00
29.00
174.00
cum
0.12
0.00
0.00
day
0.77
420.00
323.40
Mazdoor (unskiled)
day
0.80
320.00
256.00
B. LABOUR
20% labour
115.88
115.88
8260.91
1124.72
Total/10 sqm
9385.64
Total/ sqm
938.56
79
Flooring with vitrified tiles of 1st quality, ( ordinary soluble salt porcelain vitrified tiles screen printed and
polished of size 400 x 400 mm and thickness between 8-9 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs) set over base coat
of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full
depth mixed with pigment of matching shade, including cost of all materials like cement, sand water and
tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but including
the cost of conveyance of all materials
.BLD-CSTN-7-5
Ground floor
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size( ordinary soluble salt
porcelain vitrified tiles screen printed and polished of
size 400 x 400 mm and thickness between 8-9 mm
1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs) BMT.C.58
sqm
10.10
560.00
5656.00
kg.
kg.
21.60
33.00
5.84
5.84
126.14
192.72
kg.
6.00
5.84
35.04
cum
0.12
1222.09
146.65
cum
0.020
1222.09
24.44
cum
0.140
0.00
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskiled)
day
3.30
320.00
1056.00
B. LABOUR
20% on labour
459.84
8940.04
1.00%
89.40
9029.44
1229.36
10258.79
1025.88
First floor
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size( ordinary soluble salt
porcelain vitrified tiles screen printed and polished of
size 400 x 400 mm and thickness between 8-9 mm
1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs) BMT.C.58
sqm
10.10
560.00
5656.00
kg.
21.60
5.84
126.14
kg.
33.00
5.84
192.72
kg.
6.000
5.84
35.04
cum
0.12
1222.09
146.65
cum
0.020
1222.09
24.44
cum
0.140
0.00
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskiled)
day
3.30
320.00
1056.00
B. LABOUR
20% on labour
459.84
229.92
9169.96
1.00%
91.70
9261.66
1260.97
10522.63
1052.26
2nd floor
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size( ordinary soluble salt
porcelain vitrified tiles screen printed and polished of
size 400 x 400 mm and thickness between 8-9 mm
1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs) BMT.C.58
sqm
10.10
560.00
5656.00
kg.
21.60
5.84
126.14
kg.
33.00
5.84
192.72
kg.
6.000
5.84
35.04
cum
0.12
1222.09
146.65
cum
0.020
1222.09
24.44
cum
0.140
0.00
0.00
B. LABOUR
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskiled)
day
3.30
320.00
1056.00
20% on labour
459.84
459.84
9399.88
Add water charges 1%
1.00%
94.00
9493.87
1292.59
10786.47
1078.65
80
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to flooring
stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency spread at
the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade
to full depth, including cost of all materials like tiles, cement, sand and water etc., complete including
seigniorage charges, etc., complete for finished item of work, but including the cost of conveyance of all
materials BLD-CSTN-7-20
Ground floor
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size( ordinary soluble salt
porcelain vitrified tiles screen printed and polished of
size 400 x 400 mm and thickness between 8-9 mm
1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs) BMT.C.58
sqm
10.10
560.00
5656.00
cum
0.12
1222.09
146.65
kgs
34.56
5.84
201.83
kgs
33.00
5.84
192.72
kgs
2.00
29.00
58.00
cum
0.12
0.00
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskilled)
day
3.30
320.00
1056.00
B. LABOUR
20 % on labour
459.84
9014.24
1.00%
90.14
Grand Total
9104.38
1239.56
Rate/10sqm
10343.94
Rate/sqm
1034.39
First floor
Unit = 10 sqm
A. MATERIALS:
sqm
10.10
560.00
5656.00
cum
0.12
1222.09
146.65
kgs
34.56
5.84
201.83
kgs
33.00
5.84
192.72
kgs
2.00
29.00
58.00
cum
0.12
0.00
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
Mazdoor (unskilled)
day
3.30
320.00
1056.00
B. LABOUR
20 % on labour
459.84
229.92
9244.16
1.00%
92.44
Grand Total
9336.60
1271.18
Rate/10sqm
10607.78
Rate/sqm
1060.78
2nd floor
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size( ordinary soluble salt
porcelain vitrified tiles screen printed and polished of
size 400 x 400 mm and thickness between 8-9 mm
1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs) BMT.C.58
sqm
10.10
560.00
5656.00
cum
0.12
1222.09
146.65
kgs
34.56
5.84
201.83
kgs
33.00
5.84
192.72
kgs
2.00
29.00
58.00
cum
0.12
0.00
0.00
day
0.96
420.00
403.20
day
2.24
375.00
840.00
B. LABOUR
Mazdoor (unskilled)
day
3.30
320.00
1056.00
20 % on labour
459.84
459.84
9474.08
1.00%
94.74
Grand Total
9568.82
1302.80
Rate/10sqm
10871.62
Rate/sqm
1087.16
81
Providing and fixing of top hung Ventilators made of pre-painted steel (Base steel as per IS 513 of 0.80
mm thick galvanized as per IS 277 with Zinc of 120 GSM), finish painted with a polyester paint of 60-65
microns thick and section for outer frame of 80 x 45 mm, centre mullion of 80 x 60 mm, section for shutter
of 52 x 25 mm x 0.6 mm thick, outer frame and mullions to have rebate for glazed shutter with a provision
for guard bars/grills and the sections cut to length metre joined with corner bracket, centre mullion fixed
with mullion cap, 1 No. of High grade nylon latch handle, window stopper, 2 nos. of with MS Powder
coated /SS ball bearing butt Hinges provided per shutter and windows fitted with 4 mm thick plain float
glass with rubber gaskets including fixing the frames in concrete/masonry wall by means of self expanding
screws, Including 10 mm Square guard bars with 6 (152.4mm) pitch etc., complete for finished item of
work
Double openable ventilator shutter Size of 4 0 x 2 0 (1219.2mm x 609.6mm) outer frame section size of
80 x 45mm,shutter frame section size of 52 x 25mm, vertical mullion section size of 80 x 60 mm BMTP.100
basic rate
Overheads & Contractors Profit 13.615%
Rate/sqm
6105.00
831.20
6936.20
Double fixed Louvers Ventilator size of 40 x 30 (1219.2mm x 914.4mm) outer frame box section size of
80 x 45mm , Vertical mullion section size of 80 x 60 mm BMT-P.104
basic rate
4177.00
568.70
Overheads & Contractors Profit 13.615%
Rate/sqm
4745.70
Manufacture as per BIS:12592 (Part 1&2)Supply & Delivery of manhole covers and frames with ISI
marking anywhere in A.P.,F.O.R. destination including, loading, unloading & stacking at site but including
central excise duty, sales tax, octroi and other Govt levies etc., as applicable.I.S.I Mark PH SSR Item No
-29
H.D.-20 with 500mm diaclear opening
central VAT 5%
1989.00
99.45
2088.45
82
284.34
Rate/each
2372.79
Supplying and fixing of false ceiling using Plaster of paris Boards 12 mm thick with standard GI ceiling
angles, sections perimeter channels including cost and conveyance of all materials and labour charges
etc complete BMT-M.53
basic rate
441.00
60.04
Rate/sqm
501.04
83
Supply and Transportation of 18W Down lighter with system lumens of 1580lm, suitable for Recessed /
Surface mounting made of diecast alluminium body with powder coating, acrylic diffuser with Driver,
operating voltage range of 150 to 265 Volts AC, P.F > 0.9, Surge protection: 2KV,THD<15%, with high
power LED's having efficacy of > 120 lumins/watt,CCT: 3000K - 5700K, minimum CRI>70, .etc., complete
a) LUMINAIRE MAKE : Phillips / OSRAM / GE / Crompton
b) LED MAKE : PHILIPS LUMILEDS / CREE / NICHIA / OSR
basic rate ELEC-3.9.13
2722.00
0.00
Rate/each
84
2722.00
Supply of Bulk head fitting with cast aluminium enamel painted body with water tight, clear glass with wire
guard hinged with lock and key arrangements etc., complete.Makes: Bajaj / Crompton / Surya
basic rate ELEC-8.1.4
396.00
0.00
Rate/each
84a
396.00
Supply of 6-32A 10KA DP MCB, C/D Curve ISI Mark. Makes: Legrand / Schneider
basic rate ELEC-ELEC-2.9.3
595.00
0.00
Rate/each
collection and supply and spreading of 90 to 45 mm HBG SS5 m/c metal for unit 1.00 cum -
595.00
85
RBR-SBBS-12(11)
Taking output = 300 cum
a) Labour
Mate
day
Mazdoor (Skilled)
day
2.48
320.00
793.60
Mazdoor (Unskilled)
day
10.00
320.00
3200.00
20% on labour
798.72
b) Machinery
Motor grader 110 HP 50 cum per hour
hour
6.00
0.00
0.00
Three
hour
hour
30.00
0.00
0.00
hour
12.00
0.00
0.00
hour
5.00
0.00
0.00
cum
300.00
1116.63
334987.96
kl
30.00
0.00
0.00
c) Material
90 to 45 mm HBG SS5 m/c metal
Water
339780.28
d&e) Overheads & Contractors Profit 13.615%
46261.09
386041.37
1286.80
86
collection and supply and spreading of 40 to 20 mm HBG SS5 m/c metal for unit 1.00 cum - RBR-SBBS12(11)
Taking output = 300 cum
a) Labour
Mate
day
Mazdoor (Skilled)
day
2.48
320.00
793.60
Mazdoor (Unskilled)
day
10.00
320.00
3200.00
20% on labour
798.72
b) Machinery
Motor grader 110 HP 50 cum per hour
hour
6.00
0.00
0.00
Three
hour
hour
30.00
0.00
0.00
hour
12.00
0.00
0.00
hour
5.00
0.00
0.00
cum
300.00
1626.63
487987.96
kl
30.00
0.00
0.00
c) Material
40 to 20 mm HBG SS5 m/c metal
Water
492780.28
87
67092.04
559872.32
1866.24
collection and supply and spreading of 20 to 10 mm HBG SS5 m/c metal for unit 1.00 cum - RBR-SBBS12(11)
Taking output = 300 cum
a) Labour
Mate
day
Mazdoor (Skilled)
day
2.48
320.00
793.60
Mazdoor (Unskilled)
day
10.00
320.00
3200.00
20% on labour
798.72
b) Machinery
Motor grader 110 HP 50 cum per hour
hour
6.00
0.00
0.00
Three
hour
hour
30.00
0.00
0.00
hour
12.00
0.00
0.00
hour
5.00
0.00
0.00
cum
300.00
1691.63
507487.96
kl
30.00
0.00
0.00
c) Material
20 to 10 mm HBG SS5 m/c metal
Water
512280.28
69746.96
582027.24
1940.09
Assistant Engineer
Superintending Engineer
Executive Engineer
Description of item
No
No
Qty
Rate
Unit
Total
Ground floor
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches
with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH
Note : Classifications of Earth Work
Specification are as per 302.2.1(a) of MORD and 301.2.1 of MORT&H--ordinary soil--manual
means upto 3m depth (Manual) for foundations of buildings in restricted places
Column footings
F1Type-A1,A4,F1,F2,F3,F4=6
F2TypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
F3TypeC1,C2,C3,D1,D2,D3,E2,E3=8
F4Type-G2,G3=2
2.55
2.55
2.00
78.03
10
2.95
2.95
2.00
174.05
3.60
3.60
2.00
207.36
1.70
1.70
2.00
11.56
471.00
471.00
258.06
cum
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches
with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH RBRFNDN-1 1(A) & SOR -2013-14 CL-2-II
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of
MORT&H--ordinary soil--manual means upto 3m depth
side entrace portico approach
4.00
5.20
0.30
6.24
4.00
4.50
0.30
5.40
2.375 0.50
0.20
0.48
2.05
0.50
0.20
0.41
1.73
0.50
0.20
0.69
2.05
0.50
0.20
0.62
1.40
0.50
0.20
0.70
1.14
0.50
0.20
0.23
0.81
0.50
0.20
0.16
2.00
0.50
0.20
0.40
A1-B1,A4-B4
GL= 0.15m
A2-B2,A3-B3
5.00-2.30/22.95/2=2.375
5.00-2.95=2.376
5.00C1-D1,C2-D2,D2-E2,D3-E3,
5.00C3-D3 5.003.60=1.40m
3.76-2.95/2E2-F2,E3-F3 3.76-3.60/22.30/2=0.81m
F2-G2,F3-G3 4.00-2.30/21.70/2=2.00m
121546.53
2.46
0.50
0.20
0.25
2.13
0.50
0.20
0.21
1.48
0.50
0.20
0.30
1.805 0.50
0.20
0.18
2.78
0.50
0.20
0.28
C2-C3,D2-D3,E2-E3
A2-A3,B2-B3 4.48-2.95=1.53
1.53
0.50
0.20
0.31
0.88
0.50
0.20
0.26
4.48F2-F3
4.48-2.30=2.18
3.60=0.88
2.18
0.50
0.20
0.22
G2-G3 4.48-1.70=2.78
2.78
0.50
0.20
0.28
1.585 0.50
0.20
0.16
1.26
0.50
0.20
0.13
0.94
0.50
0.20
0.28
4.21-3.60/2F3-F4 4.21-2.30=1.91
1.91
0.50
0.20
0.19
5.00
0.45
0.45
2.03
5.00 14.00
0.40
28.00
B1-B2,
5.085.08-2.95=2.13m
C1-C2,D1-D2
5.08-3.60=1.48
4.21-2.95/2B3-B4, 4.21-2.95=1.26
48.38
48.38
F1Type-A1,A4,F1,F2,F3,F4=6
2.55
2.55
0.15
5.85
F2TypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
10
2.95
2.95
0.15
13.05
F3TypeC1,C2,C3,D1,D2,D3,E2,E3=8
3.60
3.60
0.15
15.55
F4Type-G2,G3=2
1.70
1.70
0.15
0.87
4.00
5.20
0.10
2.08
4.00
4.50
0.10
1.80
10
4.70
0.50
0.10
2.35
3.46
0.50
0.10
0.69
4.55
0.50
0.10
1.37
4.63
0.50
0.10
0.46
4.48
0.50
0.10
0.90
4.18
0.50
0.10
0.21
B3-C3,C3-D3
A1-A2,C1-C2
3.76-
5.00-0.60/25.08(0.45-.15)-0.30/2=4.63
158.81
cum
7683.06
4.18
0.50
0.10
1.05
3.76
0.50
0.10
0.19
3.61
0.50
0.10
0.72
3.76
0.50
0.10
0.19
3.70
0.50
0.10
0.37
3.18
0.50
0.10
0.16
4.77
4.85
0.60
55.52
3.53
4.85
0.60
10.27
4.77
4.25
0.60
48.65
3.53
4.25
0.60
9.00
4.77
3.98
0.60
11.39
3.70
4.18
0.15
2.32
5.00 14.00
0.40
28.00
5.00
0.45
0.10
0.45
5.00 14.00
0.325
22.75
4.21-0.30/2B3-B4,D3-D4,E3-E4,F3-F4
4.21-0.30*2=3.61
4.00A1A2-B1B2
,B1B2-C1C2,
G2-G3 4.48-0.30=3.18
Basement 0.75-0.15=0.60
E1E2-F1F2
C1C2-
D1D2,D1D2-E1E2
3.76-0.23=3.53,
5.00-0.23=4.77,5.08-0.23=4.85
C2C3E2E3-F2F3
D2D3,D2D3-E2E3
5.08-0.23=4.85
A3A4-B3B4,B3B4-C3C4,
4.480.23=4.25
C3C4D3D4,D3D4-E3E4
front entrance
portico
3.76-0.23=3.53
5.004.000.23=4.77,4.21-0.23=3.98
resar
side ramps 0.75-0.15 M30
0.30=3.70,4.48-0.30=4.18
concrete
-0.10 CC 1:4:8=0.50
(0.50+0.30)/2=0.40
236.21
236.21
4
2.20
2.20
0.15
2.90
F2TypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
12
2.80
2.80
0.15
14.11
F2ATypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
2.90
2.90
0.15
2.52
1288.88
cum
304446.02
F3TypeC1,C2,C3,D1,D2,D3,E2,E3=8
3.30
3.30
0.15
9.80
F4Type-G2,G3=2
1.30
1.30
0.15
0.51
4.00
5.20
0.10
2.08
4.00
4.50
0.10
1.80
10
4.70
0.50
0.10
2.35
3.46
0.50
0.10
0.69
4.55
0.50
0.10
1.37
4.63
0.50
0.10
0.46
4.48
0.50
0.10
0.90
4.18
0.50
0.10
0.21
4.18
0.50
0.10
1.05
3.76
0.50
0.10
0.19
4.21-0.30/2B3-B4,D3-D4,E3-E4,F3-F4
0.30=3.76
4.21-0.30*2=3.61
C3-C4,
3.61
0.50
0.10
0.72
F2-G2,F3-G3
3.76
0.50
0.10
0.19
3.70
0.50
0.10
0.37
3.18
0.50
0.10
0.16
5.00
0.45
0.10
0.45
5.00 14.00
0.10
7.00
4.48- 0.30=4.18
F2-F3 4.48-0.30
4.21-0.15-0.30=3.76
4.00G2-G3 4.48-0.30=3.18
0.30=3.70m
side ramp walls
Ramps
49.82
50.00
4210.79
cum
210539.55
Providing concrete for plain/reinforced concrete in open foundations using 2/3 of 40 mm and 1/3 of
20mm nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation and
compacted by vibration including curing for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH.Nominal mix
1:3:6
Rear side ramp walls
5.00
0.45
0.25
1.13
5.00
0.35
0.375
1.31
2.44
2.44
4820.50
cum
11762.02
Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a
prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than
0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel
plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes,
compacted using needle, scareed and plate vibrators and finished in continuous operation
including provision of contraction and expansion, construction joints, applying debonding strips,
primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures
as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water
finishing to lines and grade as per drawing and Technical Specification Clause 1501 MORD.
10.50
3.12
2.70
16.32
16.32
6345.76 cum
Providing concrete for plain/reinforced concrete in open foundations using 40 mm nominal size
Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by
vibration including curing for 14 days complete as per drawings and technical specifications Clause
802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH. Nominal mix 1:4:8- For Flooring
A1A2-B1B2 ,B1B2-C1C2,
for flooring
E1E2-F1F2
1
1
1
5.00 14.00
4.00 5.20
4.00 4.50
0.15
0.15
0.15
103562.83
C1C2-
D1D2,D1D2-E1E2
4.77
4.85
0.15
13.88
A2A3-B2B3,B2B3-C2C3,
3.76-0.23=3.53,
5.00-0.23=4.77,5.08-0.23=4.85
3.53
4.85
0.15
2.57
C2C3E2E3-F2F3
D2D3,D2D3-E2E3
5.08-0.23=4.85
4.77
4.25
0.15
12.16
A3A4-B3B4,B3B4-C3C4,
4.48- 5.000.23=4.25
0.23=4.77,4.48-0.23 =4.25
3.53
4.25
0.15
2.25
C3C4D3D4,D3D4-E3E4
3.76-0.23=3.53
front entrance
portico
4.77
3.98
0.15
2.85
3.70
4.18
0.15
2.32
5.004.000.23=4.77,4.21-0.23=3.98
0.30=3.70,4.48-0.30=4.18
1
1
1
36.03
36.03
4210.79 cum
Supply and placing of the design mix concrete corresponding to IS -456 using WEIGH
BATCHER/MIXER using 20 mm size graded machine crushed hard granite metal (coarse
agggregate) from approved quarry including cost and conveyance of all materials like cement,fine
aggregate(sand),coarse aggregate ,water etc to site and including seigniorage charges ,sales and
other taxes on all materials including all operational ,incidental and labour charges such as weigh
batching ,machine mixing ,laying concrete ,curing etc complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS NO 402) with minimum cement content as per
IS Code from standard suppliers approved by the deparment including pumping ,
centering,shuttering,laying concrete ,vibrating,curing etc M25 design mix
Column footings
F1Type-A1,A4,F1,F2,F3,F4=6
2.35
2.00
0.20
3.76
151714.80
Tripizoidal portion
(2.00+0.60)/2=1.30
1.30
1.30
0.15
1.01
F2TypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
12
2.60
2.60
0.30
24.34
Tripizoidal portion
(2.6+0.75)/2=1.675
12
1.675 1.675
0.15
5.05
F2ATypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
2.70
2.70
0.30
4.37
Tripizoidal portion
(2.7+0.75)/2=1.725
1.725 1.725
0.15
0.89
F3TypeC1,C2,C3,D1,D2,D3,E2,E3=8
3.10
3.10
0.30
17.30
Tripizoidal portion
(3.10+0.75)/2=1.925
1.925 1.925
0.30
6.67
F4Type-G2,G3=2
1.10
0.25
0.61
1.10
64.00
64.00
b
8552.54
cum
547362.62
8977.46
cum
44887.31
Pedestals
F1Type-A1,A4,F1,F2,F3,F4=6
0.50
0.50
0.60
0.60
F2TypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
12
0.50
0.50
0.60
1.80
F2ATypeA2,A3,B1,B2,B3,B4,D4,E2,E4=1
0
0.50
0.50
0.60
0.30
F3TypeC1,C2,C3,D1,D2,D3,E2,E3=8
0.60
0.60
0.60
1.30
F4Type-G2,G3=2
0.50
0.50
0.60
0.30
4.30
5.00
A1-B1,B1-C1,C1-D1,D1-E1 ,
Plinth beams
PB1
,A4B4,B4-C4,
4.70
0.23
0.40
3.46
3.46
0.23
0.40
0.64
0.23
0.40
E1-F1,E4-F4
C4-D4,D4-E4 5.000.30=4.70
3.76-0.30=3.46
PB2
E2-F2,E3-F3,
A2-B2 ,B2-C2 ,C2-D2 ,A3-B3,
B3-C3,C3-D3
3.76-0.30=3.46
5.00-0.60/2D2-E2,D3-E3 5.00-0.30=4.70
0.30/2=4.55
PB3
3.46
0.23
0.40
0.64
4.55
0.23
0.40
2.51
4.70
0.23
0.40
0.86
0.23
0.40
A1-A2,C1-C2
B1-B2,D1-D2 ,E1-E2,F1-F2
4.63
0.23
0.40
0.85
5.08(0.45-.15)-0.30/2=4.63
A2-A3
4.48
0.23
0.40
1.65
4.18
0.23
0.40
0.38
4.18
0.23
0.40
1.92
3.76
0.23
0.40
0.35
3.61
0.23
0.40
1.33
3.76
0.23
0.40
0.35
3.70
0.23
0.60
1.02
8.70
0.23
0.60
1.20
4.78
0.23
0.45
0.49
WC front walls
5.00-0.30=4.700.23=4.47/2=2.235
2.24
0.23
0.23
0.24
WC partation walls
1.20
0.23
0.23
0.13
urinals
0.75
0.23
0.23
0.16
4.78
0.30
0.45
0.65
5.08-0.30-0.30=4.48
B2-B3,C2-C3,D2-D3,E2-E3,
4.48- 0.30=4.18
F2-F3 4.48-0.30
4.21-0.30/2B3-B4,D3-D4,E3-E4,F3-F4
4.21-0.30*2=3.61
PB4
4.00G2-G3 4.48-0.30=4.18
Inside toilets
18.82
18.82
d
C1
type F1 type footings
Columns
2.00--0.15-0.150.20-0.30-0.90
pedestal=0.30+0.75
C1
type F2 type footings
basement+3.60
superstructure=4.65 m
A1,F1,A4,F1,F2,F3,F4,=6
2.00--0.15-0.150.20-0.35-0.90
pedestal=0.25+0.75
C1
type F3 type footings
basement+3.60
superstructure=4.60 m
B1,B2,B3,B4,C4,D4,E1,E4,=8
2.00--0.15-0.150.30-0.40-0.90
pedestal=0.10+0.75
basement+3.60
superstructure=4.45 m
D2,D3,C1,D1,E2,E3=6
0.23 0.375
4.65
2.41
0.23 0.375
4.60
3.17
0.23 0.375
4.45
2.30
10665.33
cum
200721.42
2.00--0.15-0.150.20-0.35-0.90
pedestal=0.25+0.90
basement+3.60
C2
type F3 type footings
superstructure=4.75 m
A2,A3,=2
2.00--0.15-0.150.30-0.40-0.90
pedestal=0.10+0.75
basement+3.60
C3 type F4 type footings
superstructure=4.45 m
C2,C3=2
2.00--0.15-0.150.15-0.20-0.90
pedestal=0.45+0.30
basement+3.45
superstructure=4.20 m
G2,G3=2
e
Lintels
over doors citizen service center
office rooms
(5.00-0.30)
over doors tiolet entrance rooms
(5.000.30)=
Toilet inside rooms
5.00+0.23=5.23
over widows citizen service
center office rooms
(5.00-0.30)=
0.30
0.45
4.60
1.24
0.30
0.45
4.45
1.20
0.786
0.375 0.375
4.20
0.93
11.26
16.19
4.70
0.23
0.20
0.22
4.70
0.23
0.20
0.22
5.23
0.23
0.20
0.24
4.70
0.23
0.20
0.22
10702.75
cum
173277.45
10935.88
cum
9732.94
0.89
0.89
24.06 14.07
338.52
3.46
4.78
-16.54
4.60
5.38
24.75
346.73
346.73
3.78
1.73
6.54
3.78
1.73
6.54
3.99
1.73
6.90
1359.50
sqm
471380.25
1422.41
sqm
28405.56
19.97
19.97
h
A1-B1,B1-C1,C1-D1,D1-E1
,
Beams
GFRB1
,A4B4,B4-C4,
4.70
0.23
0.45
3.89
3.46
0.23
0.45
0.72
3.46
0.23
0.45
0.72
4.55
0.23
0.45
2.83
4.70
0.23
0.45
0.97
4.63
0.23
0.45
0.48
4.18
0.23
0.45
0.43
3.76
0.23
0.45
0.39
4.48
0.23
0.45
0.46
5.08-0.30F2-F3 4.48-0.30
4.18
0.23
0.45
0.43
F3-F4 4.21-0.30*2=3.61
3.61
0.23
0.45
0.37
4.48
0.23
0.45
1.39
4.63
0.23
0.45
0.48
E1-F1,E4-F4
C4-D4,D4-E4 5.000.30=4.70
3.76-0.30=3.46
GFRB2
B3-C3,C3-D3
5.00-0.60/2D2-E2,D3-E3 5.00-0.30=4.70
GFRB3
5.08-(0.45-.15)-
4.21-0.30/2-
GFRB4
5.08-(0.45-.15)-
4.21-
4.18
0.23
0.45
1.73
3.61
0.23
0.45
1.12
3.76
0.23
0.45
0.39
4.70
0.23
0.45
1.95
3.70
0.23
0.45
0.77
4.18
0.23
0.45
0.43
3.46
0.23
0.45
0.36
1
1
2
1
4.00
8.70
0.23
0.23
0.45
0.60
0.83
1.20
GFRB2a
4.00G2-G3 4.48-0.30=4.18
for staircase midlanding GFRB4
Portico beams
22.34
say
I
22.35
10509.67
cum
Column footings
46.00 cum
100
kg/cum 4599.90
Pedestals
5.00
cum
100
kg/cum
Plinth beams
18.82 cum
100
kg/cum 1882.00
columns
16.19 cum
120
kg/cum 1942.80
Lintels
0.89
cum
100
kg/cum
52.01 cum
80
kg/cum 4160.76
3.99
cum
80
kg/cum
Beams
22.35 cum
120
kg/cum 2682.00
sunshades
0.20
80
kg/cum
cum
234891.16
2586.95
500.00
89.00
319.52
15.84
16191.82
32383.64
48.74
Brick masonary in CM (1:6) with traditional bricks of size 23x11x7cm including cost and
10 conveyance of all materials and labour charges
Basement 0.75-0.45=0.30
kg
1578405.65
A1-B1,B1-C1,C1-D1,D1-E1 ,
,A4B4,B4-C4,
E1-F1,E4-F4
4.70
0.23
0.30
2.59
E2-F2,E3-F3,
C4-D4,D4-E4 5.003.76-0.30=3.46
0.30=4.70
A2-B2 ,B2-C2 ,C2-D2 ,A3-B3,
B3-C3,C3-D3
3.76-0.30=3.46
3.46
0.23
0.30
0.48
3.46
0.23
0.30
0.48
4.55
0.23
0.30
1.88
4.70
0.23
0.30
0.65
B1-B2,D1-D2 ,E1-E2,F1-F2
5.08(0.45-.15)-0.30/2=4.63
A2-A3
4.63
0.23
0.30
0.64
4.48
0.23
0.30
1.24
5.08-0.30-0.30=4.48
B2-B3,C2-C3,D2-D3,E2-E3,
4.48- 0.30=4.18
A3-A4
4.18
0.23
0.30
0.29
4.18
0.23
0.30
1.44
3.76
0.23
0.30
0.26
3.61
0.23
0.30
1.00
3.76
0.23
0.30
0.26
5.00-0.60/2A1-A2,C1-C2
D2-E2,D3-E3 5.00-0.30=4.70
0.30/2=4.55
F2-F3 4.48-0.30
4.21-0.30/2B3-B4,D3-D4,E3-E4,F3-F4
0.30=3.76
4.21-0.30*2=3.61
C3-C4,
Inside
toilets
4.21-0.15-0.30=3.76
0.30
4.78
0.23
0.30
0.33
WC front walls
5.00-0.30=4.700.23=4.47/2=2.235
2.235 0.23
0.30
0.31
WC partation walls
1.20
0.23
0.30
0.17
urinals
0.75
0.23
0.30
0.21
4.78
0.23
0.30
0.33
4.70
0.23
3.30
7.13
3.46
0.23
3.30
2.63
3.46
0.23
3.30
2.63
4.55
0.23
3.30
3.45
5.00-0.60/2-0.30/2=4.55
C1-C2
D2-E2,
5.00-0.30=4.70
4.70
0.23
3.30
3.57
D1-D2 ,E1-E2,
5.08-(0.45-.15)0.30/2=4.63
4.63
0.23
3.15
3.35
4.48
0.23
3.15
6.49
super structure
E1-F1
E2-F2,
5.00-0.30=4.70
3.76-0.30=3.46
C2-D2 ,
3.76-0.30=3.46
5.08-0.300.30=4.48
F1-F2
1
4.48
0.23
3.30
3.40
4.78
0.23
3.60
3.96
WC front walls
5.00-0.30=4.700.23=4.47/2=2.235
2.24
0.23
3.05
3.14
WC partation walls
1.20 0.115
3.05
0.84
urinals
0.75 0.115
0.75
0.26
4.78
0.23
3.60
3.96
4.00
0.23
0.30
0.28
4.78
0.23
0.30
0.66
0.50
24
1.73
0.30
0.15
0.93
3.78 0.115
0.75
0.65
1.20
0.23
2.10
-1.16
1.00
0.23
2.10
-0.97
Toilet doors D2
0.75
0.23
2.10
-1.45
1.80
0.23
1.50
-1.24
1.80
0.23
0.60
-0.50
ventilators toilets
0.80
0.23
0.60
-0.44
1.50
0.23
1.20
-0.41
staircase steps
staircase railing walls
deductions
lintels
-0.46
53.24
2.48
55.72
11
4869.38
cum
RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh & nominal reinforcement
as directed by Engineer-in-charge with dubara sponge finishing, including cost & conveyance of all
materials to site, seigniorage charges, sales & other taxes on all materials, operational & incidental,
cost and conveyance of cement, wire mesh, water to work site, centering, scaffolding and form
work, lift charges etc., complete for finished items of work but excluding cost of steel & its
fabrication charges, for finished item of work.
windows
vertical 1.50
1.50
0.83
4.98
horizontal bottom
1.80
0.83
2.99
0.60
0.83
1.99
1.80
0.83
5.98
vertical 0.60
0.60
0.83
3.98
0.80
0.83
5.31
ventilators toilets
271332.93
25.23
25.23
1611.00
sqm
40645.54
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing with
aluminium anodised sections of Jindal sections and outer frame top horizontals & both verticals of
2408 of size 101.6 x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of 4504 of size 44.45
mm x 47.62 mm x 3.18 and Middle lock rail of 4621 of size 49.91 x 44.45 x 3 mm with tintedbronze/green glass 5 mm thick(middle to top),MDF Board-exterior both sides laminaed 12mm
12 thick(middle to bottom) fixed including supply and fixing aluminium handles of 150 mm for each
shutter and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts and
including labour charges for fixing the frame in position, fixing shutter to frame etc. completed for
finished item of work
14547.35
each
29094.69
Supply and fixing Aluminium Anodised Two/ Three Track Sliding Windows as per approved drawing
with aluminium anodised sections of Series C Jindal sections and outer frame top horizontals &
both verticals of 8774 of size 62 x 29.5 mm and bottom horizontal - two track frame of 8773 of size
62 x 29.5 mm, Shutter frame top, bottom and verticals of 8304 of size 50 mm x 20 mm and
Weather interlocking frame of 8306 of size 50 x 20 with plain clear float glass 5 mm thick fixed
13 including supply and fixing aluminium handles of 100 mm for each shutter, nylon rollers assembly
and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts and including
labour charges for fixing the frame in position, fixing shutter to frame etc. completed for finished
item of work
windows 1.80x1.50m
9269.33
each
18538.66
50.00
kg/each
100.00
346.73
Staircase slabs
19.97
sides of beams
,A4B4,B4-C4,
4.70
0.45
33.84
3.46
0.45
6.23
3.46
0.45
6.23
4.55
0.45
24.57
4.70
0.45
8.46
4.63
0.45
4.17
4.18
0.45
3.76
3.76
0.45
3.38
4.48
0.45
4.03
5.08-0.30F2-F3 4.48-0.30
4.18
0.45
3.76
F3-F4 4.21-0.30*2=3.61
3.61
0.45
3.25
E2-F2,E3-F3,
A2-B2 ,B2-C2 ,C2-D2 ,A3-B3,
B3-C3,C3-D3
3.76-0.30=3.46
5.00-0.60/2D2-E2,D3-E3
0.30/2=4.55 5.00-0.30=4.70
5.08-(0.45-.15)-
4.21-0.30/2-
85.89
kg
8589.29
C1-C2
4.48
0.45
12.10
4.63
0.45
4.17
4.18
0.45
15.05
3.61
0.45
9.75
3.76
0.45
3.38
4.70
0.45
16.92
3.70
0.45
3.33
4.00G2-G3 4.48-0.30=4.18
4.18
0.45
1.88
3.46
0.45
3.11
C1 type
A1,F1,A4,F1,F2,F3,F4,=6
1.50
3.60
32.40
C1 type
B1,B2,B3,B4,C4,D4,E1,E4,=8
1.50
3.60
43.20
C1 type D2,D3,C1,D1,E2,E3=6
1.50
3.60
32.40
C2 type A2,A3,=2
1.80
3.60
12.96
1.80
3.60
12.96
3.142
0.30
3.60
6.79
front portico
4.00+4.48+0.30+4.00=12.78
12.78
0.30
3.83
portico beams
3.70
0.30
4.44
4.18
0.30
2.51
B2-B3,C2-C3,D2-D3,E2-E3,
5.08-(0.45-.15)0.30/2=4.63
B3-B4,D3-D4,E3-E4,
4.48-0.30
C3-C4,
4.210.30*2=3.61
A2'-B2',B2'-C2',C2'-D2',D2'-E2'
4.21-0.15-0.30=3.76
entrance
portico beams
5.00-0.30=4.70m
columns
2.00--0.15-0.150.30-0.40-0.90
pedestal=0.10+0.90
basement+3.60
superstructure=4.60 m
C3 type G2,G3=2
689.57
647.26
14
24.00
0.75
36.00
147.19
sqm
95270.42
14.06
3.75
52.73
4.00
0.75
3.00
4.78
0.75
7.17
98.90
24.68
3.75
92.55
3.46
3.30
-11.42
3.78
1.65
12.47
deduct doors D
1.20
2.10
-5.04
Toilet doors D1
1.00
2.10
-4.20
windows
1.80
1.50
-5.40
1.80
0.60
-2.16
ventilators toilets
0.80
0.60
-1.92
1.50
1.20
-1.80
Inside
171.98
15
18.02
190.00
14.24
3.60
102.53
16.76
3.75
62.85
3.46
3.30
-11.42
19.24
3.60
69.26
4.85
3.60
34.92
2.27
3.05
27.69
Toilets inside
1.20
3.05
14.64
urinals
0.75
1.65
4.95
deduct doors D
1.20
2.10
-5.04
Toilet doors D1
1.00
2.10
-4.20
0.75
2.10
-12.60
128.08
sqm
24335.56
windows
1.80
1.50
-5.40
1.80
0.60
-2.16
ventilators toilets
0.80
0.60
-1.92
1.50
1.20
-1.80
272.31
16
17.69
290.00
196.21
sqm
56900.13
1.80
456.73
sqm
822.12
8.10
137.81
sqm
1116.30
supply and fixing of pre cast RCC jollys of approved design 50mm
thick
RCC jolly in staircase room
1.50
1.20
Painting with Synthetic Enamel paints - Two Coats - For New Iron
17 Work including primary coat for window grills with primary coat of red
oxide one coat
iron safety grill of windows
1.50
2
1.80
1.50
Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the size 50 x 47mm with
a wall thickness of 5mm, made out of extruded 5mm rigid PVC foam sheet, mitre cut at two corners
and joined with 2nos. of 150mm long brackets of 15x15mm M.S. square tube. The two vertical door
profiles are to be reinforced with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be
18 fixed to the wall using 65/100mm long M.S. Screws through the frame by using PVC fasteners. A
minimum of 4nos. of screws to be provided for each vertical member & minimum 2nos. for
horizontal member etc. complete as per manufacturers specification and direction of Engineer-inCharge for finished item of work
Toilet entrance doors D1
2*(1.00+2.10)
6.20
12.40
5.70
22.80
35.20
369.25
Rmt
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame made out of M.S.
tubes of 19 gauge thickness and size of 19mm x 19mm for stiles, & 15mm x 15mm for top &
bottom rails. M.S. frame shall have a coat of steel primers of approved make and manufacture.
M.S. frame shall be covered with 5mm thick heat moulded PVC C channel of size 30 x 50mm
forming stiles, and 5mm thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail on either
side, and 10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap insert for top rail & bottom
19 rail. Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded / sealed to the stiles &
rails with 30mm wide x 5mm thick PVC sheet beading on either side, and joined together with
solvent cement adhesive etc. An additional 5mm thick PVC strip of 20mm width is to be stuck on
the interior side of the C Channel using PVC solvent adhesive. Complete as per direction of
Engineer-in-charge, manufacturers specification & drawing for finished item of work
1.00
2.10
4.20
Toilet doors D2
0.75
2.10
6.30
10.50
12997.56
2683.59
sqm
28177.66
222.96
sqm
36128.68
24.00 4.51
108.24
parking
10.00 5.38
53.80
162.04
Painting to new walls with two coats plastic emulsion paint of approved brand shade after
thoroughly brushing surface to remove dirt & remains of loose powerderd materials including cost
21 and conveyance of materials to work site & all operational, incidental, labour charges etc complete
for finshined item of work as per SS 911 for Internal walls with primary coat of cement primer one
coat
inside plastering area 12 mm thick
91.11
290.00
647.26
1028.36
1028.36
167.04
sqm
171779.98
Painting to new walls with two coats plastic emulsion paint of approved brand shade after
thoroughly brushing surface to remove dirt & remains of loose powerderd materials including cost
22 and conveyance of materials to work site & all operational, incidental, labour charges etc complete
for finshined item of work as per SS 911 for external walls with primary coat of cement primer one
coat
outside plastering area
RCC drop wall windows
RCC drop wall ventilators over
windows
RCC drop wall ventilators in
toilets
98.90
2
6.60
26.40
4.80
19.20
2.80
22.40
166.90
166.90
204.77
sqm
34176.45
Flooring with ceramic tiles,(Non-skid red or white full body Ceramic floor tiles of size 300 x 300 mm
and thickness between 7-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to
15) of any colour and finish in all shades and designs ) set over base coat of cement mortar(1:8),
12mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
23 consistency spread @3.3. kgs per sqm & jointed neatly with white cement paste of full depth mixed
with pigment of matching shade,including cost of all materials like cement,sand water and tiles
etc.,complete, including seigniorage charges, etc., complete for finished item of work,but including
toilet
rooms
the cost
of conveyance of all materials
staircase room
(5.00-0.23-0.23)/2
mid landing slab
2.270 4.85
22.02
3.53
4.85
17.12
3.53
1.50
5.30
44.43
44.43
898.22
sqm
Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles )glazed red or
white full body ceramic wall tiles of size 200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs for skirting ) 7.30 mm thick length equal to flooring stones, set over base coat
of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs
24 per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth,
including cost of all materials like tiles, cement, sand and water etc., complete including
seigniorage charges, etc., complete for finished item of work, but including the cost of conveyance
of all materials for skirting
staircase steps
12
1.73
0.45
18.68
3.78
0.20
3.02
midlanding 3.53+2*1.50
6.53
0.20
1.31
39907.95
14.24
1.50
42.72
wc gents 1.20+1.07
2.27
1.50
6.81
wc ladies 1.20+1.07
2.27
1.50
6.81
urinal walls
0.75
1.65
4.95
deduct doors
1.00
1.50
-3.00
0.75
1.50
-4.50
76.80
3.20
80.00
925.40
sqm
74034.14
1361.11 each
4
Flooring with chequrred terrazzo tiles of 22 mm thick (medium shade) (precast terrazzo chequered
tiles conforming to IS: 13801 using marble aggregates of size 10 mm , sand, marble powder, white
cement pigments etc., with terrazzo topping not less than 6 mm of tiles overall size not less than 20
mm thick of any coloured shades.) set over base coat of cement mortar (1:6) 12 mm thick over CC
bed already laid or RCC roof slab, including near cement slurry of honey like consistency spread @
26 3.3.kgs per sqm & jointed with neat cement to full depth mixed with pigment of matching shade
including cost of all materials like cement, sand water and tiles etc., complete, including
seigniorage charges, complete for finished item of work, but excluding the cost of conveyance of all
materials
front entrance portico
4.30
4.78
20.55
24.00 4.18
100.32
5444.43
120.87
120.87
718.07
sqm
86793.60
Flooring with vitrified tiles of 1st quality, ( ordinary soluble salt porcelain vitrified tiles screen printed
and polished of size 400 x 400 mm and thickness between 8-9 mm 1st quality conforming to
IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs) set
over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly
27 with white cement paste to full depth mixed with pigment of matching shade, including cost of all
materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc.,
complete for finished item of work, but including the cost of conveyance of all materials.
(5.00-
2.27
4.85
22.02
0.23-0.23)/2=2.27,
22.02
1025.88 sqm
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to
flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with
28 pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges, etc., complete for finished item of work, but
including the cost of conveyance of all materials
22589.86
(5.00-
14.24
0.20
5.70
deduct doors
1.00
0.20
-0.40
0.18
0.20
0.14
0.23-0.23)/2=2.27,
5.44
5.44
1034.39
sqm
5627.11
Providing and fixing of top hung Ventilators made of pre-painted steel (Base steel as per IS 513 of
0.80 mm thick galvanized as per IS 277 with Zinc of 120 GSM), finish painted with a polyester paint
of 60-65 microns thick and section for outer frame of 80 x 45 mm, centre mullion of 80 x 60 mm,
section for shutter of 52 x 25 mm x 0.6 mm thick, outer frame and mullions to have rebate for
glazed shutter with a provision for guard bars/grills and the sections cut to length metre joined with
corner bracket, centre mullion fixed with mullion cap, 1 No. of High grade nylon latch handle,
29 window stopper, 2 nos. of with MS Powder coated /SS ball bearing butt Hinges provided per shutter
and windows fitted with 4 mm thick plain float glass with rubber gaskets including fixing the frames
in concrete/masonry wall by means of self expanding screws, Including 10 mm Square guard bars
with 6 (152.4mm) pitch etc., complete for finished item of work
ventilators 1.80x0.60m
1.80
0.60
2.16
2.16
6936.20
sqm
4.85
2.27
22.02
14.24 0.30
8.54
14982.18
9111.74
0.23-0.23)/2=2.27,
borders on walls
30.56
501.04
sqm
15311.85
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of
water proof compound per bag of cement laid over roof when it is green including cost of all
materials, seigniorage charges, excluding conveyance charges of materials and including all
31 operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work
395.46
sqm
9787.66
septic tank
5.00
3.00
2.00
30.00
30.00
4.70
2.70
0.15
4764.20
1288.88
cum
2448.87
4210.79
cum
8000.50
4933.07
cum
46272.23
1.90
1.90
4.70
2.70
0.15
1.90
1.90
cum
158.81
4.70
0.35
2.00
6.58
short walls
2.00
0.35
2.00
2.80
9.38
9.38
Providing concrete for plain/reinforced concrete in open foundations using 20 mm nominal size
Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by
vibration including curing for 14 days complete as per drawings and technical specifications Clause
802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH. Lean cement concrete 1:3:6
nominal mix. Rate may be taken as per item 11.4.P.C.C grade M 10 Nominal mix 1:3:6
septic tank inside slope
2.35
2.00
0.025
0.24
0.24
4975.43
cum
1194.10
222.96
sqm
10167.04
4.00
2.50
10.00
walls 2(4.00+2.00)
12.00
2.00
24.00
Top 2(4.00+2.00)
12.00 0.35
14.80
4.20
0.50
7.40
45.60
45.60
4.70
2.70
0.15
1.90
1.90
5808.50
cum
11036.15
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel
(MS) steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works ,
including labour charges for straightening, cutting, bending to required sizes and shapes, placing
in position with cover blocks of approved materials and size and tying and lap-splicing with binding
wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental,
operational, labour charges such as cutting, bending, placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
120
1.90
228.00
48.74
kg
11112.91
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches
with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD
and 301.2.1 of MORT&H--ordinary soil--manual means upto 3m depth (Manual)
3.50
3.00
1.70
17.85
17.85
3.50
3.00
0.15
2834.70
1288.88
cum
2036.43
4210.79
cum
6653.05
4933.07
cum
30535.73
222.96
sqm
7183.82
1.58
1.58
3.50
3.00
0.15
1.58
1.58
cum
158.81
3.20
0.35
1.70
3.81
short walls
2.00
0.35
1.70
2.38
6.19
6.19
2.50
2.00
5.00
walls 2(3.20+2.00)
10.40
1.70
17.68
Top 2(3.20+2.00)
10.40 0.35
11.80
3.64
0.50
5.90
32.22
32.22
3.20
2.70
0.15
1.30
1.30
5808.50
cum
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel
(MS) steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works ,
including labour charges for straightening, cutting, bending to required sizes and shapes, placing
in position with cover blocks of approved materials and size and tying and lap-splicing with binding
wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental,
operational, labour charges such as cutting, bending, placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
7551.05
48.74
kg
120 1.30
156.00
Manufacture as per BIS:12592 (Part 1&2)Supply & Delivery of manhole covers and frames with ISI
marking anywhere in A.P.,F.O.R. destination including, loading, unloading & stacking at site but
including central excise duty, sales tax, octroi and other Govt levies etc., as applicable.I.S.I Mark
H.D.-20 with 500mm diaclear opening
7603.57
2372.79
2372.79
each
5478169.75
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Superintending Engineer
Executive Engineer
Description of item
No
No
Qty
Rate
Unit
Total
II First floor
Supply and placing of the design mix concrete corresponding to IS -456 using WEIGH
BATCHER/MIXER using 20 mm size graded machine crushed hard granite metal (coarse agggregate)
from approved quarry including cost and conveyance of all materials like cement,fine
aggregate(sand),coarse aggregate ,water etc to site and including seigniorage charges ,sales and
other taxes on all materials including all operational ,incidental and labour charges such as weigh
1 batching ,machine mixing ,laying concrete ,curing etc complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS NO 402) with minimum cement content as per IS
Code from standard suppliers approved by the deparment including pumping ,
centering,shuttering,laying concrete ,vibrating,curing etc M25 design mix
a Columns
C1 type
A1,A4,F1,F2,F3,F4,=6
0.23
0.375
3.60
1.86
C1 type
B1,B2,B3,B4,C4,D4,E1,E4,=8
0.23
0.375
3.60
2.48
C1 type D2,D3,C1,D1,E2,E3=6
0.23
0.375
3.60
1.86
C2 type A2,A3,=2
0.30
0.450
3.60
0.97
C2 type C2,C3=2
0.30
0.450
3.60
0.97
8.15
8.15
10921.43 cum
89053.33
11154.57 cum
32571.33
b Lintels
over doors
Engineering section,Town
planning section,Health
section,Establishment
section,Revenue
section,commissioner chamber
and waiting rooms
over doors tiolet entrance rooms
(5.000.30)=
Toilet inside rooms
5.00+0.23=5.23
commissioner anti room
over widows individual
Engineering section,Town
planning section,Health
section,Establishment
section,Revenue
section,commissioner chamber
1.60
0.23
0.20
0.59
4.70
0.23
0.20
0.22
5.23
0.23
0.20
0.24
1
1
1
5
1.60
2.20
0.23
0.23
0.20
0.20
0.07
0.51
4.70
0.23
0.20
1.30
2.92
2.92
24.06
14.07
338.52
3.46
4.78
-16.54
321.99
321.99
3.78
1.73
6.54
3.78
1.73
6.54
3.99
1.73
6.90
19.97
19.97
A1-B1,B1-C1,C1-D1,D1-E1 ,
e Beams
FFRB1
,A4B4,B4-C4,
E1-F1,E4-F4
C4-D4,D4-E4 5.00FFRB2
0.30=4.70
3.76-0.30=3.46
B3-C3,C3-D3
5.00-0.60/2D2-E2,D3-E3 5.00-0.30=4.70
4.70
0.23
0.45
3.89
3.46
0.23
0.45
0.72
3.46
0.23
0.45
0.72
4.55
0.23
0.45
2.83
4.70
0.23
0.45
0.97
4.63
0.23
0.45
0.48
4.18
0.23
0.45
0.43
3.76
0.23
0.45
0.39
4.48
0.23
0.45
0.46
1
1
1
1
4.18
3.61
0.23
0.23
0.45
0.45
0.43
0.37
4.48
0.23
0.45
1.39
4.63
0.23
0.45
0.48
4.18
0.23
0.45
1.73
3.61
0.23
0.45
1.12
3.76
0.23
0.45
0.39
4.70
0.23
0.45
0.97
3.46
0.23
0.45
0.36
FFRB3
5.08-(0.45-.15)-
4.21-0.30/25.08-0.30F2-F3 4.48-0.30
F3-F4 4.21-0.30*2=3.61
FFRB4
5.08-(0.45-.15)-
4.21FFRB2a
E2'-F2' 3.76-030
5.00-
1377.61
sqm
443577.44
1440.52
sqm
28767.22
3.46
0.23
0.45
0.36
18.49
18.50
10630.41 cum
196662.51
16
2.20
35.20
Engineering section,Town
planning section,Health
section,Establishment section,
20.30
0.75
15.23
commissioner
chamber,Revenue section
5.30
0.75
7.95
593.38
Rmt
20886.84
959.65
sqm
22244.63
23.18
23.18
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel
(MS) steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works ,
including labour charges for straightening, cutting, bending to required sizes and shapes, placing in
position with cover blocks of approved materials and size and tying and lap-splicing with binding wire
of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including
2 cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying including sales and other taxes on all
materials etc., complete for finished item of work in all floors.
columns
Lintels
Roof slab 0.15m thick
Staircase slabs 0.20m thick
Beams
sunshades
loft slab 0.075m thick
8.15
2.92
48.30
3.99
18.50
1.58
1.74
cum
cum
cum
cum
cum
cum
cum
120
100
80
80
120
80
80
kg/cum
kg/cum
kg/cum
kg/cum
kg/cum
kg/cum
kg/cum
978.48
292.00
3863.88
319.52
2220.00
126.72
139.08
7939.68
8510.52
4.70
0.23
3.30
28.54
3.46
0.23
3.30
2.63
3.46
0.23
3.30
2.63
4.55
0.23
3.30
10.36
4.70
0.23
3.30
3.57
4.63
0.23
3.30
3.51
E4-F4
C4-D4,D4-E4 5.00E1-F1,
0.30=4.70
3.76-0.30=3.46
A2-B2 ,B2-C2 ,C2-D2
3.76-0.30=3.46
A1-A2
5.00-0.60/2-0.30/2=4.55
D2-E2,
5.00-0.30=4.70
5.08-(0.45-.15)0.30/2=4.63
48.74
kg
414809.85
A2-A3
1
4.18
0.23
3.30
3.17
3.76
0.23
3.30
2.85
0.30=3.76
4.48
0.23
3.30
3.40
5.08-0.30F2-F3 4.48-0.30
0.30=4.48
4.18
0.23
3.30
3.17
B1-B2,D1-D2
,E1-E2,
F3-F4 4.21-0.30*2=3.61
3.61
0.23
3.30
2.74
C1-C2
4.48
0.23
3.15
9.74
5.08-0.30-0.30=4.48
B2'-B4,C2'-C4,D2'-D4,E2'-E4,
5.08-(0.45-.15)0.30/2=4.63
A2'-B2',B2'-C2',
4.210.30/2+4.48-.30-2.40=
C2'-D2',D2'-E2'
5.000.30=4.70m
4.63
0.23
3.15
3.35
5.84
0.23
3.15
16.92
4.70
0.23
3.60
7.78
4.70
0.23
3.30
7.13
4.85
0.23
3.60
4.02
2.27
0.23
3.60
1.88
2.70
0.115
3.05
0.95
4.78
0.23
3.60
3.96
WC front walls
5.00-0.30=4.700.23=4.47/2=2.235
2.24
0.23
3.05
3.14
WC partation walls
1.20
0.115
3.05
0.84
urinals
0.75
0.115
0.75
0.26
0.50
24
1.73
0.30
0.15
0.93
3.78
0.115
0.75
0.65
doors D
1.20
0.23
2.10
-4.64
1.20
0.23
2.10
-1.16
Toilet doors D2
windows
ventilators
ventilators toilets
RCC jolly in staircase room
lintels
2
1
1
2
1
2
16
16
2
1
0.75
1.80
1.80
0.80
1.50
0.23
0.23
0.23
0.23
0.23
2.10
1.50
0.60
0.60
1.20
-1.45
-9.94
-3.97
-0.44
-0.41
-2.92
103.19
A3-A4
4.48- 0.30=4.18
F1-F2
4.21-0.30/2-
Inside toilets
staircase steps
staircase railing walls
deductions
2.81
106.00
4973.40
cum
527204.29
RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh & nominal reinforcement as
directed by Engineer-in-charge with dubara sponge finishing, including cost & conveyance of all
materials to site, seigniorage charges, sales & other taxes on all materials, operational & incidental,
4 cost and conveyance of cement, wire mesh, water to work site, centering, scaffolding and form work,
lift charges etc., complete for finished items of work but excluding cost of steel & its fabrication
charges, for finished item of work.
windows
vertical 1.50
16
1.50
0.83
39.84
horizontal bottom
16
1.80
0.83
23.90
16
0.60
0.83
15.94
16
1.80
0.83
47.81
vertical 0.60
0.60
0.83
3.98
0.80
0.83
5.31
ventilators toilets
136.78
136.78
1548.05
sqm
211742.40
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing with aluminium
anodised sections of Jindal sections and outer frame top horizontals & both verticals of 2408 of size
101.6 x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of 4504 of size 44.45 mm x 47.62
mm x 3.18 and Middle lock rail of 4621 of size 49.91 x 44.45 x 3 mm with tinted-bronze/green glass 5
mm thick(middle to top),MDF Board-exterior both sides laminaed 12mm thick(middle to bottom) fixed
5
including supply and fixing aluminium handles of 150 mm for each shutter and all labour charges for
fixing the fixtures with required no.of screws, bolts and nuts and including labour charges for fixing the
frame in position, fixing shutter to frame etc. completed for finished item of work
doors 1.20x2.10m D
Supply and fixing Aluminium Anodised Two/ Three Track Sliding Windows as per approved drawing
with aluminium anodised sections of Series C Jindal sections and outer frame top horizontals & both
verticals of 8774 of size 62 x 29.5 mm and bottom horizontal - two track frame of 8773 of size 62 x
29.5 mm, Shutter frame top, bottom and verticals of 8304 of size 50 mm x 20 mm and Weather
interlocking frame of 8306 of size 50 x 20 with plain clear float glass 5 mm thick fixed including supply
6 and fixing aluminium handles of 100 mm for each shutter, nylon rollers assembly and all labour
charges for fixing the fixtures with required no.of screws, bolts and nuts and including labour charges
for fixing the frame in position, fixing shutter to frame etc. completed for finished item of work
windows 1.80x1.50m
16
16
16
50.00
kg/each
800.00
89.07
kg
71259.33
321.99
Staircase slabs
19.97
sides of beams
E3-F3,E2-F2
4.70
0.30
5.64
3.46
0.45
3.11
350.71
349.68
173.35
sqm
60615.91
143.99
sqm
53275.04
76.00
3.75
285.00
20.30
3.60
146.16
3.78
1.65
12.47
deduct doors D
1.20
2.10
-20.16
1.00
2.10
-4.20
windows
16
1.80
1.50
-43.20
16
1.80
0.60
-17.28
ventilators toilets
0.80
0.60
-1.92
1.50
1.20
-1.80
inside
inside corridor 4*5.00+0.30
Inside
355.07
Add extra for sides and soffits
14.93
370.00
10
21.20
3.60
305.28
entrance hall
3.53+1*6.06+4.21+4.48
18.28
3.60
65.81
Revenue section,commissioner
chamber and waiting rooms
2(4.77+4.85)
19.24
3.60
207.79
16.76
3.75
62.85
3.46
3.30
-11.42
4.85
3.60
34.92
2.27
3.60
16.34
2.70
3.05
16.47
19.24
3.60
69.26
4.85
3.60
34.92
2.27
3.05
27.69
Toilets inside
1.20
3.05
14.64
urinals
0.75
1.65
4.95
deduct doors D
1.20
2.10
-20.16
1.00
2.10
-4.20
0.75
2.10
-12.60
windows
16
1.80
1.50
-43.20
16
1.80
0.60
-17.28
ventilators toilets
0.80
0.60
-1.92
1.50
1.20
-1.80
748.35
11
748.35
212.11
sqm
158734.41
1.80
456.73
sqm
822.12
145.48
sqm
9427.36
supply and fixing of pre cast RCC jollys of approved design 50mm thick
RCC jolly in staircase room
1.50
1.20
Painting with Synthetic Enamel paints - Two Coats - For New Iron Work
12 including primary coat for window grills with primary coat of red oxide
one coat
iron safety grill of windows
1.50
16
1.80
1.50
64.80
64.80
Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the size 50 x 47mm with a
wall thickness of 5mm, made out of extruded 5mm rigid PVC foam sheet, mitre cut at two corners and
joined with 2nos. of 150mm long brackets of 15x15mm M.S. square tube. The two vertical door
profiles are to be reinforced with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be
13 fixed to the wall using 65/100mm long M.S. Screws through the frame by using PVC fasteners. A
minimum of 4nos. of screws to be provided for each vertical member & minimum 2nos. for horizontal
member etc. complete as per manufacturers specification and direction of Engineer-in-Charge for
finished item of work
Toilet entrance doors
D12*(1.00+2.10)
Toilet doors 2(0.75+2.10) D2
commissioner room toilet D2
6.20
12.40
5.70
22.80
5.70
5.70
40.90
369.25
Rmt
15102.27
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame made out of M.S.
tubes of 19 gauge thickness and size of 19mm x 19mm for stiles, & 15mm x 15mm for top & bottom
rails. M.S. frame shall have a coat of steel primers of approved make and manufacture. M.S. frame
shall be covered with 5mm thick heat moulded PVC C channel of size 30 x 50mm forming stiles, and
5mm thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail on either side, and 10mm (5mm
x 2) thick, 20mm wide cross PVC sheet as gap insert for top rail & bottom rail. Panelling of 5mm thick
14 PVC sheet to be fitted in the M.S. frame welded / sealed to the stiles & rails with 30mm wide x 5mm
thick PVC sheet beading on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior side of the C Channel
using PVC solvent adhesive. Complete as per direction of Engineer-in-charge, manufacturers
specification & drawing for finished item of work
Toilet entrance doors D1
1.00
2.10
4.20
Toilet doors D2
0.75
2.10
6.30
0.75
2.10
1.58
12.08
12.08
2683.59
sqm
32417.72
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and
conveyance of materials to work site & all operational, incidental, labour charges etc complete for
15
finshined item of work as per SS 911 for Internal walls with primary coat of cement primer one coat
85.00
748.35
349.68
1183.03
1183.03
175.82
sqm
207995.01
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and
16 conveyance of materials to work site & all operational, incidental, labour charges etc complete for
finshined item of work as per SS 911 for external walls with primary coat of cement primer one coat
outside plastering area
285.00
16
6.60
105.60
16
4.80
76.80
2.80
44.80
512.20
512.20
211.23
sqm
108193.54
Flooring with ceramic tiles,(Non-skid red or white full body Ceramic floor tiles of size 300 x 300 mm
and thickness between 7-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15)
of any colour and finish in all shades and designs ) set over base coat of cement mortar(1:8), 12mm
thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
17 consistency spread @3.3. kgs per sqm & jointed neatly with white cement paste of full depth mixed
with pigment of matching shade,including cost of all materials like cement,sand water and tiles
etc.,complete, including seigniorage charges, etc., complete for finished item of work,but including the
toilet rooms
cost of conveyance of all materials
1
2.270
4.85
22.02
staircase room
(5.00-0.23-0.23)/2
mid landing slab
3.53
4.85
17.12
3.53
1.50
5.30
1.50
1.20
1.80
46.23
46.23
924.60
sqm
42744.46
Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles )glazed red or white
full body ceramic wall tiles of size 200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and
designs for skirting ) 7.30 mm thick length equal to flooring stones, set over base coat of CM (1:3) 12
mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and
18 jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of
all materials like tiles, cement, sand and water etc., complete including seigniorage charges, etc.,
complete for finished item of work, but including the cost of conveyance of all materials for skirting
staircase steps
12
1.73
0.45
18.68
3.78
0.20
3.02
midlanding 3.53+2*1.50
6.53
0.20
1.31
14.24
1.50
42.72
wc gents 1.20+1.07
2.27
1.50
6.81
wc ladies 1.20+1.07
2.27
1.50
6.81
urinal walls
0.75
1.65
4.95
deduct doors
1.00
1.50
-3.00
0.75
1.50
4.20
1.50
-4.50
6.30
76.80
add sides of doors
3.20
80.00
925.40
sqm
74034.14
1361.11 each
13611.08
2
10
Flooring with vitrified tiles of 1st quality, ( ordinary soluble salt porcelain vitrified tiles screen printed and
polished of size 400 x 400 mm and thickness between 8-9 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs) set over base
coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat
20 cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement
paste to full depth mixed with pigment of matching shade, including cost of all materials like cement,
sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of
work, but including the cost of conveyance of all materials.
inside corridor 4*5.00
20.00
2.40
48.00
Engineering section,Town
planning section,Health
section,Establishment section,
2(4.77+5.83)
4.77
5.83
111.24
entrance hall
3.53
8.69
30.68
Revenue section,commissioner
chamber and waiting rooms
2(4.77+4.85)
4.77
4.85
69.40
1.65
1.35
-2.23
257.09
257.09
1052.26
sqm
270526.30
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to
flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with
21 pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges, etc., complete for finished item of work, but
including the cost of conveyance of all materials
inside corridor 4*5.00
20.00
0.20
8.00
Engineering section,Town
planning section,Health
section,Establishment section,
2(4.77+5.83)
21.20
0.20
16.96
entrance hall
18.28
0.20
3.66
Revenue section,commissioner
chamber and waiting rooms
2(4.77+4.85)
19.24
0.20
11.54
4.85
0.20
1.94
2.27
0.20
0.91
deduct doors
1.20
0.20
-3.84
0.18
0.20
0.58
39.74
39.74
1060.78
sqm
42155.32
Providing and fixing of top hung Ventilators made of pre-painted steel (Base steel as per IS 513 of
0.80 mm thick galvanized as per IS 277 with Zinc of 120 GSM), finish painted with a polyester paint of
60-65 microns thick and section for outer frame of 80 x 45 mm, centre mullion of 80 x 60 mm, section
for shutter of 52 x 25 mm x 0.6 mm thick, outer frame and mullions to have rebate for glazed shutter
with a provision for guard bars/grills and the sections cut to length metre joined with corner bracket,
22 centre mullion fixed with mullion cap, 1 No. of High grade nylon latch handle, window stopper, 2 nos. of
with MS Powder coated /SS ball bearing butt Hinges provided per shutter and windows fitted with 4
mm thick plain float glass with rubber gaskets including fixing the frames in concrete/masonry wall by
means of self expanding screws, Including 10 mm Square guard bars with 6 (152.4mm) pitch etc.,
complete for finished item of work
ventilators 1.80x0.60m
16
1.80
0.60
17.28
17.28
0.80
0.60
6936.20
sqm
119857.46
4745.70
sqm
9111.74
1.92
1.92
Supplying and fixing of false ceiling using Plaster of paris Boards 12 mm thick with standard GI ceiling
23 angles, sections perimeter channels including cost and conveyance of all materials and labour charges
etc complete
inside corridor 4*5.00
20.00
2.40
48.00
Engineering section,Town
planning section,Health
section,Establishment section,
2(4.77+5.83)
4.77
5.83
111.24
entrance hall
3.53
8.69
30.68
Revenue section,commissioner
chamber and waiting rooms
2(4.77+4.85)
4.77
4.85
69.40
20.00
0.30
12.00
Engineering section,Town
planning section,Health
section,Establishment section,
2(4.77+5.83)
21.20
0.30
25.44
entrance hall
18.28
0.30
5.48
Revenue section,commissioner
chamber and waiting rooms
2(4.77+4.85)
19.24
0.30
17.32
4.85
0.30
2.91
2.27
0.30
1.36
borders on walls
323.83
323.83
501.04
sqm
162252.48
3706683.03
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Superintending Engineer
Executive Engineer
Description of item
No
No
Qty
Rate
Unit
Total
Supply and placing of the design mix concrete corresponding to IS -456 using WEIGH
BATCHER/MIXER using 20 mm size graded machine crushed hard granite metal (coarse
agggregate) from approved quarry including cost and conveyance of all materials like cement,fine
aggregate(sand),coarse aggregate ,water etc to site and including seigniorage charges ,sales and
other taxes on all materials including all operational ,incidental and labour charges such as weigh
batching ,machine mixing ,laying concrete ,curing etc complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS NO 402) with minimum cement content as per IS
Code from standard suppliers approved by the deparment including pumping , centering,
shuttering,laying concrete ,vibrating,curing etc M25 design mix
Columns
C1 type
A1,A4,F1,F2,F3,F4,=6
0.23
0.375
3.60
1.86
C1 type
B1,B2,B3,B4,C4,D4,E1,E4,=8
0.23
0.375
3.60
2.48
C1 type D2,D3,C1,D1,E2,E3=6
0.23
0.375
3.60
1.86
C2 type A2,A3,=2
0.30
0.450
3.60
0.97
C2 type C2,C3=2
0.30
0.450
3.60
0.97
8.15
8.15
11371.89 cum
92726.36
11538.22 cum
31614.72
Lintels
over doors
chair person room,Record
room,Computor section,
establishment section
1.40
0.23
0.20
0.26
4.70
0.23
0.20
0.22
5.23
0.23
0.20
0.24
Main door
2.40
0.23
0.20
0.11
2.20
0.23
0.20
0.40
4.70
0.23
0.20
1.51
2.74
2.74
24.06
14.07
338.52
3.46
4.78
-16.54
321.99
321.99
1417.54
sqm 456432.63
3.78
1.73
6.54
3.78
1.73
6.54
3.99
1.73
6.90
19.97
19.97
1480.45
sqm
29564.50
A1-B1,B1-C1,C1-D1,D1-E1
,
Beams
SFRB1
,A4-B4,B4-C4,
4.70
0.23
0.45
3.89
3.46
0.23
0.45
0.72
3.46
0.23
0.45
0.72
4.55
0.23
0.45
2.83
4.70
0.23
0.45
0.97
4.18
0.23
0.45
0.87
4.48
0.23
0.45
0.46
4.48
0.23
0.45
0.46
1
1
1
1
4.18
3.61
0.23
0.23
0.45
0.45
0.43
0.37
4.63
0.23
0.45
0.48
4.18
0.23
0.45
0.43
3.76
0.23
0.45
0.39
4.48
0.23
0.45
0.93
4.63
0.23
0.45
0.48
4.18
0.23
0.45
1.30
3.61
0.23
0.45
0.75
3.76
0.23
0.45
0.39
3.46
0.23
0.45
0.36
E1-F1,E4-F4
C4-D4,D4-E4
5.00-0.30=4.70
SFRB23.76-0.30=3.46
C3,C3-D3
D2-E2,D3-E3 5.00-0.30=4.70
SFRB3
4.48-
F2-F3 4.48-0.30
F3-F4 4.21-0.30*2=3.61
SFRB4
4.21-0.30/2-
17.22
17.22
17
2.20
37.40
14.06
0.75
10.55
5.30
0.75
3.98
614.35
Rmt
22976.76
990.52
sqm
14382.30
14.52
14.52
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel
(MS) steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works ,
including labour charges for straightening, cutting, bending to required sizes and shapes, placing in
position with cover blocks of approved materials and size and tying and lap-splicing with binding wire
of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including
cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all incidental, operational,
labour charges such as cutting, bending, placing in position, tying including sales and other taxes on
all materials etc., complete for finished item of work in all floors.
columns
8.15
cum
120
kg/cum
978.48
Lintels
2.74
cum
100
kg/cum
274.00
48.30
cum
80
kg/cum 3863.88
3.99
cum
80
kg/cum
Beams
17.22
cum
120
kg/cum 2066.56
sunshades
1.68
cum
80
kg/cum
134.64
1.09
cum
80
kg/cum
87.12
319.52
7724.20
8221.56
3
4.70
0.23
3.30
28.54
3.46
0.23
3.30
2.63
3.46
0.23
3.30
2.63
4.55
0.23
3.30
3.45
0.30/2=4.55
D2-E2, 5.00-0.30=4.70
A1-A2
4.70
0.23
3.30
3.57
A2-A3
4.63
0.23
3.30
3.51
4.18
0.23
3.30
3.17
E4-F4
3.76-0.30=3.46
E1-F1, 3.76-0.30=3.46
C4-D4,D4-E4
5.00-0.30=4.70
C2-D2
5.00-0.60/2-
4.48- 0.30=4.18
5.08-(0.45-.15)-0.30/2=4.63
48.74
kg
400725.70
A3-A4
F1-F2 5.08-0.30-0.30=4.48
4.21-0.30/20.30=3.76
3.76
0.23
3.30
2.85
4.48
0.23
3.30
3.40
F2-F3 4.48-0.30
4.18
0.23
3.30
3.17
F3-F4 ,E1-E2,
4.21-0.30*2=3.61
D1-D2
3.61
0.23
3.30
2.74
4.48
0.23
3.15
6.49
5.84
0.23
3.15
8.46
4.63
0.23
3.15
3.35
4.18
0.23
3.15
3.03
3.76
0.23
3.15
2.72
4.70
0.23
3.30
7.13
5.00-0.30=4.70m
3.43
0.23
3.30
2.60
4.78
0.23
3.60
3.96
WC front walls
5.00-0.30=4.700.23=4.47/2=2.235
2.24
0.23
3.05
3.14
WC partation walls
1.20
0.115
3.05
0.84
urinals
0.75
0.115
0.75
0.26
0.50
24
1.73
0.30
0.15
0.93
3.78
0.115
0.75
0.65
Main door
2.00
0.23
2.10
-0.97
doors D
1.20
0.23
2.10
-2.32
1.20
0.23
2.10
-1.16
Toilet doors D2
0.75
0.23
2.10
-1.45
windows
17
1.80
0.23
1.50
-10.56
ventilators
17
1.80
0.23
0.60
-4.22
ventilators toilets
0.80
0.23
0.60
-0.44
1.50
0.23
1.20
-0.41
D2'-D4,E2'-E4,
5.08-0.30-0.30=4.48
C1-C2
4.21-0.30/2+4.48-.30-2.40=
C2-C3, 4.48-0.30
5.08-(0.45-.15)-0.30/2=4.63
C3-C4,
C2'-D2',D2'-E2'
4.21-0.15-0.30=3.76
E2'-F2'
Inside toilets
staircase steps
staircase railing walls
deductions
lintels
-2.74
78.97
2.03
81.00
5077.43
cum
411285.13
RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh & nominal reinforcement
as directed by Engineer-in-charge with dubara sponge finishing, including cost & conveyance of all
materials to site, seigniorage charges, sales & other taxes on all materials, operational & incidental,
cost and conveyance of cement, wire mesh, water to work site, centering, scaffolding and form work,
lift charges etc., complete for finished items of work but excluding cost of steel & its fabrication
charges, for finished item of work.
windows
vertical 1.50
17
1.50
0.83
42.33
horizontal bottom
17
1.80
0.83
25.40
17
0.60
0.83
16.93
17
1.80
0.83
50.80
vertical 0.60
0.60
0.83
3.98
0.80
0.83
5.31
ventilators toilets
144.75
144.75
24494.16 each
24494.16
doors 1.20x2.10m D
14696.50 each
58785.99
Supply and fixing Aluminium Anodised Two/ Three Track Sliding Windows as per approved drawing
with aluminium anodised sections of Series C Jindal sections and outer frame top horizontals & both
verticals of 8774 of size 62 x 29.5 mm and bottom horizontal - two track frame of 8773 of size 62 x
29.5 mm, Shutter frame top, bottom and verticals of 8304 of size 50 mm x 20 mm and Weather
interlocking frame of 8306 of size 50 x 20 with plain clear float glass 5 mm thick fixed including supply
and fixing aluminium handles of 100 mm for each shutter, nylon rollers assembly and all labour
charges for fixing the fixtures with required no.of screws, bolts and nuts and including labour charges
for fixing the frame in position, fixing shutter to frame etc. completed for finished item of work
17
17
sqm 234868.79
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing with
aluminium anodised sections of Jindal sections and outer frame top horizontals & both verticals of
2408 of size 101.6 x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of 4504 of size 44.45
mm x 47.62 mm x 3.18 and Middle lock rail of 4621 of size 49.91 x 44.45 x 3 mm with tintedbronze/green glass 5 mm thick(middle to top),MDF Board-exterior both sides laminaed 12mm
thick(middle to bottom) fixed including supply and fixing aluminium handles of 150 mm for each
shutter and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts and
including labour charges for fixing the frame in position, fixing shutter to frame etc. completed for
finished item of work
windows 1.80x1.50m
7
1622.58
17
50.00
kg/each
850.00
321.99
Staircase slabs
19.97
sides of beams
B1-B2-C2-D2
13.77
0.30
8.26
92.26
kg
78417.07
A2-B2-C2
9.47
0.30
11.36
3.46
0.45
3.11
364.70
363.66
186.64
sqm
67873.41
76.00
3.75
285.00
14.06
3.60
101.23
3.78
1.65
12.47
2.00
2.10
-4.20
deduct doors D
1.20
2.10
-10.08
1.00
2.10
-4.20
windows
17
1.80
1.50
-45.90
17
1.80
0.60
-18.36
ventilators toilets
0.80
0.60
-1.92
1.50
1.20
-1.80
inside
inside corridor 2*5.00+3.76+0.30
Inside
312.25
Add extra for sides and soffits
17.75
330.00
10
21.20
3.60
152.64
18.72
3.60
67.39
19.24
3.60
69.26
46.62
3.60
167.83
16.76
3.75
62.85
3.46
3.30
-11.42
19.24
3.60
69.26
4.85
3.60
34.92
2.27
3.05
27.69
Toilets inside
1.20
3.05
14.64
urinals
0.75
1.65
4.95
2.00
2.10
-4.20
deduct doors D
1.20
2.10
-10.08
1.00
2.10
-4.20
153.88
sqm
50780.83
1.00
2.10
-16.80
windows
1.80
1.50
0.00
1.80
0.60
0.00
ventilators toilets
0.80
0.60
-1.92
1.50
1.20
-1.80
621.03
18.97
640.00
222.01
sqm 142086.39
1.80
456.73
sqm
822.12
153.15
sqm
10544.59
11 supply and fixing of pre cast RCC jollys of approved design 50mm thick
RCC jolly in staircase room
12
1.50
1.20
Painting with Synthetic Enamel paints - Two Coats - For New Iron Work
including primary coat for window grills
iron safety grill of windows
1.50
17
1.80
1.50
68.85
68.85
Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the size 50 x 47mm with a
wall thickness of 5mm, made out of extruded 5mm rigid PVC foam sheet, mitre cut at two corners
and joined with 2nos. of 150mm long brackets of 15x15mm M.S. square tube. The two vertical door
profiles are to be reinforced with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be
13 fixed to the wall using 65/100mm long M.S. Screws through the frame by using PVC fasteners. A
minimum of 4nos. of screws to be provided for each vertical member & minimum 2nos. for horizontal
member etc. complete as per manufacturers specification and direction of Engineer-in-Charge for
finished item of work
Toilet entrance doors D1
2*(1.00+2.10)
6.20
12.40
5.70
22.80
5.70
5.70
40.90
369.25
Rmt
15102.27
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame made out of M.S.
tubes of 19 gauge thickness and size of 19mm x 19mm for stiles, & 15mm x 15mm for top & bottom
rails. M.S. frame shall have a coat of steel primers of approved make and manufacture. M.S. frame
shall be covered with 5mm thick heat moulded PVC C channel of size 30 x 50mm forming stiles, and
5mm thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail on either side, and 10mm (5mm
x 2) thick, 20mm wide cross PVC sheet as gap insert for top rail & bottom rail. Panelling of 5mm thick
14 PVC sheet to be fitted in the M.S. frame welded / sealed to the stiles & rails with 30mm wide x 5mm
thick PVC sheet beading on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior side of the C Channel
using PVC solvent adhesive. Complete as per direction of Engineer-in-charge, manufacturers
specification & drawing for finished item of work
1.00
2.10
4.20
Toilet doors D2
0.75
2.10
6.30
0.75
2.10
1.58
12.08
12.08
2683.59
sqm
32417.72
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and
15 conveyance of materials to work site & all operational, incidental, labour charges etc complete for
finshined item of work as per SS 911 for Internal walls with primary coat of cement primer one coat
inside plastering area 12mm thick
45.00
640.00
363.66
1048.65
1048.65
184.59
sqm 193569.25
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and
16 conveyance of materials to work site & all operational, incidental, labour charges etc complete for
finshined item of work as per SS 911 for external walls with primary coat of cement primer one coat
285.00
17
6.60
224.40
17
4.80
163.20
2.80
22.40
695.00
695.00 217.70 sqm 151304.28
Flooring with ceramic tiles,(Non-skid red or white full body Ceramic floor tiles of size 300 x 300 mm
and thickness between 7-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to
15) of any colour and finish in all shades and designs ) set over base coat of cement mortar(1:8),
12mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
17 consistency spread @3.3. kgs per sqm & jointed neatly with white cement paste of full depth mixed
with pigment of matching shade,including cost of all materials like cement,sand water and tiles
etc.,complete, including seigniorage charges, etc., complete for finished item of work,but including
toilet rooms
the cost of conveyance of all materials
staircase room
0.23)/2
mid landing slab
(5.00-0.23-
2.270
4.85
22.02
3.53
4.85
17.12
3.53
1.50
5.30
44.43
44.43
950.99
sqm
Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles )glazed red or
white full body ceramic wall tiles of size 200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs for skirting ) 7.30 mm thick length equal to flooring stones, set over base coat of
CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per
18
sqm and jointed with white cement paste mixed with pigment of matching shade to full depth,
including cost of all materials like tiles, cement, sand and water etc., complete including seigniorage
charges, etc., complete for finished item of work, but including the cost of conveyance of all materials
for skirting
staircase steps
12
1.73
0.45
18.68
3.78
0.20
3.02
midlanding 3.53+2*1.50
6.53
0.20
1.31
42252.40
14.24
1.50
42.72
WC gents 1.20+1.07
2.27
1.50
6.81
WC ladies 1.20+1.07
2.27
1.50
6.81
urinal walls
0.75
1.65
4.95
deduct doors
1.00
1.50
-3.00
0.75
1.50
-4.50
76.80
3.20
80.00
938.56
sqm
75087.43
1361.11 each
8
Flooring with vitrified tiles of 1st quality, ( ordinary soluble salt porcelain vitrified tiles screen printed
and polished of size 400 x 400 mm and thickness between 8-9 mm 1st quality conforming to
IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs) set
over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab,
20 including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste to full depth mixed with pigment of matching shade, including cost of all
materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc.,
complete for finished item of work, but including the cost of conveyance of all materials.
10888.86
doors
14.06
2.40
33.74
4.77
5.83
55.62
Estlablishment section
2(3.53+5.83)
chairperson room
3.53
5.83
20.58
4.77
4.85
23.13
9.77
13.54
132.29
2(4.77+4.85)
council
hall 5.08+4.48+4.210.23=13.54,2*5.00-0.23=9.77.
2(9.77+13.54)=
265.36
265.36
1078.65
sqm 286229.66
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to
flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with
21 pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges, etc., complete for finished item of work, but
including the cost of conveyance of all materials
inside corridor 2*5.00+3.76+0.30
14.06
0.20
5.62
21.20
0.20
8.48
Estlablishment section
chairperson room
2(3.53+5.83)
18.72
0.20
3.74
19.24
0.20
3.85
2(4.77+4.85)
council
hall 5.08+4.48+4.210.23=13.54,2*5.00-0.23=9.77.
2(9.77+13.54)=
46.62
0.20
9.32
2.00
0.20
-0.80
deduct doors D
1.20
0.20
-1.92
0.18
0.20
0.29
28.59
28.59
1087.16
sqm
31081.95
Providing and fixing of top hung Ventilators made of pre-painted steel (Base steel as per IS 513 of
0.80 mm thick galvanized as per IS 277 with Zinc of 120 GSM), finish painted with a polyester paint
of 60-65 microns thick and section for outer frame of 80 x 45 mm, centre mullion of 80 x 60 mm,
section for shutter of 52 x 25 mm x 0.6 mm thick, outer frame and mullions to have rebate for glazed
shutter with a provision for guard bars/grills and the sections cut to length metre joined with corner
22 bracket, centre mullion fixed with mullion cap, 1 No. of High grade nylon latch handle, window
stopper, 2 nos. of with MS Powder coated /SS ball bearing butt Hinges provided per shutter and
windows fitted with 4 mm thick plain float glass with rubber gaskets including fixing the frames in
concrete/masonry wall by means of self expanding screws, Including 10 mm Square guard bars with
6 (152.4mm) pitch etc., complete for finished item of work
ventilators 1.80x0.60m
17
1.80
0.60
18.36
18.36
0.80
0.60
6936.20
sqm 127348.55
4745.70
sqm
1.92
1.92
Supplying and fixing of false ceiling using Plaster of paris Boards 12 mm thick with standard GI
23 ceiling angles, sections perimeter channels including cost and conveyance of all materials and labour
charges etc complete
inside corridor 2*5.00+3.76+0.30
14.06
2.40
33.74
4.77
5.83
55.62
Estlablishment section
2(3.53+5.83)
3.53
5.83
20.58
4.77
4.85
23.13
9.77
13.54
132.29
14.06
0.30
8.44
21.20
0.30
12.72
Estlablishment section
chairperson room
2(3.53+5.83)
18.72
0.30
5.62
19.24
0.30
5.77
2(4.77+4.85)
9111.74
46.62
0.30
13.99
311.89
311.89
501.04
sqm 156270.04
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of
water proof compound per bag of cement laid over roof when it is green including cost of all
materials, seigniorage charges, excluding conveyance charges of materials and including all
24
operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work
slab area
338.52
-16.54
321.99
321.99
441.79
sqm 142250.76
3751085.35
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Superintending Engineer
Executive Engineer
Description of item
No No
Qty
Unit
Total
0.23
0.375
3.05
1.05
1.10
Rate
11371.89
cum
12509.07
11538.22
cum
692.29
1480.45
sqm
42636.84
10946.10
cum
18670.55
Lintels
over doors
staircase room door
1.40
0.23
0.20
0.06
0.06
4.66
6.18
28.80
28.80
Beams
E1-F1,E2-F2
3.46
0.23
0.45
0.72
E1-E2,F1-F2 5.08-.30=4.78
4.78
0.23
0.45
0.99
1.71
1.71
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel
(MS) steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works ,
including labour charges for straightening, cutting, bending to required sizes and shapes, placing in
position with cover blocks of approved materials and size and tying and lap-splicing with binding wire
of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including
cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all incidental, operational,
labour charges such as cutting, bending, placing in position, tying including sales and other taxes on
all materials etc., complete for finished item of work in all floors.
columns
1.10
cum
120
kg/cum
132.00
Lintels
0.06
cum
100
kg/cum
6.00
3.60
cum
80
kg/cum
288.00
Beams
1.71
cum
120
kg/cum
204.68
630.68
631.00
48.74
kg
30755.47
5077.43
cum
55852.53
3.46
0.23
2.75
4.38
E1-E2,F1-F2 5.08-.30=4.78
4.78
0.23
2.75
6.05
doors D1
1.00
0.23
2.10
-0.48
1.50
0.23
1.20
-0.41
deductions
lintels
parapet wall 2(4.66+6.18)
-0.06
1
21.68
0.115
0.30
0.75
10.21
0.79
11.00
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing with
aluminium anodised sections of Jindal sections and outer frame top horizontals & both verticals of
2408 of size 101.6 x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of 4504 of size 44.45
mm x 47.62 mm x 3.18 and Middle lock rail of 4621 of size 49.91 x 44.45 x 3 mm with tintedbronze/green glass 5 mm thick(middle to top),MDF Board-exterior both sides laminaed 12mm
thick(middle to bottom) fixed including supply and fixing aluminium handles of 150 mm for each
shutter and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts and
including labour charges for fixing the frame in position, fixing shutter to frame etc. completed for
finished item of work
doors D1 1.00x2.10m
each
12247.08
186.64
sqm
5375.22
153.88
sqm
12310.65
slab area
28.80
6
12247.08
18.60
3.05
56.73
21.68
0.75
16.26
72.99
80.00
16.76
3.05
51.12
deduct door
1.00
2.10
-4.20
199.91
231.90
sqm
46358.16
1.80
456.73
sqm
822.12
supply and fixing of pre cast RCC jollys of approved design 50mm
thick
RCC jolly in staircase room
199.91
1.50
1.20
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and
conveyance of materials to work site & all operational, incidental, labour charges etc complete for
finshined item of work as per SS 911 for Internal walls with primary coat of cement primer one coat
7.01
199.91
28.80
235.72
235.72
10
sqm
45579.41
Painting to new walls with two coats plastic emulsion paint of approved brand shade after thoroughly
brushing surface to remove dirt & remains of loose powerderd materials including cost and
conveyance of materials to work site & all operational, incidental, labour charges etc complete for
finshined item of work as per SS 911 for external walls with primary coat of cement primer one coat
72.99
72.99
11
193.36
224.17
sqm
16361.80
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of
water proof compound per bag of cement laid over roof when it is green including cost of all
materials, seigniorage charges, excluding conveyance charges of materials and including all
operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work
slab area
28.80
464.95
sqm
13390.53
313561.74
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Superintending Engineer
Executive Engineer
Description of item
No
No
IV
water supply
Providing & Placing on Terrace (at all floor levels) polyethylene water
storage tank with Double layer approved brand & manufacture with cover
and suitable locking arrangement & making necessary holes for inlet &
outlets and over flow pipes but without fittings & base support for tanks
water storage tank
5000
25mm dia OD
Qty
Rate
Unit
5000
6.82
litre
323.80
Rmt
221.55
Rmt
178.38
Rmt
38.00
38.00
60.00
60.00
98.00
98.00
2
20mm dia OD
Gents toilets GF+FF+2nd floor
5.00
15.00
5.00
15.00
commissioner toilet FF
5.00
5.00
35.00
35.00
16mm dia OD
Gents toilets GF+FF+2nd floor
5.00
15.00
5.00
15.00
commissioner toilet FF
5.00
5.00
35.00
35.00
incoming
988.45
each
1036.17
each
705.55
each
540.81
each
24
462.41
each
8470.00
each
S & F Gunmetal (GM) Ball valve with SS Ball and SS Spindle as per IS Class - I, Indian make heavy type - 25 mm NB Size
incoming
out going
commissioner toilet FF
add extra
1
7
S & F Gunmetal (GM) Ball valve with SS Ball and SS Spindle as per IS Class - I, Indian make heavy type - 20 mm NB Size
for each floor gents and ladies
2
3
toilet
commissioner toilet FF
add extra
6
1
1
8
S & F Gunmetal (GM) Ball valve with SS Ball and SS Spindle as per IS Class - I, Indian make heavy type - 15 mm NB Size
for each floor gents urinals,
12
commissioner toilet FF
add extra
1
24
S&F 12.7 mm N.P bib tap Indian make heavy dutys Seiko/ Senior/ Nice or
equivalent
for each floor gents and ladies
toilet
12
commissioner toilet FF
add extra
Supply and Transportation of 1.0HP Single phase ISI Mono block CI body
motor pumpset (25x25mm). Makes: Kirloskar / Crompton / Texmo / CRI /
KSB / Havells Hi-flow V1
1
Sanitory arrengements
Supplying & Fixing Orissa Pan white glazed W.C 1st quality ISI marked
conforming to IS:2556-Part-3-1981 with "P" or "S" trap Hindware/
Parryware/ Neycer - ISI Mark: 630 mm x 450 mm
Gents toilets 3 floors
1
13
1891.69
each
Supplying & Fixing low down porcelain flushing tank 10 Lit Capacity
Hindustan Sanitary ware/ parry/ Neycer with internal components
Gents toilets 3 floors
1
13
10.00
10.00
10.00
10.00
10.00
10.00
30.00
30.00
1056.62
each
313.58
Rmt
94.30
each
10.00
70.00
add extra
2
23
each
Supplying of 110 mm dia 3 M single Socket PVC/SWR pipe - 6 Kg/sq.cm Prince/Sudhakar/Kisan/Supreme or any ISI Brand.
add extra
2464.31
Supplying & Fixing white glazed flat back Bowl urinals of size 440 mm x
265 mm x 315 mm with internal flushing rim fixed with screws complete
Indian make (HSW/Parry/Neycer) conforming to IS:2556-1995
10
e
each
Supplying & Fixing Indian make Flat Back Wash Hand Basin
(HSW/Parryware/ Neycer) 1st quality conforming to IS:2556-Part-4:1972
with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting
with parallel pipe thread conforming to IS:2963-1979 and fitted with 15
mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make
400 grams Seiko/ Senior/ Nice/ Esso or equivalent complete with standard
CI brackets including wooden block: 550 x 400 mm - Double C.P. Pillar
cock
13
d
2879.00
Supply of 110 mm dia - Single Tee with Door - UPVC/SWR Pipe fittings
(Prince/Sudhakar/Kisan/Supreme or any ISI Brand)
Gents toilets 3 floors
add extra
1
8
each
64.76
each
79.53
Rmt
4345.77
each
add extra
2
18
Labour charges for laying, fixing and commissioning the PVC pipes
including couplers/ bends/ tees etc any diameter including fixing
necessary fittings like bends, plugs, couplers, junctions, tees, etc with
solvent jointing as per standard practice
Gents toilets 3 floors
10.00
10.00
10.00
10.00
10.00
10.00
30.00
30.00
add extra
10.00
70.00
295.40
1
8
each
Supply of 110 mm dia - double Tee with Door - UPVC/SWR Pipe fittings
(Prince/Sudhakar/Kisan/Supreme or any ISI Brand)
add extra
147.70
2
5
electrification
Ground floor
Supply and fixing of 25 mm dia 2.00 mm thick PVC pipe concealed in roof
slab with all required accessories including masonary work all labour
chages
length
24.00
144.00
width
14.00
126.00
3.70
3.70
5.00
5.00
24.00
72.00
350.70
add extra
19.30
370.00
18
2.00
36.00
18
2.00
36.00
72
478.17
each
453.07
each
59.33
Rmt
18.27
Rmt
72
add extra
3
75
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated
Flexible copper cable in existing pipe with 6A modular siwtch control and
3/2 pin sockets fixing on board including all labour charges
each room 2 nosx18 boards
36
36
add extra
4
40
Supply and run of 2 of 36/0.3 mm. (1.5. sq.mm) Fire retardant PVC
insulated Flexible copper cable in existing pipe for mains including all
labour charges etc.
18 boardseach floor average
length and width 25m
18
25.00
450.00
25.00
25.00
add extra
25.00
500.00
Rmt
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated
Flexible copper cable in existing pipe with 6A siwtch, ceiling rose and 3
mm thick hyla sheet covering to switch control box including all labour
charges etc,., complet for light, bell , fan and exhaust fan points in non residential building- for 6 points
each room 4 nosx18 boards
70.72
3.00
75.00
Rmt
add extra
63.92
supply and run of 1 of 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC
insulated Flexible copper cable in existing pipe for earth continuity
including all labour charges etc.
18 boardseach floor average
length and width 25m
add extra
18
25.00
450.00
15.00
465.00
100.00
119.09
Rmt
2445.00
each
2618.26
each
8381.00
each
1600.00
each
198.00
each
2722.00
each
100.00
S&F of 63 Amps 415 V TPN swich disconnector fuse unit cubical type
without fuses of makes Standard/Crystal/Havells/HPL
for Ground floor
add extra
4
1
5
add extra
4
1
5
Supply and Transportation of 18W Down lighter with system lumens of 1580lm,
suitable for Recessed / Surface mounting made of diecast alluminium body with
powder coating, acrylic diffuser with Driver, operating voltage range of 150 to 265
m Volts AC, P.F > 0.9, Surge protection: 2KV,THD<15%, with high power LED's
having efficacy of > 120 lumins/watt,CCT: 3000K - 5700K, minimum CRI>70, .etc.,
complete a) LUMINAIRE MAKE : Phillips / OSRAM / GE / Crompton
b) LED MAKE : PHILIPS LUMILEDS / CREE / NICHIA / OSR
ground floor
add extra
8
2
10
Supply of 1 x 36/40W Box type tube light luminaire powder coated CRCA sheet
steel housing with Electronic Ballast Chokes and all standard accessoriesof
makes Wipro / G.E. / Phillips / Crompton / Bajaj.
Toilets
staircase room
portico
GF parking
10
10
add extra
2
20
1218.00
each
396.00
each
Supply of Bulk head fitting with cast aluminium enamel painted body with water
tight, clear glass with wire guard hinged with lock and key arrangements etc.,
complete.Makes: Bajaj / Crompton / Surya
out side
Supply of 6-32A 10KA DP MCB, C/D Curve ISI Mark. Makes: Legrand / Schneider
for 1.00HP motor
ii
1st floor
Supply and fixing of 25 mm dia 2.00 mm thick PVC pipe concealed in roof
slab with all required accessories including masonary work all labour
chages
length
24.00
144.00
width
14.00
126.00
3.70
3.70
5.00
5.00
24.00
72.00
595.00
each
63.92
Rmt
70.72
Rmt
478.17
each
453.07
each
350.70
add extra
19.30
370.00
18
2.00
36.00
18
2.00
36.00
add extra
3.00
75.00
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated
Flexible copper cable in existing pipe with 6A siwtch, ceiling rose and 3
mm thick hyla sheet covering to switch control box including all labour
charges etc,., complet for light, bell , fan and exhaust fan points in non residential building- for 6 points
each room 4 nosx18 boards
72
72
add extra
3
75
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated
Flexible copper cable in existing pipe with 6A modular siwtch control and
3/2 pin sockets fixing on board including all labour charges
each room 2 nosx18 boards
36
36
add extra
4
40
Supply and run of 2 of 36/0.3 mm. (1.5. sq.mm) Fire retardant PVC
insulated Flexible copper cable in existing pipe for mains including all
labour charges etc.
18 boardseach floor average
length and width 25m
18
25.00
450.00
for AC plugs
3.00
3.00
add extra
27.00
480.00
59.33
Rmt
supply and run of 1 of 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC
insulated Flexible copper cable in existing pipe for earth continuity
including all labour charges etc.
18 boardseach floor average
length and width 25m
add extra
18
25.00
450.00
15.00
465.00
18.27
Rmt
2445.00
each
1600.00
each
198.00
each
1300.00
each
2722.00
each
1218.00
each
S&F of 63 Amps 415 V TPN swich disconnector fuse unit cubical type
without fuses of makes Standard/Crystal/Havells/HPL
for 1sy floor
15
add extra
15
1
16
15
add extra
15
1
16
1
1
Supply and Transportation of 18W Down lighter with system lumens of 1580lm,
suitable for Recessed / Surface mounting made of diecast alluminium body with
powder coating, acrylic diffuser with Driver, operating voltage range of 150 to 265
Volts AC, P.F > 0.9, Surge protection: 2KV,THD<15%, with high power LED's
having efficacy of > 120 lumins/watt,CCT: 3000K - 5700K, minimum CRI>70, .etc.,
complete a) LUMINAIRE MAKE : Phillips / OSRAM / GE / Crompton
b) LED MAKE : PHILIPS LUMILEDS / CREE / NICHIA / OSR
first floor
36
add extra
36
4
40
Supply of 1 x 36/40W Box type tube light luminaire powder coated CRCA sheet
steel housing with Electronic Ballast Chokes and all standard accessoriesof
makes Wipro / G.E. / Phillips / Crompton / Bajaj.
Toilets
staircase room
add extra
3
9
Supply of Bulk head fitting with cast aluminium enamel painted body with water
m tight, clear glass with wire guard hinged with lock and key arrangements etc.,
complete.Makes: Bajaj / Crompton / Surya
out side for 1st floor
396.00
each
63.92
Rmt
70.72
Rmt
478.17
each
Supply and fixing of 25 mm dia 2.00 mm thick PVC pipe concealed in roof
slab with all required accessories including masonary work all labour
chages
length
24.00
144.00
width
14.00
126.00
3.70
3.70
5.00
5.00
24.00
72.00
5.00
5.00
5.00
5.00
360.70
add extra
19.30
380.00
18
2.00
36.00
18
2.00
36.00
2.00
2.00
add extra
3.00
77.00
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated
Flexible copper cable in existing pipe with 6A siwtch, ceiling rose and 3
mm thick hyla sheet covering to switch control box including all labour
charges etc,., complet for light, bell , fan and exhaust fan points in non residential buildingeach room 4 nosx18 boards
72
72
add extra
2
80
Wiring with 2 runs 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC insulated
Flexible copper cable in existing pipe with 6A modular siwtch control and
3/2 pin sockets fixing on board including all labour charges
each room 2 nosx18 boards
36
36
add extra
4
42
453.07
each
59.33
Rmt
525.00
18.27
Rmt
2445.00
each
1600.00
each
198.00
each
1300.00
each
Supply and run of 2 of 36/0.3 mm. (1.5. sq.mm) Fire retardant PVC
insulated Flexible copper cable in existing pipe for mains including all
labour charges etc.
18 boardseach floor average
length and width 25m
18
25.00
450.00
for AC plugs
3.00
21.00
10.00
10.00
add extra
29.00
510.00
supply and run of 1 of 14/0.3 mm. (1.0. sq.mm) Fire retardant PVC
insulated Flexible copper cable in existing pipe for earth continuity
including all labour charges etc.
18 boardseach floor average
length and width 25m
18
25.00
450.00
25.00
25.00
add extra
S&F of 63 Amps 415 V TPN swich disconnector fuse unit cubical type
without fuses of makes Standard/Crystal/Havells/HPL
for 3 floors
50.00
20
add extra
20
1
21
20
add extra
20
1
21
council hall
6
7
Supply and Transportation of 18W Down lighter with system lumens of 1580lm,
suitable for Recessed / Surface mounting made of diecast alluminium body with
powder coating, acrylic diffuser with Driver, operating voltage range of 150 to 265
Volts AC, P.F > 0.9, Surge protection: 2KV,THD<15%, with high power LED's
having efficacy of > 120 lumins/watt,CCT: 3000K - 5700K, minimum CRI>70, .etc.,
complete a) LUMINAIRE MAKE : Phillips / OSRAM / GE / Crompton
b) LED MAKE : PHILIPS LUMILEDS / CREE / NICHIA / OSR
2nd floor
42
42
add extra
3
45
2722.00
each
1218.00
each
396.00
each
Supply of 1 x 36/40W Box type tube light luminaire powder coated CRCA sheet
steel housing with Electronic Ballast Chokes and all standard accessoriesof
makes Wipro / G.E. / Phillips / Crompton / Bajaj.
Toilets
staircase room
add extra
3
11
Supply of Bulk head fitting with cast aluminium enamel painted body with water
m tight, clear glass with wire guard hinged with lock and key arrangements etc.,
complete.Makes: Bajaj / Crompton / Surya
out side
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Superintending Engineer
Executive Engineer
ce building for
Jangareddygudem Nagar
Panchayat
cum abstract of estimate
Total
34084.50
31732.67
7754.22
6243.14
988.45
7253.18
5644.39
12979.38
11097.91
8470.00
24591.97
37427.05
32036.02
10566.20
21950.42
2168.91
1181.60
2363.19
1165.69
5567.14
21728.87
23650.40
5304.00
35862.50
18122.67
29666.00
8497.41
11909.20
2445.00
7854.78
8381.00
8000.00
990.00
27220.00
24360.00
2376.00
595.00
23650.40
5304.00
35862.50
18122.67
28479.36
8497.41
2445.00
25600.00
3168.00
1300.00
108880.00
10962.00
2376.00
24289.60
5445.44
38253.33
19028.80
30259.32
9593.85
2445.00
33600.00
4158.00
9100.00
122490.00
13398.00
1584.00
1090521.54
Executive Engineer
Description of item
No
No
Qty
Rate
Unit
190.00
290.10
Rmt
121.57
each
335.16
each
64.76
each
158.81
cum
V Misslanious
1 Rain water pipes
a Supply, delivery and fixing of 110mm dia single socket PVC pipes 4
kg/sqcm prince/Sudhakar or any ISI brand for rain water pipes with
clamps
Rain water pipes 4 places,front
and rear
13.50
108.00
along building
24.00
48.00
15.00
30.00
add extra
4.00
c
supply of 110 mm dia - Double Tee with Door - UPVC/SWR Pipe fittings
Tees
0.786
1.00
1.00
2.50
3.93
0.786
1.40
1.40
0.50
1.54
5.47
5.47
0.786
1.40
1.40
0.10
0.31
deduct pit
0.786
1.00
1.00
0.10
-0.16
0.15
0.15
1288.88
cum
0.786
1.40
1.40
0.10
0.31
deduct pit
0.786
1.00
1.00
0.10
-0.16
0.15
0.15
4210.79
cum
4975.43
cum
0.27
5808.50
cum
27.00
48.74
kg
1286.80
cum
0.786
1.30
1.30
0.50
1.33
deduct pit
0.786
1.00
1.00
0.50
-0.79
0.54
0.54
0.786
1.30
1.30
0.10
0.27
0.27
100
0.786
1.00
1.00
0.60
0.94
0.94
0.786
1.00
1.00
0.60
0.94
0.94
1866.24
cum
0.94
0.94
1940.09
cum
1288.88
cum
0.786
1.00
1.00
1.00
1.57
1.57
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Superintending Engineer
Executive Engineer
e building for
Jangareddygudem Nagar
Panchayat
um abstract of estimate
Total
55118.42
486.27
2010.99
518.08
868.67
193.33
631.62
2686.73
1568.30
1316.00
1209.60
1754.27
1823.69
2023.54
72209.51
Executive Engineer
cost in Rs
5478169.75
3706683.03
3751085.35
313561.74
1090521.54
72209.51
14412230.91
VAT 5%
720612.00
Labour cess 1%
144122.00
432367.00
10
144122.00
11
49700.00
12
100000.00
13
144122.00
13
302724.00
Total
16449999.91
Grand Total
164.50 Lakhs
Assistant Engineer
Superintending Engineer
Executive Engineer
first floor
Brick masanary with cm 1:6 is proposed with 0.23m thick walls(0.115m thick walls in toilets). columns
0.30x0.45m, 0.30x0.45m, , beams of size 0.23x0.45m(rib),,0.30x0.45m(rib)lintel beams 0.23x0.20m are
proposed with VRCCM 25 design mix. Roof slab 0.15m thick,stair case alab 0.20m thick, proposed with
VRCCM25 design mix.. Plastering with cm 1:3 12mm thick is proposed to ceiling. Plastering cm 1:5 12 mm thick
is proposed to building.Anodised Aluminium doors of size 1.20 x2.10m(door D) are proposed in rooms.
Anodised Aluminium windows glazed of size 1.80x1.50m are proposed in rooms. ventilators glazed of
size1.80x0.60n (over windows), 0.80x0.60m(toilets)are proposed. PVC doors of size 1.00x2.10m(main entrance
doors toilets) 0.75x2.10m D1(toilets internal doors) are proposed. Synthic enamel paint two coats is proposed to
iron grill of windows with primary coat.MS safety ornamental grill is proposed to windows. Plastic emultion paint
two coats is proposed to building.Ceramic tiles flooring and skirting is proposed to toilets.Vertified tiles flooring
and skirting is proposed to all office rooms.RCM facia 5cm thick in CM (1:3) for drop walls is proposed for
windows and ventilators etc.. The first floor is proposed for engineering section,town planning section,health
section,commissioner chamber with anti room,visitors room,toilets,revenew section,entrance hall and toilets for
gents and ladies
2nd floor
Brick masanary with cm 1:6 is proposed with 0.23m thick walls(0.115m thick walls in toilets). columns
0.230x0.375m, 0.30x0.45m, , beams of size 0.23x0.45m(rib),,0.30x0.45m(rib)lintel beams 0.23x0.20m are
proposed with VRCCM 25 design mix. Roof slab 0.14m thick,stair case alab 0.15m thick, proposed with
VRCCM25 design mix.. Plastering with cm 1:3 12mm thick is proposed to ceiling. Plastering cm 1:5 12 mm thick
is proposed to building.Anodised Aluminium doors of size 2.00x2.10m (main door to council hall) ,1.20
x2.10m(door D) are proposed in rooms. Anodised Aluminium windows glazed of size 1.80x1.50m are proposed
in rooms. ventilators glazed of size1.80x0.60n (over windows), 0.80x0.60m(toilets)are proposed. PVC doors of
size 1.00x2.10m(main entrance doors toilets) 0.75x2.10m D1(toilets internal doors) are proposed. Synthic
enamel paint two coats is proposed to iron grill of windows with primary coat.MS safety ornamental grill is
proposed to windows. Plastic emultion paint two coats is proposed to building.Ceramic tiles flooring and skirting
is proposed to toilets.Vertified tiles flooring and skirting is proposed to all office rooms including council hall and
chairman chamber.RCM facia 5cm thick in CM (1:3) for drop walls is proposed for windows and ventilators etc..
The 2nd floor is proposed for council hall,chairman chamber,record room,computor section and estlablishment
section, and toilets for gents and ladies. Imprivious coat 2omm thick with CM 1:3 is proposed over roof slab
3rd floor (staircase head room)
Brick masanary with cm 1:6 is proposed with 0.23m thick walls. columns 0.23x0.375m, beams of size
0.23x0.45m(rib),lintel beams 0.23x0.20m are proposed with VRCCM 25 design mix. Roof slab 0.125m thick,
proposed with VRCCM25 design mix.. Plastering with cm 1:3 12mm thick is proposed to ceiling. Plastering cm
1:5 12 mm thick is proposed to walls.Anodised Aluminium doors of size 1.20 x2.10m(door D) are proposed in
head room. Plastic emultion paint two coats is proposed to building.The 3rd floor is proposed for stair case head
room. Imprivious coat 2omm thick with CM 1:3 is proposed over roof slab
Sanitory,water supply and electrification
5000 lts capacity polyethylene water storage tank is proposed over 2nd floor roof slab.KITEC PolyethyeneAluminium polyethene (PE-A-PE) of size 25,20,16 mm are proposed for incoming,out going and internal water
supply lines with necessary GM valves,bibcocks and other fittings.1.00 HP motor with pump is proposed for
pumping water from ground level tank to storage tank in 2nd floor.sanitary fittings like Orissa pans with flushing
tanks,wash basins,gents urinals,outlet piping system with specials,inspection chambers are proposed.electrical
wiring with nessary light,fan,plug,AC plug points are proposed with wiring.ceiling fans with regulators ate
proposed. distrubution boards,earthing arrengements,service wire are proposed in estimate.power saving light
fittings are proposed to building
Mislanious
110 mm dia PVC rain water pipes are proposed to discarge rain water from roof and these are proposed to
connect rain water recharge pits 2 nos of dia 1.00m and depth 3.00m
Assistant Engineer
Jangareddygudem Nagar
Panchayat
Superintending Engineer
Executive Engineer
Seigniorage statement
Sl No
I
1
2
3
4
5
6
Item No
236.21
CC 1:4:8
49.82
44.84
22.42
2.44
2.19
1.10
16.32
14.69
7.34
36.03
32.43
16.21
7a
64.00
51.20
25.60
4.30
3.44
1.72
18.82
15.06
7.53
11.26
9.00
4.50
Lintels
0.89
0.71
0.36
346.73
41.61
20.80
7g
19.97
3.20
1.60
7h
Beams
22.34
17.87
8.93
7i
4.40
0.35
0.18
BM (1:6)
55.72
11.14
28529.82
10
25.23
0.63
0.76
14
689.57
8.27
15
190.00
2.85
20
0.00
0.00
22
44.43
0.53
23
80.00
0.96
25
120.87
1.45
26
22.02
2.69
9
7d
7e
11
7f
15
16
17
18
19
20
21
22
23
bricks 1000
nos
236.21
7c
14
sand cum
Filling in foundation
13
Metal cum
7b
12
Qty cum/sqm
Ground floor : -
10
24
27
5.44
0.065
Septic tank
25
Impervious coat
0.00
0.00
1.90
1.90
31c
CC 1:4:8
1.90
1.71
0.86
31d
BM (1:5)
9.38
31e
0.24
31f
Plastering in CM (1:3) 20 mm
thick
31g
30
26
31 b
27
28
29
30
31
1.88
4802.56
0.21
0.11
45.60
0.96
1.90
1.71
0.86
32b
1.58
1.58
33
32c
CC 1:4:8
1.58
1.42
0.71
34
32d
BM (1:5)
6.19
1.24
3168.26
32e
Plastering in CM (1:3) 20 mm
thick
0.00
0.00
32f
1.30
1.17
0.58
35
36
II
37
38
39
40
41
42
43
44
45
46
47
48
First floor : 1a
8.15
6.52
3.26
1b
Lintels
2.92
2.34
1.17
1c
321.99
38.64
19.32
1d
19.97
3.20
1.60
1e
Beams
18.49
14.79
7.40
1f
35.20
2.82
1.41
1g
23.18
1.39
0.70
BM (1:6)
106.00
21.20
54274.43
136.78
3.42
4.10
350.71
5.26
370.00
5.55
15
46.23
0.55
49
50
16
80.00
0.96
18
257.09
31.36
19
39.74
0.477
51
III
2nd floor : -
52
1a
8.15
6.52
3.26
53
1b
Lintels
2.74
2.19
1.10
54
1c
321.99
38.64
19.32
55
1d
19.97
3.20
1.60
56
1e
Beams
17.22
13.78
6.89
1f
37.40
2.99
1.50
58
1g
14.52
0.87
0.44
59
BM (1:6)
81.00
16.20
41473.35
144.75
3.62
4.34
61
364.70
5.47
62
330.00
4.95
15
44.43
0.53
16
80.00
0.96
18
265.36
32.37
19
28.59
0.343
22
Impervious coat
321.99
6.76
57
60
63
64
65
66
67
IV
68
1a
1.05
0.84
0.42
69
1b
Lintels
0.06
0.05
0.03
70
1c
28.80
2.88
1.44
71
1d
Beams
1.71
1.36
0.68
72
BM (1:6)
11.00
2.20
5632.08
73
28.80
0.43
74
199.91
3.00
75
Impervious coat
28.80
0.60
Misslanious : 2
76
2b
0.15
0.15
77
2c
CC 1:4:8
0.15
0.14
0.07
78
2d
0.54
0.49
0.24
79
2e
0.27
0.24
0.12
2g
0.94
0.94
2h
0.94
0.94
2I
0.94
0.94
2h
1.57
1.57
389.52
622.87
137881.50
80
81
82
83
Sub Total
Metal 50.00/cum
50.00
389.52
19476.23248
sand 40.00/cum
40.00
622.87
24914.68447
38.50
137881.50 5308.437931
49699.35
Grand Total
Assistant Engineer
Superintending Engineer
say
49700.00
Executive Engineer
cost in Rs
5478169.75
3706683.03
3751085.35
313561.74
1090521.54
Mislanius like rain water pipes, rain water recharge pits etc
7
8
9
10
11
12
13
13
Sub total
VAT 5%
Labour cess 1%
Scrutiny and test check charges 3%
User Charges 1%
Seigniorage charges ( as per statement enclosed)
charges payble to electrical departmrnt
Provision towards Third Party Quality Control 1%
contingences and unforseen items 3%
Total
Grand Total
Assistant Engineer
72209.51
14412230.91
720612.00
144122.00
432367.00
144122.00
49700.00
100000.00
144122.00
302724.00
16449999.91
16449999.91
164.50
Lakhs
Executive Engineer