Security + Computer System Security

DCOM 258 E31


Name: Shaamim Ahmed
Chapter 15: Redundancy & Disaster Recovery
Part # 1

Define the following Key Terms (12 points)

1. Single Point of Failure


An element, object, or part of a system that, if it fails, will cause
the whole system to fail.
2. Redundant Power Supply
An enclosure that contains two (or more) complete power
supplies
3. Uninterruptable power supply (UPS)
An enclosure that contains two (or more) complete power
supplies
4. Backup Generator
An enclosure that contains two (or more) complete power
supplies
5. Standby Generator
Standby generator
Systems that turn on automatically
within seconds of a power outage.
6. Redundant ISP
Redundant ISP means secondary connections to another ISP; for
example, a backup T-1 line.
7. Cluster
Cluster means
two or more servers that work with each other.
8. Failover Cluster
Failover clusters, otherwise known as high-availability clusters,
they are designed so that a secondary server can take over in
the case that the primary one fails, with limited or no downtime.
9. Load Balancing Cluster
When multiple computers are connected together in an attempt
to share resources such as CPU, RAM, and hard disks
10.
Full Backup
When all the contents of a folder are backed up
11.
Incremental Backup
When all the contents of a folder are backed up
12.
Differential Backup
Backs up only the contents of a folder that have changed since
the last full backup

Security + Computer System Security


DCOM 258 E31
13.

14.

15.

16.

17.

Disaster Recovery Plans


Disaster recovery plans should include information regarding
redundancy, such as sites and backup, but should not include
information that deals with the day-to-day operations of an
organization, such as updating computers, patch management,
monitoring and audits, and so on. It is important to include only
what is necessary in a disaster recovery plan. Too much
information can make it difficult to use when a disaster does
strike.
Contact Information
Disaster recovery plans should include information regarding
redundancy, such as sites and backup, but should not include
information that deals with the day-to-day operations of an
organization, such as updating computers, patch management,
monitoring and audits, and so on. It is important to include only
what is necessary in a disaster recovery plan. Too much
information can make it difficult to use when a disaster does
strike.
Impact Determination
Disaster recovery plans should include information regarding
redundancy, such as sites and backup, but should not include
information that deals with the day-to-day operations of an
organization, such as updating computers, patch management,
monitoring and audits, and so on. It is important to include only
what is necessary in a disaster recovery plan. Too much
information can make it difficult to use when a disaster does
strike.
Recovery Plan
Regardless of how much you planned out redundancy and fault
tolerance, when disaster strikes, it can be devastating. There are
three things that you should be concerned with as a network
security administrator when it comes to disastersyour data,
your server room, and the site in general. You need to have a
powerful backup plan for your data and a comprehensive
disaster recovery plan as well.
Business Continuity Plan
Business continuity plan: A BCP defines how the business will
continue to operate if a disaster occurs; this plan is often carried

Security + Computer System Security


DCOM 258 E31

18.

19.

20.

out by a team of individuals. BCPs are also referred to as


continuity of operations plans.
Copies of Agreements
Copies of agreements: Copies of any agreements with vendors of
redundant sites, ISPs, building management, and so on should be
stored with the DR plan.
Disaster Recovery Drills
Disaster recovery drill sand exercises: Employees should be
drilled on what to do if a disaster occurs. These exercises should
be written out step-by-step and should conform to safety
standards.
Hierarchical List of Critical Systems
Hierarchical list of critical systems: This is a list of all systems
necessary for business operations: domain controllers, firewalls,
switches, DNS servers, file servers, web servers, and so on. They
should be listed by priority. Systems such as client computers,
test computers, and training systems would be last on the list or
not listed at all.

Part #2: Short Answers (8 points)


1. Discuss the following concepts: (3)
A. Surge:
An unexpected increase in the amount of voltage provided
B. Spike:
A short transient in voltage that can be due to a short circuit,
tripped circuit breaker, power outage, or lightning strike
C.
Sags:
An unexpected decrease in the amount of voltage provided
D. Brownouts:
When the voltage drops to such an extent that it typically causes
the lights to dim and causes computers to shut of
E.
Blackouts:
When a total loss of power for a prolonged period occurs.
F.
Power Supply failure:
When power supplies fail altogether and stop supplying the
computer with power
2. List and discuss 3 types of backup generators.
Portable gas-engine generator

Security + Computer System Security


DCOM 258 E31

Permanently installed generator


Battery-inverter generator

3. List and discuss 5 considerations taken into account for a backup


generator.
Redundant power supply
o An enclosure that contains two (or more) complete power
supplies
Uninterruptible power supply (UPS)
o Takes the functionality of a surge suppressor and combines
that with a battery backup
Backup generators
o Part of an emergency power system used when an outage
of regular electric grid power occurs
o Broken down into three types:
Portable gas-engine generator
Permanently installed generator
Battery-inverter generator
4. Discuss the following concepts: (3)
A.
Hot Site
A near duplicate of the original site of the organization that
can be up and running within minutes (maybe longer).
Computers and phones are installed and ready to go.
B.
Warm Site
Will have computers, phones, and servers but might
require some configuration before users can start working
on them
C.
Cold Site
Has tables, chairs, bathrooms, and possibly some technical
setup, for example, basic phone, data, and electric lines