Documente Academic
Documente Profesional
Documente Cultură
Case Studies
of Wind Park Modeling
UWIG/EnerNex/DOE Workshop
MISO, St. Paul, MN
August 16-17, 2011
Yuriy Kazachkov
Siemens PTI
Page 3
Page 4
Page 5
2011 Siemens
Energy, Inc. All rights reserved.
2011 Siemens Energy, Inc. All rights reserved.
Page 6
The user is responsible for aggregating the actual wind turbines into
equivalent machines. For N lumped machines, the output of the
equivalent machine cannot exceed N times the rated output of the
individual units.
The power factor correction shunt capacitors must be added (if
available) and connected to the terminals of the equivalent machine by
the user.
For example, for the original Vestas V80 machine, the total
compensation available is 12 capacitors of 72 kVAr each. After
compensation, the reactive power flow from the terminal bus to the
system should be in the range of +40/-40 kVAr per machine.
Page 7
Page 8
Page 9
Bus
#
1
5
Bus
Name
INFINITE
WT
Id
1
1
Code
3
2
Status
1
1
Pgen
(MW)
-49.618
50.25
Pmax
(MW)
9999
105
Pmin
(MW)
-9999
0
Qgen
(Mvar)
-0.993
-4.317
Qmax
(Mvar)
9999
34.3
Qmin
(Mvar)
-9999
-51.1
Mbase
(MVA)
100
111.69
XSource
(pu)
0.2
0.8
Wind
machine PF
1
1
The following additional data items, appended to the end of the record, are specified for wind machines:
Power factor:
is used in setting the machines reactive power limits when the wind control mode is 2 or 3
negative value may be specified when the wind control mode is 3, and is interpreted as a leading power factor
(i.e., the wind machine produces active power and absorbs reactive power).
Page 10
New variables of two categories have been added to support the wind models in PSSE:
Variables accessible for users, e.g., model outputs
Variables not accessible for users: primarily for model developers.
Page 11
Page 12
2011 Siemens
Energy, Inc. All rights reserved.
2011 Siemens Energy, Inc. All rights reserved.
Page 13
Module pssewindpy
Provides Python functions to simulate PSSE manufacturer specific wind models:
Acciona AW15/AW30,
Fuhrlaender FL2500,
GE 1.5/2.5/3.6 MW,
Mitsubishi MPS1000A,
Vestas V47/V80/V82/NM72,
Generic WT3.
Provides demo Python functions to simulate these models.
Provides example Python scripts which can be edited/modified to select/specify
desired wind model:
Page 14
Demo Simulation
5 bus demo test work
Add selected WTG, its GSU and other components if required (like fixed shunt,
switched shunt etc.)
Simulate WTG response to bus fault or complex wind input (if applicable)
99971
BUSWTG
99972
COLLECTORBUS
99973
LVBUS
99974
HVBUS
99975
SWINGBUS
G
WTG
34.5 kV
34.5 kV
138 kV
138 kV
Page 15
# PSS(R)E Version
Page 16
Page 17
Page 18
Page 19
2009 Siemens
Energy, Inc. All rights reserved.
2011 Siemens Energy, Inc. All rights reserved.
Page 20
Page 22
Page 23
Page 24
The WT4 generic model includes the special entry for Siemens 2.3 MW wind turine. It
was carefully parameterized jointly by Siemens PTI and Siemens Wind Power. We are
planning to separate the Siemens wind turbine model as a separate standard model.
Per SWPs request we have converted the WT4 generic model to earlier PSSE releases
as a user written model.
This is the example of parameterization of the WT4 generic model to match the
response of the vendor specific model of the Siemens 2.3 MW wind turbine.
Page 25
Page 26
Hot issues
2009 Siemens
Energy, Inc. All rights reserved.
2011 Siemens Energy, Inc. All rights reserved.
Page 27
Page 28
Page 29
Terminal bus voltage angle is uncertain because the reference frame is lost:
no machine flux dynamics for WT3 or PLL for WT4
Many planners use PSSE setups that include the so called Shut down model:
it calculates a number of Network not converged (NNC) events and stops
the simulation if it exceeds the given threshold, e.g. 6 NNCs.
2011 Siemens Energy, Inc. All rights reserved.
Siemens Power Technologies International
The existing model for GE WTs of 1.5 MW , 1.6, 3.6 MW (Type 3) and 2.5 MW
(Type 4): two NNCs were observed when testing the 1.5 MW and 2.5 MW WTs, with
3-phase bolted fault applied to the POI bus 2 one at the fault inception, another at
the instant of fault clearing
The upcoming model for GE WTs of 1.5 MW, 1.6 MW (Type 3) and 2.5 MW, 2.75
MW, 4.0 MW (Type 4) no NNCs with SCR as low as 3.
s1
Page 30
Slide 30
s1
stykayu1, 6/30/2011
Frequency Events
2009 Siemens
Energy, Inc. All rights reserved.
2011 Siemens Energy, Inc. All rights reserved.
Page 31
Page 32
Test System
Page 33
100
MW
Load
1000
MW
load
Bus 19 GT 100 MW
unit
Page 34
Under sudden low frequency conditions, when load demand exceeds the
generation, increase of the machine active power output by means of
converting the rotor kinetic energy into the electrical energy is a sound
response.
For a conventional generation unit, the under-speed protection may shut it
down.
Page 35
Page 36
Page 37
Page 38
Page 39
Similar response
Page 40
Similar response
Full Load
Partial load
Page 41
Page 42
in PSS E
PSS/E Implementation
Irradiance Model
PV Panel Model
Converter Model
Rest of
System
Irradence Model
1.2
Irradence
0.8
0.6
0.4
Irrad (I)
0.2
Pdc (I)
WT4
Converter/
el. control
Voltage
0
1
10
Time
IrradU1
Page 44
PANELU1
PSS/E
IR,
IQ
PVGU1, PVEU1
Irradiance Model
Standard Model that allows user to vary
the amount of solar irradiance.
User enters up to ~10 data points
(time(s), irradiance(W/m2)) as cons
Initializes based on steady state P/Pmax
For each time step, outputs linearized
irradiance level
Irradence Model
1.2
Irradence
0.8
0.6
0.4
0.2
0
1
10
Tim e
Page 45
PV Panel Model
Standard Model for a PV panels I-V
curves
PV panels output varies with
Irradiance, temperature, terminal
voltage (set by MPPT)
User enters maximum Pdc (per
unitized) for different irradiance levels
as cons
For each time step, reads irradiance
level, outputs linearized power order
Page 46
Page 47
Case Studies
of Wind Park Modeling
James W. Feltes and Bernardo Fernandes
Siemens Power Technologies International
(Siemens PTI)
james.feltes@siemens.com
bernardo.fernandes@siemens.com
Ping-Kwan Keung
Now with Alberta Electric System Operator (AESO)
Ping-Kwan.Keung@aeso.ca
Overview
Introduction
Importance of proper modeling of wind
energy projects in system studies
Wind Turbines Equipment Models
Case Study - System Modeling
Analysis Performed
- Power Flow
- Short Circuit
- Transient Stability
Conclusions
Page 49
Introduction
The US is geographically large
Areas with rich wind resources
US Department of Energy in 2008 estimated the wind generation that can be
technically developed:
300 GW needed for a 20% wind scenario
Estimates of the number of buses required to represent each wind turbine in
detail in a load flow model would be 200,000 buses (average size of 3 MW)
Computers of 2030 will likely have no problem doing the calculations
Unlikely that the engineers will be overjoyed at the efforts required to validate,
maintain, and perform studies with this vast amount of extra data.
Page 50
Page 53
Group
1
2
3
4
5
Total
Page 54
# Units
76
142
80
149
50
497
Model
Type
DFIG
DFIG
FC
DFIG
FC
-
Turbine
Type
3
3
4
3
4
-
Size
(MW)
1.5
1.5
2.3
1.5
2.3
-
Total
(MW)
114
213
184
224
115
850
Page 55
Analysis Performed
Power Flow
Determine flows on transmission lines and transformers and voltage profile
- Voltage Control
- Losses in the Collector System
Short Circuit Analysis
Wind Turbine Generators contribution on the system side
Transient Stability
Check synchronism after disturbances, damping of oscillations, and voltage
recovery following fault clearing are adequate
- Stability transfer Limit
- Power System Oscillations
- Low Voltage Ride Through (LVRT)
Page 56
Power Flow
Steady State System Studies
The similarity of both aggregate and detailed models in terms of wind farm
responses to contingencies in the system is dependent on the accuracy of the
equivalent model.
From the system studies standpoint, an equivalent model is sufficient
Optimal voltage control strategy
A detailed model is desirable. It reflects the voltage profile variation along the
feeders.
Reactive power generated or absorbed.
For the same terminal voltage setpoint, a WTG at the far end of a given feeder
will not respond the same way as the ones closer to the collector bus.
Page 57
Page 58
Page 59
Reactive
Support Reactors
at POI
(Mvar)
(Mvar)
Power to
138 kV Bus
EQV
Full
Model
Model
EQV
Model
Full
Model
EQV
Model
Full
Model
Voltage at
WF 138 kV
EQV
Full
Model
Model
Power to POI
Voltage at POI
850
510
823.0
822.8
757.4
756.3
1.050
1.049
0.999
0.991
800
340
777.0
777.2
721.5
721.7
1.038
1.038
1.020
1.021
750
340
730.8
730.8
684.9
685.1
1.048
1.048
1.044
1.045
700
340
683.8
683.8
645.5
646.9
1.055
1.056
1.060
1.061
650
170
636.2
636.0
603.2
603.2
1.039
1.039
1.067
1.068
600
170
-110
587.4
587.4
559.0
559.0
1.040
1.040
1.048
1.048
500
170
-110
491.4
491.7
472.6
472.7
1.049
1.050
1.067
1.068
400
-110
394.6
394.6
382.5
382.5
1.035
1.035
1.077
1.078
Page 60
Main
138 kV
Main
345 kV
POI
345 kV
Page 61
Total Fault
Currrent
(A)
Group 1
Group2
Group 3
Group 4
Group 5
EQV
Full
EQV
Full
EQV
Full
EQV
Full
EQV
Full
EQV
Full
6157
6178
767
755
1390
1394
1137
1167
1235
1275
831
832
2418
2420
707
694
1271
1273
1043
1071
1132
1162
765
764
12548
12537
419
410
708
704
601
623
650
641
450
446
Transient Stability
Stability simulations were performed for two contingencies involving 345 kV
transmission lines in the area surrounding the POI:
- Substation 1 to Substation 2, ckt 1
- POI to Substation 3, ckt 1
All contingencies simulated are three-phase faults cleared by line tripping with a
total clearing time of 6 cycles
Page 62
700
600
500
400
300
200
100
0
-100
-200
0
10
Time (seconds)
Page 64
1.1
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0
10
Time (seconds)
Page 65
Page 66
700
800
600
500
400
300
200
100
plant.
0
-1 00
0
10
Time (seconds)
2 38 - POWR 70 461 TO 7 046 CKT 1 : 72 0MW_ CTG POI to SB3_ EQV Model
4 555 - POWR 7 0461 TO 704 6 CKT 1 : 7 20MW_CTG POI to SB3 _Detailed Mode l
detailed model
1.4
1.3
1.2
1.1
1
0.9
0.8
0.7
0.6
0.5
0
0.25
0.5
0.75
1.25
1.5
1.75
Time (seconds)
2.25
Conclusions
The case studies presented are useful in making decisions on the level of modeling needed
to evaluate the wind farm performance. There is trade-off in accuracy versus complexity of
wind park modeling
Intent of aggregated model is to reflect the response of the wind farm as seen from the
system
For the majority of the steady state studies to evaluate the impact in the system of a given
wind farm, an equivalent representation is sufficient
For detailed steady state studies like the design of voltage control or reactive power
strategies in the wind farm, a detailed model is desirable
A detailed modeling effort is justified in stability studies, since the models must represent
accurately the plant dynamics and its response, particularly for large wind farms in weak
systems
A detailed representation can lead to more realistic results, especially when the dynamic
transfer capability is limited
Obviously, in planning practice detailed layout and data are not available.
Page 68