Sunteți pe pagina 1din 16

GENERATION BUSINESS ENGINEERING

POWER DELIVERY

PROJECT:

765KV SUPERGRID : LINE PROJECT

STATION:

HYDRA SUBSTATION

GRID:

WESTERN

REV.
0

SCOPE OF WORK:
This is the Scope of Work for the installation and commissioning of multimode fibre
optic cables required at Hydra Station within the new 765kV control room and also
between the 765kV control and the Diameter Marshalling Kiosks (DMKs).
Project Manager:

Vincent Matshego

011 800 3780

Application Engineer:

Phumzile Khoza

011 800-5682

1. REFERENCE DOCUMENTS.
All work must be done in accordance with the Standards and specifications listed below.
1.1 Eskom Standards and Specifications:
1.1.1
1.1.2
1.1.4
1.1.5

TSP41-5
TSP41-665
TST41-115
TSP41-586

Fibre Optic Cable Acceptance Testing Procedure.


Multimode Fibre Optic Duct Cable.
Installation of Fibre Optic Cable
Optical Distribution Frames.

1.2 Drawings:
1.2.1 Hydra 765kV Foundation, Trench and Earth Mat Layout Sheet 0
1.2.2 19.37/5263 Hydra 765kV Control Room Layout

2. ABBREVIATIONS.
FSP
ODF
HDPE
FO
DIP
DMK

Fibre Optic Switching Panel


Optical Distribution Frame (Patch Panel)
High Density Polyethylene
Fibre Optic
Diameter Interface Panel
Diameter Marshalling Kiosk

HYDRA STATION 765KV SUPERGRID PROJECT

3. MATERIALS
3.1 Eskom will be responsible for providing all the following materials as free issue items to
the Contractor:
3.1.1 Standard Equipment Cabinets.
3.1.2 All fibre patch leads
3.1.3 All fibre patch panels, 19 inch (1u).
3.2 The contractor will be responsible for providing:
3.2.1 All fibre cables. The contractor shall tender on the A1a.2 multimode fibre type. All
lengths of the fibre optic cables must be confirmed by the contractor.
3.2.2 All cable trays supplied. The contractor shall provide Eskom with a full technical
specification of the cable trays to be installed prior to the commencement of
work.

4. SCOPE OF WORK
4.1 The scope of work covers the supply, installation, testing and commissioning of the fibre
optic cables mentioned below.
FROM THE DMKs MA, MB and MC
4.1.1. In each DMK two 3M Patch Panels will be installed by ABB in the TIE Panel. If there is
no TIE panel, then the patch panels will be installed in the Bay 2 Panel. All cables
terminated in the DMKs will be spliced onto these 3M patch panels.
4.1.2. Two 12 core multimode (50/125m) metal free Heavy Duty Duct (HDD) cables to be
installed from each of the three 765kV DMKs to the Fibre Optic Switching cabinets
(FSP) situated in the 765kV Tx control room (as per Specification TSP41-665).
4.1.3. The fibre optic duct cable shall be installed in directly buried 40mm (Outside diameter)
or 33mm (Inside diameter) Optex ducting from Nextube, or a Class 6 HDPE
equivalent.
4.1.4. A single length of duct cable shall be utilised; no joints will be tolerated.
4.1.5. From DMK MA, one fibre cable will go FSP 1 (labelled MA.TBJBP.FSP1.8070) and the
other will go to FSP 2 (labelled MA.TBJBP.FSP2.8070).
4.1.6. From DMK MB, one fibre cable will go FSP 1 (labelled MB.B2JBP.FSP1.8070) and the
other will go to FSP 2 (labelled MB. B2JBP.FSP2.8070).
4.1.7. From DMK MC, one fibre cable will go FSP 1 (labelled MC.TBJBP.FSP1.8070) and
the other will go to FSP 2 (labelled MC.TBJBP.FSP2.8070).
4.1.8. The cables will be laid in the same trench at a minimum depth of 500mm below
ground level. Refer to points 1.2.1 & 1.2.2 for the trench layouts.
4.1.9. The fibre optic cable shall be glanded on the outer sheath using a compression gland
where it enters the FSP cabinets.

HYDRA STATION 765KV SUPERGRID PROJECT

FROM DIAMETER MA
4.1.10.

Install one 12 core multimode (50/125m) cable from the DIAMETER MA cabinet
to FSP 1. The fibre cable will be labelled MA.IP.FSP1.8070

4.1.11.

Install one 12 core multimode (50/125m) cable from the DIAMETER MA cabinet
to FSP 2. The fibre cable will be labelled MA.IP.FSP2.8070

4.1.12.

All cables terminated in the DIAMETER MA panel will be spliced onto the 3M
patch panels supplied in the cabinet.

4.1.13.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

FROM DIAMETER MB
4.1.14.

Install one 12 core multimode (50/125m) cable from the DIAMETER MB cabinet
to FSP 1. The fibre cable will be labelled MB.IP.FSP1.8070.

4.1.15.

Install one 12 core multimode (50/125m) cable from the DIAMETER MB cabinet
to FSP 2. The fibre cable will be labelled. MB.IP.FSP2.8070

4.1.16.

All cables terminated in the DIAMETER MB panel will be spliced onto the 3M
patch panels supplied in the cabinet.

4.1.17.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

FROM DIAMETER MC
4.1.18.

Install one 12 core multimode (50/125m) cable from the DIAMETER MC cabinet
to FSP 1. The fibre cable will be labelled MC.IP.FSP1.8070.

4.1.19.

Install one 12 core multimode (50/125m) cable from the DIAMETER MC cabinet
to FSP 2. The fibre cable will be labelled MC.IP.FSP2.8070.

4.1.20.

All cables terminated in the DIAMETER MC panel will be spliced onto the 3M
patch panels supplied in the cabinet.

4.1.21.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

HYDRA STATION 765KV SUPERGRID PROJECT

FROM THE D400 PANEL


4.1.22.

Install one 12 core multimode (50/125m) cable from D400 cabinet to the FSP1
cabinet. The fibre cable will be labelled D400.FSP1.8070

4.1.23.

Install one 12 core multimode (50/125m) cable from D400 cabinet to FSP 2
cabinet. The fibre cable will be labelled D400.FSP2.8070.

4.1.24.

All cables terminated in the D400 panel will be spliced onto the patch panels in the
cabinet.

4.1.25.

Refer to the D400 Panel layout shown below

4.1.26.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

FROM D20 PANEL


4.1.27.

Install one 12 core multimode (50/125m) cable from the D20 cabinet to FSP 1.
The fibre cable will be labelled D20.FSP1.8070

4.1.28.

Install one 12 core multimode (50/125m) cable from the D20 cabinet to FSP 2.
The fibre cable will be labelled D20.FSP2.8070

4.1.29.

All cables terminated in the D20 panel will be spliced onto the patch panels in the
cabinet.

4.1.30.

Refer to the D20 Panel layout shown below

4.1.31.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

BETWEEN FSP 1 AND FSP2


4.1.32.

One 12 core multimode (50/125m) cable to be installed from FSP 1 to FSP 2 and
will be labelled FSP1.FSP2.8070

4.1.33.

The FSP cabinets will be supplied by Eskom and shall be installed by the
contractor as per their positions shown on the drawings mention in points 1.2.3 &
1.2. 4. See also Specification TSP41-665.

4.1.34.

All patch panels in FSP 1 and FSP 2 must be supplied by the contractor installing
the cables.

4.1.35.

Refer to the Fibre Optic Switching Panel 1 and 2 layout shown below

4.1.36.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

HYDRA STATION 765KV SUPERGRID PROJECT

FROM FEEDER 1 LINE REACTOR


4.1.37.

One 12 core multimode (50/125m) cable to be installed from Feeder 1 Line


Reactor. Feeder 1 Line Reactor to FSP 1 will be labelled F1R.IP.FSP1.8070

4.1.38.

One 12 core multimode (50/125m) cable to be installed from Feeder 1 Line


Reactor. Feeder 1 Line Reactor to FSP 2 will be labelled F1R.IP.FSP2.8070

4.1.39.

All cables terminated in the FEEDER 1 LINE REACTOR panel will be spliced onto
the 3M patch panels supplied in the cabinet.

4.1.40.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

FROM BUSBAR REACTOR 1


4.1.41.

One 12 core multimode (50/125m) cable to be installed from Busbar Reactor 1


to FSP 1 will be labelled BR1.IP.FSP1.8070.

4.1.42.

One 12 core multimode (50/125m) cable to be installed from Busbar Reactor 1 to


FSP 2 will be labelled BR1.IP.FSP2.8070.

4.1.43.

All cables terminated in the BUSBAR REACTOR 1 panel will be spliced onto the
3M patch panels supplied in the cabinet.

4.1.44.

The fibre optic cables shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

FROM AUXILIARY TRANSFORMER 31


4.1.45.

One 12 core multimode (50/125m) cable to be installed from Auxiliary


Transformer 31 to
FSP 1 will be labelled T31A.IP.FSP1.8070.

4.1.46.

One 12 core multimode (50/125m) cable to be installed from Auxiliary


Transformer 31 to FSP 2 will be labelled T31A.IP.FSP2.8070.

4.1.47.

All cables terminated in the AUXILIARY TRANSFORMER 31 panel will be spliced


onto the 3M patch panels supplied in the cabinet.

4.1.48.

The fibre optic cable shall be glanded on the outer sheath using a compression
gland where it enters the FSP cabinets.

FROM THE IHMI


4.1.49.

One 12 core multimode (50/125m) cable to be installed from HMI workstation to


the D400 cabinet. The fibre cable will be labelled IHMI.D400.8070.
Refer to the D400 Panel equipment layout shown below.

4.1.50.
A 3M patch box must be supplied and installed by the contractor at the HMI
workstation in order to terminate the fibre cable.

HYDRA STATION 765KV SUPERGRID PROJECT

FROM THE EWS


4.1.51.

One 12 core multimode (50/125m) cable to be installed from the engineering


workstation to the D400 cabinet. The fibre cable will be labelled EWS.D400.8070
Refer to the D400 Panel equipment layout shown below.

4.1.52.

A 3M patch box must be installed by the contractor at the EWS Panel in order to
terminate the fibre cable.

4.2 All Heavy Duty Duct cables must be installed in individual OPTEXTM., from Nextube, or a
Class 6 HDPE equivalent. Single length ducts must be installed for its full length in
accordance with Specification TSP41-115
4.4 At the control room, the HDPE pipe must extend into the building. Should the where
termination be required over a cable trench, then the HDPE pipe must be anchored to
the cable trench wall by 2U clamps. A two metre length of cable must be coiled within
the cabinet to allow for work to be performed on the ODF.
4.5 The cables must be numbered as detailed above and as shown on the attached sketch 1
below.
4.6 Colour coding shall be in accordance with Eskoms specifications TSP41-16 and TSP41665. The marker buffer shall always be red and the reference buffer shall always be
green.

HYDRA STATION 765KV SUPERGRID PROJECT

4.7 BETWEEN 765kv Control Room AND 400kV control rooms


INSTALL AND TERMINATE FIBRE OPTIC CABLE, 12 CORE, MULTI-MODE, FROM 765kV CONTROL
ROOM TO 400KV WEST CONTROL ROOM [765KVCR..400KVCR WEST ]
INSTALL AND TERMINATE FIBRE OPTIC CABLE, 12 CORE, MULTI-MODE, FROM 765KV CONTROL
ROOM TO 400KV WEST CONTROL ROOM [765KVCR..400KVCR EAST ]

SUPPLY ,INSTALL AND TERMINATE FIBRE OPTIC CABLE, 12 CORE, MULTI-MODE BETWEEN 400KV
WEST ERTU 3M BOX AND OPTIC FIBRE CABINET IN THE W EST CONTROL ROOM [ERTU CABINET
NO13]
SUPPLY, INSTALL AND TERMINATE FIBRE OPTIC CABLE, 12 CORE, MULTI-MODE BETWEEN 400KV
EAST ERTU 3M BOX AND FIBRE OPTIC CABINET IN THE EAST CONTROL ROOM [ERTU- CABINET NO1]
SUPPLY, INSTALL AND TERMINATE FIBRE OPTIC CABLE, 12 CORE, MULTI-MODE BETWEEN 765KV
FIBRE OPTIC CABINET AND D400 CABINET IN THE 765KV CONTROL ROOM [D400 CABINET NO31]

INSTALL AND TERMINATE FIBRE OPTIC CABLE, 12 CORE, MULTI-MODE, BETWEEN 400kV CONTROL
ROOM EAST AND 400KV WEST CONTROL ROOM [400KVCR EAST..400KVCR WEST]

The fibre optic cables shall be glanded on the outer sheath using a compression
cabinets

gland where it enters the

5 CABLE TRAYS
5.1 A separate cable tray exclusively for fibre optic cabling needs to be installed about
500mm under the computer flooring within both the Control room and the Diameter
Marshalling Kiosk (DMK).
5.2 The contractor shall provide Eskom with a full technical specification of the cable trays to
be installed prior to the commencement of work.

6 GENERAL
6.1 All lengths of the fibre optic cables must be confirmed by the contractor.
6.2 All splicing must be done by the contractor.
6.3 The minimum bending radius of each cable as specified by the manufacturer shall be
maintained. See Installation standard TST41-115.
6.4 Care shall be taken to maintain the bending radius specification when guiding the duct
cable from the substation trench towards the control room floor. When entering the
control room floor, the top of the HDPE pipe shall be sealed with UV-resistant silicone
sealer or heat-shrink tubing.
6.5 The contractor shall provide Eskom with a full technical specification of the duct cable to
be installed prior to the commencement of work.
6.6 All patch panels to be supplied by the contractor. The contractor shall provide Eskom
with a full technical specification of the patch panels to be installed prior to the

HYDRA STATION 765KV SUPERGRID PROJECT

commencement of work. Refer to TSP41-586. Refer to the Panel layout drawings shown
below for the patch panel quantities and positions.
6.7 All

installations

must

be

in

accordance

with

Eskoms

specifications.

7 TESTING
7.1

All splices must be tested in accordance with the latest revision of Eskom Fibre
Acceptance Test Procedure TPC41-5, Class B.

7.2

The contractor must submit a list of test gear available together with their current
calibration test certificates.

7.3

The Contractor must make his this test gear available on site for acceptance testing.

7.4

All fibre optic cable splicing and connections to be quality/acceptance tested by Eskom
Transmission.

8 DOCUMENTATION
The following documentation shall be given to Eskom and approved by Eskom on completion
of this work. Installation Standard TST41-115 refers.
8.1
8.2
8.2
8.3

Test results as per the Fibre Optic cable System Acceptance Testing Procedure TPC415, Class B.
Updated drawings showing the cable routing through the yard and to the Station.
Updated drawings showing the cable tray routing within the DMK and within the control
room.
Full technical specification of all duct cables installed.

9 SAFETY
The safety and environmental requirements shall be adhered to in accordance with the
Installation Standard TST41-115.

10 QUALITY CONTROL
The contractor shall have a quality management system based on SABS ISO 9001, and
effectively implemented product/process quality plans.

11 REQUIREMENTS OF THE CONTRACTOR


11.1 The Scope of Works as set out in this document must be done by an external contractor.
11.2

The successful Contractor must complete the Operating Regulations for High Voltage
Systems (HV Regulations) Course, and must be assessed and approved by the Grid
or Grids where the work is to be performed otherwise he must work under the
supervision of a responsible person on site, who has been authorised.

HYDRA STATION 765KV SUPERGRID PROJECT

12 SCHEDULE A
SubClauses

AND

Description

Comply?
(Yes/No)

Materials
3.1.1

A1a.2 multimode fibre type. All lengths of the fibre optic


cables must be confirmed by the contractor.

3.1.2

The contractor shall provide Eskom with a full technical


specification of the cable trays to be installed prior to
the commencement of work.

Scope of Work
4.1

FROM DMK MA, TIE BAY JB PANEL

4.2

FROM DMK MB, BAY 2 JB PANEL

4.3

FROM DMK MC, TIE BAY JB PANEL

4.4

FROM DIAMETER MA INTERFACE PANEL

4.5

FROM DIAMETER MB INTERFACE PANEL

4.6

FROM DIAMETER MC INTERFACE PANEL

4.7

FROM 765KV BUSBAR


PANEL

4.9

FROM 765KV FEEDER 1 REACTOR INTERFACE


PANEL

4.10

FROM AUXILLARY TRANSFORMER 31 INTERFACE


PANEL

4.11

FROM THE D400 PANEL

4.12

FROM D20 PANEL

4.13

BETWEEN FSP 1 AND FSP2

4.14

FROM THE IHMI

4.15

FROM THE EWS

REACTOR 1 INTERFACE

A separate cable tray exclusively for fibre optic cabling


needs to be installed about 500mm under the computer
flooring within both the Control room and the Diameter
Marshalling Kiosk (DMK)

Testing
7

The contractor must submit a list of test equipment to


be used together with their current calibration test
certificates

Remarks

HYDRA STATION 765KV SUPERGRID PROJECT

SubClauses

Description

(Yes/No)

Documentation
8.1

Full technical specification of all duct cables installed


prior to the commencement of work

8.2

Test results as per the Fibre Optic cable System


Acceptance Testing Procedure TPC41-5, Class B

8.3

Updated drawings showing the cable routing through


the yard and to the Station

8.4

Updated drawings showing the cable tray routing within


the DMK and within the control room

8.5

A materials list indicating fibre cables, fibre cable trays,


and related equipment.

8.6

Comply?

The submissions to include the installation schedule


(duration in days) and early start date upon contract
award, indicating lead time of materials

Remarks

765kV Control Room


EWS

EWS.D400.8070

D400 Panel

IHMI.D400.8070

F1R.IP.FSP1.8070

IHMI

PP1

D400.FSP1.8070

PP2

D400.FSP2.8070

FSP 1

BR1.IP.FSP1.8070

PP1

Feeder 1 Line
Reactor

Busbar Reactor 1

MA.IP.FSP1.8070
MB.IP.FSP1.8070

PP2

MC.IP.FSP1.8070
T31A.IP.FSP1.8070

PP1
PP2

Diameter MA

FSP1.FSP2.8070
F1R.IP.FSP2.8070
BR1.IP.FSP2.8070

FSP 2

MA.IP.FSP2.8070

PP1

Diameter MB
PP2

MB.IP.FSP2.8070
MC.IP.FSP2.8070
T31A.IP.FSP2.8070

PP1

Diameter MC
PP2

D20.FSP1.8070

PP1
D20.FSP2.8070

PP2

Hydra 765kV Project


Intra-Control Room
Telecontrol Fibre Philosophy (Rev 000)
Multimode Fibre 50/125
Multimode Fibre on Gigabit LAN

D20 Panel

Auxiliary
Transformer 31

765kV Control Room


HV Yard
FSP 1
DMK MA

PP1
PP2

DMK MB

PP1
PP2

DMK MC

PP1
PP2

Hydra 765kV Project


From the DMKs to Control Room
Telecontrol Fibre Philosophy (Rev 000)

Multimode Fibre 50/125

MA.TBJBP.FSP1.8070
MA.TBJBP.FSP2.8070

MB.B2JBP.FSP1.8070

FSP1.FSP2.8070

MB.B2JBP.FSP2.8070

FSP 2

MC.TBJBP.FSP1.8070
MC.TBJBP.FSP2.8070

HYDRA FSP 1
RSG 2200 SW1
RSG 2200 SW2

FSP1.PP1

MA.TBJBP.FSP1.8070

FSP1.PP2

MB.B2JBP.FSP1.8070

FSP1.PP3

MC.TBJBP.FSP1.8070

FSP1.PP4

MA.IP.FSP1.8070

FSP1.PP5

MB.IP.FSP1.8070

FSP1.PP6

MC.IP.FSP1.8070

FSP1.PP7

FSP1.FSP2.8070

FSP1.PP8

D400.FSP1.8070

FSP1.PP9

F1R.IP.FSP1.8070

FSP1.PP10

BR1.IP.FSP1.8070

FSP1.PP11

T31A.IP.FSP1.8070

FSP1.PP12

D20.FSP1.8070

DRAWN

P. Khoza

DATE

29/06/2011

REVISION

Hydra Substation New 765kV Control Room


Cabinet No. 29
Fibre Optic Switching Cabinet 1 Equipment Layout

HYDRA FSP 2
RSG 2200 SW3
RSG 2200 SW4

FSP2.PP1

MA.TBJBP.FSP2.8070

FSP2.PP2

MB.B2JBP.FSP2.8070

FSP2.PP3

MC.TBJBP.FSP2.8070

FSP2.PP4

MA.IP.FSP2.8070

FSP2.PP5

MB.IP.FSP2.8070

FSP2.PP6

MC.IP.FSP2.8070
FSP1.FSP2.8070

FSP2.PP7
FSP2.PP8

D400.FSP2.8070

FSP2.PP9

F1R.IP.FSP2.8070

FSP2.PP10

BR1.IP.FSP2.8070

FSP2.PP11

T31A.IP.FSP2.8070

FSP2.PP12

D20.FSP2.8070

DRAWN

P. Khoza

DATE

29/06/11

REVISION

Hydra Substation New 765kV Control Room


Cabinet No. 28
Fibre Optic Switching Cabinet 2 Equipment Layout

HYDRA STATION 765KV SUPERGRID PROJECT

D400 Panel

RSG 2100

D400. FSP1.8070
D400. FSP2.8070
EWS.D400.8070
IHMI.D400.8070

DRAWN

P. Khoza

DATE

29/06/11

REVISION

Hydra Substation New 765kV Control Room


Cabinet No. 26
D400 Panel Equipment Layout

HYDRA STATION 765KV SUPERGRID PROJECT

D20 Panel

RSG 2100

D20.FSP1.8070
D20.FSP2.8070

DRAWN

P. Khoza

DATE

29/06/11

REVISION

Hydra Substation New 765kV Control Room


Cabinet No. 27
D20 Panel Equipment Layout

S-ar putea să vă placă și