Documente Academic
Documente Profesional
Documente Cultură
Proceedings of ICTPEA-2016
Introduction
In transmission and distribution lines, voltage instability may be due to overloading, high
reactive power and low operating power factor. It is possible to control over loading to some
extent by creating a general awareness among public about the scarcity of power.
Reactive power and power factor are interrelated to each other. In electric power systems
real power does useful work while reactive power supports the voltages that must be maintained
for the reliability of the system. Since most of the loads are inductive in nature by default reactive
power requirements will be high at the load side. Reactive power generation at generating end will
increase per unit cost of generation and decreases the reliability of the system because at generating
end generation of excess reactive power that is not utilized for any purpose makes the power
system inefficient. However it is better if the minimum reactive power required by the system is
generated at generation point and the excess requirements are injected at load side [33, 34, 35].
At present there are high voltage capacitor banks (capacitors arranged either in series or
parallel at Davanagere receiving station) to compensate reactive power and power factor. But it is
seen that this equipment will not work efficiently at all conditions of load variations. As the load
increases capacitor banks become inefficient in compensating reactive power and power factor.
The work carried out at Davanagere receiving station aims at improving the voltage
magnitude in a permissible safe limit (0.9 to 1.1 pu IEEE standards) with the help of FACTS
devices. Since both SVC and STATCOM have capacitance and inductive reactance as its
components, they both can regulate the voltage such that when voltages on the bus goes down it
injects reactive power and increases the voltage to the required level.
www.iirdem.org
33
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
Current
rating
In Amps
R+jX
In ohm
Current at
Ambient
Temperature in
Amps
Sl. No.
Name of the
Conductor
Voltage
level in
KV
01
Coyote
66
487
0.135+j0.104
30
387
50
487
02
Coyote
11
367
0.0248+j0.0337
215
367
03
Drake
220
900
0.244+j0.243
745
900
04
Drake
66
487
0.135+j0.104
400
487
05
Drake
11
387
0.038+j0.0260
325
387
Transmission line parameters of different conductors which are used at sub-station for bus
bar connection and also the transmission lines are specified .as shown in Table 4.1
: 69.24amps
Quantity
: 484 KVAR
Rated voltage
: 13.98KV
Temperature
: 50 (ambient)
Fuse protection
: Internal
Rated capacitance
: 31.03f
Frequency
: 50Hz
Insulation level
: 28/75
Standard
: IS: 19325
www.iirdem.org
34
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
At all substations in each phase there are two capacitor cells and for three phases there are
six cells. Each capacitor cell has a capacity of 484 MVAR and the capacity of each capacitor
bank at the substation is (484 x 6=2.904 MVAR). At each substation there are two capacitor
banks of identical rating. Total capacitor rating is 2*2.904 =5.808 MVAR
Ratings of SVC
Rated power
0-50 MVAR
Capacitive
0-50 MVAR
Inductive
www.iirdem.org
Description
Load in MW
MVAR
Load in Amps
66 KV Incoming from
Davanagere
10.6
4.95
106
Hiremegalgere
2.0
0.46
120
Kanchikere
2.5
0.575
150
Kyarekatte
3.10
0.713
186
Laxmipura
0.80
0.18
48
Punabgatta
2.5
0.575
150
35
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
Hosakote
2.8
0.644
168
Arasikere
1.6
0.368
96
Before charging of
Capacitor Banks
After
Charging of
Capacitor Banks
Compensation
350 amps
290 amps
62 amps
5.86MW
4.80 MW
1.03 MW
190 amps
160 amps
29.16 amps
3.16 MW
2.67 MW
0.49 MW
Bank 1
F1 and F2
Bank2
F5 and F6
Total compensation from the shunt capacitor bank of 2.904 MVAR is 0.942 MVAR
The total reactive power compensation at all the receiving stations are evaluated at a load
power factor of 0.85 lagging.
www.iirdem.org
Description
Load in
MW
MVAR
Load in
Amps
66 KV Incoming from
Davanagere
10.3
4.970
103
Wind 1 (IPP)
8.0
3.66
80
Wind 2 (IPP)
6.0
2.77
60
Kadur
1.7
0.34
102
Hirekandwadi
3.5
0.50
210
BevinaDurga
3.0
0.40
180
36
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
Kothehal
1.2
0.30
72
Chickjajur
6.1
1.8
366
Chikkandwadi
4.0
0.9
240
10
Gangiganur
0.6
0.1
36
11
Water house
0.1
0.001
06
Before charging of
Capacitor Banks
After charging of
Capacitor Banks
Compensation
Bank-1
F1 and F2
102+218=320 Amps
5.34MW
0.84MW
Bank-2
F6 and F7
202+38=240 Amps
4.0MW
3.2 MW
0.8MW
1.02 MVAR
www.iirdem.org
Description
Incoming from 400KV Guttur-1
Incoming from 400KV Guttur-2
Incoming from 400KV Guttur-3
Incoming from Receiving Station Shimoga-1
Incoming from Receiving Station Shimoga-2
66KV Sokke Line
37
Load in
MW
131
73
123
131
105.6
16.0
MVAR
42.75
23.98
59.419
42.75
34.68
12.62
Load in
Amps
327.5
182.5
307.5
327.5
564
160
IIRDEM 2016
ISBN-13: 978-1535305198
7
8
9
10
11
12
13
14
15
Proceedings of ICTPEA-2016
11.0
13.5
11.0
21.0
20.0
4.0
11.0
26.0
10.5
6.0
7.0
6.0
18.2
6.00
4.10
6.0
16.0
2.60
110
135
110
212
200
130
110
260
105
Before charging of
Capacitor Banks
After charging of
Capacitor Banks
66kv
Feeders
F1-F10
888.9amps
728.9amps
152.6 amps
88.89MW
72.89 MW
15.26MW
Compensation
Total compensation from the shunt capacitor bank of 2.904 MVAR is 9.46 MVAR
Summary
It is seen that when experiments were conducted at the load sites of Punabhgatta, Chickjajur
and Davanagere receiving station a total reactive power compensation of 0.942, 1.02 and 9.46
MVAR respectively was possible at a power factor of 0.85 lag after using the capacitor banks.
FACTS devices are not used at present at the above mentioned power grids. The experiments
conducted at the site is an unique feature of this thesis.
In the discussions which fallow simulations were done for the above powers systems up to
125% over loading and the reactive power relief on the generator side is evaluated as shown.
www.iirdem.org
38
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
each case again four sets of results were obtained that is without any compensation, with shunt
capacitors, with SVC and with STATCOMS. All the results are analyzed and the analysis is given
in Table 4.9.
It is assumed that at nominal load conditions system will be healthy and it is not necessary
to use any FACTS devices. It is seen that shunt capacitors are efficient in controlling power factor
and reactive power generation.
Bus
Voltages (pu)
Gen P.F
1.0000
0.9910
0.9992
1.0178
1.0492
1.0452
1.0509
1.0447
0.978
0.978
0.978
0.978
0.978
0.978
0.978
0.978
5.056
Gen P.F
0.993
0.993
0.993
0.993
0.993
0.993
0.993
0.993
2.860
At Bus 8 of the system with nominal load and without any compensation, variations are as
shown in Table 4.8 and the results are summarized. At Bus 2 and Bus 3 the voltages are reduced,
power factor is 0.978 and reactive power generated is 5.056 MVAR.
With shunt power capacitors of rating 2.904 MVAR, it is seen that voltages at Bus 2 and
Bus 3 the voltages are brought to unity, power factor is increased to 0.993 and reactive power
generated is 2.86 MVAR.
www.iirdem.org
39
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
6.321
3.542
1.647
0.827
Without the connection of any capacitor it is seen that at Bus 2 and Bus 3 there is a sag in
Voltage from 1.0 p,u to 0.9 p.u . This sag is considerable since the Base Voltage is in KV.
Summary:
As highlighted earlier at Punabhgatta power grid there is one incoming line at 66 KV from
Davanagere followed by installation two transformers of 12.5 and 8 MVA respectively. There are
seven loads and a capacitor bank which is connected as shunt to the loads. As seen from Tables 4.8
to 4.9 as the loads on the system is increased to 125% the amount of reactive power generated at
the generator end predominantly reduces as the FACTS devices are used. Of the various FACTS
devices used STATCOM reduces the reactive power generated at the generator side to a least value
as reactive power supplied by the STATCOM is high. It is seen that MVAR generation reduces
with reactive power compensation.
www.iirdem.org
40
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
Bus
Voltages (pu)
Gen P.F
Bus
Voltages (pu)
Gen P.F
01
1.0000
0.974
1.000-1.4
0.981
02
1.0105
0.974
1.0105
0.981
03
1.0020
0.974
1.0020
0.981
04
1.0470
0.974
1.0472
0.981
05
1.0495
0.974
1.0497
0.981
06
1.0382
0.974
1.0384
0.981
07
1.0312
0.974
1.0313
0.981
08
1.0261
0.974
1.0262
0.981
09
1.0308
0.974
1.0309
0.981
10
1.0417
0.974
1.0418
0.981
11
MVAR
gen
1.0535
0.974
1.0536
0.981
4.740
4.421
At Chickajajur receiving station there is no voltage sag at any of the buses as generation
capacity is sufficient at this receiving station.
Bus No
01
02
03
04
05
06
www.iirdem.org
Without
Compensation
Bus
Gen
Voltage (pu) P.F
1.0000
1.0068
1.0000
1.0455
1.0486
1.0330
0.973
0.973
0.973
0.973
0.973
0.973
With Shunt
Capacitors
Bus
Voltage (pu)
1.0000
1.0069
1.0000
1.0457
1.0488
1.0331
With SVC
With STATCOM
Gen
Bus
Gen
Bus
P.F Voltage (pu) P.F Voltage (pu)
Gen
P.F
0.978
0.978
0.978
0.978
0.978
0.978
1.000
1.000
1.000
1.000
1.000
1.000
41
1.0000
1.0069
1.0000
1.0574
1.0534
1.0366
0.996
0.996
0.996
0.996
0.996
0.996
1.0000
1.0070
1.0007
1.0574
1.0534
1.0367
IIRDEM 2016
ISBN-13: 978-1535305198
07
08
09
10
11
Proceedings of ICTPEA-2016
1.0228
1.0149
1.0195
1.0319
1.0455
Mvar
gen
0.973
0.973
0.973
0.973
0.973
1.0229
1.0150
1.0196
1.0320
1.0455
6.116
0.978
0.978
0.978
0.978
0.978
1.0252
1.0161
1.0198
1.0322
1.0457
0.996
0.996
0.996
0.996
0.996
1.0256
1.0164
1.0201
1.0325
1.0458
1.834
5.898
1.000
1.000
1.000
1.000
1.000
0.993
Even at 125% over load at Chickajajur receiving station there is no voltage sag at any of
the buses as sufficient generation supply is there at this Receiving Station.
Summary:
There are three incoming lines at 66 KV from Davanagere and Wind energy power plant is
installed at Chickjajur followed by installation of two transformers of 12.5 and 6.3 MVA
respectively. There are eight loads and two capacitor banks which are connected as shunt to the
loads. Table 4.4 and 4.5 shows load flow details.
As seen in Table 4.13 as the loads on the system is increased to 125% the amount of
reactive power generated at the generator end predominantly reduces as the FACTS devices are
used. Of the various FACTS devices used STATCOM reduces the reactive power generated at the
generator side to a least value as reactive power supplied by the STATCOM is high.
www.iirdem.org
01
Bus
Voltage (pu)
1.0000
Gen
P.F
0.862
Bus
Voltage (pu)
1.0000
Gen
P.F
0.866
02
1.0493
0.862
1.0493
0.866
03
1.0000
0.862
1.0000
0.866
42
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
04
1.0517
0.862
1.0517
0.866
05
1.0474
0.862
1.0475
0.866
06
0.8713
0.862
0.8715
0.866
07
0.8391
0.862
0.8395
0.866
08
0.8416
0.862
0.8421
0.866
09
0.8741
0.862
0.8744
0.866
10
0.9655
0.862
0.9657
0.866
11
0.9394
0.862
0.9395
0.866
12
0.9198
0.862
0.9200
0.866
13
0.9247
0.862
0.9249
0.866
14
0.9534
0.862
0.9536
0.866
15
1.0376
0.862
1.0377
0.866
Mvar
gen
154.817
152.234
www.iirdem.org
Without
With Shunt
With STATCOM
With SVC
Capacitors
Compensation
Bus
Gen
Bus
Gen
Bus
Gen
Bus
Gen
Voltage (pu) P.F Voltage (pu) P.F Voltage (pu) P.F Voltage (pu) P.F
1.0000
0.859
1.0000
0.863
1.000
0.900
1.000
0.930
02
1.0493
0.859
1.0493
0.863
1.009
0.900
1.009
0.930
03
1.0000
0.859
1.0000
0.863
1.0805
0.900
1.0805
0.930
04
1.0517
0.859
1.0517
0.863
1.2241
0.900
1.2241
0.930
05
1.0475
0.859
1.0475
0.863
1.1240
0.900
1.1240
0.930
06
0.8695
0.859
0.8715
0.863
0.9232
0.900
0.9638
0.930
43
IIRDEM 2016
ISBN-13: 978-1535305198
Proceedings of ICTPEA-2016
07
0.8353
0.859
0.8395
0.863
0.8893
0.900
0.9243
0.930
08
0.8394
0.859
0.8421
0.863
0.8943
0.900
0.9351
0.930
09
0.8697
0.859
0.8744
0.863
0.9235
0.900
0.9643
0.930
10
0.9602
0.859
0.9657
0.863
1.0171
0.900
1.0241
0.930
11
0.9347
0.859
0.9395
0.863
0.9841
0.900
1.0013
0.930
12
0.9154
0.859
0.9200
0.863
0.9742
0.900
0.9993
0.930
13
0.9201
0.859
0.9249
0.863
0.9620
0.900
0.9879
0.930
14
0.9503
0.859
0.9536
0.863
0.9921
0.900
1.0136
0.930
15
1.0342
0.859
1.0377
0.863
1.0398
0.900
1.0402
0.930
Mvar
gen
209.234
207.240
108.837
92.362
There is voltage sag at all the buses starting from bus 6 to bus 14 as this receiving station
has heavy loads as compared to Chickjajur and Punabhghatta receiving stations.
Summary:
There are five incoming lines at 220 KV, three from Guttur (400 KV receiving station) and
two from Shimoga (220 KV Mahatma Gandhi receiving station) followed by installation of three
transformers out of which two are 100 MVA and one transformer of 60 MVA. There are ten loads
at 66 KV and two capacitor banks which are connected as shunt to the loads. Table 4.6 and 4.7
shows load flow details and capacitor loading details conducted at site respectively.
The loads on the system are increased to 125%, the amount of reactive power generated at
the generator end predominantly reduces as the FACTS devices are used. Of the various FACTS
devices used STATCOM reduces the reactive power generated at the generator side to a least value
as reactive power supplied by the STATCOM is high.
The contribution of this work is a detailed analysis of effect of loading the system. The
response of the system to the increase in load is analysed.
[1] Renato B. L. Guedes, Luis F. C. Alberto, Newton G. Bretas, Power System Low-Voltage
Solutions Using an Auxiliary Gradient System for voltage collapse Purposes , IEEE
Transactions on Power Systems, Vol. 20, NO. 3, August 2005, Page No. 1528-1537.
www.iirdem.org
44
IIRDEM 2016