Documente Academic
Documente Profesional
Documente Cultură
Province of Bohol
Municipality of Sikatuna
Name of Project:
Location:
Project Cost:
Fund Source:
ITEM
I.
II.
SCOPE OF WORK
EARTHWORKS
1. Excavation
REINFORCE CONCRETE
QUANTITY
UNIT
6.32
cu.m
Err:509
cu.m
Equipment to be Used
concrete mixer
electric cut- off saw
plate compactor
BREAKDOWN OF ESTIMATES
Amount
1. Material Cost
2. Equipment Cost
3. Labor Cost
4. Profit
5. OCM
6. TAX
TOTAL PROJECT COST
.....
.....
.....
.....
.....
.....
.....
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Project Duration
: 45 cal days
Date Prepared
UNIT COST
AMOUNT
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
ITEM NO.
I.
DESCRIPTION
UNIT
EARTHWORKS
Excavation
cum
II.
FLOORING
Portland Cement
Sand
Gravel
Colored Cement
cum
bags
cum
cum
kg
III.
bags
cum
cum
pcs
pcs
kg
pcs
bdft
kg
DRYWALL
35mm x 92mm x 3m ga.24/0.60mm Track
35mm x 92mm x 3m ga.24/0.60mm Studs
3" Concrete nail
5/32" blind rivets
pcs
pcs
kg
pcs
IV.
V.
VI.
CEILING WORKS
ficem board 4.5mm
25mm x 25mm x 3m
19mm x 50mm x 5m
19mm x 50mm x 5m
12mm x 38mm x 5m
single furring clip
ga.
ga.
ga.
ga.
24/0.60mm
26/0.40mm
26/0.40mm
22/0.80mm
wall angle
double furring
single furring
carrying channel
pcs
pcs
pcs
pcs
pcs
pack
VII.
pack
pcs
pcs
pcs
pair
pair
unit
unit
unit
VIII.
IX.
ELECTRICAL WORKS
6-Branch Panel Board*
Single gang switch*
Two gang sweet*
Three gang sweet*
15 AT breaker*
20 AT breaker*
60 AT breaker*
2-20 watt fl w/ lumnaire*
4-3 watt led w/ 3" down light luminaire
4" x 2" utility box
4" x 4" junction box
15mm pvc conduit pipe
15mm flexible pvc pipe
3.5mm2 thhn
5.5mm2 thhn
8.0mm2 thhn
electrical tape
set
set
set
set
pcs
pcs
pcs
set
pcs
pcs
pcs
pcs
lnm
roll
roll
roll
roll
PAINTING
Flat latex
Semi-gloss latex
Elastomeric paint
Sand paper #120
9" Roller brush
3" flat brush
GAL
GAL
GAL
PCS
PCS
PCS
TOTAL MATERIAL COST
30% LABOR
TOTAL COST
nes
una
OF MATERIALS
Project Duration : 45 cal days
Date Prepared
: December 7, 2015
UNIT COST
QTY.
AMOUNT
1.80
11.80
106.00
6.00
11.00
20.00
296.70
1,564.00
1,449.00
57.50
31,450.20
9,384.00
15,939.00
1,150.00
34.00
3.00
1.00
365.00
16.00
2.00
296.70
1,564.00
1,449.00
20.70
155.25
80.50
10,087.80
4,692.00
1,449.00
7,555.50
2,484.00
161.00
2.00
50.00
5.00
396.75
21.28
48.30
793.50
1,064.00
241.50
35.00
99.00
2.00
1000.00
156.40
172.50
109.25
0.40
5,474.00
17,077.50
218.50
400.00
48.00
22.00
28.00
62.00
20.00
22.00
552.00
57.50
114.23
89.70
126.50
24.15
26,496.00
1,265.00
3,198.44
5,561.40
2,530.00
531.30
32.00
4000.00
2000.00
8.00
34.50
0.86
0.40
97.75
1,104.00
3,440.00
800.00
782.00
9.00
13.00
1.00
2.00
2.00
333.50
189.75
1,380.00
3,001.50
2,466.75
1,380.00
available
available
1.00
1.00
5.00
1.00
2.00
4.00
1.00
26.00
4.00
42.00
17.00
10.00
13.50
2.00
2.00
1.00
6.00
253.00
23.00
31.63
89.70
115.00
3,375.25
3,484.50
5,451.00
43.70
available
available
available
available
available
available
available
available
1,012.00
966.00
537.71
897.00
1,552.50
6,750.50
6,969.00
5,451.00
262.20
10.00
10.00
10.00
20.00
4.00
4.00
569.25
669.30
603.75
11.50
42.26
60.95
5,692.50
6,693.00
6,037.50
230.00
169.04
243.80
AL MATERIAL COST
% LABOR
AL COST
205,641.64
61,692.49
267,334.13
ITEM NO.
I
II
DESCRIPTION
UNIT
EARTHWORKS
Excavation
cum
CONCRETE CANAL
Cement
Sand
Gravel
4" CHB
10mm DEF. BAR
cum
cum
cum
pcs
pcs
METAL GRILLES
2"x 2" x 6mm ANGLE BAR
12mm DEF. BAR
Welding rod
pcs
pcs
kg
ines
una
OF MATERIALS
Project Duration : 45 cal days
Date Prepared
: December 7, 2015
ERIAL COST
QTY.
UNIT COST
AMOUNT
6.32
25.00
2.00
2.00
162.00
35.00
296.70
1,564.00
1,449.00
20.70
155.25
7,417.50
3,128.00
2,898.00
3,353.40
5,433.75
8.00
29.00
2.00
1,037.30
212.75
166.75
8,298.40
6,169.75
333.50
37,032.30
11,109.69
48,141.99