Sunteți pe pagina 1din 57

OPTIMISING PRODUCTIVITY

IN FOUNDRY
(INDIAN FOUNDRY CONGRESS 2014 AHMEDABAD)
Laxman Sundar, Neosym Industry Ltd., Pune
Email : lysundar@gmail.com

Past Legacies
FOUNDRY IS A COMPLEX PROCESS OF MANY SUB-PROCESSES. THE INTER PROCESS CO-ORDINATION WAS MISSING. THERE IS LACK OF CONCEPT OF
TEAM WORK AND INTERNAL CUSTOMER.
GENERAL TENDENCY IS TO EXPLAIN AWAY THE PROBLEMS. ANALYSIS ENDS
IN FIXING THE BLAME RATHER THAN PROBLEM.
TRADITIONAL APPROACH IS THE ROOT CAUSE OF RANDOM FAILURES AS THE
PROCESSES HAD NO PROACTIVE APPROACH OF PREDICT AND PREVENT .
IT WONT BE WRONG IF WE SAY GOOD RESULTS WERE BY LUCK IN MANY
CASES AND NOT BY TEAM WORK IN ALL PROCESSES COMPLIMENTORY TO A
COMMON GOAL.
OFF LINE AND SUPPORT ACTIVITIES WERE UNAWARE OF RESULTS OF THEIR
INPUTS IN MAIN STRAM PRODUCTION PROCESS.
2

Enemies of productivity
1. Equipment Failures/break downs; poor maintenance reliability
2. Set up and adjustment losses; poor operational reliability
3. Idling and minor stoppages; unplanned deviations in Operation
4. Reduced speed; forced deterioration and natural deterioration
5. Quality defects; design, process variations, poor reliability in
support activities.
6. Lack of team work, domain incompetence result in many
compromises in operations.

SOURCES OF UNRELIABILITY:
A)Operations 30-50%:
- poorly defined operating procedures and training
-ineffective cross functional team working
-lack of measures and targets
-inconsistent operations
-lack of training
B) Assets 30-40%:
-Inaccurate initial specifications
-poor design for maintenance and operations
-change of use and modifications
-Aging or inadequate assets
C) Maintenance 10-30%:
-no or inadequate strategy
-inadequate monitoring/knowledge of conditions
-poor/ no rebuild specifications
- Lack of technical skills / training

New Challenges
Automation demands and helps machine users to trace, track and
handle random component/process parameter failures which
happen in foundry process/sub processes with infinite variables
New operational strategies to maintain and operate the highly
automated assets for better utilization
Change in attitude process approach and team work

Sympathy

Apathy

Empathy
5

New Challenges continued


Everybody in the organization must believe and demonstrate
that they can do better. The need of the hour is to constantly
challenge the status-quo and develop a constructive level of
dissatisfaction with the present performance.
Variation is a basic phenomenon of nature. Controlling
process variations ON LINE is the KEY.
Chance or random causes are inherent sources present in
the system for small day today variables. They also cause
output variability because they themselves are variables.

Structure of Process Approach best to follow


(Basics of ISO/TS, TQM)
- Management Responsibility
* Commitment, Customer focus, Policy, Planning,

Responsibility, Authority & Communication, Review

-Resource Management
* Human Resources, Infrastructure, Work Environment

- Product Realization
* Customer, Design, Purchasing, Operations, Calibration

- Measurement, analysis and continuous improvement


Customer Satisfaction, Audit, Process/Product control,
Non-conforming product, Data Analysis, Improvement

Move from I Say So to real ISO


7

Standard Requirements for Process Approach


Each process should have clear definition of reliability,
sequence and interaction with other processes and the
parameters/activities with tolerances, which need to be
achieved, tracked and monitored .
* Determine the criteria, methods and tolerances needed
to control the inputs and out put of steps/Processes
* Ensure the availability of resources and information
necessary to carryout these processes within tolerances
* Monitor, measure, analyze out put of each process
* Implement actions necessary to achieve results and improve
them preferably online. Track results for effectiveness.
Move from independence to dependence to interdependence

Process Reliability Steps


Development of Process reliability through 5 stages :
1) Clearly Defined process for fulfillment of quality and
quantity of products.
2) Selection and installation of the infrastructure with design
to achieve process parameters within tolerances and
deviation monitoring.
3) Deterioration Preventive plans and back ups.
4) Condition monitoring and correction schedules.
5) Design out provisions, for new instruments, equipment etc.
These basic principles are applicable to all processes including
maintenance as an important process with the degree of
automation deployed. These steps need to be taken while
conceiving the project or need to be introduced in working
plant with adoptation.

Let us dwell on details of PROCESS in stages.


Stage 1: Clearly Defined Process Flow:
-Have clear steps of processes from scrap handling to packing
and dispatch of finished castings with volumes and flow of
activities. Consideration of manufacturability of specific
castings.
-Have clear definition of input and output parameters required
to be monitored in each process and activity.
-Definition of tolerances in each parameter with risk of failures
involved.
-Envisage likely parameters in future to be monitored and make
provisions for inclusion.
-Generally, capacities of all processes from Melting till dispatch
should be telescopically higher to avoid bottle necks.
10

Stage 2: (Infrastructure)
-Select robust equipment with proven track record.
-Select automation to meet immediate envisaged quality/quantity
needs and likely expansions in future.
-Evolve maintenance plan with risk evaluation.
-Keep spares and assemblies to cover likely risks.
-Ensure machine capabilities to meet process requirements
-Ensure facilities to detect deviations in parameters and on line
corrections.
-Erection and commissioning is the best opportunity for training.
-Layouts to ensure adequate facilities to implement modern tools,
safety, lean manufacturing etc, down the stream.
-Scope to reduce maintenance activities by up gradation of design.
11

Stage 3: (Preventive actions during operation)


-Equipment break down results in reactive repair, maintenance is
proactive.
-Preventive actions are for natural wear, carry out religiously.
-Study the failed parts and failures for causes of deterioration.
-Evaluate improved parts or improve schedule of maintenance.
-Evaluate all potential causes of failures of equipment or process
parameters, and correct them on line.
-Check sheets should be kept dynamic considering prevailing
conditions.
12

Stage 4: (condition monitoring and predictive/corrective actions)


-Monitor major parameters on equipment and process daily for
deviations within or outside tolerances and correct on line.
-Track Frequency of repetition and effectiveness of previous actions.
-Keep spares for equipment and instruments, ready in case variations
are in risk zone.
-Major equipment and process parameters have on line monitoring
and correction possible now.
-Daily standing meeting helps in training and informing all.
-Use latest technology available and Andon to trigger actions
- Solutions for quality issues can be with Maintenance and for break
down issues can be with Production. Joint plan of actions is must.

13

Stage 5: (Design out actions)


-When the corrective actions are to be taken frequently and
they dont yield results, we must revisit the earlier design of
process or equipment.
-There might be new conditions which were not envisaged at
the design stage.
-Solutions can be of different types like:
Equipment up gradations
Layout modifications
Small improvements in existing processes or equipment
System Reliability evaluation
-We have introduced new product in the process, which does
not fit or can not be accommodated in our design.

14

COST OF REACTIVE APPROACH

+
COST OF REACTIVE APPROACH

COST OF PROACTIVE APPROACH

Objective Optimize Operating cost. Cost of negligence is


high.

15

Key attributes of an Effective Process Monitoring


Some redundant actions like Preventive maintenance are eliminated
Reducing trend of downtime, rejects and costs as weaknesses in
operation are identified and corrected speedily.
Turning information into value.
Continuous training and contributions of all operating persons on new
technologies and improvements, like tracking effectiveness of actions,
proactiveness etc.
Well identified and documented operations and responsibilities,
procedures etc.
A cooperative environment between all operation processes and
personnel. Results of all actions are complimentary to common goal.
Capital projects are identified correctly to improve Productivity
effectively, reduce cost.
PM and quality check sheets are dynamic; revised periodically referring
the breakdown and preventive maintenance record
16

Bench Marking
Generally, this is a process of comparing our own performance
with the best in Industry.
Dimensions typically measured are Quality, Asset utilization, Time
and Cost.
Continuous improvements from self learning is the best method
to adopt rather than global bench marking. No two foundries have
same set up, skill levels and product portfolio.
We can create a performance tracking sheet on Time scale to
measure our own performance and effectiveness of actions on
day today basis.
Follow Select/measure/analyze/improve/control approach
Bench marking has to start from within and the bench marks
within can be improved from month on month. These bench
marks can be dynamic, like best achievements of one month can
be bench mark for next. They help us to go to perfection in given 17
set up.

Six big losses to be monitored for


A)Down time:
optimization:
1) Equipment failure
2) set up and adjustment

B)Speed losses:
3) Idling and minor stoppages -due to abnormal operation of line
components and lack of co-ordination
4) Reduced speed -due to discrepancies between design and actual speed
of equipment or deration in equipment
C) Defect/Quality Losses:
5) Process defects -due to quality parameters going out of control
6) Reduced yield critical design of process/ tooling/methoding etc, unfit
in given infrastructure.
Sense, predict, evaluate, correct on line and improve, without
compromises. Condition Monitoring deals with on line continuous
monitoring and corrections without unnecessary over doing work.
18

OPTIMIZING APPROACH
-Continuous improved internal bench marking. Do the basics well
and with proactive approach.
-Total understanding of facility by total team with limitations in
operations, maintenance, quality and design.
-Compliance to scheduled work should improve and disaster
management reduce. Compliance of Scheduled work measurement
can be one criteria to improve efficiency.
-Create capacity targets in as is condition, process wise and product
wise as reference. This should be theory based without derations.
Does not matter if your over all foundry yield works out less than
50%. This can be upgraded with improvement actions identified
every month.
- Find out the constraint process in given volumes, products etc.
-Best we can do is exploit the constraint to 100%. All other processes
have to align with even at the cost of under utilization.
19

Operational reliability Pillars


Daily work management: a short standing meeting to analyze failures,
root causes, actions identification, implementation and deviations
Wider definition of all failures: equipment, process , performance,
quality and safety failures .
Departmental reliability teams; team that includes knowledgeable
operators, production and maintenance supervisors. The facilitator
should organize the meetings, keep track of the actions and their
effectiveness, new abnormalities, consumption norms, study with old
historical data, and follow up on new actions status.
Communication to all shifts and feedback confirmation.

20

Company wide team based effort


-All employees are involved and carry out JH activities for team work
and ownership. Better the people interact with the plant and equipment,
better and longer the equipment will run.
-They understand the causes of break downs and defects in relation to their
activities. They need to know what needs to change, when and why.
-Actions are performed while production goes on.
-Effectiveness is monitored of yesterdays actions and notified.
-Historical data is maintained defect, cause and remedy wise and
upgraded daily.
-Job rotation to understand inter linkages in all processes.
- SELECT AND DEVELOP CHANGE AGENTS AND LEADERSHIP
21

CREATE MEASUREMENTS AND


To determine your opportunity
for improvement, we need to know where
TARGETS

we are today.
-Predictive, preventive and reactive maintenance, break up of time spent on
equipments process wise.
-Monitor number of deviations in all processes every day, like maintenance
calls, corrections in process parameters in all processes etc.
-Understand and Establish relationship between inputs and out puts for
effectiveness and track for a reasonable period or cycles. The side effects of
actions need to be understood and co related.
-Each Process out put can be treated as product and inputs raw materials
consumptions (even in weights, numbers is Ok, need not be only in Rs.) per
unit of out put can be monitored as measurement index.
-Out put of one process can be input of other process.
22

Implementation stages
-FIRST DECIDE THE CONSTRAINT PROCESS AND CONSTRAINT NEEDS TO BE
EXPLOITED.
-GENERALLY, FOUNDRIES ARE DESIGNED TO HAVE CAPACITIES TELESCOPICALLY
HIGHER AS WE GO AWAY FROM MELTING TO AVOID BOTTLENECKING IN FLOW.
-TARGET EXPLOITATION OF MELTING CAPACITY SHOULD BE A COMMON GOAL FOR
ALL PROCESS OWNERS, AS IT IS THE NESCENT PRODUCTION IN A FOUNDRY.
CASTINGS GET CONVERTED IN GROSS OR NET GOOD LATER.
-THE CONSUMPTION OF LIQUID METAL DRIVES ALL SUB PROCESSES TO FEED CORES,
SAND, MOLDS, EVACUATION OF CASTINGS THROUGH UP TO SALES, IN TIME.
-ALL OTHER PROCESSES MAY RUN INEFFICIENTLY AS THE CAPACITIES COULD BE
HIGHER, PRODUCT MIX COULD BE FAVOURABLE ETC.
-THE THEORITICAL CAPACITY OF MELTING AS DEMONSTRATED BY SUPPLIER SHOULD
BE THE TARGET. GENERALLY, WE SETTLE DOWN AT WHATEVER WE MAKE AND USE
THAT AS THE REFERENCE FOR EXHIBITING THE PROGRESS.
23

Implementation stages -Contd


PREPERATIONS:
-ENSURE THAT ALL PROCESSES ARE INFORMED OF THE PRODUCTION PLAN WELL
IN ADVANCE TO ACCOMMODATE THEIR LEAD TIMES.
-ENSURE BEFORE HAND THE PRODUCT MIX CAN STRAIN THE MELTING PROCESS.
-ENSURE THAT THE SPECIFIC REQUIREMENTS OF PRODUCTS ARE TAKEN CARE. GO
THROUGH THE LAST RUN OF THE PRODUCT AND DEVIATIONS OBSERVED, ACTIONS
TAKEN AND THEIR EFFECTIVENESS.
-GO THROUGH THE WORK IN PROGRESS INVENTORY, REASONS BEHIND HOLD UPS,
ECONOMICAL BATCH SIZE OF PRODUCTION AND FINISHED GOOD INVENTORY.
-ALIGN AVAILIBILITY OF ALL INPUTS AT MELTING, MOLDING AND CLEARANCES
DOWN THE LINE TO HANDLE THE PRODUCT SMOOTHLY, INCLUDING THE SKILL
LEVELS.

24

DAILY PERFORMANCE REPORTS


We need to consolidate performance at the end of the day.
Best is in the formats where total operating time is
accounted for in TIME BALANCE SHEET FORMAT.
Useful time plus wasted time should be equal to total
operating time.
Useful time can be calculated by out put divided by
theoretical rate of output of the major equipment in the
process. Rest all is wasted time.
Wasted time can be broken down in as many elements as
possible in minute details and categories like equipment
break downs, process delays, quality delays, co-ordination
delays etc.
The delays can be summarized day wise in one sheet for
tracking effectiveness and taking actions.

25

DAILY PERFORMANCE REPORTS - contd


The daily short standing review meeting should include all
level key persons.
Common measurement ( for exploiting the constraint ) is
dispensed metal vs target.
If target is not achieved, analyze reasons and generate new
actions. If achieved, scope to eliminate the delays further
and set new targets.
Some examples of such balance sheets follow.
PERFECTION MINUS ACHIEVEMENT IS THE SCOPE FOR IMPROVEMENT
26

TIME BALANCE SHEET OF MELTING MONTH 1


Date
Production time in Minutes
Target LMT 6MW Power
Actual LMT achieved
Utilization %
Time Lost in minutes
KWH/ T of Liquid metal - Melting
KWH/ T of Liquid metal - Auxiliary

A
1
2
3
4
5
6

Furance trip ON GLD, metal piece


60
Furnace water low pressure / high temparature
trip
vibro charger problem
Magnet Crane - CT Problem
Furance charger supply incomer trip
8T magnet Hot
POURING stopper rod sensor not sensing

Furnace cylinder mounting welding break

Subtotal Maintenance Delays


PROCESS DELAY

1
2
3
4
5
6
7

Metal Delay, capapcity constraint


Metal dispensation
Low temp. metal back
Laddle suspension jam
Metal Delay due Metal leak/GLD
Pouring line stop/Metal Holding
Metal return due to metal spillage on box

8
9

F/C problem metal shifting to furnace B


Furnace Hood Jam
Furnace A trip Srap piece onWCL pipe
connection
Furance Problem metal spillage F/C A.
Metal composition delay
furance jam
furance holding

15

2
630
63
16.5
26.2
465

3
660
66
25.0
37.9
410

4
660
66
19.3
29.3
467

1F
off

1F
off

1F
off

7
960
192
47.5
24.7
723

8
720
144
34.8
24.2
546

9
10
11
14
720 780 720 420
144 156 144 84
44.4 42.3 37.2 19.3
30.8 27.1 25.8 23.0
498 568 534 324

15
900
180
54.4
30.2
628

16
480
96
24.7
25.7
357

17
660
132
36.6
27.7
477

18
660
132
39.3
29.8
463

21
720
144
42.7
29.7
506

22
840
168
54.7
32.5
567

23
780
156
48.1
30.8
540

24
780
156
46.8
30.0
546

25
780
156
49.2
31.5
534

26
540
108
36.0
33.4
360

28
540
108
32.3
29.9
379

29
30
Total Frequency
600 840 16050
120 168 3210
38.1 42.3 863.6
31.8 25.2 26.9
409 628 11428
707
354

Maintenance Delays

10
11
12
13
14

1
660
132
32.1
24.3
500

Pouring nozzle Jam


Subtotal Process delays
Other Dealys
Lunch
Production Plan delayed
Subtotal Other delays
GRAND TOTAL DELAYS

40
31
60

60

224 193 164 207 373 170


95 58 89 69 170 130

34

20

29

49

41

31

60

145
150

212
151

170
132

60

45

32

40

52

25

55

68

43

50

61

45

30

33

0
0
0
0
40

0
0
0
0
1

31

60

191
0

275
151
33

4837
3054
33
0
0
994
0

1
0
0
23
0

30

0
30

0
1

27

0
0
0
0
19

131 290 142 172 214 186 290 230 251 295 158 152 193
68 194 88 130 140 152 195 171 167 175 128 115 136

25

60

35

30

123

50

80

55

30

27

0
0
0
0
1189

458

414

279 571 325 447 422 426 535 487 486 504 319 359 389

609

62
10199

400 373 360 416 702 501

62
417

40

50

50

45

55

30

30

40

40

30

50

60

30

40

20

20

20

23
2

45

55

30

30

40

40

30

50

60

30

40

20

20

20

895
133
1028

324 626 355 477 462 506 565 537 546 534 359 379 409

629

11418

47

113

111 110 160

50

50

20

45

50

50

20

45

50

50

40
81
121

500 465 410 466 722 546

498

568

535

40

40
52
92

87

35

70

90

45

25

23

ACTIONS
A7
B15

Sensor mounting Rod straightned


Removed slag, cause of Jam

A9

Rewlded the cylinder bracket

27

TIME BALANCE SHEET OF MELTING- MONTH 2


Date
Production time in Minutes
Target LMT 6MW Power
Actual LMT achieved
Utilization %
Time Lost in minutes
KWH/ T of Liquid metal - Melting
KWH/ T of Liquid metal - Auxiliary
A
1
2
3
4
5
6
7
8
B
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
C

Maintenance Delays
Furance trip ON GLD, metal piece
Furnace water low pressure / high
temparature trip
vibro charger Problem
Magnet Crane CT Problem
Furance charger supply incomer trip
8T magnet Hot
Pouring stopper rod sensor not sensing
Furnace cylinder mounting welding break
Subtotal Maintenance Delays
PROCESS DELAY
Metal Delay, capapcity constraint
Metal dispensation
Low temp. metal back
Laddle suspension jam
Metal Delay due Metal leak/GLD
Pouring line stop/Metal Holding
Metal return due to metal spillage on box
F/C problem metal shifting to furnace B
Furnace Hood Jam
Furnace A trip Srap piece onWCL
Furance Problem metal spillage F/C A.
Metal composition delays
furance jam
furance holding
Pouring stopper rod /nozzle Jam
Pouring basin checking for slag

7
480
96
22
###
369

8
760
152
38
24.8
571

9
700
140
33
23.8
533

10
600
120
23.7
19.7
482

11
735
147
35.1
23.9
560

12
700
140
41
29.2
496

13
770
154
33.2
21.6
604

14
943
189
50
26.5
693

15
751
150
40
26.4
553

16
810
162
41.1
25.4
605

18
866
173
50.2
29.0
615

19
919
184
46
25.0
689

20
480
96
34.4
35.8
308

21
840
168
43.2
25.7
624

22
840
168
51.1
30.4
584

23
920
184
40
21.6
722

25
500
100
27
27.0
365

26
660
132
35.8
27.1
481

27
806
161
44
27.0
588

28
768
154
48
31.4
527

29
838
168
21
12.4
734

30
768
154
50
32.5
518

40

25
10
0

40

60
60

25

10

173 302 222 145 285 334 335 279 196 238 211 220 225
80 135 119 84 130 135 120 180 145 138 179 164 25
28
25
21

149 247 270 170


154 182 141 74
24 58
19

265
49

160 255 170 243


70 70
20 35

30

85

70

237

60

30

50

62

27

25

64

60

74

55

40

39

46

78
36

61

98

330 142

6
45
40

25

55

100

30

30

25
110

70

40

90
42

15

15
40

120

50

138

Subtotal Process delays


Other Dealys
Lunch
Production Plan delayed
Plasma trail
Subtotal Other delays

323 522 426 379 507 496 583 633 496 490 541 608 289

547 533 565 324

434

45

65

105

60

50

30

30

45

65

105

60

50

30

30

GRAND TOTAL DELAYS

368 587 531 479 557 496 603 693 546 600 571 688 309

619 578 715 354

464

20

60

50

50

30

80

20

60
12

45

20

60

50

50

30

80

20

72

45

150
150

60
50
60

30
50

Total Freq
16454
3291
847
25.7
12219
0
0
0

0
40
0
0
25
10
60
135

0
1
0
0
1
1
1
4

5094
2325
279
0
0
1763
36
0
0
0
6
100
0
890
280

22
19
9
0
0
22
1
0
0
0
1
4
0
15
4

567 458 635 385 10741

10

30

35
45

40
70

45

885
12
225
45 28
1122

567 528 715 430 11998

19
1

TIME BALANCE SHEET OF MELTING- MONTH 2

Date

Tot Fre
7 8 9 10 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 al q

ACTIONS
A
3 Cleaned the metal on
Track
1) Forward limit switch
setting adjusted . 2)
A New braket fabricated
8 & welding done

29

TIME BALANCE SHEET OF MELTING MONTH 3

2
3
4

Date
Production time
Target LMT 6MW Power
Actual LMT achieved
Utilization %
Time Lost in minutes
KWH/ T of Liquid metal - Melting
KWH/ T of Liquid metal - Auxiliary
Maintenance Delays
Furance trip ON GLD, metal piece
Furnace water low pressure / high
temparature trip
vibro charger problem
Magnet Crane - CT Problem

5
6

Furance charger supply incomer trip


8T magnet Hot

SERT stopper rod sensor not sensing

9
B
1
2
3
4
5
6

Furnace cylinder mounting welding break


Subtotal Maintenance Delays
PROCESS DELAY
Metal Delay, capapcity constraint
Metal dispensation
Low temp. metal back
Laddle suspension jam
Metal Delay due Metal leak/GLD
Pouring line stop/Metal Holding

Metal return due to metal spillage on box

8
9

F/C problem metal shifting to furnace B


Furnace Hood Jam
Furnace A trip Srap piece onWCL pipe
connection

A
1

10
11
12
13
14
15
16
18
C

Furance Problem metal spillage F/C A.


Metal composition delay
furance jam
furance holding
Pouring stopper rod /nozzle Jam
Pouring basin checking
Sintering delay
Subtotal Process delays
Other Dealys
Lunch
Production Plan delayed
Plasma trail
JH Activities

1
0.0

2
768
153.6
50.0
32.5
518

3
934
186.8
43.6
23.4
716

4
740
148.0
43.1
29.1
525

5
644
128.8
41.3
32.0
438

6
300
60.0
0.0
0.0
300

0.0

0.0
0.0

87

87

233
179

217
189

201
177

169
119

9
930
186.0
59.0
31.7
635

10
950
190.0
63.9
33.6
631

11
0.0

12
960
192.0
74.8
39.0
586

13
960
192.0
68.0
35.4
620

14

15

0.0

0.0
0

16
820
164.0
60.7
37.0
517

17

18
870
174.0
74.5
42.8
497

115
109

282
155

30

228
210

272
240

206
200

251
201

36

10
21

30

25
60

264
80

44
10

342

472

680

429

40

30

15

347

177

57

105

105
45

60
571

614

586

617

511

497

10

Subtotal Other delays

40

30

15

10

GRAND TOTAL DELAYS

512

710

444

429

571

624

586

617

511

497

Total
8876
1775.2
578.9
32.6
5982
702
326

Frequenc
y
11
27.0
12.0
1.0

0
0
0

0
0
0

0
95

0
1

0
95

0
2

2174
1779
0
66
0
0

10
10
0
2
0
0

10

51
0

2
0

0
25
0
1159
135
0
60
5319

0
1
0
8
3
0
1
28

95
0

4
0

95

28

550130

23

S.NO.

A
1
2
3
4
5
6
7
9
B
1
2
3
4
5
6
7
8
9
10
11
13
15
16
17
18
C

MONTH
Production time
Target LMT at rated Power
Actual LMT achieved
Utilization %
Time Lost in minutes
KWH/ T of Liquid metal - Melting
KWH/ T of Liquid metal - Auxiliary
Maintenance Delays
Furance trip ON GLD, metal piece
Furnace water low pressure / high temparature trip
vibro charger problem
Magnet Crane CT Problem
Furance charger supply incomer trip
8T magnet hot
SERT stopper rod sensor not sensing
Furnace cylinder mounting welding break
Subtotal Maintenance Delays
PROCESS DELAY
Metal Delay, capapcity constraint
Metal dispensation
Low temp. metal back
Laddle suspension jam
Metal Delay due Metal leak/GLD
Pouring line stop/metal holding
Metal return due to metal spillage on box
F/C problem metal shifting to furnace B
Furnace Hood Jam
Furnace A trip Srap piece onWCL
Furance Problem metal spillage F/C A.
Metal composition delay
furance holding
Pouring stopper rod /nozzle Jam
Pouring basin checking
Sintering delay

1
16050
3210
864
26.9
11428
707
354

2
16454
3291
847
25.7
12219
723
358

3
8876
1775
579
32.6
5982
702
326

60
0
0
0
0
40
31
60
191

0
0
40
0
0
25
10
60
135

0
0
0
0
0
95
0
0
95

4837
3054
33
0
0
994
0
0
30
0
0
0
1189
62

5094
2325
279
0
0
1763
36
0
0
6
100
0
890
280

2174
1779
0
66
0
0
10
51
0
0
0
25
1159
135
0
60

Subtotal Process delays


Other Dealys
Lunch
Production Plan delayed
Plasma trials
Subtotal Other delays
GRAND TOTAL DELAYS

10199

10741

5319

895
133

885
12
225
1122
11998

95
0
0
95
5501

1028
11418

Melting Summary FOR 3 MONTHS


4
5 6 7
8
9
10

11

12

Year

31

S.NO.

A
1
2
3
4
5
B
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

MONTH
Production time
Target LMT at rated Power
Actual LMT achieved
Utilization %
Time Lost in minutes
KWH/ T of Liquid metal - Melting
KWH/ T of Liquid metal - Auxiliary
Maintenance Delays
Furance trip ON GLD, metal piece
vibro charger problem
8T magnet hot
SERT stopper rod sensor not sensing
Furnace cylinder mounting welding break
Subtotal Maintenance Delays
PROCESS DELAY
Metal Delay, capapcity constraint
Metal dispensation
Low temp. metal back
Laddle suspension jam
Pouring line stop/metal holding
Metal return due to metal spillage on box
F/C problem metal shifting to furnace B
Furnace Hood Jam
Furnace A trip Srap piece onWCL
Furance Problem metal spillage F/C A.
Metal composition delay
furance holding
Pouring stopper rod /nozzle Jam
Pouring basin checking
Sintering delay

1
2
3
16050 16454 8876
3210 3291 1775
864
847
645
26.9 25.7 36.33
11428 12219 5982
707
723
680
354
358
263

Subtotal Process delays

10199 10741 5319

60
0
40
31
60
191

0
40
25
10
60
135

0
0
95
0
0
95

4837
3054
33
0
994
0
0
30
0
0
0
1189
62

5094
2325
279
0
1763
36
0
0
6
100
0
890
280

2174
1779
0
66
0
10
51
0
0
0
25
1159
135
0
60

Melting Summary- contd


4 5 6 7 8 9 10

11 12

Year

32

Melting Summary- contd


S.NO
.

MONTH

Other Dealys

16

Lunch

895

885

95

17

Production Plan delayed

133

12

18

Plasma trials

225

1028 1122

95

Subtotal Other delays


GRAND TOTAL DELAYS

5 6 7 8 9 10 11 12

Year

11418 11998 5501

ACTIONS
B13

Sensor mounting Rod bent,


straightned
Removed slag, cause of Jam

A5
A2

Rewelded the cylinder bracket


Cleaned the metal on Track

A3

1) Forward limit switch setting


adjusted . 2) New braket fabricated
& welding done

A4

33

Month-1 MOLDING TIME BALANCE SHEET

Date
Production time
Target of mould
Actual moulds
poured
Utilization %

11

15 16

17

18

21

22

23

28

Freq
uenc
30 Total y

660

630 660 660

935

893 935 935 1360 1020 1020 10201275 680 935 935 1020 1190 1105 765 1190 22780

165

109 81

132

960 720 720 720 900 480 660 660 720 840 780 540 840 16080

268 187 234 173 297 137 188 211 230 286 237 178 289 4700

17.6 12.2 8.7 14.1 19.7 18.3 22.9 17.0 23.3 20.1 20.1 22.6 22.5 24.0 21.4 23.3 24.3 20.6

Time Lost in minutes

544

553 603 567

771 588 555 598 690 383 527 511 558 638 613 414 636 12762

Moulds made

177

116 85

291 188 250 185 305 138 190 215 246 294 240 178 302 4911

Bad moulds

12

134
2

23

16

12

16

23

222

Mixer batches- Total

2044

Bntonite
consumption T

32.77

Lustron Consumption
T

21.55
34

Month-1 MOLDING TIME BALANCE SHEET

A
1
2
3
4
5

6
7
8

Date
Maintenance Delays
VW1 positinal control missing
VW3 position control missing
ZL actual value stop lowering to
flask closing position
TZ6 cylinder position missing
TZ2 interlock forward missing
Shake out trip ( relay voltage
drop)/Motion control 1
/Emergency stop
FM lifting frame problem
FM lift HNC fault / working door
safty Ckt problem

11

15

16

17

18

21

13
14
15
16

TZ1 forward interlock ok missing /


forward position not reached
LSV safty flap missing
AS flask control missing / ALL AS
problem
19
TZ5/DZ6 cushioning missing
20
21
22

TZ5/DZ6BACK 100 position missing


TZ6/DZ5 gap position missing

28

Total

Freque
ncy

7
93

2
3

19
15
5

3
1
3

68
48

3
1

16
8

1
1

150
7

1
1

32

13

69

18
5

3
1

0
9

0
1

90

30

43
9

15
2

64
48

16
8

AR2 in position missing /Hyd. OFF IN KB1 , box shifted out of track
JVM pallet control missing
TZ4 actual value forward positon
missing
Fm lift frame control 1 missing/
frame right missing
ZL clamping missing , so only drag
box take up
TZ1 forward interlock ok gap
missing

17
18

23

5
48

9 Clamping device right close missing


10
Actual value high pressure off
11
12

22

150
7
28
3

2
4

10

2
2

9
90
15

12

35
15

Month-1 MOLDING TIME BALANCE SHEET

23
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42

Date
Filling frame control right
missing
Squeeze piston rams groove
edge bolt broken .
Tz5/Dz4actual valve forward to
cashoning pas missing
Tz5/Dz4 actuaL Position control
missing
BUR right up missing
DZ2 actual value pull missing
FM Squeeze position not
reached
Aearetor 1 rod broken
VW4 position control missing
US1 stop lifting to take over
position
DZ6 actual value pull position
missing

Frequ
ency

16

42

126
0
0

2
0
0

0
0
0

0
0
0

26

26

0
17
4

0
2
1

920

11

15

16

17

18

21

22

23

28

30

13
42

93

33

WE2 0 position missing


JVH24 hydraulic pipes oil
leakage
BAS backward slow / Forward
missing Oil lekage
DZ5/TZ6 actual value pull
position missing
VW1 log distance positioning
missing
VW3 pallet control missing
Forward flow stop missing
TZ4/DZ5 actual valve forward to
cushioning missing
Subtotal Maintenance
delays

Total

70

111

90

155

124

33

24

61

45

10

26

45

21

36

Month-1 MOLDING TIME BALANCE SHEET

B
1
2
3
4
5
6
7
8
9
10
11
12
13
14

1
2
3
Date
PROCESS DELAY
Metal not ready and transfer
time
299 180 259
20
22 47
Core setting line stop
Spillage iron detection
Programme selection mistake
by operator
Core setting fixture problem
Pattern correction work
Core fixture pin Problem
Chills not available
Wrong selection of bolster by
operator
FM Working door open
47
42 49
S4 block mould trail
Line stoppage before punch
out
Stoppage for mold validation 16
13 42
Insertion of heat code

167 448
38 43
13

300
31

295
26

11

15

16

17

18

21

22

23

28

30

302 434 225 283 331 249 385 383 267 426
41 32 60
5
30 63 40 39 12 38
50

19
52

70

63

64

67

58

30

3
62

51

120
51

60

70

46

60

Frequ
Total ency

7186
772
18

23
23
2

50
0
0
0
22

1
0
0
0
2

120
1200
30

32
426
27

1
20
2

417
0

22
0

32

17
10

30
17

34

32
12

27

30

25

25

56

10

28

319 626

466

475

464 579 334 420 457 501 547 516 351 564 10300

45

45

40

50
81

40

10

15

85

50

131

GRAND TOTAL DELAYS 560 547 600 554 765

584

549

595 690 381 525 509 557 639 611 413 635 12705

15 metal Return and restart time 6


30 30
16
Weigment dosing
Subtotal Processd
elays
17
388 287 427
Other Dealys
C
1
Lunch
45
60 50
2
Production Plan delayed
52
3
Sand delay
57
37 33
Subtotal Others delays 102 149 83

15

35
80

50

50

10

20

10

25

30

40

15

20

45

60

45

45

18

30

24

14

14

32

12

23

40

50

45

16

46

66

50

60

50

965
133
365

60

50

1463

23
2
14

37

Month-1 MOLDING TIME BALANCE SHEET

Date
ACTIONS
Adjusted JVM with gap
between Trolley pallet & Box
of locating device is not less
than 15mm. Tightened the
bolt.
A 27
A2

A 11
A3

11

15

16

17

18

21

22

23

28

30

Frequ
Total ency

JVM mechanical locks bolt


tightening done.
All sensors tightening of
pattern change stations
done.& added into monthly
Check sheet

Ferrule of the pipe was


changed to arrest the leakage.

A7-A
23

Twin press programme


verified .

A 25

Replaced broken bolt with


new

A9

Sensor mounting rod slightly


slant, plate provided .

A 21

1) Adjust the magnet and


scale with distance between
them 4-7 mm . 2) Add in
monthly check
point.3)Tightened all scale
and transduser holding
bracket bolts. 4)Replace the
magnet.

38

TIME BALANCE SHEET OF MOULDING SHOP FOR MONTH 2

A
1
2
3
4
5
6
7

Date

11

12

13

14

18

19

20

22

26

27

30

Total

Production time
Target of mould
Actual mould poured
Utilization %
Time Lost in minutes
Moulds
Bad moulds
Mixer batches- Total
Bntonite consumption T
Lustron Consumption T
Maintenance Delay
VW1 positinal control missing

480
680
121
17.8
395
135
14

760
1077
196
18.2
622
203
7

735
1041
184
17.7
605
190
6

700
992
238
24.0
532
243
5

770
1091
234
21.5
605
269
35

945
1339
293
21.9
738
298
5

866
1227
260
21.2
682
277
17

919
1302
296
22.7
710
323
27

480
680
217
31.9
327
221
4

840
1190
347
29.2
595
353
6

660
935
198
21.2
520
238
40

806
1142
246
21.5
632
276
30

768
1088
345
31.7
524
350
5

16456
23313
5144
22.1
12825
5505
361
2076
32.7
20.3

VW3 position control missing / pallet control

ZL actual value stop lowering to flask closing position


/stop lower
TZ6 cylinder missing
TZ2 interlock forward missing / forward push not
done
Shake out trip ( relay voltage drop)/Motion control 1
/Emergency stop
FM lifting frame problem

13

8 FM lift HNC fault / working door safty Ckt problem

14

27

27

15

37

Lift cylinder Clamping device right close missing

10
11
12

Actual value high pressure off


AR2 in position missing
JVM pallet control missing

0
0
0

0
0
0

13

TZ4 actual value forward positon missing

14

Fm lift frame control 1 missing/ Cylinder started with


drag box

36

15

ZL clamping missing , so only drag box take up

16

18
19
20
21
22
23

TZ1 forward interlock ok gap missing


TZ1 forward interlock ok missing gap missing /
forward position not reached
LSV safty flap missing
AS lift cylinder 90mm position not reached
TZ6/DZ5 cushioning missing
TZ6/DZ5 BACK 100 position missing
TZ6/DZ5 gap position missing
Flask control right missing

0
22
0
0
0
19

0
1
0
0
0
1

25

Squeeze piston rams groove edge bolt broken .

17

37

Frequenc
y
22
22
22
22.0
22
22
22

22

39

TIME BALANCE SHEET OF MOULDING SHOP FOR MONTH 2


Total

Freque
ncy

27 Tz5/Dz4 actuaL Position control missing

28

BUR right up missing

39

29
30
31

DZ2 actual value pull missing


FM Squeeze position not reached
Aearetor 1 rod broke

21
26
51

2
2
1

32

VW4 position control not done /


position control missing

26

33

US1 stop lifting to take over position /


gripper control missing

34

DZ6 actual value pull position missing

35

WE2 0 position missing

39

36

JVH24 hydraulic pipes oil leakage

54

37

721 safty module channel fault

38

Box locating bush came out

47

39

BAS bacKward slow missing / Forward


missing Oil lekage

24

40

DZ5/TZ6 actual value pull position


missing

41

VW1 log distance positioning missing

42

VW3 pallet control missing

18

43

TZ4/DZ5 actual valve forward to


cashoning pas missing

567

42

Date
26

11

12

13

14

18

19

20

22

26

27

30

Tz5/Dz4actual valve forward to


cashoning pas missing

Subtotal Maintenance delays

18

25

2
5
39

47
7

10

15

43

28

17

16

14

76

10

51

15

40

TIME BALANCE SHEET OF MOULDING SHOP FOR MONTH 2


Date
B
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17

PROCESS DELAY
Metal not ready and transfer
216
time
Core setting line stop
33
Spillage iron detection
Programme selection mistake
by operator
Core setting fixture problem
Pattern correction work
Core fixture pin Problem
Chills not available
Wrong selection of bolstaer by
operator
FM Working door open
39
S4 / Avtek block mould trail
Line stoppage before punch out
Stoppage for mold validation 30
Insertion of heat code
metal Return and restart time
+ Composition not ok
Weigment of dosing
Pattern change
Subtotal Process delays

11 12 13

14

18

19

20

22

26

27

30 Total

Frequ
ency

400 360 386 430 460 400 423 205 343 318 235 328 7402

22

44
5

772
61

22
12

27

0
96
0
46

0
5
0
1

48 37 40
6
7

20

49
7

47
8

26

48
5

12
2

35

30
3

42

13

60

63 64 38

87

59

68

48

67

52

77
61

22

54 22 24

26

28

42

19

37

16

25

10

23

24

46

58

18

19

28

35
4

71 1224
61
0
508
0

22
1
0
21
0

467

16

67

41
318 541 554 509 587 655 566 641 286 540 437 526 451 10664 28

TIME BALANCE SHEET OF MOULDING SHOP FOR MONTH 2


Date
C
1
2
3
4
5

D
1
2
3

Other Dealys
Lunch
Production Plan delayed
Sand delay
Pouring basin checking
Line stop due to taken F/c sintesing

11

12

13

14

18

19

20

22

26

27

30

Total

Frequenc
y

45

45

50

30

30

60

50

80

30

40

50

30

45

35

15

10

30

46

25
60

935
0
456
60
285

22
0
16
1
4

24

60
45

69

50

30

36

95

65

90

60

86

50

115

110

1391

43

GRAND TOTAL DELAYS

406

638

621

555

627

764

707

741

348

630

538

656

561

13034

28

Sand plant problem

Cooler dust conveyor Problem


Mixer gate closing problm
200 group and Bucket elevator
ACTIONS
1) Balancing done by fixing all rods. 2) One Flap
side Belt connected

D1

Filter dust with more moisture. Cleaned

D2

The probe was stuck in up position. The bushing


missing circlip provided. Added point in check list

A 35

1)Encoder wire checking . 2) Encoder tightning checking


and it added into the monthly checksheet .

A 11

All sensors tightening of pattern change stations


done.& added into monthly Check sheet

A 14

1) Cleaned Heat exchanger 2) Changed control oil


servo filter. 3)Adjusted filling frame sensor.
4)Reduced the speed.

D3

Subtotal Others delays

A 31

A8

1)Train the operator for changing the bolster.2)


Cover the sensor with plate to avoid breakage. 3)
Additional sensor provided.
1)Tightened all buckets. 2)Fix the broken bucket
with new joint.3)adjust the discharge gate.

A 29 Protection provided between boxes while pouring.


A9
A 38

The plate was provided


Poor workmanship while installation of line.
Tighteneing & inspection in weekly check list

42

Molding Time balance sheet Month - 3


Date

10

12

13

16

18

Total

Production time

768

934

740

644

930

950

960

960

820

870

8576

Target of mould

1088

1323 1048

912

1318

1346

1360

1360

1162

1233

12149

Actual mould achieved

345

305

212

292

277

327

447

438

403

415

3461

Utilization %

31.7

23.1

20.2

32.0

21.0

24.3

32.9

32.2

34.7

33.7

28.5

Time Lost in minutes

524

719

590

438

734

719

644

651

536

577

6133

Moulds

350

332

216

293

280

413

469

485

436

509

3783

27

86

22

30

34

64

276

Bad moulds
Mixer batches- Total

1378

Bntonite consumption T

34.6

Lustron Consumption T
A Maintenance Delay

15.00

ZL actual value stop lowering to flask


3 closing position /stop lower

Shake out trip ( relay voltage drop)/Motion


control 1 /Shakeout problem

49

33

FM lift HNC fault / working door safty Ckt


8 problem
10 Actual value high pressure off
11 AR2 in position missing
Tz5/Dz4actual valve forward to cashoning
26 pas missing
29 DZ2 actual value pull missing

57

108
1
20

Freq

49

33

59

108

39

30 FM Squeeze position not reached

43

Date
Production time
Target of mould

VW4 position control not done / position


32 control missing
US1 stop lifting to take over position / gripper
33 control missing
34 DZ6 actual value pull position missing
39 KEV problem
40 DZ1 back position missing
41 ZE roller conveyor missing
BAS bacKward slow missing / Forward missing
42 Oil lekage
44 VW3 pallet control missing
Subtotal Maintenance Delay
B PROCESS DELAY
1 Metal not ready and transfer time
2 Core setting line stop
3 Spillage iron detection
5 Core setting fixture problem
6 Pattern correction work
7 Core fixture pin Problem
9 Wrong selection of by operator
10 FM Working door open
11
12
13
14
15
16
17
18
19
20

2
768
1088

3
934
1323

5
644
912

Molding Time balance sheet Month - 3


9
10
12
13
16
930
950
960
960
820
1318
1346
1360
1360
1162

18
870
1233

Total
8576
12149

Freq

1
1
3

35

4
17
4
10
35

6
3
73

2
2

54

10

20
13
394

438
5

356
23

289
21
2

332
25
5

77

96

55

109

3161
254
26
59
25
46
9
763

10
9
7
1
1
2
2
10

14

45

107

53

17
15

21

120
225
15

2
9
1

10

33
456

3
2
3
2
2

537

40
36
24
95
48
5005

2
4
2

10

4
6

14
4

171

325

337
4
4

10
18
220
26

28

33

142
17
5

359
72
3

363
61
4
59

33

13

58

107

25
4
71

5
44

S4 / Avtek /JD8 /JD15 trail block mould trail


Line stoppage before punch out/ (stopper rod
cut+innoculation pipe jam)
Stoppage for mold validation
Insertion of heat code
metal Return and restart time + Composition
not ok
Weigment of dosing
Pattern change
No metal ( melting B/D)
Core not ready
Subtotal Process Delay

4
740
1048

61

65

81

39

110
14

10
5

28

17

21
2

31
2

5
87

403

486

490

386

20
8
15
596

629

529

537

2
1

44

Molding Time balance sheet Month - 3


Date

C
1
4
5
6

10

12

13

16

18

40

30
32

45
7

30
23

50
15

40
7

30
5

40
2

52

34

35
637

5
42
633

52
518

34
572

Total

Freq

305
177
60
16
482
5989

8
9
1
1

Other Dealys
Lunch
Sand delay
Line delay due to F/c sintering
Hydraulic off ( Oil circulation)

Subtotal Others delays


GRAND TOTAL DELAYS
D
Sand PLANT PROBLEM
4
Mixer dosing problem
ACTIONS
Switch made ready & 100 group
D 3 started
Done Welding of the bracket.Add
A 6 in monthly in monthly check sheet
A30-DZ2 & DZ6 cushioning adjust (46-50
A36 mm)

60
11
100
507

62 52 53 65
719 560 445 689

47
709

45

SUMMARY OF MOLDING BALANCE SHEETS


MONTH
Production time
Target of mould
Actual mould Poured
Utilization %
Time Lost in minutes
Moulds
Bad moulds
Mixer batches- Total
Bentonite consumption T
Lustron Consumption T

9 10 11 12

Total

16080
16456
8576
22780 23312.7 12149.3
4700
5144
3805
20.6
22.1
31.32
12762.4 12824.9 6132.94
4911
5505
3783
222
361
276
2076
2044
1378
32.7
32.77
34.6
20.3
21.55
15.00

Maintenance Delay

1
2

VW1 positinal control missing


VW3 position control missing / pallet control

7
93

14
27

0
0

ZL actual value stop lowering to flask closing


position

19

27

49

TZ6 cylinder missing

15

TZ2 interlock forward missing / forward push not


done

15

68
48
0
16
8
150

0
0
0
37
0
0

33
0
59
0
0
108

6 Shake out trip ,Motion control 1 /Emergency stop


7
FM lifting frame problem
8 FM lift HNC fault / working door safty Ckt problem
9
Clamping device right close missing
10
Actual value high pressure off
11
AR2 in position missing

46

12
13
14
15
16
17
18
19
20
21
22
23
25

MONTH
JVM pallet control missing
TZ4 actual value forward positon missing
Fm lift frame control 1 missing/ frame right missing
ZL clamping missing , so only drag box take up
TZ1 forward interlock gap missing
TZ1 forward interlock gap missing /position not
reached
LSV safety flap missing
AS lift cylinder 90mm position not reached
TZ6/DZ5 cushning missing
TZ6/DZ5 BACK 100 position missing
TZ6/DZ5 gap position missing
Filling frame control right missing
Squeeze piston rams groove edge bolt broken .

26 Tz5/Dz4actual valve forward to cashoning pas missing


27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44

Tz5/Dz4 actuaL Position control missing


BUR right up missing
DZ2 actual value pull missing
FM Squeeze position not reached
Aearetor 1 rod broke
VW4 position control not done / position control
missing
US1 stop lifting to take over position
DZ6 actual value pull position missing
WE2 0 position missing
JVH24 hydraulic pipes oil leakage
721 safty module channek fault
Box locating bush came out
KEV problem
DZ1 back position missing
ZE roller conveyor missing
BAS bacKward slow missing / Forward missing Oil
lekage
DZ5/TZ6 actual value pull position missing
VW3 pallet control missing
Subtotal of Maintenance Delay

1
7
32
13
0
69

SUMMARY OF MOLDING BALANCE SHEETS-CONTD


2
3
4
5
6 7 8 9 10 11 12
0
0
0
0
36
0
3
0
0
0

18

5
0
9
90
15
16
42

0
22
0
0
0
19
0

0
0
0
0
0
0
0

126
0
0
0
0

0
39
21
26
51

0
0
39
0
0

26

0
0
0
0
0
0
0
0
0

9
5
39
54
8
47
0
0
0

4
17
0
0
0
0
4
10
35

24

20

26
17
920

0
18
567

0
13
394

Total

47

MONTH
B
1
4
6
7
8
9
10
11
13
14
15
16
17
18
19
20
21
22
23
D
1
2
3
4
5
6

PROCESS DELAY
Metal not ready and transfer time
Core setting line stop
Spillage iron detection
Programme selection mistake by operator
Core setting fixture problem
Pattern correction work
Core fixture pin Problem
Chills not available
Wrong selection of (bolstaer) by operator
FM Working door open
S4 block mould trail
Stopper rod cut+innoculation pipe jam
Stoppage for mold validation
Insertion of heat code
metal Return and restart time
Weigment of dosing
Pattern change
No metal ( melting B/D)
Core not ready
Subtotal of Process Delay
Other Dealys
Lunch
Production Plan delayed
Sand delay
Pouring basin checking
Line stop due to taken F/c sintesing
Hydraulic off( Oil circulation)
Subtotal of Others Delay
Grand Total Delay

SUMMARY OF MOLDING BALANCE SHEETS- CONTD


2
3
4
5
6 7 8 9 10 11 12

7186
772
18
50
0
0
0
22
120
1200
30
32
426
27
417
0
0
0
0
10300

7402
772
61
27
0
96
0
46
0
1224
61
0
508
0
467
0
0
0
0
10664

3161
254
26
0
59
25
46
0
9
763
107
120
225
15
40
36
24
95
48
5005

965
133
365
0
0
0
1463
12705

935
0
456
60
0
0
1391
13034

305
0
177
0
60
16
482
5989

Total

48

MONTH

SUMMARY OF MOLDING BALANCE SHEETS-CONTD


2
3
4
5
6
7
8
9

10 11

12

Total

Actions taken
A27

Adjusted JVM with gap between Trolley pallet & Box of locating device
is not less than 15mm. Tightened the bolt.

A2

JVM mechanical locks bolt tightening done.

A11

All sensors tightening of pattern change stations done.

A3

Ferrule of the pipe was changed to arrest the leakage

A7

Twin press programme verified .


Replaced broken bolt with new

Sensor mounting rod slightly slant, plate provided .

A 25,
A23
A9

1) Adjust the magnet and scale with distance between them 4-7 mm .
2) Add in monthly check point.3)Tightened all scale and transduser
A 21
holding bracket bolts. 4)Replace the magnet.
A31

1) Balancing done by fixing all rods. 2) One Flap side Belt connected

Filter dust with more moisture. Cleaned


The probe was stuck in up position. The bushing missing circlip
D2
provided. Added point in check list
1)Encoder wire checking . 2) Encoder tightning checking and it added
A35
into the monthly checksheet .
1) Cleaned Heat exchanger 2) Changed the control oil servo filter.
A 14
3)Adjusted filling frame sensor. 4)Reduce the speed.

D1

A8
D3
A 29

1)Train the operator for changing the bolaster.2) Cover the sensor with
plate to avoid breakage. 3) Additional sensor provided.
1)Tightened all buckets. 2)Fix the broken bucket with new
joint.3)adjust the discharge gate.
Protection provided between boxes while pouring.

A9

The plate was provided


Poor workmanship while installation of line. Tighteneing & inspection
A 39
in weekly check list

D3

Switch made ready & 100 group started that time it start.

A6

Done Welding of the bracket.Add in monthly in monthly check sheet

A30A36

DZ2 & DZ6 cushoning adjust (46-50)

49

TREND OF BENEFITS
POWER CONSUMPTION TREND (KWH/T Liquid Metal)
800
700

722

678

680

600
500
400

Melting
327

340
263

300

Auxilary

200
100
Month 1

Month 2

Month 3

50

TREND OF BENEFITS

3500

3291

3210

3000
2500
1955

2000

Target LMT

1500
1000

27 %

864

84726 %

33 %

Actual LMT

645

500
0
Month 1

Month 2

Month 3
51

TREND OF BENEFITS
Moulding time Utilization %
35

31.32

30
25
20

20.6

22.1
Moulding time Utilization
%

15
10
5
0
Month 1

Month 2

Month 3
52

EXAMPLE OF DAILY WORK MANAGEMENT MEETING

53

EXAMPLE OF DAILY WORK MANAGEMENT MEETING

54

EXAMPLE OF DAILY WORK MANAGEMENT MEETING

55

CONCLUSIONS
BALANCE SHEET HELPS IN LEAVING NOTHING TO
SUBJECTIVITY
DAILY WORK MANAGEMENT STANDING MEETING HELPS AS
CFT AND DELEGATES ACCOUNTIBILITY
PROVOKES THOUGHT PROCESS TO RESOLVE UNSEEN
PROBLEMS AND GO TOWARDS PERFECTION
CAN HELP IN ESTABLISHING INTER PROCESS RELATIONS AND
TEAM WORK
WE CAN CREATE BALANCE SHEETS FOR MATERIAL
CONSUMPTION, REJECTIONS AND TYPES LIKE GENERIC AND
SPECIFIC REASONS ON DAY TODAY BASIS.

56

THANK YOU

57

S-ar putea să vă placă și