SOCIEDAD MINERA CERRO VERDE

BASIS SCHEDULE
CERRO VERDE PRODUCTION UNIT
EXPANSION

January 2015

BASIS SCHEDULE
1. INFORMATION OF THE PROJECT
Name of the Project:
Contract Code:
Start date:
End Date:
Term
Man Hours:

Local Assembly of Trickling Filters Media Modules.


K-168
September-2014
April-2015
214calendar days
92675 HH

2. SCOPE OF THE WORK


The scope of the work is shown with the code WBS in the following graphic:

3. STRUCTURE OF THE EXECUTION


This part shows considerations such as established Schedule, histogram of manpower,
quantity of modules to produce, sequence of the work, etc.

It is considerated as Work Schedule from Monday to Saturday, from 06:00hrs to


17:00hrs, having one hour (01) for launch, from 12:00hrs to 13:00hrs, such as the
following graphic shows:

The Schedule of the Project does not considerate the delays concerning to security,
problems with the community, changes of engineering, additional works, delay in
provision by SMI, weather aspects, strikes of the workers, interruption of Works due to
the transit of vehicles in the site.
The schedule considerate the following principal activities:
ActivityName

Original
Duration

WBS: Local Assembly of TricklingFilter Media Modules

181

Activity ID

WBS: HITOS DEL PROYECTO


K168-ME-HG10
K168-ME-HG20

181

Inicio del Proyecto (Start)

Fin del Proyecto (End Project)

WBS: GESTIN

59

WBS: FABRICACIN Y MONTAJE - GALPON METALICO

59

WBS: INGENIERIA

28

WBS: SUMINISTROS

35

WBS: SUMINISTROS IMCO

35

WBS: FABRICACIN

27

WBS: TIJERALES

12

WBS: COLUMNAS
WBS: VIGAS - VIGUETAS

6
11

Start

Finish

15-sep14
15-sep14
15-Sep14*

15-Apr15
15-Apr15

15-sep14
20-oct14
20-oct14
01-Nov14
01-Nov14
10-nov14
10-nov14
14-nov14
10-nov14

15-Apr15
21-nov14
27-Dec14
20-nov14
11-Dec14
11-Dec14
10-Dec14
22-nov14
20-nov14
21-nov14

WBS: TECHO

17

WBS: ACABADOS - GRANALLADO Y PINTADO

17

WBS: MONTAJE - ESTRUCTURAL


WBS: ESTRUCTURAS PRINCIPALES
EP-10
EP-20
EP-30
EP-40

K168-MEK168-MEK168-MEK168-ME-

EL-20

K168-MEK168-ME-

Montaje - ViguetasTipo 1 y Tipo 2

Montaje - Tijerales Tipo 1 y Tipo 2

Montaje - Vigas Tipo 1 y Tipo 2

Montaje - Templadores

Instalacin de Lona (lateral)

Grouteo de Columnas

WBS: SUMINISTROS
WBS: SUMINISTROS SMI
WBS: INSTALACIN - MECNICA
WBS: ENSAMBLAJE DE MAQUINAS
WBS: INSTALACION DE LINEAS DE PRODUCCIN

LP-20
LP-30
LP-40

K168-MEK168-MEK168-MEK168-ME-

0
44
5
39

Instalacin - Lneas de Produccin a Losa N1

Instalacin - Lneas de Produccin a Losa N2

Instalacin - Lneas de Produccin a Losa N3

WBS: SUMINISTRO SMI


WBS: ENSAMBLAJE - MECHANICAL
WBS: ARMADO DE JAULAS
Armado - Jaulas (2'x2'x4') para Lneas Produccin
N1, N2, N3

WBS: ENSAMBLAJE DE MODULOS


K168-ME-EM-LP101
K168-ME-EM-LP106
K168-ME-EM-LP201

WBS: SUMINISTROS

K168-ME-

44

Adecuacin - Lneas de Produccin Provisional N1

WBS: ASSEMBLY OF 2X2X4 MEDIA MODULES

AJ-10

10

Montaje - Cobertura Metlica TR6

WBS: INTALACIN DE LINEAS DE PRODUCCIN

LP-10

Montaje - Correas

WBS: COBERTURA METALICA


K168-MECM-10
K168-MECM-20
K168-MECM-30

12

Montaje - Columnas Principales

WBS: ESTRUCTURAS LIVIANAS


EL-10

27

Ensamble Mdulos, Lnea Provisional N1


(3426Und)
Ensamble Mdulos, Lnea de Produccin N1
(41525Und)
Ensamble Mdulos, Lnea de Produccin N2
(41525Und)

130
0
0
130
5
5
123
39
84
84

10-nov14
21-nov14
26-nov14
26-nov14
26-nov14
02-Dec14
05-Dec14
06-Dec14
12-Dec14
12-Dec14
12-Dec14
16-Dec14
16-Dec14
24-Dec14
24-Dec14
13-nov14
13-nov14
13-nov14
13-nov14
13-nov14
19-nov14
19-nov14
29-Dec14
29-Dec14
29-Dec14
13-nov14
13-nov14
13-nov14
13-nov14
13-nov14
13-nov14
20-nov14
20-nov14
07-Jan15
07-Jan15

28-nov14
10-Dec14
27-Dec14
09-Dec14
01-Dec14
04-Dec14
08-Dec14
09-Dec14
15-Dec14
15-Dec14
15-Dec14
27-Dec14
23-Dec14
24-Dec14
27-Dec14
05-Jan15
13-nov14
13-nov14
05-Jan15
18-nov14
05-Jan15
19-nov14
05-Jan15
05-Jan15
05-Jan15
15-Apr15
13-nov14
13-nov14
15-Apr15
18-nov14
18-nov14
14-Apr15
06-Jan15
14-Apr15
14-Apr15

K168-ME-EM-LP301

Ensamble Mdulos, Lnea de Produccin N3


(41524Und)

WBS: ALMACENAJE DE MODULOS TERMINADOS


K168-ME-AM-LP101
K168-ME-AM-LP106
K168-ME-AM-LP201
K168-ME-AM-LP301

Almacenaje Mdulos,
Und)
Almacenaje Mdulos,
(41525Und)
Almacenaje Mdulos,
(41525Und)
Almacenaje Mdulos,
(41524Und)

84
123

Lnea Provisional N1 (3426


Lnea de Produccin N1
Lnea de Produccin N2
Lnea de Produccin N3

WBS: DELIVERY OF MEDIA MODULE SAMPLES FOR TESTING


WBS: EMBAJAJE y ENVIO DE MODULOS

39
84
84
84
50
50

K168-ME-EEM-10

Embalaje y envi de 20 mdulos a USA

K168-ME-EEM-20

Embalaje y envi de 20 mdulos a USA

K168-ME-EEM-30

Embalaje y envi de 20 mdulos a USA

K168-ME-EEM-40

Embalaje y envi de 20 mdulos a USA

07-Jan15
21-Nov14
21-nov14
08-Jan15
08-Jan15
08-Jan15
12-Feb15
12-Feb15
12-Feb15
05-Mar15
26-Mar15
09-Apr15

14-Apr15
15-Apr15
07-Jan15
15-Apr15
15-Apr15
15-Apr15
10-Apr15
10-Apr15
13-Feb15
06-Mar15
27-Mar15
10-Apr15

4. DESCRIPTION OF THE WORKS

First, Contractor will perform the fabrication of a structural warehouse of 15tn,


after this Contractor will proceed with the assembly in the site assigned by SMI,
600 m2.

After this, Contractor will proceed with the assembly and maintenance of the
three production lines (sizing machines of disk and conveying equipment) to
install in the set area, by finishing the assembly of the structural warehouse.

After that, Contractor will build cages for each production line (supplied by the
client) to start the building and assembly of the 128 000 modules of the new 04
filters (32 000 modules per filter).

Then, the produced modules will be stored, packed and stacked in a set area
established by SMI.
The start of activities depends on the fulfillment of the requirements demanded
by the client for the start of the mobilization.

The following are the quantities of crews for the principal activities:

Crew for Structural Assembly


Crews quantity
Performance

: 02 crews per each working face.


: 15 000 kg in 27 calendar days.

Crew for Installation of Production Lines


Crews quantity
: 02 crews per each working face.
Performance
: 03 teams for 06 calendar days.

Crew for Assembly of Modules


Crews quantity
: 01 crew per each production line.

Performance

: Variable according to the learning.

Crew for Storage and Packing of Modules


Crews quantity
: 01 crews per each working face.
Performance
: 1980modules per06 calendar days.

5. HISTOGRAM
Contractor shows the histograms of HH according to the WBS:
Histogram of building, assembly and storage of modules

6. CRITICAL PATH
It is defined by the activities related to the mobilization and training of personnel, construction of the warehouse, installation of three
production lines (equipments), in order to start with the building, assembly and storage of the 128 000 modules

7. Annex
AnnexI: Histogram of total personnel (HH)

HISTOGRAM HM
8000.00

7,386
7,386
7,386
7,260
7,260
7,260
7,260

7000.00

6,458

6000.00
5,154
5,028
4,603

5000.00
4000.00

3,311

3000.00
2000.00

1,741

1000.00
0.00

2,361

2,242
2,190

302
73 73 73 73 73 126136
0

1,082
922
826855
681
485

2,609

Annex II: Curve S

Annex III: Curve S Production Line


Production Line N 01

Production Line N 02

Production Line N 03

Annex IV: Activities with restrictions


The following activities depend on the supply (by SMI) of a suitable area for the camp and
warehouse installation.

K168-ME-GE-10
materials.
K168-ME-GE-20

Mobilization of personnel, equipments, tools and


Temporary facilities.

The following activities depend on the evaluation of a specialist (vendor) with respect to the
training and supervision of modules to produce. (By SMI)

K168-ME-GE-30

Personnel training.

The following activities depend on SMI supply:

K168-ME-ST-CMI-10 SupplySizing machine of disk


K168-ME-ST-CMI-20 Supply Conveying equipment
K168-ME-ST-CMI-30 SupplyPVC Sheet
K168-ME-ST-CMI-40 SupplyGlue
K168-ME-ST-CMI-50 Supply Cages

The following activities depend on IMCO supply:

K168-ME-ST-IMCO-20 Transport of principal columns IMCO-SMCV


K168-ME-ST-IMCO-30 Transport of beams IMCO-SMCV
K168-ME-ST-IMCO-40 Transport of frames IMCO-SMCV
K168-ME-ST-IMCO-50 Transport of straps and annealing lehr IMCO-SMCV
K168-ME-ST-IMCO-60 Supply - TR6 Coverage

AnnexV: DICTIONARY OF ACTIVITIES ID


DISCIPLINE - PHASE -RESPONSIBLE - CORRELATIVE
XX XXXXXXX - 000
DISCIPLINA:
ME
: MECNICA
FASE:
HG
: HITOS GENERALES
GE
: GESTIN
ING : INGENIERA
ST
: SUMINISTRO Y TRANSPORTE
FAB : FABRICACIN
MT
: MONTAJE
INT
: INSTALACIN
EM
: ENSAMBLAJE

EEM
AM
LP1
LP2
LP3

: EMBALAJE Y ENVIO
: ALMACENAJE
: LINEA DE PRODUCCION 1
: LINEA DE PRODUCCION 2
: LINEA DE PRODUCCION 3

RESPONSABLE
SMI :
SMI
IMCO :
IMCO