BASIS SCHEDULE
CERRO VERDE PRODUCTION UNIT
EXPANSION
January 2015
BASIS SCHEDULE
1. INFORMATION OF THE PROJECT
Name of the Project:
Contract Code:
Start date:
End Date:
Term
Man Hours:
The Schedule of the Project does not considerate the delays concerning to security,
problems with the community, changes of engineering, additional works, delay in
provision by SMI, weather aspects, strikes of the workers, interruption of Works due to
the transit of vehicles in the site.
The schedule considerate the following principal activities:
ActivityName
Original
Duration
181
Activity ID
181
WBS: GESTIN
59
59
WBS: INGENIERIA
28
WBS: SUMINISTROS
35
35
WBS: FABRICACIN
27
WBS: TIJERALES
12
WBS: COLUMNAS
WBS: VIGAS - VIGUETAS
6
11
Start
Finish
15-sep14
15-sep14
15-Sep14*
15-Apr15
15-Apr15
15-sep14
20-oct14
20-oct14
01-Nov14
01-Nov14
10-nov14
10-nov14
14-nov14
10-nov14
15-Apr15
21-nov14
27-Dec14
20-nov14
11-Dec14
11-Dec14
10-Dec14
22-nov14
20-nov14
21-nov14
WBS: TECHO
17
17
K168-MEK168-MEK168-MEK168-ME-
EL-20
K168-MEK168-ME-
Montaje - Templadores
Grouteo de Columnas
WBS: SUMINISTROS
WBS: SUMINISTROS SMI
WBS: INSTALACIN - MECNICA
WBS: ENSAMBLAJE DE MAQUINAS
WBS: INSTALACION DE LINEAS DE PRODUCCIN
LP-20
LP-30
LP-40
K168-MEK168-MEK168-MEK168-ME-
0
44
5
39
WBS: SUMINISTROS
K168-ME-
44
AJ-10
10
LP-10
Montaje - Correas
12
27
130
0
0
130
5
5
123
39
84
84
10-nov14
21-nov14
26-nov14
26-nov14
26-nov14
02-Dec14
05-Dec14
06-Dec14
12-Dec14
12-Dec14
12-Dec14
16-Dec14
16-Dec14
24-Dec14
24-Dec14
13-nov14
13-nov14
13-nov14
13-nov14
13-nov14
19-nov14
19-nov14
29-Dec14
29-Dec14
29-Dec14
13-nov14
13-nov14
13-nov14
13-nov14
13-nov14
13-nov14
20-nov14
20-nov14
07-Jan15
07-Jan15
28-nov14
10-Dec14
27-Dec14
09-Dec14
01-Dec14
04-Dec14
08-Dec14
09-Dec14
15-Dec14
15-Dec14
15-Dec14
27-Dec14
23-Dec14
24-Dec14
27-Dec14
05-Jan15
13-nov14
13-nov14
05-Jan15
18-nov14
05-Jan15
19-nov14
05-Jan15
05-Jan15
05-Jan15
15-Apr15
13-nov14
13-nov14
15-Apr15
18-nov14
18-nov14
14-Apr15
06-Jan15
14-Apr15
14-Apr15
K168-ME-EM-LP301
Almacenaje Mdulos,
Und)
Almacenaje Mdulos,
(41525Und)
Almacenaje Mdulos,
(41525Und)
Almacenaje Mdulos,
(41524Und)
84
123
39
84
84
84
50
50
K168-ME-EEM-10
K168-ME-EEM-20
K168-ME-EEM-30
K168-ME-EEM-40
07-Jan15
21-Nov14
21-nov14
08-Jan15
08-Jan15
08-Jan15
12-Feb15
12-Feb15
12-Feb15
05-Mar15
26-Mar15
09-Apr15
14-Apr15
15-Apr15
07-Jan15
15-Apr15
15-Apr15
15-Apr15
10-Apr15
10-Apr15
13-Feb15
06-Mar15
27-Mar15
10-Apr15
After this, Contractor will proceed with the assembly and maintenance of the
three production lines (sizing machines of disk and conveying equipment) to
install in the set area, by finishing the assembly of the structural warehouse.
After that, Contractor will build cages for each production line (supplied by the
client) to start the building and assembly of the 128 000 modules of the new 04
filters (32 000 modules per filter).
Then, the produced modules will be stored, packed and stacked in a set area
established by SMI.
The start of activities depends on the fulfillment of the requirements demanded
by the client for the start of the mobilization.
The following are the quantities of crews for the principal activities:
Performance
5. HISTOGRAM
Contractor shows the histograms of HH according to the WBS:
Histogram of building, assembly and storage of modules
6. CRITICAL PATH
It is defined by the activities related to the mobilization and training of personnel, construction of the warehouse, installation of three
production lines (equipments), in order to start with the building, assembly and storage of the 128 000 modules
7. Annex
AnnexI: Histogram of total personnel (HH)
HISTOGRAM HM
8000.00
7,386
7,386
7,386
7,260
7,260
7,260
7,260
7000.00
6,458
6000.00
5,154
5,028
4,603
5000.00
4000.00
3,311
3000.00
2000.00
1,741
1000.00
0.00
2,361
2,242
2,190
302
73 73 73 73 73 126136
0
1,082
922
826855
681
485
2,609
Production Line N 02
Production Line N 03
K168-ME-GE-10
materials.
K168-ME-GE-20
The following activities depend on the evaluation of a specialist (vendor) with respect to the
training and supervision of modules to produce. (By SMI)
K168-ME-GE-30
Personnel training.
EEM
AM
LP1
LP2
LP3
: EMBALAJE Y ENVIO
: ALMACENAJE
: LINEA DE PRODUCCION 1
: LINEA DE PRODUCCION 2
: LINEA DE PRODUCCION 3
RESPONSABLE
SMI :
SMI
IMCO :
IMCO