DAILY ACTION PLAN ON FIRE PROOFING

8382 LOADING PLATFORM


FIRE PROOFING
What
(Action to Take)

Approx area applied = 96.5% complete as of 29/04


Date: 04 May 2015
When
Deliverables/Remarks

How

Who

(Action Steps)

(Accountable)

Start

Finish

Blasting and primer

MCD Painters Saryono/Tito

26-Apr-15

26-Apr-15

COMPLETE 100%

Joint Inspection

MCD Painters Saryono/Tito

26-Apr-15

26-Apr-15

COMPLETE 100%

Tie Coat

MCD Painters Saryono/Tito

26-Apr-15

26-Apr-15

COMPLETE 100%

27-Apr-15

COMPLETE 100%

COMPLETE FIRE PROOFING BY 30 APRIL ON:


GANGWAYS AT ZONE 3

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

Fire Proofing Application

PROSTAR-Ricky

28-Apr-15

29-Apr-15

COMPLETE 100%. To be joint


inspected.

Blasting and primer

MCD Painters Saryono/Tito

26-Apr-15

26-Apr-15

COMPLETE 100%

Joint Inspection

MCD Painters Saryono/Tito

26-Apr-15

26-Apr-15

COMPLETE 100%

Tie Coat

MCD Painters Saryono/Tito

26-Apr-15

26-Apr-15

COMPLETE 100%

27-Apr-15

COMPLETE 100%

CATWALK FRAME AT ZONE 4/3 RK-2

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

Fire Proofing Application

PROSTAR-Ricky

28-Apr-15

29-Apr-15

COMPLETE 100%. To be joint


inspected.

Blasting and primer

MCD Painters Saryono/Tito

26-Apr-15

26-Apr-15

100% COMPLETE

Joint welding nspection

MCD Painters Saryono/Tito

26-Apr-15

27-Apr-15

100% COMPLETE

Tie Coat

MCD Painters Saryono/Tito

28-Apr-15

28-Apr-15

100% COMPLETE

29-Apr-15

COMPLETED. RELEASE TO FIRE


PROOFING

PIPE SUPPORTS AT ZONE 2&3 MIDDLE LEVEL

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

Fire Proofing Application

PROSTAR-Ricky

29-Apr-15

30-Apr-15

PARTIAL APPLICATION

MCD Painters Saryono/Tito

26-Apr-15

27-Apr-15

100% COMPLETE

QA/QC Suratno/Gun and


Aliman/Taufik

28-Apr-15

28-Apr-15

MCD Painters Saryono/Tito

29-Apr-15

29-Apr-15

Impact on schedule completion.

29-Apr-15

Impact on schedule completion.

30-Apr-15

Impact on schedule completion.

PIPE SUPPORTS AT ABOVE LOWER DECK ZONE 1


Blasting and primer

Joint Inspection

Tie Coat

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

Fire Proofing Application

PROSTAR-Ricky

30-Apr-15

DAILY ACTION PLAN ON TOP COAT FOR FP


8382 LOADING PLATFORM
FIRE PROOFING TOP COAT DAILY PROGRESS
What
(Action to Take)

How

Who

(Action Steps)

(Accountable)

Approx area applied = 400.00m2 out of 2,500.00m2 as of 26/04


Date: 04 May 2015
When
Deliverables/REMARKS
Start

Finish

COMPLETE TOP COAT ON FP BY 05 MAY:


ZONE 6
Fire Proofing release to Painting

QA/QC Nedis/Suratno

Released and completed.

MCD Painters Saryono/Tito

25-Apr-15

26-Apr-15

Complete. Final inspection to be performed after break,


as informed by BC Inspector.

MCD PaintersSaryono/Tito

26-Apr-15

28-Apr-15

SLIPPED due to bad weather recorded at 10am of


27/04.

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

28-Apr-15

29-Apr-15

FIRST JOINT INSPECTION COMPLETED 29/04.


REQUIRE REPAIRS ON COATING.

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

30-Apr-15

2-May-15

RELEASED FOR REMOVAL AND MOFICATION OF


SCAFOLDING.

First Coat Application

Final Coat Application

ZONE 5
Fire Proofing release to Painting

QA/QC Nedis/Suratno

First Coat Application

MCD Painters Saryono/Tito

28-Apr-15

29-Apr-15

COMPLETED PROCEED FOR JOINT INSPECTION


30/04.

Final Coat Application

MCD PaintersSaryono/Tito

30-Apr-15

2-May-15

SLIPPED DUE TO X-RAY PERFORMED 7AM TILL 9AM


AND RESUME AT 3PM-4PM ON PIPING AT LP. TO BE
COMPLETE 02 MAY 2015

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

2-May-15

4-May-15

SLIPPED DUE TO BAD WEATHER, HOLIDAY, AND


INTERRUPTION FROM X-RAYS.

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

4-May-15

SLIPPED DUE TO BAD WEATHER, HOLIDAY, AND


INTERRUPTION FROM X-RAYS.

Released and completed.

ZONE 4
Fire Proofing release to Painting

QA/QC Nedis/Suratno

25-Apr-15

28-Apr-15

Released and completed.

First Coat Application

MCD Painters Saryono/Tito

30-Apr-15

30-Apr-15

SURFACE PREP COMPLETED. JOINT INSPECTION


ON SURFACE PREP REQUIRED PRIOR FIRST COAT
APPLICATION

Final Coat Application

MCD PaintersSaryono/Tito

2-May-15

2-May-15

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

3-May-15

4-May-15

Fire Proofing release to Painting

QA/QC Nedis/Suratno

27-Apr-15

28-Apr-15

Released and completed.

First Coat Application

MCD Painters Saryono/Tito

2-May-15

2-May-15

SURFACE PREP COMPLETE TODAY. JOINT


INSPECTION ON SURFACE PREP REQUIRED PRIOR
FIRST COAT APPLICATION

Final Coat Application

MCD PaintersSaryono/Tito

4-May-15

4-May-15

3-May-15

ZONE 3

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

5-May-15

6-May-15

QA/QC Nedis/Suratno

28-Apr-15

28-Apr-15

Released and completed.


SURFACE PREP COMPLETE TODAY. JOINT
INSPECTION ON SURFACE PREP REQUIRED PRIOR
FIRST COAT APPLICATION

5-May-15

ZONE 2
Fire Proofing release to Painting

First Coat Application

MCD Painters Saryono/Tito

2-May-15

3-May-15

Final Coat Application

MCD PaintersSaryono/Tito

4-May-15

4-May-15

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

5-May-15

6-May-15

Fire Proofing release to Painting

QA/QC Nedis/Suratno

30-Apr-15

30-Apr-15

First Coat Application

MCD Painters Saryono/Tito

2-May-15

3-May-15

Final Coat Application

MCD PaintersSaryono/Tito

5-May-15

Joint Inspection

QA/QC Suratno/Gun and


Aliman/Taufik

5-May-15

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

5-May-15

ZONE 1

6-May-15

JOINT INSPECTION REQUIRED PRIOR TOP COAT.

DAILY ACTION PLAN ON MID-LEVEL PAINTING


Area to be re-coated on existing coated frames = 60% B&P out of 325m2.

8382 LOADING PLATFORM


PAINTING ON LOADING PLATFORM MID-LEVEL
What

Area
to
be newly
painted2015
= 40% painted out of 340m2
Date:
04 May

How

Who

(Action Steps)

(Accountable)

Start

Finish

Blasting and Prime

MCD Painters Mardius

25-Apr-15

26-Apr-15

90% COMPLETE

First coating

MCD Painters Mardius

26-Apr-15

26-Apr-15

80% COMPLETE ON COSMETICS

Final Coating

MCD Painters Mardius

28-Apr-15

4-May-15

SLIPPED DUE TO LATE START. MITIGATION - O.T.


TO BE EXECUTED.

5-May-15

DFT AND HOLIDAY TEST TO BE PERFORM ON


FRAMES

(Action to Take)

When

Deliverables/Remarks

COMPLETE PAINTING ON MIDDLE LEVEL OF LP BY 10 MAY:


ZONE 6

Joint Inspection (Incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

5-May-15

7-May-15

REVISED TARGET TO PROCEED.

Blasting and Prime

MCD Painters Mardius

25-Apr-15

26-Apr-15

90% COMPLETE

First coating

MCD Painters Mardius

26-Apr-15

26-Apr-15

80% COMPLETE ON COSMETICS

Final Coating

MCD Painters Mardius

28-Apr-15

6-May-15

SLIPPED DUE TO LATE START. MITIGATION - O.T.


TO BE EXECUTED.

6-May-15

DFT AND HOLIDAY TEST TO BE PERFORM ON


FRAMES

ZONE 5

Joint Inspection (Incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

IMPACT
6-May-15

8-May-15

ZONE 4
Blasting and Prime

MCD Painters Mardius

25-Apr-15

29-Apr-15

90% COMPLETE

First coating

MCD Painters Mardius

30-Apr-15

4-May-15

80% COMPLETE ON COSMETICS

Final Coating

MCD Painters Mardius

5-May-15

6-May-15

4-May-15

7-May-15

7-May-15

8-May-15

Joint Inspection (Incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

SLIPPED DUE TO LATE START. MITIGATION - O.T.


TO BE EXECUTED.
DFT AND HOLIDAY TEST TO BE PERFORM ON
FRAMES

NEW TARGET

ZONE 3
Blasting and Prime

MCD Painters Mardius

26-Apr-15

30-Apr-15

IMPACT DUE TO BAD WEATHER 27/04 10AM.

First coating

MCD Painters Mardius

30-Apr-15

5-May-15

NEW TARGET

Final Coating

MCD Painters Mardius

5-May-15

11-May-15

NEW TARGET

Joint Inspection (Incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

7-May-15

11-May-15

NEW TARGET

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

12-May-15

13-May-15

NEW TARGET

Blasting and Prime

MCD Painters Mardius

26-Apr-15

30-Apr-15

IMPACT DUE TO BAD WEATHER 27/04 10AM.

First coating

MCD Painters Mardius

30-Apr-15

6-May-15

ON-SCHEDULE

Final Coating

MCD Painters Mardius

8-May-15

11-May-15

ON-SCHEDULE

Joint Inspection (Incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

10-May-15

11-May-15

ON-SCHEDULE

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

11-May-15

12-May-15

ON-SCHEDULE

Blasting and Prime

MCD Painters Mardius

26-Apr-15

29-Apr-15

IMPACT DUE TO BAD WEATHER 27/04 10AM.

First coating

MCD Painters Mardius

29-Apr-15

8-May-15

CAN BE EARLY START AND EARLY FINISH

Final Coating

MCD Painters Mardius

8-May-15

20-May-15

CAN BE EARLY START AND EARLY FINISH

QA/QC Suratno/Gun and


Aliman/Taufik

8-May-15

21-May-15

CAN BE EARLY START AND EARLY FINISH

ZONE 2

ZONE 1
(PIPE SUPPORTS AND TOP DECK ACCESSORIES)

Joint Inspection (Incl. HOLIDAY TEST)

DAILY ACTION PLAN ON 13.36M AND ABOVE PAINTING


8382 LOADING PLATFORM
PAINTING ON LOADING PLATFORM AT 13.36M AND ABOVE
What
How
(Action to Take)

(Action Steps)

Who

Approx area applied = 58.5% completed out of


5,127m2 as of 29/04.
Date: 04 May 2015
When
Deliverables/Remarks

(Accountable)

Start

Finish

Blasting and Prime

MCD Painters Mardius

25-Apr-15

26-Apr-15

LATE START DUE TO BAD WEATHER


ON 25/04 AFTERNOON.
COMPLETED ON 26/04

First coating

MCD Painters Mardius

26-Apr-15

29-Apr-15

COMPLETE 80%

Final Coating

MCD Painters Mardius

29-Apr-15

4-May-15

100% COMPLETED ON CABLE TRAY


SUPPORT FRAME.

5-May-15

HOLIDAY TEST ON CABLE TRAY


SUPPORT FRAME. DFT CHECKS ON
BRACINGS AND RAKERS

COMPLETE PAINTING ON MIDDLE LEVEL OF LP BY 20 MAY:


ZONE 6

Joint Inspection (Incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

5-May-15

7-May-15

REVISED TARGET TO PROCEED.

Blasting and Prime

MCD Painters Mardius

25-Apr-15

26-Apr-15

LATE START DUE TO BAD WEATHER


ON 25/04 AFTERNOON.
COMPLETED ON 26/04

First coating

MCD Painters Mardius

26-Apr-15

26-Apr-15

80% COMPLETE ON COSMETICS

Final Coating

MCD Painters Mardius

28-Apr-15

6-May-15

SLIPPED DUE TO LATE START.


MITIGATION - O.T. TO BE EXECUTED.

6-May-15

DFT AND HOLIDAY TEST TO BE


PERFORM ON FRAMES

ZONE 5

Joint Inspection (Incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

IMPACT
6-May-15

8-May-15

ZONE 4
Blasting and Prime

MCD Painters Mardius

25-Apr-15

28-Apr-15

LATE START AND SLOW


COMPLETION DUE TO BAD
WEATHER ON 25-27-29/04 and 30/04.

First coating

MCD Painters Mardius

29-Apr-15

30-Apr-15

COMPLETE 80%

Final Coating

MCD Painters Mardius

30-Apr-15

2-May-15

Joint Inspection (incl. HOLIDAY TEST)

Removal/Modification of Scaffoldings

ON-SCHEDULE

QA/QC Suratno/Gun and


Aliman/Taufik
MCD Scaffolders Darryl Kuyer

ON-SCHEDULE
2-May-15
ON-SCHEDULE
2-May-15

3-May-15

ZONE 3
Blasting and Prime

MCD Painters Mardius

26-Apr-15

29-Apr-15

LATE START AND SLOW


COMPLETION DUE TO BAD
WEATHER ON 25-27-29/04 and 30/04.

First coating

MCD Painters Mardius

30-Apr-15

1-May-15

COMPLETE 40%

Final Coating

MCD Painters Mardius

3-May-15

5-May-15

ON-SCHEDULE

5-May-15

ON-SCHEDULE

Joint Inspection (incl. HOLIDAY TEST)

QA/QC Suratno/Gun and


Aliman/Taufik

Removal/Modification of Scaffoldings

MCD Scaffolders Darryl Kuyer

6-May-15

7-May-15

ON-SCHEDULE

Blasting and Prime

MCD Painters Mardius

26-Apr-15

30-Apr-15

LATE START AND SLOW


COMPLETION DUE TO BAD
WEATHER ON 25-27-29/04 and 30/04.

First coating

MCD Painters Mardius

1-May-15

3-May-15

ON-GOING BLASTING AND PRIME

Final Coating

MCD Painters Mardius

5-May-15

13-May-15

ON-SCHEDULE

ZONE 2

Joint Inspection (incl. HOLIDAY TEST)

Removal/Modification of Scaffoldings

QA/QC Suratno/Gun and


Aliman/Taufik
MCD Scaffolders Darryl Kuyer

ON-SCHEDULE
13-May-15
ON-SCHEDULE
14-May-15

15-May-15

ZONE 1
Blasting and Prime

MCD Painters Mardius

26-Apr-15

29-Apr-15

LATE START AND SLOW


COMPLETION DUE TO BAD
WEATHER ON 25-27-29/04 and 30/04.

First coating

MCD Painters Mardius

13-May-15

17-May-15

ON-GOING SWEEP BLASTING

Final Coating

MCD Painters Mardius

17-May-15

23-May-15

CAN BE EARLY START AND EARLY


FINISH

23-May-15

CAN BE EARLY START AND EARLY


FINISH

Joint Inspection (incl. HOLIDAY TEST)

Removal/Modification of Scaffoldings

QA/QC Suratno/Gun and


Aliman/Taufik
MCD Scaffolders Darryl Kuyer

NIL