Agenda
Project Management Processes
Initiating Process Group Activities
Planning Process Group Activities
Executing Process Group Activities
Monitoring & Controlling Process Group
Activities
Closing Process Group Activities

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Agenda

Initiating Process Group


Planning Process Group
Executing Process Group
Monitoring & Controlling Process Group
Closing Process Group
Project Management Process Group and
Knowledge Area Mapping

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Project Management Processes


Define what to do when in a project.
Define what you need to do to manage the
project.
There is a process for managing projects:
Initiating (Start)
Planning (Plan)
Execution (Do)
Monitoring & Controlling (Check & Act)
Closing (End)

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Project Management Processes


Interaction of Project Management Process Groups

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Project Management Processes


Process Groups interact in a Phase or Project

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Initiating Process Group Activities


Select Project Manager
Determine company culture & existing
systems
Collect processes, procedures & historical
info
Divide large projects to phases
Understand the business case (Why is this
project done?)

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Initiating Process Group Activities

Uncover initial requirements & risks


Create measurable objectives
Develop project charter
Identify stakeholders
Develop stakeholder management strategy

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group Activities

Determine how you will do planning


Finalize requirements
Create project scope statement
Determine what to purchase
Determine team
Create WBS and WBS Dictionary
Create activity list

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group Activities

Create network diagram


Estimate resource requirements
Estimate time & cost
Determine critical path
Develop schedule
Develop budget
Determine quality, standards, procedures &
metrics

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

10

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group Activities


Create process improvement plan
Determine all roles & responsibilities
Plan communications
Perform risk identification, qualitative and
quantitative risk analysis and risk response
planning
Go back - Iterations

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

11

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group Activities


Prepare procurement documents
Finalize how to execute & control parts of
all management plans
Develop final PM plan and performance
measurement baseline that are realistic
Gain formal approval of the plan
Hold kick-off meeting

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

12

PMP Exam Complete Training Course Material-Resit Gulec

Executing Process Group Activities

Execute the work according to PM plan


Produce product scope
Request changes
Implement only approved changes
Ensure common understanding
Use the work authorization system
Continuously improve

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

13

PMP Exam Complete Training Course Material-Resit Gulec

Executing Process Group Activities

Follow processes
Perform quality assurance
Perform quality audits
Acquire final team
Manage people
Evaluate team and project performance
Hold team building activities

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

14

PMP Exam Complete Training Course Material-Resit Gulec

Executing Process Group Activities

Give recognition and rewards


Use issue logs
Facilitate conflict resolution
Send and receive information
Hold meetings
Select sellers

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

15

PMP Exam Complete Training Course Material-Resit Gulec

Monitoring & Controlling Process


Group Activities
Take action to control the project
Measure performance
Determine variances and if they warrant a
change request
Influence the factors that cause changes
Request changes
Perform integrated change control

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

16

PMP Exam Complete Training Course Material-Resit Gulec

Monitoring & Controlling Process


Group Activities

Approve or reject changes


Inform stakeholders of approved changes
Manage configuration
Create forecasts
Gain acceptance from customer
Perform quality control

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

17

PMP Exam Complete Training Course Material-Resit Gulec

Monitoring & Controlling Process


Group Activities

Report on project performance


Perform risk audits
Manage reserves
Administers procurements

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

18

PMP Exam Complete Training Course Material-Resit Gulec

Closing Process Group Activities

Confirm work is done requirements


Complete procurement closure
Gain formal acceptance
Complete final performance reporting
Index and archive records
Update lessons learned

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

19

PMP Exam Complete Training Course Material-Resit Gulec

Closing Process Group Activities


Hand-off completed product
Release resources

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

20

PMP Exam Complete Training Course Material-Resit Gulec

Initiating Process Group


Starts with authorizing the project and
providing the Project Manager
Major Outputs:
Project Charter
Identified Stakeholders
Strategy for Managing Stakeholders

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

21

PMP Exam Complete Training Course Material-Resit Gulec

Initiating Process Group


Progressive Elaboration:
Estimates, product scope and some other
steps might start in initiating and iterated in
planning process
PM Plan is finalized in planning but detailed
estimate, scope and some other points might
be clarified during execution or monitoring &
controlling.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

22

PMP Exam Complete Training Course Material-Resit Gulec

Initiating Process Group


Project Manager Assigned:
Project manager assigned early in the
process.
This is not the case in real world for many
cases.
Business Case:
The reason why project started is taken into
account throughout the project.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

23

PMP Exam Complete Training Course Material-Resit Gulec

Initiating Process Group


High-Level Planning is done:
Creating high-level WBS
Order of Magnitude Estimate
High-Level risk identification

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

24

PMP Exam Complete Training Course Material-Resit Gulec

Initiating Process Group


Reasons the project initiating process is begun:
Business Need
Begin a New
Phase of The
Project
Project has so many
problems that you reevaluate the business need

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

25

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group


Planning enables walking through the project
and getting it organized before it is actually
done.
Resources, time, and money can be saved
during planning and while the work is
being done.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

26

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group


Result of Planning Process Group is
Planning
Process
Group

PM Plan

Project
Documents

Planning is iterative, thus, result of each step


may affect or cause changes to previous steps

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

27

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group


Iterations start after Risk Analysis since final
cost and schedule can be determined after
Risk Analysis.
Risk Management can result in changing
resources, when they are used, in what
sequence activities are performed, and
almost all parts of planning.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

28

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group


High Level of Confidence in Schedule requires
more planning
Low Level of Confidence in Schedule requires
less planning
Effort you need to spend in planning when
creating a schedule with +/-20% accuracy is
less than +/-%5 accuracy.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

29

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group


Rolling Wave Planning:
You might not be able to plan a phase of your
project (test, install, etc.) in detail until the
phase is finished. This is called rolling wave
planning.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

30

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group


Who is involved in planning? Everyone!
PM Plan and project documents are compiled
by Project Manager with input from
stakeholders

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

31

PMP Exam Complete Training Course Material-Resit Gulec

Planning Process Group


Reasons the project planning process is begun:
Initiating Process
Group is Completed

Approved changes,
including corrective
and preventive actions,
require re-planning

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

32

PMP Exam Complete Training Course Material-Resit Gulec

Executing Process Group


Purpose of executing process group is to
complete the work defined in PM plan and to
meet project objectives.
Executing the project management plan
Focuses on:
Managing people
Following processes
Distributing information

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

33

PMP Exam Complete Training Course Material-Resit Gulec

Executing Process Group


Meetings are important in executing process
group
During meetings
Review risks
Upcoming contingency plans
Do not only discuss status or what is done.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

34

PMP Exam Complete Training Course Material-Resit Gulec

Executing Process Group


Reasons the project executing process is begun:
Project Planning is
completed

Integrated change
control results in a
changed project
management plan

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

35

PMP Exam Complete Training Course Material-Resit Gulec

Monitoring & Controlling Process


Group
Measuring performance of the project to the
project management plan and approving
change requests, including recommended
corrective and preventive actions and defect
repair.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

36

PMP Exam Complete Training Course Material-Resit Gulec

Monitoring & Controlling Process


Group
Project manager is accountable for meeting
the performance measurement baseline
Project manager takes actions to correct any
variances.
Any deviations from the plan should be made
up rather than requesting a change to the
project to accommodate them.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

37

PMP Exam Complete Training Course Material-Resit Gulec

Monitoring & Controlling Process Group


When to enter M&C, and why to go other
Initiating Process
process groups from M&C
Group to review
Project Charter

Requested Changes

Work Performance
Information

Deliverables

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

Planning Process
Group to Re-Plan
Monitoring &
Controlling
Process Group

Executing Process
Group is to repair
defects
Closing Process
Group if project is
finished

38

PMP Exam Complete Training Course Material-Resit Gulec

Closing Process Group

Project is finished in this process group.


Includes administrative activities.
Final product is delivered.
Celebration !
Report final project performance of resources
Latest versions of Lessons Learned are
compiled.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

39

PMP Exam Complete Training Course Material-Resit Gulec

Closing Process Group


Formal sign-off and acceptance is acquired.
Project is closed after getting final sign-off
and administrative work are completed.

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

40

PMP Exam Complete Training Course Material-Resit Gulec

Closing Process Group


Reasons the project closing process is begun:
Project Phase is
Complete

Project is
complete
Project is
terminated

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

41

PMP Exam Complete Training Course Material-Resit Gulec

Project Management Process Group


and Knowledge Area Mapping

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

42

PMP Exam Complete Training Course Material-Resit Gulec

Project Management Process Group


and Knowledge Area Mapping

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

43

PMP Exam Complete Training Course Material-Resit Gulec

Project Management Process Group


and Knowledge Area Mapping

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

44

PMP Exam Complete Training Course Material-Resit Gulec

Project Management Process Group


and Knowledge Area Mapping

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

45

PMP Exam Complete Training Course Material-Resit Gulec

Question #1
In which project management process group is
the detailed project budget created?
A-) Initiating
B-) Before the project management process
C-) Planning
D-) Executing

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

46

PMP Exam Complete Training Course Material-Resit Gulec

Question #1
In which project management process group is
the detailed project budget created?
A-) Initiating
B-) Before the project management process
C-) Planning
D-) Executing

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

47

PMP Exam Complete Training Course Material-Resit Gulec

Question #2
The BEST time to assign a project manager to a
project is during:
A-) Executing
B-) Closing
C-) Initiating
D-) Planning

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

48

PMP Exam Complete Training Course Material-Resit Gulec

Question #2
The BEST time to assign a project manager to a
project is during:
A-) Executing
B-) Closing
C-) Initiating
D-) Planning

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

49

PMP Exam Complete Training Course Material-Resit Gulec

Question #3
A project manager gets a call from a team member notifying
him that there is a variance between the speed of a system on
the project and the desired or planned speed. The project
manager is surprised because that performance measurement
was not identified in planning. If the project manager then
evaluates whether the variance warrants a response, he is in
what project management process?
A-) Initiating
B-) Planning
C-) Executing
D-) Monitoring & Controlling

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

50

PMP Exam Complete Training Course Material-Resit Gulec

Question #3
A project manager gets a call from a team member notifying
him that there is a variance between the speed of a system on
the project and the desired or planned speed. The project
manager is surprised because that performance measurement
was not identified in planning. If the project manager then
evaluates whether the variance warrants a response, he is in
what project management process?
A-) Initiating
B-) Planning
C-) Executing
D-) Monitoring & Controlling

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

51

PMP Exam Complete Training Course Material-Resit Gulec

Question #4
During a team meeting, a team member asks about the
measurements that will be used on the project to judge
performance. The team member feels that some of the
measures related to activities assigned him are not valid
measurements. The project is BEST considered in what part of
the project management process?
A-) Initiating
B-) Executing
C-) Monitoring & Controlling
D-) Closing

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

52

PMP Exam Complete Training Course Material-Resit Gulec

Question #4
During a team meeting, a team member asks about the
measurements that will be used on the project to judge
performance. The team member feels that some of the
measures related to activities assigned him are not valid
measurements. The project is BEST considered in what part of
the project management process?
A-) Initiating
B-) Executing
C-) Monitoring & Controlling
D-) Closing

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

53

PMP Exam Complete Training Course Material-Resit Gulec

Question #5
Which of the following is a characteristic of project
management processes?
A-) Iterative
B-) Unique
C-) Unnecessary
D-) Standardized

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

54

PMP Exam Complete Training Course Material-Resit Gulec

Question #5
Which of the following is a characteristic of project
management processes?
A-) Iterative
B-) Unique
C-) Unnecessary
D-) Standardized

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

55

PMP Exam Complete Training Course Material-Resit Gulec

Question #6
Which of the following is NOT an input to the initiating process
group?
A-) Company processes
B-) Company culture
C-) Historical WBSs
D-) Project scope statement

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

56

PMP Exam Complete Training Course Material-Resit Gulec

Question #6
Which of the following is NOT an input to the initiating process
group?
A-) Company processes
B-) Company culture
C-) Historical WBSs
D-) Project scope statement

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

57

PMP Exam Complete Training Course Material-Resit Gulec

Question #7
The project sponsor has just signed the project charter. What is
the NEXT thing to do?
A-) Begin to complete work packages.
B-) Verify Scope.
C-) Start integrated change control
D-) Start to create management plans

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

58

PMP Exam Complete Training Course Material-Resit Gulec

Question #7
The project sponsor has just signed the project charter. What is
the NEXT thing to do?
A-) Begin to complete work packages.
B-) Verify Scope.
C-) Start integrated change control
D-) Start to create management plans

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

59

PMP Exam Complete Training Course Material-Resit Gulec

Question #8
The high-level project risks have just been determined. What
project management process group are you in?
A-) Initiating
B-) Planning
C-) Executing
D-) Monitoring & Controlling

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

60

PMP Exam Complete Training Course Material-Resit Gulec

Question #8
The high-level project risks have just been determined. What
project management process group are you in?
A-) Initiating
B-) Planning
C-) Executing
D-) Monitoring & Controlling

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

61

PMP Exam Complete Training Course Material-Resit Gulec

Question #9
A team member notifies the project manager that the activities
comprising a work package are no longer appropriate. It would
be BEST for the project manager to be in what part of the
project management process?
A-) Corrective action
B-) Integrated change control
C-) Monitoring and controlling
D-) Project closing

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

62

PMP Exam Complete Training Course Material-Resit Gulec

Question #9
A team member notifies the project manager that the activities
comprising a work package are no longer appropriate. It would
be BEST for the project manager to be in what part of the
project management process?
A-) Corrective action
B-) Integrated change control
C-) Monitoring and controlling
D-) Project closing

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

63

PMP Exam Complete Training Course Material-Resit Gulec

Question #10
Which process groups must be included in every project?
A-) Planning, executing, and closing
B-) Initiating, planning and executing
C-) Initiating, planning, executing, monitoring & controlling, and
closing
D-) Planning, executing, and monitoring & controlling

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

64

PMP Exam Complete Training Course Material-Resit Gulec

Question #10
Which process groups must be included in every project?
A-) Planning, executing, and closing
B-) Initiating, planning and executing
C-) Initiating, planning, executing, monitoring & controlling,
and closing
D-) Planning, executing, and monitoring & controlling

Not for distribution, sale or reproduction. Cannot be used


without permission of the Author.

65

S-ar putea să vă placă și