J. Preventive Maintenance Work Orders.

Ja. Preventive Maintenance Meter Based.


Ja1. Create a Schedule Set.
Ja2. Create an Asset Group / Attach an Activity / Create an
Asset.
Ja3. Create a Meter.
Ja4. Associate the Meter to an Asset.
Ja5. Create a Schedule Name. Link an Asset / Re-buildable Item.
Link the Asset Activity. Set the Scheduling Parameters.
Ja6. Select the Meter in the Scheduling Parameters.
Ja7. Enter Work Order Trigger values.
Ja8. Update Meter Reading.
Ja9. Run Work Order Generation Program.
Ja10. Work Order generated.
Ja11. Meter Based Calculations
Ja1. Create a Schedule Set.

Ja2. Create an Asset Group / Attach an Activity / Create an Asset.

Ja3. Create a Meter.

Ja4. Associate the Meter to an Asset.

Ja5. Create a Schedule Name. Link an Asset / Rebuildable Item.


Link the Asset Activity. Set the Scheduling Parameters.
Ja6. Select the Meter in the Scheduling Parameters.
Ja7. Enter Work Order Trigger values.
Ja8. Update Meter Reading.

Ja9. Run Work Order Generation Program.

Ja10. Work Order generated.

Ja11. Meter Based Calculations


Let us check the total number of work Orders generated.

As you can observe every 12 Minutes one work Order is getting


generated.
This is because of the following Calculation.
Usage Rate = 120 Amps / Day
Interval = 1 Amp
Range = Interval / Usage Rate
= 1 Amp / 120 Amps/Day
= 1 / 120 Days
= .00833 Days
= .0833 X 24 Hours
= 0.2 Hrs
= 0.2 X 60 Minutes
= 12 Minutes.
Therefore every 12 Minutes a work order is being scheduled.
Release one of the Work Orders.

You can also update the Meter Reading in the Last service Info window
of the Schedule.