Earth work specification

2.1

2.1.1
Code

114
115

Earth work in surface excavation not exceeding 30 cm in depth but exceeding


1.5m in width as well as 10 sqm on plan including disposal of excavated earth
up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:
All kinds of soil
Description
Details of cost for 100 sqm and average depth 15 cm
LABOUR:

Unit

Beldar
Coolie

Quantity

Day

7.2

240

Day

240

114

Unit

Beldar

Quantity

Day

Rate

3.7

240
TOTAL
Cost of 10 cum
Cost of 1 cum
Say

2.29
2.29.1
Code

114

128
114

2.26
2.26.2
Code

1728

Amount

888
888
888
88.8
88.8

Ploughing the existing ground to a depth of 15 cm to 25 cm


All kinds of soil
Description
Details of cost for 100 sqm
LABOUR:
Beldar

Unit

Quantity

Day

2.25

Rate

240

TOTAL
TOTAL
Cost of 100 sqm
Say
cost of 1 sqm
2.26
2.26.1
Code

Amount

1440
3168
4386.23
TOTAL
Cost of 100sqm
4386.23
cost of 1 sqm
43.86

TOTAL

OD 1 (2.2.1- Earth work in rough excavation exceeding 30 cm


2.3.1)
All kinds of soil
Code
Description
Details of cost for 10 cum.
LABOUR:

Rate

Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.
All kinds of soil
Description
Unit
Quantity
Details of cost for 10 cum
LABOUR:
Mate
Day
0.1
Beldar
Day
1.1

Rate

240
240
TOTAL
Cost of 10.0 cum
Cost of 1 cum
Say
Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.
Ordinary or hard rock
Description
Unit
Quantity
Rate
Details of cost for 10 cum
LABOUR:

Amount

540
540
540
540
540
5.4

Amount

24
264
288
288
28.8
28.8

Amount

128
114

Mate
Beldar

2.24
2.24.1
Code

Extra rates for quantities of works, executed:


In or under water and /or liquid mud, including pumping out water as required
Description
Extra due to slow progress and dewatering:
20% of the rate of the item
1* 20 =1 *20

Day
Day

Unit

0.2
1.95

240
240
TOTAL
Cost of 10.0 cum
Cost of 1 cum
Say

Quantity

48
468
516
516
51.6
51.6

Rate

Amount

0
TOTAL
Cost of 1.0 metre

20%
20%
20%

(20% of the rate of the item. The extra percentage in rate is applicable
in respect of each item but ltd. To quantities of work excuted in
difficult condition.)

Note for item no. 2.24:- The extra percentage rate is applicable in
respect of each item but limited to quantities of work executed in
these difficult conditions. The unit, namely, metre depth, to be
considered for payment, shall be the depth measured from the sub
soil water level up to the centre of gravity of the qty executed in
difficult condition. The depth shall be reckoned correct to 0.10m, 0.05
m or more shall be taken as 0.10 and less than 0.05m ignored.
0

2.25

Code

Filling available excavated earth (excluding rock) in trenches, plinth, sides of


foundations etc. in layers not exceeding 20 cm in depth, consolidating each
deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Description
Details of cost for 10 cum.
LABOUR:
128 Mate
115 Coolie
101 Bhisti

2.28
2.28.1
Code

114
115

2.31

Unit

Day
Day
Day

Surface dressing of the ground including removing vegetation and in-equalities


not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to
1.5 m.
All kinds of soil
Description
Unit
Details of cost for 10 sqm
LABOUR:
Beldar
Day
Coolie
Day

Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees
and saplings of girth up to 30 cm measured at a height of 1 m above ground
level and removal of rubbish up to a distance of 50 m outside the periphery of
the area cleared

Quantity

Rate

0.2
2.5
0.2

240
240
240
TOTAL
Cost of 10.0 cum
Cost of 1 cum
Say

Quantity

Amount

48
600
48
696
696
69.6
69.6

Rate

Amount

240
240
TOTAL
Cost of 100.0 sqm
Cost of 1 sqm
Say

472.8
309.6
782.4
782.4
7.82
7.82

1.97
1.29

Code

114
115

2.32
Code

114
115
TOTAL

Description
Details of cost for 100 sqm
LABOUR:
Beldar
Coolie

Clearing grass and removal of the rubbish up to a distance of 50 m outside the


periphery of the area cleared.
Description
Details of cost for 100 sqm
LABOUR:
Beldar
Coolie

Unit

Quantity

Day
Day

1.08
0.6

Unit

Day
Day

Rate

240
240
TOTAL
Cost of 100.0 sqm
Cost of 1 sqm
Say

Quantity

Rate

0.6
0.25

NREGA OD Earthwork in excavation by manual means over areas (exceeding 30cm in


depth, 1.5m in width as well as 10 m2 on plan) including disposal of excavated
80.2
earth lead upto 50m and lift upto 1.5m disposed earth to be levelled and neatly
dressed For foundation
All kinds of soil
Code
Description
Details for 10 cum
114 Beldar
115 Coolie

NREGA OD Earthwork in excavation by manual means over areas (exceeding 30cm in


depth, 1.5m in width as well as 10 m2 on plan) including disposal of excavated
80.3
earth lead upto 50m and lift upto 1.5m disposed earth to be levelled and neatly
dressed for Open areas
All kinds of soil
Code
Description
Details of cost for 120 cum
128 Mate
115 Coolie

Unit
Day
Day

Unit
Day
Day

Quantity

259.2
144
403.2
403.2
4.03
4.03

Amount

240
240

Cost of 100.0 sqm


Cost of 1 sqm
Say

NREGA OD Earthwork and surface dressing the side slopes of the water bodies by removing
80.1
grass, shrubs etc.with neatly levelling and finishing the surface with available
clayey soil.
Code
Description
Unit
Details of cost for 100sqm
115 Coolie
Day
114 Beldar
Day

Amount

144
60
204
204
2.04
2.04

Rate

Amount

240
240
TOTAL
Cost of 100.0 sqm
Cost of 1 sqm
Say

144
259.2
403.2
403.2
4.03
4.03/

0.6
1.08

Quantity

Rate

Amount

0.32
8

240
76.8
240
1920
TOTAL 1996.8
Cost of 10.0 cum 1996.8
Cost of 1 cum 199.68
Say 199.68/-

Quantity

Rate

Amount

240
240
TOTAL
Cost of 120.0 cum
Cost of 1 cum
Say

432
10800
11232
11232
93.6
93.6/-

1.8
45