CONSTRUCCIN DE

PARQUES ELICOS

The present document, its content, its annexes and/or amendments (the Document)
has been drawn up by GAMESA CORPORACIN TECNOLGICA, S.A. (Gamesa)
for information purposes only, and contains private and confidential information
regarding Gamesa and its subsidiaries (the Company), directed exclusively to its
addressee. Therefore it must not be disclosed, published or distributed, partially or
totally, without the prior written consent of Gamesa, and in any case expressly
indicating the fact that Gamesa is the owner of all the intellectual property. All the
content of the Document, whether it is texts, images, brands, trademarks, combination
of colours or any other element, its structure and design, the selection and way of
presenting the information, are protected by intellectual and industrial property rights
owned by Gamesa, that the addressee of the Document must respect. In particular
(notwithstanding the general confidentiality obligation), the addressee shall not
reproduce (except for private use), copy, transform, distribute or publish to any other
third party, any of the information, totally or partially.

June 2009

LA DIFERENCIA

GENERAL

GAMESA:

&
Infraestructuras
Elctricas(*)

Aerogeneradores
(WTG)
Grupo GAMESA (7000 personas):
Fabricante
WTG

GAMESA
EOLICA

Promotor de
Parques Elicos

GAMESA
ENERGIA

Esto implica un valor aadido en comparacin con la compra exclusiva de aerogeneradores, siendo posible
tener un perfecto control sobre todas las fases del proyecto elico..
(*) GAMESA no slo tiene su propio diseo de WTG, si no tambin uno propio para Subestaciones Elctricas (lo que hace posible una media de 12
subestacin por ao construidas de forma rpida y econmica).
04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

ORGANIZACIN INTERNACIONAL

GENERAL

DEPARTMENTO DE
CONSTRUCCIN

Sede en
ESPAA

Sede en
AMERICA

Sede en
EUROPA

Galicia (Santiago)

Portugal (Lisboa /Porto)

Aragn (Zaragoza)

Italy (Rome)

* Minneapolis (Navitas)

Catalua (Barcelona)

France (Lyon)

* Austn (Texas)

Castilla y Len (Valladolid)

Greece (Athens)

Castilla- La Mancha (Toledo)

UK (Newport)

Andaluca (Sevilla)

Germany (Oldenburg)
Poland (Warszawa)

USA * Philadelphia

FUNCIONES PRINCIPALES
DEPT. DE CONSTRUCCION

- Ingenieras
- Unidades de Obra
- Contratos
(central: en oficina)
CONSTRUCCIN DE P.P.E.E.

Beijing

Mexico

ESPECIFICACIONES

04 de Octubre de 2010

Sede en
CHINA

SUPERVISIN
- Calidad
- Precio
- Planning
(local: en el parque elico)
2

TABLA GESTIN DE CONSTRUCCIN DE PP.EE.


Estudios
Geotcnicos

Control Ambiental y
Arqueolgico

(contratista local)

(contratista local)

GAMESA ENERGA
(Gestin de la Construccin)

Ingeniera
Civil
(contratista local)

s
bid

(Diseo estndar Subestacin)


(contratista local Lneas)

Control de
Seguridad y Salud
(contratista local) (1)

Especificar/ Supervisar

Ingeniera
Elctrica
s
id

Equipos elctricos
principales
(ABB, Siemens, Areva,
ZIV, Arteche, )

(1)
(2)

GENERAL

bid

Control de Calidad
de la obra civil

(contratista local) (2)

Aerogeneradores

Obra
Civil

Montaje
Electromecnico

(Gamesa)

(contratista local)

(contratista local)

Segn la legislacin de algunos pases, es obligatorio tener un supervisor de S&S independiente de la compaa constructora
Nosotros preferimos dejar esta actividad fuera del alcance del contratista civil

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

ESTUDIOS PREVIOSFFRID PARA LA CONEXIN A LA RED

33 kV

14 MW

38 MW

P.E. Pen Coed


P.E.
Ffrid E & W

33 kV

Welshpool SS
132 kV
Sin interruptor

Ffrid & Pen Coed SS


Transformador
132/33 kV

SS Carno
132/33 kV

32 MW

PCC:
Conexin en T

SS Red
132 kV
Sin interruptor

SS Oswestry

SS Carno
ICC SIstema: 2,82 kA
ICC nominal aparamenta: 20 kA
ICC Disponibilidad: 17,2 kA
(*)
(*) P.E. I
: 0,57 kA
CC

SGSP
SS Legacy
400/132 kV

132 kV
12 km

PCC

ICC SIstema: 7,33 kA


ICC nominal aparamenta : 10,9 kA
ICC Disponibilidad : 3,6 kA
(*)
(*) P.E. I
: 0,57 kA
CC

Hacia
Legacy

P.E.
Ffrid
E&W
33 kV
P.E.
Pen Coed

132 kV
20 km
Capacidad trmica nominal:
Verano 80 MVA

132 kV
18 km
Capacidad trmica nominal:
Verano 80 MVA

P.E. Carno

SS Oswestry
132 kV
132 kV

132 kV
12 km

INGENIERA ELECTRICA

PCC

Hacia
P.E. Carno

Leyenda:

Leyenda:
Infraestructuras existentes
Nuevas infraestructuras

(*)

Incremento debido a la conexin de P.P.E.E. Ffrid & Pen


Coed

132 kV
33 kV

PROPUESTA DE CONEXIN A RED: T lnea 132 kV SS Carno SS Newtown/Welshpool


04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

ESTUDIO DE ACCESOS

INGENIERA CIVIL

Ensayo

Estudio terico
(P.E. Iardino)

P.E. Iardino (Italia) para G80 (2 MW)

P.E. Catefica (Portugal) para G80 (2 MW)


04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

DISEO DE CAMINOS INTERNOS

PLANOS DE CAMINOS ; Scale: 1/10000


- Anchura y radios de giro: O.K

Perfil longitudinal ; Scale: H: 1/2000 & V: 1/400


Pendientes: O.K
04 de Octubre de 2010

INGENIERA CIVIL

PLANOS DE PLANTA ; Scale: 1/2000


Ubicacin de AEG y propietarios implicados

Cortes transversales (cada 50 M) ; Scale: 1/500


- Clculo del movimiento de tierras
CONSTRUCCIN DE P.P.E.E.

DISEO DE PLATAFORMAS G5X (850 kW)

INGENIERA CIVIL

CONFIGURACIN DE PLATAFORMAS PARALELAS AL VIAL


ACOPIO

FORMA

DIMENSION

m2

Suelo
compactado
(m2)

21x13 m

273

189

25x12 m

300

300

25x15 m

375

300

21 m

1
2

13 m

(cutting road)

9m

4m

25 m

(without cutting
road)

12 m

9m

4m

Assembly in 2 phases:
Phase 1: T1 + T2
Phase 2: T3 + N

T1+T2&+T3+N
(without cutting
road)

25 m
3m
15 m

25 m
3m

T2
15 m

Phase 1

Phase 2

9m

T1

4m

T3

4m

9m

CONFIGURACIN DE PLATAFORMAS DE FINAL DE VIAL


ACOPIO

FORMA
4m

m2

30x12 m

360

30x15 m

450

360

30x20 m

600

360

9m

8m

Suelo
compactado(m2
)

DIMENSION

360

30 m
30 m

N+T1+T2

4m

9m

11 m
3m

3 N+T1+T2+T3
Masgaln (Galicia): G52
04 de Octubre de 2010

T1

T2

4m

N
N

16 m

T55m

8m

T1

T2

9m

T3
30 m

CONSTRUCCIN DE P.P.E.E.

DISEO DE PLATAFORMAS G8X-G90 (2 MW)

INGENIERA CIVIL

CONFIGURACIN DE PLATAFORMAS PARALELAS AL VIAL


ACOPIO

FORMA

DIMENSION

m2

30x18 m

540

Suelo
compactado
(m2)
540

30x23 m

740

740

30x30 m

950

740

30 m

Nothing

N+T1

13 m

18 m
5m
30 m

23 m

13 m
5m
5m

30 m

3
2

N+T1+T2+T3

13 m

30 m
5m
5m

CONFIGURACIN DE PLATAFORMAS DE FINAL DE VIAL


Vial

ACOPIO

FORMA

DIMENSION

m2

30x20 m

625

Suelo
compactado
(m2)
625

30x24 m

745

625

30x27 m

835

625

30 m
20 m

Plataforma

5m

13 m

N
30 m

N+T1

Zanja
(paralelo
a vial)
Mountlouby (Francia): G87
04 de Octubre de 2010

T67m

5m

13 m

24 m
1
30 m
N

5m

N+T1+T2+T3

13 m

27 m

CONSTRUCCIN DE P.P.E.E.

2
3

ESTUDIO DE MONTAJE DE WTG

(Ejemplo de WTG A18, Entredicho W.F., Zaragoza, Espaa)


Montaje de rotor completo WTG

INGENIERA CIVIL

Ensamblaje del brazo de la gra

NOTA: El A18 es el WTG ms complicado para levantar en el P.E. (la plataforma al final del vial, en la cima de una colina,
elevacin en el momento).

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

INGENIERA DE SUBESTACIONES (I)


(Ejemplo de diagrama unifilar)

INGENIERA ELCTRICA

(P.E. Crookwell 330 kV subestacin, Australia)

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

10

INGENIERA DE SUBESTACIONES (II)


(Ejemplo de planos de planta y alzado)
(P.E. Crookwell 330 kV subestacion, Australia)

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

INGENIERA ELCTRICA

11

INGENIERA DE SUBESTACIONES (III)


(Planos tpicos; Ejemplo: Interruptor 220 kV)

INGENIERA ELCTRICA

MONTAJE

CIMENTACIONES

ESTRUCTURA METLICA

04 de Octubre de 2010

DIAGRAMAS DE CONTROL

CONSTRUCCIN DE P.P.E.E.

12

INGENIERA DE LNEAS ELCTRICAS

(Tpica lnea 220 kV)


(Planos de planta y alzado de la trayectoria, detalle de estructuras)

INGENIERA ELCTRCIA

32,7 m

TORRE FIN DE LNEA


04 de Octubre de 2010

4,40 m
DRAGO
TIPICA TORRE 220 kV
CONSTRUCCIN DE P.P.E.E.

13

TPICA CIMENTACIN (G58, Torre 55m)

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

CONSTRUCCIN DE CIMENTACIONES

14

HORMIGONADO DE ZAPATAS

CONSTRUCCIN DE CIMENTACIONES
Hormign

VIROLA
Acero B-500-S

Cimentacin tpica

G58:
G90:

Hormign
HA-30
(m3)

Acero
B500-S
(kg)

100
333

8000
48000

Capacidad tpica de camin


hormigonera= 10 m3

Fibra tica
04 de Octubre de 2010

Entrada/Salida cables MT
CONSTRUCCIN DE P.P.E.E.

15

CIMENTACIN ESPECIAL PILOTADA

CONSTRUCCIN DE CIMENTACIONES

- P.E. Monte Cute (Basilicata, Italia)


- G83 (2MW)
- Empleada en suelos con una compactacin no ptima.

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

16

CIMENTACIN TERMINADA (G58)

(pendiente recubrir con material de excavacin)

CONSTRUCCIN DE CIMENTACIONES

ENTRADA CABLES MT

SALIDA CABLES MT
(PROTEGIDOS CON HORMIGN)

FIBRA PTICA

ANILLO DE TIERRA
(Cu 90mm2)

UBICACIN
ARMARIO
GROUND
04 de Octubre de 2010

UBICACIN
CELDA MT
CONSTRUCCIN DE P.P.E.E.

17

CABLES MT

04 de Octubre de 2010

REDES

CONSTRUCCIN DE P.P.E.E.

18

FIBRA PTICA - COMUNICACIONES

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

REDES

19

TPICA ZANJA MT & FO

REDES

TERRENO NORMAL
BAJO VIALES O CARRETERAS

NOTA: Unidades en metros


04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

20

EXCAVACIN DE ZANJAS

JCB (EXCAVADORA TRADICIONAL)

04 de Octubre de 2010

REDES

ZANJADORA ESPECIAL
(Alta eficiencia, control automtico de profundidad de zanja,
bajo impacto ambiental)
CONSTRUCCIN DE P.P.E.E.

21

ZANJAS CON CABLES / FIBRA PTICA ENTUBADA


TUBO DE FIBRA PTICA

04 de Octubre de 2010

CRUZAMIENTO

CONSTRUCCIN DE P.P.E.E.

REDES

CINTA DE SEALIZACIN

22

DIMENSIONES DE LOS CAMINOS

CONSTRUCCIN DE VIALES

ANCHURA:
G52-G58: 4 m
G8X-G90: 5 m

PENDIENTES MXIMAS:
G52-G58-G8X-G90: 12 %

MINIMUN CURVE RADIUS:


G52-G58: 20 m
G80-G83: 30 m
G87-G90: 32 m

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

23

VIAL TPICO

CONSTRUCCIN DE VIALES

CUNETAS

W.F. TARDIENTA (2001), Huesca, Espaa


04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

24

PENDIENTES

CONSTRUCCIN DE VIALES

ZANJA DE CABLE DE MT (PENDIENTE<30%)


PENDIENTE MXIMA
12 %

SIERRA DEL TRIGO P.E. (2001), Jan, Espaa


04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

25

TRANSPORTE DE VIROLAS

MONTAJE WTG

Camin
adicional de
ayuda

VIROLA

P.E. Monte Cute (Basilicata, Italia)


04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

26

TRANSPORTES COMPONENTES AEROGENERADOR

MONTAJE WTG

Nacelle G8X (2 MW) de 72 T


Palas G58 (850 kW) de 28,3 m

Primer tramo G8X (2 MW), 17 m, 50 T

Palas G80 (2 MW) de 40 m


04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

27

GRAS PARA G8X/G90-2 MW MONTAJE (I)

GRA CON NEUMTICOS

GRA CON CADENAS

Ventajas: No requiere desmontar la gra entre WTGs


Desventajas: Requiere caminos de 10-12 metros de ancho

350 T

04 de Octubre de 2010

MONTAJE WTG

Ventajas:
Desventajas:

Requiere caminos de 4-5 metros de anchera


Requiere hacer un MOB/DEMOB entre cada WTGs

650 T

CONSTRUCCIN DE P.P.E.E.

28

GRAS G8X/G90-2 MW MONTAJE (II)

MONTAE WTG

GRA CON CADENAS DE VA ESTRECHA (GVE)

Gra Especial
(muy pocas en Europa)
Ventajas:
- Caminos de tan solo 4,5 m
- No MOB/DEMOB entre WTGs

500 T

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

29

INSTALACIN EQUIPOS EN EL GROUND DE TORRE


HUB

CELDA

MONTAJE WTG

ARMARIO CONTROL
GROUND

TRANSFORMADOR
20 kV/690 V
CIMENTACIN

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

30

FASES EN ELEVACIN DE AEROGENERADOR


G58-55m (CON CAMIN GRA)

G58
850 kW Torre 55 m

G80
2 MW -Torre 100 m

G58
850 kW Torre 55 m

MONTAJE WTG

G80-100m (CON GRA ESPECIAL)

G80
2 MW -Torre100 m

P.E. CARRASQUILLO (Burgos, Espaa, 2002)


G58:
850 kW
G80: 2000 kW
04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

31

TCNICAS ELEVACIN DEL ROTOR (G80)

Terreno plano (con mucho espacio)

Terreno complejo (poco espacio)

ELEVACIN
CON ROTOR MONTADO EN SUELO

04 de Octubre de 2010

MONTAJE WTG

ELEVACIN
PALA POR PALA

CONSTRUCCIN DE P.P.E.E.

32

PLANNINGS

PLANNING

(PARQUE ELICO 50 MW)

ACTIVIDAD

MES 1

MES2

MES 3

MES 4

MES 5

MES 6

MES 7

MES 8

MES 9

MES 10

MES 11

MES 12

OBRA CIVIL DE PARQUE


OBRA CIVIL SUBESTACION
EDIFICIO CONTROL SUBESTACION
MONTAR SUBESTACIN
LINEAS MT Y F.O.
MONTAJE DE AEROGENERADORES

(3)

(1)
(2)

LINEA ALTA TENSION

(4)

PUESTA EN MARCHA

NOTA: (1)

Montando 3 aeros (G58) / semana.

(2)

Para una lnea150 kV de15 km.

PUNTO
CONEXIN

(3)

Cuidado con empezar demasiado pronto con el montaje (en


relacin con el avance del resto de actividades) se podra tener
altos costes financieros con todos los aeros montados y sin
produccin.

PRIMERO

(4)

Tras la PEM del ltimo aero hay un perodo de 120 horas de


operacin ininterrupida antes de la aceptacin provisional.

04 de Octubre de 2010

CONSTRUCCIN DE P.P.E.E.

LNEA

SEGUNDO

SUBSTACIN

TERCERO

PARQUE ELICO

LTIMO

ORDEN CRONOLGICO
33

DIFICULTADES DE CONSTRUCCIN PLATAFORMA


G8X (2 MW)

MONTAJE WTG

Los principales problemas al construir un P.E. con mquina grande (2 MW, G8X y G9X)
frente a con mquina pequea (850 kW, G5X) son:
Exterior P.E.:

Interior P.E.:

Maquinara

04 de Octubre de 2010

-Dimensiones de carreteras regionales/locales de acceso al parque.


-

Viales ms anchos
Plataformas mayores para la elevacin del aerogenerador

- Transportes especiales (son difciles de enecontrar)


- Gras especiales, de grandes dimensiones (son difciles de encontrar)

CONSTRUCCIN DE P.P.E.E.

34

GESTIN DE RIESGOS

Gestin de Riesgos
Caso de estudio 1
CONEXIN TEMPORAL DE 7 P.E. (236 MW) EN TAJO LA ENCANTADA (Subestacin REE)
(Mlaga Espaa, 2008)

= enterrado

Fuera de
servicio
hasta
Marzo de
2009

Nueva po sicin 8
(Parques elicos)
En construccin

Paso a cable
subterrneo

Bay 7

Bay 4

Lnea 220 Kv desde P.E.

Lnea 220 kV
a P.E.

Problema: La Compaa Elctrica no termin a tiempo la posicin de conexin de 7 parques elicos.


Solutcin: Conexin a red mediante cable seco hasta el 4 Grupo de Generacin de ENDESA (ver diagrama arriba) que estaba fuera de servicio por
una avera.
Coste: 612k (Inversin recuperada con 30 horas de Produccin a Plena Potencia).
Planning: Se haba desarrollado en 3 meses (incluyendo temas de promocin).
Ventajas: 7 Parques Elicos de 236 MW estuvieron generando energa durante 6 de los meses ms ventosos del ao.

Gestin de Riesgos
Caso de estudio 2
P.E. ESCEPAR Y PERALEJO CIMENTACIONES ERRONEAS
(Cuenca Espaa, 2006)

Problema: Algunas de las cimentaciones de aerogeneradores que se ejecutaron primero, se construyeron segn un plano
Solucin: Aadir una losa de refuerzo y fijarla con nuevas barras de acero taladradas en las losas anteriores de la cimentacin errnea.
Cost: 2.000.000.
Planning: 6 meses.
Ventajas: La pronta deteccin del problema permiti energizar 2 P.P.E.E. antes de fin del ao (alcanzando el objetivo marcado).

Gestin de Riesgos
Caso de estudio 3
REFUERZO DE PUENTES EN CARRETERA ACCESO A P.E. FLORINAS
(Sardinia - Italia, 2003)

BOCA

BOCA

BANDEJA DE CABLE

La carretera de acceso a este parque incluye cruzar 5 puentes, con las siguientes implicaciones:
Caso A:
Problema:
Las carreteras de acceso al parque incluye tener que cruzar un puente que necesita ser reforzado para que los transportes
puedan pasar de forma segura.
Solucin:
El refuerzo consiste en fijar la viga metlica en los dos extremos del puente y asfaltar la carretera.
Caso B:
Problema:
La red de media tensin del parque cruza el puente.
Solucin:
Los cables MT cruzan el puente en una bandeja de cables elctricos.
Coste: Sobre 0,7 M.
Planning: Ejecucin durante 3 meses.
Vnetajas: Los transportes pueden cruzar el puente y no se modifica el planning objetivo inicial.

BANDEJA CABLE

BOCA
VIGA
METAL

COLUMNA

FOUNDATION

Gestin de Riesgos
Caso de estudio 4

Inicio del
Bypass
temporal

CONEXIN TEMPORAL DE P.E. SAN FRANCESCO


(Calabria Italia, 2010)
Lnea elctrica
bypass

Interruptor de
la posicin de P.E.
Futura
subestacin
TERNA

CONEXIN
TEMPORAL

Problema: Las instalaciones elctricas de TERNA


(Compaa elctrica italiana) se espera que estn
terminadas para Junio de 2011, y el parque ya est
finalizado.
Solucin: Conexin temporal que consiste en un
bypass de la lnea cercana a la subestacin TERNA.
Coste: 200 k.
Planning: 1 mes de instalacin en paralelo con la
construccin de la subestacin.
Ventaja: Adelantar 6 meses la puesta en marcha del
parque.

Gestin de Riesgos
Caso de estudio 5
VIROLAS FUERA DE TOLERANCIA DE NIVELACION EN BII NEE STIPA
(Oaxaca - Mexico, 2009)
Problema: Despus de la ejecucin de la cimentacin del
WTG y antes d emontar la seccin inferior de la torre, el
mximo desnivel (+/- 2mm) entre varios puntos sobre la brida
de cimentacin es comprobado segn EQ209006.
Solucin: Se mont una arandela correctora porque el
mximo desnivel superaba el valor de 4 mm.

Coste: 10K por cimentacin


Planning: Contacto directo con un fabricante local y siguendo las
medidas tomadas in situ por el topgrafo.
Ventajas: Reducir el tiempo de suministro desde Europa de la arandela
correctora. Constacto directo entre el fabricante local y los tcnicos
responsables de calidad para esta solucin.

Correcting washer

Gestin de Riesgos
Caso de estudio 6
TRANSPORTE DE PALAS PARA CRUZAR UN PASO ESTRECHO
(P.E. Iardino, Durazzano Village - Italia)

Problema: Punto estecho en un pueblo.


Solution: Uso de dos gras.
Cost: 200 k (extra coste de gras).
Planning: 1 maniobra/da.
Ventajas: Construir el P.E. sin necesidad de hacer bypass del
pueblo (muy caro).

Gestin de Riesgos
Caso de estudio 7
CORRIMEINETOS EN CARRETERA DE ACCESO
(Cerro de la Higuera W.F. , 50 MW, Mlaga - Spain)

Corte
carretera

Corrimiento

Carretera antes de reparacin

Limpieza de terreno malo (8m prof)

Relleno de suelo adecuado

Problema: Corriemiento debido a las fuertes lluvias ocasionando cortes en la carretera pblica correspondiente al acceso del P.E. (la
Administracin de negaba a reparalo en un tiempo reducido).
Solucin: Hacer un estudio geotcnico rpido y un estudio de reparacin rpido. Cost: 250 k.
Planning: 4 semanas.
Ventajas: Sin retraso en la puesta en marcha del P.E. (ahorro 3 M).

Gestin de Riesgos
Caso de estudio 8
INCENDIO PROVOCADO POR SABOTAJE EN SUBESTACIN DE PARQUE
(P.E. Serra Pelata, 42 MW, Calabria - Italia)

Cuarto celdas proteccin

Almacn

Cuarto control

Problema: Unos intrusos prendieron fuego a la sala de control y alamcn (pero curiosamente no ocurri nada en la sala de protecciones
slo queran hacernos una advertencia).
Solucin: Refuerzo del grupo de operacin local en subestacin, aumentndolo a 6 personas con turnos de da y noche en la sala de
protecciones. Cost: 300 k.
Planning: 2 meses de reparaciones (suministrando nuevos oredenadores para sala de control).
Ventajas: Solo dos semanas de paralizacin (por razones de seguros y poltica).

Gestios de Riesgos
Caso de estudio 9
PLATAFORMA PARA ALMACENAMIENTO TEMPORAL DE WTGs
(P.E. Zettingen, 12 MW, 5xN90T100 Nordex, Rhineland Palatinate, Alemania)

Problema: Reparacin de un puente cercano por parte de las autoridades locales que durante varios meses interrupir el paso de los
transportes de aerogeneradores + conseguir autorizacin de los propietarios de terreno para crear una plataforma de almacenamiento.
Solucin: Instalacin provisional de provisional installation of placas de acero (evitando obra civil).
Coste: 312 k (alquiler de placas).
Planning: un par de das.
Ventajas: Posibilidad de hacer montaje en el momento sin retrasos.