The present document, its content, its annexes and/or amendments (the Document)
has been drawn up by GAMESA CORPORACIN TECNOLGICA, S.A. (Gamesa)
for information purposes only, and contains private and confidential information
regarding Gamesa and its subsidiaries (the Company), directed exclusively to its
addressee. Therefore it must not be disclosed, published or distributed, partially or
totally, without the prior written consent of Gamesa, and in any case expressly
indicating the fact that Gamesa is the owner of all the intellectual property. All the
content of the Document, whether it is texts, images, brands, trademarks, combination
of colours or any other element, its structure and design, the selection and way of
presenting the information, are protected by intellectual and industrial property rights
owned by Gamesa, that the addressee of the Document must respect. In particular
(notwithstanding the general confidentiality obligation), the addressee shall not
reproduce (except for private use), copy, transform, distribute or publish to any other
third party, any of the information, totally or partially.
June 2009
LA DIFERENCIA
GENERAL
GAMESA:
&
Infraestructuras
Elctricas(*)
Aerogeneradores
(WTG)
Grupo GAMESA (7000 personas):
Fabricante
WTG
GAMESA
EOLICA
Promotor de
Parques Elicos
GAMESA
ENERGIA
Esto implica un valor aadido en comparacin con la compra exclusiva de aerogeneradores, siendo posible
tener un perfecto control sobre todas las fases del proyecto elico..
(*) GAMESA no slo tiene su propio diseo de WTG, si no tambin uno propio para Subestaciones Elctricas (lo que hace posible una media de 12
subestacin por ao construidas de forma rpida y econmica).
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
ORGANIZACIN INTERNACIONAL
GENERAL
DEPARTMENTO DE
CONSTRUCCIN
Sede en
ESPAA
Sede en
AMERICA
Sede en
EUROPA
Galicia (Santiago)
Aragn (Zaragoza)
Italy (Rome)
* Minneapolis (Navitas)
Catalua (Barcelona)
France (Lyon)
* Austn (Texas)
Greece (Athens)
UK (Newport)
Andaluca (Sevilla)
Germany (Oldenburg)
Poland (Warszawa)
USA * Philadelphia
FUNCIONES PRINCIPALES
DEPT. DE CONSTRUCCION
- Ingenieras
- Unidades de Obra
- Contratos
(central: en oficina)
CONSTRUCCIN DE P.P.E.E.
Beijing
Mexico
ESPECIFICACIONES
04 de Octubre de 2010
Sede en
CHINA
SUPERVISIN
- Calidad
- Precio
- Planning
(local: en el parque elico)
2
Control Ambiental y
Arqueolgico
(contratista local)
(contratista local)
GAMESA ENERGA
(Gestin de la Construccin)
Ingeniera
Civil
(contratista local)
s
bid
Control de
Seguridad y Salud
(contratista local) (1)
Especificar/ Supervisar
Ingeniera
Elctrica
s
id
Equipos elctricos
principales
(ABB, Siemens, Areva,
ZIV, Arteche, )
(1)
(2)
GENERAL
bid
Control de Calidad
de la obra civil
Aerogeneradores
Obra
Civil
Montaje
Electromecnico
(Gamesa)
(contratista local)
(contratista local)
Segn la legislacin de algunos pases, es obligatorio tener un supervisor de S&S independiente de la compaa constructora
Nosotros preferimos dejar esta actividad fuera del alcance del contratista civil
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
33 kV
14 MW
38 MW
33 kV
Welshpool SS
132 kV
Sin interruptor
SS Carno
132/33 kV
32 MW
PCC:
Conexin en T
SS Red
132 kV
Sin interruptor
SS Oswestry
SS Carno
ICC SIstema: 2,82 kA
ICC nominal aparamenta: 20 kA
ICC Disponibilidad: 17,2 kA
(*)
(*) P.E. I
: 0,57 kA
CC
SGSP
SS Legacy
400/132 kV
132 kV
12 km
PCC
Hacia
Legacy
P.E.
Ffrid
E&W
33 kV
P.E.
Pen Coed
132 kV
20 km
Capacidad trmica nominal:
Verano 80 MVA
132 kV
18 km
Capacidad trmica nominal:
Verano 80 MVA
P.E. Carno
SS Oswestry
132 kV
132 kV
132 kV
12 km
INGENIERA ELECTRICA
PCC
Hacia
P.E. Carno
Leyenda:
Leyenda:
Infraestructuras existentes
Nuevas infraestructuras
(*)
132 kV
33 kV
CONSTRUCCIN DE P.P.E.E.
ESTUDIO DE ACCESOS
INGENIERA CIVIL
Ensayo
Estudio terico
(P.E. Iardino)
CONSTRUCCIN DE P.P.E.E.
INGENIERA CIVIL
INGENIERA CIVIL
FORMA
DIMENSION
m2
Suelo
compactado
(m2)
21x13 m
273
189
25x12 m
300
300
25x15 m
375
300
21 m
1
2
13 m
(cutting road)
9m
4m
25 m
(without cutting
road)
12 m
9m
4m
Assembly in 2 phases:
Phase 1: T1 + T2
Phase 2: T3 + N
T1+T2&+T3+N
(without cutting
road)
25 m
3m
15 m
25 m
3m
T2
15 m
Phase 1
Phase 2
9m
T1
4m
T3
4m
9m
FORMA
4m
m2
30x12 m
360
30x15 m
450
360
30x20 m
600
360
9m
8m
Suelo
compactado(m2
)
DIMENSION
360
30 m
30 m
N+T1+T2
4m
9m
11 m
3m
3 N+T1+T2+T3
Masgaln (Galicia): G52
04 de Octubre de 2010
T1
T2
4m
N
N
16 m
T55m
8m
T1
T2
9m
T3
30 m
CONSTRUCCIN DE P.P.E.E.
INGENIERA CIVIL
FORMA
DIMENSION
m2
30x18 m
540
Suelo
compactado
(m2)
540
30x23 m
740
740
30x30 m
950
740
30 m
Nothing
N+T1
13 m
18 m
5m
30 m
23 m
13 m
5m
5m
30 m
3
2
N+T1+T2+T3
13 m
30 m
5m
5m
ACOPIO
FORMA
DIMENSION
m2
30x20 m
625
Suelo
compactado
(m2)
625
30x24 m
745
625
30x27 m
835
625
30 m
20 m
Plataforma
5m
13 m
N
30 m
N+T1
Zanja
(paralelo
a vial)
Mountlouby (Francia): G87
04 de Octubre de 2010
T67m
5m
13 m
24 m
1
30 m
N
5m
N+T1+T2+T3
13 m
27 m
CONSTRUCCIN DE P.P.E.E.
2
3
INGENIERA CIVIL
NOTA: El A18 es el WTG ms complicado para levantar en el P.E. (la plataforma al final del vial, en la cima de una colina,
elevacin en el momento).
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
INGENIERA ELCTRICA
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
10
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
INGENIERA ELCTRICA
11
INGENIERA ELCTRICA
MONTAJE
CIMENTACIONES
ESTRUCTURA METLICA
04 de Octubre de 2010
DIAGRAMAS DE CONTROL
CONSTRUCCIN DE P.P.E.E.
12
INGENIERA ELCTRCIA
32,7 m
4,40 m
DRAGO
TIPICA TORRE 220 kV
CONSTRUCCIN DE P.P.E.E.
13
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
CONSTRUCCIN DE CIMENTACIONES
14
HORMIGONADO DE ZAPATAS
CONSTRUCCIN DE CIMENTACIONES
Hormign
VIROLA
Acero B-500-S
Cimentacin tpica
G58:
G90:
Hormign
HA-30
(m3)
Acero
B500-S
(kg)
100
333
8000
48000
Fibra tica
04 de Octubre de 2010
Entrada/Salida cables MT
CONSTRUCCIN DE P.P.E.E.
15
CONSTRUCCIN DE CIMENTACIONES
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
16
CONSTRUCCIN DE CIMENTACIONES
ENTRADA CABLES MT
SALIDA CABLES MT
(PROTEGIDOS CON HORMIGN)
FIBRA PTICA
ANILLO DE TIERRA
(Cu 90mm2)
UBICACIN
ARMARIO
GROUND
04 de Octubre de 2010
UBICACIN
CELDA MT
CONSTRUCCIN DE P.P.E.E.
17
CABLES MT
04 de Octubre de 2010
REDES
CONSTRUCCIN DE P.P.E.E.
18
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
REDES
19
REDES
TERRENO NORMAL
BAJO VIALES O CARRETERAS
CONSTRUCCIN DE P.P.E.E.
20
EXCAVACIN DE ZANJAS
04 de Octubre de 2010
REDES
ZANJADORA ESPECIAL
(Alta eficiencia, control automtico de profundidad de zanja,
bajo impacto ambiental)
CONSTRUCCIN DE P.P.E.E.
21
04 de Octubre de 2010
CRUZAMIENTO
CONSTRUCCIN DE P.P.E.E.
REDES
CINTA DE SEALIZACIN
22
CONSTRUCCIN DE VIALES
ANCHURA:
G52-G58: 4 m
G8X-G90: 5 m
PENDIENTES MXIMAS:
G52-G58-G8X-G90: 12 %
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
23
VIAL TPICO
CONSTRUCCIN DE VIALES
CUNETAS
CONSTRUCCIN DE P.P.E.E.
24
PENDIENTES
CONSTRUCCIN DE VIALES
CONSTRUCCIN DE P.P.E.E.
25
TRANSPORTE DE VIROLAS
MONTAJE WTG
Camin
adicional de
ayuda
VIROLA
CONSTRUCCIN DE P.P.E.E.
26
MONTAJE WTG
CONSTRUCCIN DE P.P.E.E.
27
350 T
04 de Octubre de 2010
MONTAJE WTG
Ventajas:
Desventajas:
650 T
CONSTRUCCIN DE P.P.E.E.
28
MONTAE WTG
Gra Especial
(muy pocas en Europa)
Ventajas:
- Caminos de tan solo 4,5 m
- No MOB/DEMOB entre WTGs
500 T
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
29
CELDA
MONTAJE WTG
ARMARIO CONTROL
GROUND
TRANSFORMADOR
20 kV/690 V
CIMENTACIN
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
30
G58
850 kW Torre 55 m
G80
2 MW -Torre 100 m
G58
850 kW Torre 55 m
MONTAJE WTG
G80
2 MW -Torre100 m
CONSTRUCCIN DE P.P.E.E.
31
ELEVACIN
CON ROTOR MONTADO EN SUELO
04 de Octubre de 2010
MONTAJE WTG
ELEVACIN
PALA POR PALA
CONSTRUCCIN DE P.P.E.E.
32
PLANNINGS
PLANNING
ACTIVIDAD
MES 1
MES2
MES 3
MES 4
MES 5
MES 6
MES 7
MES 8
MES 9
MES 10
MES 11
MES 12
(3)
(1)
(2)
(4)
PUESTA EN MARCHA
NOTA: (1)
(2)
PUNTO
CONEXIN
(3)
PRIMERO
(4)
04 de Octubre de 2010
CONSTRUCCIN DE P.P.E.E.
LNEA
SEGUNDO
SUBSTACIN
TERCERO
PARQUE ELICO
LTIMO
ORDEN CRONOLGICO
33
MONTAJE WTG
Los principales problemas al construir un P.E. con mquina grande (2 MW, G8X y G9X)
frente a con mquina pequea (850 kW, G5X) son:
Exterior P.E.:
Interior P.E.:
Maquinara
04 de Octubre de 2010
Viales ms anchos
Plataformas mayores para la elevacin del aerogenerador
CONSTRUCCIN DE P.P.E.E.
34
GESTIN DE RIESGOS
Gestin de Riesgos
Caso de estudio 1
CONEXIN TEMPORAL DE 7 P.E. (236 MW) EN TAJO LA ENCANTADA (Subestacin REE)
(Mlaga Espaa, 2008)
= enterrado
Fuera de
servicio
hasta
Marzo de
2009
Nueva po sicin 8
(Parques elicos)
En construccin
Paso a cable
subterrneo
Bay 7
Bay 4
Lnea 220 kV
a P.E.
Gestin de Riesgos
Caso de estudio 2
P.E. ESCEPAR Y PERALEJO CIMENTACIONES ERRONEAS
(Cuenca Espaa, 2006)
Problema: Algunas de las cimentaciones de aerogeneradores que se ejecutaron primero, se construyeron segn un plano
Solucin: Aadir una losa de refuerzo y fijarla con nuevas barras de acero taladradas en las losas anteriores de la cimentacin errnea.
Cost: 2.000.000.
Planning: 6 meses.
Ventajas: La pronta deteccin del problema permiti energizar 2 P.P.E.E. antes de fin del ao (alcanzando el objetivo marcado).
Gestin de Riesgos
Caso de estudio 3
REFUERZO DE PUENTES EN CARRETERA ACCESO A P.E. FLORINAS
(Sardinia - Italia, 2003)
BOCA
BOCA
BANDEJA DE CABLE
La carretera de acceso a este parque incluye cruzar 5 puentes, con las siguientes implicaciones:
Caso A:
Problema:
Las carreteras de acceso al parque incluye tener que cruzar un puente que necesita ser reforzado para que los transportes
puedan pasar de forma segura.
Solucin:
El refuerzo consiste en fijar la viga metlica en los dos extremos del puente y asfaltar la carretera.
Caso B:
Problema:
La red de media tensin del parque cruza el puente.
Solucin:
Los cables MT cruzan el puente en una bandeja de cables elctricos.
Coste: Sobre 0,7 M.
Planning: Ejecucin durante 3 meses.
Vnetajas: Los transportes pueden cruzar el puente y no se modifica el planning objetivo inicial.
BANDEJA CABLE
BOCA
VIGA
METAL
COLUMNA
FOUNDATION
Gestin de Riesgos
Caso de estudio 4
Inicio del
Bypass
temporal
Interruptor de
la posicin de P.E.
Futura
subestacin
TERNA
CONEXIN
TEMPORAL
Gestin de Riesgos
Caso de estudio 5
VIROLAS FUERA DE TOLERANCIA DE NIVELACION EN BII NEE STIPA
(Oaxaca - Mexico, 2009)
Problema: Despus de la ejecucin de la cimentacin del
WTG y antes d emontar la seccin inferior de la torre, el
mximo desnivel (+/- 2mm) entre varios puntos sobre la brida
de cimentacin es comprobado segn EQ209006.
Solucin: Se mont una arandela correctora porque el
mximo desnivel superaba el valor de 4 mm.
Correcting washer
Gestin de Riesgos
Caso de estudio 6
TRANSPORTE DE PALAS PARA CRUZAR UN PASO ESTRECHO
(P.E. Iardino, Durazzano Village - Italia)
Gestin de Riesgos
Caso de estudio 7
CORRIMEINETOS EN CARRETERA DE ACCESO
(Cerro de la Higuera W.F. , 50 MW, Mlaga - Spain)
Corte
carretera
Corrimiento
Problema: Corriemiento debido a las fuertes lluvias ocasionando cortes en la carretera pblica correspondiente al acceso del P.E. (la
Administracin de negaba a reparalo en un tiempo reducido).
Solucin: Hacer un estudio geotcnico rpido y un estudio de reparacin rpido. Cost: 250 k.
Planning: 4 semanas.
Ventajas: Sin retraso en la puesta en marcha del P.E. (ahorro 3 M).
Gestin de Riesgos
Caso de estudio 8
INCENDIO PROVOCADO POR SABOTAJE EN SUBESTACIN DE PARQUE
(P.E. Serra Pelata, 42 MW, Calabria - Italia)
Almacn
Cuarto control
Problema: Unos intrusos prendieron fuego a la sala de control y alamcn (pero curiosamente no ocurri nada en la sala de protecciones
slo queran hacernos una advertencia).
Solucin: Refuerzo del grupo de operacin local en subestacin, aumentndolo a 6 personas con turnos de da y noche en la sala de
protecciones. Cost: 300 k.
Planning: 2 meses de reparaciones (suministrando nuevos oredenadores para sala de control).
Ventajas: Solo dos semanas de paralizacin (por razones de seguros y poltica).
Gestios de Riesgos
Caso de estudio 9
PLATAFORMA PARA ALMACENAMIENTO TEMPORAL DE WTGs
(P.E. Zettingen, 12 MW, 5xN90T100 Nordex, Rhineland Palatinate, Alemania)
Problema: Reparacin de un puente cercano por parte de las autoridades locales que durante varios meses interrupir el paso de los
transportes de aerogeneradores + conseguir autorizacin de los propietarios de terreno para crear una plataforma de almacenamiento.
Solucin: Instalacin provisional de provisional installation of placas de acero (evitando obra civil).
Coste: 312 k (alquiler de placas).
Planning: un par de das.
Ventajas: Posibilidad de hacer montaje en el momento sin retrasos.