Documente Academic
Documente Profesional
Documente Cultură
ACKNOWLEDGEMENT
We wish to express our deep sense of gratitude to our training & placement
officer Mr. Naveen Sharma and H.O.D. Mr. Neeraj for suggest and valuable
guidance us for S.T.P.S. It is our proud privilege to express our sense of
gratitude to Assistant Engineers for providing us adequate facilities to
undergo training at S.T.P.S.
We are thankful to Mr. B.P. Gautam (SE), Mr. Udaybhan Singh Shekhawat
(JEN) & Mr. Sandeep (JEN) for their valuable guidance and co-operation
without which it was not possible to get so much knowledge. We are also
Grateful to Mr. Ghanshyam Agarwal (AEN) & Mr. Ramesh Sethi (AEN),
their persistent help and for providing some of the technical data.
We are equally obliged to all those Engineers, Technical personnel And
operators at S.T.P.S. who gave us their valuable time and rendered practical
knowledge in our training period.
And at last we want to thank our colleagues. Without their help guidance and
suggestions it was not possible to produce this report.
CONTENTS
Location of SSTPS Suratgarh
General plant overview
Layout of Thermal Power Plant
Generator section
Generator Transformer Section
Electrostatic Precipitator
Switchyard Section
Turbine Section
Boiler Section
Coal Handling Plant
Ash Handling Plant
Plant Highlights
Bibliography
THERMAL POWER PLANT:General Layout of Thermal Power Plant:The general layout of plant consists of mainly four circuits. The four
circuits are
1. Coal and Ash Circuit
2. Air and Gas Circuit
3. Feed Water and Steam Circuit
4. Cooling Water System
In this circuit, the coal from the storage is fed to the boiler through
coal handling equipment for the generation of the steam. Ash
produced due to combustion of coal is removed to ash storage
through ash-handling system.
Feed Water and Steam Circuit:The steam generated in the boiler is fed to the steam prime mover to
develop the power. The steam coming out of the prime mover is
condensed in the condenser and then fed to the boiler with the help
of pump. The condensate is heated in the feed-heater using the
steam tapped from different points of the turbine. The feed heaters
may be of mixed type or indirect heating type. Some of the steam and
water are lost passing through different components of the system;
therefore, feed water is supplied from external source to compensate
this loss. The feed water supplied from external source to
compensate the loss. The feed water supplied from external source is
passed through the purifying plant to reduce to reduce dissolve salts
to an acceptable level. This purification is necessary to avoid the
scaling of the boiler tubes.
Cooling Water Circuit:The quantity of cooling water required to condense the steam is
considerably high and it is taken from a lake, river or sea. At the
Columbia thermal power plant is taken from an artificial lake created
near the plant. The water is pumped in by means of pumps and the
hot water after condensing the steam is cooled before sending back
into the pond by means of cooling towers. This is done when there is
not adequate natural water available close to the power plant. This is
a closed system where the water goes to the pond and is recirculated back into the power plant. Generally open systems like
rivers are more economical then closed systems.
Working of the Thermal Power Plant:Steam is generated in the boiler of the thermal power plant using
heat of the fuel brunt in the combustion chamber. The steam is
generated is passed through steam turbine where part of its thermal
energy is converted into mechanical energy which is further used for
generating electric power. The steam coming out of the steam turbine
is condensed in the condenser and the condensate is supplied back
to the boiler with the help of the feed pump and the cycle is repeated.
The function of the Boiler is to generate steam. The function of the
condenser is to condense the steam coming out of the low pressure
turbine. The function of the steam turbine is to convert heat energy
into mechanical energy. The function of the condenser is to increase
the pressure of the condensate from the condenser pressure to the
boiler pressure. The other components like economizer, super heater,
air heater and feed water heaters are used in the primary circuit to
increase the overall efficiency of the plant.
GENERATOR:-
Stator
Rotor
Excitation system
Cooling system
Sealing system
STATOR WINDING AND INSULATION:Stator core carries the armature winding where the voltage
is generated due to electromagnetic induction. Each stator
conductor must be capable of carrying the rated current
without overheating and the insulation must be sufficient to
prevent leakage current flowing between earth and phase.
The stator has a three phase double layer short core type
bar winding having two parallel paths. Each coil side consists
of glass insulated solid and hollow conductor with cooling
water passing through the latter in case of water cooled
conductors being used in higher capacity units. Water is fed
to and fro the winding throw Teflon tubes.
The stator winding conductors, both solid and hollow, are
transposed about a non magnetic duct, which provide the
flow path for the coolant gas in case of H 2 cooled generator.
In liquid cooled windings the transposed conductors are
rectangular tubes. The transposition can be done in no. of
ways but most commonly used method of transposition is
Roebel arrangement.
The rotor is cast chromium, nickel, molybdenum and
vanadium steel ingot and it is further forget and machined.
The rotor forging is then planed and milled to form the teeth.
Very often a hole is bored throw the center of the axially
from one end to the other for inspection. Slots are then
machined for winding and ventilation.
ROTOR:ROTOR WINDING AND RETAINING RINGS:The rotor carries the field windings. Silver bearing copper
(containing 0.03 to 0.1 % silver) is used for the winding with
mica as the insulation between conductors. A mechanically
strong insulator such as micanite is used for lining the slots.
Later designs of windings for circulation of the cooling gases
throw the actual conductors. When rotating at high speed,
centrifugal force tries to lift the winding out of the slots and
duralumin wedges contain them. The end turns outside the
slots are covered by non magnetic steel retaining end rings
are secured to a turned recess in the rotor body. By shrinking
Three Phase Pilot Exciter:Three phase pilot exciter has a revolving field with
permanent magnet poles. The controlled rectified d.c. is fed
to the main exciter field. The induced Three Phase a.c.
voltage is rectified in the rotating rectifier bridge and is fed
to the generator rotor winding through the d.c. leads in the
shaft. The pilot exciter has 16 poles. The output is 220V + 10%, 400 Hz. Ten magnets are housed together in a non
magnetic enclosure and this make one pole. These magnets
are braced between the hub and external pole shoe with
bolts.
Three Phase Main Exciter:The three phase main exciter is a six pole rotating armature
unit. The field poles with the damper windings are arranged
in the stator frame. Laminated magnetic poles are arranged
to form the field winding. To measure the exciter current a
quadrature axis coil is fitted between two poles.
The winding conductors are transposed within the core
length, and the end turns of the rotor windings are secured
with steel bands. The connections are made at rectifier
wheel end. A ring bus formed at the winding end and leads
to rotating rectifier wheel are also connected to the same.
The complete rotor is shrunk fit on the shaft. The rotor is
supported on a journal bearing positioned between the main
and the pilot exciters. Lubrication of the bearing is formed
from the turbine oil system.
The core
The windings
On load tap changer
Tanks
Bushings
Auxiliary equipments
Insulating oil
Cooling system
Installed Transformers
Station Transformer:When the unit is running, power required for L.T. and H.T.
switchgear is also be provided by this transformer. The rating
of this transformer is 220KV/6.6KV. In this type of
transformer primary and secondary is star connected.
Specification of Generator
Transformer:Type of cooling
Rating in MVA
No load voltage (HV) (kV)
No load voltage (LV) (kV)
Line current (Amp.)
HV
LV
Temp rise in oil (c)
Temp rise in windings (c)
No load loss/load loss/
Auxiliary loss (kW)
Short circuit capacity
HV:
LV:
Phases
Frequency
Connection symbol
ONAN/ONAF/OFAF
160/240/315
420
16.5
219.9/329.9/433.01
5598.5/8397.8/11022.1
45c over Ambient of 50c
50c over Ambient of 50c
145/600/19
40KA/3sec
101KA/3 sec
3
50 Hz
ynd11
HV LV normal tapping
HV LV max. Tapping
HV LV min. Tapping
Core and winding weight
Weight of oil
Total weight
14.5%-10%
14.27% approximately
14.47% approximately
112500 Kg.
56810 Kg
287545 Kg
40000/50000
220KV HV
105/135 HV
3
50
ONAN/ONAF
Ynyn0
44470
22780
86210
45230
25600
40c
50c
Auxiliary Control Panel (ACP):The ACP controls the power supply to the EP auxiliary viz.
rapping motor and heating elements dampers. The complete
ACP is of modular type with individual modules for each
feeder. Each module houses and the control circuits with
meters, push buttons, switches and indicating lamps.
Following are the modules for the outgoing feeders: Hopper heaters for each field.
Support insulator heaters.
Ash handling system:The fly ash handling system evacuates the fly ash from the
hoppers, and transports the fly ash to reprocessing or to
disposal. The ash handling system should be designed and
operated to remove the collected fly ash from the hoppers
without causing re-entrainment into the gas flow through the
precipitator. The design of the ash handling system should
allow for flexibility of scheduling the hopper discharges
according to the fly ash being collected in these hoppers.
Collecting Plate Rapping:Collecting plate rapping must remove the bulk of the
precipitated dust. The collecting plates are supported from
anvil beams or directly with hooks from the precipitator
casing. With anvil beam support, the impact of the rapping
system is directed into the beams located at the leading
and/or trailing edge of the collecting plates. For direct casing
support, the impact is directed into the rapper beams
located at or near the center of the top of the collecting
plates.
The first electrical field generally collects about 60-80% of
the inlet dust load. The first field plates should be rapped
often enough so that their precipitated layer of particulate is
about 3/8 - 1/2" thick. There is no advantage in rapping more
often since the precipitated dust has not yet agglomerated
to a sheet which requires a minimum layer thickness. Sheet
formation is essential to make the dust drop into the
precipitator hopper without re-entrainment into the gas
stream. Rapping less frequently typically results in a
deterioration of the electrical power input by adding an
additional resistance into the power circuit. Once an
optimum rapping cycle has been found for the first electrical
field (which may vary across the face of a large precipitator),
the optimum rapping cycles for the downstream electrical
fields can be established.
The collecting plate rapping system of the first field has a
repeat time T equal to the time it takes to build a 3/8 1/2"layer on the collecting plates. The plates in the second
field should have a repeat time of about 5T, and the plates in
the third field should have a repeat time of 25T. Ideally,
these repeat times yield a deposited layer of 3/8-1/2" for the
plates in all three fields. Adjustment may be required for
factors such as dust resistivity, dust layer cohesiveness, gas
temperature effects, electrical field height and length, and
the collecting area served by one rapper.
Improving
Performance:-
Rapping
System
Switch-Yard
TURBINE SECTION
INTRODUCTION:Steam turbine is a device which consist heat energy
mechanical energy. In India, steam turbine of different
capacity varying from 15-500MW, are employed in the field
of thermal power generation. The design material auxiliary
HIGH PRESSURE TURBINE:The outer causing of high pressure HP type turbine is of the
barrel type and has neither other as axial nor a radial flag.
This prevents mass accumulation with high terminal stress.
The almost perfect rotation symmetry permits maturate wall
thickness of nearly equal strength at all section.
The inner casing is axially split and kinematically supported.
As the pressure difference across the wall of inner casing is
low, the horizontal flag and connection belt can be kept
small. The barrel type casing permits flexibility of operation
in the form of short start-up time and a high rate of change
of load at high initial steam condition. Inlet steam
temperature and pressure is 538c and 150Kg/cm. Rotation
speed is 3000 rpm whose medium is steam.
LOW PRESSURE TURBINE:The casing of the double flow IP turbine is of their three-shell
design. The shell is axial split and has rigid welded
construction. The inner shell taking the first rows of guide
blades are attached cinematically in the middle.
The turbine has an electro hydraulic governing system
blacked up with a hydraulic governing. An electric system
measures and control speed and output and operates the
control valves hydraulic in conjunction with an electro
hydraulic governing system permits run up control of the
turbine up to rated speed and keeps speed swings following
sudden load shedding low. The liner output frequency
characteristics can be very closely set during operation .
IMPROVED
BOILER
METHOD
OF
HEATING
OF
GENERAL
CONSTRUCTION
OPERATION:-
OR
This boiler has divided by into these zones. In the zone first
transfer is preheated by radiation as the flam in the zone is
diffused yellow flam, which radiates much more than the
premixed blue flam. As the burnt gases upward and
secondary air is added. The effect of radiation is reduced,
becomes predominate as the flam changes from diffused to
premix.
The space marked by R+C receives heat by convention as
well as radiation provided suitable heat transfer surface is
including into path. The heat into zone 2 & 3 takes place
mainly convention. Zone two is identifying as high
temperature and 3 as low temperature zone. Zone two is
preferably for locating superheated air. Air is preheated
because we want to reduce the surface area requirement.
Zone three is used for economizer.
MAJOR PARTS OF A BOILER:In thermal plant boiler consists of many parts as discussed
below:-
STEAM DRUM INTERNALS:Steam drum as storage tank which is used to store the
steam and water. The function of the steam drum internals is
to separate water and steam from the mixture generated in
the furnace walls and to remove the desired solid content of
the steam to below the acceptable limit.
33c
8.31c
35,000m/hr.
2
15,664
CONDENSATE EXTRACTION PUMPS:This is used to feed the condensate water into low-pressure
heaters. This ump air of the vertical, eight stage, centrifugal
types. In steps, three pumps re located with condenser with
each boiler. In running conditions to the umps are used to
increase the efficiency of the boiler section of the plant.
MILL SECTION:INTRODUCTION:-
Coal handling plant deals with the under loading of the coal
racks, rushing of coal at different stages to stack the crusher
coal at the tock pile to feed the crushed coal to the coal
bunkers either irectly from the rack or stockpile stacked coal
through declaimer.
Coal handling plant is an important consistent of a plant. It
provides crushed coal to the bunker from where it is feed to
the ill in the coal mill; it gets transformed into the form of
water.
Coal wagons are unloaded at the wagon tippler. Here, it gets
rushed to 200mm size in the ruler crusher. This is the
primary tage crushing of the coal. This coal is feed to the
rotatory breaker throw conveyers belt system. In the rotary
barker the size of the coal is reduced up to 100 mm. the
secondary stage of crushing this coal. This coal is either
stacked at the stockpiles made for the storage of coal or it is
feed directly to the third stage.
In the third stage is feed either from the stacked coal at the
stockpile or directly from the rotary barker. While conveying
coal to the third stage crusher, as ILMS {In Line Magnetic
Separator} comes into the way. Here iron materials pieces
etc. get separated. The coal is feed to third stage crusher
where it is crushed into size of 10 mm. this coal feed to the
bunkers from where it is feed to the coal mills.
To unload the coal wagons or to crush coal and to stack it
and to feed it to coal bunkers. Various equipments and
conveyers are installed in coal handling plant.
Some of the important equipments are listed below: Wagon tippler
Roll crusher
In Line Magnetic Separator
Vibrating Feeder
Apron Feeder
Rotary Breaker
Ring Granulator
Grizzly Feeder
A brief description and working of above equipments is
explained below:-
Wagon tippler :-
Roll crusher:Roll Crushers are compression type crushers, and were once
widely used in mining. They have, within the last 10 or so
years, fallen into dis-favor among mining and processing
companies. The probable reason is because the large mines
require very large crushed product output with minimal cost,
makes the roll crusher uncompetitive. The roll crushers are
not nearly as productive as cone crushers, with respect to
volume, and they do have a little higher maintenance
associated with them. Roll crushers do, however, give a very
close product size distribution, and if the ore is not too
abrasive, they do not have high maintenance costs.
In Line Magnetic Separator:Type A magnetic separators utilize a number of closely
spaced north & south magnetic "poles" to create a powerful
magnetic field capture and retain small to medium sized
tramp metal contaminants. Type A magnet circuits are
ideally suited for applications such as final inspection of high
quality consumer food product. Type A magnets are
available in a wide range of models each having many
standard sizes to meet your specific magnetic application
and budget requirements.
Vibrating Feeder:Vibrating feeders are in operation worldwide and can be
found in mining and quarry operations, as well as aggregate,
chemical, and industrial processes. Some of the more
common feeder applications are in coal mining.
Apron Feeder:TENGL Apron Feeders are engineered for heavy-duty operation and for
primary or subsequent application stages. These custom-built machines are
1.Ring Granulator:-
Motor (H.P.)
400
600
800
1500
10
20
25
50
100-200
200-450
300-500
500-1200
|
|
|
|
15
30
40
100
TECHNICAL DATA:Application
System type
Eff. Dia. of shell
Eff. Length of shell
Shell (rpm)
Total weight of balls
No. of lines
Main motor reducer gain ratio
Bearing type
Coupling type
Lubricant oil temp.
Main motor rating
Auxiliary motor rating
Coal Feeder
Coal Classifier
Speed Reducer
Valve or Damper
Coal Feeder:The coal has come back into the spotlight as an alternative
energy source in thermal power generating facilities around
the world. The coal-fired power plant is increase in the
privately owned electrical power facilities.
We have been known for decades as established
manufacture of weighing equipments that are capable of
working in such a harsh environment.
Valve or Damper:-
PLANT HIGHLIGHTS
The teco-economic clearness for the project was issued
by CEA in June 1991.
The updated or total cost of the stage-1 and stage-2
projects is estimated at 2300 crores or 2050 crores
(including IDC).
It is one of the thermal power station of Rajasthan
which was produces a 1250 MW and 250 MW in each
unit of power.
In STPS the computerized coutronic-E band control and
instrumentation system. The main advantage of this
system is that of any engineer in harmony could be
operates any problems in STPS stage system.
This thermal plant was made before completes its time
or period. So that a lot of money was saved.
The cooling (air conditioner) process is also so good at
all section of STPS.
In this plant the 400 KV and 200 KV switchyard has
been consisted it is first in our country.
Bibliography:
www.powerelectrical.blogspost.com
www.softech-engr.com
www.titanindia.com
www.springerlink.com
www.worldwes.com
A complete book on Thermal Plant Engg. By H.G.Hugg.
STPS Workers
www.dte.rajasthan.gov.in
www.en.wikipedia.org
www.rajenergy.com