Documente Academic
Documente Profesional
Documente Cultură
Introduction
Amoco Trinidad produces from three offshore fields
near Trinidad in the West Indies. As shown in Fig. 1,
these are the Samaan, Teak, and Poui fields. These
fields produce from Miocene-age sands and contain
both oil and gas wells. Although sand production exists,
the Samaan and Poui fields do not have the same degree
of sand-control problems as does the Teak field. After
discovery of the Teak field, it became apparent that
some type of sand control would be necessary; the two
types of control chosen were triple-wrap screens and
gravel packing.
Initially, wells completed with the triple-wrap screen
were capable of high producing rates; therefore, emphasis was placed on this type of installation. At the
same time, wells that were completed with gravel packs
were perfonning poorly. Although attempts were being
made to stop sand production down hole and the
triple-wrap screens appeared to be working, trace
amounts of sand were continually being produced from
all wells. These traces of sand were sufficient to erode
choke manifolds and flowlines and to fill up onshore
and offshore separators. A triple-wrap screen was
pulled after only 21 days on production. This screen, as
shown by Fig. 2, had multiple eroded holes. Shortly
thereafter, a gravel-pack screen that was pulled after
less than 2 weeks on production had similar eroded
holes. Subsequently, most wells pulled had holes
eroded in the screens. At this time, a project was initiated to determine the optimum sand-control technique
for these operations. Using specially designed wellbore
Project Objectives
Our basic approach to this sand-control problem had
been to stop the migration of sand down hole by installation of either the conventional gravel pack or triplewrap screen. Neither system was completely successful
because of erosion of the screens, chokes, flowlines,
and valves by produced sand. Disposal of the produced
sand was also a problem. The primary purpose of the
project was to find a way to stop sand production and
maintain high productive capacity.
The objectives of this project were to (l) evaluate a
conventional gravel pack, where gravel is placed only
in the annulus between the screen and casing; (2)
evaluate the effectiveness of prepacking or placing
gravel outside the casing in conjunction with a gravel
pack; (3) compare the triple~wrap' screen with gravel'
packing to detennine which would better retain sand
and allow maximum productivity; and (4) compare
open-hole and perforated-casing completions with
gravel packs and triple-wrap screens.
Experimental Procedures
Apparatus - Wellbore Simulators
Wellbore models were designed to simulate a 1-ft pro-
979
.i
i
SAMAAN
TRINIDAD
;'
Pt.Galeota
:....
"""-'-'-'-'_'_'
Fig. 1 -
FIELD
~
~
...........
<>'tW.TEAK
paul
"O<>FIELD
-.....,.......
980
_- _...........
..
..........
FIELD
0' Q
(>
(>
....
_r..-""--
100
90
U SAND
80
MMllI SAND
70
CASING
SCREEN
60
CUMULATIVE
50
WEIGHT
40
PERCENT
30
20
10
30
40
60
100
Fig. 4 -
CASING
CEMENT
SCREEN
SCREEN
A.
DOWEL PREPACK
B.
"PERFECT" PREPACK
OR 19 11 PREPACK
.
CASING
SCREEN
SC RE EN
c.
STAR PAC K
Number of tests
Capacity, B/D/ft
B/D/psi-ft
Sand rate, ppm
982
Perforated Completions
Annulus Star Pack
Prepack
3
3
4
56
0.23
NA
330
1.4
0.019
Open-Hole
Completions
1
340
3.3
0.018 to 0.002
343
28
0.008
TABLE 2 -
Number of tests
Capacity, B/D/ft
B/D/psi-ft
Sand rate, ppm
Perforated Completions
16 (four 0.5-in.)
1 (eight 0.75-in.)
22 to 27
154
0.63
0.09 to 0.11
1~3 to 18
0.04
triple-wrap screen. Since triple-wrap screens were eroding and sand was being produced through the screen,
tests were run to detennine the optimum gauge spacing
for the screens and how to pack screens before they
eroded, and to compare the screen's capacity with that
of gravel pack.
Initially, it was thought that the triple-wrap screen
would provide a system for perforated completions of
high capacity and sand-retention capability similar to a
gravel pack. Although the sand-production rates were
higher, they were maintained at acceptable rates when
using 4V2-in. perforations per foot. However, as seen in
Table 2, the productivity of this system was very low.
This can also be seen in Fig. 6, where the highest pressure drop through the perforations is a system with
4lh-in. perforations per foot filled with the fonnation
sand. The capacity was greatly increased by removing
the cas.ing and allowing the triple-wrap screen to pack
as in an open-hole completion. The rate of 670 BOPD/ft
was obtained by compounding the two test-cell pumps
for this one test. This open-hole test showed that the
triple-wrap screen could be used in open hole and
would have a capacity equivalent to the better gravel
pack. The major accomplishment of this test was to
show that, to operate effectively, the screen has to
pack. Sand that is produced a grain at a time will not
pack the screen; therefore, it must move en masse. It
was found that the best way to move the sand en masse
was to cycle the flow rate.
As a result of screen failure caused by erosion, it was
concluded that to prevent erosion the screen should be
packed. A test of this concept was conducted using a
0.006- X 0.012- x 0.020-in. triple-wrap screen packed
with 0.0041- x 0.0070-in. sand. Eight 34-in. perforations were used in this test, which showed much better
sand retention and also had higher capacity. The increased flow area of 3.53 sq in. for eight 34-in. holes
compared with 0.785 sq in. for four lh-in. holes used in
previous tests was the primary reason for the increase in
capacity;
Open-Hole
Completions
2
670
8.0
0.02
Fig. 7 -
200
;g 150
....
fORMATION
4-1/2" PERfS.
-<
o"'"
OlITER WRAP
-~~r.:J
S 100
A..
MIDDLE WRAP
_~
....
INNER WRAP
40
80
120
160
200
240
FLOW RATE BBL DAY FT
320
SEPTEMBER,1976
GAUGE SPACING
a ,0.030 IN.
b 0.020 IN.
c 0.010 IN.
360
Fig. 8 -
Rate
Well
Teak A-2
Teak A-6
Teak A-6
Teak C10
Teak C11
sapo bbl/ft
---1,925
1,830
2,875
2,265
1,530
32
26
35
38
77
TABLE 4 -
Well
Teak C-12*
Teak C-13**
Rate
sapo bbl/ft
---4,230
4,195
80
36
Prepack
None
None
0.017 to 0.033
0.04 to 0.06
0.04 to 0.06
Gravel Pack
0.04 to 0.06
0.04 to 0.06
0.017 to 0.033
0.04 to 0.06
0.04 to 0.06
Screen
Size
0.012
0.02
0.012
0.02
0.02
Remarks
4 cleanouts
2 cleanouts
14 months
8 months
6 months
Prepack
Open hole
Open hole
Gravel Pack
0.04 to 0.06
0.04 to 0.06
Screen
Size
0.02
0.02
---
Remarks
6 months
4 months
984
Conclusions
1. A zero-sand-production rate was not achieved in
these laboratory tests. However, with the best method,
the concentration range was reduced to parts of sand per
billion parts of oil, which would be considered nil from
an operational standpoint.
2. The integrity of the gravel pack must be maintained during production to prevent screen erosion or
pack plugging by formation sand intrusions, which result in well sand-off and loss of productivity.
3. In the gravel-pack, perforated-casing completion,
each perforation must be filled completely with gravel
to keep the formation sand from moving and to keep the
gravel in place if high productive capacity is to be
achieved.
4. Laboratory tests indicate the triple- wrap screen
would perform very well in open hole where the formation can slough around the screen.
Acknowledgments
This report required the special efforts and time of a
large group of technical and nontechnical people. The
author wishes to give special recognition to J. W.
Sprulock of Amoco Production Research' Co. (now retired), R. J. Rundt of Phillips Petroleum Co. (formerly
of Amoco International Oil Co.), D. S. Tipton of Texas
International Petroleum Corp. (formerly of Amoco International Oil Co.), and C. R. Milam of Amoco Production Research Co.
References
1. Saucier, R. J.: "Considerations in Gravel Pack Design," J. Pet.
Tech. (Feb. 1974) 205-212; Trans., AIME, 257.
2. Coberly, C. J. and Wagner, E. M.: "Some Considerations in the
Selection and Installation of Gravel Packs for Oil Wells," Pet.
Tech. (Aug. 1938) 1-20.
3. Hill, K. E.: "Factors Affecting the Use of Gravel in Oil Wells,"
Drill. and Prod. Prac., API (1941) 134-143.
4. Karpoff, K. P.: "Laboratory Report No. EM-l.32," Earth Materials Laboratory, U.S. Dept. of Interior, Bureau of Reclamation,
Washington (March 1947).
5. Likwartz, D. J.: "A History of Sand Control in the Teak Field,"
J. Pet. Tech. (Sept. 1976) 972-978.
JPT