Documente Academic
Documente Profesional
Documente Cultură
CORPORATE MANAGEMENT
MINING
RISK ANALYSIS
FORECASTING
ROMPEV
ROMPEV
ROMPEV
ROMPEV
ROMPEV
ROMPEV
Scope of Work
Base case mine evaluation
Resource estimation Block model
Reserve estimation mine plan and design
Mineral economics DCF and NPV and sensitivity analysis
Quantitative risk analysis - Uncertainty Risk and Potential
Quantifying metal grade uncertainty
Quantifying metal price uncertainty
Quantifying operating costs
NPV and Monte Carlo simulation
ROMPEV
UNDERSTANDING BLOCK
GRADE MODELING
ROMPEV
10
ROMPEV
11
ROMPEV
12
ROMPEV
13
Elevation
East
Origen of coordinates
ROMPEV
14
Simple average?
ROMPEV
15
Principles of Interpolation
Weighted linear combination
The methods differ in the way how they establish the
weights
z can be a transformed variable, if, e.g., certain statistical
properties must be maintained
n
z z0 wi zi
i 1
ROMPEV
16
In general:
ROMPEV
17
ROMPEV
18
ROMPEV
19
ROMPEV
20
Structural component
e.g., linear trend
Spatially correlated
component
Random component
noise
ROMPEV
21
ROMPEV
22
ROMPEV
23
ROMPEV
24
ROMPEV
25
Searching for
neighbors
ROMPEV
26
ROMPEV
27
ROMPEV
28
The estimation error at location s0 is the difference between the predictor and the
random variable modeling the true value at that location:
So, as long as
However, the unbiasedness tells us nothing about how to determine the weights
wis.
ROMPEV
29
ROMPEV
30
ROMPEV
31
ROMPEV
32
Cut-Off Grade
ROMPEV
33
ROMPEV
34
UNDERSTANDING BLOCK
ECONOMIC MODELING
Observe that the block economic value is not the same as Profit or Loss (P&L).
Profit or loss may be stated as: P&L = Sum(BEV) IC.
*Waste blocks will usually have negative BEV since income from waste is zero
ROMPEV
36
Cost to include:
Incremental (or variable) costs
Directly proportional to tonnage or unit of products.
Wages, fuel, explosives, etc.
Costs must be included in the associated activity.
In General:
INCLUDE expenses that would stop if mining activity is stopped.
NOT INCLUDE expenses that would not stop if mining stopped.
ROMPEV
37
Site administration
Site infrastructure maintenance
Interest on working capital loan
Capital replacement
Truck and other equipment purchase
ROMPEV
38
Geological
Grade control
In-pit supervision
Surveying
Dewatering
Day works
Mobilisation / Demobilisation
Site clearing & topsoil
Support (e.g. Geotechnical)
ROMPEV
39
ROMPEV
40
ROMPEV
41
Rule1. The value must be calculated on the assumption that the block has
already been uncovered. That is, the block value does not need to consider
the cost for mining (upper) previous blocks.
Rule2. The value must be calculated on the assumption that the block will
be mined.
ROMPEV
42
ROMPEV
43
ROMPEV
44
Bench #
Mining & Hauling Cost Increment
1
2
3
4
5
6
ROMPEV
Top of Pit
Bottom of
Pit
45
ROMPEV
46
ROMPEV
47
ROMPEV
48
ROMPEV
50
Tonnes
Cu
(%)
(tonnes)
Au
(g/t)
(ounces)
Zn
(%)
(tonnes)
275,000
2.32%
6,380
2.55
22,546
5.69%
15,648
85%
73%
Mill Feed
Grades
Metal Contained
Copper Concentrate
Mill Recovery
Tonnes of ore per tonne of
concentrate
Grades
Metal Contained
Grade x Tonnes
10.65
25,824
21%
5,423
Zinc Concentrate
Mill Recovery
Tonnes of ore per tonne of
concentrate
Grades
Metal Contained
ROMPEV
19.93
16,549
15%
90%
3.96
3,382
53%
14,083
10.35
26,571
51
439
Lbs
1.50 $ / lb
658 $ / t. conc.
ROMPEV
16,549 ounces
0.64 ounces
19.9 grams
2.5
grams
tonnes
tonnes
tonnes
Lbs
16,549 ounces
0.64 ounces
19.9 grams
24.26 Lbs
2.5
17.4 grams
439
$925 $ / oz
518 $ / t. conc.
1.50 $ / lb
658 $ / t. conc.
Lbs
grams
tonnes
tonnes
tonnes
Lbs
3,382
0.13
4.0
ounces
ounces
grams
Lbs
grams
17.4 grams
1169
Lbs
3.0
grams
$925 $ / oz
518 $ / t. conc.
0.50
584
$ / lb
$ / t. conc.
$925
88
$ / oz
$ / t. conc.
52
Value of Metal
75
34
5
0
0
114
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
ROMPEV
80
45
5
0
0
130
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
135
26
3
0
0
164
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
$ / t. conc.
6
3
$ / oz
$ / t. conc.
0.08
35
$ / lb
$ / t. conc.
6
3
$ / oz
$ / t. conc.
0
0
$ / lb
$ / t. conc.
6
3
$ / oz
$ / t. conc.
515
$ / t. conc.
493
$ / t. conc.
515
$ / t. conc.
420
$ / t. conc.
85
$ / t. conc.
10.65
10.65
10.65
10.35
48.37 $ / t. ore
46.30 $ / t. ore
48.37 $ / t. ore
40.61
2.55
2.32%
2.55
5.69%
19.96 $ / %
18.97 $ / g
g/ t
18.97 $ / g
g/ t
7.14
10.35
$ / t. ore
$/%
8.18
$ / t. ore
2.55
g/ t
3.21
$/g
53
Smelter
Relative
sales
Copper
($ / % Cu)
Gold
($/gram)
Copper
35%
20.69
18.97
Copper
65%
19.96
18.97
100%
20.22
18.97
Copper
Zinc
100%
ROMPEV
20.22
Zinc
($ / % Zn)
3.21
7.14
22.17
7.14
54
ROMPEV
55
Waste
CB
-1
CB -2
CB
Pushbacks | Cutbacks
-3
ROMPEV
57
The shape left after the removal of all positive valued cones
forms the ultimate pit layout.
ROMPEV
58
ROMPEV
59
Figure 1 a) floating cone algorithm failure to recognise the true ultimate pit in the case of the extension
of the pit; B) true pit.
ROMPEV
60
Figure 1 a) Floating cone failure to recognise the true ultimate pit in the case of overlapped cones; b) true
ultimate pit.
ROMPEV
61
ROMPEV
62
ROMPEV
63
ROMPEV
64
ROMPEV
65
ROMPEV
66
ROMPEV
67
ROMPEV
68
ROMPEV
69
ROMPEV
71
ROMPEV
Thermal coal
Coking coal
72
Pre-production
Exploration and resources delineation
Desktop
Pre-feasibility
Feasibility
Development and construction
Production
Closure and restoration
ROMPEV
73
ROMPEV
74
ROMPEV
75
ROMPEV
76
ROMPEV
77
ROMPEV
78
Economical/Financial
Optimal annual mine throughput
Maximum expected value added to owners
ROMPEV
79
ROMPEV
80
ROMPEV
81
ROMPEV
82
its deposit,
mine plan,
process routes,
operating costs,
financial structure,
tax regime and
management qualities.
ROMPEV
83
ROMPEV
84
Year 0
Year 1
1,200,000
0.98
85%
32,138
1,500 $
Year 2
3,000,000
0.89
85%
72,966
1,500 $
Year 3
3,000,000
0.75
85%
61,488
1,500 $
Year 4
3,000,000
0.7
85%
57,389
1,500 $
Year 5
Total
2,500,000
12,700,000.0
0.65
85%
44,408
268,389.61
1,500 $
1,500
$
$
$
$
(8,000.0)
(964.1)
(3,000.0)
(800.0)
$
$
$
$
(11,000.0)
(2,189.0)
(3,400.0)
(800.0)
$
$
$
$
(15,000.0)
(1,844.6)
(3,400.0)
(800.0)
$
$
$
$
(15,000.0)
(1,721.7)
(3,400.0)
(800.0)
$
$
$
$
$
10,000
(12,000.0)
(1,332.2)
(3,060.0)
(800.0)
$
$
$
$
$
10,000.00
(61,000.0)
(8,051.7)
(16,260.0)
(4,000.0)
Less:
ROMPEV
(27,618.06) $
(21,356.34) $
(19,548.59) $
(17,826.02) $
(96,981.8)
800.00 $
800.00 $
800.00 $
800.00 $
(150,000.00)
800.00 $
$
4,000.0
(150,000.0)
(10,632.81) $
$
$
0.8929
(150,000.00) $ 22,151.68
52,045.45
31%
2.5
0.37
0.8929
0.8929
0.8929
0.8929
85
CAPEX
NPV
Discount Rate
ROMPEV
86
87
ROMPEV
88
ROMPEV
89
ROMPEV
90
ROMPEV
91
ROMPEV
92
ROMPEV
93
ROMPEV
94
If the risk is relatively low and the project represents business as usual
WACC is used as the discount rate, otherwise higher risks than WACC are
used.
ROMPEV
95
ROMPEV
96
ROMPEV
97
ROMPEV
98
ROMPEV
99
ROMPEV
100
REAL OPTIONS
CORPORATE MANAGEMENT
MINING
RISK ANALYSIS
FORECASTING
Objective
Introduction
Mine project evaluation a complex problem
Main sources of uncertainty in a mine project evaluation
Uncertainty: A source of value?.. management flexibility
Build an appreciation of mine planning, technical,
economic, logistics and access considerations and
perspectives on risk
Complex processes do not need complex solutions, but
practical ones
Provide a platform for the iVof engine
Upfront project optionality assessment
Advanced Valuation Technique (AVT) application
ROMPEV
102
Introduction
Undertaking valuations is an art rather than a pure science as they involve judgment and
analysis, and the size and scope of takeover transactions are broad
INPUT
ROMPEV
OUTPUT
103
ROMPEV
104
INTRODUCTION TO
UNCERTAINTY ANALYSIS
Understanding Uncertainty
So,what is uncertainty??
Uncertainty is a subjective definition of
an unknown event (lack of
information).
There are some statements that you
know to be true, others that you know
are false, but with the majority of
statements you do not know whether
they are true or false; we say that, for
you, these statements are UNCERTAIN.
ROMPEV
106
Understanding Uncertainty
So,... What is dynamic / static uncertainty?
It will rain tomorrow
The card drawn from a well-shuffled
pack will be an ace
Shares in a mining company will raise
over the next month
Copper grade in a specific area within
the deposit is 3%/t.....
Dynamic uncertainty because it varies with
time. Conversely, static uncertainty does
not vary with time
ROMPEV
107
ROMPEV
108
ROMPEV
109
ROMPEV
110
ROMPEV
111
ROMPEV
112
ROMPEV
113
ROMPEV
114
ROMPEV
115
ROMPEV
116
Suppression of Uncertainty
Everything about the future is uncertain, as is most of
the past; even the present contains a lot of uncertainty
ROMPEV
117
Suppression of Uncertainty
However, there are places, like the casino or the race course where
the uncertainty is openly admitted and exploited to add to the
excitement....hmmmm
ROMPEV
118
ROMPEV
119
Suppression of Uncertainty
Why people deny uncertainty even though they have the
perception of its existence?
120
ROMPEV
121
ROMPEV
122
The last thing you do before climbing on a ladder to paint the side
of your house is to give it a good shake. By bombarding it with
random physical forces, you simulate how stable the ladder will be
when you climb on it. You can then adjust it accordingly so as to
minimise the risk that it falls down with you on it.
ROMPEV
123
The shaking forces you apply to the ladder are known as the
input probability distribution and correspond to the uncertain
demand levels for your product, the magnitudes of potential
earthquakes, or the sizes of the enemy forces you will
encounter (in our example above the stability of the ladder).
ROMPEV
124
ROMPEV
125
A computational technique similar to the shaking of a ladder can test the stability of
uncertain business plans, engineering designs, or other activities. Monte Carlo
Simulation, as it is known, bombards a model of the business with thousands of
random inputs, while keeping track of the outputs. This allows you to estimate the
risk and potential of your business.
ROMPEV
126
Risk
Reference
Recoverie
Uniform distribution. s
Risk
Log-Normal distribution.
Defined byUpside
the mean
Potential
and variance
Risk
Risk
Upside
Potential
Unif
Define
Log-Normal distribution.
Defined by the mean an
Project
NormalValue
distribution.
Defined by the mean
and variance
and variance
Upside
Potential
Risk
Reference
Uniform distribution.
Defined by a maximum
and a minimum
Normal distribution.
Upside
Defined by the mean
Potential
and variance
Reference
Reference
Reference
Upside
Potential
Upside
Potential
Reference
Mining
Project
Log-Normal distribution.
Triangular distribution.
Defined by the mean
Defined by a maximum,
Uniform
distribution.
and variance
minimum and most likely values
Risk
Metal
Production
Reference
Uniform distribution.
Defined by a maximum
Triangular distribution.
and a minimum
Risk Defined by a maximum,
minimum and most likely values
Defined by a maximum
Triangular distribution.
Upside
and a minimum
Potential
Defined by a maximum,
minimum and most likely values
Log-Normal distribution.
Defined by the mean
and variance
Reference
Upside
Costs
Potential
Risk
Triangular distribution.
Defined by a maximum,
minimum and most likely values
Upside
Potential
Reference
Risk
Reference
Reference
Normal distribution.
Defined by the mean
and variance
Reference
Reference
Reference
Risk
Upside
Potential
Upside
Potential
Reference
Risk
Log-Normal distribution.
by the mean
Risk DefinedUpside
andPotential
variance
Risk
Log-Normal distribution.
Upside
Defined by the
mean
Potential
and variance
Risk
Upside
Potential
Reference
Prices
Upside
Potential
Normal distribution.
Upside
DefinedRisk
by the
mean
Potential
and variance
Risk
Risk
Reference
Reference
Reference
Risk
Upside
Potential
Risk
Reference
Grades
Normal distribution.
Upside
Defined by the mean
Potential
and variance
Upside
Potential
Risk
Reference
Risk
Upside
Potential
Un
Def
Defined by a maximum
and a minimum
ROMPEV
127
Simulations dont add up. Consider a mining project that has two
sources of uncertainty . We will model each source of uncertainty as
its own ladder, and model the entire project as the two ladders
joined by a wooden plank. Now suppose that by shaking either
ladder by itself you would predict a 10% of the project falling over
ROMPEV
128
ROMPEV
129
ROMPEV
130
ROMPEV
131
On Average is he Alive?
ROMPEV
132
ROMPEV
133
1991
1992
1995
ROMPEV
1998
2001
2002
2005
1998
2000
2002
2005
2008
2013
134
ROMPEV
135
ROMPEV
136
Year 1
80000
24000
3.78%
97.00%
2929.821574
700
-211200.00
-96000.00
-292.98
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
Year 8
Year 9
80000
80000
80000
80000
80000
80000
80000
8000
256000
32000
0
8000
224000
16000
2.77%
2.06%
2.60%
3.11%
0.51%
0.45%
0.95%
97.00%
97.00%
97.00%
97.00%
97.00%
97.00%
97.00%
2149.77237 1596.009031 2016.767044 2415.174205 399.453995 348.395968 739.605921
700
700
700
700
700
700
700
-193600.00
-734400.00
-278400.00
-214400.00 -188000.00 -716000.00 -269600.00
-96000.00
-96000.00
-96000.00
-96000.00
-96000.00
-96000.00
-96000.00
-214.98
-159.60
-201.68
-241.52
-39.95
-34.84
-73.96
8000
0
1.54%
97.00%
119.78099
700
-23200.00
-9600.00
-11.98
$83,846.69
$51,034.72
$0.36
$18,403.63
$18,403.6
2000
Series1
1800
Series2
1600
Series3
1400
Series4
Series5
1200
Series6
1000
Series7
800
Series8
Series9
600
Series10
400
Series11
200
Series12
Series13
0
1
Series14
10
$3,000,000.0
Series1
Series2
$2,500,000.0
Series3
Series4
$2,000,000.0
Series5
Series6
$1,500,000.0
Series7
Series8
Effect of GBM
prices on
Series11
Project
Series12
Series13 Cash Flow
Series9
$1,000,000.0
Series10
$500,000.0
$0.0
Series14
Series15
$500,000.0
ROMPEV
137
Year 1
80000
24000
3.78%
97.00%
2929.821574
700
-211200.00
-96000.00
-292.98
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
Year 8
Year 9
80000
80000
80000
80000
80000
80000
80000
8000
256000
32000
0
8000
224000
16000
2.77%
2.06%
2.60%
3.11%
0.51%
0.45%
0.95%
97.00%
97.00%
97.00%
97.00%
97.00%
97.00%
97.00%
2149.77237 1596.009031 2016.767044 2415.174205 399.453995 348.395968 739.605921
700
700
700
700
700
700
700
-193600.00
-734400.00
-278400.00
-214400.00 -188000.00 -716000.00 -269600.00
-96000.00
-96000.00
-96000.00
-96000.00
-96000.00
-96000.00
-96000.00
-214.98
-159.60
-201.68
-241.52
-39.95
-34.84
-73.96
8000
0
1.54%
97.00%
119.78099
700
-23200.00
-9600.00
-11.98
$83,846.69
$51,034.72
$0.36
$18,403.63
$18,403.6
Effect of MR
prices on
Project
Cash Flow
ROMPEV
138
Cu Spatial Distribution
Ordinary Kriging
ROMPEV
139
Waste
Classi
fied as
Ore
Waste Classified as
Waste
ROMPEV
140
Cu Spatial Distribution
Sequential Gaussian
Simulation Realisation
20
ROMPEV
141
Cu Spatial Distribution
Sequential Gaussian
Simulation Realisation
20
ROMPEV
142
ROMPEV
143
ROMPEV
144
Base Case
ROMPEV
145
ROMPEV
146
ROMPEV
147
ROMPEV
148
ROMPEV
149
Zone 7
Zone 6
Zone 8
Zone 5
Z
E
N
ROMPEV
Parameter Description
Assumed Production Period (years)
Expected Gold Price (Au$/gr)
Expected selling cost (Au$/gr)
WACC discount rate
Time cost / period (millions of Au$)
Mill capacity / period (Mt)
Maximum mine capacity / period (Mt)
Procesing cost Oxide rock (Au$/t)
Procesing cost Transitional rock (Au$/t)
Procesing cost Primary rock (Au$/t)
Recovery-Oxide rock
Recovery-Transitional rock
Recovery-primary rock
Slope angle Zone 1 (degrees)
Slope angle Zone 2 (degrees)
Slope angle Zone 3 (degrees)
Slope angle Zone 4 (degrees)
Slope angle Zone 5 (degrees)
Slope angle Zone 6 (degrees)
Slope angle Zone 7 Degrees)
Slope angle Zone 8 (Degrees)
Value
1
27.5
0.6875
12%
1.5
2
9
15.39
16.66
16.9
94%
94%
90%
52
57
50
48
45
50
55
60
ROMPEV
151
ROMPEV
152
ROMPEV
153
ROMPEV
154
ROMPEV
155
Mining Costs
-40
Ore Tonnes
3
2
1
0
1
-25
-20
-15
-10
-5
-20
-15
-10
1
4
3
2
1
Production Periods
3.5
3.5
3
2.5
2
1.5
1
2.5
0.5
0
1
60
45
30
15
0
1
250
200
150
100
50
0
1
Period 1
Period2
22%
Period 3
Period 4
400
300
200
100
0
60%
80%
30%
100%
120%
ROMPEV
Production Period 1
Production Period 2
Production Period 3
Production Period 4
90
Gold Grade
Stripping Ratio
-25
-30
-5
-4.5
-4
-3.5
-3
-2.5
-2
-1.5
-1
-0.5
0
Selling Costs
Processing Costs
-35
Waste Tonnes
-30
-35
ROMPEV
ROMPEV
ROMPEV
ROMPEV
ROMPEV
ROMPEV
ROMPEV
ROMPEV
ROMPEV
Orebody Simulations
Waste tonnes
Metal Production
Average Grade
Cash Flow
ROMPEV
ROMPEV
167
ROMPEV
168
ROMPEV
169
ROMPEV
171
ROMPEV
172
ROMPEV
173
ROMPEV
174
Option 1
Operational
Drilling
Base Case
Project
Time 1
ROMPEV
Option 3
Managerial
Expand
Expanded NPV
Flexibility Value
Option 2
Operational
Cut-Off
NPV
Decision Making
Optimised
Project
Time 2
175
Grades / Year
Recoveries
Year 1
Year 2
2,014
2,013
$19.00
Average
TotalProbability
$25.02
0.47
$14.43
0.53
$19.38
1.00
ROMPEV
0.47
0.53
0.47
0.53
$32.94
0.22
$19.00
0.50
$10.96
0.28
$19.77
1.00
Year 3
2,015
0.47
0.53
0.47
0.53
0.47
0.53
$43.38
0.10
$25.02
0.35
$14.43
0.40
$8.32
0.15
Year 4
2,016
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
$20.16
1.00
$57.11
0.05
$32.94
0.2176631
$19.00
0.37
$10.96
0.28
$6.32
0.08
$20.57
1.00
Year 5
2,017
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
$75.20
0.02
$43.38
0.13
$25.02
0.29
$14.43
0.33
$8.32
0.19
$4.80
0.04
$20.98
1.00
Year 6
2,018
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
$99.02
0.01
$57.11
0.07
$32.94
0.20
$19.00
0.31
$10.96
0.26
$6.32
0.12
$3.65
0.0228
$21.40
1.00
Year 7
2,019
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
0.47
0.53
$130.39
0.0049
$75.20
0.04
$43.38
0.13
$25.02
0.25
$14.43
0.29
$8.32
0.20
$4.80
0.07
$2.77
0.01214
$21.83
1.00
Year 8
2,020
$171.69
0.47
0.0023
0.53
$99.02
0.47
0.02
0.53
$57.11
0.47
0.08
0.53
$32.94
0.47
0.19
0.53
$19.00
0.47
0.27
0.53
$10.96
0.47
0.24
0.53
$6.32
0.47
0.14
0.53
$3.65
0.47
0.05
0.53
$2.10
0.0065
$22.26
1.00
176
Year 1
2,013
Year 2
2,014
Year 3
2,015
Year 4
2,016
Year 5
2,017
Year 6
2,018
Year 7
2,019
Year 8
2,020
$208,346.12
$176,243.94
$130,323.27
$90,814.51
$73,430.98
$40,747.95
$25,837.63
($2,339.56)
$0.00
($18,548.60)
$75,823.43
$33,794.90
$7,440.35
$307.94
$34,876.74
$38,111.86
$24,236.32
$9,076.37
($5,088.58)
($8,880.41)
($13,315.89)
$67,348.97
$54,870.75
$15,077.79
$7,224.91
($8,463.70)
$107,274.13
$46,096.97
$16,939.03
$119,972.56
$18,672.15
$4,403.62
($6,319.08)
($16,778.77)
($18,175.03)
$7,134.65
($7,067.12)
($15,204.01)
($23,513.54)
$476.19
($13,675.47)
($20,316.68)
($3,355.30)
($17,486.54)
($5,579.57)
ROMPEV
177
Year 1
Year 2
2,014
2,013
Year 3
2,015
Year 4
2,016
Year 5
2,017
Year 6
2,018
Year 7
2,019
Year 8
2,020
$208,389.12
$334,413.45
$386,688.79
$383,688.74
$356,394.93
$294,601.86
$225,997.54
$139,258.58
$
63,637.01
$173,353.52
$72,810.43
($371.67)
$110,197.83
$54,319.05
$41,412.74
($18,240.41)
($29,908.44)
48,809.0
63,637.01
Potencial
14,828.01
VAN Forward
64,904.71
$7,177.65
($3,506.12)
($24,728.50)
($55,049.82)
$$AU$66.6 millions
VAN proyecto
$18,715.15
$16,728.90
($481.46)
($60,621.55)
VAN caso base
$38,154.86
$51,494.96
$13,642.17
($53,322.82)
$67,391.98
$105,678.70
$87,207.09
$15,683.79
($29,110.87)
$197,465.42
$221,501.67
$205,151.66
$124,754.04
$120,015.56
$519.19
($15,166.61)
($38,698.33)
($3,312.30)
($21,895.02)
($5,536.57)
ROMPEV
178
43.0
Year 1
Year 2
2,014
2,013
Year 3
2,015
Year 4
2,016
Year 5
2,017
Year 6
2,018
Year 7
2,019
Year 8
2,020
$208,389.12
$334,413.45
$386,688.79
$120,015.56
$383,688.74
$197,465.42
$356,394.93
$221,501.67
$294,601.86
$226,135.20
$
$110,197.83
$125,017.75
74,996.89
$105,678.70
$173,353.52
$142,055.30
$51,494.96
$54,824.21
$41,412.74
$25,483.37
$16,728.90
$88.15
$1,372.24
$106.79
$
48,809.0
74,996.9
$44.83
64,904.7
145.2
ROMPEV
$44.83
$519.19
$48.47
$44.83
$44.83
Valor de la opcion
$
26,187.9
$$AU$74.9
millions
Increase %
54%
VAN Forward
$7,177.65
$48.47
$88.15
$18,715.15
$14,609.85
$3,272.69
VAN expandido-RO
$38,154.86
$87,207.09
$78,046.96
$18,933.71
$67,391.98
$205,151.66
$43.00
$44.83
$43.00
Closing Value
$
119.3
106.8
88.1
48.5
44.8
44.8
179
43.0
Year 1
Year 2
2,014
2,013
Year 3
2,015
Year 4
2,016
Year 5
2,017
Year 6
2,018
Year 7
2,019
Year 8
2,020
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
48,809.00
74,996.89
26,187.89
54%
VAN Forward
64,904.7
CONTINUE
CONTINUE
CONTINUE
CLOSE
CONTINUE
CLOSE
CLOSE
CLOSE
$$AU$74.9 millions
ROMPEV
CONTINUE
CONTINUE
CLOSE
$
$
$
CONTINUE
CONTINUE
CLOSE
CLOSE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CONTINUE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
180
ROMPEV
181
ROMPEV
182
ROMPEV
183
P2
P1
CS
2
CS
1
RC1
RC2
OP3
OP2
OP1
PC21
PC22
PC32
PC11
LO1
PC33
LO2
LO3
Product 1
ROMPEV
Product 2
Product 3
Loadout
184
ROMPEV
185
MIDSTREAM
ANALYSE
ANALYSE
Option
Modelling
Risk / Potential Quantification & Analysis
DOWNSTREAM
IMPLEMENT
IMPLEMENT
Solution
Syndication
Option Modelling and Decision Making
Data Collection
Quantify & Model Uncertainties
Integration/Interaction of
uncertainties
Opportunities
Low Impact
High Cost
Low Impact
Low Cost
High Impact
High Cost
High Impact
Low Cost
Risk
AU$ Millions
Expected Target
Cost of Implementing
Economic/Technical Strategy
(AU$ Millions)
Minimum
Maximum
Risk/Opportunity
Assessment
Quantative analysis using
Value@Risk &
Upside/Downside
Management
Decision making
Process
Impact of decision
on Project Outcome
/ NPV
0.9
Optimistic
0.16
0.8
0.14
0.12
0.1
0.7
0.08
0.6
Expected
0.06
F(x)
Prioritize
key
uncertainties
for modeling
Average
0.04
Expected
Expected
0.02
0
0.75
0.5
0.8
0.85
0.9
0.95
1.05
1.1
1.15
1.2
1.25
9
x 10
0.4
0.3
0.2
0.1
BC-Expected
0
0.75
0.8
0.85
0.9
0.95
1
1.05
Current Project Value (A$)
1.1
1.15
1.2
1.25
9
x 10
Commercial in confidence. 2010 Copyright ROMPEV Pty Ltd. All rights reserved
ROMPEV
186
ROMPEV
187
Thanks
But.............,
we still need to
model
some risks through
the
discount rate, which
is
easier than
modelling the
entire project risk
through it.
ROMPEV
188