Shandong Kerui Group Holding Co.,Ltd.

XJ250 Workover and flushby Rig Technical Specification

XJ250 self-propeller Workover Rig is a special facility for oil field. Design rated
hook load is 400Kn(88185lbs), The Max. hook load is 675Kn(150000lbs), Servicing
depth is 3200m(10667ft) (2 7/8EUE tubing ), Carrier driving type: 8X6 Strong
frame is made of wing span sectional material. Power package will be adopted
Caterpillar diesel engine and Allison transmission. The engine power is transmitted
to PTO and from PTO either to working unit or to carrier driving shaft. PTO power
upper output: through propeller shaft transmit to angle gear box, to chain, to bailing
drum. Using clutch can be completed bailing and swabbing work. The power of
bailing drum has be transmitted to main drum by chain and clutch; using clutch can
be completed hoisting work.
PTO power lower output: through propeller shaft to carrier front axle and rear
axle complete driving function. The PTO has a handle to control servicing work or
carrier driving work; it cant be completed at same time.
The carrier load is rational distributed; its very good in driving and cross-country
function. Every core assembly must have enough space to operating and servicing.
The workover rigs property of resistant to wind, sand vibration is very good too, it
working temperature is in -2045
1. Technical Requirement Design Technical Standard
GB/T24263-2009 Petroleum drilling weight table
JB/T 9088-2013 Reciprocating pump impurity
GB-T 9234-1997 Motor reciprocating pump
API Spec 4F
Specification for Drilling and Well Servicing Structures
API Spec Q1
Specification for Quality Programs for the Petroleum and
Natural Gas
API Spec 8C
Specification for Drilling and Production Hoisting Equipment
API Spec 7K
Specification for Drilling and Well Servicing Equipment
API Spec 7
Specification for Rotary Drill Stem Elements
1


Shandong Kerui Group Holding Co.,Ltd.

API Spec 9A
Specification for wire line
Quality system certification: According to the ISO9001 Quality System to control the
design and manufacturing process quality.
2.Main Specification for Equipment
Servicing Depth: 3200m(2 7/8EUE tubing)
Rated Hook Load: 400kN(88185lbs)
Max. Static Hook Load: 675Kn(150000lbs)
Rated Power of Engine: 269Kw(360hp)
Derrick Height (net height):21m(70ft)
Rod hanger Height: 15m(5ft)
Traveling System: 32.
Carrier Driving Type: 86
Diameter of Wire Line: 26mm(1).
Overall Dimension for moving: 12.52.64.4m(41.7X8.7X14.7ft)
Max. Speed of Carrier: 55km/h (limit speed: 45km/h)
Return Diameter of Carrier: 34m(113.3ft)
Total Weight for moving: 48000kg(105821lbs)
3. Match for Equipment
3.1 Match for equipment


Shandong Kerui Group Holding Co.,Ltd.

1. Power system

2. Carrier System
Driving type: 86
Engine
Model:
CAT C11
3.2 Match
Parts
Front tyre:18-22.5 (No.4)
Engine Power:287kw (385HP)
Rear tyre:12.00-20 (No.8)
Heating installation
in cab,Allison 2 spare wheels and 2ea 8kg fire
Hydraulic
Transmission:
4700
OFS in cab
extinguishers
Defroster

3.Transfer
Lift toolsSystem
for workover rig
4. Angle Gear Box
EngineTransmission
Welded case, alloy forging gear
Dead line fixer and weight indicator
Anglegearboxdrawwork
triplex
pump
Spare
wheel frame
5. Drawwork System
6. Derrick and Travelling system
Spare
wheel(18-22.5),
Qty:1
It
includes
drums
assembly, Derrick height: 21m(70ft)
drawwork seat, brake system, chain Travelling system: 3x2
4.
cover, clutch cover, roller chain, etc. YG70 Traveling block,
Wire line Dia:26mm(1)
7. Triplex pump System
8. Liquid circulation pump system
In includes HTB200 triplex pump, It includes 65CYZ-A-15 self-sucking
suction manifold, high pressure pump, suction manifold, exhaust
manifold, plug valve, high pressure manifold, butterfly valve, etc.
active elbow.
9. Liquid storing tank assembly
10. Simple work platform assembly
and the weight indicator
It includes tank, tank base, manhole It includes platform base, platform
assembly, suction flange, discharge landing leg, platform, etc. The weight
flange, liquid indicator, etc.
indicator is hydraulic pressure sensor.
11. Hydraulic system
12. Air system
It consists of a hydraulic pump, a Air storage tank, driller console, crown
hydraulic motor, hydraulic oil tank saver, air horn, throttle controller,
assembly, relief valve, multiple clutch, etc.
directional control valve, assist
lifting jack(consists of former lifting
jack and telescoping lifting jack),
mast rising liquid cylinder, main
lifting jack, hydraulic winch, etc.
13. Electric system
14. Other
Explosion proof lighting LED lamps, Spare parts, tools, operation manual,
electric crown saver, outline marker chassis
manual,delivering
list,
lamps, etc.
manufacture certificate, etc.
Specification and Requirement for Main Assy
4.1 Diesel Engine
Model: CAT C11
Power: 287kw(385HP)/2100r/min;
859XGFJP-D5XS power takeoff
4.2 Hydraulic transmission
Model: Allison 4700 OFS
Torque converter type:
3

TC-521


Shandong Kerui Group Holding Co.,Ltd.

Max. Torque ratio:


2.42
Max. Input torque:
2500r/min
Max. Static Input torque:
2508 Nm(1851lb.ft)
Transmission ratio: 7.63:1 3.51:1 1.91:1 1.43:1
1:1
0.74:1 0.64:1 -4.8:1
4.3 Carrier
The frame beam is made of 16Mn wing span sectional material; its very strong;
selecting width wheel tread; heavy duty axle.
Incidence angle: 30
Descent angle:15
Min. turning diameter: 34mm(1.34)
Max. grade climbing: 32%
Min. ground clearance: 300mm(11.8)
Max. Speed: 55km/h (limit speed 45km/h)
Tier: front: 18-22.5 single tier, rear: 12.00R20 double tier
4.4 Angle gear box.
Steels shell, spiral bevel gear is forging steel, the input and output shaft is made of
high grade alloy steel, splash lubrication. The transfer power will be suffice.
4.5 Driving chain:
Angle gear box Bailing drum
1 1/4Triplet chain
Bailing drum Main drum
1 1/4Triplet chain
4.6 Drawwork
The drawwork has double drum. Main drum has Lebus groove, match cross ring
valve to protect crown. The drum shaft is made of high grade alloy steel. Main drum
is adopted similar ATD-224H gas bag trust disc clutch, brake rim is cooled by
splash water. So is the bailing drum. The brake rim of main drum and bailing drum
is made of alloy steel. There is protective device in the front of main drum guard
cover.
Main drum:
Model:
JC18
Drum diameter:
406mm (15.9)
Drum length:
890mm (35)
Brake rim length width: 1070mm264mm (42.110.4)
Max. Fast line pull:
180kN (39680lb)
Max. Rotating speed:
290r/min
Wire line diameter:
26mm (1)
It adopts brake block structure, air assist braking, the emergency brake,
mechanical and electrical crown block saver.
Bailing drum
Drum diameter: 315mm (12.4)
Drum length: 908mm(35.75)
Brake rim diameter: 870mm(34.25)
Brake rim width: 190mm(7.48)


Shandong Kerui Group Holding Co.,Ltd.

Brake rim wrap angle: 340


Wire line diameter: 14mm(9/16)
Storage capacity of wire line:3600m(12000ft)
Bailing drum control system main include change shift valve, clutch controlling
valve, engine kill valve, control desk is on the stage that is in the middle of main
drum and bailing drum, it is at opposite side of brake so operating will be central
convenient, easy.
4.7 Derrick and Traveling System:
The derrick is telescopic structure. Upper and lower of body is made of 16Mn
square pipe. Net is 21m(70ft). The mast is raised and telescoped by different
hydraulic cylinder, it is centralizing and reliability. The substructure fit a angle
gauge, the dip angle of mast is 5.55.2when it is normal working.
The crown block of derrick is a similar box integrity structure. The sheaves are
adopted rolled part and having dynamic balance test. The wire lines groove
arcograph design act on API 8A requirement and relative wire line. The wire line
seat have wire line retainer to prevent wire line jump groove. The crown shaft has
heat treatment and fault detection. The crown is adopted 32 system. The crown
have guardrail, it is safety and reliability. There is a layer bumper on the crown
block seat.
The racking board pipe finger is cross arranged, its distance can be adjusted. The
pipe finger have safe link to prevent drilling rod and oil tube slipping. The racking
board has space for outstep drilling to convenience tube throw from the driller side.
The racking board and basket of pumping rod automatic open and cling while the
upper body of mast outspread and contract.
There is long ladder directing to grown. The racking board has an escaper
The mast anchor act on API 4F strict execute
The mast mach a safe belt and dropproof device for workers safety
----Mast
Model: JJ70/21
Net height: 21mm(70ft)
Max. static load: 675Kn(150000bls)(traveling system:32)
dip angle: 5.5-5.2(with dip angle indicator)
sheave: the bottom diameter is 610mm(24)(relative wire line: 26mm (1)
Bailing sheave: the bottom diameter is 304mm(12)(relative wire line:
14.5mm(9/16))
Traveling system: 32
Racking board capacity: 3200m(10667ft) (2 7/8 EUE tubing)
Max. Wind resistance: 110m/h (about: No. 11 storm)
Arrangement type for racking board pipe finger: cross arrangement
----Traveling block and hook
Model: YG70(relative wire line: 26mm(1))
Max. Load: 700Kn(154323lbs)
Sheave: the bottom diameter is610mm(24)(relative wire line: 26mm(1))
Sheaves Qty: 2
5


Shandong Kerui Group Holding Co.,Ltd.

Wire line diameter: 26mm(1)


4.8 Mast substructure and seat
Simple integrated substructure
4-hydraulic jack seat
2-H type frame seat
4.9 Light work platform
Steel structure with operating platform and guardrail
Height: 1.3-2.5m(4.3-8.3ft)
Relative racking board
The height can be adjusted
4.10 Hydraulic system
Hydraulic system consists of some back way: pump (include oil tank), jack, winch,
mast raising, mast telescoping, and the relative parts is included too. It supply the
tong power.
Main assy and parts of hydraulic system include: main pump, winch, break cylinder,
raising cylinder, telescoping cylinder and oil level oil pressure indicator etc. The
pump and 4-link valve use import device. System central controlling is at the
opposite of driller operating platform. Its main controlling assy and parts have
protecting function. Its action is stabilizer and reliability.
Max. Pump displacement: 165L/min
Max. Pressure of system: 14MPa
Hydraulic oil: 68# antiwear hydraulic oil
The capacity of oil tank: 833L(220gal)
Tongs cylinder:
Stroke:1600mm(5.3ft)
Rated working pull: 150Kn(33069lbs)
Rated working pressure: 14Mpa(2000psi)
Qty: 1Stroke: 1200mm(4ft)
Make up cylinder
Rated working pull: 80Kn(17637lbs)
Rated working pressure: 14MPa(2000psi)
Qty: 1
3ton hydraulic winch:
Model: YC-3
Rated pressure: 14Mpa(2000psi)
Lifting capacity: 30Kn(6614lbs)
Max. Lifting speed: 40m/min
Wire line diameter/storage capacity: 14mm(9/16)/120m(400ft)
Qty: 1
The winch have arrange line device. There is net guard around it to prevent hurting
operator
4.11 Air system
The function that drawwork controlling, transmission change shift, pump unloading,
assisting brake controlling, emergency power cut off, crown protect, air slip, horn
6


Shandong Kerui Group Holding Co.,Ltd.

alarm, throttle control, engine kill, working and driving interlock, carrier driving brake
and parking brake etc can be completed by air compressor connected with air line.
Air compressor equips pressure adjustor. Max limiting pressure is 0.95MPa
Working pressure: 0.7-0.85MPa
Displacement: 300-430L/min/1300rpm
Air tank capacity is 0.155m it equipped safe valve( arrangement pressure:
1.05MPa) and automatic degassing, dewater switch. The valves of carrier are
centralized in cab. The valves and gauges of working unit are centralized in driller
box act on man- machine engineering principle. The driller box is made of stainless
plate welding structure. All lines are adopted FESTO import parts (include joint)
4.12 Electric System
Both driving and working light system, the power source of carrier drive system is
24V; it is supplied battery and silicon rectifier generator. Its main function includes
generator starting, monitoring sign light of carrier different light and sound parts.
The power source of working unit is supplied outside AC 110V/460V/60Hz, its main
function includes mast and well head lighting. There is a red warning light on the
mast top; the electric line is protected with steel pipe. The mast is fitting seven
vapor proof fluorescent light, the working unit is two. The electric system is central
controlled in vapor proof box. The gauge, light switch and joint etc use professional
company vapor proof product.
The power source of carrier of carrier: 24V DC
The power source of outside: 110/460V AC 60Hz
Mast light: vapor proof type
4.13Triplex plunger pump
Model: HTB200 (The horizontal type three single-acting cylinders plunger
pump)
Stroke Length: 135mm(5)
Cylinder Dia.: 100mm(4)
Max. Pressure: 35Mpa(5000psi)
Max. Displacement: 942L/mi
Piston dia.:100mm(4)
Pipe system:Dia of suction manifold:4;
The pump will be equipped with 0-5000psi heavy duty pressure gauge;2 safety
valve and 2 bleed line with valve as per drawing
Dia of discharge manifold:2, pressure:35Mpa(5000psi); 2(5000psi) Low-torque
valve
4.14 Liquid circulation pump
Model: 65CYZ-A-15
Max. Displacement: 498L/min
Max. Lift: 15 m(50ft)
4.15 Liquid Storage Tank
Liquid tank capacity: 6500L(1717gal)
Liquid: Water
The tank body material is stainless steel . The internal surface of the tank
7


Shandong Kerui Group Holding Co.,Ltd.

body complies
5
Attachment List
Item
Name
Electric device

Lamp 24V 75/70W

lamp 24V 5W

24V 70W lamp

24V, 5W lamp

24V ,21W lamp,

24V,10W Lamp,

24V,10W Lamp, 21/5W

24V,10W Lamp, 10W

Flasher

Shift indicater

Key start switch

Engine kill switch

Piece fuse 5A

Piece fuse 10A

Piece fuse 20A


Propeller shaft bolt assy of carrier driving parts

Bolt

No.and
Specification

Qty.

13342 H4
13961 W5W
13336 H3
13821 W-R5W
13498
P21P2
ZW
24V,10W
13499p21/5W
13854 C10W
J115
ZSY02WX
JK406B
JK931-111
BX2011C-5A
BX2011C-5A
BX2011C-5A

2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
10

Nut

10

Lock Washer
Repairing bag for steering mechanism

Repairing bag for steering mechanism

GB93-87

Angle gear box assy

Repairing bag for angle gear box


Main drum

Air bag

Spring

Friction disc

Platen
Main drum brake system

Knit brake block

Cast brake block

Tension spring

Screw and Nut

10

1
XJ801-6-1-1-9-0
XJ801-6-1-1-11
SJ801-6-1-1-12
XJ801-6-1-1-0

1
12
3
1

4JC1-4-4-2
4JC1-4-4-3
4JC1-4-7

16
4
4
each120


Shandong Kerui Group Holding Co.,Ltd.

Bailing drum assy

Spring

Friction disc

Air bag

Platen
Bailing drum brake system

Brake block

Brake block

Screw M1032

Tension spring

Nut

XJ801-6-1-1-11
XJ801-6-1-1-12
XJ801-6-1-1-9-0
XJ801-6-1-1-10

6
1
1
1

CX301-8-2-5-3A
4JC1-4-7
GB68-1985
GB6170-20000

2
18
30
4
30

Working unit driving system propeller shaft

Bolt

10

Nut

10

Lock washer

10

Crown anti-collision cylinder

Repairing cylinder bag

Anti-collision valve

Repairing bag for anti-collision valve

Leg cylinder

Repairing bag for leg cylinder

Rising cylinder

Repairing bag for Rising cylinder

Guide sleeve

Telescoping Cylinder

Repairing bag for telescoping cylinder

Tongs cylinder

Repairing bag for tongs cylinder

Make up cylinder

Repairing bag for make up cylinder

Traveling block and hook assy

Repairing bag for travelling block and


hook assy
Weight indicator

Sensor module
9

2-piece


Shandong Kerui Group Holding Co.,Ltd.

5.2 Tool attachment list


Item
Name and Specification
1.
Box wrench (32 piece/set)
2.
Double head wrench (10 piece/set)
3.
Ring wrench (8 piece/set), Allen wrench (8 piece/set)
4.
5
6
7
8

8 adjustable wrench
10adjustable wrench
12adjustable wrench
15adjustable wrench
45050 adjustable wrench

Qty
1
1
Every 1
set
1
1
1
1

9
18pipe spanner
1
10
8 slip joint pliers
1
11
5screw driver
1
12
10 screw driver
1
13
Snapring pliers(4 piece/set)
1
14
Bench hammer( 2 pound)
1
15
Jack (15ton)
1
16
Grease gun
1
17
Oil gun
1
18
Tire presser gauge
1
19
Gas filled tube(with joint)
1
20
Working light
1
21
Long pinch bar
1
22
Short pinch bar
1
23
Double head sleeve
1
24
Pressing plate
2
25
Pressing plate
2
26
Locating rod of spring
6
27
Drawer
1
28
Similar hook wrench for raising cylinder(5 piece/set)
1set
30
8 pipe spanner
1
31
Muck-stick
1
32
Bow saw
1
33
600 lever ruler
1
6 Appearance colour:
Ship hull paint, it shall be corrosion resisting, heat resisting, and damp
proofing.
Crown block is scarlet
One third lower mast is blue, one third middle mast is white, and one third
upside of mast is scarlet. Light working platform is black. Centralizer and
carrying mechanism is scarlet.
10


Shandong Kerui Group Holding Co.,Ltd.

1.
2.
3.
4.
5.
6.

1.
2.
3.
4.

Upside of carrier is scarlet


Carrier cab is white, carrier is black, the rim is white
The guardrail is yellow
Others colour may be determined by seller
7Technical Information
Seller should refer below technical information when referring workover rigs
Integrated product conformity certificate
Quality certificate: API, ISO9000 quality certificate each one duplication
Seller should refer operating instruction book and servicing maintenance
book(English and Chinese each third)
Product delivery order(English and Chinese each third)
Attachment tool list(English and Chinese each third)
Fault detector report for each important assy and part, material qualification
test report for key assy and part(mast, traveling block and hook assy),(English and
Chinese each one)
80thers
The agreement is a contract attachment, possessing legal right with
contract when both side sign and take one. It can be consulted added and change
The agreement attach product matching list, tool list easily worn parts list
each one
Seller should note buyer check and accept product while the product gassy
and test. If acceptability may be delivery
No statement both side discuss and treat and then form a file so becoming
a added agreement.
9. Delivery time: after contract come into force 100workdays in KERUI factory.