Documente Academic
Documente Profesional
Documente Cultură
SECTION: I
Risk Overview
Risk Management
Risk Identification
Initial Risk Catalog:
Risk Analysis & Categorization
Mitigating Risks
Identifying Risks for an AMS Account
SECTION: II
Risk Management with IBM Program Work Center (IPWC)
IPWC Interface for Risk Management
IPWC Customizing Risk Log
Risk Probability and Impact would decide Risk Level
IPWC - Create Risk
IPWC Risk Closure
IPWC Reopening a Risk
IPWC Associating a Risk with Task
IPWC Associating a Risk with Discussion
IPWC Association in Risk Log
APPENDIX: I
Risk Management with IBM Rational Portfolio Manager
APPENDIX: II
References
SECTION: I
Risk Overview
What is Risk?
A Risk is a potential problem or situation, if
materializes, may adversely affect the Project. When
risks materialize they are no longer risks but
Problems.
All Projects have risks and all risks are ultimately
handled,
Category I: Some Risks never happen or disappear from the
scenario
Category II: Some Risks develop into problems and those demand
attention.
Category III: A few escalate into crisis and destroy the Project
4
Risk Example
A company has introduced object-oriented (OO) technology into its
organization by selecting a well-defined project "X" with hard schedule
constraints to pilot the use of the technology. Although many "X" project
personnel were familiar with the OO concept, it had not been part of their
development process, and they have had very little experience and
training in the technology's application. It is taking project personnel
longer than expected to climb the learning curve. Some personnel are
concerned, for example, that the modules implemented to date might be
too inefficient to satisfy project "X" performance requirements.
The risk is: Given the lack of OO technology experience and training,
there is a possibility that the product will not meet performance or
functionality requirements within the defined schedule.
Reference: http://www.sei.cmu.edu/risk/
6
Risk Management
Risk management ensures that risks never fall into
third category, i.e. restricts risks in taking shape of
crisis which leads to project closure.
Steps of Risk Management:
Risk Identification
Risk Analysis & Categorization
Risk Mitigation
Equipment Risk
Client Risk
Scope Risks
10
Delivery Risks
Physical Risks
11
Impact
Degree of Risk
High
High
Extreme
High
Medium
High
High
Low
Medium
Medium
High
High
Medium
Medium
Medium
Medium
Low
Low
Low
High
Medium
Low
Medium
Low
Low
Low
Low
13
14
15
Mitigating Risks
To mitigate a risk we need to reduce its probability,
impact or both. So we need to be proactive to reduce
the probability and impact of Risks.
Risk identification and prioritization activities are only
useful if actions are defined and executed to mitigate
risks.
Aggressive, proactive risk mitigation actions for top
priority risks are essential to achieve the benefits of
Software Risk Management.
Risk mitigation actions are defined individually for
project risks.
16
Mitigating Risks
Risks may be categorized according to SDLC like
Requirement Risks, Design Risks, Coding Risks and
Testing Risks etc.
In some cases, immediate action will be called for; in
others, future consideration will be more appropriate.
So for each and every risk we need to prepare an action
plan and have to strictly implement the defined plan.
Risk, its analysis, action or mitigation plan as well as the
implementation details should be well documented.
It is a simplistic way of Risk Management.
17
Probability
(H/M/L)
Impact
(H/M/L)
Status
Probability
(H/M/L)
Impact
(H/M/L)
Status
Probability
(H/M/L)
Impact
(H/M/L)
Status
Probability
(H/M/L)
Impact
(H/M/L)
Status
Probability
(H/M/L)
Impact
(H/M/L)
Status
22
Probability
(H/M/L)
Impact
(H/M/L)
Status
SECTION: II
24
Delete Risk
Create Risk
Select the Is Calculated check box if you want the Risk Level to be auto-calculated
If the Is Calculated is unchecked , each of the parameters can be selected and set appropriately.
The Consequence / Mitigation Strategy and the status needs to be updated appropriately.
When the risk is created/deleted/updated IPWC will send the notification to the stakeholders
identified with escalation matrix.
28
To close the
risk-view or
page. Nothing to
do with risk
closure
After the Risk is closed the Reopen Option will be activated it is useful in case the Risk
needs to be reopened.
Certain fields such as Closed By, Date will be auto-updated when you press the close
button.
29
30
Associate with a
discussion
Attachments docs,
MoM, Mitigation sign
ups, action item
approvals etc.
32
34
Thank You!!
35