GOVERNMENT OF KHYBER PAKHTUNKHWA

PAKHTUNKHWA HIGHWAYS AUTHORITY


OFFICE OF THE DEPUTY DIRECTOR (EAST) ABBOTTABAD
Ph No. 0992-382607, E-mail: ddeastpkha@gmail.com Street No. 03 House No. 417, Jinnah Abad Abbottabad

No. _

/ / DD (E) / PKHA

Dated Abbottabad the __ _/12/2015

To
M/S ACE
45-l Model Town Extension
Lahore, in association with M/S Pavron, Islamabad
(Fax #: 042-5171084)
Subject:
Reference:

CONSTRUCTION OF HARIPUR BY-PASS ROAD


1. Deputy Director (HQ) letter No.20-PKHA/2532 dated 17/12/2015

In continuation to above, the Supervisory staff as approved by the Competent


Authority and communicated to you vide letter under reference above, be got mobilized at site
with immediate effect to start the construction activities and all other preliminary requirements in
accordance with the terms of reference for carrying out your assignment may also be got
completed at the earliest.

DEPUTY DIRECTOR (EAST)


Copy forwarded to:1) The Director (Construction) Pakhtunkhwa Highways Authority Peshawar.
2) The Assistant Director (East) PKHA, Haripur for information and necessary action.
3) PA to the Managing Director Pakhtunkhwa Highways Authority Peshawar.

DEPUTY DIRECTOR (EAST)

GOVERNMENT OF KHYBER PAKHTUNKHWA


PAKHTUNKHWA HIGHWAYS AUTHORITY
OFFICE OF THE DEPUTY DIRECTOR (EAST) ABBOTTABAD
Ph No. 0992-382607, E-mail: ddeastpkha@gmail.com Street No. 03 House No. 417, Jinnah Abad Abbottabad

No. _
To

/ / DD (E) / PKHA

Dated Abbottabad the __ _/12/2015

M/S Creative Engineering Consultant-H&B (JV)


House No. 6 Sector D-5, Phase-I Hayatabad
Peshawar
(Fax #: 091-5822184)
Subject:
Reference:

WIDENNG/DUALIZATION OF MURREE CHOWK- HARNO ROAD AND


NAWANSHER-LINK ROAD, DISTRICT ABBOTTABAD
1. Deputy Director (HQ) letter No.20-PKHA/2531 dated 17/12/2015

In continuation to above, the Supervisory staff as approved by the Competent


Authority and communicated to you vide letter under reference above, be got mobilized at site
with immediate effect to start the construction activities and all other preliminary requirements in
accordance with the terms of reference for carrying out your assignment may also be got
completed at the earliest.

DEPUTY DIRECTOR (EAST)


Copy forwarded to:1) The Director (Construction) Pakhtunkhwa Highways Authority Peshawar.
2) The Assistant Director (East) PKHA, Abbottabad for information and necessary action.
3) PA to the Managing Director Pakhtunkhwa Highways Authority Peshawar.

DEPUTY DIRECTOR (EAST)