GOVERNMENT OF KHYBER PAKHTUN KHWA

PAKHTUNKHWA HIGHWAYS AUTHORITY PESHAWAR

CONSTRUCTION OF HARIPUR BYPASS ROAD FROM KM. 0+000 TO KM. 24+480 (24.480 KM.)

S. No

Description

Location

Status

Contractor

Contract
Commencement
Amount (Rs.)
Data

Completetion
Date

Progress up to 10-03-2016

Remarks/Issues

PACKAGE-I

Km 0+000 to Km 5+250

Contract Awarded

M/s New Khan


Builders

395,442,568

30-09-2015

29-12-2018

Center Line from Km. 0+000 to Km 5+250


has been marked. Joint X-Section from Km
0+000 to Km 2+200 has been taken.

Land Acquisition is in
progress

PACKAGE-II

Km 5+250 to Km 10+500

Contract Awarded

M/s Khattak Allied


Construction Co.

436,777,930

19-10-2015

18-01-2019

Center Line from Km. 5+250 to Km 10+500


has been marked.

"

PACKAGE-III

Km 10+500 to Km 16+450

Contract Awarded

M/s Khattak Allied


Construction Co.

414,126,232

19-10-2015

18-01-2019

Center Line from Km. 10+500 to Km


16+450 has been marked.

"

PACKAGE-IV

Km 16+450 to Km 20+650

Contract Awarded

M/s Khattak Allied


Construction Co.

293,652,805

19-10-2015

18-01-2019

Center Line from Km. 16+450 to Km


20+500 has been marked.

"

PACKAGE-V

Km 20+650 to Km 24+480

Contract Awarded

M/s Haji Raees Khan


& Sons Cont: Co

337,240,304

10/10/2015

9/1/2019

"

PACKAGE-VI

03 Nos. Bridges (Km 8+450, Km


14+880 & Km 23+930)

Contract Awarded

M/s Haji Raees Khan


& Sons Cont: Co

220,525,317

10/10/2015

9/1/2019

"

5 Nos. Flyovers (Km 2+200, Km


PACKAGE-VII 3+045, Km 5+283, Km 8+930 &
Km 12+315)

Contract Awarded but


Contract Agreement yet
to be signed.

M/s Khattak Allied


Construction Co.

136,231,915

"

GOVERNMENT OF KHYBER PAKHTUN KHWA


PAKHTUNKHWA HIGHWAYS AUTHORITY PESHAWAR

CONSTRUCTION OF HARIPUR BYPASS ROAD FROM KM. 0+000 TO KM. 24+480 (24.480 KM.)

PROGRESS STATUS AS ON 07-04-2016

S. No

Description

Location

Status

Contractor

Contract
Commencement
Amount (Rs.)
Data

Completetion
Date

Progress up to 07-04-2016

Remarks/Issues

PACKAGE-I

Km 0+000 to Km 5+250

Contract Awarded

M/s New Khan


Builders

395,442,568

30-09-2015

29-12-2018

Center Line and Joint X-Sections


completed from Km. 0+000 to Km.
5+250 .

Land Acquisition is
Under Process.

PACKAGE-II

Km 5+250 to Km 10+500

Contract Awarded

M/s Khattak Allied


Construction Co.

436,777,930

19-10-2015

18-01-2019

Center Line and Joint X-Sections


completed from Km. 5+250 to Km.
10+500.

"

PACKAGE-III

Km 10+500 to Km 16+450

Contract Awarded

M/s Khattak Allied


Construction Co.

414,126,232

19-10-2015

18-01-2019

Center Line and Joint X-Sections


completed from Km. 10+500 to Km.
16+450.

"

PACKAGE-IV

Km 16+450 to Km 20+650

Contract Awarded

M/s Khattak Allied


Construction Co.

293,652,805

19-10-2015

18-01-2019

Center Line from Km. 16+450 to Km.


20+650 has been marked.

"

PACKAGE-V

Km 20+650 to Km 24+480

Contract Awarded

M/s Haji Raees Khan


& Sons Cont: Co

337,240,304

10/10/2015

9/1/2019

Center Line from Km. 20+650 to Km.


24+480 has been marked.

"

PACKAGE-VI

03 Nos. Bridges (Km 8+520, Km


14+875 & Km 23+942)

Contract Awarded

M/s Haji Raees Khan


& Sons Cont: Co

220,525,317

10/10/2015

9/1/2019

Not started yet.

"

5 Nos. Flyovers (Km 2+135, Km


PACKAGE-VII 3+070, Km 5+295, Km 9+017 &
Km 12+323)

Contract Awarded but


Contract Agreement yet
to be signed.

M/s Khattak Allied


Construction Co.

136,231,915

Layout of KKH Road Interchange at


Km. 5+283 has been completed.

Mushtaq Ahmad
Resident Engineer
ACE/PAVRON Haripur Project

"

GOVERNMENT OF KHYBER PAKHTUN KHWA


PAKHTUNKHWA HIGHWAYS AUTHORITY PESHAWAR

CONSTRUCTION OF HARIPUR BYPASS ROAD FROM KM. 0+000 TO KM. 24+480 (24.480 KM.)

PROGRESS STATUS AS ON 30-04-2016

S. No

Description

Location

Status

Contractor

Contract
Commencement
Amount (Rs.)
Data

Completetion
Date

Progress up to 30-04-2016

Remarks/Issues

PACKAGE-I

Km 0+000 to Km 5+250

Contract Awarded

M/s New Khan


Builders

395,442,568

30-09-2015

29-12-2018

Center Line and Joint X-Sections


completed from Km. 0+000 to Km.
5+250 .

Land Acquisition is
under process.

PACKAGE-II

Km 5+250 to Km 10+500

Contract Awarded

M/s Khattak Allied


Construction Co.

436,777,930

19-10-2015

18-01-2019

Center Line and Joint X-Sections


completed from Km. 5+250 to Km.
10+500.

"

PACKAGE-III

Km 10+500 to Km 16+450

Contract Awarded

M/s Khattak Allied


Construction Co.

414,126,232

19-10-2015

18-01-2019

Center Line and Joint X-Sections


completed from Km. 10+500 to
Km. 16+450.

"

"

"

PACKAGE-IV

Km 16+450 to Km 20+650

Contract Awarded

M/s Khattak Allied


Construction Co.

293,652,805

19-10-2015

18-01-2019

Center Line from Km. 16+450 to


Km. 20+650 has been marked.
Joint X-sections from Km. 16+450
to Km. 18+725 has been
completed.

PACKAGE-V

Km 20+650 to Km 24+480

Contract Awarded

M/s Haji Raees Khan


& Sons Cont: Co

337,240,304

10/10/2015

9/1/2019

Center Line from Km. 20+650 to


Km. 24+480 has been marked.

PACKAGE-VI

03 Nos. Bridges (Km 8+520, Km


14+875 & Km 23+942)

Contract Awarded

M/s Haji Raees Khan


& Sons Cont: Co

220,525,317

10/10/2015

9/1/2019

5 Nos. Flyovers (Km 2+135, Km


PACKAGE-VII 3+070, Km 5+295, Km 9+017 &
Km 12+323)

Contract Awarded but


Contract Agreement yet
to be signed.

M/s Khattak Allied


Construction Co.

136,231,915

Not started yet.

"

Layout of KKH Road Interchange


at Km. 5+283 has been
completed. SPT at Km. 2+135 and
Km. 3+070 Flyovers are
completed while SPT at Km.
5+295 Flyover is in progress.

"

Engr. Mushtaq Ahmad


Resident Engineer
ACE/PAVRON Haripur Project