Sunteți pe pagina 1din 13

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

Financial Analysis
For PPP projects, financial analysis forms a key element of the due diligence to be
undertaken. Both the private sector and contracting authority need to know the projects
projected financial performance and for the public sector this is provided by the Stage 2
financial analysis. The analysis will also indicate whether the project needs fiscal support
and/or guarantees from Government.
Clearly, the assumptions used by the public and private parties may not/will not be the
same. This would account for the differences in the results from financial analysis. Very
likely these differences will be a basis for negotiation at a later stage.
Two commercial issues are relevant to this section, and comprise tariffs and fiscal support.
These are discussed below.
Financial analysis uses costs and revenues and is focused on assessing the project from
an investment viewpoint, usually from the point of view of the private sector or a
corporation (Sometimes referred to as a Special Purpose Vehicle or Company (SPV or
SPC)), specially created for the execution of the project.
The financial analysis is based on the standard methodology used by the private sector,
and by the public sector for private sector oriented projects, in the analysis of project
feasibility. The financial analysis uses debt service, the commercial weighted cost of
capital, the return on equity and is expressed in current terms (i.e. with inflation/
escalation). It therefore differs from the standard financial analysis used by donor
agencies and public sector.
It should be assumed, at least initially, that PPP projects will either not need any
financial support from the government, or if needed, such support will be targeted and
minimized.

odu

le

odu

le

49

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

Based on its assumptions, the financial analysis is able to show:


If the project is financially viable (or bankable may be a better word, since
a bankable project will always be financially viable, but a financially viable
project may or may not be bankable) and and sets out the financial performance,
including direct financial risk, of the project over its life. It should be noted that
all risks have a financial dimension. Direct here is used in the sense of sensitivity
of the projects financial performance to the variables used in the model e.g. toll
rates, demand, costs, debt service etc.;
What would be needed to make the project viable (bankable or acceptable to the
private sector) if it turns out to be only marginally viable; and
The clear identification, approximate costing and timing of any proposed project
support measures, and through which financial instruments this support may be
provided, minimized and scheduled.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

Financial Model Inputs


In order to assess a project in financial terms, it is necessary to develop a financial
model. This is provided in the Toolkit (Module 6 -> Financial Models). By necessity, this
is usually more complicated than the economic analysis in that in particular (i) revenue
streams and (ii) debt servicing need to be detailed and projected based on a number
of scenarios and assumptions. However, economic analysis of large multi facetted
development projects can be equally complex.
The following are the key factors needed to be input to a financial model:
Financial Project Costs (construction, land, engineering, surveys etc.) and by the
year incurred
Demand (traffic by type)
First Year Tariffs (by type) and Tariff Escalation Formula(s)
Annual Operating and Maintenance Costs (base year estimate plus an inflation
related increase or can be related pro rata to the inflation related revenue)
Types of Equity
Debt to Equity Ratio (usually varies between 80:20 and 60:40, commonly 70:30)
Debt service arrangements and costs (types of debt and interest rates, grace and
repayment periods)
Weighted average (opportunity) cost of capital
Tax rates (national corporate rates)
Depreciation basis allowed (national regulations)
The financial model structure, and these types of inputs, will be largely similar for all PPP
projects. Road projects have much simpler traffic groups than say airports or ports where
there are many more revenue streams.
Costs can be calculated by building up direct, indirect and overhead costs based on
historic data or more usually as a percentage of project costs or as a percent of revenue.
It should be noted that historic/actual data is paradoxically usually quite unreliable and
the percentage (rule of thumb) basis at least as good and much easier to generate at
this stage.
All projects suffer from forecasting difficulties and this should be borne in mind at both
the modeling stage and risk assessment stage where inaccuracies in demand forecasts
may substantially outweigh uncertainties in other model inputs/assumptions.
Project costs will be initially in base year values (i.e. when the analysis is undertaken)
but price contingency will be added for each construction year and revenue and costs
inflated by an appropriate index.

odu

le

odu

le

50

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

The Request for Proposals (RFP) should include the proposed index, or the proposed
tariff escalation rates, which will be allowed under the contract. Tariff escalation should
be a criterion in bidder procurement allowing bidders to compete on initial as well as
future tariffs.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

Financial Model Outputs


The model then outputs the Profit and Loss statement and the Cash Flow statement
providing estimates of the key data for each project year. (Other supplementary
accounting outputs are usually needed later, such as balance sheets).
These statements show:
The overall project cash flow.
The cash flow available to the equity participants (investors).
Profitability/Viability: The Financial Internal Rate of Return/Return on Equity
(project FIRR/or ROE). This is based on the same mathematical process as the
EIRR but instead uses financial costs and revenues over the project life. Further, it
does not use incremental costs and benefits but actual costs and actual revenues.
Cost recovery; the number of years to pay back the equity investment (the norm
is 5-7 years for commercial projects but infrastructure projects may only generate
payback over 10-15 years or more).
Debt Service Cover Ratio (the projected cash flow must, at a minimum, be
adequate to finance the projected debt service. (The usual requirement is that
the net cash flow each year must be at least 1.2 times (depends on the risk
profile) the debt payment due in that year)
The estimated FNPV. (It may be useful to distinguish the NPV from the SCBA
and financial analysis by using ENPV and FNPV).
Quantitative risk analysis are also increasingly standard model outputs.
Together, these make up most of the quantitative basis of bankability, although
other aspects can also be important such as non-quantified risk.

Financial Model Assessments


Models can be used to assess the:
Length of contract needed to generate an acceptable return on equity.
The financial impact of different types of debt and equity and thus the optimum
debt equity ratio.
Losses in early years (if applicable) that need to be met by the PPP concessionaire
(and/or by fiscal support/guarantees).
Fiscal support that may be needed (and as input to the projection of the cost of
guarantees)
The financial impact and the subsequent optimum timing of the claw back of
subsidies (fiscal support).
Corporate Tax revenue to government (when profits are made).
Impact of changing key variables such as tariff, projects costs etc.
Government returns if an equity participant (and if on different terms to the
private sector e.g. secondary equity).

odu

le

odu

le

51

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

Hence key parameters are input to the model which then produces the financial estimates
from which decisions on the PPP project can be made.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

Generally, if a project is financially viable, it is usually economically viable. However,


an economically viable project may or may not be financially viable as the revenue may
not be adequate (Traffic or Tariff or both). For example, road projects generate high
economic benefits but tariffs are set to be socially/politically responsive.

Tariff Escalation
Tariffs and tariff escalation are normally determined to ensure a proper rate of return
based on an efficient operation. However, a subsidy may be specifically allowed by the
regulations and procedures with such funding being paid by the Government to the PPP
concessionaire based on a lower toll rate related to estimates of the users Ability to
Pay concept.
The concept of an agreed financial return incorporates several important subordinate
principles;
The need for full cost recovery (capital, operating and financing costs) if at all
possible i.e. the user pays.
The application of non-uniform tariffs (tariffs determined by project not sector).
The proposed tariff escalation also to be project based and written into the
concession agreement.
The tariff and/or subsidy, if necessary, should be determined through competitive
bidding to ensure the best deal for the user/the lowest liability for Government.
What constitutes a proper or acceptable rate of return on equity (ROE) is not specified
but might be around 18%-20% or more but would vary on a case by case and country
by country basis. The macro economic situation including inflation and returns available
in other sectors (opportunity costs) should also be included in the assessment of a fair
return.
Risks and target profit levels are directly related in that generally the lower the risk, the
lower is the private sectors target return on a project. Therefore, in assessing a fair
return to the private sector, it is critical that Government must understand this risk/
profit relationship in general and also specifically related to the subject project.
The more the risks of a project can be allocated to the best party able to bear and
mitigate them, the lower the private sectors demands for a specific return will be (More
accurately, the lower the private sectors demand for risk premiums, over and above a
risk-free return will be) and the cheaper the cost of the services provided under the
project will be.
The role of government is to negotiate a contract that neither provides for (i) more or
(ii) less than around the approximate hurdle rate of return for the specific project in
question. The former would mean too high a cost would be borne by the users and the
latter means the project will probably not be implemented.

odu

le

odu

le

52

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

Therefore, Government should be clear that in trying to avoid what may be regarded as
excessive returns, it is not itself taking on unreasonable and/or excessive contingent
liabilities and risks, nor negating legitimate commercial interest in the project.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

Government must therefore be sufficiently flexible and agree to higher returns if project
or other relevant circumstances demand.
This balance should be appreciated, by Government, as being a difficult and somewhat
delicate issue on which adequate consideration (including consultation) should be
included within the pre-or full FS study.

Financial Analysis and Concession Agreements


The Concession Agreement is a detailed contract between the parties that describes the
project in technical and financial terms including risk management. Many projects suffer
from vague contracts but a contract that may runs for up to 30 years or more has to
anticipate all types of eventualities, at least, in broad terms to cover all wider, general
and potential problems.
The financial analysis allows the Government to draft the financial aspects of the
concession agreement with confidence for inclusion in the RFP. The pre- or full feasibility
study contains the SCBA, the above financial analysis as well as other information which
provides the key bases for negotiation on an equal playing field (which implies that all
parties will have all of the appropriate information and no party will be disadvantaged
by insufficient information at the time of negotiations) with the preferred bidder.
The financial analysis and model can also be used later to model the tenders received to
assess the financial bids of tenderers for accuracy and realism.
One example is indicative of the difficult issues that often arise in dealing with the
outputs of a financial analysis. Based on a 25-year concession, the Return on Equity
(ROE) is about 18%. If this was assumed to be without major risks, that should be
sufficient to get the private sector interested although they would prefer a return of the
order of at least 20 %.
However, the model could show that other financial indicators are weak with a payback
of 10 years and the debt service cover ratio (DSCR) does not become acceptable until
between years 5 and 6 of operation. As the DSCR indicates, the cash flow is weak in the
early years and the first three years show a negative cash flow.
A PPP project based on the above assumptions would be termed risky (or not bankable)
in financial terms by the private sector even though Government might consider the
FIRR/ROE was adequate. The sensitivity and risk analysis would show that should
construction costs rise beyond that expected or if demand was lower than forecast, the
financial returns would be less than 18%. In these circumstances, the key to financing
infrastructure will be credit enhancement.

Credit Enhancement

odu

le

odu

le

53

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

The term credit enhancement is defined as taking those measures to improve the risk
and return profile of a project (which is economically viable) to attract financing so that
it will proceed to financial closure.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

The term credit enhancement may cover a variety of meanings. In principle, anything
that improves a projects bankability, may be considered credit enhancement. In broad
terms, this may include (i) a sound, credible, transparent cooperation program and (ii)
project identification and structuring which understands and addresses the concerns of
the private sector.
It may include the following three types of measures;
Typical project finance techniques. These include measures (such as escrow
accounts, mezzanine financing, and securitization) which seek to minimize
the typical types of risk found in any cooperation project. They include the
measures agreed to by the sponsors and developers (the equity participants) and
the debt participants, and usually do not directly involve the host government.
It is important, however, for the contracting authority and other agencies
of government that are involved, to be aware of and conversant with these
techniques as a part of their oversight and due diligence responsibilities in
procuring and monitoring the desired infrastructure services.
Government support. This includes a range of policies and measures (such as
off-take agreements, revenue guarantees, tax holidays) that the government can
provide to reduce the levels of risk, and improve the finances of the project, or
both, as perceived and analyzed by the PPP concessionaire, and especially the
lenders.
IFI (and Donor) support. This includes a range of instruments that IFIs and
donor agencies, such as USAID/DCA, the IFC, the ADB, OPIC, EXIM banks and other
bilateral and multilateral donors can provide to assist a country to develop its
cooperation program and bring projects to financial closure and implementation.
These typically come into force when the overall country risk is perceived to be
high (thus making purely commercial financing difficult) even though individual
projects may have sound financial and economic dynamics and deserve to be
implemented as cooperation projects.
Therefore if a project has characteristics which indicate weak or marginal financial
feasibility and/or higher than acceptable risks, the following steps would be considered
by the private sector, each with different implications for the Government, such as;
Project Costs: review/reduce costs, rephase/defer some costs
Tariff: increase proposed tariff and/or agree higher or more rapid escalation rates
Funding/ debt service improvements including seeking to reduce interest rates
or increase loan tenor (repayment period) terms (possibly in conjunction with
item 2 following)
Seek to reduce annual costs
Consider if donor support might enhance bankability partly through iii above and
consider providing some kind of fiscal support
Guidelines on government guarantees are presented in the following section.

odu

le

odu

le

54

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

A typical layout of a financial model and financial template for a PPP highway project are
shown in the Module 6 -> Financial Models.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

Evaluating Government Financial Support


Government financial support is discussed in detail in Module 3-Financial Framework.
The challenge at this stage is that once it is established that a project needs support, to
evaluate and value the different types of support. Assuming that all the types of support
achieve the objective required, the aim is to select that support which ensures value for
money and is in line with the Governments fiscal framework.
The types of support and the methods to determine costs of each type are shown in table
below.
INSTRUMENTS OF FINANCIAL SUPPORT AND THEIR VALUATION
Easy to estimate in early years
but progressively more difficult
over time. For short-term use
standard forecasting techniques.
For longer term use PV of expected expenditure. While there
are difficulties, problems in estimating relatively small.

2. In Kind Grants

Opportunity Cost or 'At Cost'

Generally the 'easiest' to calculate. For example, land costs


based on market value although
other costs may be somewhat
more difficult to value.

3. Tax Breaks

Opportunity Cost or Net Loss in


Tax Revenue

Given that tax is included in the


financial model, it would be possible to model with and without
the tax breaks, the difference
then providing the value of the
tax break.

4. Capital Contributions

Opportunity cost of capital

Capital contributions are classified as a subsidy or commercially


focused support depending on
the cost of the support.

4.1 Debt

Return elsewhere compared to


the return of this project

(Value of loan contribution) =


(Amount of Loan) minus (Present Value of interest and principal discounted at an agreed discount rate (possibly commercial
rates)).

4.2 Equity

Return elsewhere compared to


the return of this project

As with debt, but with a risk


premium. The risk premium and
its derivation were described in
the WB report.

odu

le

odu

le

odu

le

55

odu

le

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

Value of the Explicit Subsidy


Discounted over the Period

1. Output Based Subsidies

Comment

Valuation

Instrument

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

5. Guaranteed Risks
(Not under government Control)

PV of expected payouts

Payments should be capped.


Based on what is expected to be
paid out on average.
Can also estimate payments
Government is likely to make
and calculate PV based on the
methodology described in Section 3.8.

6. Guaranteed Risks
(Under government Control)

Same as 5. in principle

Because of difficulties with such


guarantees such as the failure to
raise tariffs as contracted, WB
advises against such valuation.

Source: Public Money for Private Infrastructure Deciding When to Offer Guarantees, Output- Based
Subsidies, and Other Fiscal Support Timothy Irwin. World Bank Working Paper No. 1

Financial Rationale for the Provision of Government Fiscal Support


The evaluation of Government financial support should be considered from several
viewpoints. The starting point for support assessment by Government should initially be
based on the objectives of the subsidy. The Government should link the objectives with
the financial performance of the project including its riskiness without any support.
If support is needed, the Government should base its support on the need to;
Attract the private sector to participate, and on fair and equitable terms
Minimize its risks
Minimize its financial obligations
Maximize certainty in providing support
Reduce risks to the private sector in order to reduce the cost of private sector
borrowing and/or to reduce the risk premium on equity
Recoup any financial support in later years
Estimating the Expected Cost of Fiscal Support for a PPP Project
This section describes a method for estimating the expected cost to or payout by the
government if it were to commit to a particular type of fiscal support.

odu

le

odu

le

56

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

The proposed method is appropriate for all types of fiscal support including:
Capital grant;
Minimum revenue or demand guarantee, including government-backed off-take or
power purchase agreement;
Full debt service guarantee;
Revenue rights to other infrastructure facilities;
Tax honeymoon or holiday; and
Operating subsidy.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

The method is intended primarily for the contracting agencies, as they are the best party
to take an informed view on the commercial aspects of a PPP project.
At this stage, any need for fiscal support for a PPP project needs justification by the
contracting authority. An assessment of the likely cost of the various types of fiscal
support that are considered appropriate would be required by;
The PPP cell, node or PPP unit in the relevant line ministry;
The PPP center; and
The PPP cell, node or Risk Management Unit (RMU), at a Ministry of Finance.
The assessment would assist the line ministry to decide if it would submit the evaluated
project to the central agencies. The PPP center, in turn, would then decide on the basis
of the due diligence conducted by the contracting authority whether to negotiate with
the RMU for fiscal support for the PPP project in question.
However, the RMU would make its own assessment of fiscal support, using possibly a
similar, but more sophisticated, method. Its decision would also certainly take into
consideration the governments fiscal policy and balance sheet (both present and future).
The final arbiter on providing government financial support for a PPP project is usually
a MOF.
The Method of Valuing the Future Cost of Fiscal Support
The method is based on a probabilistic model, specifically the expected utility model. It
calculates the expected cost of a particular type of fiscal contingent support in present
day (present value) terms. In order to simplify the analysis, it is assumed that the
opportunity cost of a monetary unit for all forms of fiscal support is the same.
This approach results in the estimated Present Value (PV) of the support options. Through
estimating the future (year 1 to n of the project) costs of each method of support, each
type can be brought back to PVs by using the appropriate discount rate and compared.
An Excel model can be developed to apply this model. Its application requires the
contracting authority to;
define the forecast volume of demand for each year (this is calculated as part of the
financial analysis);
define the period of fiscal support;
define the outcome scenario for each year (demand is, say 50%, 75%, 85% and
100% of forecast);
calculate the value of each outcome i.e. the amount of fiscal support; and
define the probability for the occurrence of each outcome in the scenario.
Thus, for each year there would be a number of outcomes with a probability assigned to
each outcome.
The results can be integrated into the Toolkit financial model.

odu

le

odu

le

57

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

Table below shows a template example of the valuation of fiscal support.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

FISCAL SUPPORT VALUATION TEMPLATE


General Assumptions

Cost of Support (PV millions)


Unit

Project Cost

Both
Risks

500

USD million

Length of
Concession

30

years

Projected
initial demand

90

units

Demand
Increase per
year

Demand
Risk

Price
Risk

Model
Result

123

95

28

0,05

Projected
initial Price

per unit

Price Increase per


year

7.5%

Discount
Factor

0,12

Period of
Support

10

years

Year

90

102

115

129

146

165

Expected
Value of
Support per
year

USD

(b)

34

30

26

18

12

14

56

71

89

111

134

151

199

123

(a) - (b)

PV of Fiscal Support
(Both Scenarios)

USD

(10
Years)

USD

odu

le

odu

le

58

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

Total Expected Value


of Fiscal
Support

(a)

USD

Projected
Revenue

RESULT SUMMARY

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

RISK#1: DEMAND SCENARIO


Year

Base Case

0.05

0.2

0.5

0.6

Shortfall 1

0.1

0.05

0.1

0.5

0.45

0.35

Shortfall 2

0.2

0.05

0.1

0.6

0.2

0.05

0.05

Shortfall 3

0.3

0.1

0.7

0.2

0.1

Shortfall 4

0.4

0.8

0.15

0.05

Shortfall 5

0.5

0.05

1.5

Year

Base Case

0.9

0.8

0.7

0.6

0.5

Shortfall 1

0.05

0.1

0.15

0.2

0.25

0.3

Shortfall 2

0.1

0.05

0.1

0.1

0.15

Shortfall 3

0.15

0.05

0.05

Shortfall 4

0.2

Shortfall 5

0.25

0.75

Sum
RISK#1: PRICE SCENARIO

Sum

Notes:
(1) Actual Model Years is 10 but simplified for presentation.
(2) Probabilities are entered manually by user.
(3) See section 3.8 for explanation on how to use
(4) Source: Draft PPP Operational Guidelines Manual, Indonesia, 2006

Criteria for Fiscal Support to PPP Projects


A number of criteria are suggested to help assess whether fiscal support should be
provided to PPP projects. These include;
The support complies with the national laws.
The proposed project has been selected as a priority within the national planning
process.
The company requesting support has been selected/procured under a fair,
transparent and competitive process with no conflicts of interest.
The level of support meets fiscal criteria of the MOF.
Other methods of support, policies or other measures would not yield equivalent
or greater socio-economic benefits.
The project is consistent with sector strategy.

odu

le

odu

le

59

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

The above criteria are a useful checklist but all of these criteria must be met.

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

Procurement and Negotiating Strategy and Fiscal Support


Based upon its above assessment, Government must determine its procurement and
negotiating strategy with regard to fiscal support.
The feasibility study will have already indicated to Government whether support is
necessary and approximately how much will be needed.
It is a vitally important principle that subsequent to the study, the government will
decide for that project whether any support will be forthcoming and the preferred type
or types.
It is therefore necessary that discussions will take place with the center and MOF at
an early stage in the project cycle to ensure coordination and that projects have not
proceeded to study stage that have little hope of support.
The RFP can either indicate a maximum level of support or indicate no figure at all, and
one of the bid criterion must be the minimization of support (or no support) requested
by bidders.
Fall back Strategy
Given that the actual agreed support will depend on negotiation with the private sector,
the Government must have a maximum level of support that it will not go beyond. The
government must therefore determine the fall back negotiation position i.e. the point at
which it considers the type/costs and/or risks of support are not justified.
Summary of Policy Guidelines on Government Support
The Government requires more and better infrastructure while maintaining fiscal prudence.
However, if the project is risky and/or cannot generate sufficient revenue (demand is
less than projected and/or users do not pay enough) the government through taxpayers
must make up the difference.
Government needs to know whether it should contribute any support and, if so, how
much support should it provide and its timing.
It is clear that each project will have different characteristics and therefore support will
vary.

odu

le

odu

le

60

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

The guidelines for support are therefore as follows:


Assess if support is necessary through the results of the feasibility study
Determine the objectives of the support
Ensure the support meets the criteria for fiscal support set down by the MOF (as
described above)
Assess how to target/focus support and its timing
Assess how to minimize support and risks
Assess the costs and risks of the different types of support

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s

odu

le

odu

le

61

odu

le

odu

le

Module 5 : Implementation and monitoring


Updated march 2009

odu

le

Assess the best support strategy from the Governments viewpoint


Decide on the maximum support that would be justified for the project
Agree on the Governments appropriate initial support strategy before proceeding
to tender
Confirm and/or refine the Governments support strategy in the light of project
tenders
Negotiate on the basis of the above information which can be refined during the
PPP project cycle.

S-ar putea să vă placă și