Documente Academic
Documente Profesional
Documente Cultură
Table of Contents
Contents
1 Prologue...................................................................................1
2 City Development Plans and Transport Plans .............................5
3 Commuter Rail System and its importance for Bangalore......... 16
4 Rail system: Integrates City Core and Suburbs ........................ 24
5 Demand Supply Assessment ................................................... 33
6 CRS Implementation: Infrastructure Development .................. 45
7 Land The Game Changer....................................................... 90
8 Cost Estimates and Phasing of Investments ............................. 99
9 Return on Investment ........................................................... 116
10 Institutional Arrangements & Financing ................................ 125
11 Recommendations and Roadmap further .............................. 142
RITES
Table of Contents
Detailed Contents
1 Prologue...................................................................................1
1.1
1.2
1.3
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3.2
3.3
3.3.1
3.4
3.4.1
3.5
3.6
3.7
The Reality....................................................................................................................... 24
4.2
4.3
4.4
ii
RITES
Table of Contents
4.5
Reverse Engineering......................................................................................................... 27
4.6
4.6.1
4.6.1.1
4.6.1.2
4.6.1.3
4.6.1.4
4.6.1.5
4.6.2
Locating Commuter Rail Terminals: Enter City Core or Terminate at Outskirts ................... 28
Commuter Needs ............................................................................................................ 28
Passenger Travel Patterns ................................................................................................ 29
Provision of alternate Public Transport ............................................................................ 30
Impact of forced transfers on service patronage .............................................................. 30
Development of BMR ...................................................................................................... 30
Indian Railways Considerations ........................................................................................ 31
RITES Recommends ......................................................................................................... 31
4.7
Modal Transits................................................................................................................. 31
4.8
Conclusions...................................................................................................................... 32
5.2
5.2.1
5.2.2
5.2.3
5.2.4
5.3
5.4
5.5
5.6
5.7
5.8
Backdrop ......................................................................................................................... 45
6.2
6.3
6.3.1
6.3.1.1
6.3.1.2
6.3.1.3
6.3.1.4
6.3.1.5
6.3.1.6
6.3.2
6.3.3
6.3.4
6.3.5
Terminal Strategies.......................................................................................................... 46
Bangalore Terminal (SBC)................................................................................................. 46
Over View........................................................................................................................ 46
Platforms:........................................................................................................................ 47
Lie-Overs and Engine Reversals ........................................................................................ 48
Lengths of various Lines: The Operational constraints ...................................................... 50
Interconnectivity of Lines................................................................................................. 51
Yard Speeds ..................................................................................................................... 53
Yesvantpur Terminal ........................................................................................................ 54
Additional Terminals........................................................................................................ 55
Binny Mill Land Terminal: An extension to SBC terminal ................................................... 56
Baiyyappanahalli North: The Maintenance Terminal ........................................................ 57
iii
RITES
Table of Contents
6.3.5.1
6.3.5.2
6.3.6
6.3.7
6.3.8
6.3.9
6.4
6.4.1
6.4.2
6.4.3
6.4.4
6.4.5
6.4.6
6.4.7
6.4.8
6.4.9
6.4.10
6.5
6.5.1
6.5.2
6.6
6.7
6.8
6.8.1
6.8.2
6.8.3
6.8.4
6.9
6.9.1
6.9.2
6.9.3
6.9.4
6.9.5
6.10
6.11
7.2
7.3
7.4
7.4.1
iv
RITES
Table of Contents
7.4.2
7.4.3
7.5
Land for locating new terminal (4 coaching terminal) in SBC-MYS section ....................... 94
7.6
7.7
7.8
7.9
7.10
7.11
7.12
7.13
th
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.10
8.11
8.12
8.13
9.2
9.3
9.4
9.5
RITES
9.5.1
9.5.2
9.5.3
Table of Contents
10.2
10.3
10.4
10.5
10.6
10.6.1
10.6.2
10.6.3
10.6.4
10.6.5
10.6.6
10.6.7
10.6.8
11.2
11.3
vi
RITES
Table of Contents
Tables
Table: 1.1 Population of Bangalore Metropolitan Region ........................................................................ 1
Table: 1.2 Modal Splits Comparison with Mumbai .................................................................................. 2
Table: 1.3 Past studies on CRS - Bangalore............................................................................................. 3
Table: 1.4 Terms of Reference ................................................................................................................ 3
Table: 2.1 Authorities functioning within BMR....................................................................................... 5
Table: 2.2 Population projections and allocations ................................................................................. 11
Table: 2.3 Share of various modes of transport ...................................................................................... 12
Table: 2.4 Phasing of Investments (WSA recommendations) ................................................................. 13
Table: 2.5 Total investment program for long term scheme (WSA recommendations) ............................ 13
Table: 2.6 Phasing of total investments (WSA recommendations) ......................................................... 13
Table: 2.7 Corridors suggested by RITES (2011) .................................................................................. 14
Table: 2.8 Section overlap of other modes of transport with CRS .......................................................... 14
Table: 2.9 Value of Overlap .................................................................................................................. 15
Table: 3.1 Capacity comparison of different modes ............................................................................... 18
Table: 3.2 Average Trip Lengths of different modes .............................................................................. 22
Table: 4.1 CRS Network in Bangalore .................................................................................................. 25
Table: 4.2 Other modes of transport parallel to IR Network within 1 Km ............................................... 25
Table: 4.3 Other modes of transport parallel to IR Network within 2 Km ............................................... 26
Table: 4.4 Other modes of transport parallel to IR Network within 5 Km ............................................... 26
Table: 4.5 IR Network parallel to other modes of transport .................................................................... 26
Table: 4.6 Consultant suggestions for Hyderabad MMTS ...................................................................... 27
Table: 4.7 Existing travel pattern of Bangalore rail commuters .............................................................. 29
Table: 5.1 Population density in 2011 ................................................................................................... 35
Table: 5.2 Assumed decadal growth rate of population ......................................................................... 35
Table: 5.3 Split of each section district wise .......................................................................................... 35
Table: 5.4 Modal split of commuter traffic in Mumbai .......................................................................... 36
Table: 5.5 Per Capita Trip Rate ............................................................................................................. 36
Table: 5.6 Modal share Vs trip lengths .................................................................................................. 37
Table: 5.7 The three scenarios ............................................................................................................... 38
Table: 5.8 Assessed Commuter Rail Trips (Scenario: Low) ................................................................... 38
Table: 5.9 Assessed Commuter Rail Trips (Scenario: Medium) ............................................................. 39
Table: 5.10 Assessed Commuter Rail Trips (Scenario: High)................................................................. 39
Table: 5.11 Suburban rail services Supply position ............................................................................. 40
Table: 5.12 Historical trend of passenger growth ................................................................................... 41
Table: 5.13 Traffic Projections for various commuter system in India .................................................... 42
Table: 5.14 Assessment of additional services required to bridge demand supply gap ............................ 44
Table: 6.1 Major rail projects in Bangalore area in the past .................................................................... 45
Table: 6.2 Rakes lie over at SBC........................................................................................................... 49
Table: 6.3 Lines length of SBC yard ..................................................................................................... 50
Table: 6.4 Interconnectivity of running lines at SBC ............................................................................. 51
Table: 6.5 Trains being terminated short of SBC ................................................................................... 52
Table: 6.6 Scenario of SBC yard after suggested remodelling ................................................................ 54
Table: 6.7 Likely scenario of BYPL (N) 3rd coaching terminal.............................................................. 58
vii
RITES
Table of Contents
viii
RITES
Table of Contents
Figures
Figure: 2.1BBMP, BDA and BMR Boundaries ........................................................................................... 5
Figure: 2.2 LPAs in BMR .......................................................................................................................... 5
Figure: 2.3 Preferred Scenario Map......................................................................................................... 8
Figure: 2.4 Land utilisation zoning ........................................................................................................... 9
Figure: 2.5 Transport Network .............................................................................................................. 10
Figure: 6.1 Binny Mill land towards Mysore end.................................................................................... 48
Figure: 6.2 Connecting MYS line to grid one .......................................................................................... 53
Figure: 6.3 Utilisation of Binny Mill Land for Commuter terminal .......................................................... 56
Figure: 6.4 Baiyyappanahalli (North) maintenance terminal .................................................................. 58
Figure: 6.5 Hejjala 4th coaching terminal ............................................................................................... 62
Figure: 6.6 Flyovers at BYPL area........................................................................................................... 66
Figure: 6.7 Connecting Dodballapur line with Chikballapur line ............................................................. 72
Figure: 6.8 EMU rake of MRVC .............................................................................................................. 83
Figure: 8.1 CRS Implementation Phases .............................................................................................. 108
Figure: 8.2 CRS Implementation Phases .............................................................................................. 111
Annexures
Annexure: 1 Lie-Over at SBC yard........................................................................................................ 148
Annexure: 2 Criss-Cross movements that can be made seamless by Flyovers ...................................... 152
Annexure: 3 Additional Halts suggested by voluntary organisations .................................................... 153
Annexure: 4 Trains presently serving Bangalore commuters and enhancing their capacities ................ 156
Annexure: 5 Cost Estimates in a Nutshell ............................................................................................ 160
Annexure: 6 EMU Rakes requirement for New Services....................................................................... 161
Annexure: 7 Hourly Distribution of total scheduled trains running in CRS network at present .............. 163
Annexure: 8 Hourly distribution of commuter trains running at present .............................................. 164
Annexure: 9 Hourly distribution of assessed potential for introducing additional services after proposed
investments..................................................................................................................... 165
Annexure: 10 ROBs with TVUs more than 50000 ................................................................................. 167
ix
RITES
List of Abbreviations
List of Abbreviations
BBMP
BCRC
BDA
BEML
BIAL
BMR
BMR RSP
BMRDA
BMTC
CIDCO
CRS
DEMU
EMU
FOB
GoAP
GoI
GoK
GoM
GPS
HMDA
IB
ICF
IR
KRCL
LCs
LPA
MEMU
MMTS
MoR
MoU
MRVC
NICE
O&M
ROB
RUB
SPV
SWR
TVUs
WSA
RITES
Code
AEK
Station Name
S. No
Code
Anekal Road
32
KGI
AVT
Avatihalli H
33
KHLL
Ketohalli H
BAND
Banaswadi
34
KIAT
Kyatsandra
BAW
Chikbanavar
35
KJM
Krishnarajapuram
BFW
Byatrayanahalli
36
LOGH
Lottegollahalli H
BID
Bidadi
37
MAD
Maddur
BLRR
Belandur Road H
38
MDLL
Muddalinganahalli H
BNC
Bangalore Cantt
39
MLO
Malur
BNCE
Bangalore East
40
MWM
10
BNKH
Bhairanayakanahallli H
41
MYA
Mandya
11
BWT
Bangarapet Jn
42
MZV
Maralahalli
12
BYPL
Baiyyappanahalli Jn
43
NDV
Nidvanda
13
CBP
Chikballapur
44
NDY
Nandi
14
CPT
Channapatna
45
NMGA
Nelamangala
15
CRLM
Karmelaram
46
NYH
Nayandahalli
16
CSDR
Channasandra
47
NZH
Nidaghatta H
17
DBL
Dodbele
48
Oddarahalli
18
DBS
Dobbspet H
49
19
DBU
Dodballapur
50
ORH
RMG
M
RNN
20
DHL
Devenahalli
51
SBC
Bangalore City Jn
21
DJL
Dodjala H
52
SDVL
Soldevanahalli H
22
DKN
Devangonthi
53
SET
Settihalli
23
GHL
Gollahalli
54
24
25
26
27
28
29
30
31
GNB
HEB
HHL
HJL
HLE
HNK
HSRA
KDGH
Jnana Bharthi H
Hebbal
Hirehalli
Hejjala
Heelalige
Hanakere
Hosur
Kodigehalli H
55
56
57
58
59
60
61
SGT
TCL
TK
TLS
VTE
WFD
YNK
YPR
xi
Station Name
Kengeri
Malleswaram
Ramanagaram
Rajankunti
Tyakal
Tumkur
Betthalsoor H
Venkatagiri Kote H
Whitefield
Yelahanka Jn
Yesvantpur Jn
RITES
1
1.1
Prologue
Back Drop
Bangalore, the capital of south Indian state Karnataka is Indias fifth largest and
a rapidly growing metropolis. It is known world over as Indias Garden City and
Silicon Valley. What started as a pensioners paradise in post independent
India transformed itself into a metropolis with presence of large public sector
companies and educational institutions. Emergence of IT sector however,
overshadowed other areas and metamorphosed the city into a global IT hub. It
continues to attract Indias best and brightest human capital given its
undisputed status as the knowledge capital of India. In the last decade or so, a
genial small city, dotted with breathtakingly beautiful gardens and dominated by
large defence establishments and government funded labs transformed quickly
in to a teeming metropolis which struggled to cope with its explosive growth. Its
inadequate road infrastructure, exponential growth of personal vehicles due to
raise in income levels all have combined to make local commute a nightmare.
Bangalore Metropolitan Region is spread over 3 districts namely Bangalore,
Bangalore Rural and Ramanagara. Population of this region is:
Table: 1.1 Population of Bangalore Metropolitan Region
No
District
Area
(Sq.
Km)
2001
2011?
Population
Decadal Growth
Density (per SqKm)
Rate (%)
(91-01) (01-11)
2001
2011
Bangalore
2174
6537124
9588910
35.09
46.68
2985
4378
Bangalore Rural
2295
850968
987257
18.60
16.02
380
441
Ramanagara
3556
1030546
1082739
7.84
5.06
288
303
Total 8025
8418638
11658906
38.49
Source: http://www.censusindia.gov.in/2011-prov-results/prov_data_products_karnatka.html
@
Projected Population by 2031 : 180 Lakhs
RITES
about 4.5 million trips by public transport. BMTC daily ridership is about 4.5
million1. Ridership of metro is presently about 25000 and ridership of Railways
is about 150000. Thus, public transport commuting needs of Bangalore are met
virtually by BMTC alone as on today!
With the kind of traffic congestion in Bangalore city today, BMTC can hardly
increase its ridership any further (except on account of extensions to new
geographical areas). Metro and Monorail which are being considered seriously
by GOK are certainly going to provide some relief. But the relief is limited
because of their limited spread in the city. The growth of demand is so huge
that dependence on a particular mode of commuting will grossly under serve
the public.
Bangalore has not yet actively involved in tapping the huge potential of the
Railway system like in case of Mumbai. Mumbais modal share of its public
transport can be seen as under:
Table: 1.2 Modal Splits Comparison with Mumbai
Mumbai
Bangalore
Share
Share
46%
1.5%
Bus
34%
40.5%
Autos etc.
10%
12%
5%
36%
Walk, Cycle
5%
10%
100%
100%
Mode
Total
Bangalore (for that matter any growing urban agglomeration) should take
Mumbai as its role model and integrate the rail system into its commuter
system.
Towards this objective, many studies were conducted in the past as under:
RITES
Study
Year
2
3
4
5
Remarks
Recommended 24 Km of metro, 3 commuter rail
lines and 58 Km ring rail over 25 years period.
Suggested many improvements to roads &
railways.
Reiterated Southern Railway recommendations of
1983.
Recommended to strengthen existing rail corridors
in Bangalore City.
Recommended strengthening of existing Rail
Corridors of Bangalore.
1983
1988
1993
2002
2007
None of the above studies were comprehensive. The studies analysed the
system at macro level and did not lay stress on workable and implementation
aspects. There were no enough detailing to convince the IR. With the result, IR
did not agree the recommendations.
undergo any major revamp so far towards serving commuters despite many
studies since 1983.
1.2
Terms of Reference
Table: 1.4 Terms of Reference
No
1
Description
Review City and Transport Plans
Review of city master plans and future projections of growth
Review of city transport plans
Assessment of current Rail traffic and projections for the next 20 years
Review the demands for long and medium distance trains
Assess the current freight traffic and potential for future freight traffic
under different scenarios
Assess the future demand for each stream of traffic for the next 20 years
Assessment of Infrastructure requirements: Sectional and terminal
requirements
Assess the current capacity utilization over different sections
Review the current terminal availability and problems associated with the
terminal operations
Assess the future capacity needs for the terminals
RITES
No
4
1.3
Description
Suggest suitable measures to enhance the terminal capacity
Suburban Rail traffic: Assessment of potential and evaluation of options
Assess the demand for suburban commuter trains in consultation with
various state government bodies and SWR
Projection of demand for the next 20 years
Evaluation of the services provided by SWR for suburban system
compared to alternate options for the government of Karnataka.
Assess the feasibility of providing services and the infrastructure
developments required to provide the services.
Identification of optimal infrastructure utilization
Assess the section capacity needs over different time periods by deploying
Line Capacity Simulator jointly developed by IIT Bombay and RITES Ltd.
Identify possible combination of train running on different sections and
identify suitable criterion for evaluating them
Assess the optimal combination for running trains by deploying the line
capacity simulator developed by IIT Bombay.
Infrastructure investment requirements
Provide a phased plan for an estimate of broad costs for developing the
infrastructure
Institutional Management
The Management, Operations and Maintenance of the Commuter Rail
System
Identification of fare structure
As a number of base studies were completed earlier, present study has been
limited to analysis of the secondary data.
RITES
2
2.1
The Bangalore Metropolitan Region (BMR), the area of this study contains
within itself, different planning and development units such as the BBMP, BDA,
and many LPAs (Local Planning Areas).
No
Area in
Sq. Km.
426.24
63.06
402.30
735.00
1219.50
RITES
No
Area in
Sq. Km.
501.52
535.00
412.78
792.00
10
462.60
11
2455.00
Total
2.2
8005.00
RITES
2.3
In the introductory text, the BMR Revised Structure Plan (RSP), 2031 reviews
the other plans for the different planning and development units in the area and
concludes thus:
An analysis of the various plans operational in this region reflects not only
contrary development strategies but also certain inherent contradictions, and a
lack of coordination and acceptance of the overall policy framework laid out by
the BMR SP (Structure Plan) 2011. Rationalizing these contradictions emerged
as the main objective of the BMR RSP 2031.
After a detailed spatial analysis of the land capability, demographic capability,
transport
accessibility,
and
industrial
location,
the
following
alternate
RITES
locations of growth clusters in the BMR. It will be observed that in locating the
growth clusters, the focus is on roads rather than rail. It is only by coincidence
that in two cases (the Mysore and Chikballapur corridors) the growth clusters
fall on the rail axis, because they are close to the roads in the area. Also the
proposed transport network that is supposed to support the land use zoning
corroborates this focus on road based development proposed in the BMR RSP,
2031.
RITES
RITES
2.4
Finally the land use zoning, transport plan and the growth clusters converge to
the population projections and allocations detailed in the BMR RSP, 2031.
10
RITES
The RSP discusses three alternate scenarios for the population allocation in the
BMR, with respect to the proportion of the population in the core and the rest of
BMR. These three scenarios are for the 75:25; 70:30; and 60:40 proportions of
population in the core and rest of BMR. The RSP states that the second
alternative that is 70:30 share is the preferred population allocation. This
particular table showing the population projections and allocation to different
areas within the BMR is reproduced here.
Table: 2.2 Population projections and allocations
2.5
The Travel patterns of the city and the BMRDA region are analysed by various
bodies based on various reports and the latest is the one prepared by WSA
associates for the BMRDA. The share of various modes of transport is given in
the Table: 2.3.
11
RITES
Travel Mode
Share
Walk
34.0%
Bicycle
4.5%
Taxi
0.5%
Auto
4.6%
Maxi Cab
0.5%
Two Wheeler
Car/Van
Public Transport
30.0%
Total
100%
21.4%
4.5%
2.6
Keeping the growing importance of the city, various projects were taken up the
by different development agencies. Among this the important projects under
execution is phase 1 of Bangalore metro project. In addition, the following
projects are under different stages of sanction:
In addition, two master plans were prepared; one by RITES limited in 2011 and
the other by Wilbur Smith Associates (WSA) in 2011. The RTIES report covers
only the Bangalore Development Authority area and that of WSA covers the
entire Bangalore Metropolitan Region (BMR). Since the CRS is in BMR, we
review the WSA plans in greater detail.
2.7
12
RITES
Phase-I
66
1529
15880
17475
Phase-II
0
847
29543
30390
Phase-III
0
0
25368
25368
Total
66
2376
70791
73233
Table: 2.5 Total investment program for long term scheme (WSA recommendations)
Unit
Assumed
Unit Rate
(Rs. In
crores)
Quantity
Amount
(Rs. In
crores)
Metro
Km
250
95.7
23930
Mono Rail
BRT /High Density Dedicated
Bus
Bus Corridor
Km
150
213.1
31964
Km
15
393.315
5900
Km
0.1
324.4
32.44
Road Up gradation
Km/lane
1.5
341.25
1507.35
New Roads
Km/lane
1.5
515.8
4642
Missing Links
Km/lane
1.5
529.1
1587
Transfer Stations
No.
25
17
425
No.
45
15
675
Truck Terminals
No.
10
80
Bus Terminals
No.
12
48
Item
Total
70791
Phase 1
(2010 2015)
Phase 2
(2016 2021)
Phase 3
(2022 2031)
Total
Rs. In Crores
2.8
Total
17475
30390
25368
73233
24%
41%
35%
100%
commuter rail system at all. It focused only on other modes of transport. But
13
RITES
due to inherent advantages and large potential that has, rail system just cannot
be ignored by any urban/suburban transport system. Potential of rail system is
discussed in greater detail in subsequent chapters.
Corridor
Kengeri Ramanagaram
Baiyyappanahalli Hosur
Yeshvantpur Tumkur
Yelahanka Dodballapur
1
2
3
4
Estimated Cost
(in Rs. Crores)
480
615
960
360
2415
Length Km
Total
32.0
41.0
64.0
24.0
161.0
Present study relooked the whole gambit of Rail Service in detail i.e. not only
doubling costs, but also terminal facilities, rolling stock procurement,
maintenance and provision of additional halts etc.
2.9
Costs being incurred (or planning to incur) on other modes to replicate the
services that otherwise can be provided by Railways is assumed as
under:
55
23
23
1680
2070
1380
50
76
98
600
684
588
HSRL
11
26
1400
1650
2600
Total
100
159
202.00
9480
11754
10068
Metro Rail
Less
than 1
Km
29
1 to
2
Kms
49
Mono Rail
14
BRT
S.No
2 to 3
Kms
14
RITES
250
Mono Rail
150
BRT
15
HSRL
250
From the above, it can be seen that about Rs.10,000 crores is being spent (or
planning to spend) to replicate service which can be easily provided by rail
network.
15
RITES
3
3.1
Fundamental Questions
3.2
th
quadrupling, 5 line, 6th line etc. In fact, capacity enhancement of any system
needs to be a continuous process. As technology changes and as the thinking
process changes, more and more innovative solutions come up for increasing
the capacity and meeting the growing demand.
Indian Railways is a highly complex entity constituting various disciplines,
various departments and various technologies.
16
RITES
every day. It is an excellent rail operator and probably one of the worlds best
systems to run such a massive network without any hitch.
Disaster
management and crisis management systems of the Indian Railways are the
best India can ever think of. Very big bridges washed out during floods are
constructed in just a few hours or at the most a few days and such disasters are
hardly felt by the travelling public.
IR has been enhancing capacity continuously with its limited resources. But
such enhancement is very marginal and cannot match the ever growing
demand. If the inability of IR to enhance capacity is supplemented by other
means, IRs strengths can be well leveraged to cater to ever growing demand to
a very large extent at much lesser costs.
3.3
17
RITES
Average Speed
(Kmph)
Maximum Peak
Throughput
(passengers/Hr)
Average Cost per Km
(Rs Crores)
Investment in Lakhs
of Rupees/Passenger
Km / Hr / Direction
Rail
(Double Line)
Metro
(Double Line)
BRT
(Bi-Directional)
40 to 70
36 to 40@
25 to 55
25 to 50
60000
40000
20000
15
250
14
0.03
0.61
0.07
Source : Draft final report Jun 2010 of M/s Wilbur Smith Associates on Comprehensive Traffic and
Transportation Study for Bangalore Metropolitan Region for BMRDA
@Indian Railways Year Book 10-11
It is assumed that surface rail will use existing right of way. Metro will use elevated right of way. BRT would
require a right of way of about 3 to 3.5 metre per lane.
The above table gives the case where the CRS system runs only sub-urban
trains. However, a normal CRS system has to allocate paths between different
types of trains. In this scenario, it is presented in subsequent paragraphs how
CRS capacity would compare with a metro in capacity and cost dimensions.
Metro is chosen for comparison as it has the second highest capacity and it is a
rail based system.
The present commuter rail system of Bangalore runs at average speed more or
less at its potential. But the present throughput is far below its potential ( about
2000 per hour Taking 1 train of about 10 coaches per hour and 200 passengers per coach) and can
be exploited fully to its potential to serve the public. Capacity is high mainly
because of the train length. Train length can go virtually up to 28 coaches
which is just not possible with Metro or any other mode.
18
RITES
19
RITES
WSA (Draft final report Jun 2010 of M/s Wilbur Smith Associates on Comprehensive Traffic and
Transportation Study for Bangalore Metropolitan Region for BMRDA) provides plans for
25 x 440 x 15 x 200
x 2 = 2.2 Millions / day
30
Costs are as per block cost estimates given in Cost Estimates and
Phasing of Investments chapter.
25 commuter trains per direction in the entire CRS network of about 440
Km.
The 2.2 million passengers capacity is about half of the present day public
transport commuter demand of 4.5 million trips per day.
20
RITES
In fact, the 25 trains per direction taken in above calculation can be increased
substantially with marginal additional investment. Train lengths also need not
be 15 cars. It can be even more in future.
Metro Rail costs about 12000 Cr for 42.3 Km to serve about 1 million
passengers per day (as per phase-I of Namma Metro).
Investment per
3.5
21
RITES
Source
BMTC
10.8
Metro
6 to 7
IR
(Suburban network)
33.8
IR is able to disperse the commuter traffic much effectively as its average trip
length of suburban travel is 33.8 Km which is much higher than trip lengths
possible by any other mode. With increase in trip lengths only suburban areas
like Hosur etc. can be integrated with city core.
22
RITES
From the above, it can be seen that IR has got potential to bring up the average
trip length of Bangalore public transport system from the present 10.8 Km to as
high as 33.8 Km. Such dispersion by Metro or Monorail or BMTC are nearly
impossible because it is prohibitively expensive to extend Metro or Monorail to
cover more locations.
3.6
No
complicated modelling studies are required to fully exploit this network. The
existing network can be studied for its bottlenecks and can be enhanced
continuously to meet ever growing passenger demands. It is also easier to
extend the backbone further to new geographical areas in all directions and also
in the form of ring rail or so
3.7
From the above, it can be appreciated that IR has very huge potential:
With such a huge potential and advantages associated with it, no commuter
system can be claimed to be complete or satisfactory without the appropriate
mix of commuter rail.
It is only the Mumbai (Chennai and Kolkata also to some extent) that have
tapped the potential to their maximum practicable levels and benefited
immensely. They have been still tapping the potential further. Hyderabad also
is now joining the league of coveted commuter rail systems of India with its
MMTS.
potential and integrate the rail system with the citys commuter system to satisfy
the public needs.
23
RITES
4
4.1
The Reality
No single mode of commuting (say it rail or road or metro or mono rail or so)
can fully satisfy the commuting needs of any city. Bus, rail, metro, mono rail
etc. have got different applications associated with them. They are meant for
different sections of commuters and for different trip lengths. An optimal mix of
different modes of public transport is normally the strategy for any urban
transport planning.
4.2
As already discussed in Para 3.5, due to more trip lengths associated with it,
CRS can be designed to reach both city core and suburbs seamlessly. The city
has a network of about 440 Kms (brought out in next paragraph) serving the city
in 7 directions.
4.3
From the trend of commuter ticket sales at various stations in and around
Bangalore, and from interaction with various officials of South Western Railway
and Government of Karnataka, IR network that can serve Bangalore commuters
is identified as under:
24
RITES
From
To
Distance (Km)
Bangalore
Bangalore
Yesvantpur
Yesvantpur
Yelahanka
Mandya
Yesvantpur
Tumkur
Yelahanka
Baiyyappanahalli
92.88
5.35
64.00
12.45
19.23
Yesvantpur
Yelahanka
Yelahanka
Baiyyappanahalli
Bangalore
Soldevanhalli
Baiyyappanahalli
Dodballapur
Chikballapur
Hosur
Bangarapet
Kunigal
Total
16.12
20.72
46.05
48.59
70.21
45.2@
440.8
4.4
S.No
1
2
3
4
5
6
7
8
9
10
11
From
SBC
SBC
YPR
YPR
YNK
YPR
YNK
YNK
BYPL
SBC
SVDL
Draft final report Jun 2010 of M/s Wilbur Smith Associates on Comprehensive Traffic and Transportation Study for
Bangalore Metropolitan Region for BMRDA
25
RITES
S.No
1
2
3
4
5
6
7
8
9
10
11
From
SBC
SBC
YPR
YPR
YNK
YPR
YNK
YNK
BYPL
SBC
SVDL
To
Km
MYA
YPR
TK
YNK
BYPL
BYPL
DBU
CBP
HSRA
BWT
Kunigal
Total
BRT
Mono
Rail
92.88 36.63
5.35
64.00
12.45 3.64
19.23 6.00
16.12
14.00
20.72 20.31
46.05 9.90
48.59
9.41
70.21
45.2
440.80
S.No
1
2
3
4
5
6
7
8
9
10
11
From
SBC
SBC
YPR
YPR
YNK
YPR
YNK
YNK
BYPL
SBC
SVDL
To
Km
MYA
YPR
TK
YNK
BYPL
BYPL
DBU
CBP
HSRA
BWT
Kunigal
Total
92.88
5.35
64.00
12.45
19.23
16.12
20.72
46.05
48.59
70.21
45.2
440.8
BRT
Mono
Rail
36.63
12.00
3.64
11.42
14.00
20.31
14.00
9.41
5.00
Mode
1 Metro Rail
2 BRT
3 Mono Rail
Length in Kms
114.35
393.3
213.20
Within 1 Km
29.08
Within 2 Km
48.68
25%
49.85
13%
48%
103.00
19%
23.41
7%
26
55.18
43%
76.48
14.07
Within 5 Km
26%
23.41
11%
11%
RITES
Mode
Length in Kms
4 Bus Corridor
324.40
35.00
1080.25
Within 1 Km
0.00
Within 2 Km
0
0.00
0%
7.30
0%
10.61
21%
100.30
Within 5 Km
0%
26.30
30%
159.18
9%
75%
207.89
15%
19%
From the above, it can be seen that about 25% of commuter rail network is
along the identified commuter corridors of different modes. This clearly gives
an indication that the existing rail network is well in tune with the citys
commuting needs and commuting plans.
4.5
Reverse Engineering
consultant studied the demand pattern of the city commuters and suggested to
develop:
Table: 4.6 Consultant suggestions for Hyderabad MMTS
Priority
Timeframe
Sections
2006-2009
II
2009-2011
Secunderabad-Shamshabad, Lingampalli-Pattancheruvu
III
2011-2016
Lingampalli-Nampalli-Koti-Upppal
But, even much before the receipt of consultants report (Feb 04), major part of
priority-III (Lingampalli - Nampalli) section was commissioned (Aug 03). The
reason behind giving priority III for this section by the consultant was clearly
reflected in the poor patronage of the section initially. However, the patronage
has shot up tremendously in this section and the real estate business in these
27
RITES
sections also shot up and resulted in many new housing projects in this section.
The priority II and III projects were subsequently sanctioned in MMTS phase-II.
Therefore, developing Bangalore commuter rail network of 440.8 Km is going to
serve the commuting public both by conventional engineering as well as by
reverse engineering.
Historically, dispersion of urbanisation by Reverse Engineering is possible
only with rail network but not with any other mode (like metro, mono rail, road
network or so).
4.6
Capacity of terminals
28
RITES
To
From
Estimated
Originating
Commuters per
Day
SBC
SBC
31500
21%
0%
1%
1%
30%
0%
33%
32%
1%
1%
1%
YPR sector
12000
8%
6%
1%
0%
2%
1%
75%
6%
3%
4%
2%
BYPL sector
12000
8%
9%
0%
3%
76%
0%
0%
4%
6%
0%
1%
BWT sector
34500
23%
24%
0%
10%
64%
0%
0%
1%
0%
0%
0%
HEB sector
1500
1%
11%
0%
0%
0%
0%
0%
0%
60%
29%
0%
TK sector
24000
16%
64%
13%
1%
1%
0%
21%
1%
0%
0%
0%
MYA sector
25500
17%
39%
2%
2%
2%
0%
2%
54%
0%
0%
0%
HSRA sector
4500
3%
26%
25%
14%
0%
15%
0%
0%
19%
0%
1%
DBU sector
3000
2%
35%
34%
0%
1%
11%
1%
3%
0%
15%
0%
CBP sector
1500
1%
44%
33%
17%
0%
0%
0%
0%
0%
0%
0%
Source: Actual Tickets sales data that could be collected has been modelled into this matrix.
From the above, it can be seen that demand pattern is not supporting the
proposition of locating commuter terminals short of Bangalore.
From
It can be seen from the above that the traffic has two distinct patterns.
First is the traffic within the sector. This traffic is expected to be high as
people would be moving to nearby places more frequently. This traffic,
however, would not be influenced by the location of terminals as they
terminate their journeys short of the terminals.
29
RITES
Another is the cross sector traffic. This traffic moves across the sectors
and thus terminating traffic at suburban terminals will force a major
transhipment. It can be observed from the above table that major portion
of commuters move towards Bangalore terminal indicating predominant
preference for it.
Suburban terminals like YPR, YNK, KGI and BYPL etc. cannot handle
this break in service even with huge investments.
Such capacity
30
RITES
Terminating trains would reduce the system capacity as trains are run for
shorter distances.
An
additional line (or two) at every station (or at every alternate station or so)
shall be handy to terminate the EMUs.
4.7
Modal Transits
Commuters changing from one mode to another mode during the course of their
trip is a big challenge in urban transport planning. All stations on CRS network
act as modal transit locations because commuters normally come to station by
DULT Government of Karnataka
31
RITES
4.8
Conclusions
Conventional rail system has grown to its present stage over a very very long
period and is a part and parcel of common mans life whether for long distance
travel or commuting. Unintentionally, it has become itself integrated into the
commuting system of the city. It can itself become a mass rapid transport
system and also it can act as feeder system to other modes of transport.
Therefore, exploiting its full potential gets automatically (and so naturally)
integrated into the transport needs of the city. Such exploiting should be a
continuous process (like in the case of MRVC) rather than discrete.
32
RITES
5
5.1
Freight Traffic.
Demand for traffic for each of these streams is different and projected
separately. As the CRS capacity created has to be shared between 3 streams,
the demand assessment will help in optimally configuring the share of different
types of traffic.
5.2
However due to the unique layout of the rail network within the central city area,
and the many hubs and the resultant routes between the hubs and
destinations in the metropolitan region, the CRS rail network of 440.8 Km
belonging to the above seven corridors were identified for the study.
Accordingly, the macro estimates in brief:
33
RITES
Total projected public transport trips in BMR, 2031 (@43% of total trips 3):
9.91 million
Average no. of Commuter Rail trips per corridor (divided uniformly over
the 7 corridors) by 2031: 0.45 million (approx.).
Potential gap in current (2011) supply and future (2031) demand for daily
trips by commuter rail: 2.82 million (approx.).
1 Km, 2 Km and 5 Km on both sides of the rail lines have been taken as
the catchment areas of the commuter rail sections for which the
populations are estimated.
Outside BBMP, 3
This
Wilbur Smiths Draft Final Report, Comprehensive Traffic and Transportation Study for the BMR)
34
RITES
were identified into districts they came under and the population density
of the districts as per census 2011 is taken:
Wilbur Smiths Draft Final Report, Comprehensive Traffic and Transportation Study for the BMR)
BBMP
Bangalore District
Bangalore Rural District
Ramanagara District
Mandya District
Tumkur District
Kolar District
Chikballapur District
10592.5
4378
441
303
365
253
384
298
Source: http://www.censusindia.gov.in/2011-provresults/prov_data_products_karnatka.html
BMR
29.14%
26.77%
BBMP
25.29%
25.29%
Ramanagara
Mandya
12.3
11
SBC
YPR
5.35
YPR
TK
7.9
YPR
YNK
12.45
12.45
YNK
BYPL
19.23
19.23
YPR
BYPL
16.12
16.12
YNK
DBU
3.8
Total
Distance
(Kms)
MYA
To
Kolar
SBC
From
Tumkur
Bangalore
23.58
BBMP
46
No
Bangalore
Rural
92.88
5.35
13
10.92
35
31.1
12
64
20.72
RITES
13.8
30.05
BYPL
HSRA
13.4
35.19
10
SBC
BYPL
10.76
11
BYPL
BWT
10.9
12
SDVL
Kunigal
46.05
48.59
10.76
18
16
Total
Distance
(Kms)
2.2
Kolar
CBP
To
Tumkur
Bangalore
Rural
YNK
From
Mandya
Bangalore
No
Ramanagara
BBMP
30.55
7.2
16
92.35
62
6
23.58
18
59.45
45.2
30.55
440.8
Trips (Millions)
6.5
4.7
1.4
0.7
0.7
14.0
Share
46%
34%
10%
5%
5%
100%
Year
2011
PCTR
1.00
Source
WSA CTTP for BMR
2021
1.10
Assumed
2031
1.28
Modal shares are highly influenced by trip lengths. RITES (2011) data for
BDA area, given in Table below is used as a basis to assume appropriate
modal shares:
36
RITES
Bus
Car
Two
Wheeler
Three
Wheeler
Cycle
Walk
Total
02
0%
0%
20%
0%
8%
72%
100%
02-05
12%
3%
50%
29%
5%
0%
100%
05-10
11%
13%
60%
14%
2%
0%
100%
10-15
68%
7%
15%
9%
0%
0%
100%
15 20
68%
7%
15%
9%
0%
0%
100%
20 35
83%
4%
11%
1%
0%
0%
100%
> 35
85%
12%
0%
3%
0%
0%
100%
Total
Average
Trip
Length
42%
7%
29%
12%
2%
8%
100%
14.99
11.59
8.02
8.59
3.88
1.01
10.57
Source: RITES report, Comprehensive Traffic and Transportation Plan for Bengaluru 2011
Trip lengths that can attract CRS are normally beyond about 10 to 15
Kms. Thus, CRS mostly captures the traffic from Bus.
37
RITES
Catchment
Modal
Share of
CRS
Catchment
Modal
Share of
CRS
Catchment
Modal
Share of
CRS
10%
1 Km
10%
1 Km
10%
2 Km
20%
1 Km
10%
5 Km
30%
2021 1.10 1 Km
10%
1 Km
10%
1 Km
10%
2 Km
20%
1 Km
10%
5 Km
30%
2031 1.28 1 Km
10%
1 Km
10%
1 Km
10%
2 Km
20%
1 Km
10%
5 Km
30%
Per Capita
Trip Rate $
Modal
Share of
CRS
Other Area
Catchment
BBMP
Modal
Share of
CRS
Other Area
Catchment
BBMP
Modal
Share of
CRS
Other Area
High
2011 1.00 1 Km
Year
Catchment
BBMP
Medium
PCTR for 2011 and 2031 is adopted from Draft final report Jun 2010 of M/s Wilbur Smith Associates on Comprehensive
Traffic and Transportation Study for Bangalore Metropolitan Region for BMRDA. However, for 2021 it is assumed as 1.10.
After studying the Travel Pattern of existing commuter train services and
after detailed deliberations with S W Railway and GoK, 440.8 Km is
identified as potential CRS network. Demand is assessed in this network
as under:
Table: 5.8 Assessed Commuter Rail Trips (Scenario: Low)
No
1
2
3
4
5
6
7
8
9
10
11
12
From
SBC
SBC
YPR
YPR
YNK
YPR
YNK
YNK
BYPL
SBC
BYPL
SDVL
To
Distance in
Kms
MYA
YPR
TK
YNK
BYPL
BYPL
DBU
CBP
HSRA
BYPL
BWT
Kunigal
Total
92.88
5.35
64.00
12.45
19.23
16.12
20.72
46.05
48.59
10.76
59.45
45.2
440.8
38
Share
12%
3%
10%
2%
12%
10%
6%
6%
19%
7%
8%
5%
100%
RITES
No
1
2
3
4
5
6
7
8
9
10
11
12
From
SBC
SBC
YPR
YPR
YNK
YPR
YNK
YNK
BYPL
SBC
BYPL
SDVL
To
Distance in
Kms
MYA
YPR
TK
YNK
BYPL
BYPL
DBU
CBP
HSRA
BYPL
BWT
Kunigal
Total
92.88
5.35
64.00
12.45
19.23
16.12
20.72
46.05
48.59
10.76
59.45
45.2
440.8
Share
13%
2%
12%
1%
6%
5%
8%
11%
25%
3%
6%
8%
100%
From
SBC
SBC
YPR
YPR
YNK
YPR
YNK
YNK
BYPL
SBC
BYPL
SDVL
Distance in
Kms
MYA
92.88
YPR
5.35
TK
64.00
YNK
12.45
BYPL
19.23
BYPL
16.12
DBU
20.72
CBP
46.05
HSRA
48.59
BYPL
10.76
BWT
59.45
Kunigal
45.2
Total
440.8
To
2011
2021
2031
Share
117298
11334
120125
8050
40739
34150
53290
97865
280955
22795
67576
50486
904663
175851
15620
181636
11095
56146
47065
80481
149374
426493
31416
100051
77432
1352660
264700
22772
274242
16175
81853
68615
121462
226279
644835
45800
149924
117496
2034153
13%
1%
14%
1%
4%
3%
6%
11%
32%
2%
7%
6%
100%
From the above tables, it can be seen that most important sections from
commuters consideration are:
39
RITES
But all these sections are non-electrified sections and/or mostly single line
sections. For introducing CRS, these sections need to be made double line
electrified sections with automatic signalling.
5.3
S.No
1
2
3
4
5
7
8
9
10
11
Sector
MYA
YPR
TK
HEB
HEB
DBU
CBP
HSRA
BYPL
BWT
From
SBC
SBC
YPR
YPR
YNK
YNK
YNK
BYPL
SBC
BYPL
#
To
MYA
YPR
TK
YNK
BYPL
DBU
CBP
HSRA
BYPL
BWT
Distance (Km)
92.88
5.35
64
12.45
19.23
20.72
46.05
48.59
12
58
Total
Passengers
Capacity
(@ 150 per
coach in
No of @
Total
case of
Commuter Coaches
passenger
Services at being run
coach and
present at present
200 in case
of DEMU/
MEMU
coach)
10
114
17100
18
204
30600
14
164
24600
6
62
9300
2
16
3200
4
48
7200
4
30
5300
6
62
10100
24
242
40000
20
198
34600
108
1140
182000
No of
Passenger passeng
Km being er trips
Run
being
served #
1588248 46990
163710
4843
1574400 46580
115785
3426
61536
1821
149184
4414
244065
7221
490759 14519
480000 14201
2006800 59373
6874487 203388$
Assuming average trip length as 33.8 Km as taken from Indian Railways Year Book 10-11
$
This tallies with the ridership assessment of 150000 made from ticket sales analysis.
@
List of present commuter services is at Annexure - 4
From the above table, it can be seen that present supply is able to cater for
about 30% of commuter demand (medium scenario) of 2011.
5.4
The demand for non-suburban passenger trains is based on the long term
growth trends of non-suburban passenger traffic on IR. Historical trend of
passenger and passenger kilometre growth of non-suburban passengers is
given in the Table below.
40
RITES
1950-51 to 10-11
2.4
4.4
2000-01 to 2010 to 11
6.2
7.7
5.5
Business as usual
In the business as usual scenario, the freight is limited to bulk cargo like cement
and steel, and Exim container cargo. Then freight growth would be at historical
trend around 1-2 trains per annum.
In the aggressive market capture approach, in addition to the above forecast,
additional non bulk traffic is expected. In this scenario traffic will be much higher
but cannot be predicted easily. As per RITES national estimates, non-bulk
occupies around 25 % of the national traffic and there could be 6-7 rakes of
non-bulk cargo. If such a scenario emerges, then IR and GoK have to think of
ring rail system so that freight trains by pass the city core.
5.6
41
RITES
handled.
However, higher freight trains load (per day) on the system are
Similarly, for
enhancing the freight capacity also, necessary facilities are developed by Indian
Railways with their own funds depending on the requirement.
Measures suggested in various phases of this report are aimed at running trains
at about 10 minutes frequency. These phases are very much enough to take
care of the above cited quantum of increase in long distance trains and freight
trains apart from meeting the commuter requirement.
Therefore, long term growth of long distance passenger trains and freight trains
should not be a cause of concern while planning the commuter services.
5.7
Recent commuter systems in India are found to have been falling short of the
initial traffic projections as seen under.
Table: 5.13 Traffic Projections for various commuter system in India
System
DMRC
33.7 Lacs
(by 2009)
19 Lacs
(Maximum: 22 Lacs on 01/08/12)
(Over 187 Km network)
Hyderabad MMTS
3 Lacs
1.6 Lacs
BMRCL
Therefore, to have some idea of the reliability of traffic projections made for
CRS, these projections are compared with BMRCL projections as under:
BMRCL Traffic Projections
Length of metro network
:
:
42
RITES
0.141 Lacs/Km.
440.8 Km
:
:
=
220.4 Km
220.4 Km
(220.4 x 0.141) + (220.4 x
0.14110)
34 Lacs
But, as seen in Table 5.10, CRS demand in 2021 for high scenario is estimated
as 13.52 Lacs which is far less than 34 Lacs projected based on BMRCL
methodology.
Thus, it can be reasonably concluded that demand estimation is quite
conservative and poor patronage of fully developed CRS network will be a very
remote possibility provided feeder roads and last mile connectivity are properly
addressed. It can also be seen in subsequent chapters that in case demand is
going to be far higher than projections, such demand can be met by simply
procuring additional EMU rakes as necessary infrastructure (even for higher
than projected demand) is already covered in various phases recommended.
5.8
43
RITES
Table: 5.14 Assessment of additional services required to bridge demand supply gap
From
To
Assessed
No of
Commuter
Distance Commuter trips (2021)
(Km) Services at for Demand
present
High
Scenario
Commuter
Trips
generated
by existing
Services @
Commuter
Trips after
upgrading
present
services to
EMUs /
MEMUs $
Balance
requiremen
Additional
Additional
t to be met
Services
Services
by
$ rounded
Required
additional
off &
Services
1 SBC
MYA
92.88
10
175851
46992
82710
93141
9.415
10
2 SBC
YPR
5.35
18
15620
4846
7172
8448
14.826
16
3 YPR
TK
64
14
181636
46576
64756
116880
17.146
18
4 YPR
YNK
12.45
11095
3426
5304
5791
4.367
5 YNK
BYPL
19.23
56146
1820
4096
52050
25.413
26
6 YPR
BYPL
16.12
47065
1470
45595
27.412
28
7 YNK
DBU
20.72
80481
4412
4412
76069
34.469
34
8 YNK
CBP
46.05
149374
7222
19622
129752
26.454
26
48.59
426493
14520
14520
411973
79.320
80
9 BYPL HSRA
10 SBC
BYPL
12
24
31416
14112
21884
9532
7.458
11 BYPL
BWT
58.21
18
100051
59382
97922
2129
0.343
12 SDVL Kunigal
45.2
77432
77432
16.084
16
Total
440.8
106
1352660
203308
323868
1028792
262.707
266
Commuter Trips are worked out taking average trip length as 33.8 Km (Indian Railways Year Book 10-11)
Worked out based on MEMU rake length of 16 cars and EMU rake length of 15 cars taking EMU capacity as 240 and
MEMU capacity as 200.
&
Rounded off to nearest even digit because they have to form pairs of trains for Up & Dn direction
44
RITES
6
6.1
Backdrop
The existing rail network in Bangalore area got developed over a period of time.
The recent major rail projects for Bangalore area:
Table: 6.1 Major rail projects in Bangalore area in the past
Project
Year
1983
1992
1993
Each of the above projects substantially altered the rail network scenario of
Bangalore. But, the thrust in every project was to complete the project and give
some connection to Bangalore.
means or provision to study the rail network in Bangalore area in a holistic and
integrated view.
It is due to this
legacy, the system is not geared up for suburban operations. This leaves lot of
potential and opportunity to study and upgrade the system to serve larger public
needs specially commuting needs. In fact, the system needs complete overhaul
and redesign (but not incremental up gradations) to serve as good suburban rail
system apart from serving long distance passenger traffic and freight traffic.
6.2
45
RITES
with the system to improve capacity throughout the system. For the purpose of
the analysis, components of the rail system are considered as under:
6.3
Terminal Strategies
wants to have direct link to this station from his/her place. Therefore, maximum
number of trains should pass through this station for better service to the public.
Today, SBC position is such that it cannot handle even one additional train. It is
not in a position to effectively handle a major delay in arrival or departure of
even a single train.
maintenance after each trip. Stabling lines are meant for stabling trains during
their idle time or when they are waiting for their turn onto platform line or pit line.
DULT Government of Karnataka
46
RITES
Number of platforms.
Number of lines (platform lines, pit lines, stabling lines, shunting lines
etc.).
Length of each line. More the length of each line, higher is the capacity of
the yard.
Connectivity of platform lines with pit lines, stabling lines and shunting
lines etc. Ideally, all platform lines should have connection to all pit lines,
shunting lines and stabling lines etc.
Lie-Over i.e. time spent by each train in the yard (Lesser the lie-over,
more is the capacity).
Requirement of Engine Reversal for the train. More the trains which need
engine reversals, lesser is the capacity of the yard.
6.3.1.2 Platforms:
The 10 platforms present in SBC yard today are fully occupied and there is
hardly any slot on any platform for dealing additional trains. SBC is catering to
3 directions i.e. YPR, BYPL and MYS. If commuter trains are to be dealt from 3
directions, SBC should have at least 2 platforms exclusively for commuter
trains.
exclusively earmarked for commuter trains. In fact, hardly any additional train
can be dealt on any of the existing platforms.
Therefore, it is required to
47
RITES
SBC yard has got 4 pit lines sandwiched between platform lines. These 4 pit
lines can be conveniently converted into 2 platforms and they can be earmarked
for commuters. However, the pit lines need to be relocated to accommodate
platforms.
On MYS end of the yard, there is vacant land (Binny Mills Land) which can be
conveniently used for constructing exclusive commuter platforms and/or pit
lines. This is the first and foremost requirement for introducing CRS trains in
SBC.
Being in very prime location, Binny Mills Land may be difficult to get spared to
Railways.
that possible number of platforms and/or pit lines can be constructed here. And
to that extent, SBC can be provided with additional platforms for commuter
trains.
6.3.1.3 Lie-Overs and Engine Reversals
Presently SBC yard is dealing 92 coaching trains (some of them are daily and
some of them are non-daily).
shows:
48
RITES
Yes
No
30 Minutes
23
> 30 Mts 1 Hr
> 1 Hr 2 Hr
> 2 Hr 4 Hr
> 4 Hr 6 Hr
No
Yes
No
5
1
> 6 Hr 8 Hr
> 8 Hr 10 Hr
> 10 Hr 12 Hr
> 12 Hr 14 Hr
> 14 Hr 16 Hr
> 16 Hr 18 Hr
> 18 Hr 20 Hr
Total
26
33
22
Details at Annexure-1
Very few trains only leave the yard within the minimum lie-over required.
Majority of the trains are lying-over for more time than required (even
more than 18 Hrs. in case of one train).
It is highly difficult for the yard to handle such massive lie-over and engine
reversals. It is because of this reason, many empty rakes are being taken to
Baiyyappanahalli marshalling yard, Krishnarajapuram, Whitefield and Bangalore
Cantt just for stabling during their idle time. To stable these rakes and to bring
back these rakes to SBC, light engines are also being moved.
All these
unproductive movements are badly eating away the capacity of SBC as well as
49
RITES
Or terminal activities
PF-1
PF-2
PF-3
PF-4
Stabling Line
Stabling Line
Stabling Line
PF-5
PF-6
PF-7
PF-8
PF-9
PF-10
659
589
572
598
476
476
559
559
495
462
570
625
602
Present Utilisation
26 Coaches
24 Coaches
24 Coaches
24 Coaches
19 Coaches
19 Coaches
24 Coaches
24 Coaches
20 Coaches
19 Coaches
23 Coaches
26 Coaches
25 Coaches
63%
100%
46%
71%
Pit Lines
Shunting Neck
63%
71%
45%
71%
42%
63%
85%
92%
79%
60%
75%
75%
With ever growing demand for more capacity, numbers of coaches get
increased for more and more trains. Freight trains are normally full length trains
(means 686 metres). Longer passenger trains and freight trains can be dealt
50
RITES
only on very few lines in SBC yard as can be seen above. Inadequate length of
lines coupled with absence of universal reception and despatch facilities for all
the lines forces number of unproductive (shunt) movements in the yard and thus
adversely affects the capacity of the SBC yard.
Thus, SBC needs to offload some of its terminal activities and also needs to
increase in length of lines.
6.3.1.5 Interconnectivity of Lines
SBC yard has 10 platforms presently as under:
Table: 6.4 Interconnectivity of running lines at SBC
PF
1
2
3
4
5
6
7
8
9
10
Trains Arriving from
this direction
Entry/Exit towards
BYPL
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
49
20
23
From the above, it can be seen that majority of the trains enter into SBC yard
from BYPL side. They can come only onto PFs 1 to 7. Out of these platforms,
4 platforms have no exit to other directions.
platforms cannot go anywhere. Presently, trains received from BYPL are being
disposed by:
51
RITES
All the above disposal schemes except the last one consume lot of time.
Engine also needs to be reversed. A few shunt movements (movements from
one line to another within the yard) are also required. These shunt movements
have to wait in between to give way for trains entering and leaving the yard
from/to different directions. In shunt movements alone, each train may need to
spend a couple of hours bringing down the capacity of the yard drastically.
For the trains entering SBC from MYS or YPR, the situation is not this much
critical. Trains from MYS can go either towards BYPL or YPR as seen from
above table. Trains from YPR also can go towards MYS. However, if they are
terminated at SBC, they are to be taken onto stabling lines or pit lines. Such
terminal activities need lot of shunt movements and take away substantial
capacity of SBC.
Due to above cited constraints coupled with heavy lie-over and inadequate line
lengths, SBC is not able to use the platforms and pit lines to the full extent as
seen in above tables.
It is for this reason, any new train announced by Ministry of Railways shall
either run short of Bangalore (like YPR, BYPL or so) or it is accommodated by
making some other existing train to terminate short of Bangalore. Trains which
are ideally required to come to SBC but are presently terminated short of SBC
are:
Table: 6.5 Trains being terminated short of SBC
Train No
From
To
66533
66534
76506
76507
76508
76505
BWT
KJM
KQZ
BNC
BWT
BNC
KJM
BWT
BNC
BWT
BNC
KQZ
52
Terminated
Station
Time
KJM
19:10:00
KJM
19:30:00
BNC
09:40:00
BNC
11:00:00
BNC
17:20:00
BNC
17:55:00
RITES
These trains are during peak commuter timings and they can serve commuters
better if these trains can be brought up to SBC.
There should also be seamless movement of trains from YPR/BYPL side to
MYS side for enhanced capacity of SBC.
Trains coming from MYS side and getting terminated here should be able
to go to pit lines or to BYPL side easily.
Terminating trains should be taken onto stabling lines or pit lines without
reversing the engine and without any shunt movements. This way, the
terminating train shall leave the yard within about 10 minutes.
To achieve these objectives, all the lines of SBC should have entry/exit to MYS
side. However, this connection needs some Binny Mills land. Image showing
typical arrangement of connection to MYS side is shown in figure 5.2 above.
6.3.1.6 Yard Speeds
Normally, trains move with 15 Kmph in yards. But with latest improvements in
turnouts and signalling technology, speed in yard can be enhanced to 30 Kmph
while redesigning the yard.
In the above lines, SBC yard should be redesigned such that:
53
RITES
All lines have universal R&D facilities from all directions (BYPL, YPR and
MYS directions).
All lines shall be of full length (i.e. full length freight train or coaching
train).
Other lines like shunting necks, pit lines (if provided) etc. also should be
of full length.
To make all these options feasible, a very meticulous and innovative detailing is
required while redesigning the SBC yard.
If the yard is redesigned like this, SBC yard shall have:
Speed of 30 Kmph.
Capacity :
Table: 6.6 Scenario of SBC yard after suggested remodelling
Likely to be
(if above cited measures are
implemented)
10
14 or 15
(different lengths and
(More or less full length
without universal R&D)
and universal R&D)
Present
Platforms
Capacity
60 pairs of trains per day 150 pairs of trains per day
(commuters, long distance and freight)
54
RITES
Some terminating trains are waiting in stabling lines for their turn onto pit lines.
This necessitates shunt movements and eats away some yard capacity.
Therefore, additional pit lines are required at YPR for increasing the yard
capacity. Work is presently in progress for providing 1 additional pit line. If 3
more pit lines are constructed, terminal capacity of YPR increases to about 60
pairs from the present 37 pairs of trains.
converting some of the existing stabling lines into pit lines. Normally, 2 stabling
lines go away for 1 pit line. Therefore, S W Rly should critically analyse the
operational implications of retaining stabling lines as it is and/or replacing a few
of them into pit lines and plan for optimum number of additional pit lines.
Possibility of acquiring military land for Railway operations at YPR also need to
be explored so that additional pit lines can be constructed without any difficulty.
The locations should be such that long distance and commuter trains do
not conflict their interests each other but supplement each other.
More the terminals, the better it is. More terminals facilitate more dispersion of
congestion and also reduces load on any particular terminal.
Thus, more
capacity to run commuter trains. As per the preliminary studies and as per
55
RITES
In fact, this is not a new terminal; But an extension of SBC terminal. As already
discussed in above paragraphs, this area can be provided with a few platforms
and/or pit lines so that these additional platforms can be earmarked exclusively
for commuter trains.
platforms etc. in Binny Mill Land. This arrangement can accommodate about 12
lines (pit lines or platform lines or any other line). Feeder roads also can be
developed easily for this terminal as this area is well connected by road
network. This is also nearer to the metro station coming up nearby. Therefore,
this proposition is very ideal and most of the problems of SBC can be solved in
one go with this terminal. This arrangement needs full Binny Mill Land. This
56
RITES
land shall make an excellent suburban terminal at SBC to deal commuter trains
from all directions.
Binny Mill land is in very prime location and has lot of commercial value. In
case it is not practicable to give this whole land to Railways, part of the land can
also be spared to Railways so that just a few facilities can be constructed
instead of full-fledged coaching facilities.
deliberated with open mind along with all stake holders. Depending on the
extent of land that can be spared, facilities can be planned here. Issue of Binny
Mill land is discussed in detail in Para 7.4.
A few commuter trains also can pass through this station and stop at this
station.
57
RITES
This terminal eases off the SBC yard to a very great extent and SBC can
be improved to handle more commuter trains by providing more platforms
and lengthier platforms with almost universal R&D facilities.
This is very nearer to BYPL metro station. Long distance passengers can
easily go to metro station from this BYPLN new terminal. A skywalk can
also be planned in future to facilitate transhipment.
70 Pairs
Present
Platforms
Capacity
(commuter and long
distance)
58
RITES
With
59
RITES
Hejjala:
coaching terminal.
BAND: Some Railway land is available on either side of BAND yard. This
can be developed into EMU shed. However, acquisition of a small patch
of land (about an acre or so) may be required. Another feature worth
noting is that there exists a road in Railway land (Lingarajapuram area i.e.
other than station building side). Implications of closing this road may
need to be reviewed.
CSDR: Channasandra yard also has got enough Railway land on main
road side to accommodate EMU shed.
When the issue is discussed with Divisional Officers, it was felt that EMU
shed at BAND is operationally more convenient compared to CSDR or
Km 8-9.
60
RITES
extended shall also serve as commuter trains from SBC up to that terminal.
However, this arrangement has some logistic problems for S W Railway.
Arranging crew for operating these trains at isolated locations may pose
additional burden on S W Railway.
61
RITES
This land is very strategically located near the track and can be best used
for enhancing the capacity of overall rail system of Bangalore.
This can be fully developed into coaching terminal and some trains can
be terminated here.
On date, public demands for starting more than 30 new trains from
Bangalore remain unmet due to capacity constraints at SBC. Majority of
those requests can be conceded with Hejjala terminal.
The land available can facilitate a small terminal. If some more land can
be acquired adjacent to the available land, this terminal also can be
developed for a capacity like SBC or BYPL (North) or YPR.
Alternatively GoK and SWR can form a team to identify any other location
where land can be acquired for 4th coaching terminal in Mysore section.
th
It is highly recommended to develop all the four terminals (Binny Mill, BYPLN,
BAND and Hejjala) as discussed above.
62
RITES
trains from all direction to SGT badly occupies the sections and net capacity for
commuter trains shall come down.
terminal in the north will be required first in DBU area. Then some more freight
terminals in south and west can be planned depending on growth in freight
traffic. The new freight terminals should be developed as multimodal logistic
hubs providing one stop logistic solutions to customers. On date, Bangalore
City does not have such terminals.
However, additional freight terminals are not warranted immediately to introduce
CRS trains as brought out in Demand Supply Assessment chapter.
6.4
Sectional Strategies
This phenomenon
causes hurdle to commuter trains as well as long distance trains. Any small
hitch anywhere hits series of trains.
63
RITES
Even with this arrangement also, handling peak time rush is posing
64
RITES
Bangarapet
Bangalore
Bangarapet
Bangalore
Yelahanka
Main Line
Main Line
Yelahanka
Direct
Movement
Hosur
No Connection
Hebbal
Direct
Connection
Infringes
BangaloreBangarapet
trains. Flyover
required (via
Channasandra)
Direct
Movement
Direct
Connection
Hosur
Hebbal
Infringes
BangaloreBangarapet
trains.
Flyover
required
No Connection
Infringes
BangaloreBangarapet
trains.
Flyover
required
Direct
Connection.
Infringes
BangarapetBangalore
trains.
Flyover
required
Direct
Connection
No
Connection.
No Connection
No Connection
Direct
Connection
Already Fly
over exists
From the above it can be seen that to avoid criss-cross movements and for
seamless movement of trains in this area, 4 flyovers are required.
These
goes waste to a large extent in this criss-cross movement area unless these
flyovers are constructed. This is to say that full advantage of the doublings and
automatic signalling cannot be realised without these flyovers.
65
RITES
66
Typical
RITES
Yesvantpur
Tumkur
Yelahanka
Hebbal
Direct
Connection
Direct
Connection
Direct
Connection.
Direct
Connection
Infringes YPRHEB line
No Connection
exists
Yesvantpur
Tumkur
Yelahanka
Hebbal
Direct
Connection
Direct
Connection
Direct
Connection
Infringes TK-YPR
line
Infringes YPRYNK line and TKYPR line
No connection
exists
When such a
Yesvantpur
Tumkur
Yelahanka
Hebbal
Direct
Connection
Direct
Connection
Direct
Connection.
Direct
Connection
Direct
Connection
No Connection
exists
Yesvantpur
Tumkur
Yelahanka
Hebbal
Direct
Connection
Direct
Connection
Direct
Connection
Infringes TK-YPR
line
Infringes TK-YPR
line
67
No connection
exists
RITES
developed in DBU side or TK side or MYS side or so. Similarly, when the entire
area is changed to electrified territory and diesel traction is totally done away
with, the diesel shed needs re-design and/or probably relocation. Therefore,
proposals like flyovers etc. in K R Puram Whitefield should be planned in the
changed scenario and therefore not contemplated in the present study.
68
RITES
Signals spacing
along the track
Train can start
Operation of
Signal
Automatic Signalling
2 Km or even less
After previous train passes the
signal ahead
Gets automatically operated as
soon as train passes the signal
From the above, it can be seen that how automatic block signalling boosts up
the capacity of rail system. Mumbai, Chennai and Hyderabad are able to run
local trains because they have automatic signalling. Thus, automatic signalling
is a must to introduce commuter rail system in Bangalore.
As already discussed above, in Bangalore Whitefield area is full of criss-cross
movements. Added to this, there is rush of unidirectional traffic in morning and
evening peak hours. Therefore, trains in this section may crawl specially when
more trains are introduced. Capacity of this section needs to be increased on
top most priority by automatic signalling or IB signals or Twin Single Line
system as already discussed.
Subsequently, the automatic signalling should be extended to all other sections
also as under:
1. Bangalore Whitefield
2. Whitefield Bangarapet
3. Bangalore-Mysore (along with full doubling and electrification)
4. Yeshvantpur Tumkur (along with electrification)
5. Baiyyappanahalli Yelahanka Dodballapur (along with doubling)
6. Banaswadi Hosur (along with doubling and electrification)
7. Soldevanahalli Kunigal (line under construction)
69
RITES
Twin single line systems or IBs can be introduced in select block sections
(like SBC-BNC etc.).
To decide on exact strategies for each section or sub section, detailed field
surveys and studies are to be undertaken. When the projects are sanctioned by
IR, normally IR studies all these aspects before deciding the signalling
arrangements.
70
Without full
RITES
locomotives
and
electric
locomotives
need
Maintenance of
different
facilities.
Electrification
Sanctioned
(in order of priority for
execution)
1. Kengeri Mysore
(126 Km)
2. Yeshvantpur
Yelahanka (13 Km)
3. Yelahanka
Channasandra (14 Km)
4. Yelahanka
Dodballapur (22 Km)
5. Yeshvantpur Chikbanavar (8 Km)
To be sanctioned
(in order of priority)
1. Yelahanka
Dodballapur (22 Km)
2. Yeshvantpur
Baiyyappanahalli (18
Km)
3. Banaswadi Hosur
(54 Km)
4. Yelahanka
Chikballapur (47 Km)
5. Soldevanhalli
Kunigal (45.2 Km)
To be sanctioned
(in order of priority)
1. Bangalore Yeshvantpur - Tumkur
(70 Km).
2. Soldevanhalli
Kunigal (45.2 Km)
3. Yeshvantpur Banaswadi Hosur
(along with doubling)
(67 Km)
4. Yelahanka
Chikballapur (along
with doubling) (47
Km)
The sanctioned projects should be executed as per the priority and new projects
also need be taken up for introducing commuter trains in Bangalore.
71
RITES
Therefore, to
minimize
the
the
effect
of
goods trains on
CRS
routes,
following
Presently goods trains which are to go from DBU side to HSRA side are
being taken to YPR, engine getting reversed and taken to HEB and then
to HSRA.
reversals and also YPR gets relieved. This creates additional capacity at
YPR. Such connection from YNK to HEB may need to pass through
heavily built up area.
72
RITES
Freight train movements on CRS should be planned only during off peak
hours especially during nights. In fact, South Western Railway has been
already adopting this strategy to some extent or other.
the running time of the trains. Average spacing of manned level crossings in
CRS area are:
Table: 6.13 Average spacing of Level Crossings in CRS area
Section
Length (Kms)
YPR-YNK
YPR-BYPL
YNK-DBU
SBC-MYA
BYPL-HSRA
YNK-BYPL
YNK-TK
YNK-CBP
SBC-YPR
12.45
16.11
20.72
92.88
48.59
16.12
64.00
46.05
5.35
Average spacing of
manned Level Crossings
(Kms)
1.78
1.79
1.88
2.32
2.56
2.69
2.78
4.61
5.35
Apart from spacing of manned level crossings, traffic at each of these level
crossings also affect the train operations. More the TVUs (Train Vehicle Units),
more is the average running time of the trains. TVUs of LCs in CRS area can
be appreciated as under:
From
To
SBC
BWT
70.21
SBC
MYA
92.88
73
14
26
39
RITES
Section
From
To
SBC
YPR
5.35
YPR
TK
64.00
YPR
YNK
12.45
YPR
BYPL
16.11
YNK
DBU
20.72
YNK
CBP
46.05
YNK
BYPL
16.12
BYPL HSRA
48.59
Total
1
1
1
1
12
11
10
1
12
23
6
19
20
19
22
66
141
Details of Level Crossings with TVUs more than 50000 are at Annexure-10
Level crossing becomes unmanageable and severely affects the train as well as
road operations if the TVU exceeds about 100000. How a train will be able to
maintain its speed with the level crossings with heavy TVUs and with less
average spacing as seen above is anybodys guess. Suburban trains should be
run at 5 to 10 minute frequency. How can a gate with 4 Lakh TVUs be opened
and closed once in 5 to 10 minutes. It is difficult even to think of. In commuter
train operations, every minute counts.
matters for the commuters.
74
RITES
due to land problems, construction is taking too long time. ROBs sanctioned in
CRS area on date are:
Table: 6.15 ROBs sanctioned in CRS area
Year of Sanction
No of LCs
00-01
06-07
07-08
09-10
10-11
11-12
12-13
3
2
1
8
3
1
6
24
Total
The snail pace of ROBs execution deters the planners to sanction new ROB
projects. At this pace, elimination of more than 100 Level crossings in CRS
area just cannot be thought of. A few things worth noting are:
The above issues are brought out here just to reiterate the seriousness of the
issue of level crossings. Like Jharkhand Government, GoK also may consider
entrusting ROBs execution (or at least critical ROBs) to one agency.
5
6
http://www.konkanrailway.com/node/610
Honble Minister for Railways Sri Dinesh Trivedis 12-13 Railway Budget Speech
75
RITES
6.4.10 Quadrupling
With the above cited measures, on all commuter sections (double line sections),
trains can be run at about 10 minutes frequency during peak hours. However,
such running can be made comfortable and also enhanced further (to 5 minutes
frequency or so), by having an exclusive corridor for commuters. Wherever
quadrupling is not feasible due to land problems or so, at least tripling can be
done in those stretches.
6.5
Station Strategies
76
RITES
City core area (lying within 15 km radius from SBC): Here population
density is more and very 1.5 Km or so, there can be a halt.
Spacing of stations in Mumbai, the role model for any CRS in India is as under:
Table: 6.16 Spacing of stations in Mumbai Suburban Rail System
Stations in
Quadruple lines
with Automatic
Signalling
(Mumbai)
Spacing of
Stations
Less than 1 Km
1 to 2 Km
21
2 to 3 Km
More than 3 Km
41
Total
73
Stations in Double
Line with
Automatic
Signalling
(Mumbai)
3
4%
4%
12
29%
18%
9
11%
14%
42
56%
64%
66
100%
100%
Stations in Double
Line with
conventional
Signalling
(Bangalore CRS)
0
0%
1
2%
5
13%
33
85%
39
100%
Stations in Single
Line with
conventional
Signalling
(Bangalore CRS)
0
0%
0
0%
2
9%
20
91%
22
100%
From the above, it can be seen that Bangalore needs good number of additional
halts.
However, provision of more halts has limitations as under:
EMU rakes take very less time for acceleration, deceleration and also for
passengers to entrain/detrain. With normal passenger rakes, more halts
is not feasible. All commuter rakes should be made EMU rakes before
increasing number of halts.
77
RITES
Hence all
Feeder roads should be feasible and should be developed for every halt.
There need to be habitations nearby so that the new halt gets patronised.
Land should be available for all these facilities for establishing a new halt.
While acquiring the land, it needs to be planned for 20 coach trains
though, that much lengthier trains are not proposed now. This goes a
long way to enhance the CRS capacity in future.
Presently there are about 64 halts in the CRS area of about 440 Km. As felt
necessary by public and various voluntary organisations, another about 45 halts
are required in the CRS area (List at Annexure - 3). However, the list does not
cover the additional halts of full CRS area. These additional halts and even
more can be made possible provided
addressed and a detailed field survey is done duly covering above cited
aspects.
6.6
Existing terminals SBC and YPR have got certain natural convenience to deal
trains of particular direction as shown under:
Table: 6.17 Directional Convenience of Terminals
Trains from (direction)
Convenient Terminal
DBU
BWT
HSRA
MYS
TK
CBP
YPR
SBC
YPR and SBC
SBC
YPR
YPR
78
RITES
If a train from DBU is terminated at SBC instead of YPR, extra time taken is
about 15 to 25 minutes. Similarly, if a train from BWT side is taken to YPR
instead of SBC, it takes about 15 to 25 minutes extra.
considered in the present time-table. With the result, both the terminals are
dealing trains from virtually all directions. If the time table is changed making
the terminals strictly as per the above cited directions:
6.7
79
RITES
A commuter needs a well-integrated, faster and simple terminal access (not like
long distance passenger who does not mind spending even 30 minutes extra
moving from one platform to another etc.). Hence it would be preferable to
develop a new terminal exclusively for CRS users.
RITES surveyed the surrounding open areas - both railway and non-railway
lands, to locate the terminal. While available railway land is not sufficient to
provide the terminal, open land vacated by the Binny Mills, lying abutting the
railway land is most promising. The terminal can be located at this place with
ease of access to the railway station. The place also has road access and thus
it can be designed into a multimodal terminal.
This can also be connected to the Mysore line directly as it lies towards the
Mysore end. The terminal would connect to other directions also suitably.
Therefore, it is suggested to develop an exclusive commuters handling area
(platforms, foot over bridges, feeder roads etc.) in Binny Mills Land.
6.8
Average Speed
(KMPH)
Engine Reversal
Terminal
Detention
Width of Coach
Rake Design
MEMU/DEMU Rakes
EMU rakes
36.8@
38.5#
40.2@
Required
30 minutes to 1 Hr or
even more
10 feet
They are made for
normal long distance
travel. Toilets,
Not Required
Not Required
10 to 20 minutes
5 to 10 minutes
10 feet
It is nothing but normal
passenger rake except the
interior seating. Seating is
12 feet
Made especially for commuter
travel with more space for
standing, no toilets, wider
80
RITES
MEMU/DEMU Rakes
changed to suit sitting
passengers.
EMU rakes
entry/exit etc.
Suitability
Provision of
Toilets
Provided
Not provided
Entrain / Detrain
Capacity
Cost
Overall
Lower
Higher
When the CRS trains get patronised, the rakes get overloaded beyond
normally designed for. In Mumbai, one EMU car carries more than 600
commuters in peak time against its seating capacity of about 120 or so. 4
car units cannot handle such over loadings due to less powering.
Average cost per car of 3 car rake is about 8% to 12% higher than that of
4 car rake.
81
RITES
General look, feel and seating arrangements etc. are constantly under up
gradation.
DEMU/MEMUs are not meant for mass transit. They are medium transit
systems.
EMU
is
even
50%
more
considering
standing
commuters,
However, routes where EMUs are to be run need special survey and
attention especially with reference to tracks spacing and platform heights
and lengths. Such attention is required only in CRS network of about 440
Km (where EMUs are proposed to be run).
82
RITES
Such up
Therefore, EMU
6.9
6.9.1 Parameters
The operating plan for suburban system would be dictated by the available
capacity and type of trains run and the type of traffic different types of the day.
83
RITES
Mumbais main terminals (CSTM and CCG) are dead end terminals
whereas SBC and YPR are passing through terminals connecting many
directions.
Mumbai has mostly quadruple lines whereas Bangalore will have double
lines.
84
RITES
Chhatrapati
Shivaji
Terminus (CSTM) and evening peak is 1700 hrs. to 2000 hrs. departing from
CSTM while on the Western Railway system it follows morning peak from 0830
to 1130 hrs. arriving at Churchgate and evening peak of 1730 to 2030 hrs.
departing from Churchgate.
In addition to the peak, the day can be split into off peak and lean. Lean period
will be from 2300 to 0500 hrs. and the remaining 12 hours being off peak hours.
Frequency of trains during peak can be 10 minutes, during off peak 15-20
minute frequency, and during the lean period will be every 45 minutes or 1 hour.
Typical potential for headway for Bangalore CRS trains is as under:
Table: 6.19 Typical Potential for headway of CRS Trains
Phase
To start with
After the system gets
stabilised and
patronage picked up
Peak period
(800 to 1100 &
1700 to 2000)
20 Minutes
10 Minutes
20 Minutes
Lean period
(23-5)
A maximum of 1 every
hour subject to demand
and needs of maintenance
blocks
A detailed time tabling of these schedules will have to be done to see how each
sector is served but it is beyond the scope of this report. Hourly distribution of
potential number of CRS trains that can be run after the CRS is implemented is
given at Annexure 9.
85
From
RITES
Hour wise beak up of existing services (total trains as well as trains serving
commuters) are given in Annexures 7 and 8 respectively. These annexure
indicate that during the morning and evening peak periods of 0800 to 1100 hrs.
and 1700 to 2000 hrs., except in two sections all others have 4 or fewer trains.
Even the lone exception of SBC-BYPL-BWT section has 5 trains.
Thus,
retaining the existing services intact, it is possible to meet the peak services of
the CRS as hourly capacity of fully developed system is going to be 7 to 8.
Hourly distribution of possibility of running additional commuter services after
implementing CRS is given at Annexure-9.
reasonable
allowance
for
running
goods
departmental
trains,
rakes. Plan for stabling rakes is a part of detailed time tabling of services by S
W Railway and any study like the present one cannot attempt to draw stabling
plans.
discussed as under:
86
RITES
EMU Rakes: Out of 26 EMU rakes, any time 3 to 4 rakes will be in EMU
shed. 3 to 4 rakes will be under run even during nights and weekends.
Additional 2 lines proposed at each of the 7 terminals (MYA, TK, HSRA,
DBU, CBP, BWT, and Kunigal) and one additional line at various other
stations can be used to stable the balance EMU rakes when not in run. In
addition, some stabling lines that exist in YNK, some more stabling lines
proposed at BYPLN, and proposed exclusive coaching terminal in Binny
Mill land also can be used to stable good number of EMU rakes.
6.10
Capacity enhancement of existing rail network has been brought out above
sections. However, the mission of commuter rail shall not stop there. It is a
continues process to enhance capacity and to extend the rail network to new
geographical areas to keep in pace with growing public needs.
MRVC in its phase II and phase III plans, made proposals to extend the network
to new areas which Indian Railways cannot do with its resources.
Developing 5th and 6th coaching terminals (in DBU route and TK route
respectively) to keep in pace with growing demand also adds to
commuter capacity of the CRS system.
87
RITES
These
An Air Port link can also be developed instead of costly alternative like
High Speed Rail Link to Air Port.
Suggesting alignments and locations for rail network to new areas need lot of
physical survey specially details about road network, demand pattern and land
availability.
6.11
Airport Connectivity
As desired by client, Airport Connectivity using CRS vis--vis Airport
connectivity by metro is discussed hereunder.
The proposed High Speed Rail Link from Cubban park to Air Port (about
33.3 Km) cost about Rs. 8325 Crores (@ Rs 250 crores per Km).
Even with this huge investment, the air travellers from different parts of
the city shall need to travel by CRS or BMTC or any other mode to reach
HSRL station (i.e. either Cubban Road or Hebbal or Yelahanka).
CRS network passes very close to airport. Track between Dodjala and
Devenahalli stations of CBP line is just about 6 Km away from airport. If
this 6 Km track laid, CRS can reach the airport.
Air travellers may stay in any part of the city say HSRA or BWT or DBU or
MYA or so. Travel time for them to reach airport is the most important
criteria for the investment decision.
30 Minutes
to 2 Hrs.
DPR for High Speed Rail Link from City Centre to Bangalore International Airport by DMRC (2007)
88
RITES
the passenger
boards High speed
rail)
Travel Time for an air traveller to reach Airport without High Speed Rail
Link, but by extension of CRS to airport =
Time from his place of
residence to Airport on
CRS network (via) SBC
or YPR or YNK or so
15 Minutes to 2 Hrs.
depending on where
the passenger stays
Maximum travel time saving due to High Speed Rail link is only for the air
travellers who stay just near to any of the high speed rail stations i.e.
Cubban Road or Hebbal or Yelahanka.
saving may not be substantial and may be even negative in some cases.
In view of the heavy cost implications and in view of the minimal time
advantages to larger air travelling population, it may be worth reviewing
the issue in detail before making any final investment decision.
Savings by such review alone may finance the entire CRS project costing
Rs 8000 to 9000 Crores.
It is worth noting that Hyderabad MMTS phase-II provides for a rail link to
Shamshabad Airport just by extending the existing rail network by about 6
Km.
89
RITES
7
7.1
In any highly urbanized area, land definitely is a crucial issue. All big plans and
projects may get struck up when it comes to land.
In the context of CRS Bangalore, land issues that can change the game and
that need special attention by GoK are brought out in brief here.
7.2
For doublings and triplings, except at few locations, existing Railway land would
suffice. Additional land may need to be acquired at certain locations. Physical
field survey is required to identify the land requirement.
7.3
To serve more public, more stations need to be developed in the CRS. For
every such station, land for platforms, ticketing, parking, commercial space etc.
is required.
stations and for bus stops. At existing stations, available Railway land may be
mostly sufficient to develop required facilities. However, for developing new
halts, land may need to be acquired.
7.4
If at all there exists one single most important issue that can bring CRS to
Bangalore, it is Binny Mills Land in SBC yard.
extension of SBC yard and therefore, can be connected to SBC and other rail
network very easily and so naturally. This facilitates construction of additional
platforms exclusively for commuters so that commuters and long distance
passengers will have separate facilities at SBC. This land can also help for
locating lines, platforms, FOBs etc. to deal exclusively commuter trains so that
load on over saturated SBC get relieved which in turn help to run more and
DULT Government of Karnataka
90
RITES
more commuter trains in the entire CRS. Easy connection of SBC yard to MYS
side and thus making almost all lines of SBC universal for receipt/dispatch
from/to any direction is also possible with this land.
It is highly recommended that this land entirely should be made available for
Railways for bringing best CRS to Bangalore. In exceptional difficulties, if part
of this land is spared to Railways, other scaled down options can be explored
wherein capacity additions also shall be accordingly less.
To put in simple and plain words: Without Binny Mill Land, there may not
be CRS.
PFs, FOBs etc. of SBC yard are very much congested even with present
level of passengers. With increase in CRS trains, passengers present at
any moment in SBC area will become more and more; and cause
inconvenience to commuters as well as long distance passengers.
Exclusive CRS area in Binny Mills Land will address this issue. Without
Binny Mills Land, passengers handling may be unmanageable at SBC.
91
RITES
Such multi-level PFs are to be connected to all the 3 sides i.e. MYS, YPR
and BYPL side. Such arrangements are not impossible, but costs very
high. SBC yard alone may cost something like Rs. 5000 cores or so.
SBC has to run EMUs in 7 different directions. To start any service in the
early morning to any of these directions, a few EMU rakes needs stabling
at SBC during nights. Without Binny Mill land, it may not be possible to
stable any EMU rake in nights.
Capacity of SBC yard estimated as 150 pairs of trains per day in chapter
6 is based on the assumption of availability of full Binny Mills Land. If all
the remodelling suggested to SBC yard is done without Binny Mills land,
the capacity of SBC yard will be somewhere around 100 to 120 pairs.
The most crucial activity of connecting as many lines as possible of SBC
yard to MYS side reduces the length of various lines considerably in SBC
yard. Repercussions of reduced lengths of lines are already discussed in
this report. To maintain the same length of lines (or to increase) even
after connecting them to MYS side, Binny Mills land is essential.
Ideally, SBC should not have any terminal activities (i.e. pit lines etc.).
But, presence of a couple of pit lines at SBC will be handy in the long
term interests of the system. If Binny Mills land is not present, when all
the existing pit lines are converted into PFs for CRS trains, pit lines will be
totally absent. If any pit line is retained, number of PFs will come down.
With Binny Mills Land, there will be flexibility in redesigning SBC yard duly
retaining a few pit lines so that future train operations have flexibility,
especially with reference to introduction of any new trains.
Though
Binny Mill land issue assumes prominence and significance due to the
commercial value it has got.
92
RITES
93
Without detailed
RITES
Facilities possible
About 5 to 6 PFs, FOBs, etc. can be developed to make it an exclusive
Full (about 29 Acres)
CRS trains handling area so that commuter traffic can be isolated from
long distance passengers as in case of Mumbai
2 to 3 PFs and FOB can be developed so that some CRS trains can be
About 15 Acres
dealt. Balance CRS trains will be dealt in main SBC yard
About 12 Acres
2 stabling lines and 2 pit lines can be developed
1 stabling line and 1 pit line can be developed or entry to MYS side can
About 9 Acres
be given to more lines of SBC yard
About 6 Acres
2 stabling or shunting lines (or 1 pit line) can be developed.
About 3 Acres
1 line is possible to construct. It can be used as shunting neck
Note: For developing commuter terminal, road side land is required to give entry. For facilities like
pit lines and stabling lines alone, road side land may not be essential.
7.5
7.6
94
RITES
quadrupling.
sanctioned by Indian Railways in 1997 itself. But it has not yet taken off due to
various issues including the land acquisition issues.
7.7
7.8
7.9
For
geography like Bangalore, ring rail (one at 40 Km radius and another at about
60 to 70 Km radius from SBC) is an ideal proposition. Fortunately, land is said
to have been already earmarked in master plan for ring rail adjacent to outer
ring road.
7.10
On date, there exists only one freight terminal (SGT) near Whitefield on CRS.
For the present level of freight traffic, existing freight facilities are considered
good enough. However, as the freight traffic increases, movement of freight
95
RITES
trains from all directions to SGT badly occupies the sections and net capacity
for commuter trains shall come down. Therefore, in future, some more freight
terminals need to be developed in Bangalore area.
terminal in DBU area and one in TK area will be required. Land will be required
for these freight terminals.
7.11
Land is required for doublings, flyovers etc. suggested in this report. Detailed
field study is required to assess the total land requirement, land available with
Railways and state government and private land requirement.
7.12
Source: http://right2information.wordpress.com/category/rti-success-stories/page/3/
96
RITES
7.13
Vision of any city comes from its master plan. If master plan is made with due
care and vision, probably city development, particularly the transport problems
do not pose serious problems.
contemplating to make City Master Plan for 2035. In fact, it has also called for
suggestions from public in this regard.
actively associated to identify future land requirements for Railway use. Land
requirement for all the above cited railway uses should be thoroughly studied
(by engaging a professional consultant if required) and analysed and land
should be clearly earmarked in the master plan for railway use.
It is worth
for
future
Railway
passenger
terminal
at
Manoharabad
and
97
RITES
terminal at Timmapur and Bhongir in the Hyderabad draft master plan published
in 20109.
Identifying land for railway use needs physical survey and series of
deliberations with various stake holders. In fact, it is a separate study by itself.
Therefore, specific locations (for earmarking the land for railway use) are not
suggested in this report.
source: http://www.thehindu.com/todays-paper/tp-national/article2297287.ece
98
RITES
8
8.1
Converting all CRS sections into double line, electrified and automatic
signalled.
Other works en-route for introducing EMUs (checking and adjusting the
spacing of tracks, offsets to FOBs, ROBs, signal posts etc.).
8.2
99
RITES
8.3
summarised as under:
Entry to MYS side facilitates movement of more trains to Mysore side and
to terminate trains (which do not need any pit line attention) at different
stations of MYS section.
100
RITES
After finalising the plan of SBC, detailed phase wise activities are to be
drawn.
services from these sectors are not extended upto SBC, YPR may not be
able to handle additional commuters congestion.
101
RITES
SBC-YPR. This block section is already provided with Twin Single Line
arrangements. This section may need to be further provided with IB
(Intermittent block) signals for both lines for both directions so that this
section capacity almost doubles.
facility for 9 car rakes and 16 car rakes is also not substantial.
started with 9 car EMU rakes initially and can be changed to 12 car rakes
and 15 car rakes in phases.
102
RITES
Facilities at terminals i.e. BWT, MYA, TK, HSRA, DBU, CBP, YPR and
YNK should be upgraded (like parking area, waiting area, platforms,
FOBs etc.).
8.4
The block cost estimates are made considering the latest design EMUs
with 3 car EMU units. (Energy efficient 3 phase motors, stainless steel
body, GPS based passenger information system etc.)
However, in case GoK desires to bring down the costs, the issue can be
deliberated with MoR and ICF to finalise the features required.
Such cost cutting measures can save upto about 40% of cost (of rolling
stock plus cost of EMU shed). On total project cost of Rs. 8000 to 9000
crores, this savings may work out to upto about 10% to 12% depending
on the design finalised.
103
RITES
accordingly.
8.5
Phasing Philosophy
Apart from the above cited issues, phasing of investments and corresponding
benefits to the public are also important considerations while deciding the
phases.
Client advised that they had deliberated among their officials and
desired to keep TK, CBP and HSRA sections under Phase 1 and balance in
phase 2. Accordingly, total proposed investment is recommended in 3 phases.
Phase 1:
Phase 2:
Phase 3:
However, during the meeting organised by DULT on 11th July 2012, some
Railway officials present expressed that a small sub-set of activities out of total
scheme of CRS project can be completed immediately (in about 6 months to 1
year time) and a few additional services can be run to give some immediate
service to the public and rest of the CRS project can follow later. The Railway
officials present during the meeting were DRM, CTPM and other divisional
officers (along with GoK and RITES officials). Sub-set of activities suggested
were by the Railway officials were:
Making SBC BNC into twin single line and BNC BYPL into automatic
signalling or IBs.
104
RITES
8.6
Phase 1A
As discussed in above paragraph, few activities of the total scheme for
immediate implementation are:
o Procurement of 5 MEMU rakes:
Rs.
105 Cr
Rs.
8 Cr
Rs.
40 Cr
Rs.
20 Cr
MEMU rakes can be run on electrified double line sections i.e. SBC-BWT
and SBC-MYA sectors. Additional services possible with these 5 rakes:
o Out of 5 rakes, 3 rakes can be operated in MYA sector and 2 in
BWT sector.
o Thus, 3 rakes can make 12 services (6 up and 6 down) in SBCMYA section and 2 rakes can make 12 services (6 up and 6 down)
in SBC-BWT sector. This is calculated taking 500 Km travel per
day for each rake and catering for 20% maintenance buffer.
o Thus, 24 services can be run with the proposed facilities which
give good relief to the commuting public.
105
RITES
proposed to be run beyond the CRS network. These rakes will be used
in phase-2 to replace existing services as all new services will be run
with EMUs in phase-1 and 2.
Table: 8.1 Phase 1A in a Nutshell
Potential $
Investment
(Services that can
Phase (in Crores of
be additionally
Rupees)
introduced)
Additional
Services
proposed to be
introduced #
Commuter trips
that can be
generated per
day at the end of
Phase 1A in lakhs
1A
173
24
24
4
In addition to enhancing the capacity of existing services by replacing with
MEMUs and EMUs. Services in both directions together are indicated.
# Each service proposed is assumed to originate and terminate in the same
section. For example, if a new service starts in SBC-YPR section and ends in
YPR-TK section, it is counted as 2 services in this figure.
$
8.7
Phase 1
This phase is aimed at tackling the sections with maximum commuters
demand.
106
RITES
Amount
(Cr)
Total
Qty
Amount
YNKCBP
Qty
Amount
Qty
YPRYNK
Amount
YPRTK
Qty
Amount
SBCYPR
Qty
Amount
BYPLHSRA
Qty
Amount
Qty
YPRBYPL
Per
Activity
S. No
Doubling
12 Km 16.12 194 48.59 583
46.05 553 177 1330
Electrification&& 1.25 Km 32.24 40 97.18 121 10.70 13 128.00 160
92.10 115 471 449
Auto Signalling 0.75 Km 16.12 12 48.59 36 5.35
4 64.00
48 12.45
9 46.05
35 441 144
Extn/Rising PFs 3 Stn
2
6 4.00 12 1.00
3 10.00
30 2.00
6 6.00
18
53 75
Facilities at
5
15 Stn
1 15 1.00 15
1.00
15 1.00 15 1.00
15
9 75
Terminals
Addl. lines at
6
10 Line
1 10 4.00 40
5.00
50
3.00
30
36 130
Stns$
Facilities at
7
10 Stn
2 20 4.00 40 1.00 10 10.00 100 2.00 20 6.00
60
53 250
Exg. Stations^
9 car EMUs (to
8 replace exg.
36 Rake
0.08
3 0.92
33 0.21
8 0.79
28
2 72
services)&
9 car EMUs (for
9
36 Rake
2.5 90 7.51 270 0.23
8 2.77 100 0.64 23 2.36
85
24 576
new services)*
3101
Sections Cost Total -> 387
1117
41
536
81
939
10
Development of EMU cum MEMU maintenance shed at Banaswadi 200
11
SBC yard remodelling duly including Binny Mill Land 370
12
Facilities at BYPLN (4 pit lines proposed in Phase 1A; Balance 6 pit lines, stabling lines PFs etc.) 160
Total Cost of Terminals 730
Total Cost of phase 1 (Sections Cost + Terminals Cost) 3831
$
2 additional lines at terminals and one additional line at alternate stations are recommended
^
Facilities like parking, waiting & ticketing area, bus stop etc. are required to cater for increased commuter traffic.
&
Existing services requiring replacement with EMUs can be seen at Annexure -4
*
EMU rakes requirement at Annexure -6 assumes 15 car rakes. However, in this phase, 9 car rakes recommended.
&&
Where exg single line is electrified, one line cost is taken. Where exg Single line is non-electrified, both lines cost is
taken.
1
2
3
4
107
RITES
BYPLHSRA
SBCYPR
YPRTK
YPRYNK
YNKCBP
3831
330
Additional
Services
proposed to be
introduced #
172
Commuter trips
that can be
generated per
day at the end of
Phase 1 in lakhs
8
108
RITES
8.8
Phase 2
In this phase, it is recommended to take up all remaining sections for fullfledged implementation of CRS in Bangalore.
109
RITES
19.23 14 20.72
1.00
16 45.20
34
66
111
791
139
59.45
45 92.88
70 237
179
9 8.00
24 12.00
36 28
84
1.00
15 1.00
15 4
60
3 1.00
3 3.00
1.00
15 1.00
15
1.00 10 3.00
30 4.00
40 2.00
20 6.00
60 7.00
70 23
230
1.00 10 1.00
10 3.00
30 3.00
30 8.00
80 12.00 120 28
280
1.44 52 1.56
56 1.00
36 0.15
6 0.85
30 3.00
288
89
9 3.00
Amount
(Cr)
Total
Amount
Qty
SBCMYA
Amount
BYPLBWT
Qty
Amount
Qty
SBCBYPL
Amount
Qty
SVDLKunigal
Amount
Qty
Amount
YNKDBU
Qty
16 car MEMUs
1 (for replacing
21 Rake
exg. services)@
2 Doubling
12 Km
3 Electrification && 1.25 Km
Automatic
4
0.75 Km
Signalling etc.#
Extension/
5
3
Stn
Rising of PFs
Facilities at
6
15
Stn
Terminals
Addl. lines at
7
10 Line
Stations$
Facilities at Exg.
8
10
Stn
Stations^
9 car EMUs (for
9
36 Rake
new services)*
Sections Cost Total ->
10
Qty
YNKBYPL
Per
Activity
S. No
108 8
405
819
65
254
419
2051
Developing Hejjala 4th Coaching Terminal 200
Total Cost of Terminals 200
Total Cost of phase 2 (Sections Cost + Terminals Cost) 2251
@
Services requiring replacement with MEMUs are at Annexure 4. Costs included in phase 1A; Hence not shown.
#
SBC-BNC is recommended as twin single line. All other sections are recommended for Automatic Signalling.
$
2 additional lines at terminals and one additional line at alternate stations are recommended
^
Facilities like parking area, waiting/ ticketing area, bus stop etc. required to cater for increased commuter traffic.
*
EMU rakes requirement at Annexure-6 assumes 15 car rakes. However, in this phase, 9 car rakes recommended.
@@
Addl Services are proposed based on demand (high scenario) for 2021. In case patronage is more, services can
be increased upto the potential of the section simply by procuring additional EMU rakes
##
Potential is given in terms of services that can be introduced in both directions together in commuter timings
(Annexure-9) with the proposed up gradations duly making reasonable provision for freight trains, long distance
trains, maintenance operations etc.
$$
Share in overall commuter demand of the CRS area. This demand is expected to be met in this phase.
&&
If existing single line is electrified, cost is taken for one line only. If existing single is non-electrified, cost is taken
for both lines.
Table: 8.6 Phase 2 in a Nutshell
$
Potential
Additional
Investment
Commuter trips that can be
(Services that can
Services
Phase (in Crores of
generated per day at the end of
be additionally
proposed to be
Rupees)
Phase 2 in lakhs
introduced)
introduced #
2
2251
320
94
15
$
In addition to enhancing the capacity of existing services by replacing with MEMUs and EMUs.
Services in both directions together are indicated.
# Each service proposed is assumed to originate and terminate in the same section. For example, if a
new service starts in SBC-YPR section and ends in YPR-TK section, it is counted as 2 services in this
figure.
110
RITES
8.9
Phase 3
Making use of the up graded infrastructure for serving more and more
public by introducing additional halts in the CRS network and by
increasing the length of EMU rakes and removing further finer
bottlenecks.
No
1
2
3
4
From
YPR
BYPL
SBC
YPR
YPR
YNK
YNK
YNK
To
BYPL
HSRA
YPR
TK
YNK
CBP
BYPL
DBU
Distance
in Kms
16.12
48.59
5.35
64
12.45
46.05
19.23
20.72
Cost in Cr
135
135
15
165
45
45
105
45
111
Total Cost
in Rs of
Crores
240
510
96
276
96
186
72
222
RITES
SDVL
SBC
BYPL
SBC
6
7
Kunigal
BYPL
BWT
MYA
Total
45.2
10.76
59.45
92.88
440.8
4
1
7
14
72
60
1
24
15
1
24
105
210
3
72
1080
26
624
Bypass Line connecting DBU and CBP lines
Quadrupling between SBC and WFD
Total
84
144
282
1704
300
500
2504
Investment
(in Crores of
Rupees)
Potential
(Services that can
be additionally
introduced)
Additional
Services
proposed to be
introduced
Additional EMUs proposed in this phase are for increasing the length of EMU
rakes. However, these additional EMUs can also be used to run additional
services instead of lengthening existing rakes as CRS network will have
potential to run additional services with various up-gradations recommended.
8.10
activities
should
be
planned
in
such
way
that
their
112
RITES
ICF has capacity of about 1500 coaches per annum which include all
varieties i.e. EMUs, MEMUs, sleeper class coaches, guard coaches, AC
coaches etc.
Once Railway Board approves the program, ICF can start delivering
EMUs/MEMUs after about 8 to 12 months. Their supply rate shall be
normally about 3 rakes per month.
8.11
By
that time, total load on Bangalore public transport system shall be about 60 lakh
trips. Thus CRS shall cater for at least 40% of public transport needs of the city
which is a very healthy indication for any urban/suburban transport system. In
fact, this much of capacity shall be available even at the end of phase 2 but with
too much over crowding like in case of Mumbai (about 600 commuters per car!).
Extension of length of EMUs is recommended in phase 3 to ease out this
overcrowding. In fact, the EMUs procured in phase 3 can also be used for
running additional services instead of lengthening existing rakes as already
brought out.
113
RITES
8.12
Once the above phases are completed, to increase the capacity of the system
further, it will be required to remove finer bottlenecks. Also it is required to
extend the CRS to new geographical areas. Some activities to take forward the
mission of CRS Bangalore are:
a. Increasing the frequency of CRS trains by procuring additional rakes
upto the potential shown in Annexure 9.
b. Development of 5th coaching terminal in TK side (within about 15 Km
from YPR).
c. Restoration of abandoned line in Baiyyappanahalli Vimanpura area
and introducing commuter services.
d. Construction of 3 flyovers at BYPL area (connecting SBC-HSRA, BWTYNK, BWT-HEB) and 1 flyover at YPR (connecting HEB/YPR side to TK
side).
e. Constructing a line to facilitate direct entry of train from YNK to HEB
without touching YPR (bypass at LOGH).
f. Introducing longer EMUs (even beyond 15 cars) and fast (limited halts)
services.
g. Quadrupling of BYPL-HSRA, SBC, TK, SBC-MYS and other sections.
h. Elimination of all Level Crossings with ROBs/RUBs in CRS area.
i. Skywalk connecting Baiyyappanahalli North 3rd coaching terminal to
Baiyyappanahalli Metro Station.
j.
After these
114
RITES
side) so that freight trains need not enter into whitefield area
unnecessarily and eating away commuter capacity.
k. Extension of rail services to new areas or extending CRS to some more
length on existing rail network i.e. beyond HSRA, TK, and MYA etc.
l. Development of Ring Rail around the city to cover greater public (One at
40 Km radius and another at 60-70 Km radius from SBC).
m. Construction of Air Link Rail.
8.13
Especially at SBC, activities like extension of existing pit lines etc. should
not be attempted as they will bring down capacity of SBC.
115
RITES
9
9.1
Return on Investment
Apart from direct revenues in the form of surcharge, there will be indirect
revenue to GoK due to increase in property values.
To appreciate such
Out of the identified CRS network of 440.8 Km, about half the network is
in Bangalore Urban District / BBMP area.
This works out to about 1100 SqKm i.e. about half the area of urban
district area.
Total:
5000 Cr
2500 Cr
1500 Cr
That means, more than Rs 1500 Crores return to GoK in the first 1 or 2
years.
10
Income for the state of Karnataka is Rs 4800 Crores in 11-12 out of which 73 % is from Bangalore Urban Area
source : http://www.thehindu.com/news/states/karnataka/article3009869.ece)
116
RITES
This little calculation is illustrated here just to emphasis the fact that
considering direct revenue alone (in the form of surcharge or so) is very
misleading while taking investment decisions.
9.2
No
From
1
2
3
4
5
6
7
8
9
10
11
SBC
SBC
YPR
YPR
YNK
YPR
YNK
YNK
BYPL
SBC
SVDL
117
RITES
reduction (due to fully developed CRS) in one or more of the above modes shall
bring great savings to GoK as the per Km costs are huge (Metro / High Speed
Rail Link to Airport: Rs 250 Cr/Km,
Savings on account of such review can be like Rs. 10,000 crores as brought out
in discussion about cost of overlap (Para 2.9 and Table 2.9). Savings from
review of High Speed Rail Link to Airport proposal as brought out in Para 6.11
alone can fully finance this CRS implementation project of Rs. 8000 to 9000
crores.
9.3
Rate of return depends on the demand and pricing. For a commuter rail project,
especially for a system like Bangalore, demand is not an issue. Demand is
normally much more than the project can offer. But, the pricing is very tricky.
Any business model adopts scientific pricing model like demand-supply model
(price is fixed such that demand equals to supply) or cost plus profit model. As
is well known, Commuter train fares are not decided based on any of these
scientific methods. Fares are decided based on popular considerations without
concerning about the costs incurred to produce the service. Therefore, it is too
much of an optimism to think in terms of recovery of capital costs or even
running costs from a commuter project.
In this context, costs and returns scenario of Indian Railways is worth looking at.
Indian Railways accounting system is not in the form of a typical profit and loss
statement which normally any corporate entity maintains. It is in the form of
various indices and comparisons to previous years. Most of the assets (Track,
Signals, Locomotives, and Stations etc.) are used for all trains i.e. commuter
trains, long distance trains,
118
RITES
Segment
Vehicle Km
(in Millions)
Earnings
(in Crores of
Rupees)
Earnings
(Rupees per
Vehicle Km)
Sub-Urban Passenger
Service (EMUs only)
1438.50
1792.59
12.46
18207.00
24000.04
13.18
Freight Service
17749.00
62844.72
35.41
All together
37394.50
88637.35
23.70
This is again a notional figure and does not truly reflect the real
119
RITES
Rs 23.70
Rs 22.42
Rs 12.46
Rs 9.96
44.4%
9.4
1A
173
24
1
2
3
3831
2251
2504
56
24
330
172
320
NA
Additional
Services
proposed to be
introduced
&
Commuter trips
that can be
generated per
day (Cumulative
in Lacs)
2
4
94
15
NA
&
25
120
RITES
Savings in journey time because rail is going to capture the traffic which is
presently being served by bus or private transport etc.
Reduction in fuel consumption (trains are more fuel efficient than busses).
9.5
IR Non sub-urban fare is less than Sub-urban fare for the same distance
and same class.
121
RITES
Overall CIDCO fare > Overall MRVC fare > Overall MMTS fare.
Distance
Upto 10 Km
MRVC
1st Class
Ticket
0
11 to 50 Km
10
20
51 to 100 Km
15
30
101 to 150
20
40
Not based on
distance but
for a
CIDCO
particular
origin to
destination
1 to 4
17 to 80
2 to 6
42 to 200
Remarks
Surcharge levied
on 16th Sep 03.
Not revised since
then
Surcharge initially
levied in 1990.
Revised once in
04-05.
Figures in Rupees
Surcharge accrued from MRVC projects is somewhere around Rs.90 Cr in 11-12 with ridership of about 60 lacs. This
works out to about 41 paisa per commuter trip
Upto 25
Km
Beyond
25 Km
In Hyderabad MMTS, basic fare charged is for Non Sub-urban category whereas in Mumbai and Chennai etc.,
basic fare charged is for Sub-Urban category.
122
RITES
Distance
Basic Fare
Total Basic Fare
Total Basic Fare
Total
(Non
DC
DC Surcharge
DC Surcharge
Fare (Suburban)
Fare (Suburban)
Fare
Suburban)
1
1
1
2
3
1
2
6
3
1
3
7
5
1
1
2
3
1
2
6
3
1
3
7
10
1
1
2
3
1
2
6
3
1
3
7
15
1
1
2
4
1
2
7
4
1
4
9
20
2
1
3
5
1
3
9
5
1
5
11
25
3
1
4
6
1
3
10
6
1
6
13
50
7
1
8
10
1
5
16
10
1
10
21
Surcharge accrues per annum
(taking 18 lac commuters by 2021
and average sub-urban revenue of
Rs 130 Crores
Rs 260 Crores
Rs 4.40 per commuter trip as per
IR year book 10-11)
18 lac commuters is considered on week days. On weekends, travel will be less. Therefore, a small correction factor
is applied while working out Surcharge accrual.
Fares of 10-11 are considered for working out Surcharge accrued. Fares may get revised in future. Surcharge
accrued will also go up as and when fares get revised
GoKs Share of surcharge (50% or 100% or so) depends on the agreement/MOU with GOI
From the above, it can be seen that fares with 100% surcharge are
comparable to BMTC fares.
123
RITES
124
RITES
10
10.1
Route Km in India
Track Km in India@
1950#
53596
77609
64460
113994
0.31%
0.64%
2010
10.2
Feasibility study was got done by GoAP to develop mass rapid transport plan
for Hyderabad. This feasibility study and further follow up by Government of
Andhra Pradesh (GoAP) led to signing of MOU between MOR and GoAP on
25th Sep 2000. Based on the report prepared by GoAP, Railways put up a
feasibility report to CCEA (Cabinet Committee on Economic Affairs) in Jul01.
The MOU was basically to develop commuter rail services on existing rail
network in HYB/SC-Lingampalli (28.1 KM) and SC-Falaknuma (14.54 KM)
125
RITES
sections. As per the MOU, Cost has to be shared at 50%-50% with a provision
for levy of at least 25% surcharge to be retained by IR.
336000
13104
25486
35770
#
Over 150000
Source : http://www.cag.gov.in/html/reports/railways/2007_6_peraud/chap_4.pdf
#
Source: http://www.thehindu.com/news/cities/Hyderabad/article2981025.ece
Govt. of Andhra Pradesh mooted the proposals for Phase-II even when Phase-I
was under execution. However, Railways decided (in 2006) that Phase-II would
not be taken up until phase-I becomes financially viable. Finally Phase-II was
sanctioned by Railways in 2012 with financing by GoAP (66.67%) and MOR
(33.33%). MOR also proposed to set up a SPV for commercial management of
MMTS leaving the O&M to IR for rapid growth of MMTS and to meet public
aspirations12. While the South Central Railway started making all planning for
execution, the SPV is yet to take shape. The scope of the project under MMTS
phase-II is:
Table: 10.3 Projects under MMTS Phase II
Section
Activity
Length
(KM)
Estimat
e (Cr)
20
85
Falaknuma Umdanagar
Doubling
New Line
Telapur Patancheru
32
Secunderabad Bolaram
14
30
Doubling
22
170
10
25
Bolaram Medchal
28
74
12
126
RITES
Section
Length
(KM)
12
Activity
Estimat
e (Cr)
120
Moula-Ali Ghatkesar
Quadrupling
Passenger Amenities
20
EMU Rakes
Rakes
85
Total
115
641
In 2000-01 period, the then ruling party of AP was the most key ally of
the then ruling party at the centre. Therefore, the project (Phase-I) got
sanctioned and got executed expeditiously.
available
in
the
existing
network,
therefore
capacity
As per MOU, state government shall provide land free of cost wherever
required for development of stations and concerned facilities like roads
etc.
GoAP and political uncertainty prevailing in the states and the centre,
phase-II may take more time than expected.
127
RITES
In the first year of sanction i.e. 2012-13, Railway allotted about Rs 100 Cr
budget for the phase-II project whereas Government of AP has not
allotted any funds so far. In fact, first year of sanction normally goes for
planning, survey, tendering etc. and not much budget grant will be spent.
Success of this project depends on how Railway and GoAP allot the
funds in subsequent years.
Today, the finance crunch being faced by Railway is probably the worst
ever.
While the system (phase-I) was expected to cater for more than 3 lacs
passengers per day, patronage even today is about 1.6 lacs per day.
This is mostly due to non-development of feeder roads to MMTS
stations. There is no institutional mechanism to plan and monitor the
development of feeder roads. The patronage has been increasing not
because some additional facilities were created to the public (like feeder
128
RITES
roads etc.). It is simply due to its low cost. Even without proper feeder
roads, public is taking all pains to make use of this cheaper service.
GoAP has virtually no say in the services being run. IR decides on their
own the number of services, their direction, timings etc. IR is under no
obligation to run certain number of services etc.
Surcharge if at all levied, accrues to IR and not to GoAP as per the MOU
(phase-I). Levy of surcharge (or otherwise) shall be mostly decided by IR
themselves and GoAP does not have any say.
expansion/increase
of
network/infrastructure
(or
even
services).
10.3
urban
settlements
with
full-fledged
physical
and
social
In Nov 1986, MOU was entered by CIDCO with IR for provision of rail
connectivity to Navi Mumbai.
129
RITES
IR levied surcharge of Re 1/- per ticket on 2nd class & Rs 2/- on first
class ticket and the same was transferred to CIDCO. In 04-05, the
surcharge was raised to Rs 2/- to 6/- per ticket depending on the class
and distance.
CIDCO had the rights to commercialize the air space and other parts of
the station area.
Under this model, The Mankhurd to Belapur new line (27 Km) was
commissioned in 1993.
10.4
MRVC came into existence in Jul 99 with equity of Rs 25 Cr (GOI: GOM = 51%:
49%). The corporation gets the identified projects executed and also plans
development of Mumbai Suburban Rail System on a continuous basis. The
mandate of the entity is:
130
RITES
Where direct involvement of running trains and signals is involved, works are
executed by IR. Works like station buildings, circulating areas etc. which need
not involve disturbance to train operations are executed by MRVC directly.
Procurement of EMU rakes is also done by MRVC. Feeder roads etc. are
executed by GoM. Phase-I costs about Rs 4200 Cr. The funding mechanism:
Procurement of EMUs.
131
RITES
10.5
This stage
Making a formal
132
RITES
Considering the
133
RITES
should be taken into confidence and Ministry of Railways also should be kept
formally informed.
10.6
Pure Business entity Model: This model is like KRCL (Konkan Railway
Corporation Ltd). The SPV shall be totally responsible for generating
necessary revenue for its operations and also for debt servicing apart
from executing the projects.
earnings, KRCL ran into losses in the initial years of its inception due to
debt servicing burden. Then equity was enhanced to bring down the
debt burden on KRCL to manageable levels.
amounts to GOI and GoM directly in equal proportion (as GOI and GoM
are more or less equal shareholders in MRVC). GOI executes tracks,
signals etc., GoM executes feeder roads etc. on their own. GOI and
GoM transfer certain funds to MRVC to execute works like Car Sheds,
circulating areas and other works not connected with tracks etc. MRVC
executes those activities.
executing certain activities etc., MRVC charges a fee (in terms of certain
percentage on the projects cost) from the shareholders i.e. GoI and
GoM.
134
RITES
and transfers half of the surcharge to GoM. World Bank loan is directly
repaid by GoI and GoM.
With the surcharge income or with the very less commuter fares, the SPV
cannot sustain to function in KRCL model. Therefore, it is recommended that
BCRC be formulated in the same lines of MRVC.
equity share holding or 51% (GOI): 49% (GOK) like in the case of MRVC. In
case GoI does not come forward, it is worth even to hike GoKs equity upto
100% considering the importance of CRS for Bangalore.
Equity can be provided either directly by the government or through their
entities like IDD or K-RIDE or so.
Normally no infrastructure project can take off purely with equity. Some debt
component may be a must for the success of any project. However, BCRC per
se does not have any debt component as it only offers some services as
discussed above. Debt component is jointly decided by shareholders (GoI and
GoM) separately for each project. Accordingly, justification is made and lending
agencies are approached.
Private Equity can be attracted only in case of viable projects. Commuter rail
business per se does not attract private equity due to its less revenue.
Therefore, some options that need to be explored to attract private equity by the
SPV:
Provide alternate income sources like real estate exploitation etc. (apart
from commuter fares) to investors.
135
RITES
Accordingly, BCRC can also formulate certain projects involving private equity.
Therefore, private investor can only finance the project leaving design,
construction and operation to IR.
136
RITES
Assumed return of 12% may not attract any private investors because
their cost of capital itself will be around 10%.
137
RITES
Commissioner, DULT
Apart from Chairman, MD and above cited independent directors, BCRC shall
also have full time functional as under:
of
EMUs,
construction
of
EMU
sheds
and
Director (Finance).
138
RITES
The projects shall be proposed keeping in view the total transport plan of
the city.
shareholders (IR and GoK). This will also help IR to plan the necessary
arrangements for O & M of such projects (for manpower recruitment,
training etc.).
BCRC shall divide each project into logical and meaningful packages.
Packages which directly affect running trains, track and signalling
systems shall be executed by South Western Railway.
projects are normally executed by
Feeder road
All assets created shall be handed over to Indian Railways for O & M. O
& M costs and O & M profits / losses shall be borne by IR.
Working out O&M costs by IR is easier said than done. IRs accounting
system does not facilitate bifurcation of O&M costs into various heads
139
RITES
like freight, commuter rail, long distance trains etc. Moreover, IR takes
entire South Western Railway as one unit (not even Bangalore Division)
while working out O&M costs.
commuter rail that too only for Bangalore area alone is very complex with
IRs accounting system. Therefore, any model to share O&M costs (or
profits/loss) may not be practicable. Instead, simple surcharge model
which is easy to implement is suggested.
Available Railway land shall be used for commuter rail projects and the
same shall continue to be Indian Railways property.
Also, land
belonging to GoK if required for the projects shall also be handed over to
Railways duly charging its cost to the projects or free of cost as decided
from project to project.
Vacant Railway land and vacant GoKs lands and even vacant air space
along the commuter lines shall be processed by BCRC for commercial
exploitation.
BCRC can take such properties on nominal lease rentals from GoI and
GoK and exploit them. Alternatively, it can charge certain fee from the
shareholders for co-ordinating the process and the revenues accrue to
GoI or GoK as the case may be.
140
RITES
GoK may also consider enhancing the property taxes, property values,
and other indirect charges from the properties around the CRS stations
to tap the increased commercial value of those areas due to
implementation of CRS.
141
RITES
11
11.1
Summing up
For
metro rail, there is an entity BMRCL. For roads, there is BMTC. Similarly, for
commuter rail, an exclusive entity BCRCL (Bangalore Commuter Rail
Corporation Ltd) should come into existence. Then only CRS will get upgraded
continuously in tune with demand.
11.2
142
RITES
Railway and all other stake holders to decide on the extent of land that
can be made available to CRS.
Physical survey is
143
RITES
e) Developing conceptual plans in the above lines for SBC and all other
stations of the CRS network.
f) Detailed survey for airport rail link as discussed in Para 6.11.
g) Once Railway sanctions the projects (on commitment of finances from
GoK or otherwise), Railway does all the surveys and planning required to
run the EMUs (again to say only to run EMUs). IR makes plans for
MEMU/EMU
sheds,
automatic
signalling
arrangements,
Other
activities [like the ones referred at (a) to (f) above] are not essential to
run EMUs by IR. Therefore, IR has simply no mechanism to put its soul
in these activities and IR has no expertise to make proper plans for these
activities which are not directly connected with Railway operations. It is
GoK which has to take immediate action to make plans for these
activities which are not directly connected with train operation but have
lot of bearing on serving commuters.
detailed physical surveys (required to run EMUs) and also executes the
works for implementing the CRS as brought out in above paragraph.
DULT Government of Karnataka
144
RITES
i) RITES has got expertise and all wherewithal to undertake the above
cited physical surveys.
11.3
Proposal to GoI
An SPV coming into existence and start delivering services to the public is a
long drawn process. Therefore, it is recommended that:
Make out a proposal to Ministry of Railways duly bringing out the total
scope of the projects (covering all the 3 phases suggested) and its
readiness to finance 100%.
The proposal can also contain a request to form BCRC in the lines of
MRVC to implement phases 2 and 3 and take the mission further.
Against this investment, GoK should not expect any further returns like
share of revenues, say in fare policy, say in day to day O & M, ownership
145
RITES
146
RITES
147
RITES
Train
12683
22607
12785
12678
16322
16316
16215
56242
56228
56229
56263
12613
16557
16591
18463
56914
16519
56912
12639
16202
56237
12726
56261
16228
17210
56234
16222
56226
Rake Arrival
Origin
Direction
ERS
BYPL
ERS
BYPL
KCG
BYPL
ERS
BYPL
TVC
BYPL
KCVL
BYPL
MYS
MYS
YPR
YPR
ASK
YPR
MYS
MYS
MYS
MYS
MYS
MYS
MYS
MYS
UBL
BYPL
BBS
BYPL
UBL
YPR
JTJ
BYPL
UBL
YPR
MAS
BYPL
SMET
YPR
MYS
MYS
DWR
YPR
MAS
BYPL
SMET
YPR
CCT
BYPL
MYS
MYS
MAS
BYPL
TK
YPR
Time
4:20
4:20
6:25
19:50
8:35
8:35
9:40
10:45
11:20
12:10
4:00
13:30
19:40
6:10
12:05
20:40
8:00
5:15
13:20
11:55
18:00
14:05
18:45
4:30
12:35
22:30
4:10
17:40
Train
12684
22608
12786
12677
16321
16315
16216
56227
56230
56241
56510
16201
16592
16558
18464
56911
56262
56913
12640
12725
56238
12614
16522
56233
17209
16227
16222
56223
Rake Departure
Destination
Direction
ERS
BYPL
ERS
BYPL
KCG
BYPL
SBC
BYPL
TVC
BYPL
KCVL
BYPL
MYS
MYS
ASK
YPR
MYS
MYS
YPR
YPR
MKM
BYPL
SMET
YPR
UBL
BYPL
MYS
MYS
BBS
BYPL
UBL
YPR
AJJ
BYPL
UBL
YPR
MAS
BYPL
DWR
YPR
MYS
MYS
MYS
MYS
MKM
BYPL
MYS
MYS
CCT
BYPL
SMET
YPR
MYS
MYS
ASK
YPR
148
Time
17:15
17:15
18:20
6:15
18:50
17:15
18:15
16:45
16:25
16:05
7:00
16:30
22:00
8:15
14:00
22:15
9:20
6:30
14:30
13:00
19:00
15:00
19:35
5:15
13:20
23:15
4:50
18:20
LieOver
12:55
12:55
11:55
10:25
10:15
8:40
8:35
6:00
5:05
3:55
3:00
3:00
2:20
2:05
1:55
1:35
1:20
1:15
1:10
1:05
1:00
0:55
0:50
0:45
0:45
0:45
0:40
0:40
Maintenance
Type
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Engine needs
Reversal?
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
No
Yes
No
No
Yes
RITES
No
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
Train
56222
12692
22818
16209
12648
16521
56509
11013
16731
22817
56214
56224
11014
16232
16210
16221
22681
12691
12647
56213
12975
12976
16559
22682
56231
16231
12008
12007
16732
Rake Arrival
Origin
Direction
TK
YPR
SSPN
BYPL
MYS
MYS
AII
YPR
NZM
BYPL
BWT
BYPL
MKM
BYPL
LTT
BYPL
TN
BYPL
HWH
BYPL
TPTY
BYPL
ASK
YPR
CBE
BYPL
MYS
MYS
MYS
MYS
MYS
MYS
MYS
MYS
MAS
BYPL
CBE
BYPL
CMNR
MYS
MYS
MYS
JP
BYPL
MYS
MYS
MAS
BYPL
MYS
MYS
MV
BYPL
MYS
MYS
MAS
BYPL
MYS
MYS
Time
13:10
22:30
3:00
4:00
1:00
23:25
17:00
21:50
6:40
1:40
7:10
9:10
15:05
18:45
21:40
23:30
22:45
5:25
23:00
20:15
12:55
12:55
16:50
5:30
9:10
5:50
16:15
10:50
21:10
Train
56225
1692
22818
16209
12648
56264
16520
11013
16731
22817
56214
56232
11014
16232
16210
16221
22681
12691
12647
56213
12975
12976
16559
22682
56221
16231
12008
12007
16732
Rake Departure
Destination
Direction
TK
YPR
MAS
BYPL
HWH
BYPL
MYS
MYS
CBE
BYPL
MYS
MYS
JTJ
BYPL
CBE
BYPL
MYS
MYS
MYS
MYS
CMNR
MYS
MYS
MYS
LTT
BYPL
NV
BYPL
AII
YPR
MAS
BYPL
MAS
BYPL
SSPN
BYPL
NZM
BYPL
TPTY
BYPL
JP
BYPL
MYS
MYS
YPR
YPR
MYS
MYS
TK
YPR
MYS
MYS
MAS
BYPL
MYS
MYS
TN
BYPL
149
Time
13:40
23:00
3:30
4:30
1:30
23:55
17:30
22:15
7:00
2:00
7:30
9:30
15:25
19:05
21:55
23:45
23:00
5:40
23:15
20:30
13:05
13:05
17:00
5:40
9:20
6:00
16:25
11:00
21:20
LieOver
0:30
0:30
0:30
0:30
0:30
0:30
0:30
0:25
0:20
0:20
0:20
0:20
0:20
0:20
0:15
0:15
0:15
0:15
0:15
0:15
0:10
0:10
0:10
0:10
0:10
0:10
0:10
0:10
0:10
Maintenance
Type
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Engine needs
Reversal?
Yes
Yes
No
No
Yes
No
Yes
Yes
No
No
No
No
Yes
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
RITES
No
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
Train
16518
17303
12430
12577
12591
12510
16505
16507
16507
16593
16525
12657
12494
16590
16501
12296
56513
12609
56516
16529
16538
12027
56524
12628
56507
12607
12080
56526
Rake Arrival
Origin
Direction
CAN
MYS
MYS
MYS
NZM
BYPL
DBGA
BYPL
GKP
BYPL
GHY
BYPL
GIM/JU
YPR
GIM/JU
YPR
YPR
YPR
NED
YPR
CAPE
BYPL
MAS
BYPL
NZM
BYPL
KOP
YPR
YPR
YPR
PNBE
BYPL
NCR
BYPL
MAS
BYPL
CTA
YPR
CSTM
BYPL
NCJ
BYPL
MAS
BYPL
HUP
YPR
NDLS
BYPL
MKM
BYPL
MAS
BYPL
UBL
YPR
CBP
YPR
Time
7:05
15:05
6:40
20:50
4:50
11:50
4:00
4:00
4:00
6:10
6:55
5:10
6:40
7:35
4:50
20:40
19:00
20:05
20:00
8:50
4:00
22:30
9:25
13:40
9:15
21:35
21:25
9:45
Train
16518
17303
12429
12578
12592
12509
16537
16506
16508
16594
16526
12627
12493
16589
16532
12295
56514
12610
56515
16530
16502
12028
56523
12658
56508
12608
12079
56525
Rake Departure
Destination
Direction
YPR
YPR
YPR
YPR
NDLS
YPR
DBGA
BYPL
GKP
BYPL
GHY
BYPL
NCJ
BYPL
GIM
YPR
JU
YPR
NED
YPR
CAPE
BYPL
NDLS
BYPL
NZM
YPR
KOP
YPR
AII
YPR
PNBE
BYPL
NCR
BYPL
MAS
BYPL
CTA
YPR
CSTM
BYPL
ADI
YPR
MAS
BYPL
HUP
YPR
MAS
BYPL
MKM
BYPL
MAS
BYPL
UBL
YPR
CBP
YPR
150
Time
7:10
15:10
20:20
10:10
16:50
23:30
23:05
21:55
21:55
23:00
21:40
19:20
20:20
21:15
17:20
9:00
7:15
8:00
7:50
20:10
13:30
6:00
18:40
22:45
18:05
6:30
6:00
18:00
LieOver
0:05
0:05
13:40
13:40
12:00
11:40
19:05
17:55
17:55
16:50
14:45
14:10
13:40
13:40
12:30
12:20
12:15
11:55
11:50
11:20
9:30
9:30
9:15
9:05
8:50
8:45
8:35
8:15
Maintenance
Type
N/A
N/A
Secondary
Secondary
Secondary
Secondary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Primary
Engine needs
Reversal?
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
RITES
Train
Rake Arrival
Origin
Direction
Time
Train
86
76512
MKM
BYPL
10:30
76511
MKM
87
56910
HDT
YPR
5:15
56913
88
56918
SMET
YPR
21:10
89
66531
BWT
BYPL
90
76552
CBP
91
76554
92
66529
No
Rake Departure
Destination
Direction
Time
LieOver
Maintenance
Type
Engine needs
Reversal?
BYPL
12:20
1:50
Primary (Only
on Sunday, Non
Running Day)
No
(DEMU/MEMU)
SBC
YPR
6:30
1:15
Primary (Only
on Sunday, Non
Running Day)
No
(DEMU/MEMU)
56909
UBL
YPR
22:15
1:05
Primary (Only
on Sunday, Non
Running Day)
No
(DEMU/MEMU)
14:25
66532
BWT
BYPL
14:55
0:30
Primary (Only
on Sunday, Non
Running Day)
No
(DEMU/MEMU)
BYPL
18:00
76553
DPJ
BYPL
18:30
0:30
Primary (Only
on Sunday, Non
Running Day)
No
(DEMU/MEMU)
DPJ
BYPL
8:10
76551
CBP
BYPL
8:40
0:30
Primary (Only
on Sunday, Non
Running Day)
No
(DEMU/MEMU)
BWT
BYPL
9:30
66530
BWT
BYPL
9:50
0:20
Primary (Only
on Sunday, Non
Running Day)
No
(DEMU/MEMU)
151
RITES
Train No.
Origin
Destination
Time at
BYPL
Direction of
Train
Flyover
No
1
2
12648
12648
NZM
NZM
CBE
CBD
00:20:00
01:42:00
YNK-SBC
SBC-HSRA
4
1
12778
KCVL
UBL
03:50:00
BWT-HEB
12835
THE
YPR
04:00:00
BWT-HEB
12889
TATA
YPR
04:10:00
BWT-HEB
6
7
8
12292
16591
12785
MAS
UBL
KCG
YPR
SBC
SBC
05:03:00
05:46:00
05:56:00
BWT-HEB
YNK-SBC
YNK-SBC
3
4
4
9
10
11
12
13
12863
12677
16614
56514
12254
HWH
SBC
CBE
SBC
BGP
YPR
ERS
RJT
SA
YPR
06:18:00
06:37:00
07:32:00
07:44:00
07:53:00
BWT-HEB
SBC-HSRA
BWT-YNK
SBC-HSRA
BWT-HEB
3
1
2
1
3
14
15
16529
12845
CSTM
BBS
SBC
YPR
08:16:00
09:37:00
YNK-SBC
BWT-HEB
4
3
16
15228
MFP
YPR
10:19:00
BWT-HEB
17
18
19
20
15902
18642
12976
12628
DBGR
BBS
JP
NDLS
YPR
SBC
MYS
SBC
10:27:00
11:23:00
12:23:00
12:56:00
BWT-HEB
YNK-SBC
YNK-SBC
YNK-SBC
3
4
4
4
21
12245
HWH
YPR
15:28:00
BWT-HEB
22
23
24
25
26
12540
22601
76552
76553
16232
LKO
MAS
CBP
SBC
SBC
YPR
SNSI
SBC
DPJ
MV
15:44:00
16:04:00
17:34:00
18:55:00
19:33:00
BWT-HEB
BWT-YNK
YNK-SBC
SBC-HSRA
SBC-HSRA
3
2
4
1
1
27
22618
TYTY
YPR
20:08:00
BWT-HEB
28
12544
TYTY
YPR
20:21:00
BWT-HEB
29
17311
MAS
VSG
20:40:00
BWT-HEB
30
11013
LTT
CBE
21:16:00
YNK-SBC
31
12692
SSPN
MAS
21:44:00
YNK-SBC
32
16332
TVC
CSTM
21:45:00
BWT-YNK
33
16732
MYS
TN
21:48:00
SBC-HSRA
34
11013
LTT
CBD
22:40:00
SBC-HSRA
152
RITES
S.No
1
3.00
6.50
Gokula Extension
4.10
2.80
Lottegollahalli
1.40
Chikballapur
3.60
1.60
Hebbal
1.30
Benniganahalli
0.00
Guddadahalli
1.10
Channasandra
2.20
Kanakanagar
1.30
1.80
Nagavara Main rd
1.40
Hennur
1.80
Kadugondhalli
1.10
Bagalur rd cross
1.80
Banaswadi
Kamanahalli Rd (IOC
Flyover)
Kasturinagar (near SAIL)
1.30
Thanisandra
2.10
1.00
Jakkur East
3.00
1.50
2.00
Benniganahalli
1.20
Yelahanka Jn
1.40
Baiyyappanahalli
2
Inter
Distance
Baiyyappanahalli - Hosur
Baiyyappanahalli- Yelahanka
Yelahanka Dodballapur
Yelahanka Jn
0.00
Benniganahalli
Kaggadasapura (near Railway
Cross)
Karthik Nagar (east of ORR)
Varthur Rd (Marathalli
bridge)
Belandur Rd
0.00
Kenchanhalli West
2.20
2.10
Naganahalli
1.60
2.60
Rajankunte
Dodballapur Ind Area
(middle)
Dodballapur
5.00
Karmelaram
Sarjapur Rd (just past level
crossing)
Heelalige
3.30
1.10
Yeshvantpur
0.00
10.90
3.20
Anekal road
10.50
Hosur
13.40
HMT
Jalahalli West (Near Jalahalli
Main Rd)
Chikbanavar
Soldevanahalli
2.90
1.80
2.50
6
Yelahanka Chikballapur
8.30
3.20
Yesvantpur Tumkur
1.80
2.90
Yelahanka Jn
0.00
Gollahalli
9.90
Kenchanhalli East
2.20
Bhairanayakanhalli
6.60
MVIT /Ganganahalli
4.10
Dodbele
4.40
Betthalsoor
2.10
Muddalingahalli
6.90
Dodjala
NH-7 /BIAL trumpet
Interchange
Devenahalli
4.30
Nidvanda
4.40
3.70
Dobbspet
1.00
7.10
Hirehalli
8.50
153
RITES
S.No
2.80
Tumkur
2.60
Yesvantpur - Yelahanka
10
Inter
Distance
6.10
Malleswaram
2.70
Bangalore City
2.70
Yeshvantpur
0.00
Bangalore city
0.00
Gokula Extension
4.10
2.30
Lottegollahalli
1.40
Chord Road
2.20
Kodigehalli
Jakkur West (Allalasandra
main rd)
Yelahanka south (NH7 /Level
crossing)
Yelahanka Jn
Baiyyappanahalli Bangarapet
1.60
Nayandahalli
2.90
1.60
1.40
1.70
2.30
2.00
Kengeri
1.20
NICE Rd (Southwest)
1.80
Benniganahalli
0.00
KR Puram
1.60
Kumbalgodu (Rajarajeswari
Dentl /Engg)
Hampapura (WonderLa)
4.70
Hejjala
1.90
2.00
Bidadi
6.40
2.60
Ketohalli
8.30
Devangonthi
7.80
Ramanagaram
6.50
Malur
12.20
Channapatna
6.90
Byatrayanahalli
8.80
Settihalli H
6.12
Tyakal
6.00
Nidaghatta H
5.23
Maralahalli
5.80
Maddur
9.06
Bangarapet Jn
6.20
Hanakere
10.11
Mandya
7.78
4.10
3.20
0.00
1.70
154
RITES
155
RITES
Annexure: 4 Trains presently serving Bangalore commuters and enhancing their capacities
Existing
Capacity
Rakes
Requirement
Distance
From Station
Departure
To Station
Arrival
Existing Formation
Total
MEMU Rake Km
EMU Rake Km
56229
Pass
MYS
SBC
137
MYA
09:21
SBC
12:10
92.88
3710
8793
8793
137
56230
Pass
SBC
MYS
137
SBC
16:25
MYA
18:16
92.88
3710
8793
8793
137
56231
Pass
MYS
SBC
137
MYA
06:45
SBC
09:10
92.88
16
6595
8793
8793
137
56232
Pass
SBC
MYS
137
SBC
09:30
MYA
11:23
92.88
16
6595
8793
8793
137
SBC
05:15
MYA
07:24
92.88
3710
8793
8793
137
Leave as it is
To
From
Capacity Enhanced to
Existing Type
Strategy
Train
No
Service
56233
Pass
SBC
MYS
137
56234
Pass
MYS
SBC
137
MYA
19:41
SBC
22:30
92.88
3710
8793
8793
137
56237
Pass
MYS
SBC
137
MYA
15:25
SBC
18:00
92.88
3298
8793
8793
137
56238
Pass
SBC
MYS
137
SBC
19:00
MYA
20:47
92.88
3298
8793
8793
137
56507
Pass
MKM
SBC
86
BWT
07:05
SBC
09:15
70.21
15
4674
6647
6647
86
10
56508
Pass
SBC
MKM
86
SBC
18:05
BWT
19:58
70.21
15
4674
6647
6647
86
11
56509
Pass
MKM
SBC
86
BWT
14:40
SBC
17:00
70.21
10
3116
6647
6647
86
12
56510
Pass
SBC
MKM
86
SBC
07:00
BWT
08:58
70.21
10
3116
6647
6647
86
13
66529
MEMU
KPN
SBC
104
BWT
07:30
SBC
09:30
70.21
3324
6647
6647
104
14
66532
MEMU
SBC
MKM
86
SBC
14:55
BWT
16:39
70.21
3324
6647
6647
86
15
66533
MEMU
MKM
KJM
72
BWT
18:00
KJM
19:10
56
2651
5302
5302
72
156
RITES
Existing
Capacity
Rakes
Requirement
Existing Formation
Total
MEMU Rake Km
EMU Rake Km
20:40
56
2651
5302
5302
90
86
SBC
12:20
BWT
14:30
70.21
3739
6647
6647
86
86
BWT
08:37
SBC
10:30
70.21
3739
6647
6647
86
TK
70
SBC
09:20
TK
11:05
69.35
2462
4432
2955
7387
70
TK
SBC
70
TK
11:20
SBC
13:10
69.35
2462
4432
2955
7387
70
Pass
SBC
TK
70
SBC
13:40
TK
15:25
69.35
2462
4432
2955
7387
70
56226
Pass
TK
SBC
70
TK
15:50
SBC
17:40
69.35
2462
4432
2955
7387
70
23
56525
Pass
SBC
CBP
64
SBC
18:00
CBP
19:50
63.85
1984
4080
2720
6800
64
24
56526
Pass
CBP
SBC
64
CBP
07:55
SBC
09:45
63.85
1984
4080
2720
6800
64
25
66530
MEMU
SBC
BWT
70.21
SBC
09:45
BWT
12:05
70.21
3324
4487
2991
7478
70.21
26
66531
MEMU
BWT
SBC
70.21
SBC
14:55
BWT
16:25
70.21
3324
4487
2991
7478
70.21
27
76507
DEMU
BNC
BWT
66
BNC
11:00
BWT
12:50
66
3124
4218
2812
7030
66
28
76508
DEMU
BWT
BNC
66
BWT
15:30
BNC
17:20
66
3124
4218
2812
7030
66
29
76551
DEMU
SBC
CBP
73
SBC
08:40
CBP
10:50
77.28
3658
4939
3293
8232
73
30
76552
DEMU
CBP
SBC
73
CBP
15:55
SBC
18:00
77.28
3658
4939
3293
8232
73
31
56213
Pass
CMNR
TPTY
532
MYA
17:55
BWT
22:00
163.09
15
10857
10857
10857
DEMU
SBC
MKM
DEMU
MKM
SBC
56221
Pass
SBC
20
56222
Pass
21
56225
22
Train
KPN
No
KJM
66534
17
76511
18
76512
19
157
Leave as it is
BWT
MEMU
16
Arrival
19:30
To
KJM
From
90
Existing Type
To Station
Capacity Enhanced to
Departure
Strategy
From Station
Distance
Service
RITES
Existing
Capacity
Rakes
Requirement
Leave as it is
Existing Formation
Total
MEMU Rake Km
EMU Rake Km
10857
10857
10857
18:20
TK
19:50
69.35
2462
2462
2462
07:20
SBC
09:10
69.35
2462
2462
2462
SBC
16:45
TK
18:20
69.35
2770
2770
2770
274
TK
09:15
SBC
11:20
69.35
2770
2770
2770
YPR
225
HSRA
08:30
YPR
10:45
67
2676
2676
2676
YPR
SA
225
YPR
16:05
HSRA
17:31
67
2676
2676
2676
Pass
AJJ
SBC
289
BWT
16:40
SBC
18:45
70.21
10
3116
3116
3116
56262
Pass
SBC
AJJ
289
SBC
09:20
BWT
11:00
70.21
10
3116
3116
3116
41
56503
Pass
YPR
BZA
741
YPR
08:00
DBU
09:00
33.17
11
1619
1619
1619
42
56504
Pass
BZA
YPR
741
DBU
14:55
YPR
17:10
33.17
11
1619
1619
1619
43
56513
Pass
NCR
SBC
557
HSRA
16:50
SBC
19:00
60.59
14
3764
3764
3764
44
56514
Pass
SBC
NCR
557
SBC
07:15
HSRA
08:32
60.59
14
3764
3764
3764
45
56515
Pass
SBC
UBL
470
SBC
07:50
TK
09:28
69.35
16
4924
4924
4924
46
56516
Pass
UBL
SBC
470
TK
17:22
SBC
20:20
69.35
16
4924
4924
4924
47
56523
Pass
SBC
HUP
101
SBC
18:40
DBU
19:33
38.52
13
2222
2222
2222
532
BWT
Pass
SBC
ASK
166
SBC
Pass
ASK
SBC
166
TK
56227
Pass
SBC
SMET
274
36
56228
Pass
SMET
SBC
37
56241
Pass
SA
38
56242
Pass
39
56261
40
Train
CMNR
No
TPTY
56214
33
56223
34
56224
35
158
15
Pass
32
From Station
163.09
Distance
09:15
To
MYA
From
05:15
Existing Type
Capacity Enhanced to
Arrival
Strategy
To Station
Departure
Service
RITES
Leave as it is
Existing Formation
Total
MEMU Rake Km
EMU Rake Km
2222
2222
06:30
TK
07:58
69.35
12
3693
3693
3693
21:05
SBC
22:45
69.35
12
3693
3693
3693
SBC
06:30
TK
08:00
69.35
21
6463
6463
6463
274
TK
19:22
SBC
21:30
69.35
21
6463
6463
6463
KQZ
83
BNC
17:55
BWT
19:30
66
3124
3124
3124
KQZ
BNC
83
BWT
08:00
BNC
09:40
66
3124
3124
3124
DEMU
SBC
DPJ
152
SBC
18:30
HSRA
19:36
60.59
2868
2868
2868
DEMU
DPJ
SBC
152
HSRA
06:33
SBC
08:10
60.59
2868
2868
2868
204778
134124
53176
35452
101116
Pass
SBC
UBL
470
SBC
Pass
UBL
SBC
470
TK
56917
Pass
SBC
SMET
274
52
56918
Pass
SMET
SBC
53
76505
DEMU
BNC
54
76506
DEMU
55
76553
56
76554
Train
DBU
No
101
49
56913
50
56914
51
Total
18
SBC
Arrival
2222
From Station
13
Distance
To
38.52
From
09:25
Existing Type
SBC
HUP
56524
Rakes
Requirement
Capacity Enhanced to
07:53
Pass
48
Existing
Capacity
Strategy
To Station
Departure
Service
12
323868
1964
826.42
3.928
1.653
4.714
1.984
26
Rounding off
159
RITES
35 19.23
Stn
6 4.00
12 1.00
3 10.00
30 2.00
6 6.00
18 1.00
15
Stn
15 1.00
15
1.00
15 1.00
15 1.00
10
Line
10 4.00
40
5.00
50
10
Stn
20 4.00
40 1.00
10 10.00
36
Rake
0.08
36
Rake
2.5
90 7.51
15
Stn
24
Rake
2.5
5
6
7
8
9
10
11
12
Extension/ Rising
of PFs
Facilities at
Terminals
Addl. lines at
Stations
Facilities at Exg.
Stations
9 car EMUs (for
Replacing Exg.
services)
9 car EMUs (for
new services)
Developing New
Halt Stations
EMUs Conversion
(9 to 15 car)
Qty
Qty
Qty
92.10
115
63
Amount
(Cr)
9 46.05
553
26.00 3.00
Qty
48 12.45
160
46.05
Amount
4 64.00
583
Total
Qty
13 128.00
36 5.35
SBCMYA
Amount
121 10.70
12 48.59
BYPLBWT
Qty
40 97.18
16.12
SBCBYPL
Amount
32.24
Km
SVDLKunigal
Qty
Km
0.75
Qty
1.25
Amount
3 Electrification
Amount
194 48.59
Qty
16.12
Amount
Km
Amount
12
Qty
Rake
Amount
21
Amount
Per
Activity
YNKDBU
Amount
YNKBYPL
Qty
YNKCBP
Amount
YPRYNK
Qty
YPRTK
Rate
(in Cr)
Qty
S.
No
SBCYPR
Amount
BYPLHSRA
YPR-BYPL
105
177
2121
20.72
249 45.20
542
20.72
26 90.40
113
471
588
14 20.72
16 45.20
34 10.76
8 59.45
45 92.88
70 441
331
3 1.00
3 3.00
9 3.00
9 8.00
24 12.00
36 53
159
1.00
15 1.00
15
1.00
15 1.00
15
135
15
3.00
30 1.00
10 3.00
30 4.00
40 2.00
20 6.00
60 7.00
70 36
360
100 2.00
20 6.00
60 1.00
10 1.00
10 3.00
30 3.00
30 8.00
80 12.00
120 53
530
3 0.92
33 0.21
8 0.79
72
270 0.23
8 2.77
100 0.64
23 2.36
85 1.44
52 1.56
56 1.00
36 0.15
6 0.85
30 3.00
108 24
864
135 9.00
135 1.00
15 11.00
165 3.00
45 3.00
45 7.00
105 3.00
45 4.00
60 1.00
15 7.00
105 14.00
210 72
1080
60 7.51
180 0.31
7 3.69
89 0.85
20 3.15
76 1.44
35 1.56
37 1.00
24 0.15
4 0.85
20 3.00
72 26
624
582
1432
Phase Cost
1A
173
1
3831
2
2251
3
2504
Total
8759
63
790
146
28
1060
229
487
903
108
405
764
6969
160
RITES
Additional
Services
required
EMUs required
for Additional
Services
10
10
1.858
18
16
0.171
64
14
18
2.304
From
To
Distance
(Km)
SBC
MYA
92.88
SBC
YPR
5.35
YPR
TK
YPR
YNK
12.45
0.1
YNK
BYPL
19.23
26
YPR
BYPL
16.12
28
0.903
YNK
DBU
20.72
34
1.409
YNK
CBP
46.05
26
2.395
BYPL
HSRA
48.59
80
7.774
10
SBC
BYPL
12
24
0.192
11
BYPL
BWT
58.21
18
12
SDVL
Kunigal
45.2
16
1.446
Total -->
440.8
106
266
Add 20% for maintenance spares -->
Total Requirement -->
19.552
3.910
24
Phase
1
2
Rakes
16
8
Total
24
161
RITES
162
RITES
Annexure: 7 Hourly Distribution of total scheduled trains running in CRS network at present
S.No
1
2
3
4
5
6
7
8
9
10
11
12
Section
5-6
6-7
7-8
8-9
9-10
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
19-20
20-21
21-22
TOTAL
SBC - MYA
MYA - SBC
SBC - YPR
YPR - SBC
YPR - TK
TK - YPR
YPR - YNK
YNK - YPR
BYPL - YNK
YNK - BYPL
BYPL - YPR
YPR - BYPL
YNK - DBU
DBU - YNK
YNK - CBP
CBP - YNK
BYPL/BYPLA - HSRA
HSRA - BYPL/BYPLA
SBC/BNC - BYPL
BYPL - SBC/BNC
BYPL - BWT
BWT - BYPL
SVDL - Kunigal
Kunigal - SVDL
2
1
0
0
0
2
0
0
1
2
1
2
0
3
0
0
0
1
1
5
0
2
0
0
1
1
2
0
3
1
0
2
0
0
1
0
1
2
0
0
1
2
3
3
4
5
0
0
2
1
1
1
1
1
1
1
0
1
1
1
1
1
0
1
1
1
2
2
1
2
0
0
1
0
0
1
1
1
1
1
0
0
0
3
2
3
0
0
0
1
2
5
3
3
0
0
1
1
1
0
1
2
0
4
1
0
1
0
0
3
1
0
0
0
3
2
4
2
0
0
1
0
0
0
1
1
0
2
0
0
1
1
0
2
0
0
0
0
2
1
4
4
0
0
2
2
1
2
0
1
0
0
0
2
1
1
0
1
0
0
0
0
0
3
3
1
1
0
0
0
0
1
1
1
0
0
0
1
0
0
1
2
0
0
0
0
1
3
1
1
0
0
1
1
2
1
2
0
1
1
1
0
0
1
1
0
0
0
0
1
2
1
1
0
0
0
0
2
0
0
0
1
1
0
1
0
0
0
2
0
0
0
0
0
3
1
2
3
0
1
1
1
0
1
1
1
0
0
1
0
2
1
1
1
0
1
0
0
1
0
1
2
0
0
1
1
2
0
1
0
1
1
0
0
0
0
3
2
0
0
1
0
2
2
2
1
0
0
0
1
0
1
1
1
3
0
1
1
0
0
3
0
0
0
0
1
5
1
6
0
0
0
1
2
1
0
1
0
1
1
1
0
0
0
1
1
1
0
1
1
4
2
2
3
0
0
1
2
0
1
1
1
1
0
1
0
0
1
2
0
0
0
1
0
3
3
3
4
0
0
1
1
0
1
0
2
2
0
1
1
3
0
3
1
0
0
1
0
2
1
2
3
0
0
0
1
4
1
3
1
0
0
0
1
0
0
2
1
0
0
2
1
2
3
0
2
0
0
16
18
14
11
18
17
12
13
9
9
11
11
23
23
2
2
8
9
38
38
39
38
1
1
163
RITES
Section
SBC - MYA
MYA - SBC
SBC - YPR
YPR - SBC
YPR - TK
TK - YPR
YPR - YNK
YNK - YPR
BYPL - YNK
YNK - BYPL
BYPL - YPR
YPR - BYPL
YNK - DBU
DBU - YNK
YNK - CBP
CBP - YNK
BYPL/BYPLA - HSRA
HSRA - BYPL/BYPLA
SBC/BNC - BYPL
BYPL - SBC/BNC
BYPL - BWT
BWT - BYPL
SVDL - Kunigal
Kunigal - SVDL
5-6
6-7
7-8
8-9
9-10
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
19-20
20-21
21-22
TOTAL
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
0
0
1
1
0
1
0
0
0
0
0
0
0
0
0
0
0
0
1
0
1
0
0
0
0
1
0
1
0
0
1
0
0
0
0
0
0
0
0
0
1
1
0
2
0
1
2
0
0
0
0
0
1
1
0
1
1
0
0
0
0
1
1
0
0
0
1
1
2
0
2
0
0
1
1
1
0
1
1
0
1
1
0
0
0
0
0
1
0
0
0
2
2
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
1
0
0
0
0
0
1
1
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
1
0
0
0
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
1
1
0
0
0
0
1
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
0
1
0
1
0
1
0
1
0
1
0
0
0
0
0
0
0
1
0
1
0
0
0
0
1
1
0
0
1
0
1
0
0
0
0
1
0
0
0
0
0
0
0
0
1
0
0
2
0
1
0
0
0
0
0
1
1
1
0
0
0
1
0
0
0
0
0
0
0
1
1
0
0
0
0
0
0
1
1
0
1
0
1
0
0
0
0
0
0
0
1
0
1
0
2
2
2
1
0
0
1
1
0
1
0
1
1
0
0
0
0
0
1
0
0
0
0
0
0
0
1
0
0
0
0
0
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
5
5
7
7
6
6
3
3
1
1
0
0
2
2
2
2
3
3
13
10
10
10
1
1
164
RITES
Annexure: 9 Hourly distribution of assessed potential for introducing additional services after proposed investments
S.No
1
2
3
4
5
6
7
8
9
10
11
12
Section
SBC - MYA
MYA - SBC
SBC - YPR
YPR - SBC
YPR - TK
TK - YPR
YPR - YNK
YNK - YPR
BYPL - YNK
YNK - BYPL
BYPL - YPR
YPR - BYPL
YNK - DBU
DBU - YNK
YNK - CBP
CBP - YNK
BYPL/BYPLA - HSRA
HSRA - BYPL/BYPLA
SBC/BNC - BYPL
BYPL - SBC/BNC
BYPL - BWT
BWT - BYPL
SVDL - Kunigal
Kunigal - SVDL
5-6
6-7
7-8
8-9
9-10
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
19-20
20-21
21-22
TOTAL
0
1
0
2
1
1
0
1
1
2
0
1
1
2
1
2
2
3
1
0
1
1
2
2
1
3
1
2
1
3
1
2
1
2
1
2
1
3
1
2
2
3
1
1
1
0
2
2
2
3
1
2
1
3
1
2
3
2
1
2
1
3
1
2
2
3
1
2
1
2
2
2
2
3
1
2
1
3
1
2
2
2
1
2
1
2
1
2
3
3
1
0
1
1
2
2
2
2
1
2
1
3
1
1
1
2
1
2
1
2
1
2
3
4
1
0
0
2
2
2
2
3
1
2
1
3
1
1
1
3
1
1
2
2
1
2
3
3
1
2
1
1
2
2
1
1
1
0
2
1
1
1
1
1
1
1
2
2
1
2
3
3
1
1
2
2
1
2
3
2
1
0
1
2
1
1
1
1
1
0
1
1
1
2
3
1
1
1
1
1
1
1
1
1
0
0
0
2
0
0
1
2
1
0
1
2
2
1
2
1
1
1
0
1
1
1
1
1
0
1
2
2
1
1
1
2
1
1
2
2
2
1
2
1
0
1
1
1
1
0
1
2
2
1
3
1
1
1
3
3
1
1
3
1
3
1
3
3
2
2
2
1
2
2
2
1
2
1
3
1
1
1
2
2
2
1
2
2
3
1
3
4
2
1
2
1
2
2
3
1
2
1
3
1
2
1
3
1
2
1
2
1
3
2
3
2
0
2
0
2
2
2
3
2
2
1
3
1
2
1
3
2
2
2
3
2
2
2
3
3
1
2
2
1
2
2
3
2
2
1
3
1
2
1
2
1
2
1
3
1
3
2
3
2
2
2
2
1
2
2
2
1
2
1
3
1
2
2
2
1
1
1
2
1
2
2
3
3
2
2
2
1
2
2
1
1
1
1
1
1
2
1
2
1
1
1
2
1
2
2
2
3
2
0
1
1
2
2
30
30
20
20
30
30
20
20
30
30
20
20
30
30
30
30
45
45
20
20
20
20
30
30
165
RITES
166
RITES
Section
Block
Section
LC
No.
Location
Attached
to Stn
Census
Dt
TVU
JTJ-SBC
BYPL-BNC
136
345/800-900
BYPL
Jun-06
1141760
SBC-MYA
HJL-BID
24
26/000-100
HJL
Jan-10
716416
SBC-MYA
HJL-BID
26
27/600-700
BID
Jan-10
715968
JTJ-SBC
WFD-KJM
133
337/300-400
SGWF
Dec-09
670444
SBC-TK
YPR-BAW
7/500 - 600
YPR
Feb-09
580420
YNK-DBU
RNN-DBU
27
33/600-700
DBU
Nov-09
475106
YNK-BYPL
CSDR-YNK
4/800-900
CSDR
Nov-09
411216
JTJ-SBC
BYPL-BNC
137
347/100-200
BYPL
Jun-07
366160
JTJ-SBC
KJM-BYPL
134
343/000-100
KJM
Dec-09
363617
10
JTJ-SBC
WFD YARD
131
332/000-100
WFD
Dec-09
305531
11
JTJ-SBC
DKN-WFD
130
330/200-300
WFD
Dec-09
283782
12
YNK-CBP
YNK-DHL
14
18/800-900
DHL
Nov '09
240000
13
SBC-MYA
SBC-NYH
4/500-600
SBC
Jan-10
239168
14
15
YPR-YNK
SBC-TK
YPR-YNK
KIAT-TK
11
40
15/700-800
67/700-800
YNK
TK
Sep '09
Dec '09
223460
193260
16
JTJ-SBC
BFW-TCL
120
298/100-200
TCL
Nov.09
190876
17
SBC-MYA
SBC-NYH
3/800-900
SBC
Jan-10
173504
18
JTJ-SBC
BWT-MZV
116
286/800-900
BWT
Nov.09
171116
19
20
SBC-MYA
YNK-BYPL
RMGM-CPT
CSDR-YNK
37
9
44/500-600
11/600-700
RMGM
CSDR
Jan-10
Nov-09
168128
166584
21
JTJ-SBC
DKN-WFD
129
325/400-500
DKN
Dec-09
159617
22
SBC-TK
KIAT-TK
41
68/600-700
TK
Jan '10
153031
23
YNK-DBU
YNK-RNN
21
24/600-700
RNN
Nov-09
140209
24
25
BYPL-HSRA
BYPL-HSRA
HLE - CRLM
HLE - CRLM
131
125
192/600-700
185/600-700
CRLM
HLE
Sep-09
Oct' 08
139936
138892
26
SBC-TK
GHL-DBL
16
26/800-900
GHL
Dec-09
134520
27
SBC-MYA
NYH-KGI
10
10/900-11/000
KGI
Jan-10
134112
28
YPR-BYPL
BAND - HEB
142
212/600-700
BAND
Nov-09
126568
29
YPR-YNK
YPR-YNK
8/600-700
YPR
Mar '08
120303
30
BYPL-HSRA
CRLM - BYPL
136
203/100-200
BYPL
Nov-09
117369
31
YPR-YNK
YPR-YNK
4A
8/100-200
YPR
Mar '08
115448
32
SBC-MYA
KGI-HJL
16
17/500-600
KGI
Jan-10
108432
33
YPR-YNK
YPR-YNK
10
12/300-400
YPR
Sep '09
105454
34
YNK-CBP
DHL-CBP
39
43/700-800
CBP
Nov '09
105000
35
SBC-TK
KIAT-TK
37
64/200-300
KIAT
Nov. 09
97585
167
RITES
Block
Section
Attached
to Stn
Census
Dt
36
YNK-BYPL
CSDR-YNK
5/800-900
CSDR
Nov-09
90192
37
YNK-BYPL
CSDR-YNK
11
13/300-400
YNK
Nov-09
89136
38
BYPL-HSRA
HSRA-AEK
114
173/900-174/00
AEK
Oct' 08
83412
39
BYPL-HSRA
HSRA-AEK
104
160/000-100
HSRA
Nov-09
71622
40
BYPL-HSRA
AEK-HLE
120
182/400-500
HLE
Nov-09
68149
41
YPR-BYPL
BAND - HEB
144
213/800-900
BAND
Nov-09
66792
42
SBC-MYA
RMGM-CPT
47
55/200-300
CPT
Jan-10
66592
43
SBC-YPR
SBC-YPR
4/200-300
YPR
Feb-09
66080
44
SBC-MYA
SBC-NYH
1/900-2/000
SBC
Jan-10
65984
45
YPR-BYPL
BAND - HEB
144A
214/400-500
BAND
Nov-09
64124
46
SBC-TK
KIAT-TK
38
65/300-400
KIAT
Nov. 09
58150
47
SBC-TK
YPR-BAW
12/000-100
BAW
Feb-09
53960
48
YPR-YNK
YPR-YNK
11/300-400
YPR
Sep '09
53920
49
YPR-BYPL
BAND - HEB
143
213/200-300
BAND
Nov-09
52532
50
SBC-TK
KIAT-TK
39
66/200-300
KIAT
Jan '09
52160
51
52
SBC-MYA
YNK-DBU
SET-MAD
RNN-DBU
58
25
72/100-200
32/100-200
MAD
RNN
Dec.09
Nov-09
51470
50135
53
SBC-TK
HHL-KIAT
35
62/400-500
KIAT
Mar'08
50010
Sl. No.
LC
No.
Location
168
TVU
RITES