Documente Academic
Documente Profesional
Documente Cultură
TABLE OF CONTENTS
1 INTRODUCTION .................................................................................................................. 3
2 DEVELOPMENTS IN TUNNELING METHODS ............................................................... 4
2.1 IMPORTANT YEARS IN TUNNEL CONSTRUCTION: ............................................. 4
3 A NEW CONSTRUCTION METHOD- TUNNEL COLUMN METHOD........................... 5
3.1 TUNNEL COLUMN METHOD FOR BEIJING METRO STATION ........................... 5
3.1.1 Procedures of the New Construction Method........................................................... 7
3.2 CONSTRUCTION OF UNDER PASSING TUNNEL USING TUNNEL COLUMN
METHOD ............................................................................................................................ 11
4. PROTECTION SCHEMES IN THE DESIGN PHASE...................................................... 17
4.1. COMPONENTS OF THE LIFTING SYSTEM WITH JACKS .................................. 17
4.2. DESIGN PRINCIPLES OF THE PROTECTION SCHEME ...................................... 18
4.3. STAGES OF LIFTING WORK WITH JACKS........................................................... 18
4.4. INSTALLING THE LIFTING SYSTEM AND DIVIDING THE JACKS INTO
GROUPS ............................................................................................................................. 20
4.4.1. Facilities of the lifting system ............................................................................... 20
4.4.2. Calculations of lifting force and layouts of jacks .................................................. 20
5. MONITORING MOVEMENTS OF THE OVERLYING TUNNEL AND INFORMATION
MANAGEMENT .................................................................................................................... 22
6. TEST OF LIFTING THE OVERLYING TUNNEL USING IN-TUNNEL JACKS AND
ADJUSTMENTS OF THE LIFTING SCHEMES .................................................................. 25
6.1 TEST OF LIFTING THE OVERLYING TUNNEL USING JACKS ........................... 25
6.2 ADJUSTMENTS OF THE LIFTING SCHEMES ........................................................ 27
7 CONCLUSION .................................................................................................................. 30
8 REFERENCES ..................................................................................................................... 31
1 INTRODUCTION
In recent years, the metro systems have been increased dramatically
due to the large population and limited surface space. When building tunnels in
densely populated urban areas, it is of paramount importance to control the adverse
effects of tunnelling on existing structures and utilities in the surrounding
environment. In particular, tunnelling under an existing tunnel can induce ground
movements and tunnel settlements, which, if uncontrolled, might not only produce
damaging effects to the overlying structure but also pose serious threat to passengers
in the tunnel. Therefore, protective measures must be considered and analyzed in the
design phase to ensure safe construction of the new tunnel as well as operation of the
existing tunnel.
To meet the requirements for the heavy passenger flow, twin tunnels
are constructed side by side and one above the other. In the later case, it is important
to investigate the effects of tunnelling on the support systems of existing adjacent
tunnels so that the existing tunnels can continue to operate safely both during and
after construction of the new tunnel.
For twin tunnel construction generally adopt combined application of
ground reinforcement by glass-fiber components and multi-layer grouting or
underpinning methods or ground freezing technologies. It is clear that the above
commonly employed schemes and methods centeron reducing disturbances to
surrounding ground of the tunnels and then indirectly reduce settlements of overlying
structures. Based on a case study in Beijing metro construction, a direct protection
methodology using in-tunnel jacks for excavating an under-passing tunnel is
presented herein. Lifting schemes with jacks are widely used in moving and
reconstruction of buildings and bridges in China. However, it was the first time that
an in-tunnel support methodology using lifting jacks was employed to control
settlements of the overlying tunnel in China metro construction.
Rock excavation:
Year 1600 Use of black powder for blasting.
1862 Use of dynamite for blasting
1918 Tungsten carbide bit for drill
4
flow, the station was designed to be a two-story structure with center platform. On
completion, the station is a typical three-arch structure supported by two columns, as
shown in Figure 1. The station has a total length of about 227m and width of 24m
with a height of 14 m (Fig. 2).
This type of structure normally would be excavated by the cut-and cover method.
However, because the location of the station was very sensitive to the
surrounding environment, the choice of the construction method carried a high risk. In
comparison to many other types of cut-and-cover techniques, the tunnelling method
selected was the only possible choice, as it creates little disturbance above ground and
affects the pipelines less.
as a shell to protect the excavation works inside and created a part of the station
structure which did not need to be demolished.
Because the side piles and middle columns would bear the load from
the arching both vertical and horizontal direction in this case, it was believed that the
soil around the piles could provide sufficient support to the piles and columns. Under
the protection of this temporary structure, a normal top-down excavation technique
could be carried out. This procedure is shown in detail in Figure 3.
The advantages of this method can be summarized as follows:
1. By making the shoring pile wall and the center columns structure of the station in
the pilot tunnel, there is no disturbance to the ground surface, in comparison to the
cut-and-cover method.
2. Under the protection of the initial arch support structure based on the piles and the
center columns, the normal top-down or bottom-up technique can be carried out,
which is more favourable to the quality of the station structure than the multi-section
tunnelling method.
This approach has advantages in terms of environmental safety and structural stability
for large-scale underground excavations in loose soil.
Figure 6
Figure 7
The ground settlement curve would be non-symmetrical in the
procedure of pilot tunnel excavation for the scheme in Figure 6, but at last the
settlement curve would come to be symmetric for both schemes. The maximum
settlement induced by the scheme in Figure 6 would be smaller than that shown in
10
Figure7 because the area of excavation disturbance in the eight-step excavation would
likely be less than that of in a two-step excavation.
11
double arched and composite lining structure, consisting of primary support made of
C20 concrete, waterproofing layer and secondary lining made of C30 concrete. The
thicknesses of primary support and secondary lining of the tunnel are both 0.3 m. The
scissors crossovers and movement joints in the existing tunnel are especially sensitive
to the under passing tunnel excavation induced settlements, and the main challenges
facing the construction of Zone C of Dongzhimen station on Airport Express were to
limit settlements of overlying structures when constructing the under-passing tunnel
of Dongzhimen station on Airport Express.
Special measures were needed to prevent the tunnel in service from
excessive settlements that could damage the tunnel structures and influence operation
of the existing tunnel. However, due to the restrictions by surface and subsurface
environments, it was not possible to have any working site above ground surface. A
more direct choice was to use in-tunnel lifting jack support methodology to control
movements of the existing tunnel.
13
14
(i) Two No. 1 drifts were excavated with the primary support consisting of sprayed
concrete, lattice girder and bolts.
(ii) Reinforced concrete piles were driven into the ground from within the No. 1 drifts
and L-shaped support beams were cast on top of piles.
(iii) The No. 2 drift was excavated and the strip foundation was built with concrete
casting, and steel props were erected.
(iv) Jacks were arranged in the No. 1 and No. 2 drifts, and the No.3 drifts were
excavated.
(v) Side walls between drifts were demolished and the roof of the under-passing
tunnel was built with concrete casting.
(vi) The remaining part was excavated and steel props were set up together with
anchor cables.
(vii) The side wall and floor of the under-passing tunnel were built with concrete
casting.
(viii) Jacks were removed and gaps between new and old structures backfilled.
15
Fig. 13. Construction steps for the under-passing tunnel (Section II).
16
17
18
Stage II: when step 5 was initiated, i.e. the side walls between drifts
were removed piecewise and the cast roof attained its designed strength and vertical
props set up under the roof, the adjustments and instalments of hydraulic jacks were
performed in time with the development of the roof construction, and the lifting work
could be performed when necessary.
Stage III: in step 7, i.e. the under-passing tunnel was finished and the
structural concrete attained its designed strength, the work of lifting the overlying
tunnel using in-tunnel jacks was performed based on the measured settlements of the
overlying tunnel.
Fig. 15. Flowchart of the lifting schemes and main construction items.
19
Based on the design drawings, the existing tunnel within the zone of
influence of the under-excavation was zoned for calculating the weights that should
be supported by jacks. It was estimated that the weights of the cut and cover tunnel
and the mined tunnel were about 1982 T and 1046 T respectively.
In the first stage, twenty-eight 200-ton hydraulic jacks in total were
arranged. Six jacks were in the No. 1 drift below the cut and cover tunnel, fourteen
jacks in the No. 2 drift and eight jacks in the No. 1 drift below the mined tunnel. The
maximum lifting force of the jacks was 5600 T and enough to lift the overlying tunnel
structures.
In the second and third stages, eight 200-ton jacks were arranged
below the mined tunnel and twenty 200-ton jacks arranged below the cut and cover
tunnel. Underneath the mined tunnel the jacks were positioned along the top of the Lshaped beam and under the bottoms of the middle wall and side walls of the mined
tunnel. Underneath the cut and cover tunnel, the jacks were positioned along and
under the bottom of the side walls and the floor centreline of the cut and cover tunnel.
The configurations of the PLCs and jacks for the second and third stages are given in
Fig. 17. It is observed from Figs. 16 and 17that in the first stage the jacks were
divided into six groups and in the second and third stages the jacks were divided into
eight groups.
20
Fig. 16. Configurations of the jacks and PLCs for the first stage.
Fig. 17. Configuration of the jacks and PLCs for the second and third stages.
21
22
23
24
6. TEST OF LIFTING THE OVERLYING TUNNEL USING INTUNNEL JACKS AND ADJUSTMENTS OF THE LIFTING
SCHEMES
6.1 TEST OF LIFTING THE OVERLYING TUNNEL USING JACKS
25
26
The loading process of jacks presented in Fig. 23 remains roughly the same, but is not
in full agreement mainly on account of imperfect layout and grouping of jacks. The
measured movements of the overlying tunnel in Figs. 22 and 24 showed that the
installed jacks were able to raise the above tunnel. It can be argued that in Fig. 24 the
vertical movements are a reflection of differential settlement from the jacks
foundation settlements and total vertical movement. It may be used to show
settlements of the jacks.
Fig. 24. Measured vertical movements of the existing tunnel on August 11.
Through the lifting test the lifting of the overlying tunnel was
previewed and the minimum hydraulic pressure of jacks was mastered, and from Fig.
23 it was found to be about 10 MPa average loads on the eight jacks. Of course, this
pressure should be increased with the construction development of the overlying
tunnel and surface backfilling.
6.2 ADJUSTMENTS OF THE LIFTING SCHEMES
Adjustments of the lifting schemes were made based on the lifting test,
and are given as follows:
(i) The forces of jacks directly acted on the primary support of the under-passing
tunnel instead of the floor of the existing tunnel. The following are the reasons. When
excavating the under layer and primary support of the existing tunnel, it was found
27
that the exposed structure face was rough and uneven. There was no enough time to
chisel and level off the face. So the initial support of the under-passing tunnel
consisting of welded wire mesh, lattice girders and sprayed concrete was employed to
directly bear the lifting forces.
28
(iii) On account of the uneven rigidities of the under layer of the existing tunnel and
the initial support of the under-passing tunnel, it was impossible in practice to realize
the synchronous lifting only in the light of measured movements by grating scales.
Measured movements of the existing tunnel by the hydrostatic levelling system were
indispensable to realizing the synchronous movement of the existing tunnel.
(iv) Based on the construction period, the lifting jacks played the role of temporary
support during construction. As at October24, 2007, the secondary lining of the underpassing tunnel was completed to provide firm support. At the same time, fracture
occurred in the primary support of the overlying mined tunnel, and it was time to
cease further lifting of the existing tunnel
29
7 CONCLUSION
Because of its special location and difficult ground conditions, the
West-Tiananmen Metro Station requires special ground control, which affects the
choice of construction methods. In this situation, the tunnel-column method was
adopted to avoid disturbance to the ground surface and to limit the ground settlement
successfully. The ground movements were monitored. The experience on this project
is valuable for solving similar problems of large scale underground excavation in
urban areas.
Experience indicates that, such an in-tunnel protection methodology
using jacks, when combined with cautious tunnelling procedures, was able to
effectively control the extent and degree of influence of the under-excavation on the
overlying tunnel. Based on the above statements and discussions, the following
conclusions are drawn:
(i) The completing of the settlement control of the existing tunnel in construction of
the under-passing tunnel using the in- tunnel jacking above tunnel methodology lies in
the prepared schemes, the lifting test, adjustments of the schemes, the construction
method of the under-passing tunnel, and most important of all, the application of the
high precision and automatic hydrostatic levelling system. Monitoring played an
important role in this project, modern instruments with advanced accessories, timely
processing of measured data, and feed-back to operators resulted in an informationoriented lifting work. This ensured the settlement control of the existing tunnel
without interruption of metro traffic.
(ii) Once lifting work is started it is unreasonable to unload the supporting jacks and
move them, and the suggested approach is to add jacks where needed.
(iii) Based on the lifting work presented, the loading rate of 0.44 2.87 MPa/min and
the unloading rate of 2.542.87 MPa/min are reasonable.
(iv) The lifting work using in-tunnel jacks is an active defence methodology and can
be used effectively to reduce settlements of existing tunnels caused by underexcavation.
30
8 REFERENCES
Liu H.Y., Small J.C., Carter J.P., Williams D.J., Effects of tunnelling on
existing support systems of perpendicularly crossing tunnels, Computers and
Geotechnics, vol.36,pp 880-894.
Liu W, Luo, F., Mei, J., (2000), A new construction method for a metro station
in Beijing, Tunnelling and Underground Space Technology, vol. 15 (4), pp. 409
413.
Srinivasan,R., Harbour, Dock and Tunnel Engineering,25th edn, Charotar
Publishing House,India,2012
Xinggao Li, Chengping Zhang, Dajun Yuan. (2013),An in-tunnel jacking above
tunnel protection methodology for excavatinga tunnel under a tunnel in
service,Tunnelling and Underground Space Technology, vol. 34,pp. 22-37.
31
32